1 Rhode Island DOT Replaces Bridges Over Extended Weekends Using PBES and SPMTs DAVID W. FISH, P.E. ADMINISTRATOR OF PROJECT MANAGEMENT RI DEPARTMENT OF TRANSPORTATION WITOLD H. KLOCZKOWSKI, P.E. PROJECT MANAGER COMMONWEALTH ENGINEERS & CONSULTANTS, INC. EAST SHORE EXPRESSWAY BRIDGE McCORMICK QUARRY BRIDGE 1
2 Opening Remarks Mr. David W. Fish, P.E. Administrator of Project Management RI Department of Transportation 2
3 OWNER: RI DEPARTMENT OF TRANSPORTATION OVERSIGHT: FHWA RI DIVISION DESIGN CONSULTANT: COMMONWEALTH ENGINEERS & CONSULTANTS, INC CONTRACTOR: MANAFORT BROTHERS INC. 3
4 PROJECT LOCATION PROVIDENCE EAST PROVIDENCE BOTH BRIDGES ARE LOCATED IN EAST PROVIDENCE, RHODE ISLAND EAST BAY COMMUNITIES RHODE ISLAND 4
5 PROJECT LOCATION PROVIDENCE EAST SHORE EXPRESSWAY BRIDGE McCORMICK QUARRY BRIDGE N EAST PROVIDENCE EAST SHORE EXPRESSWAY SB EAST SHORE EXPRESSWAY NB TRAFFIC DATA: - US ROUTE 6 (WARREN AVE), 19,000 VPD - EAST SHORE EXPRESSWAY, 38,000 VPD 5
6 PROJECT LOCATION McCORMICK QUARRY BRIDGE RIDOT Maintenance Facility N EAST SHORE EXPRESSWAY BRIDGE 6
7 EXISTING BRIDGES EAST SHORE EXPRESSWAY BRIDGE McCORMICK QUARRY BRIDGE EAST SHORE EXPRESSWAY BRIDGE: - CONSTRUCTED IN SPAN CONTINUOUS T-BEAM - ~ SPANS - 60 DEG SKEW McCORMICK QUARRY BRIDGE: - CONSTRUCTED IN SPAN P/C I-GIRDER - ~ SPANS - 40 DEG SKEW 7
8 GENERAL BRIDGE CONDITION EAST SHORE EXPRESSWAY BRIDGE McCORMICK QUARRY BRIDGE 8
9 WHY ABC? TWO SEASON, TWO PHASE CONVENTIONAL CONSTRUCTION RAISED TRAFFIC CONCERNS FOR THIS MAJOR EXPRESSWAY. RIDOT SUCCESSFULLY EMPLOYED SPMT S FOR A PRIOR CONTRACT. PROJECT SITE IS WELL SUITED TO SPMT S, DUE TO PROXIMITY OF BSA S AND SHORT TRAVEL PATHS. CONSULTED WITH AN SPMT CONTRACTOR. ALL AGREED THE SITE WAS IDEAL. CONSULTANT PROPOSED GEOSYNTHETIC REINFORCED SOIL (GRS) ABUTMENTS, TO BE CONSTRUCTED IN ADVANCE OF THE W/E CLOSURE, UNDER THE EXISTING BRIDGE. PRECAST CONCRETE SUBSTRUCTURE COMPONENTS HELPED TO SPEED UP THE REPLACEMENT. PRECAST COMPONENTS GRS SPMT s 9
10 NEW BRIDGE CONFIGURATIONS EAST SHORE EXPRESSWAY BRIDGE EXISTING BRIDGE NEW BRIDGE 3-SPAN BECOMES SINGLE SPAN 10
11 NEW BRIDGE CONFIGURATIONS McCORMICK QUARRY BRIDGE EXISTING BRIDGE NEW BRIDGE 3-SPAN BECOMES SINGLE SPAN 11
12 NEW BRIDGE CONFIGURATIONS EAST SHORE EXPRESSWAY BRIDGE McCORMICK QUARRY BRIDGE 12
13 TYPICAL GRS DETAIL NO LONG-TERM SETTLEMENT CONCERNS 13
14 SKEW/RACKING ACCOMMODATIONS 14
15 PRECAST ELEMENTS & INTEGRAL BACKWALL TYPICAL FOOTING SEGMENT SIZE = 20 X13 X2, 78,000 LBS. LARGER WALL SEGMENT SIZE = 20 x11 x1-7, 52,000 LBS. 15
16 INCENTIVES & DISINCENTIVES EACH BRIDGE WAS ASSIGNED A DISTINCT 80 HOUR EXTENDED WEEKEND INCENTIVE CLOSURE PERIOD, FROM 9PM FRIDAY TO 5AM TUESDAY (CONTINUOUS DAY/NIGHT). CONTRACT LANGUAGE: 16
17 BRIDGE STAGING AREAS McCORMICK QUARRY BRIDGE BSA RIDOT Maintenance Facility N BSA EAST SHORE EXPRESSWAY BRIDGE 17
18
19
20
21
22
23 ADVANCED UTILITY RELOCATIONS EAST SHORE EXPRESSWAY BRIDGE (McCORMICK QUARRY BRIDGE SIMILAR) 23
24 ADVANCED GRS CONSTRUCTION McCORMICK QUARRY BRIDGE (BRIDGE EAST SHORE EXPRESSWAY SIMILAR) CONSTRUCTING GRS ABUTMENTS UNDER THE EXISTING BRIDGE 24
25 SUPERSTRUCTURE IN THE BSA EAST SHORE EXPRESSWAY BRIDGE (McCORMICK QUARRY BRIDGE SIMILAR) BUILDING THE NEW BRIDGE IN THE BRIDGE STAGING AREA 25
26 CONSTRUCTION EAST SHORE EXPRESSWAY BRIDGE (McCORMICK QUARRY BRIDGE SIMILAR) COMPLETED SUPERSTRUCTURE, WITH BARRIERS INCLUDED 26
27 CONTRACTOR S DEMOLITION SUBMITTAL Demolition equipment, materials, sequence designed by the Contractor to suit his means and methods. Contractor s engineer analyzed the existing bridge members to address their condition, and to accommodate the proposed sequence. Bridge ratings were made available to the Contractor. Demolition was performed entirely during the 80 hour road closure. 27
28 EAST SHORE EXPRESSWAY BRIDGE 28
29 EAST SHORE EXPRESSWAY BRIDGE START OF THE W/E ROAD CLOSURE 29
30 EAST SHORE EXPRESSWAY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 30
