APPENDIX F. Structural Design Report
|
|
- Benjamin Richard
- 5 years ago
- Views:
Transcription
1 APPENDIX F Structural Design Report
2 CONSULTANT SERVICES FOR AN ENVIRONMENTAL ASSESSMENT (EA) STUDY OF WHARNCLIFFE ROAD WIDENING FROM BECHER STREET TO COMMISSIONERS ROAD CNR SUBWAY BRIDGE REPLACEMENT STRUCTURAL DESIGN REPORT November 2017
3 TABLE OF CONTENTS 1.0 INTRODUCTION PROJECT LOCATION EXISTING BRIDGE BRIDGE ALTERNATIVES CONSIDERED Two Span Bridge Single Span Bridge Through Plate Girder Options MAINTENANCE OF RAIL TRAFFIC Option A Rail Diversion Track Protection Away from the Bridge Track Protection at the Bridge Track Protection for Installation of Retaining Walls Option B Trestles Soldier Pile Installation Trestle Installation Track Protection for Installation of Retaining Walls Cost Estimate Construction Duration Preferred Option FOUNDATIONS BRIDGE ERECTION Erection for Rail Diversion Option Erection for Trestle Option PROPOSED BRIDGE... 9 Wharncliffe Road Widening from Becher Street to Commissioners Road MMM Group Limited November CNR Subway Bridge Replacement i
4 9.0 ALIGNMENTS AND CROSS-SECTIONS Horizontal Vertical Vertical Clearance Cross Sections UTILITIES MISCELLANEOUS Design Code Protection System at Existing Bridge Access to Site Drainage SUMMARY AND RECOMMENDATION APPENDICES Appendix A Key Plan Appendix B Site Photographs Appendix C Preliminary General Arrangement Appendix D Rail Diversion and Track Protection Concepts Appendix E Trestle, Track Protection and Lateral Slide Concepts Appendix F Minutes from January 22, 2016 meeting with CNR Appendix G Cost Estimates Appendix H Schedules Wharncliffe Road Widening from Becher Street to Commissioners Road MMM Group Limited November CNR Subway Bridge Replacement ii
5 1.0 INTRODUCTION The City of London has initiated an Environmental Assessment Study for the Wharncliffe Road South widening project. The study area, as shown on the Key Plan in Appendix A, is the Wharncliffe Road South Corridor extending from Becher Street to Commissioners Road West. The City of London has retained MMM Group Limited (MMM) to undertake the Environmental Assessment Study. As part of the City of London s 2030 Transportation Master Plan, the recommendation was made to widen Wharncliffe Road South from Becher Street to Springbank Drive from 2 lanes to 4 lanes as well as the possible widening of the Canadian National Railway (CNR) Subway. This report focuses on the CNR Subway at Mile Strathroy Subdivision. This report documents the alternatives considered for replacement of the CNR Subway. In addition, recommendations for track protection and the final structural configuration are provided. For the purposes of this report, the bridge is considered to be oriented in an east-west direction. 2.0 PROJECT LOCATION The CNR Subway is located on Wharncliffe Road South immediately north of Horton Street in the City of London. It is located at Mile of the CNR Strathroy Subdivision. A key plan is provided in Appendix A of this report. 3.0 EXISTING BRIDGE The existing bridge is a three (3) span bridge, carrying two CNR tracks, supported on concrete abutments and steel bent piers. The main span is m and the end spans are 4.34 m. The floor system consists of transverse floor beams framing into three (3) longitudinal girders. The girders are of riveted steel construction consisting of plates for the webs and angles for the flanges. The railway ballast is retained with concrete in-fill between the floor beams. The steel bent piers are comprised of rolled steel columns at each of the girders braced with horizontal and diagonal bracing. The pier foundations appear to be mass concrete spread footings. There is a trainman s walk on the south side of the bridge. Existing ducts run along both sides of the bridge. Photographs of the existing bridge are provided in Appendix B. Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
6 4.0 BRIDGE ALTERNATIVES CONSIDERED 4.1 Two Span Bridge A two span bridge with spans in the range of 16 m to 24 m was initially considered. The issue with any two span bridge, irrespective of structure type, was that a centre pier would reduce the sight distance (compared to the single span alternative) for southbound traffic on Wharncliffe Road South. The desire from a road operation and safety point of view was to have a single span structure. As a result, the two span alternatives were not carried forward for further consideration. 4.2 Single Span Bridge The following single span bridge types were considered: a) Cast-in-place post tensioned concrete; b) Precast, post tensioned, concrete girders; c) Deck plate girders; and d) Through plate girders. For preliminary design purposes, a span length of 34.5 m was selected to accommodate the required cross section of Wharncliffe Road South. For a single span cast-in-place post tensioned concrete bridge with a 34.5 m span length, the required deck thickness is approximately 2.35 m. This would result in a substantial lowering of the grade on Wharncliffe Road South and Horton Street in order to meet vertical clearance requirements. Compared to a through plate girder bridge, the post tensioned concrete bridge would require an additional grade lowering of 1.5 m which would result in significant additional costs. In addition, the construction duration for the cast-in-place post tensioned alternative would be longer than the other alternatives. On this basis, the option of using a single span cast-in-place post tensioned concrete bridge was not carried forward for further consideration. A precast, post tensioned, concrete girder option would require the same thickness as the cast-in-place option. Therefore, the same issue with grade lowering to achieve the required vertical clearance is present. The ability to transport the girders was assessed and found to be problematic. Also, the ability to lift the precast girders into place is a concern; there would be limited options for crane placement with such heavy girders. As a result, the precast, post tensioned, concrete girder option was not carried forward for further consideration. A deck plate girder option was also considered. The required superstructure depth (below the bottom of the ballast) is 3.1 m. Compared to a through plate girder, the deck plate girder would require an additional grade lowering of 2.2 m which would result in significant additional costs. As a result, this option was not carried forward for further consideration. The through plate girder bridge would have the least thickness (below the base of rail) of all the alternatives considered. For preliminary design purposes, the thickness has been assumed to be 0.9 m Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
7 below the bottom of the ballast. This option would minimize the grade lowering of Wharncliffe Road South and Horton Street which would reduce the overall construction cost. As a result, the single span through plate girder option was carried forward as the preferred alternative. 4.3 Through Plate Girder Options The options for the single span through plate girder bridge that were considered are: a) Two separate single track through plate girder bridges; or b) One double track through plate girder bridge. The use of two single track through plate girder bridges would be more expensive compared to a double track through plate girder. The increased cost would be associated with a wider abutment and additional steel tonnage. In addition, there would be costs associated with changing the horizontal alignment to accommodate each of the single track through plate girder bridges (the track centre to centre spacing would need to increase). Due to these increased costs, the two single track through plate girder bridges were not carried forward. 5.0 MAINTENANCE OF RAIL TRAFFIC Two (2) options were reviewed for maintaining the rail traffic. The first option considered was to maintain railway traffic using a diversion. The second option considered was to maintain railway traffic on the existing curved alignment using trestles over the excavation for the new abutments (referred to as inplace construction). Both options may involve the installation of caissons and/or tieback anchors. The possibility of encountering old timber trestles buried in the railway embankment, used prior to construction of the current embankment, was identified during preliminary design. During detailed design, an effort should be made to locate the timber trestles through review of existing drawings and/or a ground penetrating radar survey. Locating any caissons or tieback anchors to avoid the remains of the timber trestles is recommended. 5.1 Option A Rail Diversion Conceptual sketches of the rail diversion and the required track protection have been provided in Appendix D. Reference to the sketch Sheet numbers has been provided in this section. For preliminary design purposes, it has been assumed that track protection will be required along Horton Street to retain the railway diversion embankment (see Section 3 on Sheet S3). Closer to the bridge, it has been assumed that a two sided track protection system is required to permit excavation for the new abutments (see Section 2 on Sheet S2). At Wharncliffe Road South, a two sided plug has been assumed for preliminary design (see Section1 on Sheet S2). The plug option would require the closure of Wharncliffe Road South for the duration of construction. Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
