1 THE CASE OF A SUCCESSFUL PFC APPLICATION 1
2 Chapter One: Scene of the case study 2
3 Chapter One: The Scene Spokane, WA Home of the RED TURF at Eastern WA University (and Gonzaga) 3
4 Chapter One: The Scene Small Hub Airport ~FULL RESIDUAL AUA ~1.5M enplanements ~ $6M PFC Annually Currently have 10 PFC applications Most issues are Internal Unsophisticated Small Staff Coordinating CIP Understanding Eligibility 4
5 Chapter Two: Timeline 5
6 Chapter Two: Timeline Planning INTERNALLY Project Development Pre-Eligibility Determination Advance FAA Coordination (OPTIONAL) NOTIFICATION TO STAKEHOLDERS Air Carriers providing significant service Public AIR CARRIER CONSULTATION (AAAC) COMMENT WAITING PERIOD 6
7 Chapter Two: Timeline Planning DEVELOP APPLICATION In honor of Daytona, to Draft or not to Draft? COLLECT COMMENTS (Airlines do NOT approve, they agree or disagree) SUBMIT APPLICATION Do you ever wonder when they ll get this online? WAIT FOR IT KEEP WAITING.. 7
8 Chapter Two: Timeline Planning APPROVAL BY FAA (Final Agency Decision FAD) NOTICE TO AIRLINES # OF DAYS # OF MONTHS Planning????? Project ID????? Pre-Consultation????? Notices Airline Consultation Comment Period Application Substantially Complete Final FAA Approval Air Carrier Notice Ability to Collect 8
9 Chapter Three: The CIP Capital Improvement PLAN 9
10 Chapter Three: The Capital Improvement Plan Capital Improvement Plan (CIP) is vital to identify and prioritize development needs Project descriptions along with justifications for each project Safety, security, capacity, environmental, contractual obligations Needs vs. Wants Prioritization should produce a refined project pool that will promote and advance the overall organizational goals Houston Airport System CIP = 86 pages Philadelphia CIP = 143 pages Port of Portland = 87 pages 10
11 Chapter Three: The Capital Improvement Plan 11
12 Spokane Airports (Spokane International, Business Park, and Felts Field) 5-Year Capital Improvement Plan (FY ) Item FEDERAL FUNDS LOCAL FUNDS Project Description No. Entitlement Discretionary PFC OTHER Airport 2018 (FY January - December 2018) Total Spokane International Airport 283 Landside/Parking Projects: Spokane Internatio 284 Install Snow-Barrier Exterior Wall Panels on Parking Garage - Phase II - Design and Construction $500,000 $500, Landscaping - Phase V - Design and Construction $300,000 $300,000 nal 286Airport 287 Airfield Projects: Business Park 288 Rehabilitate Shoulders on R/W 7-25, T/Ws A & C and R/W 7-25 Marking & Signage Change - Phase II - Construction $7,000,000 $2,000,000 $900,000 $9,900, Rehabilitate Apron Areas - Phase I - Design $0 $0 $1,111,111 $1,111, Total Spokane International Airport Business Park FY 2018 $0 $0 $0 $0 $0 $0 290 Rehabilitate Building 725 Apron - Design and Construction $850,000 $850, Street Lighting LED Upgrade $200,000 $200,000 Felts Field 292 Acquire Fleet Vehicles (Replace #980 - E-1, old boom truck) $50,000 $50, Airfield: Improve Glycol Recovery System - Construction $8,000,000 $8,000, Acquire Fleet Wheel Vehicles Loader (Replace (Airfield#912 and - John Operations) Deere 544) $250,000 $50,000 $50,000 $250, Install Closed Circuit TV (CCTV) and Access Controls - Phase II - Construction $0 $ Fuel Facility Projects: Aviation Fuel Facility Leased Road Property Improvements Projects: - Phase II - Design & Construction $850,000 $850, Acquire Rehabilitate Land Pavement at Fuel Facility (Mill & Overlay, Cut, Patch, Fill) $200,000 $1,000,000 $1,000,000 $200, Terminal: Aviation Leased Property Projects: 301 New Hangar Development, Rehabilitate Central Ramp, and Access Roads - Phase I - Design and Construction $6,000,000 $6,000, Improve Terminal Lobby and Second Floor Office Space - Phase II - Construction $700,000 $700, Improve Airport Terminal Parking Lot - Phase II - Construction $1,500,000 $1,500, Non Aviation Leased Property Projects: $ Total 306 Terminal Felts Projects: Field FY 2018 $0 $0 $0 $0 $3,250,000 $3,250, Terminal Renovation and Expansion (TREX) - Central Bag Claim and Utility Relocations - Phase III - Construction $55,000,000 $55,000, TOTAL Replace FY Concourse 2018 Chair - Phase III - Upper C Concourse $7,000,000 $2,000,000 $56,100,000 $0 $24,001,111 $500,000 $89,101,111 $500, Replace Concourse C