1 PROGRESS PARK CONNECTOR Project No R65, P102 ALTERNATIVES ANALYSIS 6 April 2015 Revised for updated dates

2 PROGRESS PARK CONNECTOR ROAD ALTERNATIVES

3 ALTERNATIVE # 1 West from the intersection of E. Lee Trinkle Drive and Gator Lane intersection. Intersect Peppers Ferry Road approximately 1 ¼ miles east of the I 77 Interchange with Peppers Ferry Road. Peppers Ferry Road will be 6 lanes from its intersection with connector road to Country Lane where it will increase to 7 lanes until the northbound I 77 exit/entrance ramps.

4 ALTERNATIVE #1 PROS AND CONS PROS Fewer disturbances to undeveloped land Remains on existing Peppers Ferry alignment Acceptable level of service CONS May encounter environmental issues Significant town utility relocations Traffic queuing, major intersection and road section improvement Ramp widening (Interchange) Bridge widening (Interchange)

5 ALTERNATIVE # 2 West from the intersection of E. Lee Trinkle Drive and Gator Lane intersection. Intersect Peppers Ferry Road approximately 3/4 mile east of the I 77 Interchange with Peppers Ferry Road Peppers Ferry Road will be 6 lanes from its intersection with connector road to Country Lane where it will increase to 7 lanes until the northbound I 77 exit/entrance ramps.

6 ALTERNATIVE #2 PROS AND CONS PROS Fewer disturbances to undeveloped land Remains on existing Peppers Ferry alignment Acceptable level of service CONS May encounter environmental issues Significant town utility relocations Traffic queuing, major intersection and road section improvements Ramp widening (Interchange) Bridge widening (Interchange)

7 ALTERNATIVE # 3 Four lane divided Progress Park Connector route from the intersection of E. Lee Trinkle and Gator Lane intersection west to intersect Nye Road. Six lanes (4 northbound, 2 southbound) north from Nye Road intersection to Peppers Ferry Road to a signalized intersection at Peppers Ferry Road. Peppers Ferry Road will be 7 lanes from Country Lane to I 77 Northbound exit/entrance ramps. I 77 northbound exit/entrance ramps widened to 5 lanes. Peppers Ferry Road bridge over I 77 will be 6 lanes.

8 PROS Fewer disturbances to Peppers Ferry Road beyond interchange Nye Road remains on existing alignment Fewer (reduced) traffic queues than Alternative #1 and Alternative #2 Peppers Ferry Rd remains 2 lanes east of Granite Acres CONS Ramp widening (Interchange) Traffic queuing, major intersection and road section improvements Bridge widening (Interchange) Acceptable level of service ALTERNATIVE #3 PROS AND CONS

9 ALTERNATIVES #3A, 3AA Four lane divided Progress Park Connector route from the intersection of E. Lee Trinkle and Gator Lane intersection west and intersect with a Nye Road Extension. o Existing Nye Road will be right in/right out at Peppers Ferry Road. Alternative 3A: From Nye Road intersection, six lanes west to a signalized intersection at Peppers Ferry Road (4 westbound, 2 eastbound). Peppers Ferry Road will be 7 lanes to I 77 Northbound exit/entrance ramps. I 77 northbound exit/entrance ramps will be widened to 4 lane and the Peppers Ferry Road bridge over I 77 will be 4 lane.

10 PROS Fewer disturbances to undeveloped land Nye Road remains on existing alignment as a right in/right out Less ramp widening Peppers Ferry Rd remains 2 lanes east of Granite Acres Acceptable level of service Ramp widening (Interchange) Bridge widening (Interchange) CONS Traffic queuing, major intersection and road section improvements ALTERNATIVE #3A, 3AA PROS AND CONS

11 2024 Supplemental Analysis Progress Park Development Cap Two lane paved, graded for future median and four lane divided Progress Park Connector route from the intersection of E. Lee Trinkle and Gator Lane intersection west and intersect with Peppers Ferry Road (Alt. 1 and 2) and intersect with Nye Road (Alt. 3) Alternative 1: Minimal improvements at intersection with Peppers Ferry Road, up to 15,000 vehicles per day. Alternative 2: Minimal improvements at intersection with Peppers Ferry Road, up to 17,000 vehicles per day. Alternative 3: Minimal improvements at intersection with Nye Road, up to 12,000 vehicles per day.