8 The option of using a temporary bridge at Wharncliffe Road South was considered. Wharncliffe Road South needs to be closed for a minimum period of approximately 6 months in order to complete the grade lowering on Horton Street. A detour bridge would allow Wharncliffe Road South to remain open during construction of the new bridge. One downside to keeping the road open is that the through plate girder superstructure would need to be constructed, in place, over traffic. There would be limited opportunity to stage traffic to avoid working directly over traffic. The cost premium associated with a detour bridge which would maintain traffic on Wharncliffe Road South, compared to a plug, was estimated to be approximately $425,000. The option of using the final through plate girder superstructure on the temporary alignment as a detour bridge and laterally sliding it into its ultimate location was also considered. The cost premiums associated with the temporary substructures and lateral slide for this option are $1,200,000 and $800,000, respectively. It is anticipated that the shoring for the detour alignment would be installed with CNR flagging, but without any track blocks. This should be confirmed during detailed design if the rail diversion is the chosen alternative Track Protection Away from the Bridge For the south rail detour, track protection is required away from the bridge to ensure that the proposed detour embankment does not encroach onto Horton Street. Solider piles with lagging and tiebacks have been assumed to be the method used for track protection (see Section 3 on Sheet S3). An alternative to solider piles with lagging is sheet piles. Sheet piles were not considered as a preferred alternative because an effective penetration depth, for resistance to lateral loads, may not be achievable in the dense native soils. The usage of sheet piles is discussed in the Geotechnical Design Report by Golder Associates dated December 2015 in Appendix I Track Protection at the Bridge At the bridge, the track protection concept developed during preliminary design is to use two shoring walls. See Section 2 and Plan on Sheet S2 for the conceptual details of this method. The north shoring wall would be installed first; temporary tieback anchors would be installed into the railway embankment. This would allow the material in front of the wall to be excavated. At this point, the south shoring wall could be installed and the horizontal anchors could also be installed. Then, backfilling of the detour and transferring of rail traffic to the detour could be completed. This would make the temporary tieback anchors redundant such that they could be removed and the new bridge could be constructed Track Protection for Installation of Retaining Walls It is envisioned that the retaining walls on the north side of the bridge would be constructed with rail traffic on the detour alignment. Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
9 For the retaining walls on the south side of the bridge and along Horton Street it is anticipated that rail traffic would be transferred back to the permanent alignment and that the shoring would be modified to allow for construction of the retaining walls. The retaining walls could be conventional reinforced concrete walls. Alternatively, permanent solider pile (with or without permanent tiebacks) and lagging walls with a concrete facing could be utilized. There may be some opportunity to utilize the shoring required for the detour alignment, along Horton Street, as the permanent retaining walls as well. This should be explored during detailed design. 5.2 Option B Trestles For this option, it has been assumed that a shoring system consisting of solider piles and lagging would be installed. Some of the solider piles would need to be installed from the existing railway embankment which would necessitate track blocks to complete the work. A temporary trestle would then need to be installed to maintain railway traffic while the permanent foundations and abutments are constructed under the active tracks. Further details on these components are provided in the following sections. Conceptual sketches for the track protection and trestle have been provided in Appendix E. Reference to the sketch Sheet numbers has been provided in this section Soldier Pile Installation It is anticipated that the soldier piles directly adjacent to the north and south track (lines 5, 6, 7, and 8 on the Plan on Sheet S4) would need to be installed with track blocks on one or both tracks. The remainder of the solider piles would be installed with railway flagging. The requirements for track blocks and flagging are outlined in Table 1 below. See Plan on Sheet S4 for the soldier pile numbering. Table 1 Anticipated Track Block and Flagging Requirements Soldier Pile North Track South Track A1, A2, A3, A4, B1, B2, B3, B4, C1, C2, C3, C4, Flagging D1, D2, D3, D4 A5, B5, C5, D5 Block (6 hrs. +/- per caisson) A6, A7, B6, B7, C6, C7, Block D6, D7 (6 hrs. +/- per caisson) A8, B8, C8, D8 Flagging A9, A10, B9, B10, C9, C10, D9, D10, E1, E2, Flagging E3, F1, F2, F3 Flagging Flagging Block (6 hrs. +/- per caisson) Block (6 hrs. +/- per caisson) Flagging Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
10 CN has previously confirmed that the existing train movement is 28 trains per day. Twenty two of these trains (passenger and freight) operate between 7:00 am and 11:00 pm. Six freight trains operate from 11:00 pm to 7:00 am. Approximately four passenger (VIA) trains operate in each direction each day. Both the north and south track need to be maintained for passenger trains with no interruption to service. Given the need to maintain the tracks for passenger trains, it is anticipated that daytime solider pile installation is not feasible. CN has previously confirmed that night (11:00 pm to 7:00 am) track blocks between 4.5 hours and 8 hours can be obtained with 6 weeks advance notice. The anticipated production rate for caisson installation is one (1) caisson per drill rig per night. It is anticipated that both tracks would need to be taken out of service for a total of 8 nights with one drill rig working. Alternatively, if two drill rigs were utilized, then both tracks would only need to be taken out of service for a total of 4 nights. For the remainder of the caissons, where only one track needs to be taken out of service, it is anticipated that a total of 8 nights is required if one drill rig was utilized Trestle Installation The total depth of excavation required to install each trestle is approximately 2.0m. Accordingly, the excavation required for trestle installation will extend into the influence zone for the adjacent track. Therefore, as a minimum, both trestles at one end of the existing bridge would need to be installed during a single closure period. CN has previously indicated that their preference is to install all the trestles during a weekend closure. A 36 hour closure has been previously suggested by CN (see minutes from January 22, 2016 meeting with CN in Appendix F). Ramps for access to the work area, for the permanent foundations, would need to be constructed at both the east and west abutments. It is anticipated that the access ramps would be installed on the north side of the bridge. The area available for access ramps on the south side of the bridge is more limited. See Sheets S5 to S8 for conceptual details of the trestle Track Protection for Installation of Retaining Walls It is envisioned that the retaining walls on the north side of the bridge would be constructed within the solider pile and lagging shoring system used for the trestle. For the retaining walls on the south side of the bridge and along Horton Street, permanent solider pile (with or without permanent tiebacks) and lagging walls with a concrete facing are recommended. An alternative to soldier pile walls would be to install a shoring system and construct cast-in-place walls. 5.3 Cost Estimate For the rail diversion (Option A) and the new bridge, the total estimated construction cost is $18,500,000 (including a 40% contingency). Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
