TRAFFIC ALERT FOR JUNE 4-8, 2018 Highway Work Zones in the Staunton District

Size: px
Start display at page:

Download "TRAFFIC ALERT FOR JUNE 4-8, 2018 Highway Work Zones in the Staunton District"

Transcription

1 RELEASE: IMMEDIATE June 1, 2018 CONTACT: Sandy Myers (office) STA (cell) Ken Slack (office) (cell) TRAFFIC ALERT FOR JUNE 4-8, 2018 Highway Work Zones in the Staunton District STAUNTON The following is a list of highway work that may affect traffic in the Staunton transportation district during the coming weeks. The Staunton district consists of 11 counties from the Alleghany Highlands to the northern Shenandoah Valley: Alleghany, Bath, Rockbridge, Highland, Augusta, Rockingham, Page, Shenandoah, Frederick, Clarke and Warren. Scheduled work is subject to change due to inclement weather and material supplies. Motorists are advised to watch for slow-moving tractors during mowing operations. When traveling through a work zone, be alert to periodic changes in traffic patterns and lane closures. (NEW) or (UPDATE) indicates a new entry or a revised entry since last week s report. ALLEGHANY COUNTY INTERSTATE 64 (UPDATE) Mile marker 0 to 41, eastbound and westbound Overnight, mobile lane closures for vegetation management. June 3-7 from 8 p.m. to 5 a.m. Mile marker 29 to 36, eastbound Alternating lane closures for milling, paving and pavement marking. Weekdays through June 29 from 7 a.m. to 7 p.m. (UPDATE) Various roads Flagger traffic control for mowing and pavement patching at various locations. Monday to Friday from 7:30 a.m. to 3 p.m. Route 600 (Morris Hill Road) Road closed through June 7 for bridge work over Rucker Hollow Stream and Dry Branch tributary. Residents will have access to properties on either side of the bridges. Through traffic will follow posted detours.

2 Route 638 (Natural Well Road) Road closed for Jackson River bridge replacement between Route 687 (Jackson River Road) and Route 666 (East Morris Hill Road). Follow posted detour. Estimated project completion summer Route 696 (Selma-Low Moor Road) Occasional flagging operations as needed near Route 1101 (Winterberry Avenue) and I-64 for intersection improvements. Estimated project completion summer (UPDATE) Various roads Flagger traffic control for mowing and pavement patching at various locations. Monday to Friday from 7:30 a.m. to 3 p.m. BATH COUNTY (UPDATE) Various roads Mobile work zones for mowing at various locations. Monday to Friday from 7:30 a.m. to 3 p.m. (UPDATE) Various roads Mobile work zones for mowing and pavement patching at various locations. Monday to Friday from 7:30 a.m. to 3 p.m. ROCKBRIDGE COUNTY INTERSTATE 64 (UPDATE) Mile marker 41 to 57, eastbound and westbound Overnight, mobile lane closures for vegetation management. June 3-7 from 8 p.m. to 5 a.m. (UPDATE) Mile marker 57 to 41, westbound Right lane closures as needed for guardrail maintenance. June 4-9 from 6 a.m. to 9 p.m. (UPDATE) Mile marker 174 to 206, northbound and southbound Overnight, mobile lane closures for vegetation management. June 3-7 from 8 p.m. to 5 a.m. (NEW) Exit 175, southbound Shoulder closures along on- and off-ramps for shoulder repairs, June 6-8 from 8 a.m. to 4:30 p.m. (UPDATE) Mile marker 189 to 190, northbound Overnight right lane closure for excavation work from 8 p.m. June 5 to 7 a.m. June 6. Inclement weather will delay the work to June 6-7. (UPDATE) Various roads Flagger traffic control for paving, pipe replacement and tree removal. Mobile work zones for mowing and pavement patching. Monday to Friday from 7:30 a.m. to 3 p.m. (UPDATE) Route 780 (Brattons Run Road) Flagger controlled lane closures for bridge work over Bratton Run. June 4-8 from 7 a.m. to 5 p.m. (UPDATE) Various roads Flagger traffic control for paving, pipe replacement and tree removal. Mobile work zones for mowing and pavement patching. Monday to Friday from 7:30 a.m. to 3 p.m. HIGHLAND COUNTY

