1 PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: SEPTEMBER 12, 2012 STATUS FOR SEPTEMBER 17, 2012 THROUGH SEPTEMBER 23, 2012 *** CONSTRUCTION WORK ZONES ADDED OR CHANGED *** *** SINCE LAST REPORT *** 1. LOCATION: West Atlantic Ave. from Lyons Rd. to Starkey Rd. (west of the City of Delray Beach) Road widening from 2 lanes to 4 lanes. The east-west traffic has been switched to the new westbound lanes on September 5, The new alignment of Lyons Road is now open. 2. LOCATION: Caroline Ave. at Belvedere Rd. West of the Town of Haverhill) Bridge removal and piping of the canal. Lane closures are not expected. 1

2 3. LOCATION: Hypoluxo Rd. at I-95 northbound on ramp. (Town of Lantana) Ramp widening. Ramp closures will occur at night between 10:00 PM and 6:00 AM on September 16, 2012, through September 23, Traffic will detour via: Hypoluxo Rd., Congress Ave. and Lantana Rd. *** UNCHANGED CONSTRUCTION WORK ZONES *** 4. LOCATION: Old Dixie Hwy. at Hidden Valley Blvd. (City of Boca Raton) Road widening to expand the intersection. There will be lane closures for pavement marking and reflective pavement markers. 5. LOCATION: Sims Road at West Atlantic Blvd. (west of the City of Delray Beach) Underground utility work. Sims Rd. will be closed to all traffic at 6:00 AM on September 17, 2012, and will remain closed until 6:00 PM on September 19, Traffic will be detoured via: Lake Ida Rd., El Clair Ranch Rd. and West Atlantic Blvd. 2

3 6. LOCATION: Northlake Blvd. west of SR 710/Bee Line Hwy. (City of West Palm Beach) Construction of 2 bridges The east bound vehicle and pedestrian traffic has been shifted to the new bridge. Westbound will remain in the present location. 7. LOCATION: Australian Ave. between 7 th St. and north of Banyan Blvd. (City of West Palm Beach) Permit for the City of West Palm Beach to install pumps, dredging and piping. The right southbound lane and the left northbound lanes are closed through September. 8. LOCATION: SR 7 at the C-51 Canal (Village of Royal Palm Beach) Bridge widening and roadwork. Lane closures may occur but only between the hours of 8:00 PM to 6:00 AM. 9. LOCATION: 10 th Ave. North at the Keller Canal between Florida Mango Rd. and Boutwell Rd. (west of the City of Lake Worth) Installation of 2 pedestrian bridges and minor bridge widening. There will not be any daytime lane closures. The only lane closures allowed will be from 9:00 PM to 6:00 AM. 3

4 10. LOCATION: RESTRICTION: Blue Heron Blvd. at Congress Ave. (City of Riviera Beach) Intersection improvements. There will be intermittent lane closures on Blue Heron Blvd. Monday through Friday. 11. LOCATION: Seminole Pratt Whitney Rd. from S.R. 80 to Sycamore Dr. (west of the Town of Loxahatchee Groves) Construction of a 4 lane divided roadway from the existing 2 lanes. Lane closures are not planned. 12. LOCATION: Old Dixie Hwy. from NE 20 th St. to 38 th St. (City of Boca Raton) Installation of pavement markings and reflective pavement markers There will be lane closures. 13. LOCATION: Old Dixie Hwy. from Spanish River Blvd. to Yamato Rd. (City of Boca Raton) Installation of pavement markings and reflective pavement markers. There will be lane closures. 4

5 14. LOCATION: Ocean Ave. Bridge over the Intracoastal Waterway (Town of Lantana) Bridge removal and construction of a new bridge. The bridge closed on March 18, 2012, and will reopen early Traffic will be detoured via: A1A, Lake Ave./Lucerne Ave. and U.S. #1. F:\TRAFFIC\EGM\2012\pbcr&bcu.doc 5

Ocean Way at U.S. #1 (Town of Jupiter) Installation of a new traffic signal.