11 For the trestle (Option B) and the new bridge, the total estimated construction cost is $15,600,000 (including a 40% contingency). A detailed breakdown of the costs for each option is provided in Appendix G. The unit prices utilized assume a base year of Any of the costs that CNR would pass along to the City, such as costs for railway flagging, are not included in the estimated construction costs. 5.4 Construction Duration For the rail diversion option (Option A), the estimated construction duration is 21.5 months. This excludes some paving and landscaping work which would need to be completed in favourable temperatures. For the trestle option (Option B), the estimated on site construction duration is 15 months. Gantt charts for Options A and B showing the critical activities are provided in Appendix H. 5.5 Preferred Option A meeting was held with CNR on January 22, 2016 to discuss the rail diversion and trestle options. CNR indicated that their initial preference is in-place construction using trestles (Option B). A copy of the minutes from the January 22, 2016 meeting is provided in Appendix F. 6.0 FOUNDATIONS A preliminary geotechnical report was prepared by Golder Associates which provides preliminary geotechnical recommendations (see Wharncliffe Road South CN Rail Bridge Replacement Preliminary Geotechnical Design Report by Golder Associates dated December 2015 in Appendix I). In general, the subsurface conditions at the site consist of the following layers: granular road base or topsoil, surficial layers of sand and silts, and an extensive stratum of silty clay. Glacial till was found in two boreholes close to the proposed bridge, at elevations ranging from m to m. The surface of the limestone bedrock was encountered in one borehole at an elevation of which is approximately 40 m below the existing ground surface. Groundwater was observed in the boreholes and measured in piezometers and found to be ranging from elevation m to m which is 1.9 m to 4.5 m below the existing ground surface. Spread footings or deep foundations (H Piles or Micropiles) were considered for this site. Spread footings were found to be impractical due to the relatively low bearing capacities of the Glacial Till and the depth of excavation required to found the bridge on the Glacial Till. For preliminary design purposes, deep foundations have been assumed. Micropiles have been assumed as the preferred foundation type on the preliminary general arrangement. Micropiles would allow the Contractor to complete the foundation work in a relatively confined area underneath a trestle using in-place construction techniques for the abutments. Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
12 The Preliminary Geotechnical Report indicates that H Piles or Micropiles would be founded in the very dense sandy silt glacial till below elevation 234 m to 235 m. This would result in piles which are approximately 5 m in length. 7.0 BRIDGE ERECTION The options for erection of the through plate girder bridge were reviewed during preliminary design. 7.1 Erection for Rail Diversion Option For the rail diversion option, conventional erection in-place is the most feasible and cost effective alternative. The bridge could also be moved into place using self-propelled modular transporters or by using a lateral slide approach. Either of these two options would be more costly, but would reduce the overall construction duration. 7.2 Erection for Trestle Option For the trestle option, a number of options for bridge erection were considered. The option of using cranes to lift the entire bridge into place, as a unit, during a weekend closure was reviewed. This option is not recommended due to the weight of the through plate girder superstructure and the limited area for the footprint of the large cranes required to lift the span. The option of using self-propelled modular transporters (SPMT s) to move the bridge into place, during a weekend closure (track block), was also considered. There would be a considerable amount of work that would need to occur to ensure a reasonably level surface for the SPMT s to drive on. During the weekend closure, this work would entail removal of the existing abutments/sidewalk and significant grading work. There would not be enough time, during a weekend closure, to complete this work and move the bridges using SPMT s. Therefore, the option of using SPMT s was not considered further. The option that is most feasible is to laterally slide the bridge into place, from temporary supports to the final position, during a weekend closure (track block). The bridge could be erected on temporary supports on either side of the existing bridge. There is more working area available on the north side of the existing bridge for cranes and construction equipment to erect the new bridge span on temporary supports. Based on MMM s assessment of the alternatives, we have concluded that the new bridge would be erected north of the existing bridge. To ensure appropriate vertical clearance to Wharncliffe Road South, the bridge could be built higher than the final required elevation and jacked down (prior to the lateral slide) using an incremental jacking scheme. See Sheet S9 in Appendix E for conceptual details of the lateral slide option. Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
13 8.0 PROPOSED BRIDGE The recommended new bridge consists of a 34.5 m through plate girder bridge with reinforced concrete abutments. The span length was determined such that the final configuration of Wharncliffe Road South can be accommodated. The width of the through plate girder bridge has been assumed to be 11.1 m (centre to centre of the girders). This will ensure that the standard railway clearance envelope can be achieved on the exterior portions of the bridge. It is recommended that the new bridge superstructure be coated and that galvanized bolts are used. This will avoid issues with rust staining of components below the bridge due to the use of atmospheric corrosion resistance structural steel. Coating and illumination may be used to improve the appearance of the finished bridge. The existing cross section of the north and south tracks is super-elevated due to the curved horizontal track alignment. The preferred alternative is to adjust the profile over the bridge such that the low rail for both tracks is at the same elevation. This would ensure that the bridge can be installed level. The steel plate girders can still be utilized if the existing configuration of superelevation is maintained. The assumed top of footing elevation is m (+/-) which has been set such that that the new sidewalks can be constructed. For preliminary design, micropiles have been assumed as the deep foundation solution. Wingwalls parallel to the railway alignment, 8.75 m in length, have been assumed for preliminary design. The use of an H-Pile foundation is an alternative to micropiles for the Rail Diversion option where headroom isn t an issue. During detailed design, the impact of any vibrations on the underground utilities would need to be confirmed. Retaining walls are required north of the new bridge along Wharncliffe Road South. In addition, retaining walls are required along the north side of Horton Street to avoid impacting the railway embankment. A preliminary General Arrangement is provided in Appendix C. 9.0 ALIGNMENTS AND CROSS-SECTIONS 9.1 Horizontal The proposed horizontal alignment for Wharncliffe Road South at the new CNR Subway is on tangent. The proposed horizontal alignment of the north and south CNR tracks is on an approximately 1 degree curve in the vicinity of the new CNR Subway. Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
14 9.2 Vertical The proposed vertical alignment for Wharncliffe Road South at the new CNR Subway will be a sag vertical curve with K = 8.00 and initial and final grades of approximately 3.6% (see Profile of Wharncliffe Rd on Sheet S1 in Appendix C). The vertical alignment for the north and south CNR tracks is proposed to be a crest vertical curve in the vicinity of the bridge. 9.3 Vertical Clearance The existing CNR Subway has a posted vertical clearance of 4.2 m. The minimum vertical clearance required under the proposed bridge is 5.0 m. 9.4 Cross Sections The proposed cross section for Wharncliffe Road South (see Elevation on Sheet S1 in Appendix C) is as follows: Variable width east sidewalk (minimum 2.0 m wide) 3.0 m boulevard Two, 3.5 m northbound lanes 1.5 m median 3.5 m southbound left turn lane Two, 3.5 m southbound lanes 3.3 m southbound right turn lane 3.0 m boulevard Variable width west sidewalk (minimum 2.0 m wide) The proposed cross section for the CNR tracks will not be changed from the existing cross section. Currently, the centre to centre spacing of the tracks varies and is approximately 3.92 m. The 11.1 m spacing of the girders, shown on Section 1 on Sheet S1 in Appendix C, will provide for a future track centre to centre spacing of 4.27 m UTILITIES There may be cables in the ducts running along either side of the existing bridge. They will need to be relocated off the existing bridge prior to commencing construction of the new bridge. There are buried sanitary and storm sewers under Wharncliffe Road South in the vicinity of the proposed CNR Subway. In plan, these buried utilities are outside of the limits of the new proposed bridge foundations. The use of micropiles will mitigate any impacts associated with vibration on the utilities that may have occurred with the use of conventional steel pile driving. Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
