1 Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and Red Rock Drive Intersection Improvements will include adding a south bound right turn lane and a north bound left turn lane in the through lane, thus removing the slowing/stopping left and right-turning vehicles accessing Red Rock Drive from the higher speed vehicles traveling on S. Perry Park Road (DC 105). The intersection improvements will begin Sept. 4 through approximately Dec. 28 and typical work hours will be 7am to 7pm. Early utility locating and potholing work may begin later next week, as the contractor is able, which may require intermittent lane and shoulder closers. Chambers Road Widening Project (Lincoln to Mainstreet) Sunday 9/9/2018 Saturday, 9/15/2018 Contractor will be working on the east side of Chambers Road project. No lane closures scheduled. For further information, please contact Neil Sarno, Project Manager, at nsarno@douglas.co.us Concrete Pavement Repairs Lake Gulch Road between Ridge Road and State Highway 83 will intermittently be reduced to one lane for road construction. Street Paving Aster Court, Blandford Circle, Bur Oak Lane, Bur Oak Place, Citation Circle, Crocus Way, Honey Locust Court, Hillary Circle, Hyperion Way, Meadow View, Nashua Circle, Pine Forest Lane, Red Oak Way, Saratoga Road, Tamarac Court, and White Ash Place will intermittently be reduced to one lane for road construction.
2 - Countywide - Kelty Court, Kelty Trail, and Trails End will intermittently be reduced to one lane for road construction. Autumn Oaks Rd, Barn Swallow Way, Chickadee Ct, Forest View Rd, Fox Sparrow Rd, Golden Oak Pl, Golden Ridge Ct, Gopher Ct, Grand Fir Ct, Grand Fir Way, Hidden Pines Ct, Horned Owl Way, Little Meadow Ct, Morningside Way, Owl Roost Ct, Porcupine Pointe, Rambling Oak Pl, Sage Thrasher Rd, Scenic Pine Dr, Serene View Way, Shade Tree Ln, Songbird Way, Sunshine Meadow Pl, Warbler Ct, Wild Elk Pl, and Windhaven Dr will intermittently be reduced to one lane for road construction. Sunday 09/09/2018 Blakeland Drive and Riverview Parkway will intermittently be reduced to one lane for road construction. Saturday 09/15/2018 Blakeland Drive will intermittently be reduced to one lane for road construction. Meridian Boulevard Phase 1 Sunday 09/09/2018 through Saturday 09/15/2018 Meridian Boulevard between Oswego Street and Belford Avenue will be reduced to one lane in each direction for road reconstruction. Business access will remain open. Democrat Rd Drainage Improvement Project Rocky Mountain Excavating started work on improving a drainage outfall next to the shoulder of Democrat Rd within the Timbers at the Pinery on July 24 th, They will be repairing a storm sewer outfall into a drainage channel with a new concrete drop structure and additional riprap to protect against channel erosion. Work will also include new curb and gutter, seeding and mulching. Work hours will be 7am to 7 pm with anticipated completion in September 2018.