3 (NEW) Various roads Mobile work zones for mowing at various locations. Monday to Friday from 7:30 a.m. to 3 p.m. Route 608 (Ravens Run Road) Stop and proceed traffic and flaggers as needed on weekdays for bridge work near intersection with Route 220 (Jackson River Road). Through June 27. Route 640 (Meadowdale Road/Blue Grass Valley Road) Mobile work zone for patching operations at various locations. Monday to Friday from 7:30 a.m. to 3 p.m. (NEW) Various roads Mobile work zones for mowing and grading at various locations. Monday to Friday from 7:30 a.m. to 3 p.m. AUGUSTA COUNTY INTERSTATE 64 Mile marker 87 to 100, eastbound and westbound Overnight left lane closures for mowing, 8 p.m. to 6 a.m. through June 2. Daytime right shoulder closures for mowing from 12 noon to 8 p.m. through June 2. (NEW) Mile marker 94 to 88, westbound Right shoulder closures for shoulder repairs, June 4-6 from 8 a.m. to 4:30 p.m. (UPDATE) Mile marker 205 to 237, northbound and southbound Overnight left lane closures for mowing, 8 p.m. to 6 a.m. through June 10. Daytime right shoulder closures for mowing/trimming and litter pickup, 7 a.m. to 8 p.m. through June 10. (NEW) Mile marker 217 to 219, northbound and southbound Right shoulder closures for sign installation, June 4-15 from 9 a.m. to 3 p.m. (NEW) Mile marker 227 to 237, northbound Overnight right lane closures for pavement marker installation, June 5-7 from 3 a.m. to 6 a.m. (NEW) Mile marker 237 to 231, southbound Overnight single lane closures with temporary ramp closures for milling, paving and pavement marking. Monday through Friday nights from 8 p.m. to 7 a.m. through October (NEW) Route 262 (Woodrow Wilson Parkway) Flagger controlled lane closures just east of I-81 for bridge work over Lewis Creek. June 4-8 from 7 a.m. to 5 p.m. (NEW) Route 42 (Little Calfpasture Highway) Single lane closures for guardrail work between Route 703 (Hewitt Road) and Route 685 (Lehigh Road). June 4-18 from 6 a.m. to 8 p.m. Route 610 (Howardsville Turnpike) Road closed to through traffic through summer 2018 between Route 912 (Hodge Street) and Route 660 (Lake Road) for roadway and utility work. Route 912 and Route 660 will serve as detour routes. Residents will have access to Route 610 with flagger traffic control. Route 742 (Willow Spout Road) Flagger controlled alternating lane closures for pipe installations and tree removal from Route 11 (Lee Highway) to Route 744 (Leaport Road) as part of a Rural Rustic repair project. Through September 28 from 8 a.m. to 4 p.m.

4 Route 744 (Leaport Road) Flagger controlled alternating lane closures for pipe installations and tree removal from Route 616 (Morningside Drive) to Route 781 (Bald Rock Road) as part of a Rural Rustic repair project. Through September 28 from 8 a.m. to 4 p.m. Route 840 (Old Churchville Road) Road closed through June 5 between east and west intersections of Route 250 (Churchville Avenue) for box culvert installation. Follow posted detours. ROCKINGHAM COUNTY (UPDATE) Mile marker 252 to 253, northbound Overnight right lane closures for paving operations, May 30-June 2 from 8 p.m. to 7 a.m. (NEW) Mile marker 257 to 262, northbound Overnight right lane closures for pavement patching, June 5-9 from 8 p.m. to 5 a.m. Mile marker 259 to 261, northbound Overnight right lane closures for paving operations, May 31- June 4 from 8 p.m. to 7 a.m. (UPDATE) Mile marker 262 to 263, northbound Overnight right lane closures for paving operations, May 30-June 2 from 8 p.m. to 7 a.m. (NEW) Route 11 (Lee Highway) Flagger and pilot-truck traffic control for paving and pavement marking from Augusta County line to Mount Crawford town limits. June 7-15 from 7 a.m. to 7 p.m. (NEW) Route 33 (Town of Elkton) Alternating lane closures for bridge work over Fifth Street and Norfolk Southern railway. June 4-July 13 from 7 a.m. to 5 p.m. (NEW) Route 33 (Spotswood Trail) Short duration closure for utility-line crossing near intersection with Route 276 (Cross Keys Road), June 5 from 9 a.m. and 10 a.m. Route 257 (Ottobine Road) Signal-controlled single-lane traffic during bridge replacement. Vehicles limited to 13 feet in width. Estimated project completion December Route 602 (East Point Road/Maryland Avenue) Bridge rehabilitation. Temporary signals control traffic across bridge over South Fork Shenandoah River, at Page county line near town of Shenandoah. Vehicle width restriction of 10 feet. Estimated completion of project November Route 636 (Cub Run Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 602 (Point Road) to dead end. Through June 6 Route 672 (Pineville Road) Flagger traffic control for pavement operations from Route 253 (Port Republic Road) to Route 655 (Lawyer Road). Weekdays June 1-7 from 7 a.m. to 7 p.m. Route 715 (Kettle View Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 636 (Runkles Gap Road) to dead end. Through June 6 Route 738 (Dry River Road, Bridgewater area) Road closed to all traffic (including pedestrians and bicycles) south of Route 257 during bridge and intersection construction. Follow posted detour. Estimated project completion December (UPDATE) Route 772 (Greenmount Road) Flagger traffic control for pavement operations from Route 910 to Route 42. Weekdays through June 5 from 7 a.m. to 7 p.m. Route 856 (Park Way) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 340 (East Side Highway) to dead end. Through June 5 Route 867 (North River Road, Mount Crawford area) Road closed for bridge replacement over Pleasant Run through fall Follow posted detours. Route 884 (Homestead Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 340 (East Side Highway) to dead end. Through June 5

