35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

Size: px
Start display at page:

Download "35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS"

Transcription

1 35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

2 35EXPRESS PROJECT OVERVIEW 2

3 ABOUT THE 35EXPRESS PROJECT 3

4 DESIGN-BUILD TEAM 4

5 PROJECT PARTNERS Great partnerships make this project work Collaboration on a local, regional, state and federal level 5

6 PROJECT OVERVIEW Approximately 30-mile project US Highway 380 to I-635 Ultimate construction cost: $4.8 B Available funds: $1.4 B (Phase 1) Phase I began: Fall 2013 AGL Constructors contracted to complete Phase 1 only Estimated completion: Summer

7 PROJECT OVERVIEW North One additional main lane (three total) in each direction New bridges at North Texas Boulevard, Corinth Parkway, and Post Oak Drive Rehab and expansion of the bridges at Mayhill, Loop 288, US 77, McCormick, and Bonnie Brae Lengthening and widening ramps throughout the corridor Adding continuous frontage roads Middle One additional main lane (four total) in each direction New bridges at Turbeville/Hundley, South Denton/Oak Drive, Garden Ridge Boulevard, FM 407 and Fox Avenue New southbound bridge at Lewisville Lake Bike/pedestrian paths and connections across Lewisville Lake 7

8 PROJECT OVERVIEW Middle Improvements to Copperas Branch Park New trails on the east side of Copperas Branch Park, new beach areas, parking lots and other amenities New collector/distributor lanes between President George Bush Turnpike and Sam Rayburn Tollway Adding direct connector ramps to the north side of I-35E intersection with the Sam Rayburn Tollway South 18-mile reversible TEXpress toll (managed lane) system from Farmers Branch to north of Lewisville Lake New interchanges at Dickerson Parkway and Belt Line Road Bridge widening at Whitlock Lane, Crosby Road, Valwood Parkway and Valley View Lane Direct connections from LBJExpress managed lane system to the new I-35E managed lane system 8

9 TEXPRESS LANES Branded as TEXpress Lanes in the North Texas region Congestion management system with variable pricing Fixed rate schedule first six months, dyamic pricing thereafter Offers motorists choice, predictable travel and congestion relief The two lanes located in the center of the current roadway will be reversible Open southbound for morning rush hour, northbound for afternoon rush hour Lanes barrier separated and designed for limited traffic weaving 9

10 CONSTRUCTION OVERVIEW 10

11 NORTH TEXAS BOULEVARD The North Texas Boulevard bridge was demolished in April. Connectivity was restored in mid-august with one lane in each direction and one turn lane The additional lanes are scheduled to open Feb. 20 One through lane in each direction Two designated turn lanes in each direction Work will continue into Spring with completion of the bridge prior to UNT commencement ceremonies Additional through lane in each direction A U-turn lane on each end of the bridge A 15-foot-wide pedestrian walkway on the east side 11

12 NORTH TEXAS BOULEVARD RAMP CLOSURES North- and southbound I-35E lanes have shifted onto temporary pavement at the North Texas Boulevard bridge with four feet of additional clearance Work removing the original roadway and constructing the new mainlanes in this area has begun The northbound entrance ramp from North Texas Boulevard and the southbound exit ramp to North Texas Boulevard are scheduled to open this spring The southbound entrance ramp from North Texas Boulevard is scheduled to reopen in February 12

13 MCCORMICK STREET The northbound exit ramp to McCormick Street will reopen in spring Southbound mainlane traffic is scheduled to be moved onto the new portion of the McCormick Street bridge in February Demolition of the center portion of the original bridge is scheduled in February McCormick Street has closed between the north- and southbound frontage roads through February Work on the expanded McCormick Street bridge is scheduled for completion in spring 13