HVAC - Phase I - Design $50,000 $50, Acquire Fleet Vehicles (Replace #301) $40,000 $40, Aircraft Rescue and Fire Fighting (ARFF) Projects: 313 Acquire ARFF Truck (Replace #502 - Oshkosh T-3000) $900,000 $900, Information Technology Projects: 316 Airfield Perimeter Security - Phase IV - Gate Access Controls, Closed-circuit TV (CCTV), and Fiber Optics $400,000 $400, Security (Police/Communications) Projects: 319 Enhance Terminal Access Control - Phase I - Bollards and Exit Lane Technology $700,000 $700, Acquire Fleet Vehicle (Replace #601 - Ford Expedition) $50,000 $50, $ Total Spokane International Airport FY 2018 $7,000,000 $2,000,000 $56,100,000 $0 $20,751,111 $85,851,111 12
13 PFC Local 13
14 Chapter Four: Project Development 14
15 Chapter Four: PFC Project Development Preserve or enhance: Safety Security Capacity o of the national air transportation system Reduce or mitigate noise impacts resulting from an airport Furnish opportunities for enhanced competition between or among air carriers 15
16 Chapter Four: Project Development PFC 11 Project Costs 1 AIRFIELD WINTER OPERATIONS EQUIPMENT $ 4,085,000 a Airfield Pavement Weather Sensors 1,000,000 b Continuous Friction Measurement Vehicle 250,000 c Five (5) Pieces of SRE i Rotary Plow 605,000 ii Quad Track Loader / Ramp Plow 675,000 iii (2) MB-5 Combo 1,470,000 iv Skid Steer 85,000 2 TERMINAL REHABILITATION 9,902,352 a Roof Replacment, Rotunda, SkyBridge, A/B Ramps, Elevator Tower 1,000,000 b HVAC System 450,000 c A/B Restrooms Rehab 650,000 d PLC Boarding Bridges 2,202,352 e Terminal Vestibule Doors 900,000 f Skywalk A/B Windows & ceiling tile / lighting 1,000,000 g Concourse A/B Windows 1,850,000 h Entire Front of Terminal excluding TREX related 1,850, % DESIGN TERMINAL RENOVATION & EXPANSION (TREX) 1,890,590 4 PFC ADMINISTRATION FEES 45,000 $ 15,922,942 16
17 17
18 Chapter Five: 2:30PM later today "directly related to the movement of passengers and baggage movement" 18
19 Chapter Six: Pre-Consultation 19
20 Chapter Six: Pre-Consultation People skills and relationship building vs. Asking regulatory agency for permission to do things you are already authorized to do Concise description and justification Prior to AAAC Consultation Wordsmith: a person who works with words, a skillful writer (always pointing to eligibility) 20
21 Chapter Seven: Airline Consultation 21
22 Chapter Seven: Airline Consultation People skills and relationship building Business vs. Personal Timing In-Person / Conference Call Agenda History of PFCs Current Collections Open PFC Applications Project Descriptions Photos Next Steps: Comment Period, Application Submission 22
23 Chapter Eight: Application Submission 23
24 Chapter Eight: Application Submission HIRE IT OUT? Form CIP Attachment B Attachment G ALP, 7460, Environmental, Cat-Ex? Proof of process Notices, Consultations, Comments Meeting Notes ETC, ETC, ETC A-Grade Paper 24
25 Chapter Nine: Hurry up and wait 25
26 Chapter Ten: 26
27 What might it look in the future Original Part 158 document = 45 pages Current AIP Handbook = 544 pages Original PFC Handbook = 183 pages Recent Draft PFC Handbook Update = 212 pages Consult, Consultant, Consultation, Re-Consult Original Part 158 document = 18 uses Current AIP Handbook = 84 uses Original PFC Handbook = 191 uses Recent Draft PFC Handbook Update = 228 uses 27
28 Recent News Office of Inspector General (OIG) October 1, 2015 Audit Initiated of the Passenger Facility Charge Program Given the importance of the program and substantial funds involved, we are initiating an audit of the Federal Aviation Administration s (FAA) administration and oversight of the PFC program. AAAE Security Smart Brief November 1, 2016: FAA report predicts decline in AIP-eligible projects Because the vast majority of big terminal construction and renovation undertakings are not eligible for the AIP grants, those larger projects were not part of the FAA's latest figures. 28
29 End Result? More time Less Funds More Compliance Less Local Control Less application of the original concepts 29