31 EAST SHORE EXPRESSWAY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 31
32 EAST SHORE EXPRESSWAY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 32
33 EAST SHORE EXPRESSWAY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 33
34 EAST SHORE EXPRESSWAY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 34
35 EAST SHORE EXPRESSWAY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 35
36 EAST SHORE EXPRESSWAY BRIDGE SETTING THE PRECAST COMPONENTS 36
37 EAST SHORE EXPRESSWAY BRIDGE SETTING THE PRECAST COMPONENTS 37
38 EAST SHORE EXPRESSWAY BRIDGE SETTING THE PRECAST COMPONENTS 38
39 EAST SHORE EXPRESSWAY BRIDGE MOVING THE BRIDGE ON THE SPMT s 39
40 EAST SHORE EXPRESSWAY BRIDGE MOVING THE BRIDGE ON THE SPMT s 40
41 EAST SHORE EXPRESSWAY BRIDGE MOVING THE BRIDGE ON THE SPMT s 41
42 EAST SHORE EXPRESSWAY BRIDGE FINISHING THE APPROACH FILL & WALLS 42
43 EAST SHORE EXPRESSWAY BRIDGE MOVING THE BRIDGE ON THE SPMT s 43
44 EAST SHORE EXPRESSWAY BRIDGE FINISHING THE APPROACH FILL & WALLS 44
45 EAST SHORE EXPRESSWAY BRIDGE AFTER THE W/E CLOSURE - NEW STRUCTURE OPEN TO TRAFFIC 45
46 McCORMICK QUARRY BRIDGE 46
47 McCORMICK QUARRY BRIDGE START OF THE W/E ROAD CLOSURE 47
48 McCORMICK QUARRY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 48
49 McCORMICK QUARRY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 49
50 McCORMICK QUARRY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 50
51 McCORMICK QUARRY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 51
52 McCORMICK QUARRY BRIDGE DEMOLITION DURING THE WEEKEND ROAD CLOSURE 52
53 McCORMICK QUARRY BRIDGE SETTING THE PRECAST COMPONENTS 53
54 McCORMICK QUARRY BRIDGE SETTING THE PRECAST COMPONENTS 54
55 McCORMICK QUARRY BRIDGE SETTING THE PRECAST COMPONENTS 55
56 McCORMICK QUARRY BRIDGE MOVING THE BRIDGE ON THE SPMT s 56
57 McCORMICK QUARRY BRIDGE MOVING THE BRIDGE ON THE SPMT s 57
58 McCORMICK QUARRY BRIDGE MOVING THE BRIDGE ON THE SPMT s 58
59 McCORMICK QUARRY BRIDGE MOVING THE BRIDGE ON THE SPMT s 59
60 McCORMICK QUARRY BRIDGE FINISHING THE APPROACH FILL & WALLS 60
61 McCORMICK QUARRY BRIDGE AFTER THE W/E CLOSURE - NEW STRUCTURE OPEN TO TRAFFIC 61
62 A PDF OF THIS PRESENTATION, AND WEB-LINKS TO TIME- LAPSE VIDEO S WILL BE PROVIDED BY FIU 62
63 FINAL STRUCTURES - Contract Type: Design/Bid/Build - Total Construction Cost - Bid = $12.7 million, to-date = $11.8 million - Total Construction Duration = 16 months - East Shore Expressway Bridge incentive payment = $ McCormick Quarry Bridge incentive payment = $152k = 19hrs x $8k/hr - Total Incentive Payments - $152k McCORMICK QUARRY BRIDGE EAST SHORE EXPRESSWAY BRIDGE - Contract Closure = 80 hrs per bridge - Actual Closure: - East Shore Expressway Br = 80hrs - McCormick Quarry Bridge = 61 hrs No traffic gridlock! 63
64 Key take-aways: Conducted successful public out-reach, Weekend move = less traffic and short-lived impacts, Lesson learned from 1 st bridge - construct some of the approach fill and wing walls with wrapped-face system before the SPMT move rather than after, Adjustable bearing detail pros/cons. 64
65 THANK YOU FOR WATCHING 65
Project Overview. Hunter Mill Road Over Colvin Run Bridge Replacement Fairfax County. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate any information received as a result of the public information meeting. The comment sheet in this brochure is provided to assist in making your
More informationPhoenix Sky Harbor transit guideway bridge
Phoenix Sky Harbor transit guideway bridge by David A. Burrows, Gannett Fleming The evolution of the PHX Sky Train s crossing of Taxiway Romeo At one of the 10 busiest airports in the United States, cast-in-place,
More informationACCELERATED CONSTRUCTION LANE RENTAL FEES & A+B BIDDING DALLAS DISTRICT. June 7, 2018 Transportation Planning Conference June 7, 2018
ACCELERATED CONSTRUCTION LANE RENTAL FEES & A+B BIDDING DALLAS DISTRICT June 7, 2018 Dallas District Accelerated Construction Techniques Accelerated Construction Techniques commonly used by the Dallas