12 Typical Roadway Section TWO LANE INITIAL BUILDOUT WITH GRADING FOR FOUR LANES ULTIMATE BUILDOUT

13 Progress Park Utilization TWO LANE INITIAL BUILDOUT WITH GRADING FOR FOUR LANES Two lane paved section will be adequate for Progress Park buildout utilizing typical trip generation traffic numbers for industrial land. The two lane section will be adequate until additional Board permitted development or development within the Town creates traffic conditions which exceed the development cap.

14 SCHEDULE DATE EVENT MARCH 30 JOINT MEETING WITH TOWN OF WYTHEVILLE Review Alignments within Town Limits APRIL 4 & 11 ADVERTISE FOR PUBLIC REVIEW MEETING MAY 6 MAY MAY 26 MAY 27 PUBLIC REVIEW MEETING (WYTHE COUNTY BOARD CHAMBERS) Review Alignments with public and concerned citizens REVIEW PUBLIC COMMENTS PRESENT RECOMMENDED ALTERNATIVE TO BOARD OF SUPERVISORS PROCEED WITH DESIGN OF SELECTED ALTERNATIVE

15 QUESTIONS?

16 ALTERNATIVE # 3 Realigned I 77 Ramp Option Four lane divided Progress Park Connector route from the intersection of E. Lee Trinkle Drive and Gator Lane intersection west to intersect Nye Road. Six lanes (4 northbound, 2 southbound) north from intersection with Nye Road to a signalized intersection at Peppers Ferry Road opposite the I 77 ramps. Peppers Ferry Road will be 5 lanes west from Country Lane to signalized intersection. I 77 northbound exit/entrance ramps widened to 4 lanes. Peppers Ferry Road bridge over I 77 will be 4 lanes.

17 ALTERNATIVE #3 (Ramp Realignment) PROS AND CONS PROS CONS Fewer disturbances to Peppers Ferry Road beyond interchange Less queuing than other alternatives Only one major intersection upgrade Less road widening Nye Road remains on existing alignment Ramp widening and realignment (Interchange) Bridge widening (Interchange) Fewer (reduced) traffic queues than Alternative #1 and Alternative #2 Peppers Ferry Rd remains 2 lanes east of Granite Acres Acceptable level of service

FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A

FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A VIRGINIA DEPARTMENT OF TRANSPORTATION I-85 / I-95 INTERCHANGE FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A Columbia Rd REFINED CONCEPT 1 PROJECT A Bellevue Rd COST: $3.3M Siege Rd Eliminate the loop ramp

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure

More information

PRIORITIES COMMITTEE MEETING

PRIORITIES COMMITTEE MEETING PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony

More information

Springettsbury Township. Road Improvement Projects

Springettsbury Township. Road Improvement Projects Springettsbury Township Road Improvement Projects 2009 2016 2016 Township Road Improvement Projects Springettsbury Township is divided into the following 4 Sectors: Northwest Sector Sherman Street Route

More information

Appendix 4.1 L. No-Build Project Descriptions

Appendix 4.1 L. No-Build Project Descriptions Appendix 4.1 L No-Build Project Descriptions No-Build Projects New Bedford A new traffic signal system was installed and activated in early 2009 at the intersection of King s Highway and Mount Pleasant

More information

WELCOME US 83 Public Meeting

WELCOME US 83 Public Meeting WELCOME US 83 Public Meeting From north of the Starr/Zapata County Line to Loma Blanca Road Thursday, June 8, 2017 Roma Middle School Lecture Hall Open House: 5 6 p.m. Presentation and Public Comment:

More information

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell) RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)

More information

TABLE OF CONTENTS. Coral Springs Charter High School and Middle School Job No Page 2

TABLE OF CONTENTS. Coral Springs Charter High School and Middle School Job No Page 2 Job No. 15-019 Page 2 TABLE OF CONTENTS 1.0 INTRODUCTION... 4 2.0 EXISTING CONDITIONS... 5 3.0 TRAFFIC GENERATION... 7 4.0 TRIP DISTRIBUTION... 8 5.0 FUTURE CONDITIONS... 8 6.0 SITE ACCESS...13 7.0 CONCLUSION...13