30 Curtain Call: Reading Material Aviation Safety and Capacity Expansion Act of 1990 AIP Handbook: Order D (Especially the Tables) Federal Register 14 CFR Part 158 (15 pages of really small type) PFC Handbook Explaining 14 CFR Part 158 (45 pages of larger type) PFC Order : FAA PFC Administration Handbook Current FAA Advisory Circulars Required for Use in AIP Funded and PFC Approved Projects ARP SOP5.00 CATEX Determinations AND MORE Dave Armstrong, CPA Spokane International Airport
PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017
PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 Agenda Overview of PFC Program at Spokane Airport (GEG) Proposed New PFC 11 Application Project
More informationJACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007
JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 27 11242 1 of 14 Sponsor: City of Naples Airport Authority NPIAS No.: 12-53 Sponsor ID: 122 Airport ID: APF Site No.: 3379.*A 11242 Airport Project ID: 1
More informationP U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS
P U B L I C N O T I C E MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application 10-07-C-00-MBS INTRODUCTION: This Public Notice is issued as part of a Federal Aviation
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 LAWTON-FORT SILL REGIONAL AIRPORT LAWTON, OKLAHOMA PASSENGER FACILITY CHARGE PROPOSED
More informationNew PFC Application #13
PUBLIC CONSULTATION New PFC Application #13 Buffalo, NY December 16, 2015 Agenda PFC Program at Notice to Carriers and Consultation Meeting Class of Carrier Not Required to Collect PFC Air Carrier Requirements
More informationPassenger Facility Charge Application #1
Passenger Facility Charge Application #1 February 2017 APPLICATION PUNTA GORDA AIRPORT PFC ASSURANCES CERTIFICATION STATEMENT The undersigned Chair of the Charlotte County Airport Authority assures
More information2017 Appropriation Budget Table of Contents Board Approved August 19, 2016
INDIANAPOLIS AIRPORT AUTHORITY 2017 APPROPRIATION BUDGET ORDINANCE NO. 2-2016 BOARD APPROVED AUGUST 19, 2016 2017 Appropriation Budget Table of Contents Board Approved August 19, 2016 1 Appropriation Summary
More informationSession 6 Airport Finance 101 Funding Sources for Airports
Session 6 Airport Finance 101 Funding Sources for Airports 31 st Annual AAAE Basics of Airport Law Workshop and 2015 Legal Update November 1-3, 2015 Desk Reference Chapters 2, 19, 22 Frank J. San Martin
More informationAirport Master Plan Open House Front Range Airport February 23, 2017
Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the
More informationSTUDY WORK GROUP MEETING No. 4. July 12, 2017
STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,
More information2018 Appropriation Budget Table of Contents Board Approved August 18, 2017
INDIANAPOLIS AIRPORT AUTHORITY 2018 APPROPRIATION BUDGET ORDINANCE NO. 1-2017 BOARD APPROVED AUGUST 18, 2017 2018 Appropriation Budget Table of Contents Board Approved August 18, 2017 1 Appropriation Summary
More informationChapter Seven COST ESTIMATES AND FUNDING A. GENERAL
Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction
More informationPUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application
PUBLIC NOTICE ***************************** New Castle Airport Intention to File a Passenger Facility Charge (PFC) Application The Delaware River & Bay Authority (DRBA), the sponsor of the New Castle Airport
More information1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201
More information14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice
14 C.F.R. Part 158 Passenger Facility Charge Program Logan International Airport Public Notice Summary of Proposed 2018 PFC Application PFC Project Descriptions and Justifications PFC Financial Plan Class
More informationFORECASTING FUTURE ACTIVITY
EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver
More informationAirport Finance 101 Session 3 - Capital Funding
Airport Finance 101 Session 3 - Capital Funding Capital Development Funding Improvement Projects usually require substantial funding to be implemented In business world capital is associated with funds
More informationRegular Board Meeting August 4, 2015
Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956 PUBLIC COMMENT FY 16 Rates & Charges FY 16 Budget Approval Rates & Charges will provide the Board the ability to operate
More informationChapter 8.0 Implementation Plan
Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.
