Application to Impose and Use Passenger Facility Charges - #16

Size: px
Start display at page:

Download "Application to Impose and Use Passenger Facility Charges - #16"

Transcription

1 Application to Impose and Use Passenger Facility Charges - #16 Submitted to: The Federal Aviation Administration By: The Des Moines International Airport

2 June 23, 2017 Ms. Sheila Bridges PFC Coordinator FAA Central Region Airports Division Airports Division Ace 615E 901 Locust Street Kansas City, MO RE: DSM Passenger Facility Charge Application #16 Dear Ms. Bridges: Enclosed is Des Moines Airport Authority s Application to Impose and Use Passenger Facility Charges in accordance with Federal Aviation Regulation (FAR) Part 158. Should any additional information be needed in your review of this application, please contact me directly at or bcmulcahy@dsmairport.com. We appreciate your earlier assistance with the initial review of our application prior to the airline consultation and any assistance you can provide in working through the remainder of the process. Sincerely, Brian C. Mulcahy Director of Finance Enclosure Des Moines Airport Authority, 5800 Fleur Drive, Room # 201, Des Moines, IA 50321; T ; F ;

3 PFC Application #16 Table of Contents Section 1. FAA Form Assurances 3. Capital Improvement Program Budget 4. Attachment B a. Runway 13/31 Reconstruction b. Runway 05/32 Reconstruction c. Airport Documentation Update d. Terminal Programming Phase II 5. Airline Consultation a. Consultation Meeting Notification b. Summary of Meeting c. Airline Response Letters i. Airline #1 ii. Airline #2 6. Public Notice

4 OMB Approved Exp. 8/31/2013 Federal Aviation Administration U. S. Department of Transportation PASSENGER FACILITY CHARGE (PFC) APPLICATION 1. Application Type (Check all that apply) FAA USE ONLY a. Impose PFC Charges b. Use PFC Revenue Date Received PFC Number c. Amend PFC No. PART I 2. Public Agency Name, Address, and Contact Person 3. Airport(s) to Use 4. Consultation Dates Agency Name _Des Moines Airport Authority Address _5800 Fleur Drive, Suite 207 City, State, ZIP Des Moines, IA Contact Person Brian Mulcahy 5. Charges a. Airport to Impose Des Moines International Des Moines International (DSM) PART II b. Level c. Total Estimated PFC Revenue by Level Impose $1.00 $2.00 $3.00 Use Impose $7,724,227 $4.00 $4.50 Use $7,724,227 PART III a. Date of Written Notice to Air Carriers: July 5, 2017 b. Date of Consultation Meeting with Air Carriers: August 8, 2017 c. Date of Public Notice August 9, 2017 d. Proposed Effective Date: October 1, 2024 e. Estimated Expiration Date: October 1, Attachments (Check all that Apply) Attached Submitted with Application Number Document a. b. c. d. e. f. g. h. i. Airport Capital Improvement Plan Project Information (Attachment B) Air Carrier Consultation and Public Notice Information Request to Exclude Class(es) of Carriers Alternative Uses/Projects Competition Plan/Update ALP/Airspace/Environmental Notice of Intent Project Information PART IV 7. With respect to this PFC application I hereby certify as follows: To the best of my knowledge and belief, all data in this application are true and correct; This application has been duly authorized by the governing body of the public agency; The public agency will comply with the assurances (Appendix A to Part 158) if the application is approved; For those projects for which approval to use PFC revenue is requested, all applicable ALP approvals, airspace determinations, and environmental reviews required by the National Environmental Policy Act have been completed. If required, the public agency has submitted a competition plan in accordance with 49 U.S.C (f); and If required by 49 U.S.C (d)(4), adequate provision for financing the airside needs, including runways, taxiways, aprons, and gates, has been made by the public agency. a. Typed Name of Authorized Representative b. Title c. Telephone Number Director of Finance Brian Mulcahy d. Address bcmulcahy@dsmairport.com e. Fax Number f. Signature of Authorized Representative g. Date Signed Paperwork Reduction Act Statement: This form is the FAA s primary source for collecting information for the authority to collect PFC revenue for airport development. This information is used to determine the eligibility and justification of airport development projects regarding safety, security, or capacity of the national air transportation system; or which reduce noise or mitigate noise impacts resulting from an airport; or furnish opportunities for enhanced competition between or among air carriers. It is estimated that it will take approximately 5-80 hours to fill out the application depending on the complexity. The use of the form is required to obtain FAA approval of authority to collect PFC revenue (49 U.S.C (c)). No assurance of confidentiality is necessary or provided. It should be noted that an agency may not conduct or sponsor, and a person is not required to respond to a collection of information unless it displays a currently valid OMB control number. The OMB control number associated with this collection of information is Comments concerning the accuracy of this burden and suggestions for reducing the burden should be directed to the FAA at: 800 Independence Ave. SW, Washington, DC, 20591, Attn: Information Collections Clearance Officer, AIO-20. FAA Form (8-10) Supersedes Previous Edition

5 FAA Fiscal Year 2018 Five Year Capital Improvement Program (CIP) Des Moines International Airport (DSM) Date: 2/8/17 Telephone: Project Phase VI - 1,850 ft Runway 13 Rehab with RSA of Intersection Phase I - Engineering Analysis Rwy 5/23, Phase II - Design Rnwy 5 Reconstruct Airfield Pavement Maintenance Program Update GA/FBO Phase I - site development Bld 34 - box hangar demolition Bld 33 - box hangar relocation Phase III - Runway 5 Reconstruct - West of Intersection including R3/P3 RIM removal. Phase IV - Design Runway 23 Reconstruct GA/FBO Phase II - Apron Phase V - Reconstruct Runway 23,Bravo - East of Intersection Design/Reconstruction Taxiway Papa Terminal Apron "A" - Design Phase I Terminal Apron "A" - Demolition of existing buildings/apron. Phase II Interior Service Rd - pavement to utilize for fueling access Terminal Apron "A" - Reconstruction Phase III Terminal Apron "B" - Design Phase IV Building 35 - Demolition/Apron Removal Funding FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Notes Source Federal 11,731, State Local 1,303, Total 13,035, Federal 928, State Local 103, Total 1,032, Federal 108, State Local 12, Total 120, Federal 6,100, State Local 677, Total 6,778, Federal 1,163, State Local 129, Total 1,293, Federal 1,821, State Local 202, Total 2,023, Federal - 9,459, State Local - 1,051, Total - 10,510, Federal - 876, State Local - 97, Total - 974, Federal - 8,633, State Local - 959, Total - 9,592, Federal ,036, State Local - - 1,892, Total ,929, Federal - - 2,079, State Local , Total - - 2,310, Federal , State Local , Total , Federal - - 2,610, State Local , Total - - 2,900, Federal , State Local , Total , Federal ,882,000 - State Local ,098,000 - Total ,980,000 - Federal ,000 - State Local ,000 - Total ,000 - Federal ,363,158 - State Local ,575 - Total ,625,733 - Intersection safety area pavement reconstruct of Rwy 13/31 only. Compression seals on Twy Delta. Keep compressions joints seals separate. Show Div 1 & 2. Still AIP eligible. Design of Bravo to meet standards is included. 4 years since last performed. Beneficial for 5/23 programming & analysis. Bring existing site up to grade, perform install of site utilities and fencing Demolition of this hangar as required per Terminal master plan. Hangar is at its end of life. Associated apron will be demoed as well. Relocation of existing hangar to allow master plan for relocations. Demolition is eligible. Anything above and beyond this responsibility of the Airport Includes removal of Twy R3 and P3 (Hotspot) and relocation of Twy P4 apron connector to meet design standards. Added Twy Delta area to assist in shifting of projects and keeping flow of traffic moving. Will include the design and relocation of Bravo to meet design standards. Show $90k funding for R.A. Paving of GA/FBO Apron and parking. 50' outside of the building is responsbility of the Airport. Intersection safety area pavement reconstruct of Rwy 5/23 incl. (a)discuss non standard option. Raise 23 end approximately 2'. This will also assist in Terminal elevation to maintain no elevation change within building. (b)can aircraft be square to 23 off of Papa? Includes design and CA/CO. Reconstructed apron/ron parking located at old East GA apron Demolition of relocated FBO buildings and associated apron in preparation for new apron and Terminal building. Could shift this project to 2021 and occur with Apron A reconstruction. Interior access road for fuel trucks to gain access to Terminal ramp. Single lane w/ pulloff locations. Associated with demo of East GA complex. Centralized De Icing Pads and RON parking locations. Removal of building/apron for future hangars/apron. Page 1 of 2

6 FAA Fiscal Year 2018 Five Year Capital Improvement Program (CIP) Des Moines International Airport (DSM) Date: 2/8/17 Telephone: Project Terminal Apron "B" - Reconstruction Phase IV Funding FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Notes Source Federal ,940,000 State Centralized De Icing Pads and RON parking locations. Local ,000 Total ,600,000 Terminal AIP Annual Total Costs FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Totals Federal $ 21,854,318 $ 18,969,329 $ 22,838,310 $ 12,765,158 $ 5,940,000 $ 82,367,114 State $ - $ - $ - $ - $ - $ - Local $ 2,428,258 $ 2,107,704 $ 2,537,590 $ 1,420,575 $ 660,000 $ 9,154,126 Total $ 24,282,575 $ 21,077,032 $ 25,375,900 $ 14,185,733 $ 6,600,000 $ 91,521,240 Runway AIP Annual Total Costs FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Totals Federal $ 12,768,390 $ 10,335,921 $ 22,445,100 $ 10,402,000 $ 5,940,000 $ 61,891,411 State $ - $ - $ - $ - $ - $ - Local $ 1,418,710 $ 1,148,436 $ 2,493,900 $ 1,158,000 $ 660,000 $ 6,879,046 Total $ 14,187,100 $ 11,484,357 $ 24,939,000 $ 11,560,000 $ 6,600,000 $ 68,770,457 Project Terminal Area Environmental Assessment Terminal Design Passenger Facility Charge Projects Funding Source FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Notes Federal $ - $ - State $ - $ - Local $ 550,000 PFC Funds Total $ 550,000 $ - $ - $ - Federal $ - $ - $ - $ - State $ - $ - $ - Entitlement funding only can be used (cargo cannot be Local $ - $ - $ 22,500,000 $ 22,500,000 used) Total $ - $ - $ - $ 22,500,000 $ 22,500,000 PFC Annual Total Costs FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Totals Federal $ - $ - $ - $ - $ - State $ - $ - $ - $ - $ - Local $ 550,000 $ - $ - $ 22,500,000 $ 22,500,000 $ 45,550,000 Total $ 550,000 $ - $ - $ 22,500,000 $ 22,500,000 $ 45,550,000 Page 2 of 2

7 Des Moines International Airport PFC Application 16 Project PFC Request Runway (PH VI) 1,303,510 Runway (PH I through V) and Apron 3,789,226 Airport Documentation Update 239,722 Terminal Programming 2,391,769 Total $ 7,724,227

8 PFC Application #16 TOTAL Reconstruction of 13/31 Phase VI $1,303, Project Reconstruction of 13/31 Phase VI AIP Grant Total Cost Entitlement Discretionary Local PFC Request Phase VI 1850 ft Runway 13 13,035,100 4,411,772 7,319,818 1,303,510 1,303,510 13,035,100 4,411,772 7,319,818 1,303,510 1,303,510

9 PFC APPLICATION NUMBER: DSM PFC Application #16 ATTACHMENT B: PROJECT INFORMATION 1. Project Title: Runway 13/31 Reconstruction Phase VI 2. Project Number 3. Use Airport of Project: Des Moines International (DSM) 4. Project Type [ ] Impose Only: [ X ] Concurrent: [ ] Use Only: Link to application: 5. Level of Collection: [ ] $1.00 [ ] $2.00 [ ] $3.00 [ ] $4.00 [ X ] $ Financing Plan PFC Funds: Pay-as-you-go $ 1,303,510 Bond Capital $ Bond Financing & Interest $ Subtotal PFC Funds*: $ 1,303,510 If amount is over $10 million, include cost details sufficient to identify eligible and ineligible costs. Existing AIP Funds: Grant # Grant Funds in Project Subtotal Existing AIP Funds: Anticipated AIP Funds (List Each Year Separately): Fiscal Year: 2018 Entitlement $4,411,772 Discretionary $ 7,319,818 Total $ 11,731,590 Fiscal Year: Entitlement $0 Discretionary $ 0 Total $ Subtotal Anticipated AIP Funds: $ 11,731,590

10 Other Funds: State Grants $ Local Funds Other (please specify) $ Subtotal Other Funds: Total Project Cost: $13,035,100 For FAA Use a. Does the project include a proposed LOI? [ ] YES [ ] NO If YES, does the Region support? [ ]YES [ ] NO. If YES, list the schedule for implementation: b. For any proposed AIP discretionary funds, does the Region intend to support? [ ] YES [ ] NO c. For any proposed AIP funds, is the request within the planning levels for the Region's five year CIP? [ ] YES [ ] NO d. For project requesting PFC funding levels of $4.00 and $4.50: Is there an expectation that AIP funding will be available to pay the project costs. [ ] YES [ ] NO What percentage of the total project cost is funded through AIP? List the source(s) of data used to make this finding. e. Terminal and surface transportation projects requesting a PFC funding level of $4.00 and $4.50. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ ] YES [ ] NO [ ] N/A List the source(s) of data used to make this finding. f. Reasonableness of cost. Project Total Cost Analysis

11 PFC Share of Total Cost Analysis 7. Back-up Financing Plan: The 2018 portion of this project consists of reconstruction of runway 13/31. If discretionary AIP funding is not available for work to be completed, the construction will be delayed until adequate entitlement money is available to complete the project. If proposed AIP discretionary funds or a proposed LOI are included in the Financing Plan, provide a Back-up Financing Plan or a project phasing plan in the event the funds are not available for the project. For FAA Use If required to use a back-up financing/phasing plan, indicate the need to obtain additional approvals to obtain an alternate source of financing. Indicate the additional PFC duration of collection required if PFC s are to be used to fund the difference. Recap any discussion from previous item regarding likelihood of public agency obtaining the funding it proposes. 8. Project Description: Reconstruct 1,850 ft Runway 13 end and reconstruct safety area pavement at intersection of Runway 5/23 and 13/31, Taxiway D Compression Seals. If applicable for terminal projects, Prior to implementation of this project, Number of ticket counters: Number of gates: Number of baggage facilities: At completion of this project, Number of ticket counters: Number of gates: Number of baggage facilities: Net change due to this project: Number of ticket counters: Number of gates: Number of baggage facilities: Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates.