Ocean Way at U.S. #1 (Town of Jupiter) Installation of a new traffic signal. PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: FEBRUARY 13, 2013 STATUS FOR FEBRUARY 18, 2013 THROUGH FEBRUARY 24, 2013 *** CONSTRUCTION WORK ZONES ADDED

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

Land Use Context Definitions

Land Use Context Definitions Land Use Context Definitions Note: The colors to the right of the land use context names refer to the mapset. Land Use Context Type Description Building Placement and Parking Land Uses Data Source Higher

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

IST FUNDING THROUGH CURRENT FISCAL YEAR ONLY

IST FUNDING THROUGH CURRENT FISCAL YEAR ONLY IST FUNDING THROUGH CURRENT FISCAL YEAR ONLY Data Date: 1/17/2019 Expended Engineering B04 - Bridge Modifications Smith Sundy Rd. over LWDD Lat. 33 Canal (PB934411) 600,000 600,000 $162,437 $75,944 Palm

More information

Draft Year 2040 Cost Feasible Plan

Draft Year 2040 Cost Feasible Plan Year 2040 Plan Ranking of Desires Plan Projects And Matching of Available Revenues Palm Beach Metropolitan Planning Organization (MPO) Technical Advisory Committee (TAC) Citizens Advisory Committee (CAC)

More information

Palm Beach County Infrastructure Sales Tax Program Project Tracking. FY 2017 Projects

Palm Beach County Infrastructure Sales Tax Program Project Tracking. FY 2017 Projects FY 2017 Projects Engineering Lake Osborne Dr. over Lake Bass Canal Palm Beach Lakes Blvd over FEC R/R Smith Sundy Rd. over LWDD Lat. 33 Canal Kudza Rd. over LWDD Lat. 8 Canal Prairie Rd. over LWDD Lat.

More information

Palm Beach County Traffic Report. Aug. 25 through Sept. 1, 2017

Palm Beach County Traffic Report. Aug. 25 through Sept. 1, 2017 August 25, 2017 Meredith Cruz, (561) 641 6440 mcruz@corradino.com Palm Beach County Traffic Report Aug. 25 through Sept. 1, 2017 Palm Beach County Palm Beach County traffic will be affected this week by

More information

What is Shovel Ready Palm Beach? What is a Shovel Ready Site?

What is Shovel Ready Palm Beach? What is a Shovel Ready Site? What is Shovel Ready Palm Beach? Shovel Ready Palm Beach is one of the first programs of its kind in Florida. Under the program, the BDB identifies vacant commercial and industrial property that is Shovel

More information

PALM BEACH MPO. May 3, Valerie Neilson, AICP Multimodal Manager Palm Beach MPO

PALM BEACH MPO. May 3, Valerie Neilson, AICP Multimodal Manager Palm Beach MPO PALM BEACH MPO May 3, 2017 Valerie Neilson, AICP Multimodal Manager Palm Beach MPO VNeilson@PalmBeachMPO.org US-1 MULTIMODAL CORRIDOR STUDY 1. Project Overview 2. Goals 3. Timeline 4. Next Steps PROJECT

More information

PALM BEACH COUNTY INFRASTRUCTURE SURTAX REVENUES As of November 30, 2017

PALM BEACH COUNTY INFRASTRUCTURE SURTAX REVENUES As of November 30, 2017 PALM BEACH COUNTY INFRASTRUCTURE SURTAX REVENUES As of November 30, 2017 Interest Sales Tax TOTAL BUDGET Overage/(Shortfall) FY 2017 $ 185,642.45 $ 50,430,391.92 $ 57,708,049.23 $ 50,398,384.00 $ 7,309,665.23

More information

MUNICIPAL COMMISSION/COUNCIL TERMS, TERM LIMITS, SALARIES AND BENEFITS SURVEY

MUNICIPAL COMMISSION/COUNCIL TERMS, TERM LIMITS, SALARIES AND BENEFITS SURVEY City of Atlantis 2 years ne Mayor - $12,800 ne Council - $10,800 City of Belle Glade 3 years ne Mayor - $11,712 Vice-Mayor - $11,036 $10,360; Mayor also has an assigned vehicle City of Boca Raton 3 years

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness, From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY

More information

1 6:52 AM BUS YARD 4:38 PM 2 7:12 AM N SEACREST BLVD & NE 16TH AVE 4:18 PM

1 6:52 AM BUS YARD 4:38 PM 2 7:12 AM N SEACREST BLVD & NE 16TH AVE 4:18 PM 8th 9th Grade Routes SouthTech Academy Transportation Routes STEC Trip 01 1 6:34 AM OKEECHOBEE BLVD & ROYAL PALM BEACH BLVD 5:00pm 2 6:52 AM GOODWILL @N MILITARY TRL & OKEECHOBEE BLVD 4:42pm 3 7:00 AM

More information

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015 From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

Government in Palm Beach County

Government in Palm Beach County Government in Palm Beach County 2018 STAY CONNECTED Are you getting the latest updates and information from county government? If not, we invite you to visit our Stay Connected page at pbcgov.com/stayconnected.