15 In addition, there are existing overhead utilities in the vicinity of the new CNR Subway which will be relocated prior to commencing construction MISCELLANEOUS 11.1 Design Code The design will be completed in accordance with the latest version of the A.R.E.M.A. Manual and CN Guidelines for Design of Railway Structures Protection System at Existing Bridge Depending on the selected staging configuration, a protection system at the existing bridge may be required in order to lower Wharncliffe Road South to the desired elevation Access to Site Access to the site would be via southbound or northbound Wharncliffe Road South Drainage The longitudinal grade of the bridge will be 0.5%. Horizontal drainage pipes shall be embedded in the ballast. The pipes will drain to the abutments and will be connected to a vertical drainage system behind the abutment walls SUMMARY AND RECOMMENDATION It is recommended that the new CNR Subway be built in place. This recommendation is based on the construction cost, construction duration, and CNR s preference. Trestles would be used behind the existing abutments to maintain railway traffic and allow for construction of the abutments. It is proposed to laterally slide the new CNR Subway into place from temporary supports constructed north of the existing bridge. It is recommended that the abutments for the existing bridge be cored vertically and horizontally prior to detailed design. This will allow the designer to confirm the thickness of the abutments, the presence of a footing, and the composition (i.e. rubble, solid concrete) of the abutments. In addition, the location of any shoring relative to the back face of the existing abutments can be confirmed by coring. Also, it is recommended that investigations of the embankments be undertaken for signs of timber bents (from old wooden trestles). Wharncliffe Road Widening from Becher Street to Commissioners Road CNR Subway Bridge Replacement MMM Group Limited November
16
17 APPENDIX A Key Plan
18 Key Plan CNR Subway
19 APPENDIX B Site Photographs
20 Photograph 1 South Elevation Photograph 2 Girders, Soffit and Floor System
21 Photograph 3 Northeast Wingwall Photograph 4 East Pier
22 Photograph 5 West Abutment
23 APPENDIX C Preliminary General Arrangement
24
25 APPENDIX D C Rail Preliminary Diversion Cost and Estimates Track Protection Concepts
26
27
28 APPENDIX E C Trestle, Preliminary Track Protection Cost Estimates and Lateral Slide Concepts
29
30
31
32
33
34
35 APPENDIX F Minutes from January 22, 2016 meeting with CNR
36 MEETING MINUTES Date of meeting: Friday, January 22, 2016 Location: Time: Purpose: CN Office 1 Administration Road Concord, ON L4K 1B9 10:30 a.m. Project: Wharncliffe Rd CNR (Strathroy Sub) Grade Separation Project Number: Author: Bob Rook To review and update CNR on the Environmental Assessment Study to Grade Separate the CN (Strathroy Subdivison) and Wharncliffe Road. Attendees: Title Company: Phone: Stefan Linder Manager, Public Works CNR stefan.linder@cn.ca (905) Vincent White Engineering Assistant CNR Vincent.White@cn.ca (905) Josh Ackworth Technologist, Transportation City of London jackwort@london.ca (519) x 7348 Doug Dixon Senior Project Manager, Structure MMM Group / WSP DixonD@mmm.ca (905) x 1236 Chris Suffern Project Engineer, Structure MMM Group / WSP SuffernC@mmm.ca (905) x 1527 Bob Rook, P. Eng., Senior Project Manager, Municipal MMM Group / WSP RookB@mmm.ca (905) x 1249 Distribution: All attendees above and the following: Ted Koza Transportation Design Engineer City of London tkoza@london.ca (519) x 5806 Michael Chiu Vice President MMM Group / WSP ChiuM@mmm.ca (905) x 1243 Gillian Thompson Project Manager MMM Group / WSP ThompsonG@mmm.ca (905) x 1285 Jay Goldberg Designer MMM Group / WSP GoldbergJ@mmm.ca (905) x 1284 Item Details Action By 1.0 Existing Condition Bob Rook provided an overview of existing conditions. Wharncliffe Road, a four lane urban roadway, north and south of CN crossing. At the CN structure, a 3 span structure provides an opening for a single lane northbound and two lanes southbound. Immediately south of the rail corridor is a major east/west four lane roadway, Horton Street. The intersection is signalized. Left turn movement from Wharncliffe Road onto Horton Street is not provided. Southbound left turn lanes turn onto Stanley Street while northbound left turn lanes turn onto Springbank Drive. Both streets are residential. Land use on Wharncliffe Road is a mixture of single family residential and commercial. The CN corridor has 2 main line tracks and carries approximately 28 trains per day. This includes 4 VIA trains in each direction. Vertical clearance at the underpass (road under rail) is substandard at 4.2 metres. Any omissions or errors in these notes should be forwarded to the author immediately North Sheridan Way, Suite 300, Mississauga, ON L5K 2P8 t: f: w:
37 Page 2 The City of London has acquired 3 residential properties, north of CNR corridor on the west side of Wharncliffe Road. Golder Associates have completed a geotechnical investigation for the grade separation project. A copy of the draft report was provided to CN (CD file). Wharncliffe Road is founded on layers of sand and silt, which is undertaken by silty clay and glacial till. The glacial till is very dense material. Limestone bedrock was encountered at 40m depth. It is expected that groundwater can be handled by pumping. Stefan Linder inquired if the project team was aware that fill embankments were constructed around timber trestle components which may be present in the rail corridor. MMM/WSP had received photos from their geotechnical consultant, Golders that identified the possibility of conflicts with the timber piles, if caissons or tie backs were installed through the fill embankment. Stefan will review CNR construction files. If necessary, a ground penetrating radar (GPR) investigation may be considered. Doug Dixon noted that it would be beneficial to have construction plans for the existing structure if CN is considering in-place construction. Coring of the abutments will still be required in the design phase of the project. Stefan Linder will review the availability of asconstructed bridge plans. 2.0 Preliminary Alternatives In the preliminary design phase, the project team reviewed 4 alternatives for Wharncliffe Road including two span and single span structures. East and west side widenings were considered along Wharncliffe Road. Copies of the preliminary options were provided in PDF. CNR CNR Wharncliffe Road would be reconstructed as a four lane roadway with left turn and right turn lanes at Horton Street. Provisions were provided for a future 1.5m on-street bike lane. Sidewalks are provided on both sides of Wharncliffe Road. Due to the proximity of Wharncliffe Road to Horton Street, the two span alternatives with a centre median pier was considered undesirable. The pier was a safety concern as well as restricting sight visibility. A single span structure is recommended. To minimize structure depth, a through plate girder bridge is proposed. Two alignments for Wharncliffe Road are still under consideration. The east side widening is recommended for in-place construction of the rail bridge. A west side widening is recommended if CN decides to construct a rail diversion. The road profile for Wharncliffe Road will result in a lowering of the existing road grade. At the rail crossing, a 0.8m profile lowering is required. At Horton Street, the lowering is 1.8 metres. 3.0 Track Profile Bob Rook noted that the City has completed a survey of the CN rail embankment including top of rail elevations (20m interval) from approximately 300m east to 300m west of Wharncliffe Road. Any omissions or errors in these notes should be forwarded to the author immediately North Sheridan Way, Suite 300, Mississauga, ON L5K 2P8 t: f: w:
38 Page 3 In reviewing the track profile, the rail tracks are in super-elevation. The Super-elevation is approximately 125mm. The track grade is relatively flat west of Wharncliffe Road. East of Wharncliffe Road, the track profile grade increases to 0.9%. At the rail structure, the track profile is locally depressed. To improve the vertical clearance (i.e. reduce road cut), MMM/WSP is recommending that the low rail for both tracks be the same. This will result in the floor beams being level and maintain a minimum ballast depth (400mm) under the low rail for each track. Opportunities are also available for a very nominal profile grade raise at Wharncliffe Road. An exaggerated profile (20:1 exaggeration) is provided in PDF. CN was requested to review the raising of the north track profile. 4.0 Horton Street Reconstruction Horton Street plan and profile was reviewed. The grade lowering extends from 200m west of Wharncliffe Road to 250m east of Wharncliffe Road. Horton Street will provide a four lane urban roadway with left turn and right turn lanes at Wharncliffe Road. Horton Street has been shifted to the south to minimize encroachment onto CN right-of-way. Immediately east and west of Wharncliffe Road, there is a nominal encroachment of the sidewalk into the CN right-of-way. This may be further reduced by reducing the boulevard width. CN was requested to review the feasibility of the sidewalk encroachment into the CN right-of-way. CNR CNR To maintain grading on the CN right-of-way, a retaining wall is required along the rail corridor. 