12 [ X ] YES [ ] NO [ ] N/A FOR FAA USE Comment upon and/or Clarify Project Description. Include source citation if clarification information is not from PFC application. If project involves the construction of a new runway or modification of an existing runway, have the requirements of Order , with regard to runway safety areas been met? If not, is the runway grandfathered or has a modification been approve, or is there a likelihood the requirements will be met, or should the project be disapproved. If the project involves terminal work, confirm information regarding ticket counters, gates, and baggage facilities for construction and/or rehabilitation above has been completed. Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ ] YES [ ] NO [ ] N/A 9. Significant Contribution: FOR FAA USE Air safety. Part 139 [ ] Other (explain) Certification Inspector concur. Yes [ ] No [ ] Date Air security. Part 107 [ ] Part 108 [ ] Other (explain) CASFO concur. Yes [ ] No [ ] Date Competition. Competition Plan [ ] Other (explain) Congestion. Current [ ] or Anticipated [ ] LOI [ ] FAA BCA [ ] FAA Airport Capacity Enhancement Plan [ ] Other (explain) Noise. 65 LDN [ ] Other (explain) Project does not qualify under significant contribution rules.

13 Quantitative and qualitative analysis of significant contribution option chosen by public agency. If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. How does this project address the deficiency sited by the public agency? If competition is the chosen option, provide the FAA s analysis of any barriers to competition at the airport. 10. Project Objective: This project will enhance the safety of Des Moines International Airport by ensuring the runway environment meets the FAA specifications. FOR FAA USE Safety, Preserve [ ] Enhance [ ] Security, Preserve [ ] Enhance [ ] Capacity, Preserve [ ] Enhance [ ] Furnish opportunity for enhanced competition between or among air carriers at the airport Mitigate noise impacts resulting from aircraft operations at the airport Project does not meet any PFC objectives (explain) Finding Current deficiency. List the source(s) of data used to make this finding if it is not a part of the PFC application. Address adequacy of issues. 11. Project Justification: As detailed in the Functional Design Report for Runway 13/31 completed in 2014, Runway 13/31 has deteriorating pavement, profile that does not meet standards, and drainage and lighting systems that are failing. As part of this project approximately 1,850 ft of the 13 end of the runway will be reconstructed. Included with this project the full depth reconstruction of the safety area of Runway 5/23 within the intersection of Runways 13/31. The blast pad, and portions of Taxiway D6 will be reconstructed to allow for elevation adjustments. Project includes grading, drainage, lighting, markings along with the pavement improvements. Compression sealing of joints on this section of the runway as well as along Taxiway D will be performed as part of this project as well. It is anticipated that the MALSR lights may require elevation adjustment. Also includes cost of construction administration, observation, and material testing services.

14 FOR FAA USE Define how the project accomplishes PFC Objective(s) Explain how project is cost-effective compared to other reasonable and timely means to accomplish this objective(s) Based on informed opinion or published FAA guidance, specify how the cost of the project is reasonable compared to the capacity, safety, security, noise and/or competition benefits attributable to the project. Include citation for any documents that are not a part of this PFC application. If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. Discuss any non-economical benefits which are not captured above. Project Eligibility: Indicate project eligibility by checking the appropriate category below. [ ] Development eligible under AIP criteria (paragraph of Order _ or PGL ); [ ] Planning eligible under AIP criteria (paragraph of Order _ or PGL ); [ ] Noise compatibility planning as described in 49 U.S.C ; [ ] Noise compatibility measures eligible under 49 U.S.C [ ] Project approved in an approved Part 150 noise compatibility plan; Title and Date of Part 150: [ ] Project included in a local study. Title and Date of local study: [ ] Terminal development as described in 49 U.S.C (a)(3)(C); [ ] Shell of a gate as described in 49 U.S.C 40117(a)(3)(F) (air carrier, percentage of annual boardings ); [ ] PFC Program Update Letter [ ] Project does not meet PFC eligibility (explain). If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. Are any work elements or portions of the overall project ineligible? Provide associated costs. 12. Estimated Project Implementation Date (Month and Year): April 2018 Estimated Project Completion Date (Month and Year): November 2018 For FAA Use

15 For Impose and Use or Use Only projects, will the project begin within 2 years of PFC application Due date (120-day)? [ ] Yes [ ] No For Impose Only project, will the project begin within 5 years of the charge effective date or PFC application Due date, whichever is first? [ ] Yes [ ] No Is this project dependent upon another action to occur before its implementation or completion. Explain. 13. For an Impose Only project, estimated date Use application will be submitted to the FAA (Month and Year): For FAA Use Is the date within 3 years of the estimated charge effective date or approval date, whichever is sooner. [ ] Yes [ ] No Which actions are needed before the use application can be submitted? What is the estimated schedule for each action? 14. Project requesting PFC funding levels of $4.00 and $4.50: a. Can project costs be paid for from funds reasonably expected to be available through AIP funding. [ ] YES [ X ] NO b. If the FAA determines that the project may qualify for AIP funding, would the public agency prefer that the FAA approve [ X ] the amount of the local match to be collected at a $4.50 PFC level, or [ ] the entire requested amount at a $3.00 PFC level. c. Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ X ] YES [ ] NO [ ] N/A 15. List of Carriers Certifying Agreement

16 List of Carriers Certifying Disagreement: Recap of Disagreements Public Agency Reasons for Proceeding: 16. List of Comments Received from the Public Notice: List of Parties Certifying Agreement. Recap of Disagreements Public Agency Reasons for Proceeding: For FAA Use Provide an analysis of each issue/disagreement raised by the air carriers and/or the public. Provide citations for any documents not included in the PFC application that are relied on by the FAA for its analysis. If a Federal Register notice is published, discuss and analyze any new issues raised. (If the comments from the consultation are repeated, state that.) ADO/RO Recommendation: Does the ADO/RO find the total costs of this project to be reasonable? Did the ADO/RO use comparable projects to make this finding? If so, list projects. If the amount requested if over $10 million, was the level of detail sufficient to identify eligible and ineligible costs. Summarize ineligible costs. Is the duration of collection adequate for the amount requested? ADO/RO RECOMMENDATION: [ ] Approve. [ ] Partially Approve. Summarize findings from earlier in the Attachment B discussing issues that lead to determination. [ ] Disapprove. Summarize findings from earlier in the Attachment B discussing issues that lead to determination. Application Reviewed by: Name Routing Symbol Date Item(s) reviewed.

17 Name Routing Symbol Date Item(s) reviewed

18 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION SKETCH: Reconstruct 1,850 ft Runway 13 end and reconstruct safety area pavement at intersection of Runway 5/23 and 13/31, Taxiway D Compression Seals Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2018 Intersection RSA Reconstruct Taxiway D Compression Seals Runway 13 End Reconstruction JUSTIFICATION: As detailed in the Functional Design Report for Runway 13/31 completed in 2014, Runway 13/31 has deteriorating pavement, profile that does not meet standards, and drainage and lighting systems that are failing. As part of this project approximately 1,850 ft of the 13 end of the runway will be reconstructed. Included with this project the full depth reconstruction of the safety area of Runway 5/23 within the intersection of Runways 13/31. The blast pad, and portions of Taxiway D6 will be reconstructed to allow for elevation adjustments. Project includes grading, drainage, lighting, markings along with the pavement improvements. Compression sealing of joints on this section of the runway as well as along Taxiway D will be performed as part of this project as well. It is anticipated that the MALSR lights may require elevation adjustment. Also includes cost of construction administration, observation, and material testing services. COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $11,731,590 State $0 Local (10%) $1,303,510 Total $13,035,100 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

19 DES MOINES INTERNATIONAL AIRPORT RUNWAY 13/31 RECONSTRUCTION RECONSTRUCT 1,850 FT RUNWAY 13 END October 25, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY $ ,679 $ 79, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY $ ,500 $ 335, DRAINAGE PIPE REMOVAL, SUBDRAIN LF $ ,000 $ 36, DRAINAGE PIPE REMOVAL, LESS THAN 24 INCHES LF $ ,000 $ 63, DRAINAGE STRUCTURE REMOVAL EA $ 1, $ 2, D INCH CLASS III RCP LF $ ,000 $ 210, D-705 NON-PERFORATED SUBDRAIN, 6" DIA. LF $ ,000 $ 38, D-705 PERFORATED SUBDRAIN, 6" DIA. LF $ ,000 $ 270, D-705 SUBDRAIN CLEANOUT EA $ $ 10, D-705 SUBDRAIN CONNECTION TO EXISTING STRUCTURE OR PIPE EA $ $ 3, D-751 SW-401 SINGLE INTAKE EA $ 7, $ 7, P-152 UNCLASSIFIED EXCAVATION CY $ ,000 $ 262, P-158 CEMENT SUBGRADE TREATMENT SY $ ,500 $ 182, P-157 CEMENT TON $ $ 80, P-208 AGGREGATE BASE COURSE, VAR. THICKNESS, 0 TO 11.5 INCHES SY $ ,250 $ 97, P-219 RECYCLED CONCRETE AGGREGATE BASE COURSE, 8" SY $ ,500 $ 252, STORM WATER POLLUTION PREVENTION PLAN (SWPPP) PREPARATION 16 P-156 AND MANAGEMENT LS $ 20, $ 20, P-156 INLET PROTECTION DEVICE EA $ $ P-156 WATTLES LF $ ,000 $ 11, P-307 DRAINABLE BASE COURSE, 6" SY $ ,500 $ 636, P-403 BITUMINOUS BASE COURSE TON $ ,500 $ 472, P " PCC SHOULDER PAVEMENT SY $ ,250 $ 481, P " PCC PAVEMENT SY $ ,500 $ 2,278, P-604 COMPRESSION JOINT SEALANT LF $ ,000 $ 157, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT SF $ ,000 $ 114, P-621 SAW CUT GROOVING SY $ ,700 $ 56, L No. 6 AWG, 5KV, L-824C CABLE, INSTALLED IN CONDUIT LF $ ,000 $ 21, NO. 6 AWG, BARE SOLID COUNTERPOISE WIRE WITH GROUND RODS AND 26 L EXOTHERMIC CONNECTIONS LF $ ,000 $ 12, L WAY 2" SCHEDULE 40 PVC IN NEW SHOULDER PAVEMENT LF $ ,900 $ 33, L WAY 2" SCHEDULE 40 PVC DUCT, CONCRETE ENCASED LF $ ,800 $ 15, L L-850A RUNWAY CENTERLINE / TDZ LIGHT EA $ 2, $ 77, L L-862 RUNWAY EDGE LIGHT EA $ 1, $ 39, L SALVAGE AND REINSTALL TAXIWAY LIGHTS EA $ 1, $ 19, L L-858 LED SIGN UNIT - 1 MODULE EA $ 5, $ 11, L ELECTRICAL DEMOLITION LS $ 50, $ 50, ADJUST MALSR STATIONS LS $ 168, $ 168, REPLACE RUNWAY PAVEMENT SENSORS EA $ 17, $ 17, T-901 SEEDING AND FERTILIZING ACRE $ 1, $ 22, T-904 SODDING SY $ ,000 $ 16, T-905 TOPSOILING CY $ ,750 $ 46, T-908 MULCHING ACRE $ 1, $ 22, CONSTRUCTION ACCESS LS $ 80, $ 80, TRAFFIC CONTROL/SECURITY LS $ 140, $ 140, CONSTRUCTION SURVEY LS $ 60, $ 60, MOBILIZATION AND MISCELLANEOUS LS $ 500, $ 500, Subtotal Runway Construction Costs ********* NEED TO ADD INTERSECTION RSA RECONSTRUCT *********** Engineering, Construction Admin, Legal, Administration (8%) Total Opinion of Probable Project Costs $7,511,263 $600,901 $8,112,164 Rounded $8,112,000 c:\pw_workdir\pw_ie\cmw1\dms89696\fy18_runway 13 End and RSA Reconstruct.xlsx 10/27/2016 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