More information

October 31, 2014 Chuck McGinness, (954)

October 31, 2014 Chuck McGinness, (954) From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October

More information

Future Land Use Amendments History Report

Future Land Use Amendments History Report Amendments History Report Round 6 C 6 C 6 C 2 LGA 206 024 Feurring Commercial Southeast corner of Atlantic Ave & Adopted 206 035 4.90 Lyons Rd 2 LGA 206 025 2 LGA 205 00 6 B 2 LGA 206 007 West Boynton

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

Palm Beach County Redevelopment Sites State Road 7, Delray Beach, FL 33446

Palm Beach County Redevelopment Sites State Road 7, Delray Beach, FL 33446 14095 State Road 7, Delray Beach, FL 33446 Business Development Board of Palm Beach County, Inc. BDB.org 561.835.1008 1 2400 Metro Center Blvd - West Palm Beach - Lincoln College Business Development Board

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

Public Information Center August 12, 2010

Public Information Center August 12, 2010 Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General

More information

Toll Rates for Florida Turnpike System and Florida Department of Transportation (FDOT) Toll Facilities. South Florida

Toll Rates for Florida Turnpike System and Florida Department of Transportation (FDOT) Toll Facilities. South Florida Toll Rates for Florida Turnpike System and Florida Department of Transportation (FDOT) Toll Facilities South Florida Effective: October 29, 207 S.R. 82 (HEFT) Miami-Dade and Broward Counties S.R. 82 (HEFT)

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

Ohio Department of Transportation Traffic Advisory. District 4 Allen C. Biehl, P.E., Deputy Director S. Arlington Road.

Ohio Department of Transportation Traffic Advisory. District 4 Allen C. Biehl, P.E., Deputy Director S. Arlington Road. Ohio Department of Transportation Traffic Advisory District 4 Allen C. Biehl, P.E., Deputy Director 2088 S. Arlington Road. Akron, Ohio 44306 www.transportation.ohio.gov/dist4 Friday, September 18, 2015

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

TRANDERSOL SAMPLING OF CENTRAL STATIONS BEGINNING IN FLORIDA CURRENT PROJECTS FLORIDA TRANDERSOL - EDERP MIAMI GRAND CENTRAL LONG EXPRESS EXPRESS

TRANDERSOL SAMPLING OF CENTRAL STATIONS BEGINNING IN FLORIDA CURRENT PROJECTS FLORIDA TRANDERSOL - EDERP MIAMI GRAND CENTRAL LONG EXPRESS EXPRESS CURRENT PROJECTS FLORIDA NTSN MODULAR OUTLINE TRAIN SCHEDULE STOPS 75 10 10 95 27 95 75 75 75 75 4 4 27 75 595 75 MIRAMAR CENTRAL MIAMI KENDAL CENTRAL MIAMI TAMIAMI CENTRAL 95 595 MIAMI LAKES CENTRAL 95

More information

Long water shutdown scheduled for Tuesday, September 18

Long water shutdown scheduled for Tuesday, September 18 Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility

More information

FPL FiberNet Locations List CLLI ADDRESS MARKET SITE TYPE MIANFLHF W DIXIE HWY (Arcos) MIAMI CABLE LANDING STATION MIAMFLEL 1 NE 1ST ST MIAMI

FPL FiberNet Locations List CLLI ADDRESS MARKET SITE TYPE MIANFLHF W DIXIE HWY (Arcos) MIAMI CABLE LANDING STATION MIAMFLEL 1 NE 1ST ST MIAMI FPL FiberNet Locations List CLLI ADDRESS MARKET SITE TYPE MIANFLHF 15950 W DIXIE HWY (Arcos) MIAMI CABLE LANDING STATION MIAMFLEL 1 NE 1ST ST MIAMI CARRIER CONDO MIAMFL98 100 N BISCAYNE BLVD MIAMI CARRIER

More information

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 May 16, 2014 Chuck McGinness, (954) 777-4090 chuck.mcginness@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 FORT LAUDERDALE -- Construction and maintenance-related lane