More informationPublic Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport. Effective: February 22, 2019
Public Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport Effective: February 22, 2019 Pursuant to 49 CFR Part 158.24, the city of Charlotte
More informationTable of Contents. Master Plan March 2014 TOC i Spokane International Airport
Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land
More informationTABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved
TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING
More informationInput Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot
Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot community Airport Advisory Board meetings Elected Officials
More informationNantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012
Nantucket Memorial Airport Commission Master Plan Workshop October 26, 2012 Agenda Introductions Master Plan 101 Airport Planning Issues Noise Abatement Activities Environmental Monitoring Public Outreach
More informationFunding Package TOTAL $15,172,000
Funding Package ACT 13 $3,000,000 Transportation Capital Budget $5,000,000 Redevelopment Capital Program(RACP) $3,000,000 Passenger Facility Charge (PFC) $1,500,000 Multimodal Transportation (DCED) $1,500,000
More informationPUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT
PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT Pursuant to CFR 158.24, the City and County of Denver Department of Aviation ( City ), owner and operator of the Denver International
More informationRAPID CITY REGIONAL AIRPORT
RAPID CITY REGIONAL AIRPORT Budget: $16,232,274 Full time Employees: 24 Mission Statement It is the mission of the Rapid City Regional Airport Board to provide safe, efficient, environmentally sensitive,
More informationTABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.
TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...
More informationSTUDY WORK GROUP MEETING No. 3. November 29, 2016
STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity
More informationDRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014
DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation
More informationINFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE
INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE BRIEFING ON RONALD REAGAN WASHINGTON NATIONAL AND WASHINGTON DULLES INTERNATIONAL AIRPORTS CAPITAL CONSTRUCTION PROGRAM APRIL 2015 2015 Use & Lease
More informationNotice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application
July 3, 2018 Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application The City of Kansas City (City), Missouri through its Aviation Department ( the Department
More informationCity of Tallahassee, FL Department of Aviation
City of Tallahassee, FL Department of Aviation Proposed Application to Federal Aviation Administration For Authority to Impose a Passenger Facility Charge (PFC) at Tallahassee International Airport and
More informationSection (a)(1). Description of Projects Impose and Use
November 21, 2017 Mrs. Kelly Lane SkyWest Airlines 444 South River Road St. George, UT 84790 RE: Notice of Intent to Impose and Use a New Passenger Facility Charge Bert Mooney Airport Butte, Montana Dear
More informationAIRLINE CONSULTATION MEETING
AIRLINE CONSULTATION MEETING Passenger Facility Charges Proposed Projects South Burlington, Vermont August 2012 Prepared by: 150 Dow St., Manchester, NH 03101 603-669-5555 INTRODUCTION The Burlington International
More informationPublic Notice July 14, 2017
Public Notice July 14, 2017 PROPOSED IMPLEMENTATION OF PFC 13 NOTICE TO AIR CARRIERS AND CONSULTATION MEETING Implementation of PFC On June 14, 2017 the Omaha Airport Authority provided written notice
More informationGREATER ORLANDO AVIATION AUTHORITY
GREATER ORLANDO AVIATION AUTHORITY Amendment to PFC Applications #7, 8, and 16 and New PFC Application #18 PUBLIC NOTICE June 7, 2016 1 P age Table of Contents PUBLIC NOTICE... 3 PROPOSED ACTIONS... 3
More informationSalt Lake City International Airport April 23, 2013 Budget Briefing. Page 1
Budget Briefing Fiscal Year 2014 Budget Honorable Members of the City Council April 23, 2013 Page 1 FY 2014 Budget Goals and Objectives Develop and implement a plan of execution for the terminal redevelopment
More informationPassenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico.