More informationCommonwealth Avenue Bridge Deck Replacement Project. Legislative and Stakeholder Briefing. April 13, 2017
Commonwealth Avenue Bridge Deck Replacement Project Legislative and Stakeholder Briefing April 13, 2017 1 Project Team Contractor Walsh Construction Company Design Team HDR Lead City Point Partners, LLC
More informationEXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015
EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley
More informationBUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018
BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO
More informationAtlantic Street Bridge Project CTDOT Project Nos & (Phase 2)
Atlantic Street Bridge Project CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro North RR Bridge Replacement Track & Station Infrastructure Improvements City of Stamford
More informationPublic Information Center August 12, 2010
Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General
More informationAdd-A-Lane Contract V. along a Section of I-95 includes 6 Bridges
Newton Needham Chamber of Commerce Add-A-Lane Contract V along a Section of I-95 includes 6 Bridges Project File No. 603711 July 29, 2014 1 Agenda Project Update Overview Bid and Contract Award Schedule
More informationPre-Construction Public Meeting July 2017
Pre-Construction Public Meeting July 2017 Agenda Introduction to Project Team Project Description Schedule Impacts Communication/Public Outreach 2 Contractor Walsh Construction Design Team HDR Lead City
More informationOuter Banks Bridges Update:
Outer Banks Bridges Update: Outer Banks Chamber of Commerce Economic Summit Jerry D. Jennings, PE - Division Engineer April 12, 2018 Mid-Currituck Bridge Currituck Sound (Wright Memorial Bridge) Alligator
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Project Status Update Meeting Culver City Senior Center Wednesday, July 16, 2008 Description 8.6 mile corridor from downtown to Culver City in West Los Angeles 1.3
More informationWelcome to Webinar on Accelerated Bridge Construction Colorado Flyover Ramp Showcases Precast Pier Caps and Curved Spliced Precast U-Girders
Welcome to Webinar on Accelerated Bridge Construction Colorado Flyover Ramp Showcases Precast Pier Caps and Curved Spliced Precast U-Girders Sponsored by Accelerated Bridge Construction University Transportation
More informationWelcome to Webinar on Accelerated Bridge Construction Milton-Madison Bridge Replacement: the Mega-Lateral Slide
Welcome to Webinar on Accelerated Bridge Construction Milton-Madison Bridge Replacement: the Mega-Lateral Slide Sponsored by Accelerated Bridge Construction University Transportation Center (ABC-UTC) at
More informationTrail Feasibility Study
VOLUSIA COUNTY MPO CITY OF NEW SMYRNA BEACH FINAL REPORT JUNE 30, 2009 Trail Feasibility Study What s inside? 1 Introduction 2 Project Purpose & Scope 3 Physical Inventory & Assessment of Right-of- Way
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov A daytime lane closure on Mesa all week is needed to complete Sunday s demo
More information5.7 Local road upgrades
5.7 Local road upgrades Local roads around the St Peters interchange and the intersection of Campbell Road and Euston Road would be upgraded to ensure safe and efficient connections with the New M5, and
More informationI-35 Reconstruction Project
I-35 Reconstruction Project Business Community Meeting McLennan County Projects Jodi Wheatley, I 35 Information Specialist, TxDOT John Jasek, PE, Waco Area Engineer, TxDOT Jacob Bell, PE, Project Manager,
More informationDecember 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program
December 2012 Update I-95 New Haven Harbor Crossing Corridor Improvement Program Prepared by: Connecticut Department of Transportation District 3A 424 Chapel Street New Haven, CT 06511 Prepared for: South
More informationAtlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)