14 RAMP CONSTRUCTION BETWEEN TEASLEY LANE AND US 377/FORT WORTH DRIVE The north- and southbound mainlanes between Teasley Lane and US 377/Fort Worth Drive are being widened Temporary exit ramp to Teasley Lane under construction. Traffic is scheduled to shift onto the newly completed outside pavement in February The north- and southbound ramps between Teasley Lane and US 377/Fort Worth Drive are being lengthened and widened Traffic will be shifted onto temporary pavement during this work and ramp access will not be interrupted The southbound entrance ramp from Teasley Lane is schedule to shift to permanent location this week Ramp construction in this area is scheduled for completion this spring New pavement under construction. 14

15 RAMP CHANGES AT LOOP 288/ US 77 BRIDGE Southbound US 77 entrance ramp Northbound mainlane traffic has shifted onto the US 77 bridge The southbound entrance ramp from US 77/Dallas Drive will be reconstructed and is scheduled to open in February The southbound frontage road south of Loop 288 has been widened to two lanes New southbound Loop 288 exit ramp 15

16 POST OAK DRIVE BRIDGE Connectivity across the Post Oak Drive bridge has been restored with one lane in each direction Work will continue on the bridge and the intersection through spring 2017 The completed bridge will have two lanes in each direction and two dedicated turn lanes in each direction 16

17 CORINTH-AREA NORTHBOUND TRAFFIC SHIFT The northbound lanes of I-35E between the U-turn by the Destiny Dallas RV park and Post Oak Drive are scheduled to shift west into their permanent alignment in February When this occurs the following ramps will shift to their permanent alignment: The exit ramp to Corinth Parkway (460) shifts Mayhill Road Exit (462) Entrance Ramp from Corinth Parkway Post Oak Drive Exit (461) Corinth Parkway Corinth Parkway Exit (460) The exit ramp to Post Oak Drive (461) reopens The entrance ramp from Corinth Parkway reopens The exit ramp to Mayhill Road (462) shifts U-turn 17

18 OAK DRIVE/LAKE DALLAS DRIVE Northbound frontage road will reopen in March Work continues on the northbound mainlanes north of Lewisville Lake and the new Oak Drive/Lake Dallas Drive intersection The new Oak Drive/Lake Dallas Drive intersection is scheduled to open in spring The southbound frontage road between Hickory Creek Road and Oak Drive will remain a two-way condition until Oak Drive/Lake Dallas Drive is opened The northbound frontage road in Lake Dallas is scheduled to reopen between Janet Court and Lake Dallas Drive in March The northbound mainlanes are scheduled to switch to their permanent location this spring 18

19 LEWISVILLE LAKE BRIDGE The southbound frontage road across the Lewisville Lake bridge will open by spring The northbound bridge is scheduled to reopen in spring When the project is complete: The new Lewisville Lake bridge will carry four southbound mainlanes, two reversible managed lanes, two frontage road lanes and a 10-foot-wide bike and pedestrian walkway The original Lewisville Lake bridge will carry four northbound mainlanes, two frontage road lanes and a 10-foot-wide bike and pedestrian walkway Work removing the stone fingers from the north side of the lake will begin in February The DCTA rail bridge will not be affected by the project 19

20 HIGHLAND VILLAGE ROAD/GARDEN RIDGE BOULEVARD The work on Highland Village Road at the southbound frontage road will continue through spring 2017 Removal of the temporary stone fill in the Lewisville Lake will begin this month. The removal of the material at the portion of the lake south of Highland Village Road is scheduled for February Work has begun on the new pedestrian bridge that will connect Copperas Branch Road and the Copperas Branch Park. Work on the park road and parking lot will begin in the next several months The park is scheduled for completion in mid-2017 The completed Garden Ridge Boulevard bridge is expected to open spring 2017 with two lanes in each direction and a turn lane in each direction 20

21 FOX AVENUE Beam placement for the Fox Avenue bridge scheduled for the weekend of January Overnight mainlane and ramp closures between State Highway 121 Business and FM 1171/Main Street Overnight full closure of east- and westbound Fox Avenue North- and southbound frontage roads will be detoured to the Fox Avenue intersection 21