5 Route 988 (Scholars Road) Temporary causeway with 24/7 Stop & Proceed traffic pattern during Pleasant Run bridge replacement, through July 6. Work zone between Route 704 (Cecil Wampler Road) and Route 989 (Valley Branch Road). PAGE COUNTY Route 340 Overnight flagger traffic control for shoulder widening and guardrail replacement between Luray town limits and Warren County line. Sunday-Thursday from 6 p.m. to 6 a.m. through June 30. Route 602 (East Point Road/Maryland Avenue) Bridge rehabilitation. Flaggers or temporary signals control traffic on both sides of the bridge over South Fork Shenandoah River, at Rockingham County line near town of Shenandoah. Vehicle width restriction of 10 feet. Estimated completion of project November Route 611 (Vaughn Summit Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 654 (Sunnyview Drive) to Route 605 (Beahm Lane). Through June 5 from 5:30 a.m. to 9:30 p.m. Route 612 (Rocky Branch Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 658 (Shenk Hollow Road) to Rocky Branch Road. Through June 6 from 5:30 a.m. to 9:30 p.m. Route 615 (Serenity Ridge Road) Intermittent lane closures with flagging operations for Rural Rustic Road project from Route 615 (Egypt Bend Road) to dead end. Through August 31 from 7 a.m. to 4:30 p.m. Route 654 (Mims Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 660 (Kibler Hill Road) to Route 611 (Vaughn Summit Road). Through June 6 from 5:30 a.m. to 9:30 p.m. Route 658 (Rocky Branch Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 674 (Red Church Road) to national park boundary. Through June 5 from 5:30 a.m. to 9:30 p.m. Route 660 (Springfield Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 656 (Hulse Road) to dead end. Through June 6 Route 666 (Batman Hill Road) Pilot truck/flagger controlled traffic for surface treatment and line painting at Route 612 (Rocky Branch Road) to end of hard surface. Through June 6 from 5:30 a.m. to 9:30 p.m. SHENANDOAH COUNTY Mile marker 275 to 276, northbound Overnight single lane closures as needed for paving operations, 8 p.m. to 7 a.m. through June 5. (NEW) Mile marker 281 to 274, southbound Overnight single lane closures as needed for paving operations, June 4-6 from 8 p.m. to 7 a.m. (NEW) Mile marker 297 to 298, northbound and southbound Overnight single lane closures for bridge inspection over Norfolk Southern railway, 8 p.m. June 6 to 7 a.m. June 7.