Atlantic Street Bridge Project Update CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement Track & Station Infrastructure Improvements City
More informationDeterioration Factors at Girder Ends
Deterioration Factors at Girder Ends Robert P. Zaffetti, P.E. Connecticut Department of Transportation September 29, 2010 Northeast Bridge Preservation Partnership Meeting Hartford, CT Overview One of
More informationMilestone: Bridge to Nowhere scheduled for demolition Aug 14
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Blanca Del Valle (915) 790-4341 Blanca.DelValle@txdot.gov August 12, 16 Milestone: Bridge to Nowhere scheduled for demolition Aug 14
More informationEXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015
EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage
More informationDufferin Jog Elimination Project
Project Project Status Update November 14 2007 Project History Planning Alternatives Criteria Measured Project Benefits Structural Configurations Considered Structural Design Considerations The Preferred
More informationUS 19 Sunset Point Rd to Countryside Blvd.
Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started
More informationAPPENDIX F. Structural Design Report
APPENDIX F Structural Design Report CONSULTANT SERVICES FOR AN ENVIRONMENTAL ASSESSMENT (EA) STUDY OF WHARNCLIFFE ROAD WIDENING FROM BECHER STREET TO COMMISSIONERS ROAD CNR SUBWAY BRIDGE REPLACEMENT STRUCTURAL
More informationN. Central St. & W. Jackson Ave. Streetscape Projects
N. Central St. & W. Jackson Ave. Streetscape Projects October 13, 2016 Meeting Overview North Central Street City of Knoxville KUB History & Vision Plan Timing Project Area Overview Schedule Communications
More informationLOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017
LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20
More informationConstructor: Joseph B. Fay
1 1 2 OWNER: PENNDOT Engineering District 11-0 City of Pittsburgh Design Consultant: SAI Consulting Engineers KTA-Tator Constructor: Joseph B. Fay Construction Manager: Michael Baker Construction Inspection:
More informationCounty of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation
Silver Line Update Committee for Dulles March 2, 2017 Mark Canale Fairfax County Department of Transportation Phase 1 Summary Old Meadow Road Realignment design work proceeding, construction to be completed
More informationNeighbourhood Committee NDG - Westmount. September 12, 2016
Neighbourhood Committee NDG - Westmount September 12, 2016 2 Presentation Outline Requests from the committee members Feedback on previous questions Work update and hindrance of the Turcot Project Ministry
More informationLincoln Village Pedestrian Bicycle Bridge Community Meeting September 13th, 2016
Lincoln Village Pedestrian Bicycle Bridge Community Meeting September 13th, 2016 Purpose of the Meeting Introduce the project and the proposed improvements Review existing conditions Discuss the needs
More informationProject Summary 2009
Project Summary 2009 SB-2009-MN-55360: Lady Slipper Scenic Byway Pedestrian Walkway State Submission Date not submitted Division Submission Date not submitted State Priority 0 This application must be
More informationMain Street Station Upgrades
Main Street Station Upgrades Public Meeting Hope United Church 1 Main Street Station Upgrades Bus diversions Planned improvements Construction staging Pedestrian flows 2 Main Street Station Aerial Bar
More informationAirside Construction Safety: The Human Factor
Airside Construction Safety: The Human Factor Presented by The Massachusetts Port Authority Houssam H. Sleiman, P.E., CCM Director, Capital Programs and Environmental Affairs September 25, 2010 ACI-NA
More informationSR 429/WEKIVA PARKWAY FTBA CONFERENCE March 20-21, Presented By Suzanne Phillips, P.E., FDOT District 5
SR 429/WEKIVA PARKWAY FTBA CONFERENCE March 20-21, 2012 Presented By Suzanne Phillips, P.E., FDOT District 5 Project Description The Wekiva Parkway project constructs 25 centerline miles of new toll expressway.