20 DES MOINES INTERNATIONAL AIRPORT RUNWAY 13/31 RECONSTRUCTION RECONSTRUCT RUNWAY INTERSECTION SAFETY AREA (not bullseye) with PCC (overlay NOT INCLUDED) January 8, 2015 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 SAWCUTTING LF $ ,000 $ 739, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY $ ,500 $ 210, D-705 PERFORATED SUBDRAIN, 6" DIA. LF $ ,500 $ 70, TEMPORARY CRANE MAT SY $ ,500 $ 210, SUBGRADE SEPARATION LAYER SY $ ,500 $ 25, P-209 AGGREGATE BASE COURSE, 10" SY $ ,500 $ 210, P " PCC PAVEMENT, ACCELERATED STRENGTH SY $ ,500 $ 1,680, P-620 RUNWAY PAVEMENT MARKINGS LS $ 11, $ 11, P-621 SAW CUT GROOVING SY $ ,500 $ 36, No. 6 AWG, 5KV CABLE LF $ ,000 $ 20, L WAY 2" RGS DUCT LF $ ,500 $ 33, L L-850A RUNWAY CENTERLINE / TDZ LIGHT EA $ 2, $ 92, L L-850C BIDIRECTIONAL IN-PAVEMENT RUNWAY EDGE LIGHT EA $ 2, $ 5, L L-862 RUNWAY/TAXIWAY EDGE LIGHT EA $ 1, $ 21, CONSTRUCTION ACCESS LS $ 28, $ 28, TRAFFIC CONTROL/SECURITY LS $ 140, $ 140, CONSTRUCTION SURVEY LS $ 8, $ 8, MOBILIZATION AND MISCELLANEOUS LS $ 336, $ 336, Subtotal Runway Construction Costs Construction Admin, Legal, Administration (10%) Total Opinion of Probable Project Costs $3,877,328 $387,733 $4,265,061 Rounded $4,265,000 c:\pw_workdir\pw_ie\cmw1\dms89696\fy18_runway 13 End and RSA Reconstruct.xlsx 10/27/2016 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

21 FY2018 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT TWY DELTA COMPRESSION SEAL October 18th, 2016 ITEM NO. ITEM UNIT UNIT PRICE QUANTITY TOTAL PHASE 1 TWY D6 TO RWY 23/5 SAFETY AREA Twy D 1 MOBILIZATION LS $ 25, $ 25, TRAFFIC CONTROL / SECURITY LS $ 10, $ 10, E-816, 1/2" - 5/8" CONTRACTION AND CONSTRUCTION JOINTS LF $ ,471 $ 238, E-1006, 5/8" - 3/4" CONTRACTION AND CONSTRUCTION JOINTS LF $ ,298 $ 13, V-1625, EXPANSION JOINTS LF $ ,866 $ 15, Twy D Shoulder 3 E-816, 1/2" - 5/8" CONTRACTION AND CONSTRUCTION JOINTS LF $ ,762 $ 126, E-1006, 5/8" - 3/4" CONTRACTION AND CONSTRUCTION JOINTS LF $ ,721 $ 6, V-1625, EXPANSION JOINTS LF $ $ - Arm/De-Arm Pad 3 E-816, 1/2" - 5/8" CONTRACTION AND CONSTRUCTION JOINTS LF $ ,433 $ 39, E-1006, 5/8" - 3/4" CONTRACTION AND CONSTRUCTION JOINTS LF $ $ 2, Twy B 3 E-816, 1/2" - 5/8" CONTRACTION AND CONSTRUCTION JOINTS LF $ ,107 $ 82, E-1006, 5/8" - 3/4" CONTRACTION AND CONSTRUCTION JOINTS LF $ ,164 $ 4, V-1625, EXPANSION JOINTS LF $ $ 2, Subtotal Phase 1 Construction Costs Construction Contingency (10%) Engineering, Construction Admin, Legal, Administration Phase 1 Opinion of Probable Project Costs $566,359 $56,636 $35,000 $658,000 c:\pw_workdir\pw_ie\cmw1\dms89696\fy18 Estimate_TwyD Compression Seal.xls 11/21/2016 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

22 PFC Application #16 TOTAL Reconstruction of 05/23 and Terminal Apron $3,789, Project Reconstruction of 05/23 and Terminal Apron AIP Grant Total Cost Entitlement Discretionary Local PFC Request Phase I & II Engineering Analysis 1,032, , , ,200 and Design of RNW 23 Reconstruct Phase III Reconstruction of RNW 5 10,510,000 4,411,772 5,047,228 1,051,000 1,051,000 West of Intersection Phase IV Design RNW 5 Reconstruct 974, ,921 97,436 97,436 and Reimburseable Agreement Phase V Reconstruct RNW 23 East 18,929,000 4,411,772 12,624,328 1,892,900 1,892,900 of Intersection Papa Taxiway Design and 2,310,000 2,079, , ,000 Reconstruction Terminal Apron Phase I Design 800, ,000 80,000 80,000 Terminal Apron Phase II Demo/Replace 2,900,000 2,610, , ,000 Interior Service Road 436, ,210 43,690 43,690 37,892,257 8,823,544 25,279,487 3,789,226 3,789,226

23 PFC APPLICATION NUMBER: DSM PFC Application #16 ATTACHMENT B: PROJECT INFORMATION 1. Project Title: Reconstruction of Runway 05/23 and Terminal Apron 2. Project Number 3. Use Airport of Project: Des Moines International (DSM) 4. Project Type [ ] Impose Only: [ X ] Concurrent: [ ] Use Only: Link to application: 5. Level of Collection: [ ] $1.00 [ ] $2.00 [ ] $3.00 [ ] $4.00 [ X ] $ Financing Plan PFC Funds: Pay-as-you-go $ 3,789,226 Bond Capital $ Bond Financing & Interest $ Subtotal PFC Funds*: $ 3,789,226 If amount is over $10 million, include cost details sufficient to identify eligible and ineligible costs. Existing AIP Funds: Grant # Grant Funds in Project Subtotal Existing AIP Funds: Anticipated AIP Funds (List Each Year Separately): Fiscal Year: 2018 Entitlement $ Discretionary $ 928,800 Total $ 928,800 Fiscal Year: 2019 Entitlement $4,411,772 Discretionary $ 5,924,149 Total $ 10,335,921

24 Fiscal Year: 2020 Entitlement $4,411,772 Discretionary $ 18,426,538 Total $ 22,838,310 Subtotal Anticipated AIP Funds: $ 34,103,031 Other Funds: State Grants $ Local Funds Other (please specify) $ Subtotal Other Funds: Total Project Cost: $ 37,892,257 For FAA Use a. Does the project include a proposed LOI? [ ] YES [ ] NO If YES, does the Region support? [ ]YES [ ] NO. If YES, list the schedule for implementation: b. For any proposed AIP discretionary funds, does the Region intend to support? [ ] YES [ ] NO c. For any proposed AIP funds, is the request within the planning levels for the Region's five year CIP? [ ] YES [ ] NO d. For project requesting PFC funding levels of $4.00 and $4.50: Is there an expectation that AIP funding will be available to pay the project costs. [ ] YES [ ] NO What percentage of the total project cost is funded through AIP? List the source(s) of data used to make this finding. e. Terminal and surface transportation projects requesting a PFC funding level of $4.00 and $4.50. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ ] YES [ ] NO

25 [ ] N/A List the source(s) of data used to make this finding. f. Reasonableness of cost. Project Total Cost Analysis PFC Share of Total Cost Analysis 7. Back-up Financing Plan: The reconstruction of Runway 05/23 and Terminal Apron relies on entitlement and discretionary AIP funding. If discretionary AIP funding is not available for work to be completed, the construction will be delayed until adequate entitlement money is available to complete the project. If proposed AIP discretionary funds or a proposed LOI are included in the Financing Plan, provide a Back-up Financing Plan or a project phasing plan in the event the funds are not available for the project. For FAA Use If required to use a back-up financing/phasing plan, indicate the need to obtain additional approvals to obtain an alternate source of financing. Indicate the additional PFC duration of collection required if PFC s are to be used to fund the difference. Recap any discussion from previous item regarding likelihood of public agency obtaining the funding it proposes. 8. Project Description: This project includes reconstruction of a portion of Runway 05/23 and Terminal Apron during 2018, 2019 and If applicable for terminal projects, Prior to implementation of this project, Number of ticket counters: Number of gates: Number of baggage facilities: At completion of this project, Number of ticket counters: Number of gates: Number of baggage facilities: Net change due to this project: Number of ticket counters:

26 Number of gates: Number of baggage facilities: Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ X ] YES [ ] NO [ ] N/A FOR FAA USE Comment upon and/or Clarify Project Description. Include source citation if clarification information is not from PFC application. If project involves the construction of a new runway or modification of an existing runway, have the requirements of Order , with regard to runway safety areas been met? If not, is the runway grandfathered or has a modification been approve, or is there a likelihood the requirements will be met, or should the project be disapproved. If the project involves terminal work, confirm information regarding ticket counters, gates, and baggage facilities for construction and/or rehabilitation above has been completed. Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ ] YES [ ] NO [ ] N/A 9. Significant Contribution: FOR FAA USE Air safety. Part 139 [ ] Other (explain) Certification Inspector concur. Yes [ ] No [ ] Date Air security. Part 107 [ ] Part 108 [ ] Other (explain) CASFO concur. Yes [ ] No [ ] Date Competition. Competition Plan [ ] Other (explain) Congestion. Current [ ] or Anticipated [ ] LOI [ ] FAA BCA [ ] FAA Airport Capacity Enhancement Plan [ ]

27 Other (explain) Noise. 65 LDN [ ] Other (explain) Project does not qualify under significant contribution rules. Quantitative and qualitative analysis of significant contribution option chosen by public agency. If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. How does this project address the deficiency sited by the public agency? If competition is the chosen option, provide the FAA s analysis of any barriers to competition at the airport. 10. Project Objective: This project will enhance the safety of Des Moines International Airport by ensuring the runway environment meets the FAA specifications. FOR FAA USE Safety, Preserve [ ] Enhance [ ] Security, Preserve [ ] Enhance [ ] Capacity, Preserve [ ] Enhance [ ] Furnish opportunity for enhanced competition between or among air carriers at the airport Mitigate noise impacts resulting from aircraft operations at the airport Project does not meet any PFC objectives (explain) Finding Current deficiency. List the source(s) of data used to make this finding if it is not a part of the PFC application. Address adequacy of issues. 11. Project Justification: This project includes the reconstruction of a portion of Runway 5/23 and Terminal Apron. Project also includes replacement of Taxiway B pavement between Papa and Runway 5/23 in order to remove the direct connection of the terminal apron to the runway. Work consists of removal and replacement of existing pavement, construction of paved shoulders, and installation of edge lighting, guidance signs, grading, drainage, pavement markings and miscellaneous related work items. This section of Runway 5/23 has exceeded its design life and is

28 comprised of deteriorated pavement. The PCI Report completed in 2014 shows a PCI rating between 47 and 70 on the proposed limits of the Taxiway P reconstruction. These issues will be resolved under this project. Project includes the overlay / HMA transition pavement on Taxiway P and P1. It is anticipated that the Runway 23 end will be raised by 4 feet. Therefore, this HMA pavement will act as a transition between Runway 23 end, Taxiway Papa, and the current elevation of the terminal apron. FOR FAA USE Define how the project accomplishes PFC Objective(s) Explain how project is cost-effective compared to other reasonable and timely means to accomplish this objective(s) Based on informed opinion or published FAA guidance, specify how the cost of the project is reasonable compared to the capacity, safety, security, noise and/or competition benefits attributable to the project. Include citation for any documents that are not a part of this PFC application. If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. Discuss any non-economical benefits which are not captured above. Project Eligibility: Indicate project eligibility by checking the appropriate category below. [ ] Development eligible under AIP criteria (paragraph of Order _ or PGL ); [ ] Planning eligible under AIP criteria (paragraph of Order _ or PGL ); [ ] Noise compatibility planning as described in 49 U.S.C ; [ ] Noise compatibility measures eligible under 49 U.S.C [ ] Project approved in an approved Part 150 noise compatibility plan; Title and Date of Part 150: [ ] Project included in a local study. Title and Date of local study: [ ] Terminal development as described in 49 U.S.C (a)(3)(C); [ ] Shell of a gate as described in 49 U.S.C 40117(a)(3)(F) (air carrier, percentage of annual boardings ); [ ] PFC Program Update Letter [ ] Project does not meet PFC eligibility (explain). If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding.

29 Are any work elements or portions of the overall project ineligible? Provide associated costs. 12. Estimated Project Implementation Date (Month and Year): April 2018 Estimated Project Completion Date (Month and Year): November 2020 For FAA Use For Impose and Use or Use Only projects, will the project begin within 2 years of PFC application Due date (120-day)? [ ] Yes [ ] No For Impose Only project, will the project begin within 5 years of the charge effective date or PFC application Due date, whichever is first? [ ] Yes [ ] No Is this project dependent upon another action to occur before its implementation or completion. Explain. 13. For an Impose Only project, estimated date Use application will be submitted to the FAA (Month and Year): For FAA Use Is the date within 3 years of the estimated charge effective date or approval date, whichever is sooner. [ ] Yes [ ] No Which actions are needed before the use application can be submitted? What is the estimated schedule for each action? 14. Project requesting PFC funding levels of $4.00 and $4.50: a. Can project costs be paid for from funds reasonably expected to be available through AIP funding. [ ] YES [ X ] NO b. If the FAA determines that the project may qualify for AIP funding, would the public agency prefer that the FAA approve [ X ] the amount of the local match to be collected at a $4.50 PFC level, or [ ] the entire requested amount at a $3.00 PFC level.

30 c. Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ X ] YES [ ] NO [ ] N/A 15. List of Carriers Certifying Agreement List of Carriers Certifying Disagreement: Recap of Disagreements Public Agency Reasons for Proceeding: 16. List of Comments Received from the Public Notice: List of Parties Certifying Agreement. Recap of Disagreements Public Agency Reasons for Proceeding: For FAA Use Provide an analysis of each issue/disagreement raised by the air carriers and/or the public. Provide citations for any documents not included in the PFC application that are relied on by the FAA for its analysis. If a Federal Register notice is published, discuss and analyze any new issues raised. (If the comments from the consultation are repeated, state that.) ADO/RO Recommendation: Does the ADO/RO find the total costs of this project to be reasonable? Did the ADO/RO use comparable projects to make this finding? If so, list projects. If the amount requested if over $10 million, was the level of detail sufficient to identify eligible and ineligible costs. Summarize ineligible costs. Is the duration of collection adequate for the amount requested? ADO/RO RECOMMENDATION: [ ] Approve. [ ] Partially Approve. Summarize findings from earlier in the Attachment B discussing issues that lead to determination. [ ] Disapprove. Summarize findings from earlier in the Attachment B discussing issues that lead to determination.

