1 OFFICE OF THE CITY MANAGER September 4, 2015 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager General Information AT/ST City offices will be closed Monday, September 7 th in observance of Labor Day. Trash, green waste and recycling collection services will not be affected. Good News The ribbon cutting ceremony for the Park 20 th residences was held today. The affordable housing project, located just east of Central Park at Mill Creek, includes 55 one bedroom apartment homes and 1 on-site manager s quarters. The units will provide permanent housing for low income and homeless individuals, including 25 apartments specifically earmarked for homeless veterans. The City contributed the land and $3.25 million of redevelopment and HOME funding for the project. The new apartments are energy efficient with a balcony, dishwasher, stove, refrigerator and ceiling fans. Other amenities include an on-site community center and a full-service laundry area. Mayor Hall, along with Councilmembers Maxwell, Smith and Hanson attended today s event. Pictures of the ceremony are enclosed. Attached you will find the monthly TRIP Status Report for the month of September. The report gives a summary of each TRIP project in construction, in design, and under review. Completion percentages and pictures of projects are also included. As you are aware, the Recreation and Parks Department has taken a very proactive role in ensuring compliance with the State s drought regulations. This has included making modifications to the watering schedules and irrigation system infrastructure within the City s 59 parks and 160 miles of streetscapes. To date, the department has met or exceeded monthly water conservation targets, while simultaneously working to preserve the health of the estimated 85,000 trees the City maintains.

2 General Information September 4, 2015 Page 2 Notwithstanding the department s efforts, our staff has seen an increase in the number of dead or dying trees in parks and streetscapes. The most common trees that have been impacted include non-native and non-drought tolerant varietals, such as: Coastal Redwood, Liquidamber, Flowering Plum and White Alder. Since the beginning of the year, approximately 900 dead trees have been removed citywide. Staff has identified an additional 1,000 trees that are believed to be impacted by the drought and may need to be removed in the coming months pending further evaluation. These figures represent approximately 2.2% of the total tree population that the City maintains. Moving forward, we are evaluating different drought tolerant replacement options for the areas that have had trees removed. The process of evaluating tree conditions is ongoing, however we will not know the full extent of the drought impacts on the trees until more normal weather patterns return. The Fire Station No. 8 rehabilitation project is underway in northeast Bakersfield. The first phase includes the preparation and mobilization of temporary facilities for the crew assigned to Fire Station No. 8 to utilize when work begins on the facility later this year. The temporary facilities include a modular living quarters which was delivered to the site this week. Once the temporary site is ready, work will begin to replace outdated and deficient infrastructure at Fire Station No. 8. The fire crews will operate out of the temporary site for approximately nine months and do not anticipate any disruption to emergency services to residents in the area. Council Referrals Councilmember Maxwell o Speed Issues in the 2000 Block of Roosevelt Street

3 General Information September 4, 2015 Page 3 TRIP Reports UPDATE: Nighttime State Route 99 Lane and Ramp Closures The outside northbound lane on State Route 99, between Ming Avenue and Wilson Road, will be closed tonight between the hours of 9 p.m. and 5 a.m. to allow the contractor for the Beltway Operational Improvements Project to remove material from the construction site. This closure is in addition to tonight s closure of the southbound Ming Avenue onramp to State Route 99 and the approaching southbound outside lane on State Route 99. These closures will also occur between 9 p.m. and 5 a.m. and are needed to allow for paving on the on-ramp. The remaining lanes on State Route 99 will remain open while work is underway and all lanes, as well as the ramp, are expected to be open in time for the morning commute. Streets Division work schedule for the week of September 7 th ; and Letter from Bright House Networks regarding possible programming changes Event Notifications Event Calendar for Rabobank Arena Theater and Convention Center AT:CH:cb:al cc: Department Heads Roberta Gafford, City Clerk