3 Parker Rd & Tomahawk Rd Drainage Improvement Project JBS Pipeline Contractors continues to work on improving storm sewers and drainage channels adjacent to shoulders at the intersection of East Parker Rd. and Tomahawk Rd. The work includes extending and adding storm sewer pipes, adding inlets and re-grading drainage channels. Work will improve drainage and roadway shoulder safety. Traffic control is currently in use intermittently, as shoulder work requires it. Work hours will be from 7am to 7pm with anticipated completion still in September of Town Center Drive from Highlands Ranch Parkway to Lucent Blvd. Monday 9/10/18 to Monday 9/17/18 Town Center Drive will be reduced to one westbound lane and two eastbound lanes from Highlands Ranch Parkway to Lucent Blvd. For further information, please contact Pete George, Project Manager at Lucent Blvd. from Town Center Drive to Park Central Ave Monday 9/10/18 to Monday 9/17/18 Lucent Blvd. will be reduced to two northbound lanes and three southbound lanes from Town Center Drive to Park Central Ave. For further information, please contact Pete George, Project Manager at C-470 Express Lanes Project* UPDATES Lane Closures this coming week UPDATED 9/6/18: - Full Freeway Closures of Eastbound & Westbound C-470 from Lucent Blvd off-ramps to Lucent Blvd on-ramps: these closures are necessary to complete the installation of an overhead pavement conveyor for expedited permanent pavement transportation. Monday, September 10 and Tuesday, September 11 from 10 p.m. to 5:30 a.m. - Westbound Full Freeway Closure E-470 to Yosemite: crews will close westbound C-470 from E-470 to Yosemite St. During these closures, northbound and southbound I-25 ramps to westbound C-470 will remain open. These closures are necessary to pave a single lane median section for the E-470 to westbound express lane bridge. Wednesday, September 5; Thursday, September 6; Sunday, September 9 through Tuesday, September 11 from 10:00 p.m. to 5:30 a.m. As well as Saturday, September 8 from 12:00 a.m. to 8:00 a.m.
4 - Southbound Lucent dedicated right turn closure to Westbound C-470: The dedicated right-hand turn from southbound Lucent Blvd onto westbound C-470 will have a full closure for paving, ramp widening construction and drainage installation - Beginning mid-august for approximately six weeks. Closure is 24/7. - Turn Lane Closure at University: The dedicated right-hand turn from southbound University Blvd onto westbound C-470 will have a full closure for paving, ramp widening construction and drainage installation. Beginning in mid-august for approximately six weeks. Closure is 24/7. Please check back for updates at the following website: Continuous Lane Closures- UPDATED 8/30/18 8 p.m. -5:30 a.m. Tuesday-Thursday Alternating right and left lane closures on east and westbound C-470; traffic pace between I-25 and Wadsworth 8:30 a.m.-3:30 p.m. Monday-Friday: Right- and left-lane closures on Erickson, Acres Green, University and Yosemite; partial ramp closures on Broadway, Lucent and University; traffic pace on east and westbound C-470; northbound I-25 to County Line off-ramp closures. 7 p.m. - 5:30 a.m. Monday-Friday: Alternating right- and left-lane closures on eastbound and westbound C-470; single-lane closures on Yosemite, Acres Green, Broadway, University and Erickson. 8 p.m. - 8 a.m. Saturday and Sunday: Alternating right- and left-lane closures on eastbound and westbound C-470. This is a CDOT project. For further information, please visit CDOT s website: Regional Transportation District (RTD) Southeast Rail Extension (SERE) Project (Light Rail Extension) As part of RTD s 2004 voter-approved FasTracks plan to extend rapid transit across the Denver metro region, construction continues for the Southeast Rail Extension project. Please check back at this Website: Southeast Rail Extension - Ongoing traffic impacts - UPDATED 9/7/18 Through summer 2018 o Trainstation Circle East at Sky Ridge Avenue is closed for the installation of the track crossing, gates, signals and associated road work. Trainstation Circle West remains open and business/residential access is maintained.
5 Please check back at this Website: Southeast Rail Extension Encourage your neighbors and co-workers to sign up for Southeast Rail Extension updates. Get More Information: Construction Information Line: (720) Website: Southeast Rail Extension OR Construction activities are weather dependent and subject to change during the design/build process. The Southeast Rail Extension Project will expand the Southeast Rail Line 2.3 miles from Lincoln Station to RidgeGate Parkway in Lone Tree. The expansion encompasses three new stations as follows: the Sky Ridge Station and Kiss-n-Ride near Sky Ridge Medical Center; a second Kiss-n-Ride at the future Lone Tree City Center Station; and a 1,300- space Park-n-Ride at the RidgeGate Parkway Station. The 2.3-mile extension includes a 5-span, 620-foot-long bridge over Lincoln Avenue; an 11- span, 1,397-foot-long bridge over I-25 and a 4-span, 506-foot-long bridge over RidgeGate Parkway.
FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016
March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related
More informationPalm Beach County Traffic Report July 13 through July 20, 2012
For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be
More informationFDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015
From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction
More informationFDOT Treasure Coast Traffic Report through
FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;
More informationFDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015
June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane
More informationApril 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014
April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures
More informationLong water shutdown scheduled for Tuesday, September 18
Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility
More informationEXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015
EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley
More informationEXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015
EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage
More informationFDOT Treasure Coast Traffic Impact Report
July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane
More informationMay 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015
May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing
More informationNovember 21, 2012 Barbara Kelleher, (954)
November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related
More informationMilestone: Bridge to Nowhere scheduled for demolition Aug 14
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Blanca Del Valle (915) 790-4341 Blanca.DelValle@txdot.gov August 12, 16 Milestone: Bridge to Nowhere scheduled for demolition Aug 14
More informationEl Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012
Today s Date: Friday, September 7, 2012, #12-255 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov 530. 741.4566
More informationBROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,
From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY
More informationAll closures this week happen at night, including full closures of Mesa and I-10
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov May 25, 2018 North Mesa Tuesday, May 29 through Thursday, May 31 9 p.m. each
More informationPalm Beach County Traffic Report August 24 through August 31, 2012
For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will
More informationMay 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015
From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015
More informationCONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018
FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT
RELEASE: IMMEDIATE Aug. 10, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT August 12 August 18, 2018 All
More informationOctober 31, 2014 Chuck McGinness, (954)
From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October
More informationExit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)
RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT
RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work
More informationRELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)
RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)
More informationPennDOT Interstate Work next week March 30-April 3:
PennDOT Interstate Work next week March 30-April 3: Interstate 80 Interstate 81 DELAYS THIS WEEK: Exit 256 to the Schuylkill County line. Eastbound & Westbound. Bridge cleaning Monday (3/30), Tuesday (3/31)
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016
RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov
More informationPRIORITIES COMMITTEE MEETING
PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation
More informationExit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)
RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information
More informationAppendix 4.1 L. No-Build Project Descriptions
Appendix 4.1 L No-Build Project Descriptions No-Build Projects New Bedford A new traffic signal system was installed and activated in early 2009 at the intersection of King s Highway and Mount Pleasant
More informationWelcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO
Welcome to the Business Owners Task Force Perry Leonard Blagg Tire and Service President/COO Safety: West Nile Virus Alyssa Tenorio NorthGate Constructors Public Information Manager West Nile Virus Carried
More informationFor Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS
TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane
More informationProgress Report for Projects of Regional Significance
Rosedale Highway facing west January 2017 What s Inside? Kern Council of Governments Progress Report for Projects of Regional Significance EDITION Status Information on: Safety & Maintenance...this section
More informationSTAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk
STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT
RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All
More informationNortheast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015
Northeast Anthony Henday Drive Edmonton Ring Road Update Strathcona Chamber of Commerce March 18, 2015 Project Background 2 Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest
More informationPublic Information Center August 12, 2010
Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General
More informationEl Dorado County / Tahoe Roadwork Schedule
Today s Date: October 28, 2011 #11-267 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov (530) 741-4566 desk
More informationGuide to. Road Construction Projects
Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or
More informationTHREE MILE PLAN TOWN OF SUPERIOR COLORADO
THREE MILE PLAN TOWN OF SUPERIOR COLORADO February 23, 2015 INTRODUCTION This document has been prepared by the Town of Superior, Colorado, to address the existing and proposed land uses within an approximate
More informationOhio Department of Transportation Construction Update
Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District
More informationSierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS
Date: September 29, 2017 #17-292 District: District 3 - Marysville, www.dot.ca.gov/dist3 Amarjeet S. Benipal, District Director Contact: Liza Whitmore, liza.whitmore@dot.ca.gov Phone: Office: (530) 634-7640
More informationFDOT Treasure Coast Traffic Impact Report
July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane
More informationSite Location and Setting
Memorandum Date: To: From: Subject: Kristy Le, Gary Black Steve Orem Santa Teresa County Park Historic Area Traffic and Parking Study Hexagon Transportation Consultants, Inc. has completed a traffic and
More informationExit 148 (Quantico) to Exit 133 (Route 17/Falmouth)
RELEASE: IMMEDIATE March 8, 2019 CONTACT: Tina.Bundy 540-907-8325 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 10 March 16, 2019 All work is scheduled weather permitting. Real-time information
More informationTRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District
RELEASE: IMMEDIATE December 21, 2017 CONTACT: Sandy Myers 540-332-9201 (office) STA17-204 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016
RELEASE: IMMEDIATE June 10, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov
More informationTRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District
RELEASE: IMMEDIATE January 11, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-007 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov
More informationI-10 will close overnight Sunday through Thursday next week. Crews continue to make progress on Sunland s new bridges and ramps.