More informationDALLAS HORSESHOE PROJECT. Project Update including the Margaret McDermott Bridge Transportation and Trinity River Project Committee February 22, 2016
DALLAS HORSESHOE PROJECT Project Update including the Margaret McDermott Bridge Transportation and Trinity River Project Committee February 22, 2016 Agenda 1. Horseshoe Project 2. Purpose and Need 3. Construction
More informationRegional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017
Regional Connector Transit Project Community Leadership Council 2 nd Hope Station & Flower St Committees January 17, 2017 1 EAT SHOP PLAY LOCAL 2 Eat Shop Play Local > Free Metro marketing campaign > Make
More informationPRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction
PRESENTED TO Town of Middlebury, VT PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction Meeting with you today Brian Carpenter, Middlebury Selectboard Chair Jim Gish, Middlebury
More informationExhibit 2. Preconstruction Jan Jun-19
Activity ID Activity Name Original Broward Convention Center 1273 02-Jan-17 05-Jan-22 Preconstruction 620 02-Jan-17 10-Jun-19 Pre-Development Agreements 152 02-Jan-17 03-Aug-17 DA Pre-Development Agreement
More informationIRONTON-RUSSELL BRIDGE REPLACEMENT
IRONTON-RUSSELL BRIDGE REPLACEMENT 2012-2016 District 9 Ohio Department of Transportation Ironton-Russell Bridge Replacement Existing Ironton-Russell Bridge Ironton-Russell Bridge Replacement Existing
More informationP3 & Design-Build. 101 st Annual THE Conference February 25 th, Speaker: Andrew Gensch, P.E.
P3 & Design-Build 101 st Annual THE Conference February 25 th, 2015 Speaker: Andrew Gensch, P.E. Presentation Outline Ohio River Bridges Project Overall Discussion Downtown Crossing and East End Locations
More informationHospital Link Project Project Update September 2015
Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service
More informationAstoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019
Astoria Boulevard ADA Upgrade and Station Renewal January 7, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two Mezzanine-to-Platform
More informationTwo townships received top
Awards 35 TH ANNUAL ROAD AND BRIDGE SAFETY IMPROVEMENT AWARDS Townships Are Recognized for Projects That Increase Safety on Roads and Bridges Two townships were recognized during PSATS 95 th Annual Educational
More informationTransportation Supporting Dulles Airport
Transportation Supporting Dulles Airport Committee for Dulles Economic Development and Transportation Committee July 12, 2018 Tom Biesiadny, Director Fairfax County Multiple Transportation Improvements
More informationWhittier Bridge Project
Amesbury / Newburyport / Salisbury Whittier Bridge / I-95 Improvement Project Original Whittier Bridge Proposed Whittier Bridges 10/21/2016 Whittier Bridge Project 1 Project Description The project limits
More informationPattullo Bridge Replacement Project
Pattullo Bridge Overview This document will: Explain the challenges facing the Pattullo Bridge today Share how we propose moving forward translink.ca PAGE 1 History By Order of the Lieutenant Governor
More informationUSERS of EXISTING TOLL FACILITIES in HAMPTON ROADS
USERS of EXISTING TOLL FACILITIES in HAMPTON ROADS PREPARED BY: SEPTEMBER 2012 T12-10 ii REPORT DOCUMENTATION TITLE Users of Existing Toll Facilities in Hampton Roads AUTHOR Robert B. Case, PE, PTOE ABSTRACT
More information395 Express Lanes Major Closure Advisory
395 Express Lanes Major Closure Advisory 3-Week Schedule Lane Closure And Construction Activities Week of February 26 th 1) Highway/Name & Route #: Braddock Road Bridge Lane/Shoulder Closure: Single Lane
More information2018 Investment in Infrastructure Expo February 27, 2018 Jason Jonas, P.E. Public Works Director
2018 Investment in Infrastructure Expo February 27, 2018 Jason Jonas, P.E. Public Works Director 1 Jefferson County, Missouri Road and Bridge Sales Tax: Jefferson County has a one-half cent sales tax that
More informationProjected Advertisement Date
2013 Planned s CY 2013 and CY 2014 Richmond District Schedule Preliminary Engineering Task Order Contracts SR 288/SR 145 Survey, 288 90349 Chesterfield Ramp and Signal Design 2/27/2013 $ 0.19 I-64 Over
More informationU.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County
U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE
More informationAstoria Boulevard ADA and Station Renewal Track Improvements. January 30, 2019