4 PARK 20TH

5 September 2015 TRIP Status Report TRIP projects are moving rapidly through the various stages of project development. This report is to provide a periodic up-to-date snapshot of each project s recent major activities and progress. If you have questions, or need additional information, please contact Janet Wheeler at the TRIP office, (661) Regular project updates are also available on the TRIP website at BakersfieldFreeways.us MILESTONES The State Route 178/Morning Drive Interchange, including all on- and off-ramps, opened to traffic following a ribbon cutting event on August 18 th. Construction crews will continue working in the area for a few more weeks, completing final detail work. This work is not expected to affect traffic. The official kick-off for the State Route 178 Widening Project was also held on August 18 th, in conjunction with the State Route 178/Morning Drive Interchange ribbon cuttingevent. This project will widen State Route 178 to three lanes in each direction between Canteria Drive and Masterson Street and to two lanes in each direction between Masterson Street and Miramonte Drive. The project will also realign and improve State Route 178 intersections at State Route 184, Masterson Street, Alfred Harrell Highway, and Miramonte Drive. Concrete has been placed for the bottom of the new bridge (stems and soffit) at the State Route 99/Hosking Avenue Interchange Project. The concrete pour was also held on August 18 th and included more than 1,800 cubic yards of concrete. Another concrete pour will be scheduled in late September to complete the bridge deck. The State Route 99 Auxiliary Lane/Rosedale Highway Off-ramp Improvements Project has been advertised and bids will be opened on September 10 th. The project is estimated at $7.5 million and is funded through the State Highway Operation and Protection Program (SHOPP). Construction is expected to begin late this year. PROJECTS UNDER CONSTRUCTION State Route 178/Morning Drive Interchange Contractor: Granite Construction 99% complete; Open to traffic The new interchange project opened to traffic following a ribbon cutting ceremony on Tuesday, August 18 th. Many neighboring residents attended the ceremony to celebrate the new connection and opportunities for new development. Crews will continue working in the area for a few more weeks, completing final detail work outside the traffic lanes. State Route 99/Hosking Avenue Interchange Contractor: Granite Construction 50% complete; anticipated completion: early 2016 The contractor placed concrete for the new Hosking Avenue Bridge stems and soffit on August 18 th. The 35- member crew began work at 3 a.m. and completed the job around 4:30 p.m. This part of the bridge required two concrete pumpers and 1,800 cubic yards of concrete (more than 180 truckloads). There were no impacts to traffic. Another concrete pour is planned for late-september to complete the top deck of the bridge. Page 1

6 TRIP Status Report September 2015 In August, crews continued importing dirt for the embankment at the ramps and approaches, worked on the project s drainage systems, and placed roadway aggregate base, curb and gutter. Electrical conduit was also installed at various locations throughout the project. In September, crews will be placing conduit for utilities in the bridge bays, installing bridge deck drains and completing the forms for the top deck. Crews will continue work on the drainage systems, curb and gutter and electrical. Class II aggregate base will also be placed for the roadway. Beltway Operational Improvements Contractor: Security Paving Company 3% complete; anticipated completion: summer 2017 This project includes various improvements along State Route 58, from east of State Route 99 to Cottonwood Road, and on State Route 99 from Wilson Road to north of Ming Avenue. The contractor has cleared the work areas along State Route 99 and has begun work on a new retaining wall. This work will require intermittent lane closures through mid-october on southbound Wible Road, between Belle Terrace and Wilson Road. The closures are needed to allow the contractor to off-load materials. The contractor is also working within the median on State Route 58 at the west end of the project area. These crews are working on drainage, subgrade and existing guardrail removal. Additional temporary concrete barrier rail was placed along the State Route 58 corridor in August. In September, crews will be working on temporary on-ramp construction from Ming Avenue to southbound State Route 99. On State Route 58, crews will begin clearing operations and removing irrigation lines. Work within the median will be ongoing throughout the month. Motorists driving through this construction zone should anticipate potential construction work during daytime and nighttime hours on both State Route 58 and State Route 99. Rosedale Highway Widening Contractor: Teichert Construction 19% complete; anticipated completion: fall 2016 Currently, crews are primarily working during daytime hours and two lanes will remain open in each direction to daytime traffic as work progresses. Work continues in various locations throughout the project area. Highlights for August include work on the waterline between Wedding Lane and Mohawk Street and the start of earthwork on the south side of Rosedale Highway west of Coffee Road. This work will continue into September. Crews will also be working on the north side of Rosedale Highway, between Fruitvale Avenue and Gibson Street, making subgrade, placing aggregate base, and paving the widened roadway. Also in September, the railroad will begin relocating the crossing arms at the crossing near Gibson Street. No daytime closures are anticipated for this work, which is expected to continue into October. The contractor will be working in the southeast quadrant of Calloway Drive and Rosedale Highway beginning in mid-september. This work will take a couple of months to complete and traffic delays are expected. Motorists are encouraged to use alternate routes or allow extra time to reach their destinations while work is underway. The City has possession of all of the right-of-way necessary to construct the project; 98 ownerships have been acquired, and one is in the condemnation process. State Route 178 Widening Contractor: Granite Construction 7% complete; anticipated completion: mid-2017 A groundbreaking ceremony was held on August 18 th, in conjunction with the State Route 178/Morning Drive Interchange ribbon cutting event, officially kicking off construction on the three-mile long widening project. Page 2