More information

4. Safety Concerns Potential Short and Medium-Term Improvements

4. Safety Concerns Potential Short and Medium-Term Improvements NH Route 104 Access Management Study Page 19 4. Safety Concerns Potential Short and Medium-Term Improvements Potential safety improvement strategies are listed by priority based on field observations by

More information

Fairfax County Parkway Widening Fairfax County

Fairfax County Parkway Widening Fairfax County Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

Transportation TRANSPORTATION PROJECTS

Transportation TRANSPORTATION PROJECTS Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015 Northeast Anthony Henday Drive Edmonton Ring Road Update Strathcona Chamber of Commerce March 18, 2015 Project Background 2 Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest

More information

A. CONCLUSIONS OF THE FGEIS

A. CONCLUSIONS OF THE FGEIS Chapter 11: Traffic and Parking A. CONCLUSIONS OF THE FGEIS The FGEIS found that the Approved Plan will generate a substantial volume of vehicular and pedestrian activity, including an estimated 1,300

More information

5.1 Traffic and Transportation

5.1 Traffic and Transportation 5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane

More information

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018 FREDERICKSBURG DISTRICT District Engineer Marcie Parker, P.E. May 8, 2018 3 Interstate 95 Projects Fredericksburg Area Fredericksburg region will see greatest degree of I-95 construction since widening

More information

ROUTE 630 DIVERGING DIAMOND INTERCHANGE

ROUTE 630 DIVERGING DIAMOND INTERCHANGE ROUTE 630 DIVERGING DIAMOND INTERCHANGE Virginia Department of Transportation Contract Value and Dates Contract Value: $99,949,969.50 Start of Construction: Summer 2017 Final Completion Date: July 31,

More information

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage

More information

Ocean Way at U.S. #1 (Town of Jupiter) Installation of a new traffic signal.

Ocean Way at U.S. #1 (Town of Jupiter) Installation of a new traffic signal. PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: FEBRUARY 13, 2013 STATUS FOR FEBRUARY 18, 2013 THROUGH FEBRUARY 24, 2013 *** CONSTRUCTION WORK ZONES ADDED

More information

Lake Erie Commerce Center Traffic Analysis

Lake Erie Commerce Center Traffic Analysis LOCATION: East of NYS Route 5 at Bayview Road Town of Hamburg Erie County, New York PREPARED BY: Wendel Companies 140 John James Audubon Parkway Suite 200 Amherst, New York 14228 January 2012 i ii Table

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

Pedestrian Safety Review Spadina Avenue

Pedestrian Safety Review Spadina Avenue STAFF REPORT ACTION REQUIRED Pedestrian Safety Review Spadina Avenue Date: October 13, 2015 To: Toronto and East York Community Council From: Director, Transportation Services, Toronto and East York District

More information

Arlington County Board Work Session Eastbound Widening January 17, Amanda Baxter, VDOT Special Projects Development Manager

Arlington County Board Work Session Eastbound Widening January 17, Amanda Baxter, VDOT Special Projects Development Manager Arlington County Board Work Session Eastbound Widening January 17, 2017 Amanda Baxter, VDOT Special Projects Development Manager Program Area Map 2 Program Scope Tolling during weekdays, peak hours, peak

More information

A. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1

A. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1 Mon-Fayette Transportation Project A. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1 The Mon/Fayette Transportation Project (MFTP) from I-68 in West Virginia

More information

Road widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected.

Road widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected. PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: SEPTEMBER 12, 2012 STATUS FOR SEPTEMBER 17, 2012 THROUGH SEPTEMBER 23, 2012 *** CONSTRUCTION WORK ZONES ADDED

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Report to the Strategic Development Committee

Report to the Strategic Development Committee Report to the Strategic Development Committee Request of Virginia Department of Transportation for Easements across Washington Dulles International Airport Property at Route 28 May 2016 PURPOSE Staff requests

More information

State Project Reconstruction I-84

State Project Reconstruction I-84 State Project 151-273 Reconstruction I-84 Waterbury, Connecticut FROM WASHINGTON STREET TO PIERPONT ROAD I-84 Constructors J.V. Robert Turner Area Engineer Ken Fargnoli District Engineer John Dunham Assistant

More information

Strategic Signal Timing Changes = BIG Results. Barbara Jones, PE, PTOE DGL Consulting Engineers, LLC Senior Traffic Engineer