Astoria Boulevard ADA and Station Renewal Track Improvements January 30, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two
More informationGeorgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour
www.peachpass.com NOVEMBER 2013 Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour In This Issue GA 400 Tolls End on November 22 Lanes Closures for GA 400/I-85
More informationVasona Light Rail Signal Design Challenges. Hugh D. MacGillivray, Hatch Mott MacDonald Dennis Mellon, Santa Clara County Transportation Authority
Vasona Light Rail Signal Design Challenges Hugh D. MacGillivray, Hatch Mott MacDonald Dennis Mellon, Santa Clara County Transportation Authority Abstract The Vasona line is the most recent extension of
More information25 th Avenue Grade Separation. Community Meeting November 13, 2018
25 th Avenue Grade Separation Community Meeting November 13, 2018 Agenda I. Project Need II. Project Benefits III. Project Description IV. Funding V. Schedule VI. Construction VII. Next Steps 2 Project
More informationEast Link Project Update. Maintenance of Traffic During Construction. April 21, 2015
East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities
More informationHydraulic Report. Trail 5 Snowmobile Trail Over Mulligan Creek. Prepared By: COLEMAN ENGINEERING COMPANY Karisa V. Falls, P.E.
Prepared for: Prepared by: Marquette County Road Commission Coleman Engineering Company Marquette, Michigan Iron Mountain, MI December 2011 Hydraulic Report Trail 5 Snowmobile Trail Over Mulligan Creek
More informationPort of Long Beach 2012 Capital Program Update. G.J. Cardamone, PE, FCMAA Director of Construction Management
Port of Long Beach 2012 Capital Program Update G.J. Cardamone, PE, FCMAA Director of Construction Management Who We Are 3,500 acres of land 4,600 acres of water 6 container terminals 66 Ship-to-Shore cranes
More information12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization
REPORT FOR ACTION 12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization Date: April 27, 2018 To: Toronto and East York Community Council From: Senior Strategic Director,
More informationPlanning & Development Group
Planning & Development Group LAX Airside Technical Committee Meeting January 9, 2018 Mark Vicelja, P.E. 1 Airside Element Projects LAX AIRSIDE ELEMENT PROJECTS CONSTRUCTION SCHEDULE (as of January 1, 2018)
More informationViaduct Demolition at Girard Interchange
i-95news summer/fall 2015 2015 Stay current with construction at the Cottman Avenue, Betsy Ross Bridge/Aramingo Avenue and Girard Avenue interchanges at. PennDOT is enhancing communications with its I-95
More informationCOATING AND STRUCTURAL CONCRETE COATING (ANTI-GRAFFITI) 1'-3" FINISHED GRADE 1'-3" 3" VENEER ALLOWANCE LEDGER W/ MECHANICAL ANCHOR BOLT
R "W" PAY LIMITS OF ITEM 601 PAY LIMITS OF ITEM 601 STRUCTURAL CONCRETE STRUCTURAL CONCRETE 1'3" PCBC END SEGMENT B C 1'3" COATING AND STRUCTURAL CONCRETE COATING (ANTIGRAFFITI) 1'3" CURB FINISHED GRADE
More informationLESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014
LESLIE BARNS & CONNECTION TRACK Leslieville BIA Meeting May 2, 2014 1 OVERVIEW Communications Queen/Leslie Intersection Closure Overview Next Steps - Coordination of TTC Track Upgrades (Queen streetcar
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov August 31, 18 No closures scheduled for Labor Day weekend. Traffic lane patterns
More informationRPO AMERICA PEER SYMPOSIUM: SHARING INNOVATIONS IN REGIONAL TRANSPORTATION PLANNING Presented by David Cole, Former Commissioner, Maine DOT
National Rural Transportation Conference August 24 26, 2011 Washington, DC RPO AMERICA PEER SYMPOSIUM: SHARING INNOVATIONS IN REGIONAL TRANSPORTATION PLANNING Presented by David Cole, Former Commissioner,
More informationLittle River Trail Feasibility Study
Final April, 2014 Prepared for the State Coastal Conservancy By the Natural Resources Services Division of Redwood Community Action Agency Table of Contents Executive Summary... 1 1. Project Purpose and
More informationTexas Department of Transportation Corpus Christi District. Corpus Christi Harbor Bridge
Texas Department of Transportation Corpus Christi District Corpus Christi Harbor Bridge Presented by Russel W. Lenz, P.E. Corpus Christi District Engineer For 2009 Texas Ports and Waterways Conference
More informationDamen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501