22 CORPORATE DRIVE/MAIN STREET WEEKEND CLOSURES Full, weekend closure of the Corporate Drive bridge scheduled for February Westbound traffic will take the northbound frontage road to the U-turn at SH 121 Eastbound traffic will take the southbound frontage road to FM 3040/Round Grove Road Full, weekend closure of the FM 1171/Main Street bridge scheduled for Feb Westbound traffic will take the northbound frontage road to Valley Ridge Boulevard Eastbound traffic will take the southbound frontage road to Fox Avenue 22

23 SAM RAYBURN TOLLWAY The northbound exit ramp to FM 3040 will be closed nightly from 9 p.m. to 6 a.m. through Jan. 22 for beam setting Full, overnight closures of the southbound frontage road between Vista Ridge Drive and the Sam Rayburn Tollway through Feb. 22 Detour: Vista Ridge Mall Drive to Lake Vista to southbound frontage road Full Overnight Closures of the southbound entrance ramp from FM 3040 through Feb. 22 Detour: SH 121 entrance ramp Full, weekend closure of eastbound SRT between north- and southbound I-35E scheduled for February 23

24 SOUTHBOUND COLLECTOR/DISTRIBUTOR SYSTEM The southbound collector/distributor system between the Sam Rayburn Tollway and the President George Bush Turnpike is scheduled to open in February The system consists of barrier separated lanes that run between the mainlanes and frontage roads. These ensure traffic between the toll roads does not enter the I-35E mainlanes Southbound I-35E drivers wishing to access the President George Bush Turnpike will enter the collector/distributor system at the Sam Rayburn Tollway The southbound entrance ramp from SH 121 will divert traffic into the collector/distributor system Drivers in the collector/distributor will be able to exit onto southbound I-35E The northbound collector/distributor is scheduled to go into operation spring

25 SAFETY INITIATIVES AGL and TxDOT hold monthly meetings with law enforcement and first responders to identify ways to improve safety along the corridor The speed limit between US Highway 380 and Swisher Road has been reduced to 55 mph during construction Speed boards, that show drivers how fast they are travelling, are placed at key points along the corridor AGL trucks have bumper stickers reminding drivers to drive the speed limit #Safederive35 social media campaign designed to increase driver awareness 25

26 REACHING OUT 26

27 UPCOMING MEETINGS Community Meetings North Segment 6:30 p.m. Monday, March 6 TBD South/Middle Segment 6:30 p.m. Thursday, March 9 MCL Grand Theater, Lewisville, Texas Business Owner Meetings North Segment 10:00 a.m. Tuesday, March 21 Toyota of Denton, 4100 S. I-35E, Denton South/Middle Segment 10:00 a.m. Thursday, March 23 35Express PI Office, 2420 S. Stemmons Lewisville, Texas 27

28 REACHING OUT Website: Project Hotline: Project Facebook: I35Express Instagram: 35Express C.J. Schexnayder Office: Cell:

29 35EXPRESS PI OFFICE 2420 S. Stemmons Fwy, Suite A Lewisville, Texas The 35Express PI Office will switch to appointment only starting Feb. 1 Stakeholders may arrange appointments by phone, or walk-in The 35Express PI Office will continue to respond to citizen inquiries sent to the hotline and info@35express.com address 29

30 Q&A 30

31 THANK YOU! 31

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage

More information

October Business Owner Task Force. Matt Sanman Public Information Coordinator

October Business Owner Task Force. Matt Sanman Public Information Coordinator October Business Owner Task Force Matt Sanman Public Information Coordinator Trick-or-Treating Safety Tips for Children Plan a route in advance and have emergency plan if lost. Wear reflective clothing

More information

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30 July 20, 2018 Media Contact: Keith Bilbrey Public Involvement Manager The Southern Gateway Project kbilbrey@kstrategies.com 972-989-9995 Full I-35E Mainlane Closure at Beckley Avenue - July 27-30 DALLAS

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov March 31, 2017 This Sunday, I 10 East traffic lanes will switch onto new lanes.