5.0 Rail Diversion A preliminary rail diversion was developed on the south side of the CNR right-of-way. The existing track is presently on a continuous curve from ±300m east to ±700m west of Wharncliffe Road. The curve is approximately a 1.0 degree curve. To shift the rail track to the south, a tighter curve (1.75 degree) would be required. This may result in a lower design speed for passenger trains (i.e. 60 miles/h). Encroachment of the fill embankment on Horton Street would result in temporary track protection (shoring) to support the fill embankment. 6.0 CN Structure Doug Dixon provided an overview of the preferred structure general arrangement, which is a single span through plate girder (T.P.G.) supported on concrete abutments. The TPG structure will carry two (2) CNR tracks over Wharncliffe Road. The span length is 34.5m. The structure would be supported on piles, micropiles or caissons. The piles would be founded in the glacial till. The deposit exhibits end values ranging from 11 to greater than 100 blows per 0.3m. A very dense, grey sandy silt glacial till was encountered below the silty clay glacial till. Depth of pile is expected to be approximately 10m. Stefan Linder noted that trainmen walks would likely be required on both sides of the TPG bridge (to be confirmed). CNR Any omissions or errors in these notes should be forwarded to the author immediately North Sheridan Way, Suite 300, Mississauga, ON L5K 2P8 t: f: w:
39 Page 4 Doug Dixon noted that fiber optic cables were present on the existing rail structure and would be relocated. Temporary relocation options may include aerial relocation or supported in a U shape steel beam between the piled trestles. The cables would ultimately be enclosed in a duct structure and attached to the TPG. 7.0 Track Protection for Rail Diversion If a trestle system is proposed (i.e. build in-place alternative), micropiles would be used. For the rail diversion option, track protection details (Drawing S8) are proposed to support the existing railway embankment while excavating to install and support a continuous sheet pile or soldier pile wall. A second row of solider piles or sheeting would be installed with horizontal anchors to support the 2 track diversion. Golders report noted that driving sheeting to a suitable depth may be difficult in the dense till material. A soldier pile wall with shoring was detailed on Drawing S9 to support the widened fill embankment. 8.0 In-Place Construction Drawings S2 to S6 provides details for installation of concrete caissons for construction of soldier pile wall to support temporary trestles for each track at both abutment locations. Installation of caisson would require 8 night time closures (both tracks) for 8 hours. In addition, 8 night time closures of a single track for the remainder of the caissons would be required with CN flagging. For the trestle installation, MMM/WSP identified 2-12 hours closures (both tracks) at each abutment. Stefan Linder noted that his preference would be a longer weekend closure to complete the 4 trestles rather than 2 closures. (Suggested 36 hour closure, which includes CN removal and reinstatement of track). Doug Dixon noted that for the installation of the TPG superstructure, the project team reviewed a number of alternatives including lifting the superstructure in-place, sliding in place from a temporary concrete structure north of the permanent bridge (schematic S7) and transporting superstructure by rail and using Western Mechanical to slide in-place. The project team has reviewed the alternatives with Western Mechanical. Lifting in-place is not recommended due to the heavy load for a double track TPG and the limited work area for the size of cranes which would be required. The track closure time for a lateral slide alternative was estimated at 48 hours. Stefan Linder noted that his initial preference would be in-place construction. This would require agreement with CN Operations and Signals staff. Stefan will undertake a review with CN staff. Doug Dixon noted that MMM/WSP project team reached the same conclusion which is summarized in a comparison table between a rail diversion option and in-place construction. 9.0 Construction Staging Bob Rook provided an overview of a rail diversion and in-place construction schedule. The length of contract and road closure period for Wharncliffe Road was reduced for the inplace construction method. Any omissions or errors in these notes should be forwarded to the author immediately North Sheridan Way, Suite 300, Mississauga, ON L5K 2P8 t: f: w:
40 Page 5 Bob Rook noted that if the in-place construction was the selected method the east side widening alternative would be the preferred. This option would require relocation/removal of the private home at 100 Stanley Street. Josh Ackworth noted that this option may result in a Part II request in the EA process Stefan Linder noted that to respond to the preferred staging option, encroachment onto CN right-of-way and raising the track profile would take approximately 4 to 6 weeks for CN review Josh Ackworth noted that the City is proposing to proceed with construction of the grade separation in The 1200mm dia sanitary sewer that presently crosses the CN right-ofway along Wharncliffe Road would be relocated and the existing crossing abandoned. To abandon the sewer, the City would likely fill the sewer with grout. The City would review the schedule of both projects to minimize impact on Wharncliffe Road traffic Stefan Linder asked if the option of a jacked box would be considered at this crossing. Doug Dixon noted that the structure span would require a significant top slab depth, which would lower the road profile. This would have greater property impacts. City The foregoing represents the writer s understanding of the major items of discussion and the decisions reached and/or future actions required. If the above does not accurately represent the understanding of all parties attending, please notify the author within 48 hours of receiving these minutes at Minutes Prepared By: Bob Rook, P.Eng. Senior Project Manager Transportation Municipal Road Design 2655 North Sheridan Way, Suite 300 Mississauga, ON Canada L5K 2P8 t: x1249 f: c: RookB@mmm.ca Any omissions or errors in these notes should be forwarded to the author immediately North Sheridan Way, Suite 300, Mississauga, ON L5K 2P8 t: f: w:
41 APPENDIX G Cost Estimates
42 Part 1 Option A Rail Diversion Main Structure ITEM DESCRIPTION UNIT QTY PER UNIT AMMOUNT ROADWAY PROTECTION LS 1 $ 200, $ 200, EARTH EXCAVATION FOR STRUCTURE m $ $ 209, GRANULAR B BACKFILL TO STRUCTURE m $ $ 58, PILE DRIVING, MOBILIZATION AND DEMOBILIZATION LS 1 $ 70, $ 70, SUPPLY & PLACE HP310 X 110 m 648 $ $ 168, SUPPLY AND INSTALLATION OF CAST IN PLACE CONCRETE IN ABUTMENT FOOTINGS m $ $ 163, SUPPLY AND INSTALLATION OF REINFORCING STEEL IN ABUTMENT FOOTINGS t 32 $ 2, $ 70, SUPPLY AND INSTALLATION OF CAST IN PLACE CONCRETE FOR ABUTMENTS AND WINGWALLS SUPPLY AND INSTALLATION OF REINFORCING STEEL FOR ABUTMENTS AND WINGWALLS SUPPLY AND INSTALLATION OF COATED REINFORCING STEEL FOR ABUTMENT FOOTINGS, ABUTMENTS AND WINGWALLS m $ 1, $ 645, t 22 $ 2, $ 48, t 8 $ 2, $ 22, PERMENANT SOLDIER PILE AND LAGGING RETAINING WALLS m $ 2, $ 2,800, FABRICATION OF THROUGH PLATE GIRDER SPAN t 480 $ 3, $ 1,872, DELIVERY OF THROUGH PLATE GIRDER SPAN t 480 $ $ 216, ERECTION OF THROUGH PLATE GIRDER SPAN t 480 $ $ 465, COATING STRUCTURAL STEEL LS 1 $ 60, $ 60, SUPPLY AND INSTALLATION OF BEARINGS each 4 $ 17, $ 69, REMOVAL OF EXISTING STRUCTURE LS 1 $ 100, $ 100, WATERPROOFING OF BRIDGE DECK m $ $ 125, SUBTOTAL CONTINGENCY (40%) TOTAL $ $ $ 7,364, ,945, ,310,062.00
43 Part 2 - Option A -Rail Diversion - Detour ITEM DESCRIPTION UNIT QTY PER UNIT AMMOUNT EARTH EXCAVATION FOR STRUCTURE m $ $ 103, GRANULAR 'B' BACKFILL BEHIND SHORING WALLS m $ $ 184, SUPPLY & PLACE SHORING WALLS, C/W TIMBER LAGGING LS 1 $ 1,233, $ 1,233, TRACK & SHORING MONITORING LS 1 $ 50, $ 50, SUPPLY & PLACE 1200mm CHAIN LINK FENCE ON SHORING WALLS m 320 $ $ 35, SUPPLY & PLACE TRAINMEN'S WALKWAY $ - A) TRAINMEN'S WALKWAY FOR PRECAST CONCRETE SPANS LS 1 $ 20, $ 20, B) RAILING FOR TRAINMEN'S WALKWAY LS 1 $ 10, $ 10, GRADING WORK (RAILWAY EMBANKMENT, INSTALLATION OF TRACKS) LS 1 $ 4,000, $ 4,000, REMOVE DETOUR STRUCTURE AND CUT SHORING LS 1 $ 200, $ 200, SUBTOTAL $ CONTINGENCY (40%) $ TOTAL $ GRAND TOTAL PART 1 AND 2 $ 5,835, ,334, ,169, ,480,042.00
44 Option B - Trestle Option ITEM DESCRIPTION UNIT QTY PER UNIT AMMOUNT SUPPLY AND INSTALLATION OF TEMPORARY SHORING AND TRACK PROTECTION LS 1 $ 1,427, $ 1,427, ROADWAY PROTECTION LS 1 $ 200, $ 200, EARTH EXCAVATION FOR STRUCTURE m $ $ 135, GRANULAR B BACKFILL TO STRUCTURE m $ $ 57, SUPPLY, INSTALLATION, GROUTING AND TESTING OF MICROPILES m 920 $ $ 644, SUPPLY AND INSTALLATION OF CAST-IN-PLACE CONCRETE IN ABUTMENT FOOTINGS m $ $ 142, SUPPLY AND INSTALLATION OF REINFORCING STEEL IN ABUTMENT FOOTINGS t 28 $ 2, $ 70, SUPPLY AND INSTALLATION OF CAST-IN-PLACE CONCRETE FOR ABUTMENTS AND WINGWALLS SUPPLY AND INSTALLATION OF REINFORCING STEEL FOR ABUTMENTS AND WINGWALLS SUPPLY AND INSTALLATION OF COATED REINFORCING STEEL FOR ABUTMENT FOOTINGS, ABUTMENTS AND WINGWALLS m $ 1, $ 709, t 22 $ 2, $ 55, t 7 $ 2, $ 19, PERMENANT SOLDIER PILE AND LAGGING RETAINING WALLS m $ 2, $ 2,800, SUPPLY AND INSTALLATION OF TEMPORARY SUPPORT FOR THROUGH PLATE GIRDER LS 1 $ 1,179, $ 1,179, FABRICATION OF THROUGH PLATE GIRDER SPAN t 480 $ 3, $ 1,872, DELIVERY OF THROUGH PLATE GIRDER SPAN t 480 $ $ 216, ERECTION OF THROUGH PLATE GIRDER SPAN t 480 $ $ 465, COATING STRUCTURAL STEEL LS 1 $ 60, $ 60, SUPPLY AND INSTALLATION OF BEARINGS each 4 $ 17, $ 69, MOVE NEW BRIDGE INTO FINAL POSITION USING LATERAL SLIDE LS 1 $ 800, $ 800, REMOVAL OF EXISTING STRUCTURE LS 1 $ 100, $ 100, WATERPROOFING OF BRIDGE DECK m $ $ 125, SUBTOTAL CONTINGENCY (40%) TOTAL $ $ $ 11,148, ,459, ,607,620.00
