LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation

Size: px
Start display at page:

Download "LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation"

Transcription

1 LESLIE BARNS & CONNECTION TRACK Project Update Construction and Traffic Management Consultation

2 PRESENTATION SUMMARY Part 1 Brief Project Update (New Streetcars & Streetscape Improvements) Part 2 Construction Objectives and Principles Construction Phasing Traffic & Communication Plans 2

3 STREETCAR LINE-UPS, WHAT LINE-UPS? 3

4 NEW STREETCARS! Meet Toronto s New Streetcars Key Features Accessible Low Floor Four Entrances 4

5 Leaving Hillcrest Yard South on Bathurst Street Heading South on Bathurst Street Back to Hillcrest Yard

6 NEW STREETCARS Mobility Device Locations 6

7 EXISTING STREETCAR FACILITIES Roncesvalles and Russell (Connaught) Carhouses are over 80 years old Cannot support the maintenance and full storage needs of the new streetcar fleet Will continue operating to store approximately half of the new streetcars 7

8 CONTEXT PLAN Tracks And Streetscaping 8

9 NEW STREETCARS NEW HOME Leslie Barns Looking north on Leslie from Commissioners St 9

10 STREETSCAPE IMPROVEMENT PLAN Key benefits of the Leslie Streetscape Improvement Plan include: New, wider sidewalks Decorative pavers New trees and greenery New street lighting and hydro poles Public Art (location to be determined) 10

11 NEW STREETCARS NEW GREEN HOME Built to Green Development Standards Green Roof Storm Water Management Bird-Friendly Windows Hundreds of Trees and Plantings Integrated with the Martin Goodman Trail Looking south from Lake Shore Blvd 11

12 PROJECT OVERVIEW Perimeter Landscape Plan Plant Palette Native Species 12

13 BROWN AND STOREY PERIMETER LANDSCAPE PLAN Looking north on east side of Leslie along Martin Goodman Trail 13

14 BROWN AND STOREY PERIMETER LANDSCAPE PLAN Metal mesh for vines & window panels for viewing into Leslie Barns 14

15 LESLIE STREETSCAPE IMPROVEMENT PLAN South Of Lake Shore Blvd East Looking south on west side of Leslie 15

16 LESLIE STREETSCAPE IMPROVEMENT PLAN Eastern Avenue Wider Sidewalks Before Looking north from Eastern Ave After 16

17 LESLIE STREETSCAPE IMPROVEMENT PLAN Before Looking south from Memory Lane After 17

18 STREETSCAPE ENHANCEMENTS QUEEN STREET View from Curzon St looking south to Queen St 18

19 STREETSCAPE ENHANCEMENTS QUEEN STREET View from Queen St looking north to Hastings Ave 19

20 LESLIE STREET CONNECTION TRACK Construction & Traffic Management

21 OVERVIEW Scope & Schedule Objectives for Community Construction Staging and Phasing Plan Traffic Monitoring and Management Communications 21

22 LESLIE STREET CONSTRUCTION SCOPE The Project involves multiple utility improvements, TTC track work, roadway, and sidewalk/streetscape construction Municipal Utility Upgrades New storm sewer Comissioners to Queen New sanitary sewer New watermains Utilities Bell, Rogers, Cogeco, Telus, Enbridge, Hydro 22

23 LESLIE STREET CONSTRUCTION SCOPE Above Ground Works New road, track and sidewalks New hydro poles and street lighting New streetscape and landscape improvements Leslie Street and Queen Street (Corners from Hastings to Rushbrooke) 23

24 LESLIE STREET CONSTRUCTION SCHEDULE Construction occurs in 2013 and 2014 Most heavy construction will occur late May 2013 to December 2014 (exact timing TBC) Coordinated Construction one major contract Most construction activities north of Lake Shore will occur over approximately 14 months Starts south of Lake Shore Boulevard late May, 2013 Queen St intersection tentatively scheduled (March-May 2014) and Leslie from Eastern to Queen (April-August 2014) 24

25 OBJECTIVES FOR COMMUNITY 1. Ensure Safety for Pedestrians, Cyclists, and Drivers 2. Maintain Access to all residences and businesses 3. Keep traffic moving on major E-W streets (reduce infiltration) 4. Fast-track construction to minimize duration 5. Pro-Active Communication (local community, TTC riders, cyclists, motorists, trucks) 6. Implement Live Traffic Monitoring to identify hot spots and adjust accordingly 25

26 IMPLEMENTATION 1. Ensure Safety for pedestrians, cyclists, drivers - At least one sidewalk on one side of the road always maintained, appropriate signage & safe crossings - Bike trails maintained in existing or alternate location - Signage program 2. Maintain Access - Maintain access to all businesses and residences on Leslie throughout construction - Temporary accesses from Lake Shore Blvd to Loblaws/BK and Tim-Wendy s/price Chopper Plazas 26

27 IMPLEMENTATION 3. Keep Major Roads Moving (reduce infiltration) - Maintain 5 of 6 E-W lanes in each direction (Queen, Eastern, Lake Shore) through majority of project - Remove Lake Shore middle median temporarily to provide lanes - Maintain minimum of 4 E-W lanes during Queen St intersection work in Avoid constructing two major intersections at same time 27

28 IMPLEMENTATION 4. Fast Track Construction - One major contract to coordinate multiple utilities under one umbrella - Segmented closures to complete full sections in one phase (except for short weekend track installation period) - Examine potential for extended work hours in some locations to speed project 28

29 IMPLEMENTATION 5. Pro-Active Communication Community Liaison assigned full time to project - Provide frequent updates ( , web, print, meetings, office) - lesliebarns@ttc.ca - Web: - Telephone: Future Community 1258 Queen St East - Construction Liaison Group (monitor construction, help reduce impacts) 29

30 IMPLEMENTATION 5. Pro-Active Communication (Continued) TTC Customers & all travelers - Notices for transit and traffic re-routings - Signage for cyclists and pedestrians on MGT Trail - Community notices by , posters at stops, at stations & on vehicles in advance - TTC Customer Service see: My TTC E-Services - Media outreach - Changeable Message Signage Program 30

31 IMPLEMENTATION 6. Implement Live Traffic Monitoring Program Cameras (Queen+Eastern+Lake Shore+Commisioners+Carlaw) Traffic counts before construction to establish base case Identify problem spots and adjust signal timings On-site investigations Quick response protocol with City s traffic management centre and Transportation Staff 31

32 PRELIMINARY SIGNAGE PLANNING Legend STATIC SIGNS Changeable Message Signs 32

33 SAMPLE STATIC SIGNAGE MARTIN GOODMAN TRAIL Input to ensure effective signage design and placement for all trail users Safety for Pedestrians and Cyclists is #1 priority 33

34 KEY INTERSECTIONS Commissioners - Leslie Intersection Short term partial closure of northside of intersection for 6-12 days Alternatively could be completed in 6 weekends (Saturday and Sunday) Lake Shore Lanes at Leslie Intersection At least 2 lanes both ways on LS + left turn lane at all times LS returned to 3 lanes + left turn lane before Queen intersection closure 34

35 KEY INTERSECTIONS Eastern Leslie Intersection - Construct half at a time - No full East-West closures (except track work over a long weekend) Queen Leslie Intersection (2014) - With work hours extended, complete in approx. 6 weeks - Transit service routing changes (2014) (details TBC well in advance) 35

36 LESLIE STREET PROPOSED PHASING Lake Shore to Commissioners Preliminary Schedule: late May 2013 Aug 2014 Canadian Tire Plaza 36

37 LESLIE STREET PROPOSED PHASING CLOSURE TO SPEED CONSTRUCTION From Lake Shore Boulevard north curb to middle of Plaza Intersection Preliminary Schedule: August 2013 Nov 2013 (Approx. 12 weeks) 37

38 LESLIE STREET PROPOSED PHASING From Eastern south curb-line to middle of Plaza intersection Preliminary Schedule: Nov 2013 Mar 2014 (Approx. 17 weeks) 38

39 LESLIE STREET PROPOSED PHASING North half of Eastern intersection Preliminary Schedule: Mar 2014 (Approx. 2 weeks) 39

40 LESLIE STREET PROPOSED PHASING South half of Eastern intersection Preliminary Schedule: Mar 2014 Apr 2014 (Approx. 2-3 weeks) 40

41 LESLIE STREET PROPOSED PHASING From Eastern north curb line to south of Queen Preliminary Schedule: Apr Aug 2014 (Approx. 20 weeks) 41

42 LESLIE STREET PROPOSED PHASING Queen intersection Preliminary Schedule: Mar 2014 May 2014 (Approx. 6 weeks w/ extended work hours) Queen WB right turns permitted onto Leslie northbound N 42

43 DISRUPTION MANAGEMENT Maintain Plaza Access (Loblaws/BK and Tim Hortons/Price Chopper) Provide new temporary accesses off Lake Shore (right-in & right-out) Reduces overload of traffic onto Eastern Avenue and Coxwell Provide access during closures of Leslie north of Lake Shore 43

44 TEMPORARY ACCESSES 44

45 TEMPORARY ACCESSES Loblaws Plaza New bike routing New bike routing Stop signs, warning signs, storage and deceleration space, temporary right turn lane proposed 45

46 TRAIL LOOKING WEST 46

47 TRAIL LOOKING EAST 47

48 LAKE SHORE CENTRE MEDIAN REMOVAL Opportunity Plant native trees in clean soil to replace non-native trees removed during construction Keep traffic moving on Lake Shore Boulevard Requirements Ensure safe soil removal, as completed at Leslie Barns site 48