6 (UPDATE) Route 11 (Old Valley Pike) Alternating lane closures as needed for soil testing at multiple locations between Strasburg and Toms Brook, June 4-8 from 8 a.m. to 5 pm. Route 11 Single lane traffic for Cedar Creek Bridge replacement between Route 629 (Oranda Road) in Shenandoah County and Route 840 (Water Plant Road) in Warren County. Northbound traffic use right lane of new Cedar Creek bridge. Southbound traffic uses right lane of the existing southbound bridge. Traffic pattern in place through mid-june. Speed limit 35 miles an hour. Estimated project completion summer Route 600 Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 11 (Old Valley Pike) to Route 642 (Swartz Road). Through June 7 Route 625 (Harman Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 643 (Swartz Road) to Route 11 (Old Valley Pike). Through June 7 from 5:30 a.m. to 9:30 p.m. Route 628 (Middle Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 606 (Gap Road) to Frederick County line. Through June 8 Route 642 (Country Brook Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 653 (Brook Creek Road) to Route 641 (Mount Olive Road). Through June 7 from 5:30 a.m. to 9:30 p.m. Route 653 (Brook Creek Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 623 (Back Road) to Route 11 (Old Valley Pike). Through June 7 from 5:30 a.m. to 9:30 p.m. Route 657 Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 642 (Dean Road) to Route 1505 (Baer Oak Drive). Through June 7 Route 720 (Wissler Road) Closed to through traffic at Meems Bottom covered bridge just west of Route 11. Various roads Flagger traffic control for utility tree trimming. Monday to Friday during daylight hours. FREDERICK COUNTY (NEW) Mile marker 311 to 312, northbound Overnight single-lane closures as needed for paving operations, June 5-7 from 8 p.m. to 7 a.m. (UPDATE) Mile marker 325 to 317, southbound Overnight single-lane closures as needed for paving operations, June 5-8 from 8 p.m. to 7 a.m. Route 11 Flagger traffic control for pavement marking from Winchester northern city limit to end of divided highway (2 miles north of Winchester), from 7 a.m. to 5 p.m. through June 24. Route 11 Flagger traffic control for pavement marking from Reliance Road to Winchester southern city limit, 8 a.m. to 6 p.m. Monday-Friday through June 30. (NEW) Various roads Mobile work zones for line painting, Monday to Friday during daylight hours through June 13. Route 634 (Cougill Road, Middletown) Road closed through July 25 between Route 11 and Route 635 (Mineral Street) for the installation of water and sewer lines. Follow posted detour.

7 (NEW) Route 649 (Springdale Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 648 (Passage Road) to Route 11 (Valley Pike). June 8-15 from 5:30 a.m. to 9:30 p.m. (NEW) Route 672 (Hopewell Road) Overnight single lane closures for maintenance of bridge over I- 81 (exit 321, Clearbrook), June 4-13 from 8 p.m. to 7 a.m. (NEW) Route 880 (Development Lane) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 651 (Shady Elm Road) to dead end. June 8-15 (NEW) Various roads Mobile work zones for line painting, Monday to Friday during daylight hours through June 13. Various roads Flagger traffic control for utility tree trimming. Monday to Friday during daylight hours. CLARKE COUNTY No lane closures reported. Route 610 Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 340 (Lord Fairfax Highway) to Dairy Lane. Through June 6 (UPDATE) Route 620 (Pyletown Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 655 (Salem Church Road) to Route 340 (Lord Fairfax Highway). June 7-14 (UPDATE) Route 627 (Carters Lane Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 622 (Bordens Spring Road) to Route 658 (White Post Road). June 6-13 (UPDATE) Route 628 (Berrys Ferry Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 658 (White Post Road) to Route 626 (Nelson Road). June 6-13 from 5:30 a.m. to 9:30 p.m. (UPDATE) Route 631 (Page Brook Lane) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 723 (Old Winchester Road) to dead end. June 7-14 from 5:30 a.m. to 9:30 p.m. (UPDATE) Route 634 (Salem Church Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 655 (Opequon Road) to Route 657 (Senseny Road). June 7-14 (UPDATE) Route 644 (Gun Barrel Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 340 (Lord Fairfax Highway) to Route 655 (Parkins Mill Road). June 7-14 (UPDATE) Route 646 (Nations Spring Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Frederick County line to Route 644 (Gun Barrel Road). Through June 6-13 (UPDATE) Route 655 (Ginns Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 644 (Parkins Mill Road) to Route 723 (Old Winchester Road). June 7-14 from 5:30 a.m. to 9:30 p.m. (UPDATE) Route 655 (Opequon Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 634 (Salem Church Road) to Frederick County line. June 7-14 from 5:30 a.m. to 9:30 p.m.