Passenger Facility Charge: No. 7 Application December 2013 Public Notice Materials Luis Muñoz Marín International Airport San Juan Puerto Rico INTRODUCTION Aerostar Airport Holdings has initiated the process
More informationRNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan
RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally
More informationPFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018
PFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018 Table of Contents Section Page I. Overview 2 II. Notice and Opportunity for Public Comment 3 III. Application
More information6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)
6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement
More informationPFC Quarterly Status Report September 30, 2016
PFC Quarterly Status Report September 0, 06 Public Agency: Greater Orlando Aviation Authority Use Airport: Orlando International Airport (MCO) Charge Expiration Date: $4.50 8//08 Total Collection Authority
More informationPFC Application #2 Niagara Falls International Airport
Public Notice Application #2 Falls International April 12, 2018 Agenda Program at the Falls International Notice to air carriers and consultation meeting Class of air carriers not required to collect Air
More informationPENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN
PENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN OCTOBER 2018 T A B L E O F C O N T E N T S Table of Contents Chapter 8 Financial Plan 8.1 Introduction... 8-1 8.2 Enplanement
More informationFinance and Implementation
5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter
More informationMASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4
MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis
More informationDallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting
Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting 10.27.16 Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting Agenda Welcome / Introductions DFW
More informationSECTION 7. THE AIRPORT IMPROVEMENT PROGRAM (Source: City of Dayton Department of Aviation)
SECTION 7 THE AIRPORT IMPROVEMENT PROGRAM (Source: City of Dayton Department of Aviation) The Dayton International Airport spans over 4,500 acres in both Montgomery and Miami Counties. The airport encompasses
More informationAirport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal
Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred
More informationOffice of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN
Overview of the FAA s Office of Airports Prepared for: Presented by: 2016 ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Eduardo Angeles Associate Administrator for Airports Date:
More informationBOARD OF AIRPORT COMMISSIONERS
1 8/17/2018 8/21/2018 8/16/2018 i ElY MY Y I : JH MT BY...01,, III1*.ji,"1.111Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: la Approved by: e1. "ampbell, Chief Airports
More informationNEW PFC APPLICATION #5
NEW PFC APPLICATION #5 New PFC Application #5 Public Notice Norfolk International Airport Norfolk, VA Table of Contents PFC Program at Norfolk International Airport Class of Air Carrier Not Required to
More informationState of the Airport Robert S. Bowen, Executive Director October 18, 2018
Robert S. Bowen, Executive Director October 18, 2018 A Year of Change The last year will be remembered as a period when the airlines, bolstered by a growing national economy, moderate fuel prices and changing
More informationBrief Recap of Project to Date
CITY AND BOROUGH OF SITKA Rocky Gutierrez Airport (SIT) Terminal Improvements Project Brief Recap of Project to Date Schematic Design: Design Development Meetings June 26 & 27, 2018 Project Description
More informationKittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016
Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Project Team Kittitas County, WA Airport Owner (Sponsor) and Operator, Land Use Century West
More informationPEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE REGIONAL AIRPORT
PEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE REGIONAL AIRPORT PUBLIC NOTICE FOR PASSENGER FACILITY CHARGE APPLICATION NO. 2 AUGUST 6, 2014 Prepared By: PUBLIC NOTICE PEE DEE REGIONAL AIRPORT AUTHORITY FLORENCE
More informationBlue Grass Airport (LEX) serves the needs of a multi-county area that
SUMMARY BACKGROUND This Master Plan Update balances needed airport improvements with the goals of the community and arrived at a consensus on how to best meet future demand without sacrificing those natural
More informationPublic Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport
Re: Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Los Angeles World Airports (LAWA) intends to submit
More informationCatExes vs. EAs When and How to Prepare
CatExes vs. EAs When and How to Prepare Panel: Steve Culberson, Ricondo & Associates Frank Smigelski, FAA Mary Vigilante, Synergy Tuesday December 10, 2013 Washington, DC 1 So you have a project Do I have
More informationChapter 1: Introduction Draft
Chapter 1: Draft TABLE OF CONTENTS 1... 4 1.6.1 Stakeholder Engagement Plan... 10 Chapter 1 Page 2 TABLE OF EXHIBITS Exhibit 1.1-1 ABIA Annual Growth Since 1993... 5 Exhibit 1.4-1: ABIA Location Map...