More information

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO Welcome to the Business Owners Task Force Perry Leonard Blagg Tire and Service President/COO Safety: West Nile Virus Alyssa Tenorio NorthGate Constructors Public Information Manager West Nile Virus Carried

More information

DRAFT. Public Meetings November 7, 9, 15, Year UTP Planning Effort Cost/Revenue Matrix FY FY 2026

DRAFT. Public Meetings November 7, 9, 15, Year UTP Planning Effort Cost/Revenue Matrix FY FY 2026 Collin FM 2478 FM 1461 to US 380 (Prosper) US 380/McKinney Bypass Candidate Project; Collin Roadway Action Plan #3 $32,600,000 $32,600,000 A Collin FM 2514 East of Lavon Parkway to North of Drain Dr. Roadway

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release.

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release. NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov January 18, 2017 Mesa Continuous for 6 weeks The following closures started

More information

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

Milestone: Bridge to Nowhere scheduled for demolition Aug 14 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Blanca Del Valle (915) 790-4341 Blanca.DelValle@txdot.gov August 12, 16 Milestone: Bridge to Nowhere scheduled for demolition Aug 14

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation

More information

All closures this week happen at night, including full closures of Mesa and I-10

All closures this week happen at night, including full closures of Mesa and I-10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov May 25, 2018 North Mesa Tuesday, May 29 through Thursday, May 31 9 p.m. each

More information

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required. NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour

More information

PennDOT Interstate Work next week March 30-April 3:

PennDOT Interstate Work next week March 30-April 3: PennDOT Interstate Work next week March 30-April 3: Interstate 80 Interstate 81 DELAYS THIS WEEK: Exit 256 to the Schuylkill County line. Eastbound & Westbound. Bridge cleaning Monday (3/30), Tuesday (3/31)

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov August 31, 18 No closures scheduled for Labor Day weekend. Traffic lane patterns

More information

I-10 will close overnight Sunday through Thursday next week. Crews continue to make progress on Sunland s new bridges and ramps.

I-10 will close overnight Sunday through Thursday next week. Crews continue to make progress on Sunland s new bridges and ramps. NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Rebecca Reyes (915) 790-4205 Rebecca.Reyes@txdot.gov I-10 will close overnight Sunday through Thursday next week. Crews continue to make

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

September 1, 2017 I-10 night closures scheduled for September hour full closure of I-10 West happens Sunday, Sept. 10

September 1, 2017 I-10 night closures scheduled for September hour full closure of I-10 West happens Sunday, Sept. 10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Rebecca Reyes (915) 790-4205 Rebecca.Reyes@txdot.gov September 1, 2017 I-10 night closures scheduled for September 5-7. 27-hour full

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

I-35 Reconstruction Project

I-35 Reconstruction Project I-35 Reconstruction Project Business Community Meeting McLennan County Projects Jodi Wheatley, I 35 Information Specialist, TxDOT John Jasek, PE, Waco Area Engineer, TxDOT Jacob Bell, PE, Project Manager,

More information

Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour

Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour www.peachpass.com NOVEMBER 2013 Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour In This Issue GA 400 Tolls End on November 22 Lanes Closures for GA 400/I-85

More information

FORT WORTH DISTRICT. Springtown Area Projects. Loyl C. Bussell, P.E. Acting District Engineer. Thursday, February 8, 2018 Date.

FORT WORTH DISTRICT. Springtown Area Projects. Loyl C. Bussell, P.E. Acting District Engineer. Thursday, February 8, 2018 Date. FORT WORTH DISTRICT Springtown Area Projects Loyl C. Bussell, P.E. Acting District Engineer Photo by Liam Frederick Footer Text Thursday, February 8, 2018 Date Maintaining a Safe System TxDOT is responsible

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop.

GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop. GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop. I-10 & Mesa Continuous Until further notice The right turn-only

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

IMPLEMENTATION OF COMPREHENSIVE DEVELOPMENT AGREEMENT (CDA) PROJECTS:

IMPLEMENTATION OF COMPREHENSIVE DEVELOPMENT AGREEMENT (CDA) PROJECTS: IMPLEMENTATION OF COMPREHENSIVE DEVELOPMENT AGREEMENT (CDA) PROJECTS: SH 130 Project, Segments 5 & 6, Travis, Caldwell and Guadalupe counties; DFW Connector, Tarrant County; North Tarrant Express (NTE),

More information

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018 FREDERICKSBURG DISTRICT District Engineer Marcie Parker, P.E. May 8, 2018 3 Interstate 95 Projects Fredericksburg Area Fredericksburg region will see greatest degree of I-95 construction since widening

More information

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE January 11, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-007 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

N O R T H T E X A S T O L L W A Y A U T H O R I T Y

N O R T H T E X A S T O L L W A Y A U T H O R I T Y N O R T H T E X A S T O L L W A Y A U T H O R I T Y On he Move NTTA Board Names New Interim Executive Director Current Assistant Executive Director of Project Delivery Gerry Carrigan Assumes New Post The

More information

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 21, 2017 CONTACT: Sandy Myers 540-332-9201 (office) STA17-204 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

AGENDA ITEM I-6 Public Works

AGENDA ITEM I-6 Public Works AGENDA ITEM I-6 Public Works STAFF REPORT City Council Meeting Date: 8/6/2018 Staff Report Number: 18-150-CC Informational Item: Update on the Willow Road and highway 101 interchange construction, upcoming

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 7, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 187 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

October 31, 2014 Chuck McGinness, (954)

October 31, 2014 Chuck McGinness, (954) From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October

More information

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell) RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)

More information

NDG-Westmount Neighbourhood Committee. November 16, 2015

NDG-Westmount Neighbourhood Committee. November 16, 2015 NDG-Westmount Neighbourhood Committee November 16, 2015 2 Feedback on previous questions Order-in-Council 890-2010 - condition 8 The ministère des Transports must : Establish a buffer zone at the foot

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road T 1800 997 057 (free call) E enquiries@northconnex.com.au PO Box 343 Pennant Hills NSW 1715 northconnex.com.au 28 April 2017 Ref: N0075M Night work update: and westbound on ramp at Dear resident, NorthConnex

More information

Important Lane Closures March 1 5, 2010

Important Lane Closures March 1 5, 2010 February 26, 2010 CONTACT: Marcia McAllister 703 572 0506 marcia.mcallister@dullesmetro.com Important Lane Closures March 1 5, 2010 C aisson Load Test Scheduled for Mar. 3 Crews will perform another load

More information

A VISION FOR I-95. January 12, Delaware Department of Transportation

A VISION FOR I-95. January 12, Delaware Department of Transportation A VISION FOR I-95 January 12, 2011 Delaware Department of Transportation The East Coast s Main Street Along with SR 1, the most significant highway in Delaware 29 miles to I ".', 2 Sponsoring / Cooperating

More information

INTERSTATE 35 CORRIDOR UPDATE

INTERSTATE 35 CORRIDOR UPDATE INTERSTATE 35 CORRIDOR UPDATE Transportation Commission Workshop July 27, 2016 I-35 Corridor Planning History Lauren D. Garduño, P.E. 2 I-35 Corridor Planning Previous Planning on I-35 1999,IH 35 Trade

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov A daytime lane closure on Mesa all week is needed to complete Sunday s demo

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

Capital Beltway HOT Lanes Project

Capital Beltway HOT Lanes Project New Travel Choices Ahead Some things can t wait for traffic Capital Beltway HOT Lanes Project Project Update August 16, 2011 Major Milestones Reached Some things can t wait for traffic Project over 75%

More information

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE

More information

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015 From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015

More information

Williamsburg Town Hall Meeting

Williamsburg Town Hall Meeting Williamsburg Town Hall Meeting DEVELOPMENT UPDATE ORANGE COUNTY PLANNING DIVISION November 30, 2017 1 AREA CONTEXT FUTURE LAND USE MAP MEADOW WOODS MEADOW WOODS GINN PROPERTY ZONING MEADOW WOODS MEADOW

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work

More information

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015 Northeast Anthony Henday Drive Edmonton Ring Road Update Strathcona Chamber of Commerce March 18, 2015 Project Background 2 Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest

More information

Weekly East Tennessee Construction Report for May 31-June 6, 2018

Weekly East Tennessee Construction Report for May 31-June 6, 2018 Weekly East Tennessee Construction Report for May 31-June 6, 2018 Thursday, May 31, 2018 01:30pm ANDERSON COUNTY, SR 62 between Union Valley Road and SR 162: Motorists should be alert for possible lane

More information

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Road Construction Ahead January-April 2015 NORTHWEST REGION

Road Construction Ahead January-April 2015 NORTHWEST REGION NORTHWEST REGION 1 Interstate 64 Augusta, Nelson, Albemarle counties: Installing communications conduit in median for active traffic management system on Afton Mountain. Periodic left-shoulder closures,

More information

First rail. August 2011

First rail. August 2011 August 2011 First rail A downtown resident showed his son in early August the first completed section of embedded track on Fourth Street in front of the Farmer s Market. During July, the Central Corridor

More information

5.1 Traffic and Transportation

5.1 Traffic and Transportation 5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the

More information

Mission Statement. Spur 601 Project Highlights

Mission Statement. Spur 601 Project Highlights Mission Statement SPUR 601 is a TxDOT project dedicated to provide a safe, efficient, reliable new corridor to improve the mobility in east-central El Paso. The SPUR 601 team is working in partnership

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane

More information

US 380 FEASIBILITY STUDY

US 380 FEASIBILITY STUDY US 380 FEASIBILITY STUDY Denton County CSJ(s): 0135-10-061, 0135-10-062 Public Meeting(s): January 15 & 22, 2019 WELCOME US 380 Denton County Feasibility Study DALLAS DISTRICT PUBLIC MEETING January 15

More information

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness, From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

Section 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps

Section 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps Section 106 Update Memo #1 Attachment D Traffic Diversion & APE Expansion Methodology & Maps I-65/I-70 North Split Interchange Reconstruction Project (Des. Nos. 1592385 & 1600808) Traffic Diversion and

More information

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 1, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 020 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

CDOT North I-25 Express Lanes Update April 28, 2016

CDOT North I-25 Express Lanes Update April 28, 2016 CDOT North I-25 Express Lanes Update April 28, 2016 Why Express Lanes? CDOT/HPTE new focus on: Increased choice in travel Increased mobility through operational improvements Reduce delay on most seriously

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Aug. 10, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT August 12 August 18, 2018 All

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth) RELEASE: IMMEDIATE March 8, 2019 CONTACT: Tina.Bundy 540-907-8325 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 10 March 16, 2019 All work is scheduled weather permitting. Real-time information

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

DULLES AREA HIGHLIGHTS. Gary Garczynski Commonwealth Transportation Board Northern Virginia District. Committee for Dulles August 4, 2016

DULLES AREA HIGHLIGHTS. Gary Garczynski Commonwealth Transportation Board Northern Virginia District. Committee for Dulles August 4, 2016 DULLES AREA HIGHLIGHTS Gary Garczynski Commonwealth Transportation Board Northern Virginia District Committee for Dulles August 4, 2016 Smart Scale (formerly HB2) Overview Round 1 completed with the adoption

More information

Possible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar

Possible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar Possible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar A construction truck drives along the newly paved westbound 60 freeway Lemon Avenue on-ramp in City of

More information

Appendix 4.1 L. No-Build Project Descriptions

Appendix 4.1 L. No-Build Project Descriptions Appendix 4.1 L No-Build Project Descriptions No-Build Projects New Bedford A new traffic signal system was installed and activated in early 2009 at the intersection of King s Highway and Mount Pleasant

More information

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 23, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 057 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

2 Construction Program

2 Construction Program 2018 C P 2018 Districtonstruction 2 Construction Program rogram district 2 Governor John Kasich ODOT Director Jerry Wray District Deputy Director Pat McColley, PE, SI 2018 Construction Program Thank you

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

Major Projects Overview

Major Projects Overview Major Projects Overview Miami-Dade Expressway Authority February 2018 About MDX MDX operates 5 roads in Miami Dade County SR 924, SR 112, SR 836, SR 874 and SR 878 MDX Primary Source of Revenue: User Fees-Tolls