31 Application Reviewed by: Name Routing Symbol Date Item(s) reviewed. Name Routing Symbol Date Item(s) reviewed

32 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION Engineering Analysis of Entire Runway 5/23, Design of Runway 5/23 Reconstruction West of Intersection Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2018 Remove Twy R3 Reconstruct Approximately 1,330 LF of Runway 5/23 Remove Twy R3 Reconstruct Twy D Intersection Remove/Reconstruct Taxiway P4 JUSTIFICATION: Portions of Runway 5/23 pavement condition is nearing the threshold where major rehabilitation or reconstruction will be required. Project to identify issues with current runway and develop plan for future rehabilitation/reconstruction projects. Once the analysis is completed, the design of 1,330 LF of Runway 5/23 west of the intersection to Runway 13/31 will be completed. Work consists of removal and replacement of existing pavement, construction of paved shoulders, installation of edge lighting, guidance signs, grading, drainage, pavement markings, etc. This section of Runway 5/23 has exceeded its design life and is comprised of deteriorated pavement. These issues will be resolved under this project. Also, as addressed on the Airport Facility Diagram, Taxiway R3 is referred to as Hot Spot 1. In order to remove the Hot Spot, Taxiway R3 and Taxiway P3 is being removed. The PCI on this pavement ranges between 57 and 67, as addressed in the 2014 PCI Report. Project also includes reconstruction of the Taxiway Delta Intersection to Runway 5/23 along with an asphalt transition area to transition to existing runway profile. Project also includes the reconstruction of a portion of Taxiway P4 in order to eliminate the direct access to Runway 5/23 from the South Tee Hangar Apron. COST ESTIMATE: (Attach detailed cost estimate) Design: Federal (90%) $613,800 State $0 Local (10%) $68,200 Total $682,000 Eng. Analysis: Federal (90%) $315,000 State $0 Local (10%) $35,000 Total $350,000 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

33 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION Runway 5/23 Reconstruction West of Intersection, Remove Taxiway R3 & Taxiway P3, Remove/Reconstruct Taxiway P4 and Taxilane to South Cargo Apron Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2019 SKETCH: Remove Twy R3 Reconstruct Approximately 1,330 LF of Runway 5/23 Remove Twy P3 Remove/Reconstruct Taxiway P4 Reconstruct Twy D Intersection JUSTIFICATION: This project includes the reconstruction of a portion of Runway 5/23 (1,330 LF). Work consists of removal and replacement of existing pavement, construction of paved shoulders, installation of edge lighting, guidance signs, grading, drainage, pavement markings, compression joint sealant, etc. This section of Runway 5/23 has exceeded its design life and is comprised of deteriorated pavement. These issues will be resolved under this project. Also, as addressed on the Airport Facility Diagram, Taxiway R3 is referred to as Hot Spot 1. In order to remove the Hot Spot, Taxiway R3 and Taxiway P3 is being removed. The PCI on this pavement ranges between 57 and 67, as addressed in the 2014 PCI Report. Project also includes reconstruction of the Taxiway Delta Intersection to Runway 5/23 along with an asphalt transition area to transition to existing runway profile. Project also includes the reconstruction of a portion of Taxiway P4 in order to eliminate the direct access to Runway 5/23 from the South Tee Hangar Apron. COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $9,459,000 State $0 Local (10%) $1,051,000 Total $10,510,000 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

34 FY19 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT 1330 FT RUNWAY 5/23 CONSTRUCTION - WEST OF INTERSECTION October 25, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY ,300 $ 64, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY ,890 $ 374, DRAINAGE PIPE REMOVAL, SUBDRAIN LF ,900 $ 8, D-705 PERFORATED SUBDRAIN, 6" DIA. LF ,000 $ 55, D-705 SUBDRAIN CLEANOUT EA $ 11, D-705 SUBDRAIN CONNECTION TO EXISTING STRUCTURE OR PIPE EA $ 3, P-152 UNCLASSIFIED EXCAVATION CY ,500 $ 56, P INCH SUBGRADE TREATMENT SY ,190 $ 393, P-208 AGGREGATE BASE COURSE, VAR. THICKNESS, 0 TO 11.5 INCHES SY ,300 $ 48, P-219 RECYCLED CONCRETE AGGREGATE BASE COURSE, 8" SY ,190 $ 314, STORM WATER POLLUTION PREVENTION PLAN (SWPPP) PREPARATION 11 P-156 AND MANAGEMENT LS 17, $ 17, P-156 INLET PROTECTION DEVICE EA $ P-307 DRAINABLE BASE COURSE, 6" SY ,890 $ 791, P " PCC SHOULDER PAVEMENT SY ,900 $ 459, P " PCC PAVEMENT SY ,690 $ 2,736, P-604 COMPRESSION JOINT SEALS LF ,000 $ 478, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 1 BEADS SF ,100 $ 3, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 3 BEADS SF ,600 $ 18, P-620 PAVEMENT MARKINGS - BLACK OUTLINES, PAINT SF ,900 $ 8, P-621 SAW CUT GROOVING SY ,000 $ 65, L No. 6 AWG, 5KV, L-824C CABLE, INSTALLED IN CONDUIT LF ,500 $ 11, NO. 6 AWG, BARE SOLID COUNTERPOISE WIRE WITH GROUND RODS AND 22 L EXOTHERMIC CONNECTIONS LF ,500 $ 10, L WAY 2" SCHEDULE 40 PVC IN NEW SHOULDER PAVEMENT LF $ 2, L WAY 2" SCHEDULE 40 PVC DUCT, CONCRETE ENCASED LF ,500 $ 13, L L-862 RUNWAY EDGE LIGHT EA 1, $ 25, L L-858 LED SIGN UNIT EA 4, $ 13, L ELECTRICAL DEMOLITION LS 58, $ 58, T-901 SEEDING AND FERTILIZING ACRE 1, $ 18, T-904 SODDING SY ,300 $ 60, T-905 TOPSOILING CY ,500 $ 60, T-908 MULCHING ACRE 1, $ 18, CONSTRUCTION ACCESS LS 63, $ 63, TRAFFIC CONTROL/SECURITY LS 290, $ 290, CONSTRUCTION SURVEY LS 58, $ 58, MOBILIZATION AND MISCELLANEOUS LS 464, $ 464, Subtotal Runway Construction Costs Construction Admin. And Observation, Legal, Administration (8%) Total Opinion of Probable Project Costs $7,076,609 $566,000 $7,642,609 Rounded $7,640,000 c:\pw_workdir\pw_ie\cmw1\dms89698\fy19_cost Estimate-Runway.xlsx 1/12/2017 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

35 FY19 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT TAXIWAY R3 & P3 REMOVAL October 25, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY ,130 $ 38, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY ,240 $ 165, DRAINAGE PIPE REMOVAL, SUBDRAIN LF ,000 $ 2, DRAINAGE STRUCTURE ADJUSTMENT EA 1, $ 6, D-705 PERFORATED SUBDRAIN, 6" DIA. LF $ 9, D-705 SUBDRAIN CLEANOUT EA $ 4, D-705 SUBDRAIN CONNECTION TO EXISTING STRUCTURE OR PIPE EA $ 3, P-152 UNCLASSIFIED EXCAVATION CY ,000 $ 116, P-156 INLET PROTECTION DEVICE EA $ L ELECTRICAL DEMOLITION LS ACR 40, $ 40, T-901 SEEDING AND FERTILIZING E 1, $ 5, T-904 SODDING SY $ 4, T-905 TOPSOILING CY ACR ,300 $ 21, T-908 MULCHING E 1, $ 5, TRAFFIC CONTROL/SECURITY LS 29, $ 116, Subtotal Runway Construction Costs Construction Admin. And Observation, Legal, Administration (8%) Total Opinion of Probable Project Costs $540,589 $43,000 $583,589 Rounded $580,000 c:\pw_workdir\pw_ie\cmw1\dms89698\fy19_cost Estimate-Runway.xlsx 1/12/2017 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

36 FY19 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT TAXIWAY P4 RECONSTRUCTION October 25, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY ,000 $ 6, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY ,900 $ 72, DRAINAGE PIPE REMOVAL, SUBDRAIN LF $ 1, D-705 PERFORATED SUBDRAIN, 6" DIA. LF ,500 $ 20, D-705 SUBDRAIN CLEANOUT EA $ 5, D-705 SUBDRAIN CONNECTION TO EXISTING STRUCTURE OR PIPE EA $ 2, " RCP LF $ 64, P-152 UNCLASSIFIED EXCAVATION CY ,000 $ 52, P INCH SUBGRADE TREATMENT SY ,800 $ 93, P-208 AGGREGATE BASE COURSE, VAR. THICKNESS, 0 TO 11.5 INCHES SY ,200 $ 11, P-219 RECYCLED CONCRETE AGGREGATE BASE COURSE, 8" SY ,800 $ 75, STORM WATER POLLUTION PREVENTION PLAN (SWPPP) PREPARATION 12 P-156 AND MANAGEMENT LS 17, $ 17, P-156 INLET PROTECTION DEVICE EA $ P-307 DRAINABLE BASE COURSE, 6" SY ,600 $ 189, P " PCC SHOULDER PAVEMENT SY ,200 $ 102, P " PCC PAVEMENT SY ,600 $ 678, P-604 COMPRESSION JOINT SEALANT LF ,000 $ 31, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 1 BEADS SF ,400 $ 2, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 3 BEADS SF ,000 $ 2, P-620 PAVEMENT MARKINGS - BLACK OUTLINES, PAINT SF ,800 $ 4, L No. 6 AWG, 5KV, L-824C CABLE, INSTALLED IN CONDUIT LF ,500 $ 6, NO. 6 AWG, BARE SOLID COUNTERPOISE WIRE WITH GROUND RODS AND 22 L EXOTHERMIC CONNECTIONS LF ,500 $ 3, L WAY 2" SCHEDULE 40 PVC IN NEW SHOULDER PAVEMENT LF ,000 $ 9, L L-861T TAXIWAY EDGE LIGHT EA 1, $ 46, L L-858 LED SIGN UNIT EA 4, $ 4, L ELECTRICAL DEMOLITION LS 58, $ 58, T-901 SEEDING AND FERTILIZING ACRE 1, $ 2, T-904 SODDING SY $ 4, T-905 TOPSOILING CY ,500 $ 8, T-908 MULCHING ACRE 1, $ 2, CONSTRUCTION ACCESS LS 58, $ 58, TRAFFIC CONTROL/SECURITY LS 290, $ 290, CONSTRUCTION SURVEY LS 52, $ 52, MOBILIZATION AND MISCELLANEOUS LS 139, $ 139, Subtotal Runway Construction Costs Construction Observation and Admin, Legal, Administration (8%) Total Opinion of Probable Project Costs $2,122,713 $170,000 $2,292,713 Rounded $2,290,000 c:\pw_workdir\pw_ie\cmw1\dms89698\fy19_cost Estimate-Runway.xlsx 1/12/2017 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

37 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION Design of 2,150 ft Reconstruction of Rwy 23 End to Intersection & Twy Bravo Connector, & FAA Reimbursable Agreement Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2019 Runway 5/23 Reconstruction JUSTIFICATION: Due to pavement deterioration as shown in the PCI Report, the reconstruction of the east 2,150 ft of Runway 5/23 will be completed. The design of this project will include the removal and replacement of existing pavement, construction of paved shoulders, lighting, signs, grading, markings, etc. Design will also include the relocation of Taxiway Bravo at the Terminal Apron connector. This will eliminate the direct access from the apron to Runway 5/23. Project will also include the FAA Reimbursable Agreement as well an AGIS Survey. COST ESTIMATE: (Attach detailed cost estimate) Design: Federal (90%) $719,421 State $0 Local (10%) $79,936 Total $799,357 Reimbur. Agr: Federal (90%) $90,000 State $0 Local (10%) $10,000 Total $100,000 AGIS Survey: Federal (90%) $67,500 State $0 Local (10%) $7,500 Total $75,000 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

38 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION SKETCH: Reconstruct 1,750 ft Runway 5/23 and reconstruct safety area pavement at intersection of Runway 5/23 and 13/31, Relocate Taxiway Bravo connection to Terminal Apron Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2020 Intersection RSA Reconstruct Taxiway R Reconstruct Approximately 1,750 LF of Runway 5/23 13/31 Taxiway P Reconstruct portion of Taxiway Bravo HMA Transition Pavement JUSTIFICATION: This project includes the reconstruction of a portion of Runway 5/23 (1,750 LF). Project also includes replacement of Taxiway B pavement between Papa and Runway 5/23 in order to remove the direct connection of the terminal apron to the runway. Work consists of removal and replacement of existing pavement, construction of paved shoulders, and installation of edge lighting, guidance signs, grading, drainage, pavement markings and miscellaneous related work items. This section of Runway 5/23 has exceeded its design life and is comprised of deteriorated pavement. The PCI Report completed in 2014 shows a PCI rating between 47 and 70 on the proposed limits of the Taxiway P reconstruction. These issues will be resolved under this project. Project includes the overlay / HMA transition pavement on Taxiway P and P1. It is anticipated that the Runway 23 end will be raised by 4 feet. Therefore, this HMA pavement will act as a transition between Runway 23 end, Taxiway Papa, and the current elevation of the terminal apron. COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $17,036,100 State $0 Local (10%) $1,892,900 Total $18,929,000 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangars, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