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Rebecca Reyes (915) 790-4205 Rebecca.Reyes@txdot.gov I-10 will close overnight Sunday through Thursday next week. Crews continue to make
More informationRoute 29 Solutions Projects
Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement
More informationOFFICE OF THE CITY MANAGER
OFFICE OF THE CITY MANAGER December 6, 2013 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager AT General Information Notable Items: On Wednesday, the ribbon was cut to signal
More informationOhio Department of Transportation Traffic Advisory. District 4 Allen C. Biehl, P.E., Deputy Director S. Arlington Road.
Ohio Department of Transportation Traffic Advisory District 4 Allen C. Biehl, P.E., Deputy Director 2088 S. Arlington Road. Akron, Ohio 44306 www.transportation.ohio.gov/dist4 Friday, September 18, 2015
More informationCell: (408) Release MA June 25, 2012
VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara
More informationProgress Report for Projects of Regional Significance
SR 58 BELTWAY IMPROVEMENTS MARCH 2018 What s Inside? Kern Council of Governments Progress Report for Projects of Regional Significance OCTOBER 2018 EDITION This report is updated quarterly and posted on
More informationMEMORANDUM VILLAGE OF NORTHBROOK
MEMORANDUM VILLAGE OF NORTHBROOK TO: Staff COPY: Village President & Board of Trustees Department Heads FROM: Richard Nahrstadt, Village Manager DATE: April 29, 2016 SUBJECT: STAFF BRIEFING WEEK OF April
More informationMajor Street Minor Street Agency
Major Street Minor Street Agency Allen Allen (Home Depot) Castle Rock Bayou Gulch Rd Ponderosa HS (7008) Douglas County Bayou Gulch Rd at Ponderosa High School Douglas County Bayou Gulch Rd Fire Station
More informationRoad widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected.
PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: SEPTEMBER 12, 2012 STATUS FOR SEPTEMBER 17, 2012 THROUGH SEPTEMBER 23, 2012 *** CONSTRUCTION WORK ZONES ADDED
More informationFlorida Department of Transportation MIKE DEW SECRETARY
RICK SCOTT GOVERNOR Florida Department of Transportation MIKE DEW SECRETARY July 5, 2018 JoAnn May, 239-225-1900 JoAnn.May@dot.state.fl.us DISTRICT ONE NORTHERN COUNTIES ROADWATCH REPORT #27 FOR WEEK OF
More information3529 Souris River Flood Plan (Phase MI-1)
Date: September 28, 2018 To: Derek Hackett, Public Information Officer From: Grant Goldader, Civil Engineering Specialist Re: Traffic Control Report for the week of 10/01/2018 3529 Souris River Flood Plan
More informationPROGRESS PARK CONNECTOR
PROGRESS PARK CONNECTOR Project No. 9999 098 R65, P102 ALTERNATIVES ANALYSIS 6 April 2015 Revised for updated dates PROGRESS PARK CONNECTOR ROAD ALTERNATIVES ALTERNATIVE # 1 West from the intersection
More informationTRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District
RELEASE: IMMEDIATE March 2, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-042 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov
More informationTRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District
RELEASE: IMMEDIATE March 23, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 057 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov A daytime lane closure on Mesa all week is needed to complete Sunday s demo
More informationImportant Lane Closures, April 3 9, 2011
March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route
More informationRoute 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.
EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in
More informationWEEKLY HIGHWAY ALERT RICHMOND DISTRICT
CONTACT: VDOT Customer Service 1-800-367-7623 November 18, Richmondinfo@VDOT.virginia.gov WEEKLY HIGHWAY ALERT RICHMOND DISTRICT COLONIAL HEIGHTS Below is a forecast of road construction that is expected
More informationConstructor: Joseph B. Fay
1 1 2 OWNER: PENNDOT Engineering District 11-0 City of Pittsburgh Design Consultant: SAI Consulting Engineers KTA-Tator Constructor: Joseph B. Fay Construction Manager: Michael Baker Construction Inspection:
More informationFOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY
TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces
More informationConstruction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County
Construction Update Contact: The District Two Public Information Office at (419) 373-4428 or email D02.PIO@dot.ohio.gov For Immediate Release Thursday, October 18, 2018 ODOT District Two Construction Update
More informationCommercial Sales by Subdivision
Commercial Sales by Subdivision 2017 Commercial Reappraisal Study Period: July 1, 2014 - June 30, 2016 Subdivision Filing Address 18 WILCOX 0 18 WILCOX ST R0460107 Office Building O1100 20912 Good 2005
More informationImportant Lane Closures March 1 5, 2010
February 26, 2010 CONTACT: Marcia McAllister 703 572 0506 marcia.mcallister@dullesmetro.com Important Lane Closures March 1 5, 2010 C aisson Load Test Scheduled for Mar. 3 Crews will perform another load
More informationSeptember 1, 2017 I-10 night closures scheduled for September hour full closure of I-10 West happens Sunday, Sept. 10
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Rebecca Reyes (915) 790-4205 Rebecca.Reyes@txdot.gov September 1, 2017 I-10 night closures scheduled for September 5-7. 27-hour full
More informationRELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)
RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,
More informationSpringettsbury Township. Road Improvement Projects
Springettsbury Township Road Improvement Projects 2009 2016 2016 Township Road Improvement Projects Springettsbury Township is divided into the following 4 Sectors: Northwest Sector Sherman Street Route
More informationI-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour
More information35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS
35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration
More informationMay 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014
May 16, 2014 Chuck McGinness, (954) 777-4090 chuck.mcginness@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 FORT LAUDERDALE -- Construction and maintenance-related lane
More informationRoad Commission for Oakland County 2016 Road and Permit Projects (6/29/16 Update) Community or Communities
**11 Mile culvert over the Blackwood Drain East of Milford **12 Mile Inkster and Southfield and Northwestern Hwy Farmington Hills **Adams bridge over Clinton River **Airport **Conklin **Greenfield (northbound
More informationHospital Link Project Project Update Winter 2018
Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open
More informationCONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND
BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK
More informationOcean Way at U.S. #1 (Town of Jupiter) Installation of a new traffic signal.
PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: FEBRUARY 13, 2013 STATUS FOR FEBRUARY 18, 2013 THROUGH FEBRUARY 24, 2013 *** CONSTRUCTION WORK ZONES ADDED
More informationWeekly East Tennessee Construction Report for May 31-June 6, 2018
Weekly East Tennessee Construction Report for May 31-June 6, 2018 Thursday, May 31, 2018 01:30pm ANDERSON COUNTY, SR 62 between Union Valley Road and SR 162: Motorists should be alert for possible lane
More informationWeekly construction update
November 4, 2011 For more information, contact: Kim A. Rudat, Regional Communications Manager Kim.Rudat@dot.wi.gov, (920) 492-5743 For US 41 Expansion Project information, contact: Kris Schuller, US 41
More informationElected Officials Briefing
Elected Officials Briefing North Metro Rail Line February 12, 2015 1 Welcome and Introductions 2 Rick Clarke RTD Assistant General Manager Capital Programs 3 The RTD FasTracks Plan 122 miles of new light
More information* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties
New York State Department of Transportation 2008 Highway/Bridge Construction Projects * Short term resurfacing projects are not included in this listing. Genesee 4T39.07 Project: Annual Rural County Sign
More informationSAN RAFAEL City Council January 20, 2015
SONOMA MARIN AREA RAIL TRANSIT SMART CENTRAL SAN RAFAEL STATUS UPDATE SAN RAFAEL City Council January 20, 2015 CENTRAL SAN RAFAEL SMART SOUTH OF PUERTO SUELLO TUNNEL 1. Active Construction 2. Construction
More informationCity of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting
City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting Wednesday, May 31, 2017 6:30 to 8 P.M. Frank Allis Elementary School 4201 Buckeye Road Madison,
More informationState Project Reconstruction I-84
State Project 151-273 Reconstruction I-84 Waterbury, Connecticut FROM WASHINGTON STREET TO PIERPONT ROAD I-84 Constructors J.V. Robert Turner Area Engineer Ken Fargnoli District Engineer John Dunham Assistant
More informationFORT WORTH DISTRICT. Springtown Area Projects. Loyl C. Bussell, P.E. Acting District Engineer. Thursday, February 8, 2018 Date.
FORT WORTH DISTRICT Springtown Area Projects Loyl C. Bussell, P.E. Acting District Engineer Photo by Liam Frederick Footer Text Thursday, February 8, 2018 Date Maintaining a Safe System TxDOT is responsible
More informationTRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District
RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov
More informationFOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, SALEM 69
FOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, 540-387-5238 SALEM 69 Jen.Ward@vdot.virginia.gov - The following is a list of forecasted highway projects that may impact traffic traveling
More informationCITY OF PALMDALE. REPORT to the Mayor and Members of the City Council from the City Manager
.. CITY OF PALMDALE REPORT to the Mayor and Members of the City Council from the City Manager DATE: SUBJECT: June 1, 2016 Approval of City of Palmdale's 2016 Ten-Year Capital Improvement Plan ISSUING DEPARTMENT:
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov August 31, 18 No closures scheduled for Labor Day weekend. Traffic lane patterns
More informationSECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY
WEEK ENDING FEBRUARY 1, 2019 SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY Contractor: Independence Excavating Inc. 1. Work Shift Day shift (M-F), with Saturday as a makeup day. 2. Traffic The new
More informationNight work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road
T 1800 997 057 (free call) E enquiries@northconnex.com.au PO Box 343 Pennant Hills NSW 1715 northconnex.com.au 28 April 2017 Ref: N0075M Night work update: and westbound on ramp at Dear resident, NorthConnex
More informationOFFICE OF THE CITY MANAGER
OFFICE OF THE CITY MANAGER August 28, 2015 TO: FROM: Subject: Honorable Mayor and City Council Alan Tandy, City Manager General Information AT Good News The California High-Speed Rail Authority held a
More informationPennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects
PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects Pittsburgh - PennDOT is pleased to announce the 2016 Allegheny County transportation improvement project list for state-owned
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov March 31, 2017 This Sunday, I 10 East traffic lanes will switch onto new lanes.
More informationTRAFFIC ALERT FOR JUNE 4-8, 2018 Highway Work Zones in the Staunton District
RELEASE: IMMEDIATE June 1, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 090 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov