Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

Size: px
Start display at page:

Download "Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018"

Transcription

1 Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018

2 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH) Southwestern Maintenance Yard Contractor 8.5-mile light-rail line 8 new stations: 3 underground 4 at-grade One aerial Project budget: $2.058 billion

3 Northern Segment Update Expo/Crenshaw Bl to 67th St Four new stations Three underground One at-grade Underground structures Dual parallel bored tunnels Cut and Cover tunnel One mile at-grade segment

4 Northern Segment Update Highlights Underground Station Construction Underground stations construction: Expo/Crenshaw Station MLK Jr Station Leimert Park Station Ongoing construction activities: Concrete pours of station floors and walls Concourse level installation Installation of station facilities Removal of temporary support structures at the plaza entrance of the Exposition Station.

5 Northern Segment Update Crenshaw Bl Restoration Closures WSCC implemented the closures in three progressive phases: Completed Restoration Closures Restoration Phase 1: Leimert Park Station Area Restoration Phase 2: MLK Jr Station Area Current Restoration Closure Restoration Phase 3: Expo/Crenshaw Station Area Installation of electrical conduit above the platform of the MLK Jr Station.

6 Crenshaw Bl Restoration Closures Underground Station Area Construction Phase Typical Station Area Location

7 Crenshaw Bl Restoration Closures Street Restoration Construction Phase Typical Station Area Location

8 Crenshaw Bl Restoration Closures Street Restoration Construction Phase 3 Storm Drain & Sewer Line Installation

9 Crenshaw Bl Restoration Closures Street Restoration Construction Phase 3 Installation of formwork for the storm and sewer lines during Expo Station Area restoration closure

10 Crenshaw Bl Restoration Closures Phase 3: Expo/Crenshaw Station Area Construction Activities: Backfilling and side structure construction New curb and gutter Sidewalk reconstruction Temporary pedestrian walkway Southbound traffic diverted at Jefferson Bl Local access maintained during closure Crushing operation during closure Backfill and compaction between Rodeo Rd and Rodeo Pl

11 Expo/Crenshaw Bl Station Phase 3: Expo/Crenshaw Station Area Traffic Detours Crenshaw Bl from Coliseum Av to Exposition Bl

12 Expo/Crenshaw Bl Station Phase 3: Pedestrian Detours During Phase 3 of Crenshaw Bl Restoration Closures, pedestrian access will be safely routed around construction. Pedestrian access on the east side will be routed through Rodeo Rd, Bronson Av, and back to Crenshaw Bl. Pedestrian access on the west side will be routed through Rodeo Pl, Victoria Av, and back to Crenshaw Bl. Eastbound and westbound pedestrian access will be maintained across Coliseum St and Exposition Bl. Rodeo Rd will not have through access.

13 Northern Segment Update Additional Restoration Work Station areas to remain under traffic reconfiguration Ongoing street level or station plaza construction Sidewalk reconstruction Utility work Streetscape and landscaping Final roadway re-surfacing Roof decking and falsework at the entrance side structure of the Liemert Park Station

14 Northern Segment Update Tunnel Section Final Segment Track Installation

15 North and Central Segments At Grade Segment - Park Mesa Heights 48th St to 59th St Scope of Work New sidewalks and driveways Updated/new street lights and traffic signals New roadway surface/rehabilitation New Hyde Park Station New landscaped center medians Rail safety enhancements Crenshaw Bl Streetscape Plan elements: New sidewalk trees New lighting New crosswalks

16 North and Central Segments: At Grade Segment - Park Mesa Heights 48th St to 59th St Remaining Construction Work Some outstanding sidewalk work Hyde Park Station and guideway construction on-going Street resurfacing full depth construction Landscaping Impacts Long term traffic reconfiguration Frequent lane closures Pedestrian access occasionally restricted and rerouted Temporary bus stop/route relocations Civil work street reconstruction

