1 Getting ready for the new runway: Alberta Airspace and Services Project progresses Calgary International Airport Authority s massive $2 billion redevelopment program is well underway. The ambitious project involves an expanded international terminal facility and a new 14,000 ft parallel runway with associated taxiways and a new central de-icing facility. The work to make the necessary airspace changes and re-design arrival and departure flows at the airport is keeping pace and will be complete in time for opening day in May In fact, the project is being implemented in phases and some changes will take place in advance of the runway opening in order to ensure a smooth transition. On June 27, 2013 the dimensions of Calgary Terminal Control Area (TCA) will be reduced to 30 nm from 35. New VNC and VTA charts published on this date will reflect the amended boundaries. Also in June, changes will be made to arrival waypoints south of the airport as well as the introduction of new RNAV STARs to enable better balancing for an eventual parallel runway operation. At the same time, conventional STARs from the south will be revoked. In late 2013, changes will be made to arrival waypoints and STARs north of the airport. In May 2014, when the new runway opens, new STARS will be published to the new runway and corresponding track modifications and arrival waypoint crossing altitude changes will be made to existing STARS as required to change from crossing runway operations to parallel runway operations. The changes represent an overall modernization of the air navigation system in central and southern Alberta. With the new parallel runway being built at Calgary and the planned closure of Edmonton City Centre Airport, the time was right to transform and update the airspace, en route Continued on Page SPRING 2013 Alberta Airspace and Services Project progresses NAV CANADA brings enhancements to CAP and RCAP President s Point of View NAV CANADA releases 2013 update on GHG reduction measures Fuel-saving projects continue for trans-atlantic flights Pilot s Corner: Which Way is North? Domestic implementation of CPDLC continues 1

2 Getting ready for the new runway... (cont. from pg. 1) airway and approach and departure paths in the region, said Bob Fiege, Manager ACC Operations, Edmonton. The redesign will utilize RNAV and PBN principles to achieve improved efficiency for air operations. New RNAV routes and STARs to Edmonton International will also be developed and published as part of the AASP modernization program. Collaborative design process Collaboration with air carriers, airports and air traffic controllers to develop final procedure designs and discuss issues such as taxiing procedures and the designation of preferential runways for noise purposes has been ongoing. Information, including draft CAP plates will be shared with customers and stakeholders on an iterative basis as they become available in a variety of collaborative and advisory forums. Simulation and modelling is an important part of the design process, said Dave Mastel, General Manager, Edmonton FlR. Simulation tools give us metrics on time in system, runway throughput, fuel burn, and other important measures. It allows all parties to have a common understanding of the impacts of various options and gives you essential information on which you can base decisions. By using both airspace and aircraft flight simulators we can test and tweak our procedures to ensure the new system is as efficient as possible both in terms of fly-ability and controllability. Infrastructure The infrastructure changes at Calgary require more than new approach and departure procedures to the new runway. A new control tower and a new Advanced Surface Movement Guidance and Control System, which integrates surface multilateration, have also been put in place. Two new CAT III instrument landing systems will be installed later this year. Air traffic controllers moved into the new tower this spring. The tallest control tower in Canada and equipped with the latest NAVCANatm technologies, the new facility provides an eye level view from the cab of 270 feet AGL, giving controllers improved views of the new parallel runway and expanded operating areas. The new control tower at Calgary International New tower opens NAV CANADA Air Traffic Controllers are now handling flights at the Edmonton International Airport from the new air traffic control tower located atop the Airport Terminal Building and a new nine story office building. NAV CANADA made the seamless transition from the old Tower to the new facility on March 9. Controllers are delivering services with more modern consoles, from a cab that is four metres taller and with 50 percent more floor space than its 40 year-old predecessor. The new facility equipped with the latest NAVCANatm technologies will be able to respond to anticipated traffic growth and our customers safety and efficiency requirements for years to come, says Larry Lachance, Vice President Operations. 2

3 NAV CANADA brings enhancements to CAP and RCAP NAV CANADA s Aeronautical Information Services (AIS) will be modernizing the format of the Canada Air Pilot (CAP) and Restricted Canada Air Pilot (RCAP) publications, starting in summer The initiative will bring several improvements, including the introduction of constant descent angle depictions and restructured communication blocks. The result of this initiative will be aeronautical products with increased consistency, compliance and overall usability, says Chuck Montgomery, Director, AIS. The types of charts affected by these changes include: Approach Charts Helicopter Cat II and III Procedures Circling Visual Approach Combined IAP Arrival (STAR) RNAV Departure (SID) Aerodrome Constant Descent Angle Approach A key change, the depiction of Constant Descent Angles on non-precision approach charts, will make it easier for pilots to understand and employ the optimum path to be followed. From a human factors perspective, this is very beneficial, says Montgomery. The depiction contributes to pilot situational awareness and helps reduce workload when completing stabilized descents. Constant Descent Angle also reduces the probability of infringement on required obstacle clearance during the final approach segment and reduces noise levels by minimizing the level flight time at higher thrust settings. That improves fuel efficiency compared to a traditional step-down approach. Consultation and Communication A significant amount of consultation took place over the past two years regarding these changes. President s Point of View After almost 16 years as President and CEO one would think that there would be few surprises left in the job of managing Canada s ANS. For instance, I m happy to say that NAV CANADA employees continue to impress me with their commitment to safety, dedication to their colleagues and communities and the ingenuity with which they approach challenges. No surprise there. Making a safe system even safer is the focus of every day, every shift. Whether someone s job is designing instrument approaches, maintaining navigational aids, testing operational software, providing air traffic services to pilots, or one of the many other jobs at NAV CANADA, everyone comes to work understanding the important public trust we hold for the safety of the system. That dedication shows in the company s strong safety culture, open dialogue on safety issues, and collaborative approach to everything we do. Consultation consisted of a combination of formal stakeholder communication and forum presentations. Some modifications were made based on feedback received at these meetings. We also heard that there was an appetite for additional materials that describe the changes, says Montgomery. As such, NAV CANADA, in partnership with the Canadian Council for Aviation and Aerospace, developed detailed information to help customers understand upcoming changes. These materials can be found at under CAP and RCAP. Changes will be published in late But it is NAV CANADA s employees sense of community that in recent times has really stood out for me the deep level of dedication and the surprising variety of causes our people support, in their own neighbourhoods and across the globe. Whether it is a fundraiser for a local, national or international charity, or coming to the aid of a colleague experiencing personal difficulties, NAV CANADA employees step up, donating their time, money and uncanny ability to solve whatever problem confronts them. They have held golf tournaments, bike races, bake sales, raffles and food drives. They have pulled planes, cleaned parks and rivers, sponsored sports teams and choirs, and bought trees to offset our carbon emissions. And they have sponsored hospitals, raised money for cancer treatment and research, and provided hope to the sick, to those living in poverty and to victims of natural disaster. Wherever there is a person or a community in need, NAV CANADA people are there to help. This is a source of inspiration and constant surprise, which easily makes my job the best in the country. 3