7 TRIP Status Report September 2015 The contractor and construction manager s on-site office have been moved to a location just west of the State Route 178/184 intersection. Utility companies are finishing up their efforts to relocate lines along the corridor and the road widening work is expected to begin in September. The City has possession of all of the right-of-way necessary to construct the project; 26 ownerships have been acquired and three ownerships are in condemnation. State Route 99 Auxiliary Lane/Rosedale Highway Off-ramp Improvements Designer: Parsons Design 100% complete; Project is within Caltrans right-of-way; Currently advertised for construction The project provides operational and safety improvements along southbound State Route 99 and at the Rosedale Highway off-ramp. The project has been advertised and bids will be opened September 10 th. It is anticipated that the contract will go before City Council for approval on October 14 th. The project is estimated at $7.5 million and is funded through the State Highway Operation and Protection Program (SHOPP). Construction is expected to begin late this year. PROJECTS IN DESIGN AND RIGHT-OF-WAY 24th Street Improvement Project Designer: TYLin International Design 65% complete; Right-of-Way 86% complete (full acquisitions); Anticipate bidding: mid-2016 Judicial proceedings are in process that could modify the project schedule Soundwall and streetscape design are on hold Hageman Flyover Designer: Caltrans Design 40% complete; Right-of-Way 0% complete Potholing for utilities is underway Design team is coordinating with the City and County on stage construction Right-of-way acquisition will not begin until design has progressed to 95% 12 properties, subject to change as design progresses Truxtun/Oak Intersection Operational Improvements Designer: Dokken Engineering Design 55% complete; Right-of-Way 0% complete The project will widen Truxtun Avenue, to three lanes in each direction, from Empire Drive to east of Oak Street, modify the curve at the Westwind Drive intersection, and provide a right-turn deceleration lane for westbound traffic turning north onto Westwind Drive. Construction is anticipated to begin in mid- to late-2016, depending upon environmental permits and rightof-way acquisitions. Design work continues Right-of-way 4 ownerships west of Oak; waiting for plats/legals 6-10 ownerships east of Oak; waiting for design Page 3

8 TRIP Status Report September 2015 PROJECTS UNDER ENVIRONMENTAL REVIEW Centennial Corridor Caltrans lead; Environmental Consultant: Parsons Environmental process 97% complete; Right-of-Way 62% complete for full acquisitions of single-family properties The final EIR/EIS has been sent to Caltrans Headquarters and Legal for review. The document is expected to be completed and released this fall. Advanced preliminary engineering and design work is ongoing Preparing diversion plan and permit package for Kern River Bridges Geo-technical work continues as crews collect core sample from various locations along the proposed alignment, including State Route 58 and State Route 99 The type selection process is underway for bridges and structures Construction of retaining wall to accommodate utility relocation on schedule Drainage basin development for corridor is underway Right-of-Way (Early Acquisition/Voluntary Basis) Full Acquisitions required for the project: 199 single family residences, 12 multi-family properties and 36 commercial properties - Purchase agreements approved by City Council: o 124 single family properties o 3 multi-family properties o 4 commercial properties Page 4