Strategic Signal Timing Changes = BIG Results. Barbara Jones, PE, PTOE DGL Consulting Engineers, LLC Senior Traffic Engineer Strategic Signal Timing Changes = BIG Results Barbara Jones, PE, PTOE DGL Consulting Engineers, LLC Senior Traffic Engineer Pre Signal Timing Updates Signal Timing Updates Average Retiming Interval Percent

More information

SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER

SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER Proposal to Eliminate Traffic Gridlock in South North York Centre Area With Southbound Yonge Street to Eastbound Highway 401 Fly-UNDER A much

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

Appendix H1 Traffic Study Hill St Obispo Ave Obispo Ave Student Drop-off & Pick-up Area Parking Lot Plaza Level Hill St Fire Lane Access Service Lane Access Redondo Ave Redondo Ave Parking Lot N No

More information

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE January 11, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-007 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016 RELEASE: IMMEDIATE June 10, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

MEMORANDUM. Lynn Hayes LSA Associates, Inc.

MEMORANDUM. Lynn Hayes LSA Associates, Inc. MEMORANDUM To: Lynn Hayes LSA Associates, Inc. Date: May 5, 217 From: Zawwar Saiyed, P.E., Senior Transportation Engineer Justin Tucker, Transportation Engineer I Linscott, Law & Greenspan, Engineers LLG

More information

Replace Traffic Signal By Others (will accommodate longer arm for dual left turn lane) Install New Sign Structure

Replace Traffic Signal By Others (will accommodate longer arm for dual left turn lane) Install New Sign Structure Ramp Removed By Others Roadway Improvements By Others Ramp Improvements By Others Install ew Sign Structure Replace Traffic Signal By Others (will accommodate longer arm for dual left turn lane) Close

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

Northeast Corridor Transportation Update

Northeast Corridor Transportation Update Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer

More information

San Quentin Reuse Planning Committee Minutes Thursday, May 2, 2002 San Rafael Corporate Center

San Quentin Reuse Planning Committee Minutes Thursday, May 2, 2002 San Rafael Corporate Center San Quentin Reuse Planning Committee Minutes Thursday, May 2, 2002 San Rafael Corporate Center Committee Members Present: Alex Amoroso Al Boro John Dupar Phil Frank Steve Kinsey Joan Lundstrom for Larry

More information

PUBLIC INFORMATION SESSION #2

PUBLIC INFORMATION SESSION #2 Highway 16, Highway 779 to Kapasiwin Road, Planning Study PUBLIC INFORMATION SESSION #2 Wednesday June 20, 2012 4 to 8 pm HIGHWAY 16 Highway 779 to Kapasiwin Road Functional Planning Study Blueberry Community

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

ROUTE 122 CORRIDOR STUDY ---- Bedford County and Bedford City, Virginia

ROUTE 122 CORRIDOR STUDY ---- Bedford County and Bedford City, Virginia ROUTE 122 CORRIDOR STUDY ---- Bedford County and Bedford City, Virginia Developed by Region 2000 Regional Commission In cooperation with Bedford County, Virginia City of Bedford, Virginia Virginia Department

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

9 CONSTRUCTION OF BATHURST STREET FROM GREEN LANE WEST TO SOUTH OF HIGHWAY 11, TOWN OF EAST GWILLIMBURY AND TOWNSHIP OF KING

9 CONSTRUCTION OF BATHURST STREET FROM GREEN LANE WEST TO SOUTH OF HIGHWAY 11, TOWN OF EAST GWILLIMBURY AND TOWNSHIP OF KING Clause No. 9 in Report No. 9 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on May 15, 2014. 9 CONSTRUCTION OF BATHURST

More information

5.7 Local road upgrades

5.7 Local road upgrades 5.7 Local road upgrades Local roads around the St Peters interchange and the intersection of Campbell Road and Euston Road would be upgraded to ensure safe and efficient connections with the New M5, and

More information

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 2, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-042 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

M56. New Junction 11a Summary of the consultation report

M56. New Junction 11a Summary of the consultation report M56 New Junction 11a Summary of the consultation report August 2017 M56 New Junction 11a Summary of the public consultation The scheme The M56 New Junction 11a scheme is part of our continued programme

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work

More information

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Analette Ochoa and Wana Chiu, WRECO Parag Mehta, Kimley Horn Date: November 7, 2017 Re: Santa Cruz Route 1 Tier I and Tier II HOV