49 LAKE SHORE MEDIAN LOOKING WEST 49

50 LAKE SHORE MEDIAN LOOKING EAST 50

51 ENSURING SAFE CROSSINGS Coordinating with City of Toronto Cycling to ensure temporary accesses and crossing will be safe for all trail users, Need your suggestions 51

52 PARKING LESLIE LAKE SHORE TO QUEEN Marigold Condominium Access maintained to underground parking 8 Spots 4 ON STREET PARKING SPOTS 7 ON STREET PARKING SPOTS 52

53 PARKING LESLIE SOUTH OF COMMISSIONERS Spaces adjacent to Allotment Gardens Plan to maintain all spots Spaces on west side 80m south of Commissioners across from KJ Beamish Construction impacted for approximatey 3 months 53

54 TRANSIT ROUTING TTC will keep customers moving and informed throughout construction. The following routes will have temporary changes during phases of construction: 501 Queen, 502 Downtowner, 503 Kingston Rd streetcars (Approximate 6 week impact in 2014) 31B Greenwood Bus from Greenwood Station 83 Jones Bus from Donlands Station 143 Downtown Beach Express Bus (crossing Eastern) Details will be confirmed for May,

55 Communication Preferences 379 Surveys - January, 2013

56 COMMUNITY OUTREACH Commitment for frequent two-way communication with the local community Plans include: Regular and ongoing communication through future Community Office at 1258 Queen Street (at Hastings) Dedicated community liaison staff Project website Notices/Newsletters, project updates for local community Meetings with local residents and businesses Establishment of a Construction Liaison Group (CLG), please sign-up tonight if interested Public Meetings Comprehensive Signage 56

57 NEXT STEPS Construction, Traffic and Disruption Management Queen Businesses Meeting, Tuesday April 9 th Portlands Businesses & Businesses from Eastern Avenue south April 12, 2013 Community Follow-up (early May) Updated plan, confirm construction schedule, construction phasing, safety measures, & overall traffic/disruption management plan 57

58 THANK YOU, PLEASE GET IN TOUCH Leslie Barns Community Liaison Team Telephone: Web: 58

59 END

LESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #6 January 30, 2014

LESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #6 January 30, 2014 LESLIE BARNS & CONNECTION TRACK Construction Liaison Group Meeting #6 January 30, 2014 Construction Liaison Group Jan 30 2014 1 OVERVIEW HAPPY BELATED NEW YEAR Works to Date Underground Utilities Bell

More information

LESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014

LESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014 LESLIE BARNS & CONNECTION TRACK Leslieville BIA Meeting May 2, 2014 1 OVERVIEW Communications Queen/Leslie Intersection Closure Overview Next Steps - Coordination of TTC Track Upgrades (Queen streetcar

More information

WORKING WITH BIAS ON TTC PROJECTS

WORKING WITH BIAS ON TTC PROJECTS WORKING WITH BIAS ON TTC PROJECTS David Nagler Manager Community Relations, TTC November 17, 2015 TABIA-CITY meeting Nov, 17, 2015 November 17, 2015 1 OVERVIEW 1. Working with BIAs on major construction

More information

Appendix B Connecting Track Options Evaluation Criteria

Appendix B Connecting Track Options Evaluation Criteria Appendix B Connecting Track Options Evaluation Criteria 608979-853_ra_July5-0_App Title Pages.Docx TTC ASHBRIDGES BAY MAINTENANCE AND STORAGE FACILITY CONNECTING TRACK ROUTE ALTERNATIVE - EVAULATION MATRIX.0

More information

Design Meeting Presentation

Design Meeting Presentation Contract No. 17ECS-TI-05SP April November 2017 Design Meeting Presentation November 2015 Agenda Items: Introduction (5 min) Overview (10 min) Scope of work (60 min): Schedule and Traffic Staging / Closures

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: SUBJECT: Resubmitted December 19, 2012 November 21, 2012 MODERNIZING THE TTC A NEW APPROACH TO COMMUNICATIONS, COMMUNITY

More information

Construction Staging Area Blue Jays Way (357 King Street West)

Construction Staging Area Blue Jays Way (357 King Street West) REPORT FOR ACTION Construction Staging Area Blue Jays Way (357 King Street West) Date: June 8, 2018. To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto

More information

Construction Staging Adelaide Street West

Construction Staging Adelaide Street West REPORT FOR ACTION Construction Staging Adelaide Street West Date: October 6, 2016 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

Parking Amendments - Bay Street, between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal)

Parking Amendments - Bay Street, between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal) REPORT FOR ACTION between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal) Date: October 26, 2017 To: Toronto and East York Community Council From: Acting Director,

More information

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure

More information

KING STREET TRANSIT PILOT

KING STREET TRANSIT PILOT KING STREET TRANSIT PILOT Update toronto.ca/kingstreetpilot #kingstreetpilot HIGHLIGHTS TRANSIT RIDERSHIP TRANSIT CAPACITY To respond to this growth in ridership, the TTC has increased the capacity of

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

Main Street Station Upgrades

Main Street Station Upgrades Main Street Station Upgrades Public Meeting Hope United Church 1 Main Street Station Upgrades Bus diversions Planned improvements Construction staging Pedestrian flows 2 Main Street Station Aerial Bar

More information

KING STREET TRANSIT PILOT

KING STREET TRANSIT PILOT KING STREET TRANSIT PILOT Update toronto.ca/kingstreetpilot #kingstreetpilot UPDATE Average streetcar travel times in continued to show similar trends as first observed in November. The most significant

More information

KING STREET PILOT STUDY PUBLIC MEETING

KING STREET PILOT STUDY PUBLIC MEETING KING STREET PILOT STUDY PUBLIC MEETING 2017.02.13 PUBLIC WORK with GEHL STUDIO / NEW YORK SWERHUN ASSOCIATES SAM SCHWARTZ CONSULTING LLC STARTING POINTS 17 1 - TRANSIT FIRST! Transit service is beyond

More information

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation

More information

Construction Staging Area 19 Western Battery Road

Construction Staging Area 19 Western Battery Road REPORT FOR ACTION Construction Staging Area 19 Western Battery Road Date: December 6, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York

More information

Macleod Trail Corridor Study. Welcome. Macleod Trail Corridor Study Open House. Presentation of Proposed Design Concepts

Macleod Trail Corridor Study. Welcome. Macleod Trail Corridor Study Open House. Presentation of Proposed Design Concepts Macleod Trail Corridor Study Welcome Macleod Trail Corridor Study Open House Presentation of Proposed Design Concepts Study Purpose Develop a corridor plan for Macleod Trail that aligns with The City s:

More information

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required. REPORT FOR ACTION Construction Staging Area - 81 Bay Street Date: December 11, 2017 To: Toronto and East York, Community Council From: Acting Director, Transportation Services Toronto and East York District

More information

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015 East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities

More information

Pedestrian Safety Review Spadina Avenue

Pedestrian Safety Review Spadina Avenue STAFF REPORT ACTION REQUIRED Pedestrian Safety Review Spadina Avenue Date: October 13, 2015 To: Toronto and East York Community Council From: Director, Transportation Services, Toronto and East York District

More information

Wellesley Station Second Exit and Automatic Entrance Public Open House. Tuesday, September 23, 2014 Central YMCA 20 Grosvenor Street

Wellesley Station Second Exit and Automatic Entrance Public Open House. Tuesday, September 23, 2014 Central YMCA 20 Grosvenor Street Wellesley Station Second Exit and Automatic Entrance Public Open House Tuesday, September 23, 2014 Central YMCA 20 Grosvenor Street 1 What are Second Exits? Second exits serve three functions: As a primary

More information

Long water shutdown scheduled for Tuesday, September 18

Long water shutdown scheduled for Tuesday, September 18 Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility

More information

Second Street Improvements Project Project Update Archive

Second Street Improvements Project Project Update Archive Second Street Improvements Project Project Update Archive 12/03/18: In observance of the Holiday Moratorium, crews have paused a majority of construction activity on 2nd Street until January 2, 2019. A

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

AGENDA ITEM I-6 Public Works

AGENDA ITEM I-6 Public Works AGENDA ITEM I-6 Public Works STAFF REPORT City Council Meeting Date: 8/6/2018 Staff Report Number: 18-150-CC Informational Item: Update on the Willow Road and highway 101 interchange construction, upcoming

More information

St. Clair West Station Easier Access Project Community Update Open House

St. Clair West Station Easier Access Project Community Update Open House St. Clair West Station Easier Access Project Community Update Open House 1 Easier Access Program Wide Committed to making all 69 stations accessible by 2025 31 stations completed - almost halfway there

More information

This report recommends two new TTC transit services in southwest Toronto.

This report recommends two new TTC transit services in southwest Toronto. Report for Action New TTC Services - Southwest Toronto Date: March 20, 2018 To: TTC Board From: Chief Customer Officer Summary This report recommends two new TTC transit services in southwest Toronto.

More information

ETOBICOKE CREEK NORTH TRAIL PROJECT. May 18, 2017 at Michael Power High School 105 Eringate Drive, Etobicoke ON M9C 3Z7

ETOBICOKE CREEK NORTH TRAIL PROJECT. May 18, 2017 at Michael Power High School 105 Eringate Drive, Etobicoke ON M9C 3Z7 ETOBICOKE CREEK NORTH TRAIL PROJECT May 18, 2017 at Michael Power High School 105 Eringate Drive, Etobicoke ON M9C 3Z7 1 Purpose of Open House The purpose of today s open house is to present the design

More information

Monday, September 18, 2017 Sunday, October 1, 2017

Monday, September 18, 2017 Sunday, October 1, 2017 Monday, September 18, 2017 Sunday, October 1, 2017 CONSTRUCTION UPDATE* Hurricane Irma cleanup is complete and some landscaping repairs are underway. The project was secure and no major damages were encountered.

More information

SAN RAFAEL City Council January 20, 2015

SAN RAFAEL City Council January 20, 2015 SONOMA MARIN AREA RAIL TRANSIT SMART CENTRAL SAN RAFAEL STATUS UPDATE SAN RAFAEL City Council January 20, 2015 CENTRAL SAN RAFAEL SMART SOUTH OF PUERTO SUELLO TUNNEL 1. Active Construction 2. Construction

More information

List of Our Ongoing Noise and Vibration Monitoring Projects

List of Our Ongoing Noise and Vibration Monitoring Projects List of Our Ongoing Noise and Vibration Monitoring Projects Project 1: Name of Project: Geotechnical Instrumentation and Monitoring Plan- Segment 1- Keelesdale Station Client: Metrolinx-Eglinton Crosstown

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

Old New Old New Old New M-F Saturday Sunday

Old New Old New Old New M-F Saturday Sunday 2 Bloor-Danforth M-F Midday / Weekend Afternoon 3'22" 3'20" 2 4'31" 4'30" 2 4'52" 4'52" 2 Additional running time for reliability Early Evening 3'42" 3'42" 2 192 Airport Rocket Seasonal changes and Ten

More information

Construction Staging Area 197 Redpath Avenue

Construction Staging Area 197 Redpath Avenue REPORT FOR ACTION Construction Staging Area 197 Redpath Avenue Date: January 31, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)

More information

M-F. Old New Old New Old New Old New Old New Old New Miscellaneous Changes

M-F. Old New Old New Old New Old New Old New Old New Miscellaneous Changes , September 3, 2017 Miscellaneous Changes Wheel Trans 6 Bay and 63 Ossington 22/322 Coxwell Wheel Trans will now serve bus bay 3 at Coxwell Station, and bus bay 2 at Woodbine Station. Scheduled travel

More information

WHO IS METROLINX?

WHO IS METROLINX? CROSSTOWN LRT WHO IS METROLINX? Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate

More information

2015 Volunteer Orientation Package

2015 Volunteer Orientation Package 2015 Volunteer Orientation Package TRAVELLING TO CANADA BLOOMS Direct Energy Centre is readily accessible via the TTC and Go Transit. Exhibition The Direct Energy Centre at Exhibition Place is located

More information

25 th Avenue Grade Separation. September 13, 2017

25 th Avenue Grade Separation. September 13, 2017 25 th Avenue Grade Separation September 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25

More information

Village of Lombard, Illinois Capital Improvement Plan FUNDING SOURCE SUMMARY

Village of Lombard, Illinois Capital Improvement Plan FUNDING SOURCE SUMMARY Village of Lombard, Illinois Capital Improvement Plan FY 15 FY 24 thru FUNDING SOURCE SUMMARY Source FY 15 FY 16 FY 17 FY 18 FY 19 FY 20 FY 21 FY 22 FY 23 FY 24 Construction Fund 6,318,700 2,354,800 2,430,800

More information

Bridge Collapse. Minneapolis Public Works Department. Presented by Steven Kotke, P.E. - Director of Public Works

Bridge Collapse. Minneapolis Public Works Department. Presented by Steven Kotke, P.E. - Director of Public Works Bridge Collapse Minneapolis Public Works Department Presented by Steven Kotke, P.E. - Director of Public Works 1 St. Anthony Falls I-35W Bridge History Construction started in 1964 Opened to traffic in

More information

Construction Staging Area 700 Bay Street - Elizabeth Street and Walton Street

Construction Staging Area 700 Bay Street - Elizabeth Street and Walton Street REPORT FOR ACTION Construction Staging Area 700 Bay Street - Elizabeth Street and Walton Street Date: March 7, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services,

More information

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT December 2018 Project Summary Boulder County, Colorado, in partnership with the City of Boulder, is evaluating options for multi-use

More information

N. Central St. & W. Jackson Ave. Streetscape Projects

N. Central St. & W. Jackson Ave. Streetscape Projects N. Central St. & W. Jackson Ave. Streetscape Projects October 13, 2016 Meeting Overview North Central Street City of Knoxville KUB History & Vision Plan Timing Project Area Overview Schedule Communications

More information

Waterfront Concept Plan: Community Survey Summary

Waterfront Concept Plan: Community Survey Summary Waterfront Concept Plan: Community Survey Summary Published April 20, 2016 #1100085 Introduction The survey was one component of the public consultation process endorsed by Council in October, 2015. This

More information

York Region Rapid Transit Corporation. City of Vaughan Committee of the Whole June 1, 2016

York Region Rapid Transit Corporation. City of Vaughan Committee of the Whole June 1, 2016 York Region Rapid Transit Corporation City of Vaughan Committee of the Whole June 1, 2016 0 Agenda Future rapid transit projects > Yonge North Subway Extension [YNSE] > Regional Express Rail [RER] Current

More information

STAFF REPORT FOR ACTION

STAFF REPORT FOR ACTION Insert TTC logo here STAFF REPORT FOR ACTION Hillcrest Complex Property Study Date: November 30, 2016 To: From: TTC Board Chief Executive Officer Summary This report outlines a plan for staff to proceed

More information

Woodbine Station Easier Access Project Public Open House January 27, :30 pm 8:30 pm Consultation Summary Report

Woodbine Station Easier Access Project Public Open House January 27, :30 pm 8:30 pm Consultation Summary Report Woodbine Station Easier Access Project Public Open House January 27, 2014 6:30 pm 8:30 pm Consultation Summary Report Danforth Mennonite Church 2174 Danforth Ave Prepared by Lito Romano February 18, 2014

More information

Hospital Link Project Project Update September 2015

Hospital Link Project Project Update September 2015 Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service

More information

Project Start Date: Project Completion Date: July 1, Contractor: Mattson Construction Contact Information: Nate Lillemon

Project Start Date: Project Completion Date: July 1, Contractor: Mattson Construction Contact Information: Nate Lillemon Date: 06-24-16 To: Derek Hackett, Public Information Officer From: Sunil Jeboo, Traffic Engineer Re: Road Closure for the Week of 06-27-16 (3236.1) 6 th Pump Station Western Ave. and 6 th SW Western Ave.

More information

Union Station Queens Quay Transit Link Study

Union Station Queens Quay Transit Link Study Welcome Union Station in 1899. Image: City of Toronto Archives Union Station today. Image: Camil Rosiak Activity along Queens Quay. Image: Waterfront Toronto For more information or to comment, visit toronto.ca/waterfronttransit

More information

G Street Undercrossing. City Council Meeting Date: November 3, 2008

G Street Undercrossing. City Council Meeting Date: November 3, 2008 G Street Undercrossing City Council Meeting Date: November 3, 2008 Introduction G Street undercrossing Long-term goal of the City In General Plan since 1997 In City s Public Facilities Financing Plan

More information

March 4, Mr. H. Dale Hemmerdinger Chairman Metropolitan Transportation Authority 347 Madison Avenue New York, NY Re: Report 2007-F-31

March 4, Mr. H. Dale Hemmerdinger Chairman Metropolitan Transportation Authority 347 Madison Avenue New York, NY Re: Report 2007-F-31 THOMAS P. DiNAPOLI STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK 12236 STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER March 4, 2008 Mr. H. Dale Hemmerdinger Chairman Metropolitan Transportation

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.4 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving various parking and traffic modifications associated

More information

Section II. Planning & Public Process Planning for the Baker/Carver Regional Trail began in 2010 as a City of Minnetrista initiative.

Section II. Planning & Public Process Planning for the Baker/Carver Regional Trail began in 2010 as a City of Minnetrista initiative. Section II Planning & Public Process Planning for the began in 2010 as a City of initiative. city staff began discussions with the Park District on the possibility of a north/south regional trail connection

More information

Northeast Corridor Transportation Update

Northeast Corridor Transportation Update Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer

More information

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization REPORT FOR ACTION 12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization Date: April 27, 2018 To: Toronto and East York Community Council From: Senior Strategic Director,

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 6 02.13.19.. Agenda Welcome and Introductions Community Conversations City Council Meeting Debrief Review Citywide Tunnel Video (North Portal Only) Churchill Pedestrian

More information

Capital Projects 2015 Ward 21

Capital Projects 2015 Ward 21 Capital Projects 2015 Ward 21 BIA Projects Forest Hill North Gateway: The City of Toronto Economic Development and the Forest Hill Village BIA are collaborating to create a dynamic northern gateway to

More information

City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting

City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting Wednesday, May 31, 2017 6:30 to 8 P.M. Frank Allis Elementary School 4201 Buckeye Road Madison,

More information

2018 Airport Master Plan. Public Meeting and Open House February 7, 2018

2018 Airport Master Plan. Public Meeting and Open House February 7, 2018 2018 Airport Master Plan Public Meeting and Open House February 7, 2018 Overview PortsToronto and Billy Bishop Airport Background on Airport Master Plan process, objectives and key components Managed Growth

More information

BATHURST QUAY NEIGHBOURHOOD PLAN

BATHURST QUAY NEIGHBOURHOOD PLAN BATHURST QUAY NEIGHBOURHOOD PLAN December 10, 2014 Urban Strategies Inc. BA Group PLANT Architect Vermeulens Public Launch Agenda Our Team What is a Neighbourhood Plan? The Plan Process Guiding Themes

More information

Spadina Avenue which would include two new underground stations located at Yonge Street and at University Avenue.

Spadina Avenue which would include two new underground stations located at Yonge Street and at University Avenue. TORONTO TRANSIT COMMISSION REPORT No S7 MEETING DATE June 4, 1968 FROM: General Manager Subway Construction Date June 3, 1968 Subject: QUEEN STREET SUBWAY FOR STREETCAR OPERATION The Commission, at its

More information

Cell: (408) Release MA June 25, 2012

Cell: (408) Release MA June 25, 2012 VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET Report No. 3 of the Regional Council Meeting of March 28, 2013 1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET The recommends: 1. Receipt

More information

CREATING CONNECTIONS IN THE TOWN OF GRIMSBY PUBLIC MEETING NOVEMBER 21, 2017

CREATING CONNECTIONS IN THE TOWN OF GRIMSBY PUBLIC MEETING NOVEMBER 21, 2017 CREATING CONNECTIONS IN THE TOWN OF GRIMSBY PUBLIC MEETING NOVEMBER 21, 2017 CONGESTION COSTS OUR ECONOMY The average commute in Ontario is already over 45 minutes, and that figure jumps to more than an

More information

Public Information Center August 12, 2010

Public Information Center August 12, 2010 Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General

More information

COLLEGE STREET STUDY Community Consultation Meeting. December 2015

COLLEGE STREET STUDY Community Consultation Meeting. December 2015 COLLEGE STREET STUDY Community Consultation Meeting December 2015 2 Agenda 6:30 pm Introductions, Agenda Review and Welcome 6:40 pm Presentation Planning Recommendations 7:30 pm Questions and Discussion

More information

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee. PW Royal Bank of Canada Canadian Open

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee. PW Royal Bank of Canada Canadian Open Approved - Planning and Public Works - Jun 15, 2016 Adopted - Regional Council - Jun 22, 2016 The Regional Municipality of Halton Report To: From: Chair and Members of the Planning and Public Works Committee

More information

Figure 1: Little Dry Creek Trail Crossing

Figure 1: Little Dry Creek Trail Crossing Figure 1: Little Dry Creek Trail Crossing Figure 2: Little Dry Creek Trail Crossing Northwest Rail Environmental Evaluation Temporary Trail Detour Concurrence Form Adams County, Little Dry Creek Trail

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 1 Project Overview Mainline Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 1, 2011 SUBJECT: PROCUREMENT AUTHORIZATION AMENDMENT CONTRACT AMENDMENT NO. 8 ACTION ITEM RECOMMENDATION It is recommended

More information

CREATING CONNECTIONS IN THE CITY OF NIAGARA FALLS PUBLIC MEETING DECEMBER 6, 2017

CREATING CONNECTIONS IN THE CITY OF NIAGARA FALLS PUBLIC MEETING DECEMBER 6, 2017 CREATING CONNECTIONS IN THE CITY OF NIAGARA FALLS PUBLIC MEETING DECEMBER 6, 2017 CONGESTION COSTS OUR ECONOMY The average commute in Ontario is already over 45 minutes, and that figure jumps to more than

More information

SR 934 Project Development And Environment (PD&E) Study

SR 934 Project Development And Environment (PD&E) Study SR 934 Project Development And Environment (PD&E) Study Project Advisory Group Meeting March 1, 2018 State Road 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive PD&E STUDY SR 934/NE/NW

More information

Committee. Presentation Outline

Committee. Presentation Outline CW-33-15 11/9/2015 Community and Corporate Services Committee November 10, 2015 1 Presentation Outline Background Vision and Objectives Study Process and Timeline Public and Stakeholder Engagement Organization

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

4 VIVA PHASE 2 YONGE STREET - Y2, AND HIGHWAY 7 - H3 CORRIDORS PRELIMINARY ENGINEERING UPDATE

4 VIVA PHASE 2 YONGE STREET - Y2, AND HIGHWAY 7 - H3 CORRIDORS PRELIMINARY ENGINEERING UPDATE 4 VIVA PHASE 2 YONGE STREET - Y2, AND HIGHWAY 7 - H3 CORRIDORS PRELIMINARY ENGINEERING UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the following: 1. The presentation

More information

EP8.2 Presentation Exhibition GO Station Improvements

EP8.2 Presentation Exhibition GO Station Improvements EP8.2 Presentation Exhibition GO Station Improvements JANUARY 30, 2018 WORKING TOGETHER Metrolinx is working collaboratively with the City of Toronto, Exhibition Place, and the TTC to co-ordinate efforts

More information

Pattullo Bridge Replacement Project

Pattullo Bridge Replacement Project Pattullo Bridge Overview This document will: Explain the challenges facing the Pattullo Bridge today Share how we propose moving forward translink.ca PAGE 1 History By Order of the Lieutenant Governor