9 TRIP Status Report September 2015 PROJECT PHOTOS Top: Officials cut the ribbon and open the State Route 178/Morning Drive Interchange. Middle left: All lanes, as well as the on- and off-ramps, are open to traffic on State Route 178 and Morning Drive. Middle right: Newly widened Morning Drive (looking south from Panorama Drive). Bottom left: Officials turn the first shovelfuls of dirt for the State Route 178 Widening Project. Bottom right: Utility companies continue relocating lines along State Route 178 in advance of the road widening. Utility relocations are nearly complete and road widening construction work is expected to be underway in September. Page 5

10 TRIP Status Report September 2015 Left (top to bottom): 1) Trucks line up to deliver concrete for the new Hosking Avenue Bridge stem and soffit pour. 2) Two concrete pumpers and a 35-member crew worked from 3 a.m. to late afternoon to th complete the concrete pour on August 18. 3) Construction crews excavate the south side of Rosedale Highway, just west of Coffee Road, as the widening work continues westward. 4) Beltway crews are working within the median on State Route 58. In the foreground, 72-inch diameter pipe is ready to be installed as part of the project s drainage system. Below: Beltway crews work on the footing for a new retaining wall along northbound State Route 99 near Ming Avenue Page 6

11

12 Page 1 of 2 STREETS DIVISION WORK SCHEDULE Week of September 7, 2015 September 11, 2015 Resurfacing/Reconstructing streets in the following areas: Sealing streets in the area south of Ming between Stine Rd & Wible Rd Reconstruction of streets in the Auto Mall area East of Wible Rd and north of Pacheco Preparing Panama Ln. between Freeway 99 and Stine Rd for a Maintenance Grind & Pave Preparing Hagen Oaks between Ming Ave and Camino Media for a Maintenance Grind & Pave Maintenance Grind & Pave on Easton Dr from California Ave east end to California Ave west end Paving various streets in the area east of Calloway and south of Brimhall Miscellaneous Streets Division projects: Video inspection of City owned Sewer & Storm lines to evaluate condition of pipes Repairing damaged sewer line found during video inspection Miscellaneous concrete repairs throughout the city Dirt work and storm line installation at Sports Village Working on Brick repairs at Centennial Plaza Grading for new parking lot at Mesa Marin Sports Complex Working on Temporary Fire Station #8 THIS SPACE INTENTIONALLY LEFT BLANK Week of September 7_2015_Work Schedule

13 Page 2 of 2 STREETS SWEEPING SCHEDULE Monday, September 7, 2015 Between So. H St. & Union Avenue Pacheco Rd. & Hosking Rd. Between Stockdale Hwy. & Truxtun Ave. (ext.) Coffee Rd & Partridge Ave. Tuesday, September 8, 2015 Between 99 Hwy. & So. H St. Ming Ave. & Panama Ln. Cul-De-Sacs on the north side of Magdelena Ave., west of So. H St. Wednesday, September 9, 2015 City areas between Brundage Ln. & Ming Ave. So. H St. & Union Ave. City areas between Wilson Rd. & Pacheco Rd. So. H St. & Union Ave. Between Casa Loma Dr. & Planz Rd. Madison Ave. & Cottonwood Dr. Between Planz Rd. & Brook St. Madison Ave. & Hale St. Thursday, September 10, 2015 Between Carr St. & California Ave. Mohawk St. & Stockdale Hwy. Between Stockdale Hwy. & Marella Wy. California Ave. & Montclair St. Between La Mirada Dr. & Chester Ln. Montclair St. & No. Stine Rd. Between California Ave. (ext.) & Stockdale Hwy. No. Stine Rd. & 99 Hwy. Between Stockdale Hwy. & Ming Ave. New Stine Rd. & Ashe Rd. Between Mountain Ridge Dr. & Ashe Rd. Taft Hwy. & Berkshire Rd. Friday, September 11, 2015 Between Ming Ave. & White Ln. Buena Vista Rd & Old River Rd. Between Stine Rd. & 99 Hwy. Ming Avenue & Adidas. Between Panama Ln. & Birkshire Rd. Gosford Rd. & Stine Rd. NOTE: If raining, there will be no street sweeping service and all street cleaning personnel will be assigned to cleaning plugged drains and part circle culverts. This also applies when a large number of street sweeper are in Fleet for repairs. Areas that have been missed during this time will be swept at the end of the month only when possible. Week of September 7_2015_Work Schedule

