1 State Project Reconstruction I-84 Waterbury, Connecticut FROM WASHINGTON STREET TO PIERPONT ROAD

2 I-84 Constructors J.V. Robert Turner Area Engineer Ken Fargnoli District Engineer John Dunham Assistant District Engineer Richard Symonds Transportation Supervising Engineer Christopher Zukowski Project Engineer Christopher Hylas Resident Engineer Phil Karsen Project Executive Steve Francois Project Manager Mike Lloyd Gen l Superintendent Tom Whelahan Engineering Manager Project Team

3 Washington Street Hamilton Ave. Interchange Pierpont Road Harpers Ferry Rd. Interchange Scott Rd. Interchange Project Location

4 Widening of approximately 2.7 miles of I-84 to provide a continuous third land in each direction Replacement/construction of 9 bridges, 6 culverts and 20 retaining walls Realignment of the highway in the vicinity of Harpers Ferry Road to remove the existing sharp reverse curvature that results in safety and operational deficiencies Project Summary

5 A new Westbound On-Ramp from Harpers Ferry Road with an auxiliary lane to WB Off-Ramp to Hamilton Avenue Extension of Plank Road East from Scott Road to Harpers Ferry Road Project Summary (cont.)

6 Elimination of the short weave section between the WB On- Ramp from Scott Road and the WB Off-Ramp to Harpers Ferry Road Elimination of the short weave section between the EB On- Ramp from Hamilton Avenue and the EB Off-Ramp to Harpers Ferry Road Relocation of the WB Off-Ramp to Scott Road and Beaver Pond Brook Project Summary (cont.)

7 The reconstruction of State and local roads associated with the realignment of I-84 and reconfiguration of the interchanges: Hamilton Avenue (State) Harpers Ferry Road Scott Road Plank Road Reidville Drive Plank Road East East Main Street (State) Project Summary (cont.)

8 Traffic Signal replacement and upgrades Highway Illumination New signs and pavement markings Replacement/relocation of sanitary sewer, potable water and other public utilities Project Summary (cont.)

9 The realignment and stabilization of the Mad River channel from south of the existing EB 24 Off-Ramp to Harpers Ferry Road to north of Plank Road to accommodate roadway widening and realignments and new bridge crossings The realignment of Beaver Pond Brook channel in the Scott Road area to revise the alignment of the WB 25 Off-Ramp necessary to realize traffic safety and operational improvements at this interchange Project Summary (cont.)

10 Relocation of East Mountain Brook at is confluence with Beaver Pond Brook to accommodate the I-84 relocation and widening and Reidville Drive relocation Re-establishment of a Perennial Stream in the Mountain Village Road area Extensive in-stream habitat enhancements associated with the watercourse relocations Project Summary (cont.)

11 Maintenance and Protection of Traffic There are 5 major construction stages proposed Two lanes of traffic will be open at all times during peak hours on a reduced roadway width (Two 11-foot lanes with 2-foot shoulders in each direction) Intermittent lane closures are anticipated for activities that require lifting operations (i.e. steel removal and installation, overhead sign truss installation, etc )

12 Permits CT DEPT. OF ENERGY AND ENVIRONMENTAL PROTECTION Wetlands and Watercourses Individual Permit 401 Water Quality Certificate Individual Permit Flood Management Certification for all regulated floodplain crossings FEDERAL US Army Corps of Engineers (ACOE) Section 404 Individual Permit STATE Stormwater and Dewatering Wastewater from Construction Activities General Permit

13 Anticipated Construction Schedule & Cost Start of Construction- March 30, 2015 Contract Completion- June 25, 2020 (Incentives in Place for substantial completion by August 2019) Project budget including construction contingencies and utility work is $298 million, not counting the costs to inspect and administer the work.

