SECTION DESCRPTIONS PAGE NOS.

Size: px
Start display at page:

Download "SECTION DESCRPTIONS PAGE NOS."

Transcription

1 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate SECTION DESCRPTIONS PAGE NOS. 1 Summary of Progress Critical Issues & Action Log Project Overview Physical Progress Strip Plan Land Acquisition & Clearance Change of Scope Mobilization of Resources Financial Project Details Monitoring of Operations & Maintenance Obligations Safety Features Detailed List of Physical Components as per Schedule G Monthly Progress Report - 72 (up to January 18) Page 1

2 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 1.1. Summary of Progress January, 18 The National Highways Authority of India (NHAI) has entered into concession Agreement with the Concessionaire, M/s Farakka-Raiganj Highways Limited for Four Laning of Farakka to Raiganj section of the NH 34, from Km to Km in the State of West Bengal. The total length of the project is Km from Km to Km with total cost of INR million. Project Appointed Date was 03 rd February 2011 and the initial scheduled date of completion of construction was 01 st August 2013 (with 910 days construction period). The Cumulative physical progress, as on 31 st January 2018, is 89.65%, against scheduled progress of 100%. Financial progress is 95.02% up to December Whereas total expenditure up to December 2017 is INR million, there is a delay of 1644 days of the Scheduled Four Lane Date till 31 st January According to the IE s assessment the Concessionaire is trailing behind their monthly financial expenditures for the month of January 2018 by Approx. Rs Crore. This gap is primarily due to shortage of resources and poor mobilization by the Concessionaire. Total progress achieved for the DBM layer, is nearly km (Four lane), with Km (Four lane) pending across the entire stretch. The Concessionaire has been given PCOD certificate on 19 th October 2016, for a length of Km. As per the recent revised work programme submitted by the Concessionaire, the completion of their balance Work, expected by 31 st March 2018.Now as per the present progress of the project Highway, the Concessionaire trailing behind for at about three to four month. There is a provision of 8.34 Km service road in the Concession Agreement. Land acquisitions have been totally completed but yet there are only Km of encroachments, not cleared within the ROW which affecting a length of 0.70 Km, both the development of 4 laning as well as utility shifting work. Now, Kms of the Project Highway is encumbrance free and available for construction. Monthly Progress Report - 72 (up to January 18) Page 2

3 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Current Issues & Recommended Actions by IE: 1. Slow Progress: The Progress of work is very slow as compared to revised work programme submitted, by the Concessionaire as well as available fronts. Recommendation: The Concessionaire must have to resume their Overall works with top geared efficiency and to lock the gradual slippage, from completing of the Project by 31 st March 2018, as scheduled, by the latest revised work programme. 2. Repair and Maintenance work in PCOD Stretch: The Progress of work is very slow as compared to schedule submitted by the Concessionaire for Final repair works for the severe pavement deformation work for a combination of stretches with an approximate cumulative length of about 10 km. Recommendation: The Concessionaire must have to increase their rate of progress of the works tremendously, to complete the maintenance work as scheduled by 31 st March On the Basis of Independent Engineer recommendation, damage charge issued to the Concessionaire as per the Provision of Article 17.8 of the Concession Agreement with affect from 05th May Monthly Progress Report - 72 (up to January 18) Page 3

4 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Scope available for Structural work at site, presently: A. Major Bridge : i) Km : (Deleted from Scope) ii) Km : (Completed) iii) Km : (Completed) iv) Km : (Completed) v) Km : (Completed) vi) Km : (Completed) vii) Km : (Completed) viii) Km : (Completed) B. Minor Bridge : i) Km : (Completed) ii) Km : (Completed) iii) Km : (Completed) iv) Km : (Completed) v) Km : (LHS Completed & RHS Work is in Progress) vi) Km : (Completed) vii) Km : (Completed) viii) Km : (Completed) ix) Km : (Completed) x) Km : (Completed) xi) Km : (Completed) xii) Km : (Completed) xiii) Km : (Completed) xiv) Km : (Completed) xv) Km : (Completed) xvi) Km : (Completed) xvii) Km : (Completed) xviii) Km : (Completed) xix) Km : (Completed) xx) Km : (Completed) xxi) Km : (Completed) xxii) Km : (Completed) C. Underpass: i) Km : (Completed) ii) Km : (Completed) iii) Km : (Completed) iv) Km : (Completed) Monthly Progress Report - 72 (up to January 18) Page 4

5 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate D. ROB : i) Km : (Super Structure work and obligatory span assembly and erection work is in Progress). E. Culverts: Total no. of Culverts are 89 Nos : (Totally completed (BHS) 82 nos. and construction activities are in progress for 7 nos. 3. Status of Change of Scope Proposals : Concessionaire has submitted 10 numbers of Change of Scope proposals and Change of scope order has been accorded for 01 no, principal approvals have been accorded for 03 no, 06 nos have been recommended by the IE which is pending at the Authority end. Total Amount pending for COS approval is Crore. The Independent Engineer has submitted 05 numbers proposals related to the Negative Change of Scope, to the Authority Critical Issues & Action Log Though initially, the slow rate of land acquisition had affected the overall progress of the Project to some extent, but at present the land acquisition for the Project Highway has totally been completed. The delay in utility shifting works of the Project Highway also being contributed to the delay of progress of the Project Highway to greater extent. In spite of 100% land acquisition being done, the Concessionaire s Progress is not up to the mark. If these have been properly exploited earlier, the Project could have been achieved the COD earlier. There are nothing pending with the IE, regarding source approvals and review of Design-Drawings and co-operated the Concessionaire to the best for the early completion of the Project Highway. Monthly Progress Report - 72 (up to January 18) Page 5

6 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Pending Issues & Action Log Sl No 1 Issue Description Non Available of Hindrance Free ROW Type Encroa chment Ongoing / New Issue/ Resolved Ongoing Concer ned Authori ty NHAI Chainage(s) affected due to the issue i) to (BHS) Length affected (km) 0.30 Km Action(s) taken till now 3D notification done by Authority. Actio n(s) sugge sted by the IE - - Expected date/ Actual Date for resolving issue 2 Utility Shifting Shifting of Electric pole Ongoing Conces sionaire i) to ii) to iii) to iv) to km Authority is having meeting with Administrati on on regular basis to resolve the issue Obligations as per Contract: Obligations and Constrains of the Concessionaire: Subject to and on the terms and conditions of the Concession Agreement, the Concessionaire shall, at it s own cost and expense, procure finance for and undertake the design engineering, procurement, construction, operation and maintenance of the Project Highway and observe, fulfill, comply with and perform all it s obligations as set out in the CA. Unfortunately, the Concessionaire s own lapse & latches, in acquiring the resources, due to inadequacy of funds, has greatly affected the scheduled completion of the project highway to a great extent. Monthly Progress Report - 72 (up to January 18) Page 6

7 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Obligations & Constrains of the Authority: At about 0.65 Km of encroachments are yet to be removed with the help of local Authority which is affecting the Project Highway at about 1.00 Km for Construction work Obligations of the Independent Engineer: The Independent Engineer has always discharged it s duties and functions substantially in accordance with the Terms of Reference. Various factors which were beyond the control of the IE have made IE s role difficult to maintain, but the IE fulfilled it s obligations. Monthly Progress Report - 72 (up to January 18) Page 7