14

15 BOX OFFICE HOURS Mon-Fri 10 AM - 5 PM Closed Saturday & Sunday (Excluding Event Days) UPCOMING EVENTS TICKETMASTER LOCATIONS Walmart Fashion Place Walmart Colony Street Walmart Rosedale Hwy CHARGE-BY-PHONE GROUP SALES INFORMATION SEASON TICKET INFORMATION Bakersfield Condors PUCK (7825) Bakersfield Symphony Bakersfield Community Concert Association July 24 WWE Live 7:30 PM $95, $65, $50, $35, $25, $15 On Sale Now August 27 - Florida Georgia Line 7:30 PM $54.75, $34.75 On Sale Now September 10 Ringling Bros. Circus 7:00 PM $70, $38, $10 On Sale 7/31 September Ringling Bros. Circus $70, $38, $25, $20 On Sale 7/31 September 21 Kings vs Coyotes 7:00 PM $115, $65, $40, $29 On Sale Now October 16 Pepe Aguilar 8:00 PM $149, $119, $89, $49 On Sale Now September 18 - Firefall 8:00 PM $15 On Sale Now October 1 - Gary Allan 7:00 PM $57, $37, $27 On Sale Now October 2 - Hotel California 8:00 PM $15 On Sale Now July 14 Dancing With The Stars Live 8:00 PM $74, $48, $34 On Sale Now July 28 Juanes 7:30 PM $73.50, $48, $38, $28 On Sale Now August 7 Espinoza Paz 9:00 PM $125, $95, $80, $65, $50, $30 On Sale 7/14 August 12 Fifth Harmony 7:00 PM $47.50, $27.50 On Sale Now September 25 Wild Kratts Live! 7:00 PM $43.75, $37.75, $27.75 On Sale Now October 20 J Balvin with Becky G 7:30 PM $73, $47.50, $37.50, $27.50 On Sale Now -

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER August 28, 2015 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager General Information AT Good News The California High-Speed Rail Authority held a

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER December 6, 2013 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information Notable Items: On Wednesday, the ribbon was cut to signal

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER August 29, 2014 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager AT / al General Information City offices will be closed on Monday, September 1 st,

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER TO: FROM: Honorable Mayor and City Council Alan Tandy, City Manager AT September 7, 2012 SUBJECT: General Information Miscellaneous News The month of August was very busy for

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER November 26, 2014 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information City offices will be closed Thursday and Friday, November

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER February 27, 2015 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager General Information AT Good News The Bakersfield Police Department s Citizen Volunteer

More information

OFFICE OF THE CITY MANAGER MEMORANDUM August 30, 2013

OFFICE OF THE CITY MANAGER MEMORANDUM August 30, 2013 OFFICE OF THE CITY MANAGER MEMORANDUM August 30, 2013 TO: FROM: Honorable Mayor and City Council Alan Tandy, City Manager AT/ al SUBJECT: General Information In observation of Labor Day, City offices will

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER TO: FROM: SUBJECT: OFFICE OF THE CITY MANAGER Honorable Mayor and City Council Alan Tandy, City Manager ST / RS / al General Information July 5, 2013 Good News! Staff has confirmed that $7,186,399 in Prop

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER January 27, 2017 TO: FROM: SUBJECT: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information Notable Items During the storms this past weekend, Recreation

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER November 21, 2014 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information City offices will be closed next Thursday and Friday, November

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER March 27, 2015 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager General Information CH Notable Items We learned this past week that Arthur L Rockoff,

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER January 19, 2018 TO: Honorable Mayor and City Council FROM: SUBJECT: Alan Tandy, City Manager General Information AT Notable Items The City conducted its annual budget kick-off