45 APPENDIX H Schedules
46 Wharncliffe Road South CNR Subway Project Schedule Option A Rail Diversion WBS Task Start End Work Days 2019 Mar 2019 Apr 2019 May 2019 Jun 2019 Jul 2019 Aug 2019 Sep 2019 Oct 2019 Nov 2019 Dec 2020 Jan 2020 Feb 2020 Mar 2020 Apr 2020 May 2020 Jun 2020 Jul 2020 Aug 2020 Sep 2020 Oct 2020 Nov 2020 Dec 1 Grading Work on Horton Street & Installation of Detour 4-Mar-19 2-Dec Reconstruct and lower south side of Horton Street 4-Mar Jun Construct rail diversion, install shoring, reconstruct Horton Street Jun Oct Install track and ballast Oct Nov Transfer rail traffic to diversion Nov-19 2-Dec Construct New Bridge In Place 3-Dec-19 6-Aug Remove Existing Bridge Dec-19 9-Dec Excavation Dec Dec Drive Piles Dec Jan Construct footings Jan-20 6-Feb Construct abutments and wingwalls Feb-20 6-Mar Backfill Mar Mar Delivery of Steel Girders Mar Mar Install bearings Mar Mar Erect TPG Mar Jul Waterproofing Jul Jul Place subballast and ballast Jul Jul Install tracks Jul-20 5-Aug Divert rail traffic to new bridge Aug-20 6-Aug Remove Detour Alignment 7-Aug Sep Remove diversion Aug Sep Finishing Works 0-Jan-00 0-Jan Construct retaining walls on Wharncliffe and Horton Sep Dec Open Wharncliffe to Base Asphalt Dec Dec-20 1
Hospital Link Project Project Update September 2015
Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service
More informationPublic Information Center August 12, 2010
Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General
More informationPhoenix Sky Harbor transit guideway bridge
Phoenix Sky Harbor transit guideway bridge by David A. Burrows, Gannett Fleming The evolution of the PHX Sky Train s crossing of Taxiway Romeo At one of the 10 busiest airports in the United States, cast-in-place,
More informationHospital Link Project Project Update Winter 2018
Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open
More information5.7 Local road upgrades
5.7 Local road upgrades Local roads around the St Peters interchange and the intersection of Campbell Road and Euston Road would be upgraded to ensure safe and efficient connections with the New M5, and
More informationConstruction Staging Area Blue Jays Way (357 King Street West)
REPORT FOR ACTION Construction Staging Area Blue Jays Way (357 King Street West) Date: June 8, 2018. To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto
More informationDecember 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program
December 2012 Update I-95 New Haven Harbor Crossing Corridor Improvement Program Prepared by: Connecticut Department of Transportation District 3A 424 Chapel Street New Haven, CT 06511 Prepared for: South
More informationBUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018
BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO
More informationLOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017
LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20
More informationP3 & Design-Build. 101 st Annual THE Conference February 25 th, Speaker: Andrew Gensch, P.E.
P3 & Design-Build 101 st Annual THE Conference February 25 th, 2015 Speaker: Andrew Gensch, P.E. Presentation Outline Ohio River Bridges Project Overall Discussion Downtown Crossing and East End Locations
More informationAs the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.
REPORT FOR ACTION Construction Staging Area - 81 Bay Street Date: December 11, 2017 To: Toronto and East York, Community Council From: Acting Director, Transportation Services Toronto and East York District
More informationOhio Department of Transportation Construction Update
Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District
More information12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization
REPORT FOR ACTION 12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization Date: April 27, 2018 To: Toronto and East York Community Council From: Senior Strategic Director,
More informationEXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015
EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage
More informationThird Parties/Crossing
Third Parties/Crossing Presentation by Bill Scheers Canadian Association of Petroleum Land Administration Surface Land Administration Advisory Committee November 29, 2011 Agenda EAPUOC Guide for Working
More informationDufferin Jog Elimination Project
Project Project Status Update November 14 2007 Project History Planning Alternatives Criteria Measured Project Benefits Structural Configurations Considered Structural Design Considerations The Preferred
More informationSpencer Environmental Appendix A: Alternative Analysis for Construction Access Route
Spencer Environmental Appendix A: Alternative Analysis for Construction Access Route February 2015 Valley ine-stage 1 RT EISA Update FINA REPORT Page A1 Memorandum AECOM ConnectEd Transit Partnership 10235
More informationSection 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps
Section 106 Update Memo #1 Attachment D Traffic Diversion & APE Expansion Methodology & Maps I-65/I-70 North Split Interchange Reconstruction Project (Des. Nos. 1592385 & 1600808) Traffic Diversion and
More informationMembers of the Administrative Staff Committee. Award of Tender T Trans Canada Trail Extension
To: From: Members of the Administrative Staff Committee W.H. Jackson, Director of Utility Services Meeting Date: August 26, 2015 Subject: Report USEC15-021 Award of Tender T-54-15 - Trans Canada Trail
More informationK SIGNAGE & TRAFFIC CONTROL. Table of Contents
Table of Contents K1. ACCOMMODATION OF TRAFFIC... 1 K2. MINIMUM CONSTRUCTION SIGNING... 1 K3. SUBDIVISION SIGNS... 2 K4. TRAFFIC CONTROL DEVICES... 2 K4.1 Traffic Signs Regulations... 2 K4.2 Materials...
More informationTENDER NO. T WESTDALE ROAD SANITARY SEWER UPGRADE ADDENDUM NO. 1
TENDER NO. T-2170-2018 ADDENDUM NO. 1 SCHEDULE OF QUANTITIES AND PRICES REPLACE A revised copy of the Schedule of Quantities and Prices with changes bolded in red has been posted online (pdf attached).
More informationMason Street Bike/Pedestrian Trail Project
Construction of the much-anticipated Mason Trail is underway! Mountain Constructors was awarded the contract in September but had to go through a 2- month process to obtain construction clearance permits
More information1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET
Report No. 3 of the Regional Council Meeting of March 28, 2013 1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET The recommends: 1. Receipt
More informationC. APPROACH FOR IDENTIFYING THE BEST ROUTES FOR THE NEEDED TRANSMISSION SYSTEM IMPROVEMENTS
C. APPROACH FOR IDENTIFYING THE BEST ROUTES FOR THE NEEDED TRANSMISSION SYSTEM IMPROVEMENTS CL&P s approach for identifying the best routes for the needed transmission system improvements included a determination
More informationEXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015
EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley
More informationLongmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT
Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT December 2018 Project Summary Boulder County, Colorado, in partnership with the City of Boulder, is evaluating options for multi-use
More informationSECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY
WEEK ENDING FEBRUARY 1, 2019 SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY Contractor: Independence Excavating Inc. 1. Work Shift Day shift (M-F), with Saturday as a makeup day. 2. Traffic The new
More informationDesign Meeting Presentation
Contract No. 17ECS-TI-05SP April November 2017 Design Meeting Presentation November 2015 Agenda Items: Introduction (5 min) Overview (10 min) Scope of work (60 min): Schedule and Traffic Staging / Closures
More informationPattullo Bridge Replacement Project
Pattullo Bridge Overview This document will: Explain the challenges facing the Pattullo Bridge today Share how we propose moving forward translink.ca PAGE 1 History By Order of the Lieutenant Governor
More informationProvincial Railway Technical Standards
GENERAL: INDEX: The standards and requirements listed in this document are intended for use on provincially regulated railway public grade crossings. These standards are considered the minimum requirements
More informationRailway-Highway Crossing at Grade Regulations: Guidelines for British Columbia s Provincial Heritage Railways
Railway-Highway Crossing at Grade Regulations: Guidelines for British Columbia s Provincial Heritage Railways SHORT TITLE 1. These Guidelines may be cited as the Railway-Highway Crossing at Grade Guidelines.