8 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 1.3. Project Overview: Salient Features of Project: Four - Laning of Farakka-Raiganj Section of NH-34 from Km Project Name to Km in the state of West Bengal under NHDP Phase III on Design, Build, Finance, Operate and Transfer ( DBFOT ) Toll basis. NH No. (New/Old) NH-34 Scheme / Phase NHDP-III / BOT / WB / 04 Mode of Execution (BOT Toll/BOT Annuity/EPC/HAM/Item Rate/Others) ( DBFOT ) Toll Basis No of Lanes / Configuration Four Lane Length of the Project (in Km) Kms (Existing Road = Kms & Bypass Road =10.10 Kms) (From Km to ) Total Project Cost (In Cr) (Rupees One Thousand Seventy Eight Crore Eighty Four Lakh, As per CA) No of Bypasses (Name of town, Length) 01, (Malda Bypass, Km) 08, [Km {Deleted from Scope}, Km , Km , No of Major Bridges (Number and Km , Km , Km , Km & Km Location) ) No of Toll Plazas (Number and Location) 02, (Km , Km ) No of Fly Overs (Number and Location) Nil DPR Consultant Name Lead & Consortium Members of Banks Yes Bank Concessionaire Name (SPV & Parent Company) M/S Farakka - Raiganj Highways Limited Date of Award (LOA Date) Appointed Date 03 rd February 2011 Concession Period 30 Years (Including 910 days Construction Period) Construction Period (In Days) 910 days (30 Months) O&M Period (in Days) 03 Months (90 Days) Schedule date of Completion Independent Engineer M/s URS Scott Wilson India Private Limited in Association with Rodic Consultant Pvt. Ltd IE Agreement Date 12 th January 2012 IE Mobilization Date 08 th February 2012 Monthly Progress Report - 72 (up to January 18) Page 8

9 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Project Milestones Project Milestones Description (Days from Appointed Date) Planned Physical Scheduled Progress Date (%) Actual Physical Revised Progress Date (%) Delay (No. of months) Current Status Milestone I 180 th Day 10 % 1 st Aug % - No Delay No extension applied for by the Concessionaire and Achieved on 01 st Aug 2011 Milestone II 400 th Day 35% Milestone III 650 th Day 70% 9 th Mar th Nov % 31 st Oct days 70% 31 st Jan days Achieved Extended by the Authority up to (237 days) Ref. Authority Letter No /1/2013- FRHL/94, Achieved on 31 st January 2014 Extended by the Authority up to (625 days) Ref. Authority Letter No-62023/1/2013- FRHL/185, Project Completion 910 th Day 100% 01 st Aug % 22 nd Jan 2018 (As estimated) 1636 days Not Achieved Latest Recommendation of 1636 days (Up to 22 nd January 2018), which was forwarded to the Authority on dated 29 th December 2017 is pending for Approval. Monthly Progress Report - 72 (up to January 18) Page 9

10 Four Laning of Farakka-Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Location Map Monthly Progress Report - 72 (up to January 18) Page 10

11 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Key plan Monthly Progress Report - 72 (up to January 18) Page 11

12 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 1.4 Physical Progress Component % Weightage Physical Progress (During Current Month) Physical Progress (Cumulative up to Current Month) Road Works % % Structural Works % % Other works 9.20 % % Physical Progress 89.65% Monthly Progress Report - 72 (up to January 18) Page 12

13 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Detailed Scope of Work & Physical Progress by Component: Component Cost Weightage in Project Item Description Cost Weightage in Component (%) Planned in Scope (As per Scope of work) Progress Till Date % Physical Progress Value of Physical Progress (7 x 4) C & G Km Earthworks Km Road works 2. Structural works 3. Other Works 73.50% 17.30% 9.20% GRAND TOTAL 3. GSB Km WMM Km DBM Km BC Km Major Bridges Nos Minor Bridges Nos ROB No Underpasses Nos CD works Nos Toll Plaza Nos RE Wall Km Traffic Signage Km HTMS Km MCB Km Monthly Progress Report - 72 (up to January 18) Page 13

14 (Minor Bridge) (Slab Culvert) (Minor Bridge) (1x 3.20) M (2x 7.40) M (1x 3.70) M (2x 5.00) M (1x 4.50) M (1 x 3.00) M (1x 3.00) M (1x 4.50) M Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 1.5 Strip Plan Strip Plan (Details) FARAKKA RAIGANJ SECTION OF NH-34 (PACKAGE-4) Layer Chart For Kaliachak to Sujapur (up to 31st January 2018) Structural Length () Span Arrangement Location/Structure Type BC DBM - Top DBM-1st WMM -Top WMM - 1st GSB SUBGRADE EMBANKMENT C&G LHS CHAINAGE RHS C&G EMBANKMENT SUBGRADE GSB WMM - 1st WMM -Top DBM-1st DBM - Top BC LEGEND MNBR - CD - Monthly Progress Report - 72 (up to January 18) Page 14

15 (Minor Bridge) (Minor Bridge) (Major Bridge) (VUP) (VUP) (ROB) (Minor Bridge) (Minor Bridge) (3x 5.75) M (6x 5.00) M ((5 x 28) +(6x 48)) M (1 x 12.00) M (1 x 5.50) M (5 x 40.0) M (3 x 20.00) M ( 3 x 20.00) M Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate FARAKKA RAIGANJ SECTION OF NH-34 (PACKAGE-4) Layer Chart For Malda Bypass (up to 31st January 2018) Structural Length () Span Arrangement Location/Structure Type BC DBM - Top DBM-1st WMM -Top WMM - 1st GSB SUBGRADE EMBANKMENT C&G LHS CHAINAGE RHS C&G EMBANKMENT SUBGRADE GSB WMM - 1st WMM -Top DBM-1st DBM - Top BC LEGEND MJBR - MNBR - ROB CD - VUP - Monthly Progress Report - 72 (up to January 18) Page 15

16 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Strip Plan (Summary) 1. Work front Unavailable & Reason for Unavailability Length (Km) % Total Pending length 2.Length Completed by Layer (MCW) Length (Km) % Total length Total Length Nil Total Length Total Work front Unavailable Pending Land Acquisition Pending Clearance 0.70 (Due to nonremoval of Encroachm ent) 0.70 Total Length Completed (Till DBM) Length Completed by Layer (Service Road) Total Length Total Length Completed (Till DBM) Length (Km) %Total length BC SDBC DBM DBM Encumbrances WMM WMM GSB GSB Subgrade Subgrade C & G C & G Monthly Progress Report - 72 (up to January 18) Page 16

17 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 1.6 Land Acquisition and Clearances: LA Summary Description Total Required (Ha) Total in Possession at Start (Ha) Total to be acquired (Ha) Existing ROW Pvt. Land to be Acquired - Public Land to be Transferred Grand Total LA Details by CALA CALA CALA - 1 (Malda) CALA - 2 (Uttar Dinajpur) Total Land left to be Acquire d 3 H Pending (Ha) 3 H Done (Ha) 3 G Pending (Ha) 3 G Done (Ha) 3 D Pending (Ha) 3 D Done (Ha) 3 A Pending (Ha) 3 A Done (Ha) Amount Awarded (In Cr) up to October 2016 Amount Deposited (In Cr) up to October 2016 Amount Disbursed by CALA (In Cr) up to October Pending Amount (In Cr) Grand Total Monthly Progress Report - 72 (up to January 18) Page 17

18 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Clearance Summary Environment Proposal Description Status Length Impacted Current Stage Issues/Comments Forest Land Proposal Description Status Length Impacted Current Stage Issues/Comments Wildlife Proposal Description Status Length /Chainage Current Stage Issues/Comments Tree Cutting Proposal Description Status Length /Chainage Current Stage Issues/Comments Completed Railways (ROBs / RUBs) GAD Number Status Length /Chainage Current Stage Issues/Comments NH-34-BRG-ROB-001_1 Approved Work is in Progress - Monthly Progress Report - 72 (up to January 18) Page 18