Damen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501 Bird s Eye View of Existing INTRODUCTION This project is part of the City s Building a New Chicago initiative in conjunction
More informationTHE BIG PICTURE. Week of March 11, City of Buda Accepting Applications For Boards and Commissions
City of Buda Accepting Applications For Boards and Commissions The deadline is approaching to submit applications for the City of Buda's various boards and commissions. Deadline to submit a completed application
More informationLong water shutdown scheduled for Tuesday, September 18
Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility
More informationLESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation
LESLIE BARNS & CONNECTION TRACK Project Update Construction and Traffic Management Consultation PRESENTATION SUMMARY Part 1 Brief Project Update (New Streetcars & Streetscape Improvements) Part 2 Construction
More informationClaremont Project Background and Update Community Meeting September 11, 2017
Claremont Project Background and Update Community Meeting September 11, 2017 Topics Project Background Claremont Segment Information Project Timeline Upcoming Discussion Items Upcoming Meetings Questions
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release.
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov January 18, 2017 Mesa Continuous for 6 weeks The following closures started
More informationRecommendation: THAT the Council of the Township of Centre Wellington award the following two tenders:
Report to Council To: Mayor Linton and Members of Council Prepared By: Wes Snarr, Managing Director of Corporate Services Report: COR-45 Date: 12 Jul RE: Recomendation for Award of Request for Tenders
More informationHazard Identification Questionnaire
Hazard Identification Questionnaire OVERVIEW This questionnaire is designed to help identify potential risks and help identify areas of risk exposure. It is not an exhaustive list. This questionnaire is
More informationATTACHMENT C CITY OF FEDERAL WAY 2018 ASPHALT OVERLAY PROJECT BID SCHEDULE
ATTACHMENT C CITY OF FEDERAL WAY ASPHALT OVERLAY PROJECT SCHEDULE NOTE: Unit Prices for all items, all extensions, and the total amount of the bid must be shown. Show unit prices in legible figures. Where
More informationTRAFFIC COMMISSION, VILLAGE OF LINCOLNWOOD 6900 N. Lincoln Avenue, Lincolnwood, IL 60712
TRAFFIC COMMISSION, VILLAGE OF LINCOLNWOOD 6900 N. Lincoln Avenue, Lincolnwood, IL 60712 Meeting Agenda Thursday, May 25, 2017 7:00 p.m. Village Hall Council Chambers 6900 N. Lincoln Ave. Lincolnwood,
More informationMetrolinx Projects: Temporary Delegation for Long- Term Road Closures
PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation
More informationSECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY
WEEK ENDING FEBRUARY 1, 2019 SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY Contractor: Independence Excavating Inc. 1. Work Shift Day shift (M-F), with Saturday as a makeup day. 2. Traffic The new
More informationMount Pleasant (42, 43) and Connecticut Avenue (L1, L2) Lines Service Evaluation Study Open House Welcome! wmata.com/bus
Mount Pleasant (42, 43) and Connecticut Avenue (L1, L2) Lines Service Evaluation Study Open House Welcome! Study Overview and Timeline Phase 1: Collect and Analyze Data Project Kickoff, September 2017
More informationAddendum - Airport Development Alternatives (Chapter 6)
Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary
More informationPort MacKenzie Rail Extension
Port MacKenzie Rail Extension Project The Matanuska-Susitna Borough (MSB) and the Alaska Railroad Corporation (ARRC) jointly propose construction and operation of a new rail line to connect the Borough
More informationTWO BALLSTON PLAZA AVAILABLE SPACE AMENITIES. Leasing Information: 1110 N. Glebe Road, Arlington, VA 22201
TWO BALLSTON PLAZA 1110, Arlington, VA 22201 www.brookfieldproperties.com AVAILABLE SPACE Partial 1st Floor Suite GR1-5,201 RSF Available 1/11; first floor exterior entrance, window-line overlooking fountain
More informationAUTHORIZATION TO CONDUCT ETOPS OPERATIONS
oi oauu-^.o CHAPTER 4 AUTHORIZATION TO CONDUCT ETOPS OPERATIONS 4.1. ETOPS Authorizations. As stated earlier in this chapter, the DAAO determines the final decision on whether the certificate holder has
More informationI-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour
More informationThe Covered Bridges of Preble County. Past, Present and Future By: R. Kyle Cross, P.E., P.S.