17 Northern Segment Update Hyde Park Station Progress

18 Northern Segment Update Hyde Park Station Progress

19 Northern Segment Update Hyde Park - 59th to 67th St. Tunnel/Cut and Cover Construction Current Construction: Ongoing tunnel construction and staging in the center of Crenshaw Bl Occasional lane closures Restoration/backfilling work Removal of struts at the south portal of underground tunnel Some extended street closures

20 Southern Segment Update 67th St to Green Line Station Four New Stations Three At-Grade One Aerial Five Aerial Structures One Underground Structure

21 Southern Segment Update Fairview Heights Station - Eastbound towards West Bl

22 Southern Segment Update Downtown Inglewood Station - Eastbound towards Centinela Av

23 Southern Segment Update Downtown Inglewood Station - Eastbound towards Centinela Av

24 Southern Segment Update Downtown Inglewood Station - Eastbound from platform

25 Southern Segment Update Traction Power Substation (TPSS)House - Inglewood

26 Southern Segment Update Fence Installation - Inglewood

27 Southern Segment Update Facing Westchester/Veterans Station - Southbound View

28 Southern Segment Update Aviation/Century Station June 2018: Escalator Installation.

29 Southern Segment Update Aviation/Century Station June 2018: Installation of elevators. Anticipated completion Nov Installation of Elevator Frames

30 Southern Segment Update Aviation/Century Station - Conceptual Rendering

31 Southern Segment Update Ongoing At-Grade Station Construction Location/Activity Downtown Inglewood Station: Foundation Slab - Pavilion & Fare Gate Westchester Veterans Station: Installation of Controls/Piping & Start up Westchester Veterans Station: Installation of Racks, Equipment, Pull/Term Cables Fairview Heights Station: Installation of Structural Steel Canopy

32 Southern Segment Update Inglewood/Westchester - Upcoming Lane Restrictions and Closures Location/Activity Hindry Av: Full depth paving Florence Av/Centinela Av: Full depth paving 32

33 Southwestern Maintenance Yard Project May 2018

34 Southwestern Maintenance Yard Project May 2018

35 Southwestern Maintenance Yard Project May 2018

36 Southwestern Maintenance Yard Project First train cars on site May 2018

37 Significant Milestones for SWY Project First train cars were delivered to the SWY for testing Over 90% of project complete Expected turnover to Metro anticipated for early

38 Southwestern Maintenance Yard Project Conceptual Rendering

39 AMC-Airport Metro Connector Project Located on Aviation Bl and Arbor Vitae St

40 AMC-Station Naming Preliminary outreach in form of briefings and presentation are being hosted with key stakeholder to inform and educate about the station naming process and timeline. Outreach began in May 2018 and ended September 14, Report being drafted and will ultimately be presented to Metro Board 40

41 Metro Small Business Pilot Programs Help small mom and pop businesses continue to thrive throughout construction and post construction Metro Business Solution Center (BSC) Metro Business Interruption Fund (BIF)

42 Business Solution Center Crenshaw/LAX Transit Project BSC Business Resources: Hands-on business development Expert business advice and coaching Technical assistance Referrals to expert professionals BSC Program Statistics October 31, 2018: Number of business Contacts: 459 Number of business Intakes/Assessments: 350 Number of business referrals: 1127 Learn More:

43 Business Solution Center Crenshaw/LAX Transit Project BSC Areas of Focus: Long term business planning Increasing business access to technology Website development Assessment of IT infrastructure and IT systems Workshops and Events Marketing & Social Media, Branding through Customer Service, Yelp 101, Build Your Business Plan in a Day, Get Your Business Online (Partnership with Google) Accounting Management Financial readiness Access to financial capital Learn More:

44 Business Interruption Fund Crenshaw/LAX Transit Project Financial assistance to small mom & pop businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements Grant amount determined by loss of business revenue related to period of construction disruption Learn More:

45 Business Interruption Fund Crenshaw/LAX Transit Project BIF Program Statistics Nov. 2, 2018: BIF applications submitted: 1009 BIF applications approved/awarded: 775 BIF applications pending financials: 140 BIF applications deemed not eligible: 92 BIF applications denied: 2 BIF Application Approval Rate: 84.70% BIF Grant Payments: $17,762, Crenshaw/LAX BIF Statistics: 440 grants awarded to C/LAX Total amount: $9,805, small businesses received a grant Learn More:

46 Business Interruption Fund Crenshaw/LAX Transit Project BIF Project Updates and Areas of Focus: Continued outreach along Crenshaw Corridor areas of: Baldwin Hills Crenshaw Mall Park Mesa Heights Hyde Park Inglewood/Southern Section Ongoing education of program requirements and application process through: information and application sessions and one-on-one client meetings Learn More:

47 Business Interruption Fund Crenshaw/LAX Transit Project $9,805, Value of BIF Grants Awarded (as of 11/2/18) $4,594, $564, $1,847, $950, Crenshaw/LAX Transit Project Purple Line Extension, Section 1 Purple Line Extension, Section 2 Regional Connector, Little Tokyo Area Regional Connector, 2nd/Broadway Segment Learn More:

48 Business Interruption Fund Crenshaw/LAX Transit Project 100% BIF Measures of Effectiveness (as of CY 2018 Q1) 96% 87% 92% 86% Businesses referred to support services Applications processed within 9 business days Clients satisfaction rating Businesses remaining open after 6 months of grant award Businesses remaining open after 1 year of grant award Learn More:

49 CLC Workgroup Meetings & Events CLC Special Project Workgroup Metro Art Tour: Monday, December 10 from 10am-12:00pm Free - Metro Art and Architecture Tour of Historic Union Station sponsored by the Empowerment Congress West Area Neighborhood Development Council (ECWANDC). Tour will cover Union Station art, Architecture and Historic Ticketing Hall. The tour will depart from the Crenshaw/LAX Transit Project Office. Space is limited. RSVP required to crenshawclc@metro.net

50 CLC Workgroup Meetings & Events Save the Date- CLC Joint Holiday Mixer: Wednesday, December 19 from 5pm-7:00pm Joint Holiday Mixer at the Baldwin Hills Crenshaw Plaza Macy s Bridge, 2nd Floor located at 3650 W. MLK Jr. Blvd., LA. Guests will enjoy live entertainment, refreshments, prizes, photo booth, holiday activities, prizes and a special visit from Santa Claus. Official invitation will be sent the end of November to RSVP

51 Contact Us

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 1 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 1 Project Overview Mainline Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017

Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017 Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017 1 Project Overview Design-Build Contractors: Mainline - Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017

Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017 Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance Facility:

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

June 2017: 700 Piles 9 Weeks and 3 Days Pile Caps / Tie Beams Roof Foundations

June 2017: 700 Piles 9 Weeks and 3 Days Pile Caps / Tie Beams Roof Foundations Welcome FAA FAA October 2016: Broke Ground October 2016 Excavated 6.2 Million Cubic Yards Excavated 100,000 Cubic Yards in one day at peak 36 30 Yard Scrappers 10 30 Yard Dump Trucks 85 Days to Complete

More information

INVESTMENT HIGHLIGHTS

INVESTMENT HIGHLIGHTS 6821 VICTORIA AVE EXECUTIVE SUMMARY We are pleased to offer for sale a freestanding industrial property located at 6821-6815 S. Victoria avenue in Los Angeles. It was built in 1946 as an electrical components

More information

CRENSHAW BOULEVARD LOS ANGELES, CA 90008

CRENSHAW BOULEVARD LOS ANGELES, CA 90008 4287 CRENSHAW BOULEVARD LOS ANGELES, CA 90008 HIGHLY VISIBLE RETAIL RESTAURANT FOR SALE COMMERCIAL PROPERTY SUBJECT PROPERTY Back Alley Homeland Drive Crenshaw Boulevard CONTACT: CHARLES DUNN COMPANY,

More information

Claremont Project Background and Update Community Meeting September 11, 2017

Claremont Project Background and Update Community Meeting September 11, 2017 Claremont Project Background and Update Community Meeting September 11, 2017 Topics Project Background Claremont Segment Information Project Timeline Upcoming Discussion Items Upcoming Meetings Questions