19 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Utility Cate gory Status of Utilities shifting Name Status Length Affected Department Date of Request ed by Authori ty for estimate Date when Estimate was Received from concerned dept. Date of Approval by Authority RO/HQ Date of Deposit of supervision charge Progress of Physical Shifting Date of Certification from Agency for Completion Estimate Amount (INR Cr.) Issue / Comme nts Electricity Electric Line (Malda Division) Electric Line (Uttar Dinajpur Division) In Progres s Compl eted 1.00 Km ( to , to Km ( to , to ) WBSEDCL % % Water pipeline Water pipeline (Malda Water Supply Division and Arsenic Division) Relocation of pipe line of Itahar Water supply under Raiganj division In Progres s In Progres s 2.10 Km ( to ) PHE % PHE Tree Cutting Tree Cutting Compl eted N/A WB Forest % Monthly Progress Report - 72 (up to January 18) Page 19

20 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate S No Change of Scope (Positive) Proposal Details Construction of VUP including Service road and RE wall At Aradhpur Km Date of 1 st Submission to IE Current Status COS Amount (Lacs) 25 th- Nov-13 Approved Construction of VUP at Km th -Dec-13 Approved Construction of Two nos of Culvert At Km & rd -Apr-14 Approved Construction of Two nos of Culvert At Km & rd -Apr-14 Approved Expected/Actual Date of Approval Approved from NHAI-HQ on dated and Advanced payment released on Approved by NHAI/62023/1/2015- FRHL/191/1504 Dated , 5 Malda Bypass Re-alignment 13 th -Feb-13 Not Approved th Sep-15 Not Approved th Feb 17 Not Approved th Jan 17 Not Approved st Feb 17 Not Approved Not Approved Monthly Progress Report - 72 (up to January 18) Page 20

21 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 1 2 Four Laning of Farakka Barrage on extended piers. Stage Construction Approval of tentative cost of difference in Pavement Composition (as per Appendix-BI of Schedule-B of C.A visà-vis actually provided by the Concessionaire) None Kaliachak Bypass Re-alignment Tentative costs submitted vide our letter no. IE-1311 Dt Tentative costs submitted vide our letter no. IE-631 Dt NHAI-HQ give in-principle approval vide letter no. NHAI/BOT/WB/NH-34/2009/PQ-04/418/42889 dated Submitted to NHAI-HQ on Pending at NHAI-HQ NHAI-HQ give in-principle approval vide letter no. NHAI/BOT/WB/NH-34/2009/PQ-04/418/48679 dated The documents for the final approval have been submitted to NHAI-HQ on Pending at NHAI-HQ. 4 Reduction in Scope, related to the conversion of Well Foundation to Pile Foundation in the Mahananda Bridge, made by the Concessionaire, in the Project Highway Tentative costs submitted vide our letter no. IE-1343 Dt Submitted to NHAI-HQ on Pending at NHAI-HQ 5 Reduction in Scope, No. 1, related to the Deviations in the Horizontal and Vertical Alignment made by the Concessionaire in the Project Highway Tentative costs submitted vide our letter no. IE-1330 Dt Submitted to NHAI-HQ on Pending at NHAI-HQ Monthly Progress Report - 72 (up to January 18) Page 21

22 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate S No 1.8 Mobilization of Resources (As per Concessionaire) Equipment Name Make Mod el Age of Equipment Planned/ Required Quantity Actual Quantity Deployed During the Month 1 Excavator CK 90 CK Motor Grader 140/ Vibratory Compactor Ton Reason(s) for Under/Over Mobilization Expected Delay due to Under Mobilization (Months) 4 Crawler Dozer D6H Water Tanker Ltr 6 Front End Loader 1.7 Cum Crushing Plant 300 TPH WMM Plant 160 TPH HMP Plant 160 TPH Bitumen Sprayer 8KL WMM Sensor Paver DBM Sensor Paver Tractor Dozer Tandem Vibratory Roller 8-10 MT Pneumatic tyre Roller 20 MT Tractor Compressor Mechanical Broom Kerb Laying Machine Kerb Cutting Machine Hyva Tipper Weigh Bridge Flat bed trailer 20 Ton Hydra 10 Ton Hydraulic mounted 30 Ton crane 25 JCB 3D & 5D Remarks Monthly Progress Report - 72 (up to January 18) Page 22

23 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 26 Pavement Breaker Crawler Crane 75 Ton Mobile Placer Boom Cum/Hr Stationary Concrete Pump Cum/Hr 30 Batching Plant Bar Bending Machine Bar Cutting Machine Flat Bed truck Diesel Compressor 300 CFM Transit Mixer 6 Cum Laboratory Equipment Set Diesel Browser Diesel Dewatering Pump Explosive Van Total Station Theodolite & Auto Level Mini Tandem roller Welding Generator/Transformer Concrete Vibrator Water Supply Pump Concrete Bucket KVA DG Set KVA DG Set KVA DG Set KVA DG SET Monthly Progress Report - 72 (up to January 18) Page 23

24 Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate 1.9 Financial Progress Details Pen Picture Escrow TPC (Cr) Cumulative Inflow to escrow till previous month (Cr) Cumulative outflow from Escrow till previous month (Cr) Inflow to Escrow during the month (Cr) Outflow from Escrow during the month (Cr) Are the Escrow withdrawals in accordance with the order of withdrawal as specified in the Concession Agreement? Tick as applicable Yes No If not, details to be provided below: Monthly Progress Report - 72 (up to January 18) Page 24

25 CUMULATIVE PERCENTAGE Four Laning of Farakka Raiganj Section of NH -34 from Km to Km in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate Escrow Details TPC (Cr) Cumulative exp. Till date (Cr) Escrow Plan till date Debt (BOT) (Cr) Escrow Plan till date-equity (BOT) (Cr) Escrow Plan till date VGF (BOT) (Cr) Escrow Actual till date Debt (BOT) (Cr) Escrow Actual till date-equity (BOT) (Cr) Escrow Actual till date VGF (BOT) (Cr) Note: The escrow details has not Submitted by the Concessionaire Financial Progress (Rs Crore) S Curve: Up to Dec-11Up to Dec-12Up to Dec-13Up to Dec-14Up to Dec-15Up to Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 % Program % Program-2 1 %program-3 1 % Progress Note: These financial progress related data are not verified by us. Monthly Progress Report - 72 (up to January 18) Page 25

SECTION DESCRPTIONS PAGE NOS.

SECTION DESCRPTIONS PAGE NOS. Four Laning of Farakka Raiganj Section of NH -34 from Km 295.00 to Km 398.00 in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate SECTION DESCRPTIONS PAGE NOS. 1 Summary

More information

SECTION DESCRPTIONS PAGE NOS.

SECTION DESCRPTIONS PAGE NOS. Four Laning of Farakka Raiganj Section of NH -34 from Km 295.00 to Km 398.00 in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate SECTION DESCRPTIONS PAGE NOS. 1 Summary

More information

SECTION DESCRPTIONS PAGE NOS.