More information

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/14/ :00:05 PM

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/14/ :00:05 PM OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS Incidents/: 9/14/2018 10:00:05 PM ROUTE Hwy100 15 22 7 Mi W of Ainsworth St Park Closure Information Westbound (Right

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK

More information

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

Milestone: Bridge to Nowhere scheduled for demolition Aug 14 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Blanca Del Valle (915) 790-4341 Blanca.DelValle@txdot.gov August 12, 16 Milestone: Bridge to Nowhere scheduled for demolition Aug 14

More information

Ohio Department of Transportation Construction Update

Ohio Department of Transportation Construction Update Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District

More information

PROGRESS PARK CONNECTOR

PROGRESS PARK CONNECTOR PROGRESS PARK CONNECTOR Project No. 9999 098 R65, P102 ALTERNATIVES ANALYSIS 6 April 2015 Revised for updated dates PROGRESS PARK CONNECTOR ROAD ALTERNATIVES ALTERNATIVE # 1 West from the intersection

More information

50 Largest U.S. Metropolitan Areas

50 Largest U.S. Metropolitan Areas America s Racially : Opportunities and Challenges 50 Largest U.S. Metropolitan Areas Community types in the 50 largest metropolitan areas 39,333,003 % 14,533,3 16,983,337 9% 10% 47,406,687 49,199,197 30,180,578

More information

Facility Renewal Project Budget Report July 01, 2018

Facility Renewal Project Budget Report July 01, 2018 Facility Renewal Project Report Referendum Project List August 31, 2018 ISSOC Meeting May 11, 2018 ISSOC Meeting Facility Renewal Projects Acreage Pines ES 7,001,890 7,001,890 7,001,890 - - Alexander W

More information

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration

More information

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County Construction Update Contact: The District Two Public Information Office at (419) 373-4428 or email D02.PIO@dot.ohio.gov For Immediate Release Thursday, October 18, 2018 ODOT District Two Construction Update

More information

East Coast Greenway (ECG) Southeast Region Miami-Dade/Broward/Palm Beach/Martin/St. Lucie/Indian River

East Coast Greenway (ECG) Southeast Region Miami-Dade/Broward/Palm Beach/Martin/St. Lucie/Indian River East Coast Greenway (ECG) Southeast Region Miami-Dade/Broward/Palm Beach/Martin/St. Lucie/Indian River What is the ECG/SE Region? Connects Key West to Maine 220 miles Indian River to Miami-Dade County

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

PennDOT Interstate Work next week March 30-April 3:

PennDOT Interstate Work next week March 30-April 3: PennDOT Interstate Work next week March 30-April 3: Interstate 80 Interstate 81 DELAYS THIS WEEK: Exit 256 to the Schuylkill County line. Eastbound & Westbound. Bridge cleaning Monday (3/30), Tuesday (3/31)

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

February 15, Honorable Melissa McKinlay, Mayor and Members of the Board of County Commissioners. FayeW:~~~ Assistal}f' LOUT}'~drnlnistrator

February 15, Honorable Melissa McKinlay, Mayor and Members of the Board of County Commissioners. FayeW:~~~ Assistal}f' LOUT}'~drnlnistrator Department of Engineering and Public Works P.O. Box 21229 INTEROFFICE MEMORANDUM West Palm Beach, FL 33416-1229 (561) 684-4 FAX: (561) 684-45 w ww.pbcgov.com Palm Beach County Board of County Commissioners

More information

City of Delray Beach. Additional Information for Item WS.3

City of Delray Beach. Additional Information for Item WS.3 Items for Discussion: History of the Valet Program Public Parking Allocated to Valets Valet Program Financial Review Location and inventory of current queues County Courthouse / Library Parking Facilities

More information

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015 East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities

More information

PALM BEACH COUNTY BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY I. EXECUTIVE BRIEF

PALM BEACH COUNTY BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY I. EXECUTIVE BRIEF PALM BEACH COUNTY BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY Agenda Item: Meeting Date: July 11, 2017 Department: Submitted By: Office of Financial Management and Budget Submitted For: County Administration

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

CityStats Southeast Florida Trends

CityStats Southeast Florida Trends CityStats Florida Trends 2018 Research Analyst Liane Giroux, CAE Center for Municipal Research & Innovation Florida League of Cities CityStats Florida Regional Trend Analysis Municipal Revenue Sources