More information

NORTH REGION RIGHT OF WAY SECTION RECOGNIZED FOR INNOVATION, TEAMWORK

NORTH REGION RIGHT OF WAY SECTION RECOGNIZED FOR INNOVATION, TEAMWORK October 2011 NORTH REGION RIGHT OF WAY SECTION RECOGNIZED FOR INNOVATION, TEAMWORK EMBRACING SOCIAL MEDIA @TXDOT PROTECTING OUR PAST A TXDOT PRIORITY HISTORY AND PROGRESS: THE ROBERTSON PLANTATION AND

More information

2017 Work and Launch of the Next Phase. Information meeting, Montréal-Ouest September 14, 2017

2017 Work and Launch of the Next Phase. Information meeting, Montréal-Ouest September 14, 2017 2017 Work and Launch of the Next Phase Information meeting, Montréal-Ouest September 14, 2017 2 Presentation Outline Work progress Launch of the next phase Mitigation measures Dismantling Communications

More information

JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS

JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS For Immediate Release January 2, 2018 Contact: Charles H. Pannunzio (424) 646-5260 JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS Access to Parking Structure 4 from the Upper/Departure

More information

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT CONTACT: VDOT Customer Service 1-800-367-7623 November 18, Richmondinfo@VDOT.virginia.gov WEEKLY HIGHWAY ALERT RICHMOND DISTRICT COLONIAL HEIGHTS Below is a forecast of road construction that is expected

More information

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All

More information

District Construction Progr am. John R. Kasich, Ohio Governor Jerry Wray, ODOT Director Steve Mary, P.E., District Deputy Director

District Construction Progr am. John R. Kasich, Ohio Governor Jerry Wray, ODOT Director Steve Mary, P.E., District Deputy Director District 8 2014 Construction Progr am Preble Greene Butler Warren Clinton Lebanon Hamilton Clermont Serving Butler, Clermont, Clinton, Greene, Hamilton, Preble and Warren Counties. John R. Kasich, Ohio

More information

Long water shutdown scheduled for Tuesday, September 18

Long water shutdown scheduled for Tuesday, September 18 Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility

More information

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 2, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-042 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Road widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected.

Road widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected. PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: SEPTEMBER 12, 2012 STATUS FOR SEPTEMBER 17, 2012 THROUGH SEPTEMBER 23, 2012 *** CONSTRUCTION WORK ZONES ADDED

More information

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK

More information

Work in 2015 and Annual Mobility- Management Plan

Work in 2015 and Annual Mobility- Management Plan Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector

More information

Summary of Transportation Development Credits (TDCs) Dallas-Fort Worth Metropolitan Planning Organization (MPO) (As of September 30, 2016)

Summary of Transportation Development Credits (TDCs) Dallas-Fort Worth Metropolitan Planning Organization (MPO) (As of September 30, 2016) ATTACHMENT 1 Summary of Transportation Development Credits (s) (MPO) Original Allocation of s to Dallas/Fort Worth MPO: 465,846,222 Award Type Amount Current Allocation in 2013 in 2014 in 2015 in 2016

More information

PRIORITIES COMMITTEE MEETING

PRIORITIES COMMITTEE MEETING PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony

More information

Concord Road Interchange. Standard hours of work

Concord Road Interchange. Standard hours of work Artist impression of the Concord Road interchange, Concord - concept only WestConnex s M4 East will extend the M4 Motorway with two new 5.5 kilometre tunnels from Homebush to Haberfield, providing a bypass

More information

Pre-Construction Public Meeting July 2017

Pre-Construction Public Meeting July 2017 Pre-Construction Public Meeting July 2017 Agenda Introduction to Project Team Project Description Schedule Impacts Communication/Public Outreach 2 Contractor Walsh Construction Design Team HDR Lead City

More information

US 19 Sunset Point Rd to Countryside Blvd.

US 19 Sunset Point Rd to Countryside Blvd. Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started

More information