More information

New Mixed Use Development BETWEEN EXPOSITION AND JEFFERSON CRENSHAW BOULEVARD LOS ANGELES, CA

New Mixed Use Development BETWEEN EXPOSITION AND JEFFERSON CRENSHAW BOULEVARD LOS ANGELES, CA FOR LEASE FOR LEASE PROPERTY FEATURES Available: Asking Rate: ±1,200 SF - 4,500 SF Negotiable APN: 5046-001-021 Zoning: LAC1.5 PROPERTY HIGHLIGHTS + + Fantastic retail opportunity: Ideal location for coffee,

More information

Second Street Improvements Project Project Update Archive

Second Street Improvements Project Project Update Archive Second Street Improvements Project Project Update Archive 12/03/18: In observance of the Holiday Moratorium, crews have paused a majority of construction activity on 2nd Street until January 2, 2019. A

More information

Expo E-News. Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2. Keeping Our Community Informed

Expo E-News. Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2. Keeping Our Community Informed Expo E-News Keeping Our Community Informed Winter 2014 Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2 In this Issue : Page 4: Construction Update Page 6: Artist Profiles For more information

More information

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017 LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20

More information

Cell: (408) Release MA June 25, 2012

Cell: (408) Release MA June 25, 2012 VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara

More information

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation Silver Line Update Committee for Dulles March 2, 2017 Mark Canale Fairfax County Department of Transportation Phase 1 Summary Old Meadow Road Realignment design work proceeding, construction to be completed

More information

Item # 28. Chief Capital Management Officer Report. November 20, 2008

Item # 28. Chief Capital Management Officer Report. November 20, 2008 Item # 28 Chief Capital Management Officer Report November 20, 2008 1 Metro Gold Line Eastside Extension Project Update November 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground)

More information

Having trouble reading this ? View it in your browser. Welcome

Having trouble reading this  ? View it in your browser. Welcome Page 1 of 6 Having trouble reading this email? View it in your browser. IN THIS ISSUE Remembering 2011 and Preparing for 2012 Copper Thefts Increase on West Rail Eiber Neighborhood Resident Recieves "Most

More information

West Santa Ana Branch Transit Corridor. Community Meetings March 12, 13, 17 & 19, 2018

West Santa Ana Branch Transit Corridor. Community Meetings March 12, 13, 17 & 19, 2018 West Santa Ana Branch Transit Corridor Community Meetings March 12, 13, 17 & 19, 2018 Purpose of this Meeting > Update on Public Scoping comments received > Why Metro is revisiting the Northern Alignments

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Go Local Fixed-Guideway Program History and Project Update. PowerPoint 3

ORANGE COUNTY TRANSPORTATION AUTHORITY. Go Local Fixed-Guideway Program History and Project Update. PowerPoint 3 ORANGE COUNTY TRANSPORTATION AUTHORITY Go Local Fixed-Guideway Program History and Project Update PowerPoint 3 Santa Ana-Garden Grove Fixed Guideway Project OCTA Board of Directors September 26, 2011 Project

More information

Metro Gold Line Eastside Extension Review Advisory Committee May 8, 2008

Metro Gold Line Eastside Extension Review Advisory Committee May 8, 2008 Review Advisory Committee May 8, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-Grade and 2 Underground) Park & Ride Facility at Pomona/Atlantic Direct Connection to the Pasadena Metro at Union

More information

LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation

LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation LESLIE BARNS & CONNECTION TRACK Project Update Construction and Traffic Management Consultation PRESENTATION SUMMARY Part 1 Brief Project Update (New Streetcars & Streetscape Improvements) Part 2 Construction

More information

PRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction

PRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction PRESENTED TO Town of Middlebury, VT PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction Meeting with you today Brian Carpenter, Middlebury Selectboard Chair Jim Gish, Middlebury