More information

State Route 189 Project and Draft Resolution of Support. November 2014

State Route 189 Project and Draft Resolution of Support. November 2014 State Route 189 Project and Draft Resolution of Support November 2014 Corridor Location Image sources: ADOT Statewide and National Importance: CANAMEX Corridor Image source: FHWA Statewide and National

More information

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 1, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 020 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

77 McDonnell-Lindbergh - Monday thru Friday NORTHBOUND Effective: March 18, Shopping Center North County. Shopping Center Washington &

77 McDonnell-Lindbergh - Monday thru Friday NORTHBOUND Effective: March 18, Shopping Center North County. Shopping Center Washington & 77 McDonnell- - Monday thru Friday NORTHBOUND Effective: March 18, 2019 & Valley Industries 4:53A 4:59A 5:10A 5:18A 5:27A 5:39A 5:33A 5:39A 5:50A 5:58A 6:07A 6:19A 6:13A 6:19A 6:31A 6:39A 6:49A 7:02A 6:53A

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All

More information

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 21, 2017 CONTACT: Sandy Myers 540-332-9201 (office) STA17-204 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Welcome to Dayton Parkway Interchange Open House. November 26, 2018

Welcome to Dayton Parkway Interchange Open House. November 26, 2018 Welcome to Dayton Parkway Interchange Open House November 26, 2018 Project Partners Minnesota DOT Hennepin County City of Rogers Dayton Project History NW Hennepin County I94 Study 2007/08 Interchange

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

2017 POLICY DOCUMENT. M1 Action Plan. Putting Queenslanders First

2017 POLICY DOCUMENT. M1 Action Plan. Putting Queenslanders First 2017 POLICY DOCUMENT Putting 2 Contents Message from the Premier 3 Our Commitment 4 The Newman-Nicholls Legacy 5 The Palaszczuk 6 Government s Record Our Plans: Putting 8 Call: 07 3844 8101 Mail: PO Box

More information

Penny for Pasco Renewal. FY2014/15 thru FY2024/25

Penny for Pasco Renewal. FY2014/15 thru FY2024/25 Penny for Pasco Renewal FY2014/15 thru FY2024/25 1 Background Pasco Citizens Committee (PAC) Citizens Survey Results Coordination Activities Project Schedule Category Allocations Revenue Estimates Distribution

More information

Add-A-Lane Contract V. along a Section of I-95 includes 6 Bridges

Add-A-Lane Contract V. along a Section of I-95 includes 6 Bridges Newton Needham Chamber of Commerce Add-A-Lane Contract V along a Section of I-95 includes 6 Bridges Project File No. 603711 July 29, 2014 1 Agenda Project Update Overview Bid and Contract Award Schedule

More information

Fairfax County Transportation Advisory Commission (TAC)

Fairfax County Transportation Advisory Commission (TAC) Fairfax County Transportation Advisory Commission (TAC) January 17, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Amanda Baxter, Special Projects Development Manager

More information

October 31, 2014 Chuck McGinness, (954)

October 31, 2014 Chuck McGinness, (954) From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

Chapter 4. Development Alternatives

Chapter 4. Development Alternatives Chapter 4. Development Alternatives Chapter 4. DEVELOPMENT ALTERNATIVES This chapter identifies and evaluates airport development alternatives to fulfill the facility requirements for the airport as defined

More information

US 19 Sunset Point Rd to Countryside Blvd.

US 19 Sunset Point Rd to Countryside Blvd. Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started

More information

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 23, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 057 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness, From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY

More information

HYANNIS ACCESS IMPLEMENTATION TASK FORCE NOTES April 12, PM CAPE COD COMMISSION CONFERENCE ROOM ATTENDEES. Hyannis Area Chamber of Commerce

HYANNIS ACCESS IMPLEMENTATION TASK FORCE NOTES April 12, PM CAPE COD COMMISSION CONFERENCE ROOM ATTENDEES. Hyannis Area Chamber of Commerce HYANNIS ACCESS IMPLEMENTATION TASK FORCE NOTES April 12, 2012 1 PM CAPE COD COMMISSION CONFERENCE ROOM Demetrius Atsalis Mark Ells Steve Seymour Bill Travers Chris Anzuoni JoAnn Crippen Frank Sanchez Jessica

More information

2013 El Paso County Comprehensive Mobility Plan. December 16, 2013

2013 El Paso County Comprehensive Mobility Plan. December 16, 2013 2013 El Paso County Comprehensive Mobility Plan December 16, 2013 2013 El Paso County Comprehensive Mobility Plan Map No. Project Name 01 I-10 COLLECTOR DISTRIBUTOR LANES 02 I-10/BORDER HIGHWAY CONNECTORS

More information

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

FY TRANSPORTATION IMPROVEMENT PROGRAM. Authority Projects FY

FY TRANSPORTATION IMPROVEMENT PROGRAM. Authority Projects FY Brewster Road Widening and North Avenue Bridge PA04009 This project will provide for the widening of Brewster Road at the south end of the airport as well as the replacement and realignment of the North

More information

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015 From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015

More information

Capital Beltway HOT Lanes Project

Capital Beltway HOT Lanes Project New Travel Choices Ahead Some things can t wait for traffic Capital Beltway HOT Lanes Project Project Update August 16, 2011 Major Milestones Reached Some things can t wait for traffic Project over 75%

More information

HAMPTON ROADS CROSSINGS PATRIOTS CROSSING AND HRBT

HAMPTON ROADS CROSSINGS PATRIOTS CROSSING AND HRBT HRTPO Board Meeting March 21, 2013 Agenda ITEM #9: HAMPTON ROADS CROSSINGS PATRIOTS CROSSING AND HRBT Congestion at the Hampton Roads Bridge-Tunnel (HRBT) on I-64 has long been identified as a problem

More information

Delaware County Engineer

Delaware County Engineer 2018 Project Presentation Delaware County Engineer 2018 ASHE LUNCHEON JANUARY 30, 2018 What s New at DCEO? New County Logos and Website Redesign GIS Upgrades Drone Program Planning for the Future ROADS,

More information

I-66 Inside the Beltway Feasibility Study

I-66 Inside the Beltway Feasibility Study I-66 Inside the Beltway Feasibility Study Feasibility Study Study Process Context Sensitive Dialogues Corridor Assessments / Data Collection Problem Statement Refinement Concept Development Concept Evaluation

More information

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County Construction Update Contact: The District Two Public Information Office at (419) 373-4428 or email D02.PIO@dot.ohio.gov For Immediate Release Thursday, October 18, 2018 ODOT District Two Construction Update

More information

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 May 16, 2014 Chuck McGinness, (954) 777-4090 chuck.mcginness@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 FORT LAUDERDALE -- Construction and maintenance-related lane

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route

More information

STUDY WORK GROUP MEETING No. 4. July 12, 2017

STUDY WORK GROUP MEETING No. 4. July 12, 2017 STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,

More information

SOUTHERN BELTWAY I-79 TO MON/FAYETTE EXPRESSWAY

SOUTHERN BELTWAY I-79 TO MON/FAYETTE EXPRESSWAY SOUTHERN BELTWAY I-79 TO MON/FAYETTE EXPRESSWAY Section 1 Purple Alternative (Revised: January 2007) I-79 to Mon/Fayette Expressway Purple Alternative Section 1 Photo Presentation Photo Presentation The

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

6. HIGHWAY MATTERS A. U.S. ROUTE 58 CORRIDOR STUDY

6. HIGHWAY MATTERS A. U.S. ROUTE 58 CORRIDOR STUDY SOUTHAMPTON COUNTY BOARD OF SUPERVISORS Regular Session i June 22, 2015 6. HIGHWAY MATTERS A. U.S. ROUTE 58 CORRIDOR STUDY Last year, VDOT commissioned the Route 58 Corridor Study to develop a planning

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

Hospital Link Project Project Update Winter 2018

Hospital Link Project Project Update Winter 2018 Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open

More information

1.0 Purpose and Organization of the Community Impact Assessment Addendum

1.0 Purpose and Organization of the Community Impact Assessment Addendum Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Carie Montero, Senior Project Manager/Environmental Lead, Parsons Transportation Group Parag Mehta, Kimley Horn Date: September 24,

More information

PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40

PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40 PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40 Project Description The primary purpose of this project is to improve the major

More information

Roadside Management Manual

Roadside Management Manual RSMM 550-10 Roadside Management Manual Section: DEVELOPMENTS OUTSIDE INTRODUCTION Setbacks of objects along provincial highways are controlled for various reasons: To protect the right-of-way for future

More information