SECTION DESCRPTIONS PAGE NOS. Four Laning of Farakka Raiganj Section of NH -34 from Km 295.00 to Km 398.00 in the State of West Bengal under NHDP phase III on Design, Build, Finance, Operate SECTION DESCRPTIONS PAGE NOS. 1 Summary

More information

Road Network in India, Public Private Partnership Financing & Case Study Narendra Sharma, SE(PPP), MoRT&H

Road Network in India, Public Private Partnership Financing & Case Study Narendra Sharma, SE(PPP), MoRT&H Road Network in India, Public Private Partnership Financing & Case Study 20.04.2018 Narendra Sharma, SE(PPP), MoRT&H Functions of Ministry of Road Transport and Highways, Govt. of India Formulation of

More information

Article 13, clause no of the Concession Agreement states that:

Article 13, clause no of the Concession Agreement states that: BACKGROUND Article 13, clause no. 13.2 of the Concession Agreement states that: 13.2 Inspection During the Construction Period the Independent Engineer shall inspect the Project Highway at least once a

More information

L&T WESTERN ANDHRA TOLLWAYS LTD (A SUBSIDIARY OF L&T IDPL)

L&T WESTERN ANDHRA TOLLWAYS LTD (A SUBSIDIARY OF L&T IDPL) National Highways Authority of India (Ministry of Shipping, Road Transport & Highways) 4 Laning of the Existing 2 Lane Section from Km. 80.050 (Jadcherla) to Km. 135.740 (end of Kothakota Bypass) On NH-44

More information

Development of Road Infrastructure in India

Development of Road Infrastructure in India Development of Road Infrastructure in India By Nirmal Jit Singh Director General (Road Development & Special Secretary) Ministry of Road Transport & Highways Road Network in India Total Road Length about

More information

January 2018 Air Traffic Activity Summary

January 2018 Air Traffic Activity Summary January 2018 Air Traffic Activity Summary Jan-2018 Jan-2017 CY-2018 CY-2017 Passengers 528,947 505,421 4.7% 528,947 505,421 4.7% Passengers 537,332 515,787 4.2% 537,332 515,787 4.2% Passengers 1,066,279

More information

NATIONAL HIGHWAYS AUTHORITY OF INDIA

NATIONAL HIGHWAYS AUTHORITY OF INDIA NATIONAL HIGHWAYS AUTHORITY OF INDIA (Ministry of Shipping, Road transport & Highways) Department of Road Transport & Highways Two lanning with paved shoulder of Khagaria Purnea Section of NH 31 from Km

More information

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited Gatwick Airport Limited Response to Airports Commission Consultation Appendix 37 Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Further information

More information

Alternatives Study of Alignment

Alternatives Study of Alignment Project: 4-lanning of Barhi Rajauli Section of NH-31 Sheet: 1 of 6 Alternatives Study of Alignment 1 Objectives The following objectives were kept in view while locating the alternative bypass alignments:

More information

MINUTES OF PROJECT REVIEW MEETING HELD ON

MINUTES OF PROJECT REVIEW MEETING HELD ON MINUTES OF PROJECT REVIEW MEETING HELD ON 4 th July 2016 1 The project review meeting started at 2.30 pm on 4 th July 2016 at the H.O of with the Managing Director of Shri A P M Mohammed Hanish IAS in

More information

Monitorable Targets & Milestones for INFRASTRUCTURE SECTOR : Planning Commission, Government of India

Monitorable Targets & Milestones for INFRASTRUCTURE SECTOR : Planning Commission, Government of India Page 1 of 1 S.No. Name of the Scheme Actual 2009-10 Expenditure in 2010-11 (Cumulative) (Rs. In Crores) Grand Total 2010-11 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1 CSI Airport Mumbai Target 570.00 982.00 1645.00

More information

DETAIL OF THE PROJECT

DETAIL OF THE PROJECT Page 1 Page 2 DETAIL OF THE PROJECT A CONTRACT DETAILS Project State Operation & Maintenance Phase of 4 Lane dual carriageway from Km 50.000 to Km. 100.000 of NH 6 (Kondhali Talegaon Section ) in the State

More information

CAA NZ CAR 121 Subpart K 30-Oct-2017 CAR 125 Subpart K 30-Oct-2017 CAR 135 Subpart K 30-Oct-2017 AC Oct-2006 AC Aug-2011 Fatigue of

CAA NZ CAR 121 Subpart K 30-Oct-2017 CAR 125 Subpart K 30-Oct-2017 CAR 135 Subpart K 30-Oct-2017 AC Oct-2006 AC Aug-2011 Fatigue of CAA NZ CAR 121 Subpart K 30-Oct-2017 CAR 125 Subpart K 30-Oct-2017 CAR 135 Subpart K 30-Oct-2017 AC 119-2 27-Oct-2006 AC 119-3 12-Aug-2011 Fatigue of Flight Crew Table of Contents DESCRIPTION...5 A Part

More information

NATIONAL HIGHWAYS AUTHORITY OF INDIA

NATIONAL HIGHWAYS AUTHORITY OF INDIA NATIONAL HIGHWAYS AUTHORITY OF INDIA (Ministry of Road Transport & Highways) of 4-lane divided carriageway facility of Tambaram Tindivanam Section of NH-45 (Km 28/ to 2/), Tindivanam to Ulundurpet Section

More information

Indiabulls Real Estate Limited (CIN : L45101DL2006PLC148314)

Indiabulls Real Estate Limited (CIN : L45101DL2006PLC148314) Indiabulls Real Estate Limited (CIN : L45101DL2006PLC148314) Earnings Update Audited Financial Results FY 2013-14 April 23, 2014 Safe Harbor Statement This document contains certain forward looking statements

More information

INVITATION FOR TENDERS BOSNIA AND HERZEGOVINA. CONSTRUCTION OF MOTORWAY ON CORRIDOR Vc, SECTION POČITELJ - BIJAČA, SUBSECTION POČITELJ - ZVIROVIĆI

INVITATION FOR TENDERS BOSNIA AND HERZEGOVINA. CONSTRUCTION OF MOTORWAY ON CORRIDOR Vc, SECTION POČITELJ - BIJAČA, SUBSECTION POČITELJ - ZVIROVIĆI INVITATION FOR TENDERS BOSNIA AND HERZEGOVINA CONSTRUCTION OF MOTORWAY ON CORRIDOR Vc, SECTION POČITELJ - BIJAČA, SUBSECTION POČITELJ - ZVIROVIĆI No: JPAC 841-B80-17 This Invitation for Tenders is published

More information

The presentation has been prepared for information purpose, it is not a solicitation of any offer to buy or sell any security or instruments.

The presentation has been prepared for information purpose, it is not a solicitation of any offer to buy or sell any security or instruments. Disclaimer The presentation has been prepared for information purpose, it is not a solicitation of any offer to buy or sell any security or instruments. This presentation contains forward-looking statements.

More information

Aircraft Maintenance Organisations - Certification. Contents

Aircraft Maintenance Organisations - Certification. Contents Contents Rule objective... 3 Extent of consultation... 3 New Zealand Transport Strategy... 4 Summary of submissions... 5 Examination of submissions... 6 Insertion of Amendments... 6 Effective date of rule...

More information

PPP Days 2010 PPPs Lessons from the Last 18 Months

PPP Days 2010 PPPs Lessons from the Last 18 Months PPP Days 2010 PPPs Lessons from the Last 18 Months Rajiv B Lall March 22, 2010 1 Private Sector Participation (PSP) in India Works & Services Contracts Management Contracts Operation Concessions Build

More information

MORMUGAO PORT TRUST ENGINEERING MECHANICAL DEPARTMENT

MORMUGAO PORT TRUST ENGINEERING MECHANICAL DEPARTMENT An ISO 9001 : 2008 Port ISPS CODE Compliant MORMUGAO PORT TRUST ENGINEERING MECHANICAL DEPARTMENT TENDER No:- CME/PD/X /2017. TENDER FOR VALUATION OF THE FLOATING DRY DOCK AND OTHER INFRASTRUCTURE SET

More information

CERTIFICATE OF AIRWORTHINESS ISSUE

CERTIFICATE OF AIRWORTHINESS ISSUE AIRWORTHINESS Civil Aviation Authority of Botswana ADVISORY CIRCULAR CAAB Document AAC-007 CERTIFICATE OF AIRWORTHINESS ISSUE AAC-007 Revision: Original March 2013 Page 1 of 13 Intentionally left blank

