1 TERMS OF REFERENCE FREDERICTON AIRSPACE REVIEW NAV CANADA Level of Service & Aeronautical Studies 77 Metcalfe Street, 5th Floor Ottawa, Ontario K1P 5L6 April, 2013 The information and diagrams contained in this Terms of Reference are for illustrative purposes only and are not to be used for navigation.
2 TABLE OF CONTENTS 1.0 Purpose Scope of the study Background Methodology Study Safety Management Plan Human Resources Work Management Plan Finance Resources Materiality of the changes Consultation Authority...4
3 1.0 Purpose The purpose of this Terms of Reference (TOR) document is to initiate an aeronautical study to modify the current classification of the Fredericton control zone (CZ) in relation to scheduled installation of surveillance equipment and the impact on enroute navigation and approach/departure procedures as they relate to permanent and temporary Class F airspace. 2.0 Scope of the study The aeronautical study will assess the following: 1. Modify the Class D airspace in the Fredericton CZ to transponder mandatory airspace to ensure MLAT coverage (surveillance) is assured for traffic that transits the CZ; 2. Remove the procedure turn for the VOR RWY 27 (GNSS) approach and add: RNAV or radar is required to conduct the IAP ; 3. Revoke the departure procedures for runway 15; 4. For enroute navigation re-align the V300, V352, V93, J500 and J581 airways through the Fredericton NDB to maintain the required separation from CYR724. Relocate the north end of the V310 airway to a new reporting point east of FRENN, and relocate R11 to pass through a new reporting point east of ADRAX; and 5. Formalize temporary additional airspaces located to the east and west of CYR724 as CYA or CYR areas activated by NOTAM and consult with the Department of National Defence to determine the feasibility of lowering the vertical dimensions of CYR 724 with the caveat that they can be raised if required by NOTAM. 3.0 Background The Fredericton Class D control zone served by a 16-hour per day control tower. Outside of this time Remote Aerodrome Advisory Service (RAAS) is provided by the staff of the Saint John flight service station. IFR service is provided 24 hours per day from the Moncton ACC. To the north of the Fredericton Control Zone are 11 dedicated VFR training areas. Flight training activities in the Fredericton area are primarily conducted in these areas and used extensively by pilots with English as a second language. To the south of the Fredericton Control Zone is CYR 724. An area of over 450 square nm and is active continuously surface to FL250. It is in close proximity to the Fredericton International Airport (CYFC) being 3.8nm from the departure end of Runway 15. Traffic movement data for 2012 for the Fredericton International Airport was 86,448 movements which were almost exclusively VFR movements with only 14% of traffic being IFR in origin. Due to limitations of current radar coverage, which is based at 2300ft, installation of a Multilateration (MLAT) System is scheduled for late 2013 early 2014.
4 Due to the location of CYR724, the following IFR products/services are affected either at CYFC or adjacent to it: CYFC Approach / Departure procedures VOR RWY 27 (GNSS) HARVEY SID (VECTOR) JEMSEG SID (VECTOR) RWY 15 departure procedure Airways R11 V93, V300, V310 and V352 J500 and J581 At different times of the year additional airspace is required to support various military operations. This is done by acquiring a temporary amendment to section 5.1 of the aeronautics act which is done via NOTAM, but is not depicted on aeronautical charts. Due to the lateral and vertical dimensions of CYR 724, traffic proceeding to and from adjacent airports must be routed around the area using existing airways or by controller vectors. 4.0 Methodology An aeronautical study assesses and analyzes information through data collection and customer/stakeholder consultation. The aeronautical study team will: Confirm stakeholder requirements for: o Non-transponder equipped flights, o Approach and departure procedures at CYFC, and o Area Navigation (both VFR and IFR) in relation to proposed changes in relation to Class F airspace. Analyze the concerns and issues raised by the stakeholders, Develop possible solutions and/or options, Conduct a HIRA as required, Present recommendations to senior management for approval, Coordinate with the appropriate managers who would be involved with the technical and operational implementation of the proposed service change, and Coordinate with Transport Canada. The study team will ensure that consultation with customers and affected or interested stakeholders is sufficient prior to making any recommendations to senior management. A business case will be developed to validate the recommendations. A risk management team will conduct the risk assessment and may call upon stakeholders to contribute to the analysis of some risk scenarios. 5.0 Safety Management Plan The manager responsible for implementing any decisions resulting from this aeronautical study will prepare a project safety management plan. The plan will include mitigation and