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER TO: FROM: SUBJECT: OFFICE OF THE CITY MANAGER Honorable Mayor and City Council Alan Tandy, City Manager AT General Information May 26, 2017 Good News: City offices will be closed Monday, May 29 th, in

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER July 22, 2016 TO: FROM: SUBJECT: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information Notable Items On August 2, the Bakersfield Police Department

More information

OFFICE OF THE CITY MANAGER. AT/al

OFFICE OF THE CITY MANAGER. AT/al OFFICE OF THE CITY MANAGER February 1, 2013 TO: FROM: SUBJECT: Honorable Mayor and City Council AT/al Alan Tandy, City Manager General Information Miscellaneous News Attached is information that shows

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER March 11, 216 TO: FROM: SUBJECT: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information Notable Items We are excited to announce the opening of the

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER March 31, 2017 TO: FROM: SUBJECT: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information Notable Items Great news! We were informed this week that Pacific

More information

OFFICE OF THE CITY MANAGER MEMORANDUM

OFFICE OF THE CITY MANAGER MEMORANDUM OFFICE OF THE CITY MANAGER MEMORANDUM August 2, 2013 TO: FROM: Honorable Mayor and City Council Alan Tandy, City Manager AT /al SUBJECT: General Information Good News! The Westside Parkway was officially

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER TO: OFFICE OF THE CITY MANAGER Honorable Mayor and City Council June 9, 2017 FROM: SUBJECT: Alan Tandy, City Manager General Information AT Notable Items With 100 percent of precincts reporting, we like

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER December 28, 2018 TO: FROM: Honorable Mayor and City Council Alan Tandy, City Manager AT SUBJECT: General Information City offices will be closed on Monday, December 31 st and

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER August 25, 217 TO: Honorable Mayor and City Council FROM: SUBJECT: Alan Tandy, City Manager General Information AT Notable Items When the Thomas Roads Improvement Program (TRIP)

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER September 28, 2018 TO: FROM: Honorable Mayor and City Council Alan Tandy, City Manager AT SUBJECT: General Information Good News! Earlier this summer, the 5 th District Court

More information

OFFICE OF THE CITY MANAGER AT/CH

OFFICE OF THE CITY MANAGER AT/CH OFFICE OF THE CITY MANAGER July 28, 2017 TO: Honorable Mayor and City Council FROM: SUBJECT: Alan Tandy, City Manager General Information AT/CH Notable Items This week City staff from the Departments of

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER March 21, 2014 TO: FROM: Honorable Mayor and City Council Alan Tandy, City Manager AT/ al Subject: General Information Good News! The City of Bakersfield and the Kern County

More information

Progress Report for Projects of Regional Significance

Progress Report for Projects of Regional Significance Rosedale Highway facing west January 2017 What s Inside? Kern Council of Governments Progress Report for Projects of Regional Significance EDITION Status Information on: Safety & Maintenance...this section

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER TO: FROM: SUBJECT: OFFICE OF THE CITY MANAGER Honorable Mayor and City Council Alan Tandy, City Manager AT General Information April 21, 217 Notable Items Good news! The 18 th and Eye Street Parking Garage

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER March 15, 213 TO: FROM: SUBJECT: Honorable Mayor and City Council Alan Tandy, City Manager AT /al General Information Welcome! It is my pleasure to welcome Julie Drimakis as

More information

Progress Report for Projects of Regional Significance

Progress Report for Projects of Regional Significance SR 58 BELTWAY IMPROVEMENTS MARCH 2018 What s Inside? Kern Council of Governments Progress Report for Projects of Regional Significance OCTOBER 2018 EDITION This report is updated quarterly and posted on

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER October 14, 2016 TO: FROM: SUBJECT: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information Notable Items Good news! The City recently learned it will

More information

Long water shutdown scheduled for Tuesday, September 18

Long water shutdown scheduled for Tuesday, September 18 Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER September 23, 2016 TO: Honorable Mayor and City Council FROM: SUBJECT: Alan Tandy, City Manager General Information AT Notable Items The Centennial Corridor project required

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

PennDOT Interstate Work next week March 30-April 3:

PennDOT Interstate Work next week March 30-April 3: PennDOT Interstate Work next week March 30-April 3: Interstate 80 Interstate 81 DELAYS THIS WEEK: Exit 256 to the Schuylkill County line. Eastbound & Westbound. Bridge cleaning Monday (3/30), Tuesday (3/31)

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Second Street Improvements Project Project Update Archive

Second Street Improvements Project Project Update Archive Second Street Improvements Project Project Update Archive 12/03/18: In observance of the Holiday Moratorium, crews have paused a majority of construction activity on 2nd Street until January 2, 2019. A

More information

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012 Today s Date: Friday, September 7, 2012, #12-255 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov 530. 741.4566

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Aug. 10, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT August 12 August 18, 2018 All

More information

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell) RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)

More information

LANCASTER CORRIDOR REDEVELOPMENT ROSEDALE STREET REDESIGN PEACH STREET RAILROAD CROSSINGS

LANCASTER CORRIDOR REDEVELOPMENT ROSEDALE STREET REDESIGN PEACH STREET RAILROAD CROSSINGS LANCASTER CORRIDOR REDEVELOPMENT ROSEDALE STREET REDESIGN PEACH STREET RAILROAD CROSSINGS Presented at the SEE Development Excellence Workshop By Councilmember Wendy Davis, City of Fort Worth March 24,

More information

Weekly construction update

Weekly construction update November 4, 2011 For more information, contact: Kim A. Rudat, Regional Communications Manager Kim.Rudat@dot.wi.gov, (920) 492-5743 For US 41 Expansion Project information, contact: Kris Schuller, US 41

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

Sierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS

Sierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS Date: September 29, 2017 #17-292 District: District 3 - Marysville, www.dot.ca.gov/dist3 Amarjeet S. Benipal, District Director Contact: Liza Whitmore, liza.whitmore@dot.ca.gov Phone: Office: (530) 634-7640

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018 BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO

More information

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016 RELEASE: IMMEDIATE June 10, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program December 2012 Update I-95 New Haven Harbor Crossing Corridor Improvement Program Prepared by: Connecticut Department of Transportation District 3A 424 Chapel Street New Haven, CT 06511 Prepared for: South

More information

Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,

Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program, Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program, updates on construction to be held in this area, and how

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth) RELEASE: IMMEDIATE March 8, 2019 CONTACT: Tina.Bundy 540-907-8325 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 10 March 16, 2019 All work is scheduled weather permitting. Real-time information

More information

SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY

SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY WEEK ENDING FEBRUARY 1, 2019 SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY Contractor: Independence Excavating Inc. 1. Work Shift Day shift (M-F), with Saturday as a makeup day. 2. Traffic The new

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER TO: FROM: SUBJECT: OFFICE OF THE CITY MANAGER Honorable Mayor and City Council Alan Tandy, City Manager AT General Information April 14, 2017 Notable Items Preliminary information from the League of California

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER OFFICE OF THE CITY MANAGER December 8, 2017 TO: Honorable Mayor and City Council FROM: Alan Tandy, City Manager AT SUBJECT: General Information Notable Items The Bakersfield Fire Department has deployed

More information

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road T 1800 997 057 (free call) E enquiries@northconnex.com.au PO Box 343 Pennant Hills NSW 1715 northconnex.com.au 28 April 2017 Ref: N0075M Night work update: and westbound on ramp at Dear resident, NorthConnex

More information

AGENDA ITEM I-6 Public Works

AGENDA ITEM I-6 Public Works AGENDA ITEM I-6 Public Works STAFF REPORT City Council Meeting Date: 8/6/2018 Staff Report Number: 18-150-CC Informational Item: Update on the Willow Road and highway 101 interchange construction, upcoming

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Hospital Link Project Project Update September 2015

Hospital Link Project Project Update September 2015 Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service

More information

OFFICE OF THE CITY MANAGER

OFFICE OF THE CITY MANAGER TO: FROM: SUBJECT: OFFICE OF THE CITY MANAGER Honorable Mayor and City Council Alan Tandy, City Manager AT General Information May 19, 2017 Notable Items: This past Wednesday the State Route 178 Widening