More informationChapter 1: Introduction
Chapter 1: TABLE OF CONTENTS 1... 4 1.1 Master Plan Study Content... 4 1.2 Purpose and Scope of Master Plan Study... 4 1.3 Airport History and Role... 6 1.4 Airport Location and Service Area... 6 1.5 ABIA
More informationAmended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement)
Amended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement) Briefing to the Transportation and Environment Committee Department of Aviation October 27, 2008 Purpose Review 5-Party
More informationChapter 1 Introduction and Project Overview
Chapter 1 Introduction and Project Overview Kittitas County in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Bowers Field Airport (FAA airport identifier
More informationFAA Update. Dakota-Minnesota (DMA) Airports District Office. Federal Aviation Administration. Presented to: By: Date: South Dakota Airports Conference
FAA Update Dakota-Minnesota (DMA) Airports District Office Presented to: By: Date: South Dakota Airports Conference Chris Hugunin & Dave Anderson March 18, 2015 FY 2014 DMA ADO Total AIP Funding $107.2
More informationFort Wayne International Airport Master Plan Study. Executive Summary
Fort Wayne International Airport Master Plan Study Executive Summary March 2012 Introduction Airport Background Forecast of Aviation Activity Development Plans Recommended Airfield & Access Development
More informationLos Angeles International Airport (LAX) Airside $907M
Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking
More informationChapter 2 FINDINGS & CONCLUSIONS
Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued
More informationAirports and UAS: Integrating UAS into Airport Infrastructure and Planning
ACRP Problem Statement 17-03-09 Recommended Allocation: $500,000 Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Staff Comments This is one of four UAS-themed problem statements
More informationRESOLUTION No APPROVAL OF WAYNE COUNTY AIRPORT AUTHORITY FISCAL YEAR 2018 BUDGET. By Board Member Mark Ouimet
RESOLUTION 17-87 APPROVAL OF WAYNE COUNTY AIRPORT AUTHORITY FISCAL YEAR 2018 BUDGET By Board Member Mark Ouimet WHEREAS, the Wayne County Airport Authority (the Authority ), pursuant to the Aeronautics
More informationCHAPTER 3 ALTERNATIVES CONSIDERED
CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from
More informationCHAPTER 1: INTRODUCTION
CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the
More informationPUBLIC NOTICE. Table 1 Projects Proposed by Amendment
PUBLIC NOTICE The Dallas Department of Aviation (the Department) intends to file an amendment application to increase the PFC amount of one previously approved project at Dallas Love Field Airport (the
More informationGrants Pass Airport Master Plan & Airport Layout Plan Update
Attendees: Grants Pass Airport Master Plan & Airport Layout Plan Update Meeting #3 January 26, 2010 Merlin Community Center 100 Acorn Street, Merlin 5:45 7:15 p.m. Josephine County Department of Airports:
More informationMassDOT Aeronautics Division Capital Improvements Presentation
MassDOT Aeronautics Division Capital Improvements Presentation MassDOT Board Retreat October 27, 2011 Presentation Agenda Capital Improvement Plan (CIP) Overview Airports Capital Improvement Plan (ACIP)
More informationNantucket Memorial Airport Master Plan Update
Nantucket Memorial Airport Master Plan Update CHAPTER 1 - INTRODUCTION & PUBLIC OUTREACH PROGRAM REVIEW DRAFT SUBJECT TO CHANGE Prepared for: Nantucket Memorial Airport Commission 14 Airport Road Nantucket,
More informationWestover Metropolitan Airport Master Plan Update
Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The
More informationMaster Plan Update Community Advisory Committee Kick-off Meeting
Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision
More informationFort Lauderdale Hollywood International Airport
ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County
More informationYakima Air Terminal/McAllister Field Airport Master Plan Update
Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used
More informationPrepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906
Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement
More informationAnn Arbor Municipal Airport Ann Arbor, MI Date of Latest ALP ACIP Airport Code - A Airport Identifier - ARB
MICHIGAN AIRPORT DEVELOPMENT PROGRAM AIP CAPITAL IMPROVEMENT PLAN 20102019 FEDERAL/STATE/LOCAL Ann Arbor, MI Date of Latest ALP 2008 ACIP Airport Code A Airport Identifier ARB Prepared by: MDOTAERO Sponsor:
More informationNotice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport
Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Pursuant to 14 CFR Part 158.24(a) (1) (III), the Broward County
More informationAppendix 6.1: Hazard Worksheet
Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp
More informationBURLINGTON INTERNATIONAL AIRPORT
BURLINGTON INTERNATIONAL AIRPORT VISION 2030 AIRPORT MASTER PLAN UPDATE Summary Presentation AIRPORT STAFF AND STUDY TEAM Robert McEwing, Director of Planning & Development Brad Worthen, Community Facilitator
More informationFINAL AGENCY DECISION CITY OF CHARLOTTE CHARLOTTE, NORTH CAROLINA
FINAL AGENCY DECISION CITY OF CHARLOTTE CHARLOTTE, NORTH CAROLINA Application Number 17-06-C-00-CL T to impose a passenger facility charge (PFC) at Charlotte-Douglas International Airport (CL T) for use
More informationRECOMMENDED 2013 BUDGET
RECOMMENDED 2013 BUDGET December 12, 2012 Budget Highlights Draft October 17, 2012 Aviation Operation & Maintenance (O&M) Expenses 1.5 percent overall O&M increase (including debt service) 2013 Salary
More informationCHAPTER 1 EXECUTIVE SUMMARY
CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport
More informationBNA Master Plan Update Community Advisory Committee Meeting No. 5
A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,
More informationAIRPORT COMMITTEE MEETING AGENDA September 06, :00 PM Moorhead Municipal Airport
AIRPORT COMMITTEE MEETING AGENDA September 06, 2017-4:00 PM Moorhead Municipal Airport 1. Call to Order 2. Agenda Amendments 3. Approval of Minutes A June 14, 2017 4. Citizens to be Heard 5. Airport Capital
More informationMeeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies
Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, 2017 Prepared by: File: Attendees: Shannon Eibert, C&S Companies N93.012.001 See Sign-In List A third meeting was held
More informationAirport. Improvement Program (AIP) Overview. Federal Aviation Administration. Texas Aviation Conference Ben Guttery, Texas ADO April 2017
Airport Improvement Program (AIP) Overview Texas Aviation Conference Ben Guttery, Texas ADO April 2017 Objectives Status of AIP Legislative Authority History and Summary of AIP AIP funding formulas 2 AIP
More informationAIRPORT WITH NO RUNWAYS IS A MALL
RUNWAY EXTENSION INITIATIVE AT FT. LAUDERDALE HOLLYWOOD INTERNATIONAL AIRPORT ISMAEL IZZY BONILLA DEPUTY DIRECTOR BROWARD COUNTY AVIATION AUTHORITY AIRPORT WITH NO RUNWAYS IS A MALL Runway Business Case
More informationWhat is an Airport Master Plan?
What is an Airport Master Plan? The goal of a master plan is to provide the framework needed to guide future airport development that will cost-effectively satisfy aviation demand, while considering potential
More informationChapter 9: Financial Plan Draft
Chapter 9: Draft TABLE OF CONTENTS 9... 5 9.2.1 ABIA Accounting... 6 9.2.2 Legal Environment... 6 9.2.3 Governing Documents... 8 9.3.1 FAA AIP Grants... 13 9.3.2 Local ABIA Funds... 14 9.4.1 Defer or Delay
More informationFAA Reauthorization Issues & Impacts on Airports
Issues & Impacts on Airports Presentation to Mid America Association of State Transportation Officials July 21, 2011 Presented by Greta J. Hawvermale Sr. Director of Engineering & Environmental Matters
More informationCHAPTER 7 IMPLEMENTATION PLAN
CHAPTER 7 IMPLEMENTATION PLAN INTRODUCTION An implementation plan for Blue Grass Airport (LEX) has been prepared based upon the facility needs identified in the Facility Requirements and the Alternatives
More information10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM
10.1 INTRODUCTION Based on the findings from the Facility Requirements and the combined plan recommended in the Alternative Analysis, a capital improvement program for North Perry Airport has been developed
More informationFinancial Feasibility Analysis
CHAPTER F Financial Feasibility Analysis 1. Introduction This chapter presents a funding plan for completion of recommended capital projects at Friedman Memorial Airport (the Airport) through FY 2034,