39 FY19 20 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT PORTIONS OF TAXIWAY BRAVO RECONSTRUCTION October 24, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY ,800 $ 66, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY ,700 $ 159, DRAINAGE PIPE REMOVAL, SUBDRAIN LF ,820 $ 10, DRAINAGE PIPE REMOVAL LF ,910 $ 288, DRAINAGE STRUCTURE REMOVAL EA 1, $ 11, D " RCP LF ,200 $ 183, D-705 PERFORATED SUBDRAIN, 6" DIA. LF ,500 $ 47, D-705 SUBDRAIN CLEANOUT EA $ 13, D-705 SUBDRAIN CONNECTION TO EXISTING STRUCTURE OR PIPE EA $ 3, D-751 STORM SEWER STRUCTURE EA 5, $ 17, P-152 UNCLASSIFIED EXCAVATION CY ,000 $ 296, P INCH SUBGRADE TREATMENT SY ,000 $ 211, P-208 AGGREGATE BASE COURSE, VAR. THICKNESS, 0 TO 11.5 INCHES SY ,900 $ 35, P-219 RECYCLED CONCRETE AGGREGATE BASE COURSE, 8" SY ,000 $ 183, STORM WATER POLLUTION PREVENTION PLAN (SWPPP) PREPARATION 15 P-156 AND MANAGEMENT LS 15, $ 15, P-156 INLET PROTECTION DEVICE EA $ P-307 DRAINABLE BASE COURSE, 6" SY ,300 $ 285, P " PCC SHOULDER PAVEMENT SY ,900 $ 311, P " PCC PAVEMENT SY ,300 $ 1,252, COMPRESSION JOINT SEALANT LF ,000 $ 62, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 1 BEADS SF ,500 $ 3, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 3 BEADS SF ,300 $ 2, P-620 PAVEMENT MARKINGS - BLACK OUTLINES, PAINT SF ,500 $ 5, L No. 6 AWG, 5KV, L-824C CABLE, INSTALLED IN CONDUIT LF ,500 $ 11, NO. 6 AWG, BARE SOLID COUNTERPOISE WIRE WITH GROUND RODS AND 25 L EXOTHERMIC CONNECTIONS LF ,650 $ 5, L WAY 2" SCHEDULE 40 PVC IN NEW SHOULDER PAVEMENT LF ,000 $ 18, L WAY 2" SCHEDULE 40 PVC DUCT, CONCRETE ENCASED $ 5, L-125 L-861T TAXIWAY EDGE LIGHT EA 1, $ 30, L-125 L-852K TAXIWAY CENTERLINE LIGHT EA 2, $ 42, L-125 L-804G IN-PAVEMENT RUNWAY GUARD LIGHTS EA 2, $ 22, L-125 L-858 LED SIGN UNIT EA 4, $ 13, L-125 ELECTRICAL DEMOLITION LS 36, $ 36, DEICING TANK CONTROL BUILDING RELOCATION LS 56, $ 56, T-901 SEEDING AND FERTILIZING ACRE 1, $ 3, T-904 SODDING SY ,000 $ 7, T-905 TOPSOILING CY ,300 $ 7, T-908 MULCHING ACRE 1, $ 3, CONSTRUCTION ACCESS LS 38, $ 38, TRAFFIC CONTROL/SECURITY LS 151, $ 151, CONSTRUCTION SURVEY LS 33, $ 33, MOBILIZATION AND MISCELLANEOUS LS 415, $ 415, Subtotal Taxiway Construction Costs Construction Admin. And Observation, Legal, Administration (8%) Total Opinion of Probable Project Costs $4,371,673 $350,000 $4,721,673 Rounded $4,720,000 c:\pw_workdir\pw_ie\cmw1\dms89697\fy19_cost Estimates.xlsx 11/21/2016 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

40 DES MOINES INTERNATIONAL AIRPORT RUNWAY 5/23 RECONSTRUCTION RECONSTRUCT RUNWAY INTERSECTION SAFETY AREA (not bullseye) with PCC October 28, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 SAWCUTTING LF $ ,000 $ 765, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY $ ,500 $ 217, D-705 PERFORATED SUBDRAIN, 6" DIA. LF $ ,500 $ 72, TEMPORARY CRANE MAT SY $ ,500 $ 217, SUBGRADE SEPARATION LAYER SY $ ,500 $ 26, P-209 AGGREGATE BASE COURSE, 10" SY $ ,500 $ 217, P " PCC PAVEMENT, ACCELERATED STRENGTH SY $ ,500 $ 1,740, P-620 RUNWAY PAVEMENT MARKINGS LS $ 11, $ 11, P-621 SAW CUT GROOVING SY $ ,500 $ 37, No. 6 AWG, 5KV CABLE LF $ ,000 $ 20, L WAY 2" RGS DUCT LF $ ,500 $ 34, L L-850A RUNWAY CENTERLINE / TDZ LIGHT EA $ 2, $ 95, L L-850C BIDIRECTIONAL IN-PAVEMENT RUNWAY EDGE LIGHT EA $ 2, $ 5, L L-862 RUNWAY/TAXIWAY EDGE LIGHT EA $ 1, $ 21, CONSTRUCTION ACCESS LS $ 29, $ 29, TRAFFIC CONTROL/SECURITY LS $ 145, $ 145, CONSTRUCTION SURVEY LS $ 8, $ 8, MOBILIZATION AND MISCELLANEOUS LS $ 377, $ 377, Subtotal Runway Construction Costs Construction Admin, Legal, Administration (10%) Total Opinion of Probable Project Costs $4,044,804 $404,480 $4,449,284 Rounded $4,449,000 c:\pw_workdir\pw_ie\amw\dms89697\fy19_cost Estimates.xlsx 11/2/2016 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

41 FY20 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT 2150 FT RUNWAY 5/23 CONSTRUCTION - EAST OF INTERSECTION October 24, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY ,800 $ 107, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY ,160 $ 408, DRAINAGE PIPE REMOVAL, SUBDRAIN LF ,900 $ 8, DRAINAGE STRUCTURE ADJUSTMENT EA $ 6, D-705 PERFORATED SUBDRAIN, 6" DIA. LF ,500 $ 47, D-705 SUBDRAIN CLEANOUT EA $ 18, D-705 SUBDRAIN CONNECTION TO EXISTING STRUCTURE OR PIPE EA $ 5, P-152 UNCLASSIFIED EXCAVATION CY ,000 $ 847, P INCH SUBGRADE TREATMENT SY ,650 $ 463, P-208 AGGREGATE BASE COURSE, VAR. THICKNESS, 0 TO 11.5 INCHES SY ,200 $ 82, P-219 RECYCLED CONCRETE AGGREGATE BASE COURSE, 8" SY ,000 $ 264, STORM WATER POLLUTION PREVENTION PLAN (SWPPP) PREPARATION 12 P-156 AND MANAGEMENT LS 16, $ 16, P-156 INLET PROTECTION DEVICE EA $ P-156 WATTLES LF ,000 $ 6, P-307 DRAINABLE BASE COURSE, 6" SY ,000 $ 837, P-401 HMA TRANSITION PAVEMENT TON ,500 $ 675, P " PCC SHOULDER PAVEMENT SY ,200 $ 732, P " PCC PAVEMENT SY ,000 $ 2,996, P-605 COMPRESSION JOINT SEALANT LF ,000 $ 155, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 1 BEADS SF ,500 $ 3, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 3 BEADS SF ,000 $ 18, P-620 PAVEMENT MARKINGS - BLACK OUTLINES, PAINT SF ,500 $ 8, P-621 SAW CUT GROOVING SY ,000 $ 76, L No. 6 AWG, 5KV, L-824C CABLE, INSTALLED IN CONDUIT LF ,000 $ 22, NO. 6 AWG, BARE SOLID COUNTERPOISE WIRE WITH GROUND RODS 24 L AND EXOTHERMIC CONNECTIONS LF ,000 $ 11, L WAY 2" SCHEDULE 40 PVC IN NEW SHOULDER PAVEMENT LF ,000 $ 18, L WAY 2" SCHEDULE 40 PVC DUCT, CONCRETE ENCASED LF $ 5, L L-850C BIDIRECTIONAL IN-PAVEMENT RUNWAY EDGE LIGHT EA 2, $ 4, L L-862 RUNWAY EDGE LIGHT EA 1, $ 24, L L-858 LED SIGN UNIT - 1 MODULE EA 3, $ 10, L ELECTRICAL DEMOLITION LS 56, $ 56, T-901 SEEDING AND FERTILIZING ACRE 1, $ 5, T-904 SODDING SY ,000 $ 90, T-905 TOPSOILING CY ,400 $ 19, T-908 MULCHING ACRE 1, $ 6, CONSTRUCTION ACCESS LS 67, $ 67, TRAFFIC CONTROL/SECURITY LS 259, $ 259, CONSTRUCTION SURVEY LS 67, $ 67, MOBILIZATION AND MISCELLANEOUS LS 581, $ 581, Subtotal Runway Construction Costs Construction Admin. And Observation, Legal, Administration (8%) Total Opinion of Probable Project Costs $9,040,294 $723,000 $9,763,294 Rounded $9,760,000 c:\pw_workdir\pw_ie\cmw1\dms89697\fy20_cost Estimates.xlsx 2/1/2017 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

42 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION SKETCH: Reconstruct 1,000 ft Taxiway Papa Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2020 Runway 5/23 Taxiway B Reconstruct Approximately 1,000 LF of Taxiway Papa Terminal Apron JUSTIFICATION: This project includes the reconstruction of a portion of Taxiway Papa (1,000 LF) where the PCI is 53 as of 2014 and the pavement is actively deteriorating. Work consists of removal and replacement of existing pavement, construction of paved shoulders, installation of edge lighting, guidance signs, grading, drainage, pavement markings and miscellaneous related work items COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $2,079,000 State $0 Local (10%) $231,000 Total $2,310,000 SPONSOR S VERIFICATION: Date For each and every project 2017 (pending) - Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

43 FY19 20 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT 1,000 FT OF TAXIWAY PAPA RECONSTRUCTION October 24, 2016 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY ,000 $ 27, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY ,800 $ 79, DRAINAGE PIPE REMOVAL, SUBDRAIN LF ,440 $ 4, DRAINAGE PIPE REMOVAL LF $ 20, DRAINAGE STRUCTURE REMOVAL EA 1, $ 5, D " RCP LF $ 91, D-705 PERFORATED SUBDRAIN, 6" DIA. LF ,500 $ 33, D-705 SUBDRAIN CLEANOUT EA $ 8, D-705 SUBDRAIN CONNECTION TO EXISTING STRUCTURE OR PIPE EA $ 1, D-751 STORM SEWER STRUCTURE EA 5, $ 11, P-152 UNCLASSIFIED EXCAVATION CY ,000 $ 127, P INCH SUBGRADE TREATMENT SY ,000 $ 101, P-208 AGGREGATE BASE COURSE, VAR. THICKNESS, 0 TO 11.5 INCHES SY ,700 $ 18, P-219 RECYCLED CONCRETE AGGREGATE BASE COURSE, 8" SY ,000 $ 54, STORM WATER POLLUTION PREVENTION PLAN (SWPPP) PREPARATION 15 P-156 AND MANAGEMENT LS 15, $ 15, P-156 INLET PROTECTION DEVICE EA $ P-307 DRAINABLE BASE COURSE, 6" SY ,000 $ 257, P " PCC SHOULDER PAVEMENT SY ,700 $ 167, P " PCC PAVEMENT SY ,000 $ 614, COMPRESSION JOINT SEALANT LF ,000 $ 31, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 1 BEADS SF ,500 $ 2, P-620 PAVEMENT MARKINGS - RUNWAY AND TAXIWAY PAINT, TYPE 3 BEADS SF $ 1, P-620 PAVEMENT MARKINGS - BLACK OUTLINES, PAINT SF ,500 $ 2, L No. 6 AWG, 5KV, L-824C CABLE, INSTALLED IN CONDUIT LF ,500 $ 6, NO. 6 AWG, BARE SOLID COUNTERPOISE WIRE WITH GROUND RODS AND 25 L EXOTHERMIC CONNECTIONS LF ,350 $ 3, L WAY 2" SCHEDULE 40 PVC IN NEW SHOULDER PAVEMENT LF ,000 $ 9, L WAY 2" SCHEDULE 40 PVC DUCT, CONCRETE ENCASED $ 3, L-125 L-861T TAXIWAY EDGE LIGHT EA 1, $ 15, L-125 L-858 LED SIGN UNIT EA 4, $ 4, L-125 ELECTRICAL DEMOLITION LS 20, $ 20, T-901 SEEDING AND FERTILIZING ACRE 1, $ 1, T-904 SODDING SY $ 3, T-905 TOPSOILING CY $ 3, T-908 MULCHING ACRE 1, $ 1, CONSTRUCTION ACCESS LS 18, $ 18, TRAFFIC CONTROL/SECURITY LS 75, $ 75, CONSTRUCTION SURVEY LS 17, $ 17, MOBILIZATION AND MISCELLANEOUS LS 150, $ 150, Subtotal Taxiway Construction Costs Design, Construction Admin. And Observation, Legal, Administration (15%) Total Opinion of Probable Project Costs $2,009,741 $301,000 $2,310,741 Rounded $2,310,000 c:\pw_workdir\pw_ie\cmw1\dms89697\fy19_cost Estimates.xlsx 11/17/2016 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

44 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION Design of Terminal Apron Reconstruction Phase 1 Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2020 SKETCH: Taxiway Papa Terminal Apron Existing Terminal Building Remove Existing GA Apron / Construct New Terminal Apron Ultimate Terminal Building JUSTIFICATION: This project includes the demolition of the existing East General Aviation Apron along with associated parking lots and access roads. The proposed apron will be constructed in its place to allow for the construction of the new terminal building in year This project involves extensive removals of existing utilities and pavement, storm sewer installation, subdrain installation, excavation, subgrade prep, subbase installation, drainable base course, lighting, signage, marking, PCC paving, and others. COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $720,000 State $0 Local (10%) $80,000 Total $800,000 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