More information

Ohio Department of Transportation Construction Update

Ohio Department of Transportation Construction Update Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

Transportation TRANSPORTATION PROJECTS

Transportation TRANSPORTATION PROJECTS Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All

More information

Hospital Link Project Project Update Winter 2018

Hospital Link Project Project Update Winter 2018 Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open

More information

Weekly East Tennessee Construction Report for May 31-June 6, 2018

Weekly East Tennessee Construction Report for May 31-June 6, 2018 Weekly East Tennessee Construction Report for May 31-June 6, 2018 Thursday, May 31, 2018 01:30pm ANDERSON COUNTY, SR 62 between Union Valley Road and SR 162: Motorists should be alert for possible lane

More information

El Dorado County / Tahoe Roadwork Schedule

El Dorado County / Tahoe Roadwork Schedule Today s Date: October 28, 2011 #11-267 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov (530) 741-4566 desk

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET Report No. 3 of the Regional Council Meeting of March 28, 2013 1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET The recommends: 1. Receipt

More information

All closures this week happen at night, including full closures of Mesa and I-10

All closures this week happen at night, including full closures of Mesa and I-10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov May 25, 2018 North Mesa Tuesday, May 29 through Thursday, May 31 9 p.m. each

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 1 Project Overview Mainline Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

MEMORANDUM VILLAGE OF NORTHBROOK

MEMORANDUM VILLAGE OF NORTHBROOK MEMORANDUM VILLAGE OF NORTHBROOK TO: Staff COPY: Village President & Board of Trustees Department Heads FROM: Richard Nahrstadt, Village Manager DATE: April 29, 2016 SUBJECT: STAFF BRIEFING WEEK OF April

More information

Caltrans District 5. District Director s Report A quarterly publication for our transportation partners. Rosales leads Program Project Management

Caltrans District 5. District Director s Report A quarterly publication for our transportation partners. Rosales leads Program Project Management District 5 Highway 1 near Big Sur in Monterey County District Director Timothy Gubbins Provide a safe, sustainable, integrated and efficient transportation system to enhance California s economy and livability.

More information

1.0 Purpose and Organization of the Community Impact Assessment Addendum

1.0 Purpose and Organization of the Community Impact Assessment Addendum Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Carie Montero, Senior Project Manager/Environmental Lead, Parsons Transportation Group Parag Mehta, Kimley Horn Date: September 24,

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane

More information

Monday, September 18, 2017 Sunday, October 1, 2017

Monday, September 18, 2017 Sunday, October 1, 2017 Monday, September 18, 2017 Sunday, October 1, 2017 CONSTRUCTION UPDATE* Hurricane Irma cleanup is complete and some landscaping repairs are underway. The project was secure and no major damages were encountered.

More information

Capital Improvement Program Fiscal Year

Capital Improvement Program Fiscal Year Capital Improvement Program Fiscal Year 2013-2014 Tustin City Council Mayor Al Murray Mayor Pro Tem Charles E. Chuck Puckett Council Members John Nielsen Rebecca Beckie Gomez Allan Bernstein CITY OF TUSTIN

More information

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

THE STATE OF GRAYSLAKE

THE STATE OF GRAYSLAKE THE STATE OF GRAYSLAKE Presented by: Mayor Rhett Taylor January 23, 2014 The State of Grayslake Economic Development Transportation Village Center Plans Economic Development Cost Savings Programs: Village

More information

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Analette Ochoa and Wana Chiu, WRECO Parag Mehta, Kimley Horn Date: November 7, 2017 Re: Santa Cruz Route 1 Tier I and Tier II HOV

More information

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017 LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20

More information

Culpeper District. Albemarle County Monthly Report. September 2012

Culpeper District. Albemarle County Monthly Report. September 2012 Culpeper District Albemarle County Monthly Report September 2012 Special Issues Bridges on Route 745, Arrowhead Valley Road The road will be closed at the Rail Road Bridge on the southern end of the road

More information

PRIORITIES COMMITTEE MEETING

PRIORITIES COMMITTEE MEETING PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony

More information