5 monitoring actions identified through this study that are required to implement the change in service. 6.0 Human Resources The team will be based on a multi-disciplined, matrix organization. Representation will be obtained on an as needed basis for key technical, operational and support areas. Additional members will be identified during the course of the work and will be expected to participate on specific tasks on an as required basis. The duration of those tasks may vary from a few days to two weeks. A key focus of the project manager will be to minimize the impact of all work assignments on other projects underway. The level of effort and duration will be calculated during the planning phase of project. Team Leader Al Cote, Shift Manager Moncton ACC Other NAV CANADA Team Members: Manager, Area Control Centre Operations, Moncton ACC Manager, Fredericton Control Tower Unit Procedures Specialist, Moncton ACC Airport Operations Specialist, Moncton FIR Team Supervisor, Low Specialty, Moncton ACC Unit Operations Specialist, Fredericton Control Tower Specialist, Airspace and Service Requirements Specialist AIS Customer and Commercial Services TBD 7.0 Work Management Plan TOR approval: April 2013 If the study is approved, the following will be undertaken: 1. Develop Communication and Consultation Plan April Study commencement May Consultation May Assess consultation input June Conduct HIRA June Finalize Aeronautical Study Report July Management Approvals August Circulate to Transport Canada for safety oversight review August 2013 Following Transport Canada review 9. Coordinate implemention plan and dates with appropriate departments Fall Prepare AIS Submission Winter Prepare and publish AIC Spring Prepare and publish Notice Spring Implement Summer Monitoring Post implementation Reviews (conducted at post 90 days and 1-year)
6 8.0 Finance Resources Each responsibility manager is accountable for travel and related expenses, and the management of overtime. Service design changes may generate an engineering support requirement. These requirements will be identified as the review progresses and an Opportunity Identification Form (OIF) generated to initiate project planning. 9.0 Materiality of the changes There is the potential that some of the service delivery options may represent a material change. Formal notifications per the Civil Air Navigation Services Commercialization Act should apply Consultation An appropriate communications plan incorporating a full consultation plan will be prepared. Aviation organizations representing airport, general aviation, business aviation and others as appropriate will be consulted during the Aeronautical Study. A complete list of customers and stakeholders consulted will be attached to the aeronautical study Authority NAV CANADA Vice President Operations
TERMS OF REFERENCE. Review of Aviation Weather Requirements. Lourdes-de-Blanc-Sablon, Québec
TERMS OF REFERENCE Review of Aviation Weather Requirements Lourdes-de-Blanc-Sablon, Québec NAV CANADA Level of Service 77 Metcalfe Street Ottawa, Ontario K1P 5L6 October 2018 The information and diagrams
More informationTerms of Reference CYR301 Airspace Modification TERMS OF REFERENCE. Airspace Modification CYR301. Camp Dundurn, SK
TERMS OF REFERENCE Airspace Modification CYR301 Camp Dundurn, SK NAV CANADA Navigation and airspace Level of Service 77 Metcalfe Street, 4th Floor Ottawa, Ontario K1P 5L6 Sept 2016 The information and
More informationTerms of Reference - Review LOC/DME at CYGV, CYRJ, CYHR TERMS OF REFERENCE
TERMS OF REFERENCE Review Requirement for Localizer (LOC) & Distance Measuring Equipment (DME) at: Havre St-Pierre, Roberval, and Chevery Airports, Quebec NAV CANADA Navigation and airspace Level of Service
More informationReview of Air Traffic Services Montreal International Mirabel (CYMX) TERMS OF REFERENCE. Review of Air Traffic Services
TERMS OF REFERENCE NAV CANADA Navigation and airspace Level of Service 77 Metcalfe Street, 7th Floor Ottawa, Ontario K1P 5L6 March 2018 The information and diagrams contained in this Terms of Reference
More informationTerms of Reference. Airspace and Communications Requirements in the South Oil Sands Area, Northern Alberta
Terms of Reference Airspace and Communications Requirements in the South Oil Sands Area, Northern Alberta NAV CANADA Aeronautical Studies and Analysis Air Operations Centre Edmonton International Airport
More informationUSE OF RADAR IN THE APPROACH CONTROL SERVICE
USE OF RADAR IN THE APPROACH CONTROL SERVICE 1. Introduction The indications presented on the ATS surveillance system named radar may be used to perform the aerodrome, approach and en-route control service:
More informationNATA 2018 AGM & CONFERENCE
NATA 2018 AGM & CONFERENCE Tracy Beeman A / VP, Stakeholder and Commercial Relations Jeff Cochrane Director, Navigation and Airspace TOPICS NAV CANADA Corporate Update Navigation and Airspace NAVAID Modernization
More informationProposal for designation of permanent danger area at Middlemarch
Proposal for designation of permanent danger area at Middlemarch Civil Aviation Authority Table of Contents Introduction... 1 Proposed danger area... 1 Possible effects to VFR aircraft... 2 Possible effects
More informationFIT FOR PURPOSE: A Guide to Using NAV CANADA Aeronautical Publications SECTION B PUBLICATION SPECIFIC FIT FOR PURPOSE INFORMATION
FIT FOR : A Guide to Using NAV CANADA Aeronautical Publications SECTION B PUBLICATION SPECIFIC FIT FOR INFORMATION I TABLE OF CONTENTS SECTION A: GENERAL MATERIAL 2 SECTION B: PUBLICATION SPECIFIC FIT
More informationREGULATION No. 10/2011 ON APPROVAL OF FLIGHT PROCEDURES INCLUDING SID-s AND STAR-s. Article 1 Scope of Application
Republika e Kosovës Republika Kosovo Republic of Kosovo Autoriteti i Aviacionit Civil i Kosovës Autoritet Civilnog Vazduhoplovstva Kosova Civil Aviation Authority of Kosovo Director General of Civil Aviation
More informationTANZANIA CIVIL AVIATION AUTHORITY AIR NAVIGATION SERVICES INSPECTORATE. Title: CONSTRUCTION OF VISUAL AND INSTRUMENT FLIGHT PROCEDURES
Page 1 of 8 1. PURPOSE 1.1. This Advisory Circular provides guidance to personnel involved in construction of instrument and visual flight procedures for publication in the Aeronautical Information Publication.