More information

Implementation Status & Results Mozambique Roads and Bridges Management and Maintenance Program - Phase II (P083325)

Implementation Status & Results Mozambique Roads and Bridges Management and Maintenance Program - Phase II (P083325) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Mozambique Roads and Bridges Management and Maintenance Program

More information

G.O.Ms.No.142 Dated:

G.O.Ms.No.142 Dated: Abstract Tourism - Promotion of Tourism- Government of India Assisted Scheme - 2010-2011- Development of Pilgrimage Heritage Circuit (Madurai-Rameswaram- Kanniyakumari) in Tamil Nadu under Mega Tourism

More information

Roadside Assistance and Concierge Services Terms and Conditions

Roadside Assistance and Concierge Services Terms and Conditions Roadside Assistance and Concierge Services Terms and Conditions We welcome you to enjoy the Road Assistance and Concierge services provided by IMC. We request you to go through the Terms and Conditions

More information

GOVERNMENT OF INDIA AERONAUTICAL INFORMATION SERVICES DIRECTOR GENERAL OF CIVIL AVIATION OPPOSITE SAFDARJUNG AIRPORT NEW DELHI

GOVERNMENT OF INDIA AERONAUTICAL INFORMATION SERVICES DIRECTOR GENERAL OF CIVIL AVIATION OPPOSITE SAFDARJUNG AIRPORT NEW DELHI Telephone No. : 24622495 Telegraphic Address: Commercial : AIRCIVIL NEW DELHI Aeronautical : VIDDYAYX E Mail: dri @ dgca.delhnic.in Fax : 91 11 2469 2374 GOVERNMENT OF INDIA AERONAUTICAL INFORMATION SERVICES

More information

IMPLEMENTATION OF COMPREHENSIVE DEVELOPMENT AGREEMENT (CDA) PROJECTS:

IMPLEMENTATION OF COMPREHENSIVE DEVELOPMENT AGREEMENT (CDA) PROJECTS: IMPLEMENTATION OF COMPREHENSIVE DEVELOPMENT AGREEMENT (CDA) PROJECTS: SH 130 Project, Segments 5 & 6, Travis, Caldwell and Guadalupe counties; DFW Connector, Tarrant County; North Tarrant Express (NTE),

More information

4. The Council s LTCCP decision on 30 June 2009 confirmed the extended tram route and funding.

4. The Council s LTCCP decision on 30 June 2009 confirmed the extended tram route and funding. 145 11. TRAM EXTENSION PROJECT PROPOSED PARKING CHANGES AND STREET MODIFICATIONS IN LICHFIELD STREET, MANCHESTER STREET, HIGH STREET, TUAM STREET, ASH STREET, BEDFORD ROW AND OXFORD TERRACE General Manager

More information

Environmental Assessment. Application

Environmental Assessment. Application Environmental Assessment Application For A Proposal To Enhance the Tourism Potential On The Burin Peninsula By Creating a Multi-use Ecotourist Trail Loop That Will Be Linked to the Newfoundland T Railway

More information

gives the requirements and rated or, a basic competent

gives the requirements and rated or, a basic competent GOVERNMENT OF INDIA OFFICE OF DIRECTOR GENERAL OF CIVIL AVIATION TECHNICAL CENTRE, OPP SAFDARJANG AIRPORT, NEW DELHI CIVIL AVIATION REQUIREMENTS SECTION 2, AIRWORTHINESS SERIES `L' PART XVI ISSUE I, 1

More information

Provincial Railway Technical Standards

Provincial Railway Technical Standards GENERAL: INDEX: The standards and requirements listed in this document are intended for use on provincially regulated railway public grade crossings. These standards are considered the minimum requirements

More information

Manual vs. Automatic Operation and Operational Restrictions

Manual vs. Automatic Operation and Operational Restrictions Customer Services, Operations, and Safety Committee Board Information Item IV-B March 11, 2010 Manual vs. Automatic Operation and Operational Restrictions Page 81 of 91 Washington Metropolitan Area Transit

More information

WORKS AND SERVICES COMMITTEE MEETING HELD ON WEDNESDAY 20 MAY 2015 AT MEMORIAL HALL SUPPER ROOM, ESPLANADE, KAIKOURA. AGENDA

WORKS AND SERVICES COMMITTEE MEETING HELD ON WEDNESDAY 20 MAY 2015 AT MEMORIAL HALL SUPPER ROOM, ESPLANADE, KAIKOURA. AGENDA WORKS AND SERVICES COMMITTEE MEETING HELD ON WEDNESDAY 20 MAY 2015 AT MEMORIAL HALL SUPPER ROOM,, KAIKOURA. AGENDA 1. Apologies 2. Matters of Importance to be raised as Urgent Business. 3. Reports: Operations

More information

SUMMARY OF UNAPPROVED COMMON PROPERTY AND FOREST COMMITTEE MINUTES. August 4, 2014

SUMMARY OF UNAPPROVED COMMON PROPERTY AND FOREST COMMITTEE MINUTES. August 4, 2014 SUMMARY OF UNAPPROVED COMMON PROPERTY AND FOREST COMMITTEE MINUTES August 4, 2014 Board Liaison Comments Mike Medica New Business: 6-2 Barcelona Request to check beetle and dying trees Joe Burleigh completed

More information

Part 145. Aircraft Maintenance Organisations Certification. CAA Consolidation. 10 March Published by the Civil Aviation Authority of New Zealand

Part 145. Aircraft Maintenance Organisations Certification. CAA Consolidation. 10 March Published by the Civil Aviation Authority of New Zealand Part 145 CAA Consolidation 10 March 2017 Aircraft Maintenance Organisations Certification Published by the Civil Aviation Authority of New Zealand DESCRIPTION Part 145 prescribes rules governing the certification

More information

Administration and Projects Committee Meeting STAFF REPORT July 3, 2014 Page 2 of 2 Agreement Consultant Project General Scope CT 107 URS Corporation

Administration and Projects Committee Meeting STAFF REPORT July 3, 2014 Page 2 of 2 Agreement Consultant Project General Scope CT 107 URS Corporation Administration and Projects Committee Meeting STAFF REPORT Meeting Date: July 3, 2014 Subject Summary of Issues Recommendations Authorize s to Various Agreements Over the years, the Authority has contracted

More information

Traffic data submitted by various domestic airlines has been analysed for the month of October Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of October Following are the salient features: 0.0 0.0 Pax Load Factor (%) 64.5 58.5 79.0 71.8 79.9 75.5 77.5 71.0 73.7 70.7 72.7 69.2 93.5 91.9 89.4 84.4 82.1 84.9 82.8 78.3 75.6 75.8 Pax Carried (in Lakhs) Subject: Performance of domestic airlines

More information

AUGUST 2008 MONTHLY PASSENGER AND CARGO STATISTICS

AUGUST 2008 MONTHLY PASSENGER AND CARGO STATISTICS Inter-Office Memo Reno-Tahoe Airport Authority Date: October 2, 2008 To: Statistics Recipients From: Tom Medland, Director Air Service Business Development Subject: RENO-TAHOE INTERNATIONAL AIRPORT PASSENGER

More information

Performance monitoring report for 2014/15

Performance monitoring report for 2014/15 Performance monitoring report for 20/15 Date of issue: August 2015 Gatwick Airport Limited Summary Gatwick Airport is performing well for passengers and airlines, and in many aspects is ahead of the performance

More information

N25 New Ross Bypass PPP Project

N25 New Ross Bypass PPP Project Presentation to TII National Roads Conference 2017 29 th September 2017 N25 New Ross Bypass PPP Project History & Construction Progress Joe Shinkwin & Pierre O Loughlin Presentation Content 1. Project