More information

Transportation Supporting Dulles Airport

Transportation Supporting Dulles Airport Transportation Supporting Dulles Airport Committee for Dulles Economic Development and Transportation Committee July 12, 2018 Tom Biesiadny, Director Fairfax County Multiple Transportation Improvements

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting Culver City Senior Center Wednesday, July 16, 2008 Description 8.6 mile corridor from downtown to Culver City in West Los Angeles 1.3

More information

Phoenix Sky Harbor transit guideway bridge

Phoenix Sky Harbor transit guideway bridge Phoenix Sky Harbor transit guideway bridge by David A. Burrows, Gannett Fleming The evolution of the PHX Sky Train s crossing of Taxiway Romeo At one of the 10 busiest airports in the United States, cast-in-place,

More information

Metro Gold Line Eastside Extension Review Advisory Committee October 9, 2008

Metro Gold Line Eastside Extension Review Advisory Committee October 9, 2008 Review Advisory Committee October 9, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within

More information

Link Union Station (LINK US)

Link Union Station (LINK US) Link Union Station (LINK US) Presentation for LAUS Master Commercial Developer Industry Forum October 13 th 2017 Jeanet Owens, PE Senior Executive Officer Program Management / Regional Rail Project Overview

More information

Carlisle Connectivity Projects Communication Plan and Project Status

Carlisle Connectivity Projects Communication Plan and Project Status Carlisle Connectivity Projects Communication Plan and Project Status Overview Communication Plan Communication Plan Communication Plan Objective The Borough staff will develop and execute timely and effective

More information

Long water shutdown scheduled for Tuesday, September 18

Long water shutdown scheduled for Tuesday, September 18 Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

25 th Avenue Grade Separation. September 13, 2017

25 th Avenue Grade Separation. September 13, 2017 25 th Avenue Grade Separation September 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25

More information

Hospital Link Project Project Update Winter 2018

Hospital Link Project Project Update Winter 2018 Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open

More information

Silver Line Rail Project Update

Silver Line Rail Project Update Silver Line Rail Project Update April 2013 Project Map 2 Silver Line, Phase 1 Service Pattern 3 Project Overview Silver Line Dulles Metrorail is a 23-mile extension of the existing Orange Line Total Project

More information

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation

More information

Design Meeting Presentation

Design Meeting Presentation Contract No. 17ECS-TI-05SP April November 2017 Design Meeting Presentation November 2015 Agenda Items: Introduction (5 min) Overview (10 min) Scope of work (60 min): Schedule and Traffic Staging / Closures

More information

Industry briefing NOVEMBER 2017

Industry briefing NOVEMBER 2017 Industry briefing NOVEMBER 2017 SYDNEY METRO AUSTRALIA S BIGGEST PUBLIC TRANSPORT PROJECT A new stand-alone railway, this 21st century network will revolutionise the way Sydney travels. Services start

More information

Regional Connector Transit Project Community Leadership Council

Regional Connector Transit Project Community Leadership Council Regional Connector Transit Project Community Leadership Council Grand Av Arts/Bunker Hill Station & Flower St/Financial District Committees May 9, 2017 1 COMMUNITY LEADERSHIP COUNCIL UPDATE 2 CLC Executive

More information

National Society of Professional Engineers. Charles S. Carnaggio, PE Project Director July 2, 2014

National Society of Professional Engineers. Charles S. Carnaggio, PE Project Director July 2, 2014 National Society of Professional Engineers Charles S. Carnaggio, PE Project Director July 2, 2014 Phase 1 Opening Date: July 26, 2014 Dulles Corridor Metrorail Project At-a-Glance Seamless integration

More information

Executive Summary. See Figure ES-5 on page 9. Figure ES-6: Typical At-Grade Alignment. Figure ES-7: Typical Underground Alignment

Executive Summary. See Figure ES-5 on page 9. Figure ES-6: Typical At-Grade Alignment. Figure ES-7: Typical Underground Alignment Figure ES-5 shows all of the possible LRT routes and stations identified for study in the Draft EIS/EIR. The features and impacts of each of the build alternatives are described in the following section.