More informationWAIPU COVE RESERVE BOARD POLICY DOCUMENT ANNUAL SITE DEVELOPMENT REGULATIONS
WAIPU COVE RESERVE BOARD POLICY DOCUMENT ANNUAL SITE DEVELOPMENT REGULATIONS This signed document, along with a plan and detail of any proposed works, must be submitted for approval to the board via management
More informationPRIORITIES COMMITTEE MEETING
PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony
More informationVista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington
Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington
More informationA. CONCLUSIONS OF THE FGEIS
Chapter 11: Traffic and Parking A. CONCLUSIONS OF THE FGEIS The FGEIS found that the Approved Plan will generate a substantial volume of vehicular and pedestrian activity, including an estimated 1,300
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Project Status Update Meeting Culver City Senior Center Wednesday, July 16, 2008 Description 8.6 mile corridor from downtown to Culver City in West Los Angeles 1.3
More informationU.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County
U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE
More informationTrail Feasibility Study
VOLUSIA COUNTY MPO CITY OF NEW SMYRNA BEACH FINAL REPORT JUNE 30, 2009 Trail Feasibility Study What s inside? 1 Introduction 2 Project Purpose & Scope 3 Physical Inventory & Assessment of Right-of- Way
More informationPRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction
PRESENTED TO Town of Middlebury, VT PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction Meeting with you today Brian Carpenter, Middlebury Selectboard Chair Jim Gish, Middlebury
More informationThe Holes Creek Bridge Replacement By Bradley McClelland
The Holes Creek Bridge Replacement By Bradley McClelland Each time there is a heavy rainstorm, the folks along Sheffield Road in the Dayton, Ohio suburb of West Carrollton have cause to be concerned. Holes
More information25 th Avenue Grade Separation. September 13, 2017
25 th Avenue Grade Separation September 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25
More informationHIGHWAY RAIL GRADE CROSSING CONSOLIDATION PROGRAM
HIGHWAY RAIL GRADE CROSSING CONSOLIDATION PROGRAM To decrease unnecessary train traffic exposure to life and property, promote public safety, and improve traffic conditions, the Texas Department of Transportation
More informationRoute 29 Solutions Projects
Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement
More information25 th Avenue Grade Separation. December 13, 2017
25 th Avenue Grade Separation December 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25
More informationTechnical Design Manual
Technical Design Manual BPG.TDM.VS.03.02 - November 2015 For use in the determination, application and design of Blade Piles, Slip Joint Pile Caps, Piled Slab Systems, Lateral Bracing Piles and connections
More information3. COLTA / HUGA CONNECTIONS - PRELIMINARY
9 3. COLTA / HUGA CONNECTIONS - PRELIMINARY 3.1 COLTA The Chain of Lakes Trail Association (COLTA) trail, formerly identified as the Chester Spur Line, was completed and opened for use in June 2011. The
More informationRecommendation: THAT the Council of the Township of Centre Wellington award the following two tenders:
Report to Council To: Mayor Linton and Members of Council Prepared By: Wes Snarr, Managing Director of Corporate Services Report: COR-45 Date: 12 Jul RE: Recomendation for Award of Request for Tenders
More informationLESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation
LESLIE BARNS & CONNECTION TRACK Project Update Construction and Traffic Management Consultation PRESENTATION SUMMARY Part 1 Brief Project Update (New Streetcars & Streetscape Improvements) Part 2 Construction
More informationLESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #6 January 30, 2014
LESLIE BARNS & CONNECTION TRACK Construction Liaison Group Meeting #6 January 30, 2014 Construction Liaison Group Jan 30 2014 1 OVERVIEW HAPPY BELATED NEW YEAR Works to Date Underground Utilities Bell
More informationTunnel design underneath the operating runway of Incheon airport
Geotechnical Aspects of Underground Construction in Soft Ground Yoo, Park, Kim & Ban (Eds) 2014 Korean Geotechnical Society, Seoul, Korea, ISBN 978-1-138-02700-8 Tunnel design underneath the operating
More informationAddendum - Airport Development Alternatives (Chapter 6)
Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary
More informationMetrolinx Projects: Temporary Delegation for Long- Term Road Closures
PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation
More informationFINAL. Bicycle/Pedestrian Feasibility Study City of DeBary Dirksen Drive Trail. Prepared For: Volusia County MPO
City of DeBary Dirksen Drive Trail FINAL Prepared By: Reynolds, Smith and Hills, Inc. Prepared For: Volusia County MPO September 2007 Table of Contents INTRODUCTION...1 PROJECT PURPOSE AND SCOPE...2 PHYSICAL
More informationConstruction Staging Adelaide Street West
REPORT FOR ACTION Construction Staging Adelaide Street West Date: October 6, 2016 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District
More informationConservatory awning W8 Description
1 3 4 Application Large-area external sun shading system for shading glazed conservatories, patio roofs and pergolas with flat pitch roofs. Function principle: tensioning system via toothed belt with steel
More informationConstruction Staging Area 19 Western Battery Road
REPORT FOR ACTION Construction Staging Area 19 Western Battery Road Date: December 6, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York
More informationJanuary 2018 Air Traffic Activity Summary
January 2018 Air Traffic Activity Summary Jan-2018 Jan-2017 CY-2018 CY-2017 Passengers 528,947 505,421 4.7% 528,947 505,421 4.7% Passengers 537,332 515,787 4.2% 537,332 515,787 4.2% Passengers 1,066,279
More informationLYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN. Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS
APPENDIX 15.1-3 LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN Purpose of the Structure Plan Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS LSP-P1 The District
More informationDAMAGE ASSESSMENT OF SAND FENCING GARDEN CITY, NORTH LITCHFIELD AND LITCHFIELD BEACH GEORGETOWN COUNTY, SC
OF SAND FENCING GARDEN CITY, NORTH LITCHFIELD AND LITCHFIELD BEACH GEORGETOWN COUNTY, SC June 07, 2017 PREPARED FOR: GEORGETOWN COUNTY DEPARTMENT OF PUBLIC SERVICES PREPARED BY: The EARTHWORKS Group 11655
More informationTIMBER BOLLARDS TYPE I. TYPE ll TS mm Radius 150 x 100 white painted Timber post dia Timber Post. Ground Level NOTES:
30 95 15 20mm Radius x 100 white painted Timber post 900 700 125 dia Timber Post Ground Level 500 500 TYPE I TYPE ll NOTES: 1. Type I Bollards are generally to be installed in grass verge areas. 2. Type
More informationTRAFFIC CONTROL DEVICES MANUAL FOR WORK ZONES
TRAFFIC CONTROL DEVICES MANUAL FOR WORK ZONES SUMMARY Work zone activities often create conditions on the travelled way that are hazardous particularly at night when the ability of motorists to see is
More informationEvaluation Report 569
Printed: March 1988 Tested at: Lethbridge ISSN 0383-3445 Group Evaluation Report 569 Vern Seed Boot and Banding Knife A Co-operative Program Between ALBERTA FARM MACHINERY RESEARCH CENTRE PAMI PRAIRIE
More informationRunway Status Lights (RWSL) in Japan. July 2015
Ministry of Land, Infrastructure, Transport and Tourism CIVIL AVIATION BUREAU OF JAPAN Runway Status Lights (RWSL) in Japan July 2015 Table of contents Civil Aviation Bureau Japan What is RWSL Background
More informationA63 Castle Street, Hull HullBID Network Lunch 24 August 2017
A63 Castle Street, Hull HullBID Network Lunch 24 August 2017 James D Leeming Senior Project Manager What we will cover today? Introduction to Highways England and the Road Investment Strategy A63 Scheme
More informationFrequently Asked Questions on the Route 29 Solutions Improvements Projects
Frequently Asked Questions on the Route 29 Solutions Improvements Projects Background What are the Route 29 Solutions improvement projects? These projects include the Route 29/250 Interchange ( Best Buy
More informationFDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015
June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane
More informationBUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019
BUILD CONSTRUCTION Update FEBRUARY 2019 In this issue: ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEATURED PROJECT: KENT AVENUE * Featured Project KENT AVENUE CP 2-3 CONSTRUCTION UPDATE February 2019 At
More informationLevel Crossings Design and Installation
Discipline: Engineering (Track & Civil) Category: Standard Level Crossings Design and Installation ETD-16-02 Applicability New South Wales CRIA (NSW CRN) Primary Source ARTC NSW Standard XDS 02 Document
More informationPalm Beach County Traffic Report July 13 through July 20, 2012
For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be
More informationUpdate Report - Etobicoke Creek and South Mimico Creek Trails
REPORT FOR ACTION Update Report - Etobicoke Creek and South Mimico Creek Trails Date: October 23, 2017 To: Etobicoke York Community Council From: General Manager, Parks Forestry and Recreation Wards: Ward
More informationCHICAGO DEPARTMENT OF AVIATION. Current Construction Projects AND THE O HARE MODERNIZATION PROGRAM. May 2, 2014
CHICAGO DEPARTMENT OF AVIATION AND THE O HARE MODERNIZATION PROGRAM Current Construction Projects May 2, 2014 O HARE INTERNATIONAL AIRPORT CURRENT CONFIGURATION 2 PHASE 1 & COMPLETION PHASE 9L-27R Completed
More informationINSTALLATION INSTRUCTIONS for folding arm awnings
Custom made Awnings and Blinds Item No 0757 INSTALLATION INSTRUCTIONS for folding arm awnings IMPORTANT INFORMATION BEFORE INSTALLING YOUR Updated 08/09/15 AN AWNING INSTALLATION IS A HOME IMPROVEMENT
More informationRegional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017
Regional Connector Transit Project Community Leadership Council 2 nd Hope Station & Flower St Committees January 17, 2017 1 EAT SHOP PLAY LOCAL 2 Eat Shop Play Local > Free Metro marketing campaign > Make
More informationMcCORMICK QUARRY BRIDGE EAST SHORE EXPRESSWAY BRIDGE WITOLD H. KLOCZKOWSKI, P.E. PROJECT MANAGER COMMONWEALTH ENGINEERS & CONSULTANTS, INC.