14 Noise Barrier Walls

15

16

17

18

19

20 Maintenance and Protection of Traffic Detours during Construction EB 23 On-Ramp From Hamilton Avenue WB 23 Off-Ramp to Hamilton Avenue WB 24 Off-Ramp to Harpers Ferry Road Plank Road

21 9 Month Closure: 2017 Incentive in place for early completion I-84 Eastbound Exit 23 On-Ramp Closed Follow Detour to I-84 Eastbound entry Ramp on Scott Road via Hamilton Avenue, Harpers Ferry Road and Reidville Drive. 23E Detour - EB23 On Ramp from Hamilton Avenue

22 Permanent Closure: Incentive to open Plank Road East early I-84 Westbound Exit 24 Off-Ramp Closed Follow Detour to Harpers Ferry Road via Westbound Exit 25 Scott Road and Reidville Drive. 25W 24W Detour - WB24 Off Ramp to Harpers Ferry Road

23 Weekend Ramp Closure: Summer W I-84 Westbound Exit 23 Off-Ramp Closed Follow Detour via Westbound Exit 22 and Union Avenue. 23W Detour - WB23 Off Ramp to Hamilton Avenue

24 Plank Road Extended Closure: Spring Fall 2016 Brookdale Lane Access from Plank Road Permanently Closed - Spring 2015 Brookdale Lane from Sycamore Lane to Plank Road Permanently Closed Follow Detour via White Oak Lane to Brookdale Lane to East Main Street. Plank Road Closed from Harpers Ferry Road to White Oak Lane Follow Detour via White Oak Lane to Brookdale Lane to East Main Street. Detour Plank Road

25 Work Locations Spring-Summer 2015 Hamilton Avenue Area Harpers Ferry Road Area I-84 at Plank Road East On Ramp

26 Hamilton Avenue Area

27 Harpers Ferry Road Area

28 I-84 at Plank Road East on Ramp Road

29 Public Outreach During Construction Public Information meetings will be held to inform the public of progress during construction or when there is a major change in the Maintenance and Protection of Traffic pattern. There is a sign up sheet in the lobby for those who wish to be updated vie on the status of the project throughout construction

30 Public Outreach During Construction (cont.) PROJECT WEBSITE PROJECT FACEBOOK PAGE

31 THIS CONCLUDES THE PRESENTATION REPRESENTATIVES WILL BE AVAILABLE IN THE LOBBY TO ANSWER ANY QUESTIONS OR CONCERNS WITH REGARDS TO THIS PROJECT. WE THANK YOU FOR YOUR TIME. STATE PROJECT RECONSTRUCTION OF I-84 WATERBURY, CONNECTICUT

FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A

FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A VIRGINIA DEPARTMENT OF TRANSPORTATION I-85 / I-95 INTERCHANGE FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A Columbia Rd REFINED CONCEPT 1 PROJECT A Bellevue Rd COST: $3.3M Siege Rd Eliminate the loop ramp

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

I-270 Bridge Renovation at New Florissant Road

I-270 Bridge Renovation at New Florissant Road I-270 Bridge Renovation at New Florissant Road What is the problem? The I-270 bridge over New Florissant Road in north St. Louis County is more than 50 years old. It is classified as structurally deficient

More information

Public Information Center August 12, 2010

Public Information Center August 12, 2010 Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General

More information

Fairfax County Parkway Widening Fairfax County

Fairfax County Parkway Widening Fairfax County Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

Arlington County Board Work Session Eastbound Widening January 17, Amanda Baxter, VDOT Special Projects Development Manager

Arlington County Board Work Session Eastbound Widening January 17, Amanda Baxter, VDOT Special Projects Development Manager Arlington County Board Work Session Eastbound Widening January 17, 2017 Amanda Baxter, VDOT Special Projects Development Manager Program Area Map 2 Program Scope Tolling during weekdays, peak hours, peak

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

PRIORITIES COMMITTEE MEETING

PRIORITIES COMMITTEE MEETING PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony

More information

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program December 2012 Update I-95 New Haven Harbor Crossing Corridor Improvement Program Prepared by: Connecticut Department of Transportation District 3A 424 Chapel Street New Haven, CT 06511 Prepared for: South

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

Fairfax County Transportation Advisory Commission (TAC)

Fairfax County Transportation Advisory Commission (TAC) Fairfax County Transportation Advisory Commission (TAC) January 17, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Amanda Baxter, Special Projects Development Manager

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

Hospital Link Project Project Update Winter 2018

Hospital Link Project Project Update Winter 2018 Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open

More information

* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties

* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties New York State Department of Transportation 2008 Highway/Bridge Construction Projects * Short term resurfacing projects are not included in this listing. Genesee 4T39.07 Project: Annual Rural County Sign

More information

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

2 Construction Program

2 Construction Program 2018 C P 2018 Districtonstruction 2 Construction Program rogram district 2 Governor John Kasich ODOT Director Jerry Wray District Deputy Director Pat McColley, PE, SI 2018 Construction Program Thank you

More information

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 7, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 187 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects Pittsburgh - PennDOT is pleased to announce the 2016 Allegheny County transportation improvement project list for state-owned

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30 July 20, 2018 Media Contact: Keith Bilbrey Public Involvement Manager The Southern Gateway Project kbilbrey@kstrategies.com 972-989-9995 Full I-35E Mainlane Closure at Beckley Avenue - July 27-30 DALLAS

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016 RELEASE: IMMEDIATE June 10, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth) RELEASE: IMMEDIATE March 8, 2019 CONTACT: Tina.Bundy 540-907-8325 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 10 March 16, 2019 All work is scheduled weather permitting. Real-time information

More information

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE January 11, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-007 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Add-A-Lane Contract V. along a Section of I-95 includes 6 Bridges

Add-A-Lane Contract V. along a Section of I-95 includes 6 Bridges Newton Needham Chamber of Commerce Add-A-Lane Contract V along a Section of I-95 includes 6 Bridges Project File No. 603711 July 29, 2014 1 Agenda Project Update Overview Bid and Contract Award Schedule

More information

PROGRESS PARK CONNECTOR

PROGRESS PARK CONNECTOR PROGRESS PARK CONNECTOR Project No. 9999 098 R65, P102 ALTERNATIVES ANALYSIS 6 April 2015 Revised for updated dates PROGRESS PARK CONNECTOR ROAD ALTERNATIVES ALTERNATIVE # 1 West from the intersection

More information

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016 Route 141 and I-44 Design-Build Project Community Involvement Group March 21, 2016 Purpose of CIG 1. Share information with major stakeholders 2. Keep stakeholders informed of the process 3. Reduce uncertainty

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

NDG-Westmount Neighbourhood Committee. November 16, 2015

NDG-Westmount Neighbourhood Committee. November 16, 2015 NDG-Westmount Neighbourhood Committee November 16, 2015 2 Feedback on previous questions Order-in-Council 890-2010 - condition 8 The ministère des Transports must : Establish a buffer zone at the foot

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Analette Ochoa and Wana Chiu, WRECO Parag Mehta, Kimley Horn Date: November 7, 2017 Re: Santa Cruz Route 1 Tier I and Tier II HOV

More information

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015 From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015

More information

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness, From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

Design Meeting Presentation

Design Meeting Presentation Contract No. 17ECS-TI-05SP April November 2017 Design Meeting Presentation November 2015 Agenda Items: Introduction (5 min) Overview (10 min) Scope of work (60 min): Schedule and Traffic Staging / Closures

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

NDG/Westmount Neighbourhood Committee. May 16, 2016

NDG/Westmount Neighbourhood Committee. May 16, 2016 NDG/Westmount Neighbourhood Committee May 16, 2016 2 Presentation Outline Feedback on previous questions What s new on the Turcot website Public consultations online Reconstruction of Saint-Jacques overpass

More information

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

I-66 Inside the Beltway Feasibility Study

I-66 Inside the Beltway Feasibility Study I-66 Inside the Beltway Feasibility Study Feasibility Study Study Process Context Sensitive Dialogues Corridor Assessments / Data Collection Problem Statement Refinement Concept Development Concept Evaluation

More information

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 1, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 020 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018 FREDERICKSBURG DISTRICT District Engineer Marcie Parker, P.E. May 8, 2018 3 Interstate 95 Projects Fredericksburg Area Fredericksburg region will see greatest degree of I-95 construction since widening

More information

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Project Location MP A44.5 MP A38 PRELIMINARY. A A57 (Future Project) A42 - A44.5 (Fall Fall 2019) A38 - A42. A31 - A38 - In Design

Project Location MP A44.5 MP A38 PRELIMINARY. A A57 (Future Project) A42 - A44.5 (Fall Fall 2019) A38 - A42. A31 - A38 - In Design RECONSTRUCTION AND WIDENING PROJECT Project Location A44.5 - A57 (Future Project) MP A44.5 Steinsburg Road (Fall 2015 - Fall 2016) John Fries Highway (Fall 2017 - Fall 2019) A42 - A44.5 (Fall 2017 - Fall