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation

More information

Main Street Station Upgrades

Main Street Station Upgrades Main Street Station Upgrades Public Meeting Hope United Church 1 Main Street Station Upgrades Bus diversions Planned improvements Construction staging Pedestrian flows 2 Main Street Station Aerial Bar

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 29, 2009 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION PROJECT STEELES WEST STATION APPROVAL OF CONCEPTUAL DESIGN

More information

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK

More information

CITY OF BEVERLY HILLS TRAFFIC & PARKING COMMISSION TO: FROM: SUBJECT: ATTACHMENTS: June 1,2017. Aaron Kunz, Deputy Director

CITY OF BEVERLY HILLS TRAFFIC & PARKING COMMISSION TO: FROM: SUBJECT: ATTACHMENTS: June 1,2017. Aaron Kunz, Deputy Director CITY OF BEVERLY HILLS TRAFFIC & PARKING COMMISSION June 1,2017 TO: FROM: SUBJECT: ATTACHMENTS: Traffic & Parking Commission Aaron Kunz, Deputy Director North Santa Monica Boulevard Reconstruction Project

More information

Hospital Link Project Project Update September 2015

Hospital Link Project Project Update September 2015 Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

November 9, Society of American Military Engineers

November 9, Society of American Military Engineers November 9, 2016 Society of American Military Engineers Transit Operator Transportation Planner Transportation Infrastructure Builder Transportation Funding Overseer 2 1,433 square-mile service area (nearly

More information

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015 East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

Ohio Department of Transportation Construction Update

Ohio Department of Transportation Construction Update Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District

More information

MEMORANDUM VILLAGE OF NORTHBROOK

MEMORANDUM VILLAGE OF NORTHBROOK MEMORANDUM VILLAGE OF NORTHBROOK TO: Staff COPY: Village President & Board of Trustees Department Heads FROM: Richard Nahrstadt, Village Manager DATE: April 29, 2016 SUBJECT: STAFF BRIEFING WEEK OF April

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2014 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2015 Introduction The

More information

LESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014

LESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014 LESLIE BARNS & CONNECTION TRACK Leslieville BIA Meeting May 2, 2014 1 OVERVIEW Communications Queen/Leslie Intersection Closure Overview Next Steps - Coordination of TTC Track Upgrades (Queen streetcar

More information

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program December 2012 Update I-95 New Haven Harbor Crossing Corridor Improvement Program Prepared by: Connecticut Department of Transportation District 3A 424 Chapel Street New Haven, CT 06511 Prepared for: South

More information

E-Newsletter Keeping Our Community Informed Volume 1, Issue 4

E-Newsletter Keeping Our Community Informed Volume 1, Issue 4 W ith the Expo Light Rail Line under heavy construction for almost two years now, a variety of construction activities are taking place up and down the whole alignment. In Downtown Los Angeles utility

More information

Construction Staging Adelaide Street West

Construction Staging Adelaide Street West REPORT FOR ACTION Construction Staging Adelaide Street West Date: October 6, 2016 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

US 19 Sunset Point Rd to Countryside Blvd.

US 19 Sunset Point Rd to Countryside Blvd. Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started

More information

Regional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017

Regional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017 Regional Connector Transit Project Community Leadership Council 2 nd Hope Station & Flower St Committees January 17, 2017 1 EAT SHOP PLAY LOCAL 2 Eat Shop Play Local > Free Metro marketing campaign > Make

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

Public Information Center August 12, 2010

Public Information Center August 12, 2010 Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General

More information

Work in 2015 and Annual Mobility- Management Plan

Work in 2015 and Annual Mobility- Management Plan Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector

More information

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2) Atlantic Street Bridge Project Update CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement Track & Station Infrastructure Improvements City

More information

East Link Extension. Redmond stations Open House November 17, 2016

East Link Extension. Redmond stations Open House November 17, 2016 East Link Extension Redmond stations Open House November 17, 2016 Presentation agenda Overview of East Link Extension light rail project and two stations in Redmond s Overlake area Overlake Village Station