Rhode Island DOT Replaces Bridges Over Extended Weekends Using PBES and SPMTs DAVID W. FISH, P.E. ADMINISTRATOR OF PROJECT MANAGEMENT RI DEPARTMENT OF TRANSPORTATION WITOLD H. KLOCZKOWSKI, P.E. PROJECT
More informationEAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library
EAST DON TRAIL ENVIRONMENTAL ASSESSMENT Community Liaison Committee Meeting #3 July 15, 2013 6:30 to 8:30 pm Flemingdon Park Library Agenda 1. Welcome 2. Housekeeping and Updates a) Housekeeping b) CLC
More informationMemorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description
Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Analette Ochoa and Wana Chiu, WRECO Parag Mehta, Kimley Horn Date: November 7, 2017 Re: Santa Cruz Route 1 Tier I and Tier II HOV
More informationFront Carport Design Standards, Requirements & Application
Front Carport Design Standards, Requirements & Application THIS PAGE INTENTIONALLY LEFT BLANK. Carport: A structure designed or used to shelter vehicles that is open on at least two sides. Carport shall
More informationToronto 2015 Pan Am/Parapan Am Games Temporary Traffic By-law Amendments for High Occupancy Vehicle Lanes (Supplementary Report)
STAFF REPORT ACTION REQUIRED Toronto 2015 Pan Am/Parapan Am Games Temporary Traffic By-law Amendments for High Occupancy Vehicle Lanes (Supplementary Report) Date: March 25, 2015 To: From: Wards: Reference
More informationPort MacKenzie Rail Extension
Port MacKenzie Rail Extension Project The Matanuska-Susitna Borough (MSB) and the Alaska Railroad Corporation (ARRC) jointly propose construction and operation of a new rail line to connect the Borough
More informationElectric System Serving Pierce County Current system and future investments
Electric System Serving Pierce County Current system and future investments Janet Olsen Project Manager Steve Botts Real Estate / Rights-of-Way April 13, 2011 Presentation overview Information requested
More informationIS A BUDGET ONLY DESCRIPTION QUANTITY UNIT
Miller Creek Consultants LLC CONCRETE RECAP 1/29/2009 ESTIMATE DATE: 1-Jan-09 Project: 4000 psi 95.00 Location: 3000 psi 88.00 PROJECT DATA PROJECT NAME: Concrete Estimate THIS IS A BUDGET ONLY DESCRIPTION
More informationUnited States Department of the Interior National Park Service. Boundary Expansion Listed in National Register January 11, 2017
NPS Form 10900-a (Rev. 8/2002) OMB No. 10240018 United States Department of the Interior National Park Service Boundary Expansion Listed in National Register January 11, 2017 National Register of Historic
More informationSTAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk
STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)
More informationMadison Metro Transit System
Madison Metro Transit System 1101 East Washington Avenue Madison, Wisconsin, 53703 Administrative Office: 608 266 4904 Fax: 608 267 8778 TO: FROM: SUBJECT: Plan Commission Timothy Sobota, Transit Planner,
More informationFEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A
VIRGINIA DEPARTMENT OF TRANSPORTATION I-85 / I-95 INTERCHANGE FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A Columbia Rd REFINED CONCEPT 1 PROJECT A Bellevue Rd COST: $3.3M Siege Rd Eliminate the loop ramp
More informationADDENDUM NO. TWO AB
ADDENDUM NO. TWO AB2018-28 Notice is hereby given that on June 22, 2018 at 11:00 A.M. (Prevailing time), sealed bids will be opened and read in public by the Purchasing Department in the Mercer County
More informationLevel Crossings Configuration Standards
Discipline: Engineering (Track & Civil) Category: Standard Level Crossings Configuration Standards ETD-16-04 Applicability New South Wales CRIA (NSW CRN) Primary Source ARTC NSW Standard XDS 01 Document
More informationProposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street
STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure
More informationBloor Street West Rezoning Application for a Temporary Use By-law Final Report
STAFF REPORT ACTION REQUIRED 3741 3751 Bloor Street West Rezoning Application for a Temporary Use By-law Final Report Date: June 12, 2007 To: From: Wards: Reference Number: Etobicoke York Community Council
More informationAstoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019
Astoria Boulevard ADA Upgrade and Station Renewal January 7, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two Mezzanine-to-Platform
More informationDD FORM 3009, FEB 2016 REPLACES DA FORM 1247, WHICH IS OBSOLETE. Page 1 of 6 Pages Adobe Professional X
ROUTE CLASSIFICATION For use of this form, see ATP 3-34.81/MCWP 3-17.4; the proponent agency is TRADOC. SECTION I 1. SERIAL NUMBER 2. TO 3. FOR INFORMATION 4. DATE/TIME GROUP 5. NUMBER OF SHEETS OR ENCLOSURES
More informationWhittier Bridge Project
Amesbury / Newburyport / Salisbury Whittier Bridge / I-95 Improvement Project Original Whittier Bridge Proposed Whittier Bridges 10/21/2016 Whittier Bridge Project 1 Project Description The project limits
More informationSHEET PILE WALLS A SPACE-SAVING AVALANCHE DEFENCE STRUCTURE
SHEET PILE WALLS A SPACE-SAVING AVALANCHE DEFENCE STRUCTURE ÁRNI JÓNSSON, ORION Consulting Engineers * ERIK HESTNES, Norwegian Geotechnical Institute** ABSTRACT: Steel sheet piles, primarily used as retaining
More informationSection 3-04 Cross Sectional Elements TABLE OF CONTENTS. INTRODUCTION...3 General...3 Exhibit 1-Cross-Sectional Elements...3
Section 3-04 Cross Sectional Elements TABLE OF CONTENTS INTRODUCTION...3 General...3 Exhibit 1-Cross-Sectional Elements...3 CROSS-SECTIONAL ELEMENTS...3 Traveled Way...3 Shoulder...3 Surfacing Taper...3
More informationMidland Penetanguishene Transit Committee Penetanguishene Town Office - Committee Room Tuesday, March 6 th, :00 a.m.
Midland Penetanguishene Transit Committee Penetanguishene Town Office - Committee Room Tuesday, March 6 th, 2018 9:00 a.m. 1. CALL TO ORDER 2. MINUTES FROM PREVIOUS MEETING i) Minutes from Midland Penetanguishene
More informationElectric System Serving Pierce County Current system and future investments. Janet Olsen Steve Botts
Electric System Serving Pierce County Current system and future investments Janet Olsen Steve Botts Project Manager Real Estate t / Rights-of-Way April 13, 2011 Presentation overview Information requested
More informationAPPENDIX F List of Commitments
APPENDIX F List of Commitments s Table F.1 Standard Mitigation Measures Mitigation Measure MnDOT Specification Number Status Update Description Status Update Utilities Provide early notice to utility operators
More informationAstoria Boulevard ADA and Station Renewal Track Improvements. January 30, 2019
Astoria Boulevard ADA and Station Renewal Track Improvements January 30, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two
More informationPort of Durban. Entrance Channel Widening & Deepening Project Completion Function. 31 March 2010
Port of Durban Entrance Channel Widening & Deepening Project Completion Function 31 March 2010 Presented by: Theunis Steenkamp Project Director Natcor 1 The saying goes.. THE JOB IS NOT OVER UNTILL THE
More information