More information

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2)

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2) Atlantic Street Bridge Project CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro North RR Bridge Replacement Track & Station Infrastructure Improvements City of Stamford

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 2, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-042 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road T 1800 997 057 (free call) E enquiries@northconnex.com.au PO Box 343 Pennant Hills NSW 1715 northconnex.com.au 28 April 2017 Ref: N0075M Night work update: and westbound on ramp at Dear resident, NorthConnex

More information

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County Construction Update Contact: The District Two Public Information Office at (419) 373-4428 or email D02.PIO@dot.ohio.gov For Immediate Release Thursday, October 18, 2018 ODOT District Two Construction Update

More information

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

Milestone: Bridge to Nowhere scheduled for demolition Aug 14 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Blanca Del Valle (915) 790-4341 Blanca.DelValle@txdot.gov August 12, 16 Milestone: Bridge to Nowhere scheduled for demolition Aug 14

More information

Sierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS

Sierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS Date: September 29, 2017 #17-292 District: District 3 - Marysville, www.dot.ca.gov/dist3 Amarjeet S. Benipal, District Director Contact: Liza Whitmore, liza.whitmore@dot.ca.gov Phone: Office: (530) 634-7640

More information

DISTRICT CONSTRUCTION PROGRAM PROGRAM DISTRICT CONSTRUCTION

DISTRICT CONSTRUCTION PROGRAM PROGRAM DISTRICT CONSTRUCTION ODOT ODOT DISTRICT 7 2018 CONSTRUCTION DISTRICT 7 PROGRAM 2018 CONSTRUCTION PROGRAM SERVING AUGLAIZE, CHAMPAIGN, CLARK, DARKE, LOGAN, MERCER, MIAMI, MONTGOMERY & SHELBY COUNTIES JOHN R. KASICH, OHIO GOVERNOR

More information

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell) RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)

More information

1.0 Purpose and Organization of the Community Impact Assessment Addendum

1.0 Purpose and Organization of the Community Impact Assessment Addendum Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Carie Montero, Senior Project Manager/Environmental Lead, Parsons Transportation Group Parag Mehta, Kimley Horn Date: September 24,

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov August 31, 18 No closures scheduled for Labor Day weekend. Traffic lane patterns

More information

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 23, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 057 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Pre-Construction Public Meeting July 2017

Pre-Construction Public Meeting July 2017 Pre-Construction Public Meeting July 2017 Agenda Introduction to Project Team Project Description Schedule Impacts Communication/Public Outreach 2 Contractor Walsh Construction Design Team HDR Lead City

More information

October 31, 2014 Chuck McGinness, (954)

October 31, 2014 Chuck McGinness, (954) From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October

More information

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015 Northeast Anthony Henday Drive Edmonton Ring Road Update Strathcona Chamber of Commerce March 18, 2015 Project Background 2 Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2) Atlantic Street Bridge Project Update CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement Track & Station Infrastructure Improvements City

More information

Ohio Department of Transportation Construction Update

Ohio Department of Transportation Construction Update Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District

More information

APPENDIX F List of Commitments

APPENDIX F List of Commitments APPENDIX F List of Commitments s Table F.1 Standard Mitigation Measures Mitigation Measure MnDOT Specification Number Status Update Description Status Update Utilities Provide early notice to utility operators

More information

Weekly construction update

Weekly construction update November 4, 2011 For more information, contact: Kim A. Rudat, Regional Communications Manager Kim.Rudat@dot.wi.gov, (920) 492-5743 For US 41 Expansion Project information, contact: Kris Schuller, US 41

More information

El Dorado County / Tahoe Roadwork Schedule

El Dorado County / Tahoe Roadwork Schedule Today s Date: October 28, 2011 #11-267 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov (530) 741-4566 desk

More information

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 21, 2017 CONTACT: Sandy Myers 540-332-9201 (office) STA17-204 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Carlisle Connectivity Projects Communication Plan and Project Status

Carlisle Connectivity Projects Communication Plan and Project Status Carlisle Connectivity Projects Communication Plan and Project Status Overview Communication Plan Communication Plan Communication Plan Objective The Borough staff will develop and execute timely and effective

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation

More information

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012 Today s Date: Friday, September 7, 2012, #12-255 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov 530. 741.4566