More information

Improving Transit Service to Major Music Festivals

Improving Transit Service to Major Music Festivals For Action Improving Transit Service to Major Music Festivals Date: May 8, 2018 To: TTC Board From: Chief Operating Officer Summary The purpose of this report is to respond to the Board s request to report

More information

Work in 2015 and Annual Mobility- Management Plan

Work in 2015 and Annual Mobility- Management Plan Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector

More information

Presentation Overview

Presentation Overview DON NARROWS Historical and Existing Conditions March 29, 2008 Presentation Overview 1. Project Location and Background 2. Historical Context How did the Don Narrows Come to Be? 3. The Today 4. Next Steps

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting Culver City Senior Center Wednesday, July 16, 2008 Description 8.6 mile corridor from downtown to Culver City in West Los Angeles 1.3

More information

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route

More information

Glasgow Street Traffic Review

Glasgow Street Traffic Review Glasgow Street Traffic Review Recommendation That the Standing Policy Committee on Transportation recommend to City Council: 1. That the Administration proceed with removing the pinch points installed

More information

The Light Rail System Safety & Grade Crossing Equipment

The Light Rail System Safety & Grade Crossing Equipment The Light Rail System Safety & Grade Crossing Equipment A Peer Review Provided by the American Public Transportation Association (APTA) Presented by: Mark Benedict, Director, Light Rail Operations and

More information

IL 390 Station. Wood Dale Open House Summary 5/18/17

IL 390 Station. Wood Dale Open House Summary 5/18/17 Wood Dale Open House Summary 5/18/17 The first public open house for the Wood Dale Comprehensive Plan took place on May 18 th, 2017. The program was conducted as a fun community event and there were 216

More information

Pan Am Games: July 10 26, 2015 Parapan Am Games: August 7 15, 2015

Pan Am Games: July 10 26, 2015 Parapan Am Games: August 7 15, 2015 TORONTO2015 PAN AM/PARAPAN AM GAMES Pan Am Games: July 10 26, 2015 Parapan Am Games: August 7 15, 2015 TEMPORARY HIGH OCCUPANCY VEHICLE HIGHWAY LANES There will be approximately 235 km of temporary HOV

More information

Carlisle Connectivity Projects Communication Plan and Project Status

Carlisle Connectivity Projects Communication Plan and Project Status Carlisle Connectivity Projects Communication Plan and Project Status Overview Communication Plan Communication Plan Communication Plan Objective The Borough staff will develop and execute timely and effective

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Frequently Asked Questions on the Route 29 Solutions Improvements Projects

Frequently Asked Questions on the Route 29 Solutions Improvements Projects Frequently Asked Questions on the Route 29 Solutions Improvements Projects Background What are the Route 29 Solutions improvement projects? These projects include the Route 29/250 Interchange ( Best Buy

More information

Boston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA

Boston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA Boston Redevelopment Authority 2/26/2014 Cassidy Playground Waterworks Design revisions made since the DPIR submission March 2013 Massing - Reduced project 16,030 SF, for a total project area of 218,520

More information

BILLY BISHOP TORONTO CITY AIRPORT 2018 MASTER PLAN UPDATE

BILLY BISHOP TORONTO CITY AIRPORT 2018 MASTER PLAN UPDATE BILLY BISHOP TORONTO CITY AIRPORT 2018 MASTER PLAN UPDATE City of Toronto Local Issues & Initiatives Bryan Bowen City Planning Waterfront Secretariat June 25, 2018 PRESENTATION OUTLINE BACKGROUND: ISSUES

More information

MEMORANDUM VILLAGE OF NORTHBROOK

MEMORANDUM VILLAGE OF NORTHBROOK MEMORANDUM VILLAGE OF NORTHBROOK TO: Staff COPY: Village President & Board of Trustees Department Heads FROM: Richard Nahrstadt, Village Manager DATE: April 29, 2016 SUBJECT: STAFF BRIEFING WEEK OF April

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Midland Penetanguishene Transit Committee Penetanguishene Town Office - Committee Room Tuesday, March 6 th, :00 a.m.

Midland Penetanguishene Transit Committee Penetanguishene Town Office - Committee Room Tuesday, March 6 th, :00 a.m. Midland Penetanguishene Transit Committee Penetanguishene Town Office - Committee Room Tuesday, March 6 th, 2018 9:00 a.m. 1. CALL TO ORDER 2. MINUTES FROM PREVIOUS MEETING i) Minutes from Midland Penetanguishene

More information

PORTS TORONTO Billy Bishop Toronto City Airport Summary of 2015 Traffic and Passenger Surveys

PORTS TORONTO Billy Bishop Toronto City Airport Summary of 2015 Traffic and Passenger Surveys PORTS TORONTO Billy Bishop Toronto City Airport Summary of 2015 Traffic and Passenger Surveys 1 Summary of 2015 BBTCA Traffic and Passenger Surveys Surveys of traffic volumes and pedestrian activity were

More information