More information

First rail. August 2011

First rail. August 2011 August 2011 First rail A downtown resident showed his son in early August the first completed section of embedded track on Fourth Street in front of the Farmer s Market. During July, the Central Corridor

More information

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route

More information

City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting

City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting Wednesday, May 31, 2017 6:30 to 8 P.M. Frank Allis Elementary School 4201 Buckeye Road Madison,

More information

JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS

JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS For Immediate Release January 2, 2018 Contact: Charles H. Pannunzio (424) 646-5260 JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS Access to Parking Structure 4 from the Upper/Departure

More information

SLC Airport Project Adds New Scope; Teams Scramble to Stay on Schedule

SLC Airport Project Adds New Scope; Teams Scramble to Stay on Schedule SLC Airport Project Adds New Scope; Teams Scramble to Stay on Schedule Two sky bridges will connect the parking garage to the second level of the terminal, while an elevated roadway for depa will access

More information

Union Station Queens Quay Transit Link Study

Union Station Queens Quay Transit Link Study Welcome Union Station in 1899. Image: City of Toronto Archives Union Station today. Image: Camil Rosiak Activity along Queens Quay. Image: Waterfront Toronto For more information or to comment, visit toronto.ca/waterfronttransit

More information

APPENDIX H MILESTONE 2 TRAFFIC OPERATIONS ANALYSIS OF THE AT-GRADE CROSSINGS

APPENDIX H MILESTONE 2 TRAFFIC OPERATIONS ANALYSIS OF THE AT-GRADE CROSSINGS Draft Environmental Impact Statement/Environment Impact Report Appendix H Milestone 2 Traffic Operations Analysis of the At-Grade Crossings APPENDIX H MILESTONE 2 TRAFFIC OPERATIONS ANALYSIS OF THE AT-GRADE

More information

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required. NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour

More information

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration

More information

Monday, September 18, 2017 Sunday, October 1, 2017

Monday, September 18, 2017 Sunday, October 1, 2017 Monday, September 18, 2017 Sunday, October 1, 2017 CONSTRUCTION UPDATE* Hurricane Irma cleanup is complete and some landscaping repairs are underway. The project was secure and no major damages were encountered.

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: SUBJECT: Resubmitted December 19, 2012 November 21, 2012 MODERNIZING THE TTC A NEW APPROACH TO COMMUNICATIONS, COMMUNITY

More information

WHO IS METROLINX?

WHO IS METROLINX? CROSSTOWN LRT WHO IS METROLINX? Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate

More information

SCOPING INFORMATION PACKET

SCOPING INFORMATION PACKET SCOPING INFORMATION PACKET Project Description The proposed project would provide a direct link connecting several light rail lines in operation or in construction, including the Metro Gold Line to Pasadena,

More information

Head to University Avenue and save!

Head to University Avenue and save! April 2011 Head to University Avenue and save! Liberty Tax Service at 1731 University Ave. W. in is offering a special for first-time customers who drive through the construction zone to get their taxes

More information

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017 A63 Castle Street, Hull HullBID Network Lunch 24 August 2017 James D Leeming Senior Project Manager What we will cover today? Introduction to Highways England and the Road Investment Strategy A63 Scheme

More information

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

Milestone: Bridge to Nowhere scheduled for demolition Aug 14 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Blanca Del Valle (915) 790-4341 Blanca.DelValle@txdot.gov August 12, 16 Milestone: Bridge to Nowhere scheduled for demolition Aug 14

More information

Downtown to Defiance Trolley Key Messages Jan. 2017

Downtown to Defiance Trolley Key Messages Jan. 2017 Downtown to Defiance Trolley Key Messages Jan. 2017 Overarching Messages This is a demonstration (pilot) project for one summer. We will evaluate how it went to see if we can offer it again in the future.