More information

Traffic data submitted by various domestic airlines has been analysed for the month of Nov2014. Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of Nov2014. Following are the salient features: Subject: Performance of domestic airlines for the year 2014. Traffic data submitted by various domestic airlines has been analysed for the month of Nov2014. Following are the salient features: Passenger

More information

Traffic data submitted by various domestic airlines has been analysed for the month of Dec Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of Dec Following are the salient features: Subject: Performance of domestic airlines for the year 2014. Traffic data submitted by various domestic airlines has been analysed for the month of Dec 2014. Following are the salient features: Passenger

More information

PRELIMINARY ACCOUNTS FOR 2012

PRELIMINARY ACCOUNTS FOR 2012 INTERIM REPORT FOR Q4 2012 AND INTERIM REPORT FOR Q4 2012 AND PRELIMINARY ACCOUNTS FOR 2012 HIGHLIGHTS Q4 with growth in volume and improved normalized EBITDA MNOK 261 improvement in normalized EBITDA

More information

Traffic data submitted by various domestic airlines has been analysed for the month of November Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of November Following are the salient features: Pax Load Factor (%) 58.5 71.8 75.1 75.5 80.4 71.0 74.7 70.7 74.1 78.3 69.2 74.4 68.0 75.8 81.2 91.9 92.5 84.4 87.3 84.9 88.0 86.9 Pax Carried (in Lakhs) Subject: Performance of domestic airlines for the

More information

Traffic data submitted by various domestic airlines has been analysed for the month of May Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of May Following are the salient features: Pax Load Factor (%) 35.0 26.0 32.1 48.7 75.1 75.1 84.0 81.3 85.6 80.4 84.4 80.2 89.5 89.2 95.5 94.8 91.9 91.0 87.5 89.7 88.8 85.7 80.0 82.7 Pax Carried (in Lakhs) Subject: Performance of domestic airlines

More information

Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379)

Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Operation Name: Djibouti Power Access and

More information

Subject: Performance of domestic airlines for the year 2015.

Subject: Performance of domestic airlines for the year 2015. Subject: Performance of domestic airlines for the year 2015. Traffic data submitted by various domestic airlines has been analysed for the month of September 2015. Following are the salient features: Passenger

More information

Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379)

Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Operation Name: Djibouti Power Access and

More information

OFFSHORE WIND ENERGY. Dr. Rajesh Katyal Director General Additional Charge Group Head Wind Resource Assessment & Offshore

OFFSHORE WIND ENERGY. Dr. Rajesh Katyal Director General Additional Charge Group Head Wind Resource Assessment & Offshore OFFSHORE WIND ENERGY Dr. Rajesh Katyal Director General Additional Charge Group Head Wind Resource Assessment & Offshore Higher generation Surfaces of seas are generally smooth. Low Roughness less turbulent

More information

Hampton Roads Express Lane Network

Hampton Roads Express Lane Network More Choices For Travelers Hampton Roads Express Lane Network James Utterback, PMP Hampton Roads District Administrator Presented to HRTPO Board July 20, 2017 Regional Express Lane Network 2 History of

More information

No /2003-VAS Dated the 11th Nov., SUB: GUIDELINES FOR UNIFIED ACCESS(BASIC & CELLULAR) SERVICES LICENCE.

No /2003-VAS Dated the 11th Nov., SUB: GUIDELINES FOR UNIFIED ACCESS(BASIC & CELLULAR) SERVICES LICENCE. Government of India Ministry of Communications and Information Technology Department of Telecommunications Sanchar Bhawan, 20 Ashoka Road, New Delhi-110 001. No.808-26/2003-VAS Dated the 11th Nov., 2003.

More information

STAR CRUISES SUPER STAR LIBRA 01 NIGHT CRUISE

STAR CRUISES SUPER STAR LIBRA 01 NIGHT CRUISE STAR CRUISES SUPER STAR LIBRA EX PENANG: SUPERSTAR LIBRA Sailing: 01 December, 2016 30 December, 2017 Duration: 1 NIGHT CRUISE SUN - THU 01 NIGHT CRUISE 1 Nt. Regular Cruise (Sun Thu Dep) DAY 1 Penang

More information

Subject: Performance of domestic airlines for the year 2015.

Subject: Performance of domestic airlines for the year 2015. Subject: Performance of domestic airlines for the year 2015. Traffic data submitted by various domestic airlines has been analysed for the month of October 2015. Following are the salient features: Passenger

More information

N11 Arklow / Rathnew & N7 Newlands Cross PPP Contract. Kieran Kelly

N11 Arklow / Rathnew & N7 Newlands Cross PPP Contract. Kieran Kelly N11 Arklow / Rathnew & N7 Newlands Cross PPP Contract Kieran Kelly N7/N11 PPP CONTRACT - OVERVIEW Section A N11 Arklow/Rathnew Scheme Section B Upgrade Works on Existing M11 (Arklow Bypass & Arklow to

More information

Hossana Solomon PhD; Henry H. Smith PhD University of the Virgin Islands (UVI)

Hossana Solomon PhD; Henry H. Smith PhD University of the Virgin Islands (UVI) Effectiveness of Mandatory Law of Cistern Construction for Rainwater Harvesting on Supply and Demand of Public Water in U.S. Virgin Islands Hossana Solomon PhD; Henry H. Smith PhD University of the Virgin

More information

Traffic data submitted by various domestic airlines has been analysed for the month of Mar Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of Mar Following are the salient features: Pax Load Factor (%) 29.3 26.0 53.1 77.0 72.4 70.4 68.0 86.7 83.6 90.4 86.2 90.3 87.1 90.4 88.0 96.3 95.0 91.8 89.0 88.0 82.0 91.2 88.2 84.2 (in Lakhs) Subject: Performance of domestic airlines for the

More information

Traffic data submitted by various domestic airlines has been analysed for the month of May Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of May Following are the salient features: Pax Load Factor (%) 78.7 80.9 82.8 85.3 83.3 84.3 74.6 80.3 93.4 94.3 84.7 93.0 86.9 91.1 90.1 89.4 83.6 86.8 80.2 80.1 Pax Carried (in Lakhs) Subject: Performance of domestic airlines for the year 2017.

More information

Traffic data submitted by various domestic airlines has been analysed for the month of Sept Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of Sept Following are the salient features: Subject: Performance of domestic airlines for the year 2017. Traffic data submitted by various domestic airlines has been analysed for the month of Sept 2017. Following are the salient features: Passenger

More information

TM COMPRESSOR, ROTARY: AIR DIESEL ENGINE DRIVEN; 250 CFM ORGANIZATIONAL, DS, GS, AND DEPOT MAINTENANCE MANUAL

TM COMPRESSOR, ROTARY: AIR DIESEL ENGINE DRIVEN; 250 CFM ORGANIZATIONAL, DS, GS, AND DEPOT MAINTENANCE MANUAL TM 5-4310-250-15 DEPARTMENT OF THE ARMY TECHNICAL MANUAL ORGANIZATIONAL, DS, GS, AND DEPOT MAINTENANCE MANUAL COMPRESSOR, ROTARY: AIR DIESEL ENGINE DRIVEN; 250 CFM 100 PSI; SKID MOUNTED (DAVEY FSN MODEL

More information

SmartCity (Kochi) Infrastructure Private Limited SEZ

SmartCity (Kochi) Infrastructure Private Limited SEZ SmartCity (Kochi) Infrastructure Private Limited SEZ 15th MEETING (1/2016) OF APPROVAL COMMITTEE DATE: 17-02-2016 Venue: Conference Hall CSEZ Administrative Office, Kakkanad, Kochi- 682 037 Agenda for

More information

October 2013 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport

October 2013 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport October 2013 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport December 4, 2013 U.S. DOMESTIC INDUSTRY OVERVIEW FOR OCTOBER 2013 All RNO Carriers Systemwide year over year comparison

More information

WHEN IS THE NEXT SHIPPING BOOM?