More information

FLORIDA DIVISION OF EMERGENCY MANAGEMENT STATE WATCH OFFICE DAILY INCIDENT REPORT

FLORIDA DIVISION OF EMERGENCY MANAGEMENT STATE WATCH OFFICE DAILY INCIDENT REPORT FLORIDA DIVISION OF EMERGENCY MANAGEMENT STATE WATCH OFFICE DAILY INCIDENT REPORT Incident Number: 2019-354 Incident Name: Traffic Crash with Diesel Spill Occurred: 1/18/2019 23:13 ET Reported to SWO:

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

CityStats Southeast Florida Trends

CityStats Southeast Florida Trends CityStats Southeast Florida Trends 2017 Research Analyst Liane Schrader, CAE Center for Municipal Research & Innovation Florida League of Cities CityStats Southeast Florida Regional Trend Analysis 100%

More information

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT CONTACT: VDOT Customer Service 1-800-367-7623 November 18, Richmondinfo@VDOT.virginia.gov WEEKLY HIGHWAY ALERT RICHMOND DISTRICT COLONIAL HEIGHTS Below is a forecast of road construction that is expected

More information

068D 420B 068C 421E SEMINOLE PRATT WHITNEY RD 420A SOUTHERN BLVD 500J 500Q 500B

068D 420B 068C 421E SEMINOLE PRATT WHITNEY RD 420A SOUTHERN BLVD 500J 500Q 500B 068D PIERCE HAMMOCK 068H 069A 068J 068K 068A 448 420H FRONTIER 420B 068C ACREAGE PINES ORANGE BLVD 068E 068G 069B 420C 420G 420D 420E SEMINOLE PRATT WHITNEY RD 420A 421E 421A GOLDEN GROVE 421H 421C 421J

More information

PALM BEACH MPO TRANSPORTATION IMPROVEMENT ADOPTED JUNE 15, Amended 7/20/17

PALM BEACH MPO TRANSPORTATION IMPROVEMENT ADOPTED JUNE 15, Amended 7/20/17 PALM BEACH MPO TRANSPORTATION IMPROVEMENT PROGRAM FY 2018-2022 ADOPTED JUNE 15, 2017 WWW.PALMBEACHMPO.ORG/TIP Amended 7/20/17 2300 North Jog Road - 4th Floor - West Palm Beach FL, 33411-561.684-4170 Public

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All

More information

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE January 11, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-007 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Florida Department of Transportation MIKE DEW SECRETARY

Florida Department of Transportation MIKE DEW SECRETARY RICK SCOTT GOVERNOR Florida Department of Transportation MIKE DEW SECRETARY July 5, 2018 JoAnn May, 239-225-1900 JoAnn.May@dot.state.fl.us DISTRICT ONE NORTHERN COUNTIES ROADWATCH REPORT #27 FOR WEEK OF

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 9

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 9 TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 9 From: Date: Subject: Staff October 21, 2016 Council Meeting South Dixie Highway Corridor Improvement Plan

More information

MARTIN COUNTY MANATEE PROTECTION ZONES

MARTIN COUNTY MANATEE PROTECTION ZONES MANATEE PROTECTION ZONES For description of zone boundaries see: 68C-22.024 F.A.C for State Manatee Protection Zones last amended 2/24/990 For infomation please call or write to: Fish and Wildlife Conservation

More information

Infrastructure Sales Tax Capital Projects April 4, 2017

Infrastructure Sales Tax Capital Projects April 4, 2017 Engineering & Public Works Bridge Replacements Prosperity Farms Rd. over SFWMD C-17 Canal (934116) 1 6th Ave. So. over Lake Osborne (LWDD E-4 Canal)(S Br/ East bound) (934307) Corkscrew Blvd. over SFWMD

More information

Weekly East Tennessee Construction Report for May 31-June 6, 2018

Weekly East Tennessee Construction Report for May 31-June 6, 2018 Weekly East Tennessee Construction Report for May 31-June 6, 2018 Thursday, May 31, 2018 01:30pm ANDERSON COUNTY, SR 62 between Union Valley Road and SR 162: Motorists should be alert for possible lane

More information

Palm Beach County Condo Investment Portfolio

Palm Beach County Condo Investment Portfolio Palm Beach County Condo Investment Portfolio 94 Class B Units South Florida Market Presented by: The Goldstein Group Brokerage Consulting Management Development Encompassing the entirety of the flourishing

More information

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 10/11/2018 5:24:09 PM

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 10/11/2018 5:24:09 PM OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS Incidents/: 10/11/2018 5:24:09 PM ROUTE Hwy100 15 22 7 Mi W of Ainsworth St Park Closure Information Westbound (Right