The Covered Bridges of Preble County Past, Present and Future By: R. Kyle Cross, P.E., P.S. The History of the 8 Covered Bridges There are 8 covered bridges in Preble County. Only 2 of them are moved for
More informationCHICAGO DEPARTMENT OF AVIATION. Current Construction Projects AND THE O HARE MODERNIZATION PROGRAM. May 2, 2014
CHICAGO DEPARTMENT OF AVIATION AND THE O HARE MODERNIZATION PROGRAM Current Construction Projects May 2, 2014 O HARE INTERNATIONAL AIRPORT CURRENT CONFIGURATION 2 PHASE 1 & COMPLETION PHASE 9L-27R Completed
More informationNorthaven Trail Phase 2 Initial Project Overview
Northaven Trail Phase 2 Initial Project Overview Partnership Project to extend existing Northaven Trail Improve Bike/Ped Connectivity On Dallas Trail Network Plan City and County Funding Oncor Texas Trails
More informationSquint s Ranch and Airport
Squint s Ranch and Airport Lake Arrowhead, CA Airport Project Summary The Lake Arrowhead Airport at The Lost Ranch is a valuable asset to the surrounding communities. Not only does it provide residents
More informationBUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019
BUILD CONSTRUCTION Update FEBRUARY 2019 In this issue: ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEATURED PROJECT: KENT AVENUE * Featured Project KENT AVENUE CP 2-3 CONSTRUCTION UPDATE February 2019 At
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation
More information22-23 Pavement Marking Items. (Pages 7 & 8 removed)
22-23 Pavement Marking Items (Pages 7 & 8 removed) SUMMARY OF TRAFFIC CONTROL DEVICES (FOR INFORMATION ONLY) All traffic control devices shall be placed in accordance with the applicable
More information14 YORK REGION TRANSIT (YRT/VIVA) SOUTHWEST DIVISION OPERATIONS AND MAINTENANCE CONTRACT EXTENSION
Clause No. 14 in Report No. 13 of the was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on September 11, 2014. 14 YORK REGION TRANSIT (YRT/VIVA) SOUTHWEST
More informationState Route 8 Corridor. Northern Summit County s Path to Success
State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity
More informationMadison Metro Transit System
Madison Metro Transit System 1101 East Washington Avenue Madison, Wisconsin, 53703 Administrative Office: 608 266 4904 Fax: 608 267 8778 TO: FROM: SUBJECT: Plan Commission Timothy Sobota, Transit Planner,
More informationSTATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION IN RE: IGUS BEARINGS, INC. : DOCKET NO. 4652 PETITION FOR A PRIVATE AT-GRADE CROSSING : REPORT AND ORDER On September 30, 2016,
More informationTrinity River Vision Update
Trinity River Vision Update Presented to the City Council by: Mark Rauscher, Program Manager Planning & Development Department / Program Management Office August 23, 2011 1 Purpose of the Briefing Overview
More informationToronto 2015 Pan Am/Parapan Am Games Temporary Traffic By-law Amendments for High Occupancy Vehicle Lanes (Supplementary Report)
STAFF REPORT ACTION REQUIRED Toronto 2015 Pan Am/Parapan Am Games Temporary Traffic By-law Amendments for High Occupancy Vehicle Lanes (Supplementary Report) Date: March 25, 2015 To: From: Wards: Reference
More information