4 NAV CANADA releases 2013 update on GHG reduction measures On May 13, NAV CANADA released its annual report on Collaborative Initiatives for Emission Reductions (CIFER). The report details progress in efforts to reduce aviation-related greenhouse gas (GHG) emissions through improvements to air traffic management, or the adoption of new technologies or procedures. The report outlines projects forecast to contribute to fuel savings of $7.4 billion and GHG emission reductions of 21 million tonnes between 1997 and The report details how existing collaborative initiatives between NAV CANADA and its customers continue to deliver significant efficiency benefits, while new initiatives coming on stream, such as the expansion of ADS-B surveillance via Low Earth Orbiting (LEO) Satellites, will further improve opportunities for efficiencies. The increased use of Performance Based Navigation, improvements in airspace utilization and the expansion of surveillance and communications are key factors in our ability to deliver even greater benefits for our customers and for the environment, said Rudy Kellar, Executive Vice President, Service Delivery. This is where the focus of our efforts will be in the coming years. I am constantly inspired by the initiatives that come forward from our innovative and dedicated staff, said John Crichton, President & CEO. Working with our customers and other industry partners, NAV CANADA staff have made real progress on reducing the environmental impact of aviation through more efficient air navigation services. View the CIFER report at cifer. Customer Fuel Savings Fuel-saving projects continue for trans-atlantic flights The second phase of the ENGAGE Demonstration Project is well underway with encouraging results. ENGAGE II is a collaborative initiative to reduce aircraft fuel burn and greenhouse gas (GHG) emissions in the North Atlantic airspace. NAV CANADA is leading ENGAGE II in partnership with Air France and NATS, the United Kingdom s air navigation service provider. ENGAGE II flight trials began in October 2012 and are expected to continue into the summer of The project is sponsored by the SESAR Joint Undertaking (SJU) as part of its Atlantic Interoperability Initiative to Reduce Emissions (AIRE) Program and builds on the positive outcomes demonstrated during the ENGAGE I trials executed in We are pleased to announce that the project is ahead of schedule, said Larry Lachance, Vice President, Operations. As of the end of April, we have already reached our target of 100 completed trials a four-fold increase from the entire first phase. Some 25 trial flights were conducted as part of ENGAGE I. Lachance said the project will nevertheless continue to the end of May. As the number of completed trials increases, the data we collect improves, he said. The collaboration with our customers and North Atlantic ANSP counterparts has expanded; the participation of Isavia and NAV Portugal has extended the oceanic region eligible for ENGAGE flights. This has been instrumental in helping us increase the frequency and the number of successful trials, said Lachance referring to the support of the Reykjavik Area Control Centre and the Oceanic Control Centre in Santa Maria. A total of five air carriers have been participating in ENGAGE II; Air France, Delta, British Airways, United and beginning in April KLM. ENGAGE is a perfect environment to get the full benefit of level optimization, especially combined with variable speed mode instead of fixed Mach, said Joost Können, Senior Manager Strategy & Charges, KLM Flight Operations. KLM is using an advanced wind update system for direct weather input in the Flight Management Computer (FMC). This enables the crews to use the output of the FMC advisories for inflight optimization. Continued on Page 6 4

5 Which Way is North? By Anthony MacKay, Manager, Flight Operations Note: This article is part of a recurring feature called Pilot s Corner by NAV CANADA s Manager of Flight Operations Anthony MacKay. When I learned how to fly and did my first cross country, simple math was required to convert true bearings on maps to a final magnetic heading: draw the true track on the VNC, assess the true wind to determine true heading to make good the true track, and add or subtract the magnetic variation to convert the true heading to a magnetic heading to set course in the aircraft. It was very simple in an analogue aircraft using a magnetic compass. As I progressed into larger aircraft over the course of my career, I was no longer concerned with drawing lines on VNCs as the lines were drawn for me on my IFR charts. The aircraft had magnetic stabilized Attitude Heading Reference Systems (ARHS) and, as a result, the amount of math decreased. As I progressed onto even larger aircraft with inertial reference units (IRU) and flight management systems (FMS), I became even less concerned with the true to magnetic conversions as it was all done within the magic of the navigation boxes on the aircraft. In the RNAV era however, magnetic variation on even the most complex aircraft has revived discussions in the flight deck about why displayed tracks on the flight management system are not the same as what NAV CANADA has published on the maps. This has become even more of a problem with the increased use of digital data, as there are numerous sources of magnetic variation and for any given location and point in space, they may not all match. Why this happens All IRU/FMS complete their internal calculations with reference to TRUE North. After the track calculations are complete, the navigation systems reference their internal magnetic variation table to provide a magnetic track. These tables are imported into the IRU or FMS by the unit manufacturer and each could be slightly different from the other. Older systems may not have the latest magnetic variation tables in them. Magnetic variation tables are generated as EPOCHs based on five year intervals (1995, 2000, 2005, 2010, 2015 etc.). Continued on Page 7 Domestic implementation of CPDLC continues NAV CANADA continues to make significant progress in implementing domestic Controller-Pilot Data Link Communications (CPDLC), with service now available in six Flight Information Regions (FIRs) and the remaining FIR going operational this fall. CPDLC which allows for the exchange of text-based digital messages between the cockpit and control centres delivers customer service enhancements, by relieving frequency congestion, reducing potential communications errors and contributing to efficient customer operations. CPDLC has been in use in Gander s Oceanic airspace for more than a decade, says Rudy Kellar, Executive Vice President, Service Delivery. With the national implementation of CPDLC the largest domestic roll out in the world to date appropriately equipped aircraft have another option to communicate efficiently and accurately with air traffic controllers. Continued on Page 8 5

6 Fuel-saving projects continue for trans-atlantic flights (cont. from pg. 4) The flexibility provided by ENGAGE gives us the opportunity to use the FMC to optimize the vertical flight profile during oceanic crossings. To date the results have matched the successes demonstrated in ENGAGE I. Based on the data compiled thus far, air carriers are saving an average of almost $500 per flight with an accompanying reduction of 1,300 kilograms of GHG emissions. ENGAGE flight trials test the viability of two concepts on North Atlantic operations: progressive or continuous altitude change; and, corresponding changes in aircraft speed (Mach) in place of the more traditional single speed, single altitude flight profile over the Ocean. As a flight transits the ocean, fuel is consumed and the weight of the aircraft decreases, resulting in the most efficient flight level becoming higher (assuming zero wind). Therefore, an efficient flight profile may include a progressive or continuous altitude change and/or change in Mach. In addition to the increased flight trials and the expanded region of the North Atlantic, the demonstration flights also permit the collection of data necessary to support the future implementation of the procedures after the trials have concluded. TOPFLIGHT NAV CANADA is also a key participant in another SJU project for trans-atlantic flights. The TOPFLIGHT project is being led by NATS whose goals are to develop, demonstrate (via flight trials) and transition to operations an airline-driven concept for the gate-to-gate optimisation of flights between North America and Europe. Phase one of TOPFLIGHT will see 60 trans-atlantic flights where a number of factors of the trip from pushback time, climb and descent profiles, routing and oceanic flight profile will be optimized to achieve minimal emissions and delay. The flights will take place between Heathrow and a number of North American airports beginning in May The second phase of the project will then look to introduce multiple perfect flights crossing the Atlantic simultaneously. The aim is to prove that the concept is scalable and can be implemented for many flights at the same time without penalizing those in the surrounding airspace. In addition to NAV CANADA, Boeing, Airbus ProSky and Barco Orthogon will also play key roles in the project. 6