More informationPilot Procedures Photographic Survey Flights Flight Planning, Coordination, and Control
Pilot Procedures Photographic Survey Flights Flight Planning, Coordination, and Control 2017-01-31 2017 NAV CANADA All rights reserved. No part of this document may be reproduced in any form, including
More informationReview of the designation of Class C controlled airspace in the Mount Cook area - Consultation November 2013
Review of the designation of Class C controlled airspace in the Mount Cook area - Consultation November 2013 Civil Aviation Authority Table of Contents Background... 1 Final decision... 1 The introduction
More informationSeychelles Civil Aviation Authority. Telecomm & Information Services Unit
Seychelles Civil Aviation Authority Telecomm & Information Services Unit 12/15/2010 SCAA 1 WORKSHOP EXERCISE Workshop on the development of National Performance Framework 6 10 Dec 2010 10/12/2010 SCAA
More informationContents. Subpart A General 91.1 Purpose... 7
Contents Rule objective... 3 Extent of consultation... 3 Summary of comments... 4 Examination of comments... 6 Insertion of Amendments... 6 Effective date of rule... 6 Availability of rules... 6 Part 91
More informationGestão de Tráfego Aéreo 2015/2016 Exam Name Student ID Number. I (5.5/20, 0.5 each)
Gestão de Tráfego Aéreo 2015/2016 Exam 2016.01.04 Name Student ID Number I (5.5/20, 0.5 each) What is each contracting state of ICAO required to provide? [ ] Modern radio navigation facilities for aeroplanes
More informationAERONAUTICAL INFORMATION CIRCULAR 18/18
NAV CANADA 19 JUL 18 AERONAUTICAL INFORMATION CIRCULAR 18/18 GUIDANCE FOR STANDARD TERMINAL ARRIVAL (STAR) PROCEDURES The guidance currently published in the Transport Canada Aeronautical Information Manual
More informationGOVERNMENT OF INDIA OFFICE OF DIRECTOR GENERAL OF CIVIL AVIATION
GOVERNMENT OF INDIA OFFICE OF DIRECTOR GENERAL OF CIVIL AVIATION ANSS AC NO. 1 of 2017 31.07. 2017 Air Space and Air Navigation Services Standard ADVISORY CIRCULAR Subject: Procedures to follow in case
More informationAD 2. AERODROMES. For the ICAO location indicators used for Canadian aerodromes, refer to the following publications:
AIP CANADA (ICAO) PART 3 AERODROMES (AD) AD 2. AERODROMES AD 2.1 Aerodrome Location Indicator and Name For the ICAO location indicators used for Canadian aerodromes, refer to the following publications:
More informationEuropean Aviation Safety Agency
Annexes I and II to ED Decision 2018/013/R European Aviation Safety Agency Acceptable Means of Compliance and Guidance Material to Commission Regulation (EU) No 1332/2011 and Commission Implementing Regulation
More informationConsiderations for Facility Consolidation
Considerations for Facility Consolidation ATC Guild, New Delhi, India October 21, 2010 Mimi Dobbs Overview Why consider consolidation? Co location vs Consolidation Consolidating Methodologies Areas to
More informationLearning Objectives. By the end of this presentation you should understand:
Designing Routes 1 Learning Objectives By the end of this presentation you should understand: Benefits of RNAV Considerations when designing airspace routes The basic principles behind route spacing The
More informationRNP AR Experience. Phil Rakena PBN Project Manager February 2015
RNP AR Experience Phil Rakena PBN Project Manager February 2015 1 What is PBN? Area navigation, using on-board systems to provide position and confirm navigation performance. PBN represents a shift from
More informationAPAC PBN UPDATE Slide 1 of xx
APAC PBN UPDATE Slide 1 of xx Ian Mallett FREE OFFERS! CASA Training DVDs GNSS ADS-B More available from CASA Safety Management System (SMS) Booklet CASA Shop Items www.casa.gov.au Slide 2 of xx Slide