More information

Northeast Corridor Transportation Update

Northeast Corridor Transportation Update Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer

More information

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required. REPORT FOR ACTION Construction Staging Area - 81 Bay Street Date: December 11, 2017 To: Toronto and East York, Community Council From: Acting Director, Transportation Services Toronto and East York District

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.4 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving various parking and traffic modifications associated

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Astoria Boulevard ADA and Station Renewal Track Improvements. January 30, 2019

Astoria Boulevard ADA and Station Renewal Track Improvements. January 30, 2019 Astoria Boulevard ADA and Station Renewal Track Improvements January 30, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two

More information

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2)

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2) Atlantic Street Bridge Project CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro North RR Bridge Replacement Track & Station Infrastructure Improvements City of Stamford

More information

Wellesley Station Second Exit and Automatic Entrance Public Open House. Tuesday, September 23, 2014 Central YMCA 20 Grosvenor Street

Wellesley Station Second Exit and Automatic Entrance Public Open House. Tuesday, September 23, 2014 Central YMCA 20 Grosvenor Street Wellesley Station Second Exit and Automatic Entrance Public Open House Tuesday, September 23, 2014 Central YMCA 20 Grosvenor Street 1 What are Second Exits? Second exits serve three functions: As a primary

More information

RESORT AREA STRATEGIC ACTION PLAN (RASAP) STEERING COMMITTEE MEETING - APRIL 3, 2019

RESORT AREA STRATEGIC ACTION PLAN (RASAP) STEERING COMMITTEE MEETING - APRIL 3, 2019 RESORT AREA STRATEGIC ACTION PLAN (RASAP) STEERING COMMITTEE MEETING - APRIL 3, 2019 Welcome & Introductions - Deb Zywna AGENDA FY 20 Resort CIP Proposed Projects - Kathy Warren ORDFBC Design Guidelines

More information

AGENDA ITEM I-6 Public Works

AGENDA ITEM I-6 Public Works AGENDA ITEM I-6 Public Works STAFF REPORT City Council Meeting Date: 8/6/2018 Staff Report Number: 18-150-CC Informational Item: Update on the Willow Road and highway 101 interchange construction, upcoming

More information

Report to the Strategic Development Committee. Ronald Reagan Washington National Airport Project Journey. June 2018

Report to the Strategic Development Committee. Ronald Reagan Washington National Airport Project Journey. June 2018 Report to the Strategic Development Committee Ronald Reagan Washington National Airport Project Journey June 2018 Secure National Hall Secure National Hall Project Cost Summary Prior Month Expenditures

More information

BE VE R LY HILLS CITY OF BEVERLY HILLS HUMAN SERVICES DIVISION MEMORANDUM TO: Human Relations Commission FROM:

BE VE R LY HILLS CITY OF BEVERLY HILLS HUMAN SERVICES DIVISION MEMORANDUM TO: Human Relations Commission FROM: October October November November4-5, November Metro 2017-18 BE VE R LY HILLS C CITY OF BEVERLY HILLS HUMAN SERVICES DIVISION MEMORANDUM TO: FROM: DATE: SUBJECT: ATTACHMENT: Human Relations Commission

More information

Astoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019

Astoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019 Astoria Boulevard ADA Upgrade and Station Renewal January 7, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two Mezzanine-to-Platform

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

All closures this week happen at night, including full closures of Mesa and I-10

All closures this week happen at night, including full closures of Mesa and I-10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov May 25, 2018 North Mesa Tuesday, May 29 through Thursday, May 31 9 p.m. each

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today s session will provide you with information on options The City is exploring for connecting the Green Line in the Beltline to the future Inglewood/Ramsay station.

More information

TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018

TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018 TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018 2018-2019 SCHEDULE Project progress Contract signed with the winning consortia on April 12, 2018 Project office set up for the

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

3317 EXPO- SITION PL LOS ANGELES

3317 EXPO- SITION PL LOS ANGELES FOR LEASE CREATIVE OFFICE 24,913 TOTAL SF 3317 EXPO- SITION PL LOS ANGELES INDUSTRYPARTNERS.COM 310 395 5151 CA BRE No. 01900833 RICH MALOOF rm@industrypartners.com CA BRE No. 01435225 JIM JACOBSEN jj@industrypartners.com

More information