7 Which Way is North? (cont. from pg. 5) If your IRU was installed in 1999, it may have had the 2000 EPOCH magnetic variation table installed. If that was the case, your magnetic variation would be 13 years out of date. As for AHRS units, they generally use a magnetic sense input from flux valves located somewhere on the aircraft so they are subject to changes in the earth s magnetic field which are more pronounced at high latitudes. Sources of magnetic variation Magnetic variation on the aircraft comes from either the IRU (if used instead of AHRS) or the FMS. While the EPOCH in the IRU is generally set, the Magnetic Variation Tables in the FMS database are further divided into two sources: 1. The EPOCH loaded into the core FMS for general use. 2. The magnetic variation supplied in the Navigation Database for each procedure. The magnetic variation in the Navigation Database is further broken down into individual elements dependant on the procedure to be flown and the magnetic variation source specified to be used by the FMS manufacturer and the ARINC 424 record for the procedure. These values are modified when changes are loaded into your FMS on the standard 28 day AIRAC cycle. These elements are: 1. airport magnetic variation 2. VOR declination 3. procedure design magnetic variation as designated by the procedure designer. Each of the 23 ARINC 424 legs then pulls the magnetic variation value assigned to it based on the ARINC 424 standard as adopted by the specific FMS manufacturer. When the FMS uses a different source of magnetic variation than the procedure designer used, or, the FMS is using an outdated magnetic variation table, the FMS or GPS will show a discrepancy between the published track on the IFR chart and the track displayed on the FMS or GPS. Because of these multiple sources, leg disconnects can occur and the displayed value may be different. Most issues are seen with CF and FA leg types associated with the VOR station declination and HM, HF and HA legs used in holds which typically use the airport magnetic variation value. However, the true tracks underlying the procedures are the same for all the leg types other than those mentioned above. The FMS/GPS is navigating by waypoints based on latitude and longitude and for that reason when a FMS/GPS is navigating on an airway, the true track over the ground is always the same, even if the displayed magnetic value on the FMS/GPS is different than published. Examples of FMS MAG VAR Functions: 1) Departing CYQH to CYXY with the following flight plan: CYQH YQH V326 YXY CYXY CYQH has a Magnetic Variation of 22 E assigned YQH VOR has a declination of 21 E assigned Waypoint CANYO has a magnetic variation assigned from the FMS internal table YXY VOR has a declination of 23 E assigned CYXY has a Magnetic Variation of 25 E assigned As the LO Chart above shows, V 326 has an outbound radial of 261 from YQH and this is displayed on the initial leg of the FMS from YQH. After leaving CYQH, 24 miles into the flight, the track on the FMS changes to the 260R and this will continue to be updated as the FMS Magnetic Variation table assess the aircraft position all the way to CANYO. CANYO is only 82 DME from YXY yet its track is displayed as 258 which is 4 degrees different than the published 074 radial from YXY. This is because CANYO is assigned a Magnetic Variation value from the FMS Magnetic Variation Table not the declination of the closest VOR. 41 miles from CANYO the track is now displayed as 259 degrees and this indicated track change will continue after CANYO all the way to Whitehorse where the track will eventually indicate 254 to match up with the 074R to Whitehorse. Throughout the flight the aircraft maintained the correct track (great circle route) over the ground between YQH and YXY. Magnetic variation differences can cause havoc in modern aircraft with varied sources and uses within the system. When we flight check the procedures with reference to TRUE North, we never see alignment issues, however, when working in magnetic, it can be a little more challenging. While the above example relates to the en route portion of the flight, the same issues also occur with approach procedures. Each aircraft heading source and FMS/ GPS installation is a little different. If you see discrepancies in tracks, you need to first understand how your system is processing magnetic variation. If you have IRUs, which EPOCH is your IRU using? Was it updated with the latest 2010 or 2015 data? These are all issues that need to be understood for each AHRS, IRU, FMS, GPS aircraft installation when operating in airspace with reference to magnetic tracks. 7

8 Domestic implementation of CPDLC continues (cont. from pg. 5) The 34,000-Foot Text A typical conversation conducted via text message between a pilot and an air traffic controller. Pilot 1. A download link is a message coming from a plane to air traffic control. TIME DOWNLOAD LINK MESSAGE 19:14 D/L Request climb to FL340 due to aircraft performance 2. The pilot requests allowing the plane to climb to an altitude of 34,000 feet above sea level. The plane performs more efficiently at higher altitudes and can go higher as it gets lighter through burning of the jet fuel. 3. Air traffic control grants permission for the climb in an upload link to the plane. U/L Standby Climb to and maintain FL340 Control Analysing Usage NAV CANADA, in collaboration with customers, is examining opportunities to ensure that communications via CPDLC are as efficient as they can be. This includes analysis of downlink and uplink counts to establish communications patterns, as well as response patterns at various time intervals. The analysis covers everything from the time required to receive and respond to a data link message, to response habits if an exchange is pilot-initiated versus controllerinitiated, says Crawley. This helps provide a yardstick into the customer service experience, and tells us how pilots are managing these communications against other tasks that are taking place in the cockpit. With this analysis, NAV CANADA and its partners will hope to identify opportunities to enhance performance on both ends of the message interface. Pilot D/L WILCO 4. The pilot responds that she will comply. Future Opportunities CPDLC delivers several clear benefits on its own. But when combined with other ANS technologies, it presents even greater opportunities to deliver benefits to customers. CPDLC, now in use in the Vancouver, Edmonton, Winnipeg, Montreal, Moncton and Gander Flight Information Regions above Flight Level 290, helps reduce frequency congestion by decreasing the need for voice communications, enhances safety and efficiency by using standardized messages and reducing the likelihood of read-back and hear-back errors. Overall, the more we can do to allow our controllers to focus on managing the traffic with accurate communications, the better they will be at providing the highest level of service, said Kellar. Phased Approach The capability was phased-in in three stages in each of the six centres currently using it and will be implemented in the same manner at the Toronto ACC, says Bill Crawley, Director, ATS System Integration. The first phase supported downlink of pilot requests for speed and altitude changes, with ATC acknowledging receipt via text and continuing to provide clearances via voice. Phase two supported the uplink of frequency assignments for voice communications and the third phase implemented the issuance of altitude, speed and route clearances via CPDLC. This allowed controllers to safely and gradually adapt their processes to the CPDLC user interface, says Crawley. Equipage Rates Domestic CPDLC equipage rates are growing but continue to vary by region, from about 25 per cent in western Canada to up to approximately 65 per cent in Gander Domestic airspace. The range is to be expected since Gander Domestic sees much of the same traffic that has been employing CPDLC to transit the ocean for years, says Crawley. We anticipate that the equipage rate and related benefits will grow now that we have implemented the capability and as customers make their own cases to equip for CPDLC. CPDLC is a key component of Reduced Longitudinal Separation Minima (RLongSM) now being used in the North Atlantic, increasing capacity and enabling more customer-requested climbs to fuel-saving altitudes, sooner. It s one example of improved safety and service enabled through a mix of GPS, Automatic Dependent Surveillance-Contract (ADS-C) and CPDLC. NAV CANADA expects further projects to develop as the aviation technology landscape continues to shift. When you look at the big picture and the technologies that are here or emerging, such as satellite-based ADS-B, you start seeing new opportunities to enhance service, safety and efficiency especially in locations where there was no previously feasible alternative, says Kellar. We re committed to responding to our customer needs, leaving no rock unturned and implementing those solutions such as CPDLC that can truly and positively impact our industry. 8

Updates to Procedures at St. John s International Airport

Updates to Procedures at St. John s International Airport October 10, 2017 Updates to Procedures at St. John s International Airport This document provides notice of upcoming changes to instrument procedures being implemented by NAV CANADA at the St. John s International

More information

Technology driving opportunities for customers over the North Atlantic

Technology driving opportunities for customers over the North Atlantic Technology driving opportunities for customers over the North Atlantic NAV CANADA has extended its surveillance to cover a 1.3 million square kilometre portion of airspace over the North Atlantic (coverage

More information

IMPLEMENTATION OF ADS-B BY NAV CANADA

IMPLEMENTATION OF ADS-B BY NAV CANADA IMPLEMENTATION OF ADS-B BY NAV CANADA Carole Stewart-Green Manager, ATS Regulatory Coordination ABOUT NAV CANADA Private, non-share capital company Second largest ANSP in the world 12 million aircraft