WHEN IS THE NEXT SHIPPING BOOM? WHEN IS THE NEXT SHIPPING BOOM? By Ravi K Mehrotra CBE Executive Chairman Foresight Group, London Samunder Club April & May 2012 Houston and Florida, USA 1 WHEN IS THE NEXT SHIPPING BOOM? I am not a fortune

More information

SUB:CSWIP3.1/3.2.2/PAINTING INSPECTION COURSES &EXAM DETAILS

SUB:CSWIP3.1/3.2.2/PAINTING INSPECTION COURSES &EXAM DETAILS 1 SUB:CSWIP3.1/3.2.2/PAINTING INSPECTION COURSES &EXAM DETAILS This refers to your enquiry by mail details of requirements of CSWIP 3.1/3.2.2, B.GAS Course and Examination details are given below, please

More information

CIVIL AVIATION PUBLICATION CAP 00 GENERAL

CIVIL AVIATION PUBLICATION CAP 00 GENERAL CAP 00 GENERAL FOREWORD REVISION STATUS & LEP This Page Intentionally Left Blank FOREWORD Civil Aviation Publications (CAPs) are issued under the authority granted to the Director General by Decree. The

More information

PROPINSIGHT A Detailed Property Analysis Report

PROPINSIGHT A Detailed Property Analysis Report PROPINSIGHT A Detailed Property Analysis Report 40,000+ Projects 10,000+ Builders 1,200+ Localities Report Created On - 7 Oct, 2015 Price Insight This section aims to show the detailed price of a project

More information

Item # 28. Chief Capital Management Officer Report. November 20, 2008

Item # 28. Chief Capital Management Officer Report. November 20, 2008 Item # 28 Chief Capital Management Officer Report November 20, 2008 1 Metro Gold Line Eastside Extension Project Update November 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground)

More information

ST. EUSTATIUS. Sea Arrivals ( Summer ( Winter Yacht Arrivals 11, % 32.1%

ST. EUSTATIUS. Sea Arrivals ( Summer ( Winter Yacht Arrivals 11, % 32.1% ST. EUSTATIUS TOURISM HIGHLIGHTS FOR 2007 VISITOR ARRIVALS Tourist Arrivals I ( Summer* ( Winter* 11,568 67.9% 32.1% Sea Arrivals ( Summer ( Winter Yacht Arrivals 5,858 48.5% 51.5% 707 ACCOMMODATION STATISTICS

More information

ST. EUSTATIUS. Sea Arrivals II ( Summer ( Winter Yacht Arrivals I 12, % 32.5%

ST. EUSTATIUS. Sea Arrivals II ( Summer ( Winter Yacht Arrivals I 12, % 32.5% ST. EUSTATIUS Visitor Arrival Summary Tourist Arrivals (excluding Antilleans) to St. Eustatius increased by 2.5 percent to reach a total of 12.0 thousand in 2009. Holland continues to be the most important

More information

ATM Network Performance Report

ATM Network Performance Report ATM Network Performance Report 2018. Page 1 of 16 Table of contents Summary... 3 Network Wide Performance... 4 Airborne delay... 4 Sydney... 6 Airborne delay... 6 Notable events... 6 Melbourne... 9 Airborne

More information

Traffic data submitted by various domestic airlines has been analysed for the month of Oct Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of Oct Following are the salient features: Subject: Performance of domestic airlines for the year 2014. Traffic data submitted by various domestic airlines has been analysed for the month of Oct 2014. Following are the salient features: Passenger

More information

BINBIRRI CONTRACTING PTY LTD CAPABILITY STATEMENT 2016

BINBIRRI CONTRACTING PTY LTD CAPABILITY STATEMENT 2016 BINBIRRI CONTRACTING PTY LTD CAPABILITY STATEMENT 2016 P: 08 91722341 E: binbirricontracting@hotmail.com ABN: 42 151 996 913 PO Box 2233 South Hedland WA 6722 Binbirri Contracting was established in 2010

More information

Traffic data submitted by various domestic airlines has been analysed for the month of Mar Following are the salient features:

Traffic data submitted by various domestic airlines has been analysed for the month of Mar Following are the salient features: Subject: Performance of domestic airlines for the year 2015. Traffic data submitted by various domestic airlines has been analysed for the month of Mar 2015. Following are the salient features: Passenger

More information

REPUBLIC OF INDONESIA MINISTRY OF TRANSPORATIONS DIRECTORATE GENERAL OF CIVIL AVIATION JAKARTA INDONESIA

REPUBLIC OF INDONESIA MINISTRY OF TRANSPORATIONS DIRECTORATE GENERAL OF CIVIL AVIATION JAKARTA INDONESIA LAMPIRAN KEPUTUSAN DIREKTUR JENDERAL PERHUBUNGAN UDARA NOMOR : KP 060 Tahun 2018 TANGGAL : 6 Maret 2018 STAFF INSTRUCTION SI 8900 3.329 Maintenance Records System Evaluations Amendment : 0 Date : 6 REPUBLIC

More information

ISSUE ASSESSMENT PAPER

ISSUE ASSESSMENT PAPER ISSUE ASSESSMENT PAPER Date of Assessment Meeting: 22 September 2014 08-ISS-44, 07-ISS-51, 07-ISS-43: Various Fatigue Issues Issue Description (8/ISS/44 as submitted by petition on 29/10/2007 by WilsonB)

More information

Delhi Airport Metro Express A Case of Public Private Partnership Project

Delhi Airport Metro Express A Case of Public Private Partnership Project 1 Delhi Airport Metro Express A Case of Public Private Partnership Project Surya Raj Acharya, PhD Visiting Professor Institute of Engineering, Tribhuvan University, Kathmandu 20 Feb 2017 Contents 2 1.

More information

NEPTUNE AIR SDN. BHD. ( D) B AIRCRAFT SPECIFICATION

NEPTUNE AIR SDN. BHD. ( D) B AIRCRAFT SPECIFICATION AIRCRAFT IDENTIFICATION MANUFACTURER : THE BOEING COMPANY AIRCRAFT TYPE : B727-277 22641 DATE OF MANUFACTURE : 11/Jun/1981 LINE NUMBER : 1753 VARIABLE NUMBER : QD043 BASIC NUMBER : - SELCAL : BM-GK FREIGHTER

More information

Terms of Reference: Introduction

Terms of Reference: Introduction Terms of Reference: Assessment of airport-airline engagement on the appropriate scope, design and cost of new runway capacity; and Support in analysing technical responses to the Government s draft NPS

More information

AGREEMENT APPOINTING [NAME OF AGENT] AS THE AGENT OF THE UK HOLIDAY GROUP LIMITED ATOL 5024 PURSUANT TO ATOL REGULATIONS 12 AND 22

AGREEMENT APPOINTING [NAME OF AGENT] AS THE AGENT OF THE UK HOLIDAY GROUP LIMITED ATOL 5024 PURSUANT TO ATOL REGULATIONS 12 AND 22 AGREEMENT APPOINTING [NAME OF AGENT] AS THE AGENT OF THE UK HOLIDAY GROUP LIMITED ATOL 5024 PURSUANT TO ATOL REGULATIONS 12 AND 22 THIS AGREEMENT is made the day of 20 BETWEEN (1) The UK Holiday Group

More information

CWC LA - Cash Balance (January 2012)