45 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION Demolition of Existing Terminal Apron Phase 1 Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2020 SKETCH: Taxiway Papa Remove Existing GA Apron and Bldgs 7, 8, 9, 10 Terminal Apron Existing Terminal Building JUSTIFICATION: This project includes the demolition of the existing East General Aviation Apron along with associated parking lots and access roads. Project also includes the demolition of existing Buildings 7, 8, 9, and 10. This project is in preparation of the construction of the proposed apron which will allow for the construction of the new terminal building in year This project involves extensive removals of existing utilities and pavement along with building demolition. COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $2,610,000 State $0 Local (10%) $290,000 Total $2,900,000 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

46 FY20 COST ESTIMATE DES MOINES INTERNATIONAL AIRPORT TERMINAL APRON DEMOLITION - PHASE 1 February 1, 2017 ITEM NO. ITEM CODE ITEM UNIT UNIT PRICE QUANTITY TOTAL 1 P-101 AIRFIELD PAVEMENT REMOVAL, LESS THAN 12" THICKNESS SY ,000 $ 13, P-101 AIRFIELD PAVEMENT REMOVAL, GREATER THAN 12" THICKNESS SY ,700 $ 413, DRAINAGE PIPE REMOVAL, SUBDRAIN LF ,000 $ 22, DRAINAGE PIPE REMOVAL LF ,000 $ 646, D-705 DRAINAGE STRUCTURE REMOVAL EA 1, $ 84, BUILDING 7 DEMOLITION LS 200, $ 200, BUILDING 8 DEMOLITION LS 240, $ 240, BUILDING 9 DEMOLITION LS 150, $ 150, BUILDING 10 DEMOLITION LS 340, $ 340, ELECTRICAL DEMOLITION LS 56, $ 56, CONSTRUCTION ACCESS LS 67, $ 67, TRAFFIC CONTROL/SECURITY LS 65, $ 65, CONSTRUCTION SURVEY LS 67, $ 67, MOBILIZATION AND MISCELLANEOUS LS 150, $ 150, Subtotal Runway Construction Costs $2,518,289 Engineering, Construction Admin. And Observation, Legal, Administration (15%) Total Opinion of Probable Project Costs $378,000 $2,896,289 Rounded $2,900,000 c:\pw_workdir\pw_ie\cmw1\dms89697\fy20_cost Estimates.xlsx 2/1/2017 FOTH ie 8191 BIRCHWOOD CT, SUITE L JOHNSTON, IOWA 50131

47 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION Pave Service Road Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2020 SKETCH: JUSTIFICATION: This project includes the construction of a paved service road around the southeast end of Runway 13/31. The proposed paved service road will be to allow for transportation of fuel from the future East General Aviation Apron to the Passenger Terminal Apron. Currently fueling services for the Terminal Apron are provided from Signature, a tenant of the East General Aviation Apron. The East General Aviation Apron will be relocated for the construction of the new terminal building in year This project involves subdrain installation, excavation, subgrade prep, subbase installation, PCC paving, and others. COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $393,210 State $0 Local (10%) $43,690 Total $436,900 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

48 PFC Application #16 TOTAL Airport Documentation Update $239, Project Airport Documentation Update AIP Grant Total Cost Entitlement Discretionary Local PFC Request Airfield Pavement Maintenance Update 120, ,000 12,000 12,000 Program Update Airport Layout Plan Update 227, , , , , , ,722

49 PFC APPLICATION NUMBER: DSM PFC Application #16 ATTACHMENT B: PROJECT INFORMATION 1. Project Title: Airport Documentation Update 2. Project Number 3. Use Airport of Project: Des Moines International (DSM) 4. Project Type [ ] Impose Only: [ X ] Concurrent: [ ] Use Only: Link to application: 5. Level of Collection: [ ] $1.00 [ ] $2.00 [ ] $3.00 [ ] $4.00 [ X ] $ Financing Plan PFC Funds: Pay-as-you-go $ 239,722 Bond Capital $ Bond Financing & Interest $ Subtotal PFC Funds*: $ 239,722 If amount is over $10 million, include cost details sufficient to identify eligible and ineligible costs. Existing AIP Funds: Grant # Grant Funds in Project Subtotal Existing AIP Funds: Anticipated AIP Funds (List Each Year Separately): Fiscal Year: 2018 Entitlement Discretionary $ 108,000 Total $ 108,000 Subtotal Anticipated AIP Funds: $108,000 Other Funds: State Grants $

50 Local Funds Other (please specify) $ Subtotal Other Funds: Total Project Cost: $347,722 For FAA Use a. Does the project include a proposed LOI? [ ] YES [ ] NO If YES, does the Region support? [ ]YES [ ] NO. If YES, list the schedule for implementation: b. For any proposed AIP discretionary funds, does the Region intend to support? [ ] YES [ ] NO c. For any proposed AIP funds, is the request within the planning levels for the Region's five year CIP? [ ] YES [ ] NO d. For project requesting PFC funding levels of $4.00 and $4.50: Is there an expectation that AIP funding will be available to pay the project costs. [ ] YES [ ] NO What percentage of the total project cost is funded through AIP? List the source(s) of data used to make this finding. e. Terminal and surface transportation projects requesting a PFC funding level of $4.00 and $4.50. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ ] YES [ ] NO [ ] N/A List the source(s) of data used to make this finding. f. Reasonableness of cost. Project Total Cost Analysis PFC Share of Total Cost Analysis

51 7. Back-up Financing Plan: These projects will complete required documentation for the Airport Authority to maintain, so they will be funded by operations if PFCs are not approved. If proposed AIP discretionary funds or a proposed LOI are included in the Financing Plan, provide a Back-up Financing Plan or a project phasing plan in the event the funds are not available for the project. For FAA Use If required to use a back-up financing/phasing plan, indicate the need to obtain additional approvals to obtain an alternate source of financing. Indicate the additional PFC duration of collection required if PFC s are to be used to fund the difference. Recap any discussion from previous item regarding likelihood of public agency obtaining the funding it proposes. 8. Project Description: The Airport Documentation Update project includes updating the Pavement Condition Report and the Airport Layout Plan. The Pavement Condition Report will be updated with the work completed since the last update and determine current PCI values for the airfield. The Airport Layout Plan will be updated with the findings from the programming study that is currently being completed. In addition, the update will include analysis of trees on properties surrounding the airport to ensure none are violating the airspace. If applicable for terminal projects, Prior to implementation of this project, Number of ticket counters: Number of gates: Number of baggage facilities: At completion of this project, Number of ticket counters: Number of gates: Number of baggage facilities: Net change due to this project: Number of ticket counters: Number of gates: Number of baggage facilities:

52 Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ X ] YES [ ] NO [ ] N/A FOR FAA USE Comment upon and/or Clarify Project Description. Include source citation if clarification information is not from PFC application. If project involves the construction of a new runway or modification of an existing runway, have the requirements of Order , with regard to runway safety areas been met? If not, is the runway grandfathered or has a modification been approve, or is there a likelihood the requirements will be met, or should the project be disapproved. If the project involves terminal work, confirm information regarding ticket counters, gates, and baggage facilities for construction and/or rehabilitation above has been completed. Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ ] YES [ ] NO [ ] N/A 9. Significant Contribution: FOR FAA USE Air safety. Part 139 [ ] Other (explain) Certification Inspector concur. Yes [ ] No [ ] Date Air security. Part 107 [ ] Part 108 [ ] Other (explain) CASFO concur. Yes [ ] No [ ] Date Competition. Competition Plan [ ] Other (explain) Congestion. Current [ ] or Anticipated [ ] LOI [ ] FAA BCA [ ] FAA Airport Capacity Enhancement Plan [ ] Other (explain) Noise. 65 LDN [ ] Other (explain)

53 Project does not qualify under significant contribution rules. Quantitative and qualitative analysis of significant contribution option chosen by public agency. If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. How does this project address the deficiency sited by the public agency? If competition is the chosen option, provide the FAA s analysis of any barriers to competition at the airport. 10. Project Objective: The objective of this project is to update the required documentation with the changes identified during the Terminal Programming project as well as repair and maintenance that has occurred in the last few years. FOR FAA USE Safety, Preserve [ ] Enhance [ ] Security, Preserve [ ] Enhance [ ] Capacity, Preserve [ ] Enhance [ ] Furnish opportunity for enhanced competition between or among air carriers at the airport Mitigate noise impacts resulting from aircraft operations at the airport Project does not meet any PFC objectives (explain) Finding Current deficiency. List the source(s) of data used to make this finding if it is not a part of the PFC application. Address adequacy of issues. 11. Project Justification: The Pavement Condition Report and the Airport Layout Plan are required documents for the Authority to keep current. The plans are necessary for the safe operation of the airfield and airspace. Per Grant Assurance 11, airport sponsors are required to update the airfield pavement maintenance program every 3-5 years. Last update occurred in FOR FAA USE Define how the project accomplishes PFC Objective(s)

54 Explain how project is cost-effective compared to other reasonable and timely means to accomplish this objective(s) Based on informed opinion or published FAA guidance, specify how the cost of the project is reasonable compared to the capacity, safety, security, noise and/or competition benefits attributable to the project. Include citation for any documents that are not a part of this PFC application. If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. Discuss any non-economical benefits which are not captured above. Project Eligibility: Indicate project eligibility by checking the appropriate category below. [ ] Development eligible under AIP criteria (paragraph of Order _ or PGL ); [ ] Planning eligible under AIP criteria (paragraph of Order _ or PGL ); [ ] Noise compatibility planning as described in 49 U.S.C ; [ ] Noise compatibility measures eligible under 49 U.S.C [ ] Project approved in an approved Part 150 noise compatibility plan; Title and Date of Part 150: [ ] Project included in a local study. Title and Date of local study: [ ] Terminal development as described in 49 U.S.C (a)(3)(C); [ ] Shell of a gate as described in 49 U.S.C 40117(a)(3)(F) (air carrier, percentage of annual boardings ); [ ] PFC Program Update Letter [ ] Project does not meet PFC eligibility (explain). If analysis is based on a source other than this PFC application, list the source(s) of data and attach the relevant documentation used to make this finding. Are any work elements or portions of the overall project ineligible? Provide associated costs. 12. Estimated Project Implementation Date (Month and Year): January 2017 Estimated Project Completion Date (Month and Year): October 2018 For FAA Use For Impose and Use or Use Only projects, will the project begin within 2 years of PFC application Due date (120-day)?

55 [ ] Yes [ ] No For Impose Only project, will the project begin within 5 years of the charge effective date or PFC application Due date, whichever is first? [ ] Yes [ ] No Is this project dependent upon another action to occur before its implementation or completion. Explain. 13. For an Impose Only project, estimated date Use application will be submitted to the FAA (Month and Year): For FAA Use Is the date within 3 years of the estimated charge effective date or approval date, whichever is sooner. [ ] Yes [ ] No Which actions are needed before the use application can be submitted? What is the estimated schedule for each action? 14. Project requesting PFC funding levels of $4.00 and $4.50: a. Can project costs be paid for from funds reasonably expected to be available through AIP funding. [ ] YES [ X ] NO b. If the FAA determines that the project may qualify for AIP funding, would the public agency prefer that the FAA approve [ X ] the amount of the local match to be collected at a $4.50 PFC level, or [ ] the entire requested amount at a $3.00 PFC level. c. Terminal and surface transportation projects. The public agency has made adequate provision for financing the airside needs of the airport, including runways, taxiways, aprons, and aircraft gates. [ X ] YES [ ] NO [ ] N/A 15. List of Carriers Certifying Agreement List of Carriers Certifying Disagreement: Recap of Disagreements

56 Public Agency Reasons for Proceeding: 16. List of Comments Received from the Public Notice: List of Parties Certifying Agreement. Recap of Disagreements Public Agency Reasons for Proceeding: For FAA Use Provide an analysis of each issue/disagreement raised by the air carriers and/or the public. Provide citations for any documents not included in the PFC application that are relied on by the FAA for its analysis. If a Federal Register notice is published, discuss and analyze any new issues raised. (If the comments from the consultation are repeated, state that.) ADO/RO Recommendation: Does the ADO/RO find the total costs of this project to be reasonable? Did the ADO/RO use comparable projects to make this finding? If so, list projects. If the amount requested if over $10 million, was the level of detail sufficient to identify eligible and ineligible costs. Summarize ineligible costs. Is the duration of collection adequate for the amount requested? ADO/RO RECOMMENDATION: [ ] Approve. [ ] Partially Approve. Summarize findings from earlier in the Attachment B discussing issues that lead to determination. [ ] Disapprove. Summarize findings from earlier in the Attachment B discussing issues that lead to determination. Application Reviewed by: Name Routing Symbol Date Item(s) reviewed.