More information

ADS-B via Low Earth Orbiting Satellites Benefits Assessment

ADS-B via Low Earth Orbiting Satellites Benefits Assessment ADS-B via Low Earth Orbiting Satellites Benefits Assessment Jeff Dawson Director, Operational Support NAM/CAR ANI/WG/1 July 2013 Aireon LLC is a joint venture between NAV CANADA and Iridium to finance,

More information

Atlantic Interoperability Initiative to Reduce Emissions AIRE

Atlantic Interoperability Initiative to Reduce Emissions AIRE ICAO Colloquium on Aviation and Climate Change ICAO ICAO Colloquium Colloquium on Aviation Aviation and and Climate Climate Change Change Atlantic Interoperability Initiative to Reduce Emissions AIRE Célia

More information

FIT FOR PURPOSE: A Guide to Using NAV CANADA Aeronautical Publications SECTION B PUBLICATION SPECIFIC FIT FOR PURPOSE INFORMATION

FIT FOR PURPOSE: A Guide to Using NAV CANADA Aeronautical Publications SECTION B PUBLICATION SPECIFIC FIT FOR PURPOSE INFORMATION FIT FOR : A Guide to Using NAV CANADA Aeronautical Publications SECTION B PUBLICATION SPECIFIC FIT FOR INFORMATION I TABLE OF CONTENTS SECTION A: GENERAL MATERIAL 2 SECTION B: PUBLICATION SPECIFIC FIT

More information

NATA 2018 AGM & CONFERENCE

NATA 2018 AGM & CONFERENCE NATA 2018 AGM & CONFERENCE Tracy Beeman A / VP, Stakeholder and Commercial Relations Jeff Cochrane Director, Navigation and Airspace TOPICS NAV CANADA Corporate Update Navigation and Airspace NAVAID Modernization

More information

POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW

POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Edmonton International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 January 2018 The information

More information

PBN Airspace Design Workshop. Area Navigation. Asia and Pacific Regional Sub-Office Beijing, China. 5 May 2016 Page 1 APAC RSO BEIJING

PBN Airspace Design Workshop. Area Navigation. Asia and Pacific Regional Sub-Office Beijing, China. 5 May 2016 Page 1 APAC RSO BEIJING PBN Airspace Design Workshop Area Navigation Asia and Pacific Regional Sub-Office Beijing, China 5 May 2016 Page 1 APAC RSO BEIJING Learning Objectives By the end of this presentation, you will be: Aware

More information

(Presented by the United States)

(Presented by the United States) International Civil Aviation Organization 31/07/09 North American, Central American and Caribbean Office (NACC) Tenth Meeting of Directors of Civil Aviation of the Central Caribbean (C/CAR/DCA/10) Grand

More information

MetroAir Virtual Airlines

MetroAir Virtual Airlines MetroAir Virtual Airlines NAVIGATION BASICS V 1.0 NOT FOR REAL WORLD AVIATION GETTING STARTED 2 P a g e Having a good understanding of navigation is critical when you fly online the VATSIM network. ATC

More information

POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW

POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Winnipeg James Armstrong Richardson International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 November

More information

POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW

POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Halifax Stanfield International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 November 2017 The information

More information

THIRTEENTH AIR NAVIGATION CONFERENCE

THIRTEENTH AIR NAVIGATION CONFERENCE International Civil Aviation Organization 14/9/18 WORKING PAPER THIRTEENTH AIR NAVIGATION CONFERENCE Montréal, Canada, 9 to 19 October 2018 COMMITTEE A Agenda Item 3: Enhancing the global air navigation

More information

ICAO PBN CONCEPTS, BENEFITS, AND OBJECTIVES

ICAO PBN CONCEPTS, BENEFITS, AND OBJECTIVES AFCAC/ICAO Joint Workshop Walter White ICAO PBN CONCEPTS, BENEFITS, AND OBJECTIVES 24 JUNE 2014 Airbus ProSky Corporate Presentation 29/06/2014 PERFORMANCE-BASED NAVIGATION The implementation of Performance-Based

More information

Air Navigation Bureau ICAO Headquarters, Montreal

Air Navigation Bureau ICAO Headquarters, Montreal Performance Based Navigation Introduction to PBN Air Navigation Bureau ICAO Headquarters, Montreal 1 Performance Based Navigation Aviation Challenges Navigation in Context Transition to PBN Implementation

More information

AERONAUTICAL INFORMATION CIRCULAR 33/17

AERONAUTICAL INFORMATION CIRCULAR 33/17 NAV CANADA 07 DEC 17 AERONAUTICAL INFORMATION CIRCULAR 33/17 Introduction NOTICE OF PLANNED EXPANSION OF THE TRIAL IMPLEMENTATION OF 25 NAUTICAL MILE LATERAL SEPARATION MINIMUM IN THE INTERNATIONAL CIVIL

More information

Safety and Airspace Regulation Group. 31 May Policy Statement STANDARD INSTRUMENT DEPARTURE TRUNCATION POLICY.

Safety and Airspace Regulation Group. 31 May Policy Statement STANDARD INSTRUMENT DEPARTURE TRUNCATION POLICY. Safety and Airspace Regulation Group 31 May 2018 Policy Statement STANDARD INSTRUMENT DEPARTURE TRUNCATION POLICY 1 Introduction 1.1 This Policy Statement (PS) presents CAA policy and guidance to Air Navigation

More information

Space Based ADS-B. ICAO SAT meeting - June 2016 AIREON LLC PROPRIETARY INFORMATION

Space Based ADS-B. ICAO SAT meeting - June 2016 AIREON LLC PROPRIETARY INFORMATION Space Based ADS-B ICAO SAT meeting - June 2016 1 Options to Detect an Aircraft Position Position Accuracy / Update Interval Voice Position Reporting ADS-C Position Reporting Radar Surveillance / MLAT Space

More information

PBN AIRSPACE CONCEPT WORKSHOP. SIDs/STARs/HOLDS. Continuous Descent Operations (CDO) ICAO Doc 9931

PBN AIRSPACE CONCEPT WORKSHOP. SIDs/STARs/HOLDS. Continuous Descent Operations (CDO) ICAO Doc 9931 International Civil Aviation Organization PBN AIRSPACE CONCEPT WORKSHOP SIDs/STARs/HOLDS Continuous Descent Operations (CDO) ICAO Doc 9931 Design in context Methodology STEPS TFC Where does the traffic

More information

NAV CANADA and DATA LINK IMPLEMENTATION. Shelley Bailey NAV CANADA May 2016 Sint Maarten

NAV CANADA and DATA LINK IMPLEMENTATION. Shelley Bailey NAV CANADA May 2016 Sint Maarten NAV CANADA and DATA LINK IMPLEMENTATION Shelley Bailey NAV CANADA May 2016 Sint Maarten OPDWLG Operational Data Link Working Group 5 members here today representing ANSPs, manufacturers and regulators

More information

ADS-B Implementation and Regulation Meeting for the NAM/CAR/SAM Regions 26 to 30 November 2018 Mexico City, Mexico

ADS-B Implementation and Regulation Meeting for the NAM/CAR/SAM Regions 26 to 30 November 2018 Mexico City, Mexico ADS-B Implementation and Regulation Meeting for the NAM/CAR/SAM Regions 26 to 30 November 2018 Mexico City, Mexico INTEGRATION OF SPACE-BASED (SB ADSB) TECHNOLOGY INTO THE CANADIAN AIR NAVIGATION SYSTEM

More information

Safety Enhancement RNAV Safe Operating and Design Practices for STARs and RNAV Departures

Safety Enhancement RNAV Safe Operating and Design Practices for STARs and RNAV Departures Safety Enhancement Action: Implementers: Statement of Work: Safety Enhancement 213.5 RNAV Safe Operating and Design Practices for STARs and RNAV Departures To mitigate errors on Standard Terminal Arrival

More information

AREA NAVIGATION RNAV- MANAGEMENT

AREA NAVIGATION RNAV- MANAGEMENT 1. Introduction AREA NAVIGATION RNAV- MANAGEMENT RNAV is an instrument-based navigation method that leads to fly from a fix (geographic point inside an airspace) to another fix directly. Contrary to conventional

More information

TANZANIA CIVIL AVIATION AUTHORITY AIR NAVIGATION SERVICES INSPECTORATE. Title: CONSTRUCTION OF VISUAL AND INSTRUMENT FLIGHT PROCEDURES

TANZANIA CIVIL AVIATION AUTHORITY AIR NAVIGATION SERVICES INSPECTORATE. Title: CONSTRUCTION OF VISUAL AND INSTRUMENT FLIGHT PROCEDURES Page 1 of 8 1. PURPOSE 1.1. This Advisory Circular provides guidance to personnel involved in construction of instrument and visual flight procedures for publication in the Aeronautical Information Publication.

More information

IFR SEPARATION WITHOUT RADAR

IFR SEPARATION WITHOUT RADAR 1. Introduction IFR SEPARATION WITHOUT RADAR When flying IFR inside controlled airspace, air traffic controllers either providing a service to an aircraft under their control or to another controller s

More information

NextGen Priorities: Multiple Runway Operations & RECAT

NextGen Priorities: Multiple Runway Operations & RECAT NextGen Priorities: Multiple Runway Operations & RECAT May 2018 Presented by Paul Strande & Jeffrey Tittsworth Federal Aviation Administration National Airspace System Today Air traffic services for the

More information

AERONAUTICAL INFORMATION CIRCULAR 18/18

AERONAUTICAL INFORMATION CIRCULAR 18/18 NAV CANADA 19 JUL 18 AERONAUTICAL INFORMATION CIRCULAR 18/18 GUIDANCE FOR STANDARD TERMINAL ARRIVAL (STAR) PROCEDURES The guidance currently published in the Transport Canada Aeronautical Information Manual

More information

Thank you, Director Heijl and Bon Jour. It s good to be back in Montreal for this important symposium.

Thank you, Director Heijl and Bon Jour. It s good to be back in Montreal for this important symposium. Keynote Speech by Ms. Victoria Cox, Vice President, Operations Planning United States Federal Aviation Administration Air Traffic Organization Worldwide Symposium on Performance of the Air Navigation System

More information

Pilot Procedures Photographic Survey Flights Flight Planning, Coordination, and Control

Pilot Procedures Photographic Survey Flights Flight Planning, Coordination, and Control Pilot Procedures Photographic Survey Flights Flight Planning, Coordination, and Control 2017-01-31 2017 NAV CANADA All rights reserved. No part of this document may be reproduced in any form, including

More information

GENERAL REPORT. Reduced Lateral Separation Minima RLatSM Phase 2. RLatSM Phase 3

GENERAL REPORT. Reduced Lateral Separation Minima RLatSM Phase 2. RLatSM Phase 3 IBAC TECHNICAL REPORT SUMMARY Subject: NAT Operations and Air Traffic Management Meeting: North Atlantic (NAT) Procedures and Operations Group Meeting 2 Reported by Tom Young POG2 took place at the ICAO

More information

International Civil Aviation Organization. PBN Airspace Concept. Victor Hernandez

International Civil Aviation Organization. PBN Airspace Concept. Victor Hernandez International Civil Aviation Organization PBN Airspace Concept Victor Hernandez Overview Learning Objective: at the end of this presentation you should Understand principles of PBN Airspace Concept 2 Gate

More information

North Atlantic Initiatives

North Atlantic Initiatives North Atlantic Initiatives Monday, 17 March 2014; Session 4 (3:30 5:00) PRESENTED BY: Terry Cecil FAA International Operators Conference Tampa, FL March 17 20, 2014 Briefing Objective North Atlantic Initiatives

More information

RECOMMENDED GUIDANCE FOR FPL AND RELATED ATS MESSAGES

RECOMMENDED GUIDANCE FOR FPL AND RELATED ATS MESSAGES RECOMMENDED GUIDANCE FOR FPL AND RELATED ATS MESSAGES Abbreviations ACI ADS ADS-B ADS-C AFTN AIDC AIP ANSP AMHS APAC APANPIRG ASBU ASIOACG ATFM ATM ATS AUSEP CHG CNL CPDLC CPL DARP DLA EOBT FAA FIR FIRBX

More information

The NAT OPS Bulletin Checklist is available at & NAT Documents, NAT Documents, then NAT Ops Bulletins.

The NAT OPS Bulletin Checklist is available at  & NAT Documents, NAT Documents, then NAT Ops Bulletins. Serial Number: 2017_003 Subject: RLatSM Phase 2 AIC Originator: NAT SPG Issued: 15 December 2017 Effective: 15 December 2017 The purpose of North Atlantic Operations Bulletin 2017-003 is to provide guidance

More information

Saint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis

Saint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis Saint Petersburg-Clearwater International Airport Airspace & Instrument Approach Analysis February 23, 2005 Jeppesen Boeing Jeppesen Government / Military Services Group Airspace Services Division AIRSPACE

More information

RNP AR and Air Traffic Management

RNP AR and Air Traffic Management RNP AR and Air Traffic Management BOEING is a trademark of Boeing Management Company. Copyright 2009 Boeing. All rights reserved. Expanding the Utility of RNP AR Sheila Conway RNP AR User s Forum Wellington,

More information

NAV CANADA 26/09/2017 MAGNETIC VS TRUE NORTH. Vision to Captain Anthony MacKay Director Flight Operations

NAV CANADA 26/09/2017 MAGNETIC VS TRUE NORTH. Vision to Captain Anthony MacKay Director Flight Operations 26/09/2017 MAGNETIC VS TRUE NORTH Vision to 2030 Captain Anthony MacKay Director Flight Operations THE ISSUE Which way is North? All of the aircraft, air traffic and IFR procedure design systems are built

More information

Mr. Chairman, Members of the Committee, I am Chet Fuller, President GE Aviation

Mr. Chairman, Members of the Committee, I am Chet Fuller, President GE Aviation Mr. Chairman, Members of the Committee, I am Chet Fuller, President GE Aviation Systems, Civil. Thank you for the opportunity to testify before the Subcommittee today on the issue of Area Navigation (RNAV)

More information

ACI-NA Conference NextGen at NAV CANADA. John Crichton President and Chief Executive Officer October 11, 2009

ACI-NA Conference NextGen at NAV CANADA. John Crichton President and Chief Executive Officer October 11, 2009 ACI-NA Conference NextGen at NAV CANADA John Crichton President and Chief Executive Officer October 11, 2009 IATA Roadmap Functions Current Planned Not Planned Automated ATC Coordination CAATS Early Issue

More information

Russian Federation ATM modernization program

Russian Federation ATM modernization program Russian Federation ATM modernization program Alexander Vedernikov Deputy Director of Federal Air Transport Agency 20-21 March, 2012, Moscow Main strategic directions of Russian Air Navigation System development

More information

INTERNATIONAL CIVIL AVIATION ORGANIZATION WESTERN AND CENTRAL AFRICA OFFICE. Thirteenth Meeting of the FANS I/A Interoperability Team (SAT/FIT/13)

INTERNATIONAL CIVIL AVIATION ORGANIZATION WESTERN AND CENTRAL AFRICA OFFICE. Thirteenth Meeting of the FANS I/A Interoperability Team (SAT/FIT/13) INTERNATIONAL CIVIL AVIATION ORGANIZATION WESTERN AND CENTRAL AFRICA OFFICE Thirteenth Meeting of the FANS I/A Interoperability Team (SAT/FIT/13) Durban, South Africa, 4-5 June 2018 Agenda Item 4: System

More information

Any queries about the content of the attached document should be addressed to: ICAO EUR/NAT Office:

Any queries about the content of the attached document should be addressed to: ICAO EUR/NAT Office: Serial Number: 2018_005 Subject: Special Procedures For In-Flight Contingencies in Oceanic Airspace Originator: NAT SPG Issued: 17 DEC 2018 Effective:28 MAR 2019 The purpose of this North Atlantic Operations

More information

Learning Objectives. By the end of this presentation you should understand:

Learning Objectives. By the end of this presentation you should understand: Designing Routes 1 Learning Objectives By the end of this presentation you should understand: Benefits of RNAV Considerations when designing airspace routes The basic principles behind route spacing The

More information

CHAPTER 5 SEPARATION METHODS AND MINIMA

CHAPTER 5 SEPARATION METHODS AND MINIMA CHAPTER 5 SEPARATION METHODS AND MINIMA 5.1 Provision for the separation of controlled traffic 5.1.1 Vertical or horizontal separation shall be provided: a) between IFR flights in Class D and E airspaces

More information

RNP OPERATIONS. We will now explain the key concepts that should not be mixed up and that are commonly not precisely understood.

RNP OPERATIONS. We will now explain the key concepts that should not be mixed up and that are commonly not precisely understood. RNP OPERATIONS 1. Introduction Planes were made as a means of transport. To successfully fly from a location A to a location B, pilots were first and foremost navigators. Originally relying on visual landmarks

More information

New York Aviation Management Association Conference

New York Aviation Management Association Conference New York Aviation Management Association Conference Presented by: Carmine W. Gallo Federal Aviation Administration Eastern Region Regional Administrator September 14, 2016 1 The What is and Benefits of

More information

Air Traffic Management

Air Traffic Management Air Traffic Management Transforming Air Traffic Management T rans f orming A ir Today s airspace users are grappling with the air traffic control system s inability to manage an ever-growing amount of

More information

Nav Specs and Procedure Design Module 12 Activities 8 and 10. European Airspace Concept Workshops for PBN Implementation

Nav Specs and Procedure Design Module 12 Activities 8 and 10. European Airspace Concept Workshops for PBN Implementation Nav Specs and Procedure Design Module 12 Activities 8 and 10 European Airspace Concept Workshops for PBN Implementation Learning Objectives By the end of this presentation you should understand: The different

More information

TWELFTH WORKING PAPER. AN-Conf/12-WP/137. International ICAO. developing RNAV 1.1. efficiency. and terminal In line.

TWELFTH WORKING PAPER. AN-Conf/12-WP/137. International ICAO. developing RNAV 1.1. efficiency. and terminal In line. International Civil Aviation Organization WORKING PAPER 31/10/12 English only TWELFTH AIR NAVIGATION CONFERENCE Montréal, 19 to 30 November 2012 Agenda Item 5: Efficient flight paths through trajectory-based

More information

AD 2. AERODROMES. For the ICAO location indicators used for Canadian aerodromes, refer to the following publications:

AD 2. AERODROMES. For the ICAO location indicators used for Canadian aerodromes, refer to the following publications: AIP CANADA (ICAO) PART 3 AERODROMES (AD) AD 2. AERODROMES AD 2.1 Aerodrome Location Indicator and Name For the ICAO location indicators used for Canadian aerodromes, refer to the following publications:

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

THE DEVELOPMENT OF NATIONAL PERFORMANCE FRAMEWORK FOR AIR NAVIGATION SYSTEMS MAURITIUS

THE DEVELOPMENT OF NATIONAL PERFORMANCE FRAMEWORK FOR AIR NAVIGATION SYSTEMS MAURITIUS THE DEVELOPMENT OF NATIONAL PERFORMANCE FRAMEWORK FOR AIR NAVIGATION SYSTEMS MAURITIUS 2011-2015 Presented by Ahmed Mosaheb Chief Officer ATM MAURITIUS Characteristics of the Industry FIR- 9,000,000 sq

More information

EUR/SAM corridor airspace concept

EUR/SAM corridor airspace concept TWENTYENTH MEETING ON THE IMPROVEMENT OF AIR TRAFFIC SERVICES OVER THE SOUTH ATLANTIC (SAT21) (Lisbon, Portugal, 8 to 10 June, 2016) Agenda Item 2: Air traffic management (ATM) RNP 4 IN THE EUR/SAM CORRIDOR

More information

Peter Sorensen Director, Europe Safety, Operations & Infrastructure To represent, lead and serve the airline industry

Peter Sorensen Director, Europe Safety, Operations & Infrastructure To represent, lead and serve the airline industry Future of ATM Peter Sorensen Director, Europe Safety, Operations & Infrastructure To represent, lead and serve the airline industry 1 1 Air Traffic Management (ATM) Management of aircraft and airspace

More information

Captain Jeff Martin Senior Director Flight Operations Southwest Airlines

Captain Jeff Martin Senior Director Flight Operations Southwest Airlines Captain Jeff Martin Senior Director Flight Operations Southwest Airlines Southwest s Fleet Southwest achieves one of its primary competitive strengths low operating costs by operating only one aircraft

More information

QUIETER OPERATIONS A GUIDE FOR PILOTS AND CONTROLLERS

QUIETER OPERATIONS A GUIDE FOR PILOTS AND CONTROLLERS QUIETER OPERATIONS A GUIDE FOR PILOTS AND CONTROLLERS FOREWORD It takes a cross-industry effort to ensure that every flight happens safely and efficiently airlines, air navigation services, airport authorities,

More information

PBN Syllabus Helicopter. Learning Objective. phase Theoretical PBN concept. in ICAO Doc 9613)

PBN Syllabus Helicopter. Learning Objective. phase Theoretical PBN concept. in ICAO Doc 9613) PBN Syllabus Helicopter Training Topic phase Theoretical PBN concept training (as described in ICAO Doc 9613) PBN principles PBN components PBN scope Navigation specifications RNAV and RNP Navigation functional

More information

TERMS OF REFERENCE FREDERICTON AIRSPACE REVIEW

TERMS OF REFERENCE FREDERICTON AIRSPACE REVIEW TERMS OF REFERENCE FREDERICTON AIRSPACE REVIEW NAV CANADA Level of Service & Aeronautical Studies 77 Metcalfe Street, 5th Floor Ottawa, Ontario K1P 5L6 April, 2013 The information and diagrams contained

More information

Seychelles Civil Aviation Authority. Telecomm & Information Services Unit

Seychelles Civil Aviation Authority. Telecomm & Information Services Unit Seychelles Civil Aviation Authority Telecomm & Information Services Unit 12/15/2010 SCAA 1 WORKSHOP EXERCISE Workshop on the development of National Performance Framework 6 10 Dec 2010 10/12/2010 SCAA

More information

Name of Customer Representative: Bruce DeCleene, AFS-400 Division Manager Phone Number:

Name of Customer Representative: Bruce DeCleene, AFS-400 Division Manager Phone Number: Phase I Submission Name of Program: Equivalent Lateral Spacing Operation (ELSO) Name of Program Leader: Dr. Ralf Mayer Phone Number: 703-983-2755 Email: rmayer@mitre.org Postage Address: The MITRE Corporation,

More information

Efficiency and Automation

Efficiency and Automation Efficiency and Automation Towards higher levels of automation in Air Traffic Management HALA! Summer School Cursos de Verano Politécnica de Madrid La Granja, July 2011 Guest Lecturer: Rosa Arnaldo Universidad

More information

Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7. European Airspace Concept Workshops for PBN Implementation

Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7. European Airspace Concept Workshops for PBN Implementation Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7 European Airspace Concept Workshops for PBN Implementation Design in Context TFC Where does the traffic come from? And when? RWY Which

More information

Beijing, 18 h of September 2014 Pierre BACHELIER Head of ATM Programme. Cockpit Initiatives. ATC Global 2014

Beijing, 18 h of September 2014 Pierre BACHELIER Head of ATM Programme. Cockpit Initiatives. ATC Global 2014 Beijing, 18 h of September 2014 Pierre BACHELIER Head of ATM Programme Cockpit Initiatives for ATM ATC Global 2014 Page 2 Cockpit Initiatives for ATM Airbus vision on ATM transformation Airbus position

More information

PBN Syllabus Aeroplane. Learning Objective. phase Theoretical PBN concept. in ICAO Doc 9613)

PBN Syllabus Aeroplane. Learning Objective. phase Theoretical PBN concept. in ICAO Doc 9613) PBN Syllabus Aeroplane Training Topic phase Theoretical PBN concept training (as described in ICAO Doc 9613) PBN principles PBN components PBN scope Navigation specifications RNAV and RNP Navigation functional

More information

USE OF RADAR IN THE APPROACH CONTROL SERVICE

USE OF RADAR IN THE APPROACH CONTROL SERVICE USE OF RADAR IN THE APPROACH CONTROL SERVICE 1. Introduction The indications presented on the ATS surveillance system named radar may be used to perform the aerodrome, approach and en-route control service:

More information

Next Generation Airspace Developments: Key Operational Trends and Enablers

Next Generation Airspace Developments: Key Operational Trends and Enablers Next Generation Airspace Developments: Key Operational Trends and Enablers ICNS 2013, Day 1 Plenary Nikos Fistas EUROCONTROL Herdon, VA, 23/04/13 Agenda Key goals of future European ATM system 4D Trajectory

More information

Manual on Monitoring the Application of Performance-based Horizontal Separation Minima

Manual on Monitoring the Application of Performance-based Horizontal Separation Minima Manual on Monitoring the Application of Performance-based Horizontal Separation Minima (PBHSM Manual) Presented to: 2 nd NAT PBCS Workshop By: Christine Falk Date: 17-19 June 2015 Overview Why a PBHSM

More information

i4d A MANUFACTURING INDUSTRY PERSPECTIVE GROUND AND AIRBORNE ASPECTS Michel Procoudine Lionel Rouchouse Thales

i4d A MANUFACTURING INDUSTRY PERSPECTIVE GROUND AND AIRBORNE ASPECTS Michel Procoudine Lionel Rouchouse Thales i4d A MANUFACTURING INDUSTRY PERSPECTIVE GROUND AND AIRBORNE ASPECTS Michel Procoudine Lionel Rouchouse Thales 1 Single European Sky ATM Research (SESAR) - Objectives Enabling EU skies to handle 3 times

More information

PBN ROUTE SPACING AND CNS REQUIREMENTS (Presented by Secretariat)

PBN ROUTE SPACING AND CNS REQUIREMENTS (Presented by Secretariat) International Civil Aviation Organization The First Meeting of South China Sea Major Traffic Flow Review Group (SCS-MTFRG/1) Kuala Lumpur, Malaysia, 19-20 January 2015 Agenda Item 5: Discuss strategy for

More information

The benefits of satcom to airlines. Prepared by Helios for

The benefits of satcom to airlines. Prepared by Helios for The benefits of satcom to airlines Prepared by Helios for contents INTRODUCTION 3...What is satcom? 4..the evolution of satcom Atc benefits 5.benefits from datalink applications in oceanic ATC 6.SATCOM

More information

Chapter 6. Nonradar. Section 1. General DISTANCE

Chapter 6. Nonradar. Section 1. General DISTANCE 12/10/15 JO 7110.65W Chapter 6. Nonradar Section 1. General 6 1 1. DISTANCE Use mileage based (DME and/or ATD) procedures and minima only when direct pilot/controller communications are maintained. FIG

More information

2012 Performance Framework AFI

2012 Performance Framework AFI 2012 Performance Framework AFI Nairobi, 14-16 February 2011 Seboseso Machobane Regional Officer ATM, ESAF 1 Discussion Intro Objectives, Metrics & Outcomes ICAO Process Framework Summary 2 Global ATM Physical

More information

Fly at the speed of ingenuity on your Learjet 85

Fly at the speed of ingenuity on your Learjet 85 rockwell collins Pro Line Fusion Avionics Fly at the speed of ingenuity on your Learjet 85 Image courtesy of Bombardier. Experience the most advanced avionics system ever offered on a mid-size jet. Achieve

More information

Review of the designation of Class C controlled airspace in the Mount Cook area - Consultation November 2013

Review of the designation of Class C controlled airspace in the Mount Cook area - Consultation November 2013 Review of the designation of Class C controlled airspace in the Mount Cook area - Consultation November 2013 Civil Aviation Authority Table of Contents Background... 1 Final decision... 1 The introduction

More information

Operators may need to retrofit their airplanes to ensure existing fleets are properly equipped for RNP operations. aero quarterly qtr_04 11

Operators may need to retrofit their airplanes to ensure existing fleets are properly equipped for RNP operations. aero quarterly qtr_04 11 Operators may need to retrofit their airplanes to ensure existing fleets are properly equipped for RNP operations. 24 equipping a Fleet for required Navigation Performance required navigation performance

More information

THE TOWER CONTROL POSITION (TWR)

THE TOWER CONTROL POSITION (TWR) 1. Introduction THE TOWER CONTROL POSITION (TWR) The Aerodrome Local Control, or Tower (called TWR) controller has the responsibility of ensuring Air Traffic Control (ATC) Services within a restricted

More information

Optimization of Airspace and Procedures in the Metroplex

Optimization of Airspace and Procedures in the Metroplex Optimization of Airspace and Procedures in the Metroplex Administration SoCal Metroplex Project Overview Brief To: By: Los Angeles World Airport Rob Henry, Manager SoCal Metroplex Jose Gonzalez, SoCal

More information

Modernising UK Airspace 2025 Vision for Airspace Tools and Procedures. Controller Pilot Symposium 24 October 2018

Modernising UK Airspace 2025 Vision for Airspace Tools and Procedures. Controller Pilot Symposium 24 October 2018 Modernising UK Airspace 2025 Vision for Airspace Tools and Procedures Controller Pilot Symposium 24 October 2018 Our airspace Flight Information Regions London & Scottish FIRs: 1m km 2 11% of Europe s

More information

INTERNATIONAL CIVIL AVIATION ORGANIZATION WESTERN AND CENTRAL AFRICAN OFFICE. Lisbon, Portugal, 19 to 20 May 2010

INTERNATIONAL CIVIL AVIATION ORGANIZATION WESTERN AND CENTRAL AFRICAN OFFICE. Lisbon, Portugal, 19 to 20 May 2010 INTERNATIONAL CIVIL AVIATION ORGANIZATION WESTERN AND CENTRAL AFRICAN OFFICE FOURTEENTH MEETING ON THE IMPROVEMENT OF AIR TRAFFIC SERVICES OVER THE SOUTH ATLANTIC (SAT/15) Lisbon, Portugal, 19 to 20 May

More information

FLIGHT PATH FOR THE FUTURE OF MOBILITY

FLIGHT PATH FOR THE FUTURE OF MOBILITY FLIGHT PATH FOR THE FUTURE OF MOBILITY Building the flight path for the future of mobility takes more than imagination. Success relies on the proven ability to transform vision into reality for the betterment

More information

STATEMENT OF THE NATIONAL BUSINESS AVIATION ASSOCIATION ED BOLEN PRESIDENT AND CEO BEFORE THE COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE

STATEMENT OF THE NATIONAL BUSINESS AVIATION ASSOCIATION ED BOLEN PRESIDENT AND CEO BEFORE THE COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE STATEMENT OF THE NATIONAL BUSINESS AVIATION ASSOCIATION ED BOLEN PRESIDENT AND CEO BEFORE THE COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE AVIATION SUBCOMMITTEE U.S. HOUSE OF REPRESENTATIVES REGARDING

More information

RNP AR APCH Approvals: An Operator s Perspective

RNP AR APCH Approvals: An Operator s Perspective RNP AR APCH Approvals: An Operator s Perspective Presented to: ICAO Introduction to Performance Based Navigation Seminar The statements contained herein are based on good faith assumptions and provided

More information

A World In Motion. NAV CANADA Overview for CASI December 2013

A World In Motion. NAV CANADA Overview for CASI December 2013 A World In Motion NAV CANADA Overview for CASI December 2013 Who We Are About NAV CANADA Private, non-share capital company 2nd largest ANSP in the world 12 million aircraft movements annually 18 million

More information

Overview of Evolution to Performance Based Navigation. ICAO PBN Seminar Overview of Evolution to Performance Based Navigation

Overview of Evolution to Performance Based Navigation. ICAO PBN Seminar Overview of Evolution to Performance Based Navigation Overview of Evolution to Performance Based Navigation 1 Overview Learning Objectives: at the end of this presentation you should: Understand what are the two main elements of Performance Based Navigation

More information

UPDATE ON THE 6 IDEAS (1-4) NAV CANADA

UPDATE ON THE 6 IDEAS (1-4) NAV CANADA UPDATE ON THE 6 IDEAS (1-4) THE 6 INITIATIVES 1. New approaches for night-time operations - Implemented 2. New departure procedures for night-time operations - Implemented 3. Increased downwind arrival

More information

COMMUNITY NOISE MITIGATION SUGGESTIONS

COMMUNITY NOISE MITIGATION SUGGESTIONS COMMUNITY NOISE MITIGATION SUGGESTIONS Toronto Pearson is one of North America's fastest growing global hub airports, handling nearly 40 million passengers today, and well on its way to reaching greater

More information

TWELFTH AIR NAVIGATION CONFERENCE

TWELFTH AIR NAVIGATION CONFERENCE International Civil Aviation Organization AN-Conf/12-WP/6 7/5/12 WORKING PAPER TWELFTH AIR NAVIGATION CONFERENCE Agenda Item 2: Aerodrome operations improving airport performance 2.2: Performance-based

More information

ADS-B Implementation Update 2011 CNS/ATM Conference

ADS-B Implementation Update 2011 CNS/ATM Conference ADS-B Implementation Update 2011 CNS/ATM Conference Prepared by Jeff Cochrane Manager, CNS Service Design June 2011 Briefing Overview Canadian ADS-B Implementation Review of Requirements for ADS-B surveillance

More information

Honeywell.com PBN Concepts Krakow, Poland

Honeywell.com PBN Concepts Krakow, Poland PBN Concepts Krakow, Poland EPKK (KRK) Current Operational Environment Current Operational Environment : Runways: 07/25 8,366 ft (2550m) Approaches: ILS or LOC 25 RNAV (GNSS) 07, 25 VOR 07, 25 NDB 25 Departure

More information

PBN Performance. Based Navigation. - PBN & Airspace Concepts - ICAO PBN Seminar Introduction to PBN

PBN Performance. Based Navigation. - PBN & Airspace Concepts - ICAO PBN Seminar Introduction to PBN PBN Performance Based Navigation - PBN & Airspace Concepts - Introduction to PBN 1 Learning Objectives PBN Concept within the context of an Airspace (Operational) Concept. Introduction to PBN 2/37 Components

More information

Proposed Changes to Inverness Airport s Airspace The Introduction of Controlled Airspace and Optimisation of Instrument Flight Procedures

Proposed Changes to Inverness Airport s Airspace The Introduction of Controlled Airspace and Optimisation of Instrument Flight Procedures Proposed Changes to Inverness Airport s Airspace The Introduction of Controlled Airspace and Optimisation of Instrument Flight Procedures What is an Airspace Change Proposal? It is a formal UK Civil Aviation

More information

Real-time route planning streamlines onboard operations, reduces fuel burn and delays, and improves on-time performance.

Real-time route planning streamlines onboard operations, reduces fuel burn and delays, and improves on-time performance. Real-time route planning streamlines onboard operations, reduces fuel burn and delays, and improves on-time performance. Operational Efficiency of Dynamic Navigation Charting Benefits such as improved

More information

LAMP 2 - FASI(S) Network

LAMP 2 - FASI(S) Network Future Airspace Strategy Implementation South: ATS Route Network managed by NERL under London Airspace Management Programme 2 LAMP 2 - FASI(S) Network Stage 1 Assessment Meeting Friday 23 rd February 2018

More information

4.1 This document outlines when a proposal for a SID Truncation may be submitted and details the submission requirements.

4.1 This document outlines when a proposal for a SID Truncation may be submitted and details the submission requirements. Safety and Airspace Regulation Group 13 May 2014 Policy Statement STANDARD INSTRUMENT DEPARTURE TRUNCATION POLICY 1 Introduction 1.1 This Policy Statement (PS) is intended to provide guidance to ANSPs

More information

CLEARANCE INSTRUCTION READ BACK

CLEARANCE INSTRUCTION READ BACK CLEARANCE INSTRUCTION READ BACK 1. Introduction An ATC clearance or an instruction constitutes authority for an aircraft to proceed only in so far as known air traffic is concerned and is based solely

More information

PBN Performance. Based Navigation. Days 1, 2 & 3. ICAO PBN Seminar Seminar Case Studies Days 1,2,3. Seminar Case Studies

PBN Performance. Based Navigation. Days 1, 2 & 3. ICAO PBN Seminar Seminar Case Studies Days 1,2,3. Seminar Case Studies PBN Performance Based Navigation Seminar Case Studies Days 1, 2 & 3 1 Overview 2 Case Study - Day 1 Case Study - Day 2 Case Study - Day 3 3 Case Study - Day 1 Learning Objectives Identify navigation performance

More information

Follow up to the implementation of safety and air navigation regional priorities XMAN: A CONCEPT TAKING ADVANTAGE OF ATFCM CROSS-BORDER EXCHANGES

Follow up to the implementation of safety and air navigation regional priorities XMAN: A CONCEPT TAKING ADVANTAGE OF ATFCM CROSS-BORDER EXCHANGES RAAC/15-WP/28 International Civil Aviation Organization 04/12/17 ICAO South American Regional Office Fifteenth Meeting of the Civil Aviation Authorities of the SAM Region (RAAC/15) (Asuncion, Paraguay,

More information

Continuous Descent? And RNAV Arrivals

Continuous Descent? And RNAV Arrivals Continuous Descent? And RNAV Arrivals From an ATC Perspective Presentation to: CDA Workshop GA Tech Name: Don Porter RNP Project Lead FAA, RNAV RNP Group Date: 18 April 2006 My Background 22 years Terminal

More information

Trajectory Based Operations

Trajectory Based Operations Trajectory Based Operations Far-Term Concept Proposed Trade-Space Activities Environmental Working Group Operations Standing Committee July 29, 2009 Rose.Ashford@nasa.gov Purpose for this Presentation

More information