CWC LA - Cash Balance (January 2012) CWC LA - Cash Balance 2012-13 (January 2012) 1,200,000 Cash Balance 1,000,000 800,000 ($1,000s) 600,000 400,000 200,000 - CWC LA - Actuals/Projected CWC LA - ed (Nov) 1 1 CWC Hollywood - Financial Dashboard

More information

Network Size and Growth

Network Size and Growth 16.50 25.10 30.30 11.40 5.10 9.63 10.00 8.26 64.94 km 208.24 Overview Network Size and Growth At present, metro systems are operational in seven cities in India Bengaluru, Chennai, Delhi, Gurgaon, Jaipur,

More information

(each the Supplier or, in respect of a Licensable Transaction, the Principal ATOL holder ); and

(each the Supplier or, in respect of a Licensable Transaction, the Principal ATOL holder ); and AGREEMENT BETWEEN ALL AGENTS AND SERENITY HOLIDAYS LTD/ATOL NUMBER 1866 APPOINTING ALL AGENTS AS A SERENITY HOLIDAYS LTD AGENT (PURSUANT TO ATOL REGULATIONS 12 AND 22 BETWEEN (1) Serenity Holidays Limited,

More information

Meeting held at FCC Environment Offices Thursday 12 th March 2015

Meeting held at FCC Environment Offices Thursday 12 th March 2015 Calvert Landfill Liaison Committee Meeting held at FCC Environment Offices Thursday 12 th March 2015 Present: Ms A Macpherson (chair) Ms J Phipps Mr S Essam Mr P Gaskin Ms R Bellamy Ms S D Amon Mr R Webster

More information

Air Operator Certification

Air Operator Certification Civil Aviation Rules Part 119, Amendment 15 Docket 8/CAR/1 Contents Rule objective... 4 Extent of consultation Safety Management project... 4 Summary of submissions... 5 Extent of consultation Maintenance

More information

25 th Avenue Grade Separation. September 13, 2017

25 th Avenue Grade Separation. September 13, 2017 25 th Avenue Grade Separation September 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25

More information

PROPINSIGHT A Detailed Property Analysis Report

PROPINSIGHT A Detailed Property Analysis Report PROPINSIGHT A Detailed Property Analysis Report 40,000+ Projects 10,000+ Builders 1,200+ Localities Report Created On - 7 Oct, 2015 Price Insight This section aims to show the detailed price of a project

More information

AGREEMENT BETWEEN... AND SHEARINGS HOLIDAYS LIMITED/1666 APPOINTING... AS SHEARINGS HOLIDAYS AGENT PURSUANT TO ATOL REGULATIONS 12 AND 22

AGREEMENT BETWEEN... AND SHEARINGS HOLIDAYS LIMITED/1666 APPOINTING... AS SHEARINGS HOLIDAYS AGENT PURSUANT TO ATOL REGULATIONS 12 AND 22 AGREEMENT BETWEEN... AND SHEARINGS HOLIDAYS LIMITED/1666 APPOINTING... AS SHEARINGS HOLIDAYS AGENT PURSUANT TO ATOL REGULATIONS 12 AND 22 THIS AGREEMENT is made the... day of...2012 BETWEEN (1) Shearings

More information

P/01REV. Accountability and Performance Report of the ICAO NACC Regional Office to Member States. Nassau, Bahamas, May 2016

P/01REV. Accountability and Performance Report of the ICAO NACC Regional Office to Member States. Nassau, Bahamas, May 2016 P/01REV Accountability and Performance Report of the ICAO NACC Regional Office to Member States Nassau, Bahamas, May 2016 NACC Overview and NCLB Status Background and Status of NACC NCLB Strategy Implementation

More information

Implementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466)

Implementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466) Operation Name: CO Integrated Mass Transit

More information

DETERMINATION OF MERGER NOTIFICATION M/18/34 - BIG BUS TOURS (EXPONENT) / IRISH CITY TOURS

DETERMINATION OF MERGER NOTIFICATION M/18/34 - BIG BUS TOURS (EXPONENT) / IRISH CITY TOURS DETERMINATION OF MERGER NOTIFICATION M/18/34 - BIG BUS TOURS (EXPONENT) / IRISH CITY TOURS Section 21 of the Competition Act 2002 Proposed acquisition by Big Bus Tours Limited, through Big Bus Tours Ireland

More information

GEN 3. SERVICES GEN AERONAUTICAL INFORMATION SERVICES

GEN 3. SERVICES GEN AERONAUTICAL INFORMATION SERVICES GEN 3.1-1 1. RESPONSIBLE SERVICE GEN 3. SERVICES GEN 3.1 - AERONAUTICAL INFORMATION SERVICES 1.1 The object of the aeronautical information service (AIS) is to ensure the flow of aeronautical data and

More information

Golden Ocean Group Limited Q results March 1, 2007

Golden Ocean Group Limited Q results March 1, 2007 Golden Ocean Group Limited Q4 2006 results March 1, 2007 PROFIT & LOSS 2005 2006 (in thousands of $) 2006 2005 Oct-Dec Oct-Dec Jan - Dec Jan - Dec Operating Revenues 37 292 91 253 Time charter revenues

More information

Implementation Status & Results Mexico MX Urban Transport Transformation Progr (P107159)

Implementation Status & Results Mexico MX Urban Transport Transformation Progr (P107159) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Mexico MX Urban Transport Transformation Progr (P107159) Operation

More information

PROPINSIGHT A Detailed Property Analysis Report

PROPINSIGHT A Detailed Property Analysis Report PROPINSIGHT A Detailed Property Analysis Report 40,000+ Projects 10,000+ Builders 1,200+ Localities Report Created On - 17 Aug, 2016 Price Insight This section aims to show the detailed price of a project

More information

PROPINSIGHT A Detailed Property Analysis Report

PROPINSIGHT A Detailed Property Analysis Report PROPINSIGHT A Detailed Property Analysis Report 40,000+ Projects 10,000+ Builders 1,200+ Localities Report Created On - 7 Oct, 2015 Price Insight This section aims to show the detailed price of a project

More information

Supreme Court records, (bulk , )

Supreme Court records, (bulk , ) Supreme Court records, 1793 1974 (bulk 1847 1862, 1870 1966) Ontario County Records and Archives Center Overview of the Records: Creator: Ontario County Court Clerk Extent: 48 volumes, 8 indexes, 25.53

More information

Report to the Strategic Development Committee. Ronald Reagan Washington National Airport Project Journey. June 2018

Report to the Strategic Development Committee. Ronald Reagan Washington National Airport Project Journey. June 2018 Report to the Strategic Development Committee Ronald Reagan Washington National Airport Project Journey June 2018 Secure National Hall Secure National Hall Project Cost Summary Prior Month Expenditures

More information

2017/2018 Q3 Performance Measures Report. Revised March 22, 2018 Average Daily Boardings Comparison Chart, Page 11 Q3 Boardings figures revised

2017/2018 Q3 Performance Measures Report. Revised March 22, 2018 Average Daily Boardings Comparison Chart, Page 11 Q3 Boardings figures revised 2017/2018 Q3 Performance Measures Report Revised March 22, 2018 Average Daily Boardings Comparison Chart, Page 11 Q3 Boardings figures revised Contents Ridership & Revenue... 1 Historical Revenue & Ridership...

More information

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs)

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs) OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs) Part 66 AIRCRAFT MAINTENANCE PERSONNEL LICENSING AND AUTHORISATION Published by Air Safety Support International Ltd Air Safety Support International

More information

September 2013 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport

September 2013 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport September 2013 Passenger and Cargo Traffic Statistics Reno-Tahoe International Airport October 31, 2013 U.S. DOMESTIC INDUSTRY OVERVIEW FOR SEPTEMBER 2013 All RNO Carriers Systemwide year over year comparison

More information