57 Name Routing Symbol Date Item(s) reviewed

58 CIP DATA SHEET AIRPORT Des Moines International Airport LOCID DSM LOCAL PRIORITY PROJECT DESCRIPTION Airfield Pavement Maintenance Program Update Identify FFY that you desire to construct (FFY: Oct. 1-Sept. 30) FY2018 SKETCH: JUSTIFICATION: Per Grant Assurance 11, airport sponsors are required to update the airfield pavement maintenance program every 3-5 years. Last update occurred in COST ESTIMATE: (Attach detailed cost estimate) Federal (90%) $108,000 State $0 Local (10%) $12,000 Total $120,000 SPONSOR S VERIFICATION: Date For each and every project Date of approved ALP with project shown as applicable - Date of environmental determination (ROD, FONSI, CE), or cite CE #310 paragraph # ( ) in Order E NA - Date of land acquisition or signed purchase agreement FAA USE ONLY Date of pavement maintenance program FAA Verification: (initial/date) NA - Snow removal equipment inventory & sizing worksheet (for SRE acquisition) NA - Apron sizing worksheet (for apron projects) - Revenue producing facilities (for fuel farms, hangers, etc.) NA - Date statement submitted for completed airside development NA - Date statement submitted for runway approaches are clear of obstructions SPONSOR S SIGNATURE: DATE: PRINTED NAME: Bryan Belt TITLE: Director of Engineering and Planning PHONE NUMBER: (515) FAA USE ONLY PREAPP NUMBER GRANT NUMBER NPIAS CODE WORK CODE FAA PRIORITY FEDERAL $

Passenger Facility Charge Application #1

Passenger Facility Charge Application #1 Passenger Facility Charge Application #1 February 2017 APPLICATION PUNTA GORDA AIRPORT PFC ASSURANCES CERTIFICATION STATEMENT The undersigned Chair of the Charlotte County Airport Authority assures

More information

FEDERAL AIRPORT IMPROVEMENT PROGRAM (AIP) PRE-APPLICATION FFY 2017 CHECKLIST

FEDERAL AIRPORT IMPROVEMENT PROGRAM (AIP) PRE-APPLICATION FFY 2017 CHECKLIST Form 291111wd (09-15) Storm Lake Municipal Airport Airport FEDERAL AIRPORT IMPROVEMENT PROGRAM (AIP) PRE-APPLICATION FFY 2017 SLB FAA Identifier CHECKLIST Please attach the following documents with your

More information

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment PUBLIC NOTICE The Dallas Department of Aviation (the Department) intends to file an amendment application to increase the PFC amount of one previously approved project at Dallas Love Field Airport (the

More information

Ann Arbor Municipal Airport Ann Arbor, MI Date of Latest ALP ACIP Airport Code - A Airport Identifier - ARB

Ann Arbor Municipal Airport Ann Arbor, MI Date of Latest ALP ACIP Airport Code - A Airport Identifier - ARB MICHIGAN AIRPORT DEVELOPMENT PROGRAM AIP CAPITAL IMPROVEMENT PLAN 20102019 FEDERAL/STATE/LOCAL Ann Arbor, MI Date of Latest ALP 2008 ACIP Airport Code A Airport Identifier ARB Prepared by: MDOTAERO Sponsor:

More information

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction

More information

ADDENDUM NO. TWO AB

ADDENDUM NO. TWO AB ADDENDUM NO. TWO AB2018-28 Notice is hereby given that on June 22, 2018 at 11:00 A.M. (Prevailing time), sealed bids will be opened and read in public by the Purchasing Department in the Mercer County

More information

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS P U B L I C N O T I C E MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application 10-07-C-00-MBS INTRODUCTION: This Public Notice is issued as part of a Federal Aviation

More information

Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application

Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application July 3, 2018 Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application The City of Kansas City (City), Missouri through its Aviation Department ( the Department

More information

Chapter 9 Airport Financial Plan

Chapter 9 Airport Financial Plan Chapter 9 Airport Financial Plan Introduction The purpose of this chapter is to present the projects identified in the twenty-year Airport Capital Improvement Program (ACIP) that have been developed and

More information

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP) 6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement

More information

14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice

14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice 14 C.F.R. Part 158 Passenger Facility Charge Program Logan International Airport Public Notice Summary of Proposed 2018 PFC Application PFC Project Descriptions and Justifications PFC Financial Plan Class

More information

PUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application

PUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application PUBLIC NOTICE ***************************** New Castle Airport Intention to File a Passenger Facility Charge (PFC) Application The Delaware River & Bay Authority (DRBA), the sponsor of the New Castle Airport

More information

New PFC Application #13

New PFC Application #13 PUBLIC CONSULTATION New PFC Application #13 Buffalo, NY December 16, 2015 Agenda PFC Program at Notice to Carriers and Consultation Meeting Class of Carrier Not Required to Collect PFC Air Carrier Requirements

More information

CHICAGO DEPARTMENT OF AVIATION. Current Construction Projects AND THE O HARE MODERNIZATION PROGRAM. May 2, 2014

CHICAGO DEPARTMENT OF AVIATION. Current Construction Projects AND THE O HARE MODERNIZATION PROGRAM. May 2, 2014 CHICAGO DEPARTMENT OF AVIATION AND THE O HARE MODERNIZATION PROGRAM Current Construction Projects May 2, 2014 O HARE INTERNATIONAL AIRPORT CURRENT CONFIGURATION 2 PHASE 1 & COMPLETION PHASE 9L-27R Completed

More information

BID FORM. Bid by: Name of Bidder. Address: Address: To the Texas Department of Transportation hereinafter called the Agent.

BID FORM. Bid by: Name of Bidder. Address:  Address: To the Texas Department of Transportation hereinafter called the Agent. BID FORM TxDOT CSJ No. Project Description: This project includes reconstruction of a hangar access taxiway with trench drain and pipe drainage system; local reconstruction of failing pavement on Taxiway

More information

Section (a)(1). Description of Projects Impose and Use

Section (a)(1). Description of Projects Impose and Use November 21, 2017 Mrs. Kelly Lane SkyWest Airlines 444 South River Road St. George, UT 84790 RE: Notice of Intent to Impose and Use a New Passenger Facility Charge Bert Mooney Airport Butte, Montana Dear

More information

PFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018

PFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018 PFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018 Table of Contents Section Page I. Overview 2 II. Notice and Opportunity for Public Comment 3 III. Application

More information

Passenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico.

Passenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico. Passenger Facility Charge: No. 7 Application December 2013 Public Notice Materials Luis Muñoz Marín International Airport San Juan Puerto Rico INTRODUCTION Aerostar Airport Holdings has initiated the process

More information

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Overview of the FAA s Office of Airports Prepared for: Presented by: 2016 ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Eduardo Angeles Associate Administrator for Airports Date:

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

MOST aircraft need a runway for landing and takeout.

MOST aircraft need a runway for landing and takeout. 38th Annual Concrete Paving Workshop Upcoming Airport Projects January 17, 2017 MOST aircraft need a runway for landing and takeout. 1 Airport Improvement Program AIP Eligibility The federal AIP grants

More information

JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007

JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007 JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 27 11242 1 of 14 Sponsor: City of Naples Airport Authority NPIAS No.: 12-53 Sponsor ID: 122 Airport ID: APF Site No.: 3379.*A 11242 Airport Project ID: 1

More information

Finance and Implementation

Finance and Implementation 5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter

More information

GREATER ORLANDO AVIATION AUTHORITY

GREATER ORLANDO AVIATION AUTHORITY GREATER ORLANDO AVIATION AUTHORITY Amendment to PFC Applications #7, 8, and 16 and New PFC Application #18 PUBLIC NOTICE June 7, 2016 1 P age Table of Contents PUBLIC NOTICE... 3 PROPOSED ACTIONS... 3

More information

Public Notice July 14, 2017

Public Notice July 14, 2017 Public Notice July 14, 2017 PROPOSED IMPLEMENTATION OF PFC 13 NOTICE TO AIR CARRIERS AND CONSULTATION MEETING Implementation of PFC On June 14, 2017 the Omaha Airport Authority provided written notice

More information

DALLAS LOVE FIELD MAY 2015 DRAFT

DALLAS LOVE FIELD MAY 2015 DRAFT 8. Funding Plan This section presents a potential funding plan for implementing the CIP projects recommended in the Master Plan Update, along with an assessment of the ability of the Airport sponsor (i.e.,

More information

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update Chapter Seven Implementation Plan Master Plan Update This chapter presents the 20-year improvement program for the continued development of the. The objectives of this chapter are to identify projects

More information

Yakima Air Terminal/McAllister Field Airport Master Plan Update

Yakima Air Terminal/McAllister Field Airport Master Plan Update Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used

More information

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 LAWTON-FORT SILL REGIONAL AIRPORT LAWTON, OKLAHOMA PASSENGER FACILITY CHARGE PROPOSED

More information

Public Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport. Effective: February 22, 2019

Public Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport. Effective: February 22, 2019 Public Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport Effective: February 22, 2019 Pursuant to 49 CFR Part 158.24, the city of Charlotte

More information

RESOLUTION NO

RESOLUTION NO RESOLUTION NO. 2015-15 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MARINA AUTHORIZING SUBMISSION OF A GRANT APPLICATION TO THE FEDERAL AVIATION ADMINISTRATION (FAA) FOR PARTICIPATION IN THE 2015 MILITARY

More information

Correction to Council Resolution No , dated June 25, Please add the following correction as part of the permanent record:

Correction to Council Resolution No , dated June 25, Please add the following correction as part of the permanent record: 1410 Memorandum 9 DATE October 20, 2014 CITY OF DALLAS TO Rosa Rios City Secretary SUBJECT Correction to Council Resolution No. 14-1030, dated Please add the following correction as part of the permanent

More information

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington

More information

COMMONWEALTH PORTS AUTHORITY

COMMONWEALTH PORTS AUTHORITY REPORT ON COMPLIANCE AND INTERNAL CONTROL OVER COMPLIANCE WITH REQUIREMENTS APPLICABLE TO THE PASSENGER FACILITY CHARGE PROGRAM YEAR ENDED SEPTEMBER 30, 2015 Deloitte & Touche LLC P.O. Box 500308 Saipan,

More information

Airport. Improvement Program (AIP) Overview. Federal Aviation Administration. Texas Aviation Conference Ben Guttery, Texas ADO April 2017

Airport. Improvement Program (AIP) Overview. Federal Aviation Administration. Texas Aviation Conference Ben Guttery, Texas ADO April 2017 Airport Improvement Program (AIP) Overview Texas Aviation Conference Ben Guttery, Texas ADO April 2017 Objectives Status of AIP Legislative Authority History and Summary of AIP AIP funding formulas 2 AIP

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information

Preferred Alternative Summary

Preferred Alternative Summary Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative

More information

PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT

PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT Pursuant to CFR 158.24, the City and County of Denver Department of Aviation ( City ), owner and operator of the Denver International

More information

PFC Application #2 Niagara Falls International Airport

PFC Application #2 Niagara Falls International Airport Public Notice Application #2 Falls International April 12, 2018 Agenda Program at the Falls International Notice to air carriers and consultation meeting Class of air carriers not required to collect Air

More information

Development Program and Implementation Plan

Development Program and Implementation Plan CHAPTER 8 Development Program and Implementation Plan 8.1 INTRODUCTION The FAA identifies airports that are significant to national air transportation through the development of the National Plan of Integrated

More information

Financial Feasibility Analysis

Financial Feasibility Analysis CHAPTER F Financial Feasibility Analysis 1. Introduction This chapter presents a funding plan for completion of recommended capital projects at Friedman Memorial Airport (the Airport) through FY 2034,

More information

Airport Master Plan Open House Front Range Airport February 23, 2017

Airport Master Plan Open House Front Range Airport February 23, 2017 Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future

More information

MIAMI-DADE AVIATION DEPARTMENT. Civil Environmental Engineering Division

MIAMI-DADE AVIATION DEPARTMENT. Civil Environmental Engineering Division MIAMI-DADE AVIATION DEPARTMENT MIA Runway 8R8R-26L Pavement Pavement Rehabilitation Civil Environmental Engineering Division The Project Team Mission Statement C EXPERTISE + COMMITMENT = OWNERSHIP Project

More information

8.0 AIRPORT LAYOUT PLANS

8.0 AIRPORT LAYOUT PLANS 8.0 AIRPORT LAYOUT PLANS This chapter presents a detailed graphic and narrative description of the selected development concept for General Mitchell International Airport (MKE). The plans package presented

More information

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Pursuant to 14 CFR Part 158.24(a) (1) (III), the Broward County

More information

Session 6 Airport Finance 101 Funding Sources for Airports

Session 6 Airport Finance 101 Funding Sources for Airports Session 6 Airport Finance 101 Funding Sources for Airports 31 st Annual AAAE Basics of Airport Law Workshop and 2015 Legal Update November 1-3, 2015 Desk Reference Chapters 2, 19, 22 Frank J. San Martin

More information

MassDOT Aeronautics Division Capital Improvements Presentation

MassDOT Aeronautics Division Capital Improvements Presentation MassDOT Aeronautics Division Capital Improvements Presentation MassDOT Board Retreat October 27, 2011 Presentation Agenda Capital Improvement Plan (CIP) Overview Airports Capital Improvement Plan (ACIP)

More information

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 Agenda Overview of PFC Program at Spokane Airport (GEG) Proposed New PFC 11 Application Project

More information

RESOLUTION No APPROVAL OF WAYNE COUNTY AIRPORT AUTHORITY FISCAL YEAR 2018 BUDGET. By Board Member Mark Ouimet

RESOLUTION No APPROVAL OF WAYNE COUNTY AIRPORT AUTHORITY FISCAL YEAR 2018 BUDGET. By Board Member Mark Ouimet RESOLUTION 17-87 APPROVAL OF WAYNE COUNTY AIRPORT AUTHORITY FISCAL YEAR 2018 BUDGET By Board Member Mark Ouimet WHEREAS, the Wayne County Airport Authority (the Authority ), pursuant to the Aeronautics

More information

FAA Update. Dakota-Minnesota (DMA) Airports District Office. Federal Aviation Administration. Presented to: By: Date: South Dakota Airports Conference

FAA Update. Dakota-Minnesota (DMA) Airports District Office. Federal Aviation Administration. Presented to: By: Date: South Dakota Airports Conference FAA Update Dakota-Minnesota (DMA) Airports District Office Presented to: By: Date: South Dakota Airports Conference Chris Hugunin & Dave Anderson March 18, 2015 FY 2014 DMA ADO Total AIP Funding $107.2