More informationSaint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis
Saint Petersburg-Clearwater International Airport Airspace & Instrument Approach Analysis February 23, 2005 Jeppesen Boeing Jeppesen Government / Military Services Group Airspace Services Division AIRSPACE
More informationAIP CANADA (ICAO) SUPPLEMENT 15/18
NAV CANADA 29 MAR 18 AIP CANADA (ICAO) SUPPLEMENT 15/18 General QUEBEC REGION CHANGES AND RESTRICTIONS TO AIRSPACE IN CONJUNCTION WITH THE 2018 G7 SUMMIT MEETING LE MANOIR RICHELIEU, CHARLEVOIX, QUEBEC
More information2018 Nelson and Marlborough Airspace Review Initial consultation
2018 Nelson and Marlborough Airspace Review Civil Aviation Authority Table of Contents 1. 2018 Nelson and Marlborough airspace review... 1 2. Review process... 1 Scope of review... 1 a) Airways Corporation
More informationAERONAUTICAL SERVICES ADVISORY MEMORANDUM (ASAM) Focal Point: Gen
Page 1 of 6 1 INTRODUCTION Each route shall be assigned a designator that is unique for that aerodrome. The designator shall be defined in accordance with Annex 11, Appendix 3. In addition, the first 4
More informationUK Implementation of PBN
UK Implementation of PBN Geoff Burtenshaw Directorate of Airspace Policy UK Civil Aviation Authority 1 UK airspace context Presentation Overview Future Airspace Strategy (FAS) (FAS) Industry Implementation
More informationAir Traffic Management (GTA) First semester, 2017/2018
Instituto Superior Técnico Air Traffic Management (GTA) First semester, 2017/2018 First test Solution proposal Name: Number: Read carefully each question before answering The answers should be given exclusively
More informationSID/STAR phraseology FAQ Canadian implementation April 27, 2017
SID/STAR phraseology FAQ Canadian implementation April 27, 2017 The International Civil Aviation Organization (ICAO) has developed harmonized phraseology for Standard Instrument Departures (SIDs) and Standard
More informationPerformance Based Navigation Operational End-State 2023
Performance Based Navigation Operational End-State 2023 A Regulatory View Organisation Civil Aviation Authority of New Zealand Date of this Document November 2018 Authored by: Primary Author: Ray Harvey,
More informationQueenstown control zone amendments User consultation
Civil Aviation Authority Table of Contents 1. Introduction... 1 2. Proposed changes... 1 NZT252 Ridge Peak... 1 NZG755 Coronet Peak... 2 3. Consultation... 3 4. Submissions... 4 5. Further information...
More information2016 Manawatu Airspace Review
Civil Aviation Authority Table of Contents 1. 2015 Manawatu airspace review... 1 2. Review Process... 1 Scope of review... 1 a) Airways Corporation of New Zealand... 2 b) Aerodrome operators... 2 c) Airline
More informationNAV CANADA 26/09/2017 MAGNETIC VS TRUE NORTH. Vision to Captain Anthony MacKay Director Flight Operations
26/09/2017 MAGNETIC VS TRUE NORTH Vision to 2030 Captain Anthony MacKay Director Flight Operations THE ISSUE Which way is North? All of the aircraft, air traffic and IFR procedure design systems are built
More informationSafety Enhancement RNAV Safe Operating and Design Practices for STARs and RNAV Departures
Safety Enhancement Action: Implementers: Statement of Work: Safety Enhancement 213.5 RNAV Safe Operating and Design Practices for STARs and RNAV Departures To mitigate errors on Standard Terminal Arrival
More informationIRELAND AERONAUTICAL INFORMATION SERVICES IRISH AVIATION AUTHORITY CONTROL TOWER SHANNON AIRPORT
IRELAND AIC AERONAUTICAL INFORMATION SERVICES IRISH AVIATION AUTHORITY Nr 10/02 CONTROL TOWER SHANNON AIRPORT 31 OCT CO. CLARE Tel +353 61 471954 Fax +353 61 471965 AFTN EINNYNYX OPERATIONS AT WESTON 1.
More informationPBN and airspace concept
PBN and airspace concept 07 10 April 2015 Global Concepts Global ATM Operational Concept Provides the ICAO vision of seamless, global ATM system Endorsed by AN Conf 11 Aircraft operate as close as possible
More information1. RESPONSIBLE SERVICES 2. MAINTENANCE OF CHARTS 3. PURCHASE ARRANGEMENTS 4. AERONAUTICAL CHART SERIES AVAILABLE GEN APR 2015 AIP HUNGARY
GEN 3.2-1 GEN 3.2 AERONAUTICAL CHARTS 1. RESPONSIBLE SERVICES 1.1. The aeronautical charts for the territory of are published by Pte. Ltd. Co. The charts are provided by the Publications and Static Data
More informationNEW FPL Transition Phase & Implementation Stages
International Civil Aviation Organization NEW FPL 2012 Transition Phase & Implementation Stages Victor Hernandez RO ATM/SAR New FPL implementation & Switchover Review the New FPL Strategy & Implementation
More informationPBN AIRSPACE CONCEPT WORKSHOP. SIDs/STARs/HOLDS. Continuous Descent Operations (CDO) ICAO Doc 9931
International Civil Aviation Organization PBN AIRSPACE CONCEPT WORKSHOP SIDs/STARs/HOLDS Continuous Descent Operations (CDO) ICAO Doc 9931 Design in context Methodology STEPS TFC Where does the traffic
More informationAERONAUTICAL STUDY REVIEW OF AIR TRAFFIC SERVICE REQUIREMENTS AT SUDBURY, ONTARIO
AERONAUTICAL STUDY REVIEW OF AIR TRAFFIC SERVICE REQUIREMENTS AT SUDBURY, ONTARIO Prepared by: NAV CANADA Level of Service and Aeronautical Studies 77 Metcalfe Street, 5 th Floor Ottawa, Ontario K1P 5L6
More informationINSTRUMENT RATING (SENIOR PRIVATE PILOT) UK FLIGHT TEST STANDARDS
INSTRUMENT RATING (SENIOR PRIVATE PILOT) UK FLIGHT TEST STANDARDS This document applies to Senior Private Pilot exams within UK airspace only, and should not be used elsewhere as some subjects are only
More informationSafety and Airspace Regulation Group. 31 May Policy Statement STANDARD INSTRUMENT DEPARTURE TRUNCATION POLICY.
Safety and Airspace Regulation Group 31 May 2018 Policy Statement STANDARD INSTRUMENT DEPARTURE TRUNCATION POLICY 1 Introduction 1.1 This Policy Statement (PS) presents CAA policy and guidance to Air Navigation
More informationAeronautical Studies (Safety Risk Assessment)
Advisory Circular Aeronautical Studies (Safety Risk Assessment) FIRST EDITION GEORGIAN CIVIL AVIATION AGENCY Chapter LIST OF EFFECTIVE PAGES Pages Amend. No Date of Issue List of effective pages 2 0.00
More informationAirspace Establishment Project Frequently Asked Questions Permanent SUA and Environmental Assessment March 2019
OVERVIEW OF PERMANENT SPECIAL USE AIRSPACE ESTABLISHMENT AND MODIFICATIONS AT MARINE AIR GROUND TASK FORCE TRAINING COMMAND, TWENTYNINE PALMS, CA 1. What is Special Use Airspace (SUA)? Special Use Airspace
More informationPBN IMPLEMENTATION IN INDONESIA
PBN IMPLEMENTATION IN INDONESIA Program For The PBN Workshop For ATC I Wayan Sudiartha Head of the Standardization and Certification Division Profile of AirNav Indonesia Establishment : o Declared by Government
More informationPBN Performance. Based Navigation. - PBN & Airspace Concepts - ICAO PBN Seminar Introduction to PBN
PBN Performance Based Navigation - PBN & Airspace Concepts - Introduction to PBN 1 Learning Objectives PBN Concept within the context of an Airspace (Operational) Concept. Introduction to PBN 2/37 Components
More information1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION
1.1.3 Taxiways EWN has an extensive network of taxiways and taxilanes connecting the terminal, air cargo, and general aviation areas with the runways as listed in Figure 1-15. A 50-foot wide parallel taxiway
More informationFederal Aviation Administration. Air Traffic 101. By: Michael Valencia & Dianna Johnston Date: Feb. 26, 2017
Presented to: UC Davis Aviation Symposium By: Michael Valencia & Dianna Johnston Date: Overview Part 1 Air Traffic Controllers History Safety and Navigation Terminology Air Traffic Facility Types Equipment
More informationATC Training Syllabus Philippines vacc Version 1.1 September 25, 2016
ATC Training Syllabus Philippines vacc Version 1.1 Intor Distribution and Scope This document outlines the training that will be undergone by students within the Philippines vacc and shall be used by both
More informationPOST-IMPLEMENTATION COMMUNITY IMPACT REVIEW
POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Winnipeg James Armstrong Richardson International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 November
More informationEFFECTIVE 0901Z 29 MARCH 2018 TO 0901Z 24 MAY 2018 AIP CANADA (ICAO) Part 3 Aerodromes (AD)
EFFECTIVE 0901Z 29 MARCH 2018 TO 0901Z 24 MAY 2018 AIP CANADA (ICAO) Part 3 Aerodromes (AD) Published by in accordance with ICAO Annexes 4 and 15 of the Convention on International Civil Aviation 2018
More informationPi Aero Instrument Rating Syllabus
This syllabus was created in order to maintain a high level of positive training as well as meet the minimum hours required by the Federal Aviation Regulations Part 61. There are four sections to this
More informationAREA NAVIGATION RNAV- MANAGEMENT
1. Introduction AREA NAVIGATION RNAV- MANAGEMENT RNAV is an instrument-based navigation method that leads to fly from a fix (geographic point inside an airspace) to another fix directly. Contrary to conventional
More informationAIRSPACE STRUCTURE. In aeronautics, airspaces are the portion of the atmosphere controlled by a country above its territory.
AIRSPACE STRUCTURE 1. Introduction In aeronautics, s are the portion of the atmosphere controlled by a country above its territory. There are two kinds of : Controlled is of defined dimensions within which
More informationPOST-IMPLEMENTATION COMMUNITY IMPACT REVIEW
POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Edmonton International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 January 2018 The information
More informationTerminal Airspace Design Guidelines - Part C
CHAPTER 8 - DESIGN METHODOLOGY: QUICK REFERENCE LISTS - This Chapter is comprised of one diagram which brings together the elements of the Design Methodology. It also contains six Attachments; each of
More informationSOUTH AFRICA PBN NEAR TERM IMPLEMENTATION PLAN PROJECT
PRE-PLANNING PHASE Nomination of the State Focal Point of Contact Appointment of the South Africa PBN Project Manager and Team Define the goals and objectives of Project Define the Terms of Reference for
More informationCAT E Subject to NOTAM: No
AIRSPACE CO-ORDINATION NOTICE Safety and Airspace Regulation Group ACN Reference: Version: Date: Date of Original 2015-09-0091 V1.0 10 June 2016 10 June 2016 TALLA DVOR/DME CALIBRATION CAT E Subject to
More informationMODULE 4: SIDs and STARs. Slide <#> of
MODULE 4: SIDs and STARs Slide of OUTLINE Objective: To understand SIDs and STARs and their applications CONTENT: WHAT ARE SIDS AND STARS COMMON ELEMENTS CHARTS PROCESSING OF SIDS AND STARS VECTORING
More informationAERONAUTICAL INFORMATION CIRCULAR 11/16
NAV CANADA 26 MAY 16 AERONAUTICAL INFORMATION CIRCULAR 11/16 Introduction DEPICTION OF FIVE-NAUTICAL-MILE BUFFERS AROUND SPECIAL USE AIRSPACE CONTAINED WITHIN CANADIAN FLIGHT INFORMATION REGIONS (Supersedes
More informationAIP PORTUGAL ENR NOV-2007
AIP PORTUGAL ENR 1.6-1 ENR 1.6 RADAR SERVICES AND PROCEDURES PROVISION OF RADAR SERVICES WITHIN LISBOA AND SANTA MARIA FIR / UIR Introduction Air Traffic Control Services within Lisboa and Santa Maria
More informationUnderstanding the Jeppesen. Updates: Changes, Errata and What s New
Understanding the Jeppesen Updates: Changes, Errata and What s New www.understandingaviation.com info@understandingaviation.com Table of Contents Changes... 1 Errata... 5 What s New... 5 Changes Law Amendment
More informationCivil Instrument Flight Rules at Military Aerodromes or in Military Controlled Airspace
Federal Departement of the Environment, Transport, Energy and Communications DETEC Federal Office of Civil Aviation FOCA Safety Division - Flight Operations FOCA GM/INFO Guidance Material / Information
More information1- Wher can you find the difference between ICAO standards and Iran regulation and procedure? a) GEN 2.5 b) ENR 3 c) GEN 1.