More information

Forest Hill Blvd. at Kirk Road Widening Project FM#:

Forest Hill Blvd. at Kirk Road Widening Project FM#: Seat Belts Save Lives. Buckle Up Everyone Every Time! Forest Hill Blvd. at Kirk Road Widening Project FM#: 435122-1-52-01 Project Scope This 0.298-mile project began Nov. 17, 2016 and is expected to be

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth) RELEASE: IMMEDIATE March 8, 2019 CONTACT: Tina.Bundy 540-907-8325 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 10 March 16, 2019 All work is scheduled weather permitting. Real-time information

More information

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/5/2018 2:12:06 PM

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/5/2018 2:12:06 PM OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS Incidents/: 9/5/2018 2:12:06 PM ROUTE ORE99EB 2 3 @ Salem, Hyacinth/Verda Hwy100 15 22 7 Mi W of Ainsworth St Park Southbound

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

Palm Beach County School District Eligibility Survey - Free/Reduced Count of Students Aged 5-17 as of 4/14/2019

Palm Beach County School District Eligibility Survey - Free/Reduced Count of Students Aged 5-17 as of 4/14/2019 0664 Academy For Positive Learning - 0664 - EM 128 103 6 19 109 85.16 % 2141 Acreage Pines Elementary - 2141 - E 490 213 42 235 255 52.04 % 1451 Addison Mizner Elementary - 1451 - E 849 194 59 596 253

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work

More information

MATTHEW G. MCALLISTER Director (561)

MATTHEW G. MCALLISTER Director (561) SOUTH FLORIDA INDUSTRIAL TEAM CUSHMAN & WAKEFIELD AVAILABLE PROPERTIES February 2017 CUSHMAN & WAKEFIELD 515 E. Las Olas Boulevard, Suite 860 Fort Lauderdale, FL 33301 225 NE Mizner Boulevard, Suite 300

More information

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 2, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-042 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Work in 2015 and Annual Mobility- Management Plan

Work in 2015 and Annual Mobility- Management Plan Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector

More information

FALL Construction Project Status Report PROJECT HIGHLIGHT CURRENT PROJECTS. NORTH COUNTY DISTRICT PARK New Construction PROJECT SCOPE

FALL Construction Project Status Report PROJECT HIGHLIGHT CURRENT PROJECTS. NORTH COUNTY DISTRICT PARK New Construction PROJECT SCOPE FALL 2018 Construction Project Status Report PROJECT HIGHLIGHT 1 NORTH COUNTY DISTRICT PARK PROJECT SCOPE Palm Beach County has leased 82 acres to the City of Palm Beach Gardens for the construction of

More information

October Business Owner Task Force. Matt Sanman Public Information Coordinator

October Business Owner Task Force. Matt Sanman Public Information Coordinator October Business Owner Task Force Matt Sanman Public Information Coordinator Trick-or-Treating Safety Tips for Children Plan a route in advance and have emergency plan if lost. Wear reflective clothing

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

Customer Service:

Customer Service: Customer Service: 1-877-905-0500 MIAMI - DADE COUNTY Medical Doctors House Calls 1-855-668-8798 8:00am - 5:00pm 1770 NE Miami Gardens Dr. Unit #1 North Miami Beach, FL 33179 (305) 949-4141 12555-C Biscayne

More information

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012 Today s Date: Friday, September 7, 2012, #12-255 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov 530. 741.4566

More information

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 7, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 187 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

All closures this week happen at night, including full closures of Mesa and I-10

All closures this week happen at night, including full closures of Mesa and I-10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov May 25, 2018 North Mesa Tuesday, May 29 through Thursday, May 31 9 p.m. each

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

Northeast Corridor Transportation Update

Northeast Corridor Transportation Update Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer

More information

State Highway System Key Sheet Broward County ²

State Highway System Key Sheet Broward County ² Broward County ² GOVT RD/SNAKE RD 3 0 3 Indian River St. Lucie Martin Palm Beach Broward I-75 " On System Roads #" 10 3293 Map Preparation Date: 5/2/2016 3:53:29 PM 86075000 #" 75 US 27 Inset - 3 Inset

More information

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 21, 2017 CONTACT: Sandy Myers 540-332-9201 (office) STA17-204 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell) RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)

More information

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 1, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 020 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information