More information

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35 Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements

More information

THE CASE OF A SUCCESSFUL PFC APPLICATION

THE CASE OF A SUCCESSFUL PFC APPLICATION THE CASE OF A SUCCESSFUL PFC APPLICATION 1 Chapter One: Scene of the case study 2 Chapter One: The Scene Spokane, WA Home of the RED TURF at Eastern WA University (and Gonzaga) 3 Chapter One: The Scene

More information

2017 Appropriation Budget Table of Contents Board Approved August 19, 2016

2017 Appropriation Budget Table of Contents Board Approved August 19, 2016 INDIANAPOLIS AIRPORT AUTHORITY 2017 APPROPRIATION BUDGET ORDINANCE NO. 2-2016 BOARD APPROVED AUGUST 19, 2016 2017 Appropriation Budget Table of Contents Board Approved August 19, 2016 1 Appropriation Summary

More information

II. Purpose and Need. 2.1 Background

II. Purpose and Need. 2.1 Background II. 2.1 Background The Metropolitan Washington Airports Authority is preparing an Environmental Assessment of potential environmental impacts associated with proposed enhancements to the Runway 4-22 and

More information

PUBLIC NOTICE Passenger Facility Charge Application #8 San Francisco International Airport. December 28, 2017

PUBLIC NOTICE Passenger Facility Charge Application #8 San Francisco International Airport. December 28, 2017 PUBLIC NOTICE Passenger Facility Charge Application #8 San Francisco International Airport December 28, 2017 Introduction Pursuant to 14 Code of Federal Regulations ( CFR ) Part 158.24, the San Francisco

More information

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM PORT OF PORTLAND Chapter Seven CAPITAL IMPROVEMENT PROGRAM CHAPTER SEVEN PORT OF PORTLAND CAPITAL IMPROVEMENT PROGRAM The analyses conducted in the previous chapters evaluated airport development needs

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013 New York State Department of Transportation Safety, Infrastructure, and Tenant Improvement Project Public Hearing Informational Brochure February 26, 2013 This DEIS/Draft EA evaluates the potential impacts

More information

Planning & Development Group

Planning & Development Group Planning & Development Group LAX Airside Technical Committee Meeting January 9, 2018 Mark Vicelja, P.E. 1 Airside Element Projects LAX AIRSIDE ELEMENT PROJECTS CONSTRUCTION SCHEDULE (as of January 1, 2018)

More information

City of Tallahassee, FL Department of Aviation

City of Tallahassee, FL Department of Aviation City of Tallahassee, FL Department of Aviation Proposed Application to Federal Aviation Administration For Authority to Impose a Passenger Facility Charge (PFC) at Tallahassee International Airport and

More information

Regular Board Meeting August 4, 2015

Regular Board Meeting August 4, 2015 Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956 PUBLIC COMMENT FY 16 Rates & Charges FY 16 Budget Approval Rates & Charges will provide the Board the ability to operate

More information

FINAL AGENCY DECISION CITY OF CHARLOTTE CHARLOTTE, NORTH CAROLINA

FINAL AGENCY DECISION CITY OF CHARLOTTE CHARLOTTE, NORTH CAROLINA FINAL AGENCY DECISION CITY OF CHARLOTTE CHARLOTTE, NORTH CAROLINA Application Number 17-06-C-00-CL T to impose a passenger facility charge (PFC) at Charlotte-Douglas International Airport (CL T) for use

More information

Chapter 8.0 Implementation Plan

Chapter 8.0 Implementation Plan Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.

More information

PENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN

PENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN PENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN OCTOBER 2018 T A B L E O F C O N T E N T S Table of Contents Chapter 8 Financial Plan 8.1 Introduction... 8-1 8.2 Enplanement

More information

AIRPORT NOISE AND CAPACITY ACT OF 1990

AIRPORT NOISE AND CAPACITY ACT OF 1990 AIRPORT NOISE AND CAPACITY ACT OF 1990 P. 479 AIRPORT NOISE AND CAPACITY ACT OF 1990 SEC. 9301. SHORT TITLE This subtitle may be cited as the Airport Noise and /Capacity Act of 1990. [49 U.S.C. App. 2151

More information

6.4 Aviation AVIATION FACILITIES AND SERVICES

6.4 Aviation AVIATION FACILITIES AND SERVICES 2035 Transportation Plan 6.4 Aviation This chapter describes existing aviation facilities and services in Placer County and projected needs. This chapter also discusses potential aviation issues related

More information

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Project Team Kittitas County, WA Airport Owner (Sponsor) and Operator, Land Use Century West

More information

Pavement Strength Analysis Prepared by Molzen Corbin September 2016

Pavement Strength Analysis Prepared by Molzen Corbin September 2016 Pavement Strength Analysis Prepared by Molzen Corbin September 2016 The Santa Fe Municipal Airport was originally constructed in 1941. It was constructed by the military as a B-24 bomber training base.

More information

[Docket No. FAA ; Product Identifier 2018-NM-117-AD; Amendment ; AD ]

[Docket No. FAA ; Product Identifier 2018-NM-117-AD; Amendment ; AD ] [Federal Register Volume 83, Number 236 (Monday, December 10, 2018)] [Rules and Regulations] [Pages 63397-63399] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR

More information

Grants Pass Airport Master Plan & Airport Layout Plan Update

Grants Pass Airport Master Plan & Airport Layout Plan Update Attendees: Grants Pass Airport Master Plan & Airport Layout Plan Update Meeting #3 January 26, 2010 Merlin Community Center 100 Acorn Street, Merlin 5:45 7:15 p.m. Josephine County Department of Airports:

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

AIRPORT WITH NO RUNWAYS IS A MALL

AIRPORT WITH NO RUNWAYS IS A MALL RUNWAY EXTENSION INITIATIVE AT FT. LAUDERDALE HOLLYWOOD INTERNATIONAL AIRPORT ISMAEL IZZY BONILLA DEPUTY DIRECTOR BROWARD COUNTY AVIATION AUTHORITY AIRPORT WITH NO RUNWAYS IS A MALL Runway Business Case

More information

BOARD OF AIRPORT COMMISSIONERS

BOARD OF AIRPORT COMMISSIONERS 1 8/17/2018 8/21/2018 8/16/2018 i ElY MY Y I : JH MT BY...01,, III1*.ji,"1.111Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: la Approved by: e1. "ampbell, Chief Airports

More information

Appendix F Cultural Resource Consultation

Appendix F Cultural Resource Consultation Appendix F Cultural Resource Consultation FAA Consultation Letter to the California State Historic Preservation Officer Response Letter from the California State Historic Preservation Officer STATE

More information

PUBLIC NOTICE FOR PROPOSED COLLECTION OF PASSENGER FACILITY CHARGES AT COLORADO SPRINGS AIRPORT

PUBLIC NOTICE FOR PROPOSED COLLECTION OF PASSENGER FACILITY CHARGES AT COLORADO SPRINGS AIRPORT PUBLIC NOTICE FOR PROPOSED COLLECTION OF PASSENGER FACILITY CHARGES AT COLORADO SPRINGS AIRPORT Date of Public Notice: 8/15/2016 In accordance with the requirements of Section 158.24 of Federal Aviation

More information

SUPERSEDED. [Docket No. FAA ; Directorate Identifier 2015-SW-014-AD; Amendment ; AD ]

SUPERSEDED. [Docket No. FAA ; Directorate Identifier 2015-SW-014-AD; Amendment ; AD ] [Federal Register Volume 80, Number 95 (Monday, May 18, 2015)] [Rules and Regulations] [Pages 28172-28175] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No:

More information

PEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE REGIONAL AIRPORT

PEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE REGIONAL AIRPORT PEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE REGIONAL AIRPORT PUBLIC NOTICE FOR PASSENGER FACILITY CHARGE APPLICATION NO. 2 AUGUST 6, 2014 Prepared By: PUBLIC NOTICE PEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE

More information

General Aviation Master Plan Update

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

Memorandum. Federal Aviation Administration. Date: June 19, Richard Doucette, Environmental Protection Specialist. From: To:

Memorandum. Federal Aviation Administration. Date: June 19, Richard Doucette, Environmental Protection Specialist. From: To: Federal Aviation Administration Memorandum Date: June 19, 2008 From: To: Subject: Richard Doucette, Environmental Protection Specialist LaVerne Reid, Airports Division Manager John Donnelly, Regional Counsel

More information

Wyoming Valley Airport Proposed Improvements. Presented June 26, 2012 By The WBW Airport Advisory Board & FBO

Wyoming Valley Airport Proposed Improvements. Presented June 26, 2012 By The WBW Airport Advisory Board & FBO Wyoming Valley Airport Proposed Improvements Presented June 26, 2012 By The WBW Airport Advisory Board & FBO Contents Purpose of meeting Airport overview Background of proposed improvements SWOT analysis

More information

AIRLINE CONSULTATION MEETING

AIRLINE CONSULTATION MEETING AIRLINE CONSULTATION MEETING Passenger Facility Charges Proposed Projects South Burlington, Vermont August 2012 Prepared by: 150 Dow St., Manchester, NH 03101 603-669-5555 INTRODUCTION The Burlington International

More information

[Docket No. FAA ; Directorate Identifier 2013-CE-036-AD; Amendment. Airworthiness Directives; PILATUS Aircraft Ltd.

[Docket No. FAA ; Directorate Identifier 2013-CE-036-AD; Amendment. Airworthiness Directives; PILATUS Aircraft Ltd. This document is scheduled to be published in the Federal Register on 11/08/2013 and available online at http://federalregister.gov/a/2013-25953, and on FDsys.gov [4910-13-P] DEPARTMENT OF TRANSPORTATION

More information

Chapter 2 FINDINGS & CONCLUSIONS

Chapter 2 FINDINGS & CONCLUSIONS Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued

More information

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February

More information

Passenger Facility Charge New Application #8 Phoenix Sky Harbor International Airport

Passenger Facility Charge New Application #8 Phoenix Sky Harbor International Airport Passenger Facility Charge New Application #8 Phoenix Sky Harbor International Airport Airline Consultation and Public Notice Materials Date: May 4, 2017 Agenda PFC Program Status PFC #8 New Application

More information

Notice of Air Carrier Consultation Meeting for PFC Application Niagara Falls International Airport (NFIA/IAG)

Notice of Air Carrier Consultation Meeting for PFC Application Niagara Falls International Airport (NFIA/IAG) 181 Ellicott Street Buffalo, New York 14203 716-855-7300 Fax: 716-855-7657 TDD: 855-7650 www.nfta.com Re: Notice of Air Carrier Consultation Meeting for PFC Application Niagara Falls International Airport

More information

Appendix C AIRPORT LAYOUT PLANS

Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

[Docket No. FAA ; Directorate Identifier 2013-CE-028-AD] Airworthiness Directives; DORNIER LUFTFAHRT GmbH Airplanes

[Docket No. FAA ; Directorate Identifier 2013-CE-028-AD] Airworthiness Directives; DORNIER LUFTFAHRT GmbH Airplanes This document is scheduled to be published in the Federal Register on 11/19/2013 and available online at http://federalregister.gov/a/2013-27665, and on FDsys.gov [4910-13-P] DEPARTMENT OF TRANSPORTATION

More information

Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies

Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, 2017 Prepared by: File: Attendees: Shannon Eibert, C&S Companies N93.012.001 See Sign-In List A third meeting was held

More information

Notice of Passenger Facility Charge (PFC) Approvals and Disapprovals

Notice of Passenger Facility Charge (PFC) Approvals and Disapprovals This document is scheduled to be published in the Federal Register on 12/04/2014 and available online at http://federalregister.gov/a/2014-28535, and on FDsys.gov 1 DEPARTMENT OF TRANSPORTATION Federal

More information

Revo, Incorporated: Amendment ; Docket No. FAA ; Directorate Identifier 2012-CE-013-AD.

Revo, Incorporated: Amendment ; Docket No. FAA ; Directorate Identifier 2012-CE-013-AD. 2013-08-14 Revo, Incorporated: Amendment 39-17431; Docket No. FAA-2012-0845; Directorate Identifier 2012-CE-013-AD. (a) Effective. Date This airworthiness directive (AD) is effective June 13, 2013. (b)

More information

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017 INDIANAPOLIS AIRPORT AUTHORITY 2018 APPROPRIATION BUDGET ORDINANCE NO. 1-2017 BOARD APPROVED AUGUST 18, 2017 2018 Appropriation Budget Table of Contents Board Approved August 18, 2017 1 Appropriation Summary

More information

SERVICE INFORMATION LETTER Page: 1 of 2

SERVICE INFORMATION LETTER Page: 1 of 2 SERVICE INFORMATION LETTER Page: 1 of 2 SERVICE INFORMATION LETTER NO. SILD42L-007 13 Sep 12 NOTE: NOTE: NOTE: Service Information Letters (SIL) are used only: 1. To distribute information from Diamond

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the

More information

[Docket No. FAA ; Product Identifier 2017-CE-049-AD; Amendment ; AD R1]

[Docket No. FAA ; Product Identifier 2017-CE-049-AD; Amendment ; AD R1] [Federal Register Volume 83, Number 89 (Tuesday, May 8, 2018)] [Rules and Regulations] [Pages 20719-20725] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No:

More information

THE CESSNA AIRCRAFT COMPANY

THE CESSNA AIRCRAFT COMPANY Page 1 2010-20-10 THE CESSNA AIRCRAFT COMPANY Amendment 39-16444 Docket No. FAA-2010-0380; Directorate Identifier 2009-NM-009-AD PREAMBLE Effective Date (a) This AD becomes effective November 1, 2010.

More information