1- Wher can you find the difference between ICAO standards and Iran regulation and procedure? a) GEN 2.5 b) ENR 3 c) GEN 1.7 d) ENR l 2- Which part of AIP contain conversion table? a) GEN 1 b) GEN 2 c)
More informationValidation Plan & Objectives. Maik Friedrich, DLR PJ05 Braunschweig, 22 of November 2017
Validation Plan & Objectives Maik Friedrich, DLR PJ05 Braunschweig, 22 of November 2017 Validation Plan Overview of Remote Tower Activities in SESAR 2020 2 Remote Tower PJ.05 DLR (AT-One) Remotely Provided
More informationEastern Caribbean PIARCO Virtual FIR. PIARCO Control Zone (CTR)
PIARCO Control Zone (CTR) Eastern Caribbean PIARCO Virtual FIR NOT TO BE USED FOR REAL WORLD AVIATION, STRICTLY FOR USE ON THE VATSIM VIRTUAL ATC NETWORK. 1. Introduction 1.1 Objective of this SOP is to
More informationNDS Subject to NOTAM: No
AIRSPACE CO-ORDINATION NOTICE Safety and Airspace Regulation Group ACN Reference: Version: Date: Date of Original 2017-00-0131 1.1 29 November 2016 29 November 2016 RAF VALLEY (MONA) MSSR CALIBRATION NDS
More informationAVIA 3133 INSTRUMENT PROCEDURES UNIVERSITY OF OKLAHOMA
AVIA 3133 INSTRUMENT PROCEDURES UNIVERSITY OF OKLAHOMA, 20 I,, have acquired and have in my possession a copy of the training course outline, training syllabus, and safety procedures and practices for
More informationSection 5. Radar Separation
7/24/14 JO 7110.65V CHG 1 4/3/14 JO 7110.65V Section 5. 5 5 1. APPLICATION a. Radar separation must be applied to all RNAV aircraft operating at and below FL450 on Q routes or random RNAV routes, excluding
More informationICAO Big Data Project ADS-B Data as a source for analytical solutions for traffic behaviour in airspace
ICAO Big Data Project ADS-B Data as a source for analytical solutions for traffic behaviour in airspace ICAO/IATA/CANSO PBN/2 San Jose December 8, 2016 Big Data process Quantitative Quantitative / Qualitative
More informationPOST-IMPLEMENTATION COMMUNITY IMPACT REVIEW
POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Halifax Stanfield International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 November 2017 The information
More informationAIR LAW AND ATC PROCEDURES
1 The International Civil Aviation Organisation (ICAO) establishes: A standards and recommended international practices for contracting member states. B aeronautical standards adopted by all states. C
More informationOptimization of Airspace and Procedures in the Metroplex
Optimization of Airspace and Procedures in the Metroplex Administration SoCal Metroplex Project Overview Brief To: By: Los Angeles World Airport Rob Henry, Manager SoCal Metroplex Jose Gonzalez, SoCal
More informationEffective: AUSTRALIAN INTERNATIONAL AIRSHOW AVALON 2019, AVALON AIRPORT 19 FEBRUARY - 5 MARCH 2019, IFR OPERATIONS AVALON AIRPORT
AUSTRALIA AERONAUTICAL INFORMATION SERVICE AIRSERVICES AUSTRALIA GPO BOX 367, CANBERRA ACT 2601 Phone: 02 6268 4874 Email: aim.editorial@airservicesaustralia.com Effective: AIP SUPPLEMENT (SUP) H 02/19
More information4.1 This document outlines when a proposal for a SID Truncation may be submitted and details the submission requirements.
Safety and Airspace Regulation Group 13 May 2014 Policy Statement STANDARD INSTRUMENT DEPARTURE TRUNCATION POLICY 1 Introduction 1.1 This Policy Statement (PS) is intended to provide guidance to ANSPs
More informationCHAPTER 15. (Volume 3 Bound Separately) Loch Urr Aviation Impact Assessment
CHAPTER 15 15.0 AVIATION... 1 15.1 Introduction... 1 15.2 Methodology... 3 15.3 Baseline... 8 15.4 Assessment of Effects... 12 15.5 Mitigation... 15 15.6 Residual Effects and Conclusions... 18 15.7 References...
More informationIFR SEPARATION USING RADAR
IFR SEPARATION USING RADAR 1. Introduction When flying IFR inside controlled airspace, air traffic controllers either providing a service to an aircraft under their control or to another controller s traffic,
More informationClass Alpha. In addition, if you fly above FL240 your aircraft must have DME or a suitable RNAV system.
Go For It Class Alpha Class A airspace is from 18,000 feet MSL to Flight Level 600 (60,000 feet pressure altitude). Its lateral extent includes the contiguous U.S. and Alaska, and extends 12 nm from the
More informationTHIS BULLETIN REPLACES BULLETIN WHICH IS NO LONGER CURRENT AND HAS BEEN WITHDRAWN.
IBAC Bulletin 16-03 THIS BULLETIN REPLACES BULLETIN 16-01 WHICH IS NO LONGER CURRENT AND HAS BEEN WITHDRAWN. Subject: Performance-based Navigation in Australian airspace - General guidance on the GNSS
More informationAppendix K: MSP Class B Airspace
Appendix K: MSP Class B Airspace K All of the open sky covering the United States, from less than an inch off the ground all the way to outer space, is part of America s airspace. This airspace resource
More information(Presented by the Secretariat) SUMMARY. This Working Paper presents for the Meeting s consideration, the Draft Agenda and suggested schedule
NACC/WG/2- WP/01 Rev. International Civil Aviation Organization 23/04/08 North American, Central American and Caribbean Office Second North American, Central American and Caribbean Working Group Meeting
More informationBilly Bishop Toronto City Airport; Porter Airlines Proposal Review; Interim Results/Findings, Airbiz, 26 June 2013
Billy Bishop Toronto City Airport - Outstanding Questions for Transport Canada EXECUTIVE SUMMARY Transport Action has reviewed the reports published by Airbiz and LPS Avia Consulting and found that they
More informationPurpose This Advisory Circular provides information and guidance to assist aerodrome operators and other parties to undertake an aeronautical study.