More information

Constructor: Joseph B. Fay

Constructor: Joseph B. Fay 1 1 2 OWNER: PENNDOT Engineering District 11-0 City of Pittsburgh Design Consultant: SAI Consulting Engineers KTA-Tator Constructor: Joseph B. Fay Construction Manager: Michael Baker Construction Inspection:

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

A VISION FOR I-95. January 12, Delaware Department of Transportation

A VISION FOR I-95. January 12, Delaware Department of Transportation A VISION FOR I-95 January 12, 2011 Delaware Department of Transportation The East Coast s Main Street Along with SR 1, the most significant highway in Delaware 29 miles to I ".', 2 Sponsoring / Cooperating

More information

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 10/11/2018 5:24:09 PM

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 10/11/2018 5:24:09 PM OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS Incidents/: 10/11/2018 5:24:09 PM ROUTE Hwy100 15 22 7 Mi W of Ainsworth St Park Closure Information Westbound (Right

More information

Flood History. Floodplain Descriptions

Flood History. Floodplain Descriptions Flood History The worst flooding in the area took place in 1966, 1969, 1971, 1995 and 1998. The storms in 1966 and 1969 caused considerable damage throughout the area due to flooding, erosion and debris

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane

More information

City of Grand Island Tuesday, December 12, 2017 Council Session

City of Grand Island Tuesday, December 12, 2017 Council Session City of Grand Island Tuesday, December 12, 2017 Council Session Item E-3 Public Hearing on One & Six Year Street Improvement Plan Council action will take place under Resolution item I-1. Staff Contact:

More information

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 May 16, 2014 Chuck McGinness, (954) 777-4090 chuck.mcginness@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 FORT LAUDERDALE -- Construction and maintenance-related lane

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All

More information

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE

More information

City of Olathe, Kansas Capital Improvement Plan Projects 2016 thru 2020

City of Olathe, Kansas Capital Improvement Plan Projects 2016 thru 2020 Capital Improvement Plan Projects ECONOMIC VIABILITY PROJECTS 2016 2017 2018 2019 Page Coffee Creek Regional Detention 20905B 1,688,005 - - - - 1,688,005 31 Hedge Lane Relocation - Olathe Schools 3-B-080-13

More information

I-94 at Grand Avenue Interchange: The Ride before the Roller Coaster

I-94 at Grand Avenue Interchange: The Ride before the Roller Coaster I-94 at Grand Avenue Interchange: The Ride before the Roller Coaster Introduction Presenters Lanyea Griffin, Executive Project Engineer, Illinois Tollway Rob Deming, Project Manager, Primera Engineers,

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

Road Commission for Oakland County 2016 Road and Permit Projects (6/29/16 Update) Community or Communities

Road Commission for Oakland County 2016 Road and Permit Projects (6/29/16 Update) Community or Communities **11 Mile culvert over the Blackwood Drain East of Milford **12 Mile Inkster and Southfield and Northwestern Hwy Farmington Hills **Adams bridge over Clinton River **Airport **Conklin **Greenfield (northbound

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,

Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program, Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program, updates on construction to be held in this area, and how

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Aug. 10, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT August 12 August 18, 2018 All

More information

Damen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501

Damen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501 Damen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501 Bird s Eye View of Existing INTRODUCTION This project is part of the City s Building a New Chicago initiative in conjunction

More information

Transportation Supporting Dulles Airport

Transportation Supporting Dulles Airport Transportation Supporting Dulles Airport Committee for Dulles Economic Development and Transportation Committee July 12, 2018 Tom Biesiadny, Director Fairfax County Multiple Transportation Improvements

More information

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April New M5 Work notification 4 April 2018 Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April A significant amount

More information

I-95 WIDENING INCLUDING THE INTERCHANGES AT I-4 AND US 92 DESIGN-BUILD

I-95 WIDENING INCLUDING THE INTERCHANGES AT I-4 AND US 92 DESIGN-BUILD Florida Department of TRANSPORTATION I-95 WIDENING INCLUDING THE INTERCHANGES AT I-4 AND US 92 DESIGN-BUILD From North of State Road (SR) 44 to North of US 92 (International Speedway Boulevard) Volusia

More information

Hospital Link Project Project Update September 2015

Hospital Link Project Project Update September 2015 Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service

More information