Advisory Circular AC139-15 Revision 0 Aeronautical Studies for Aerodrome Operators 23 February 2011 General Civil Aviation Authority Advisory Circulars contain information about standards, practices, and
More informationAirport Safety Management Systems: Integrating Planning Into the Process
Airport Safety Management Systems: Integrating Planning Into the Process Kenneth Jacobs Senior Airport Planner FAA Airport Planning and Environmental Division ken.jacobs@faa.gov SMS Defined A process for
More information2016 Waikato and Bay of Plenty Airspace Review v1.1
2016 Waikato and Bay of Plenty Airspace Review v1.1 Civil Aviation Authority Table of Contents 1. 2016 Waikato and Bay of Plenty airspace review... 1 2. Review Process... 1 Scope of review... 1 a) Airways
More informationTHE TOWER CONTROL POSITION (TWR)
1. Introduction THE TOWER CONTROL POSITION (TWR) The Aerodrome Local Control, or Tower (called TWR) controller has the responsibility of ensuring Air Traffic Control (ATC) Services within a restricted
More informationPBN Airspace Concept. ATS requirements
INTERNATIONAL CIVIL AVIATION ORGANIZATION PBN Airspace Concept ATS requirements Victor Hernandez RO ATM/SAR ICAO North America, Central America and Caribbean Regional Office 1 Gate to Gate concept Phases
More informationAnchorage ARTCC Phraseology Guide. Clearance Delivery Operations
Anchorage ARTCC Phraseology Guide Clearance Delivery Operations Initial Contact: The first time an aircraft calls you, you MUST identify your position, i.e. AWE123 Anchorage Delivery. Clearance Delivery:
More informationFINAL REPORT BOEING B777, REGISTRATION 9V-SWH LOSS OF SEPARATION EVENT 3 JULY 2014
FINAL REPORT BOEING B777, REGISTRATION 9V-SWH LOSS OF SEPARATION EVENT 3 JULY 2014 AIB/AAI/CAS.109 Air Accident Investigation Bureau of Singapore Ministry of Transport Singapore 11 November 2015 The Air
More informationIRISH AVIATION AUTHORITY DUBLIN POINT MERGE. Presented by James O Sullivan PANS-OPS & AIRSPACE INSPECTOR Irish Aviation Authority
IRISH AVIATION AUTHORITY DUBLIN POINT MERGE Presented by James O Sullivan PANS-OPS & AIRSPACE INSPECTOR Irish Aviation Authority 2012 Holding Holding Before Point Merge No Pilot anticipation of distance
More informationCOMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE SECRETARY OF THE AIR FORCE AIR FORCE INSTRUCTION 11-201 30 NOVEMBER 2018 Flying Operations FLIGHT INFORMATION PUBLICATIONS COMPLIANCE WITH THIS PUBLICATION IS MANDATORY ACCESSIBILITY: Publications
More informationRNP AR APCH Approvals: An Operator s Perspective
RNP AR APCH Approvals: An Operator s Perspective Presented to: ICAO Introduction to Performance Based Navigation Seminar The statements contained herein are based on good faith assumptions and provided
More informationAERODROME CHART ATIS CLNC DEL
EFF 10 NOV 16 AERODROME CHART ATIS 121.0 CLNC DEL 123.95 GND 121.9 275.8 -AD TWR 118.4 236.6 TML 119.2 DECL DISTS 05 23 14 32 TORA 10500 10500 7700 7700 TODA 11189 11189 8684 8684 ASDA 10500 10500 7700
More informationIMPLEMENTATION OF ADS-B BY NAV CANADA
IMPLEMENTATION OF ADS-B BY NAV CANADA Carole Stewart-Green Manager, ATS Regulatory Coordination ABOUT NAV CANADA Private, non-share capital company Second largest ANSP in the world 12 million aircraft
More informationImplementation of PBN in Armenian airspace
Implementation of PBN in Armenian airspace PBN implementation plan, based on the specifications of the airspace of the Republic of Armenia, has been developed in accordance with Resolution A36-23, approved
More informationProposed Changes to Inverness Airport s Airspace The Introduction of Controlled Airspace and Optimisation of Instrument Flight Procedures
Proposed Changes to Inverness Airport s Airspace The Introduction of Controlled Airspace and Optimisation of Instrument Flight Procedures What is an Airspace Change Proposal? It is a formal UK Civil Aviation
More informationDesign Airspace (Routes, Approaches and Holds) Module 11 Activity 7. European Airspace Concept Workshops for PBN Implementation
Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7 European Airspace Concept Workshops for PBN Implementation Design in Context TFC Where does the traffic come from? And when? RWY Which
More informationUK Performance-based Navigation (PBN) Implementation Status
UK Performance-based Navigation (PBN) Implementation Status Geoff Burtenshaw Technical Advisor, Navigation Systems Directorate of Airspace Policy 1 Current Implementation of PBN in UK Airspace 2 Current
More information