8 (UPDATE) Route 658 (Rockland Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Warren County line to Route 644 (Featherbed Road). June 6-13 from 5:30 a.m. to 9:30 p.m. (UPDATE) Route 669 (Highland Corners Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 340 (Lord Fairfax Highway) to Route 522 (Stonewall Jackson Highway). June 6-13 (UPDATE) Route 670 (Double Tollgate Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 669 (Highland Corners Road) to Route 340 (Lord Fairfax Highway). June 6-13 Route 761(Old Charles Town Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 632 (Crums Church Road) to West Virginia state line. Through June 7 from 5:30 a.m. to 9:30 p.m. Various roads Flagger traffic control for utility tree trimming. Monday to Friday during daylight hours. WARREN COUNTY INTERSTATE 66 No lane closures reported. No lane closures reported. Route 11 Traffic pattern change for Cedar Creek Bridge replacement between Route 629 (Oranda Road) in Shenandoah County and Route 840 (Water Plant Road) in Warren County: Northbound traffic will use the right lane of the new Cedar Creek bridge. Southbound traffic will use the right lane of the existing southbound bridge. Through mid-june. Work zone speed limit 35 miles an hour. Estimated project completion summer Route 340 (Stonewall Jackson Highway) Overnight guardrail replacement from Page/Warren county line to Route 619 (Rivermont Drive), 6 p.m. to 6 a.m. through June 30. (UPDATE) Route 609 (Ritenour Hollow Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 637 (Guard Hill Road) to Route 627 (Reliance Road). June 5-12 Route 610 (Bucks Mill Road) Pilot truck/flagger controlled traffic for surface treatment and line painting at Andrews Road. Through June 8 (UPDATE) Route 611 (Long Meadow Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 840 (Water Plant Road) to Route 637 (North River Road). June 4-11 (UPDATE) Route 627 (Reliance Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Frederick County line to Route 340/522. June 5-12 (UPDATE) Route 637 (Guard Hill Road/Cauthorn Mill Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 340/522 to Route 854 (Buckhorn Road). June 4-18 from 5:30 a.m. to 9:30 p.m. Route 664 (Whipporwill Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 55 (Strasburg Road) to dead end. June 1-8

9 Route 840 (Water Plant Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Frederick County line to Route 611 (Gafia Lodge Road). June 1-8 from 5:30 a.m. to 9:30 p.m. Route 842 (Forest Grove Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 612 (Gafia Lodge Road) to Route 611 (Long Meadow Road). June 1-8 from 5:30 a.m. to 9:30 p.m. (NEW) Route 854 (Buckhorn Road) Pilot truck/flagger controlled traffic for surface treatment and line painting from Route 637 (Cauthorn Mill Road) to dead end. June 5-12 Various roads Flagger traffic control for utility tree trimming. Monday to Friday during daylight hours. Vegetation management may take place district wide on various routes. Motorists are reminded to use extreme caution when traveling through work zones. Traffic alerts and traveler information can be obtained by dialing 511. Traffic alerts and traveler information also are available at The VDOT Customer Service Center can assist with reporting road hazards, asking transportation questions, or getting information related to Virginia s roads. Call 800-FOR- ROAD ( ) or use its mobile friendly website at Agents are available 24 hours-a-day, seven days a week. The Staunton District Twitter feed is VDOT can be followed on Facebook, Flickr, Twitter and YouTube. RSS feeds are also available for statewide information. The VDOT Web page is located at (END)

TRAFFIC ALERT FOR JUNE 25-29, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR JUNE 25-29, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE June 22, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 100 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 2, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-042 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 23, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 057 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 21, 2017 CONTACT: Sandy Myers 540-332-9201 (office) STA17-204 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE January 11, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-007 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 7, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 187 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 1, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 020 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR APRIL 23-27, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR APRIL 23-27, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE April 20, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-065 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR OCTOBER 15-19, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR OCTOBER 15-19, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE October 12, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 167 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR SEPTEMBER 17-21, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR SEPTEMBER 17-21, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE September 14, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 149 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

TRAFFIC ALERT FOR SEPTEMBER 10-14, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR SEPTEMBER 10-14, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE September 7, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 148 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell) RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Aug. 10, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT August 12 August 18, 2018 All

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

FOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, SALEM 69

FOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, SALEM 69 FOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, 540-387-5238 SALEM 69 Jen.Ward@vdot.virginia.gov - The following is a list of forecasted highway projects that may impact traffic traveling

More information

Road Construction Ahead January-April 2015 NORTHWEST REGION

Road Construction Ahead January-April 2015 NORTHWEST REGION NORTHWEST REGION 1 Interstate 64 Augusta, Nelson, Albemarle counties: Installing communications conduit in median for active traffic management system on Afton Mountain. Periodic left-shoulder closures,

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016 RELEASE: IMMEDIATE June 10, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth) RELEASE: IMMEDIATE March 8, 2019 CONTACT: Tina.Bundy 540-907-8325 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 10 March 16, 2019 All work is scheduled weather permitting. Real-time information

More information

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT CONTACT: VDOT Customer Service 1-800-367-7623 November 18, Richmondinfo@VDOT.virginia.gov WEEKLY HIGHWAY ALERT RICHMOND DISTRICT COLONIAL HEIGHTS Below is a forecast of road construction that is expected

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

PennDOT Interstate Work next week March 30-April 3:

PennDOT Interstate Work next week March 30-April 3: PennDOT Interstate Work next week March 30-April 3: Interstate 80 Interstate 81 DELAYS THIS WEEK: Exit 256 to the Schuylkill County line. Eastbound & Westbound. Bridge cleaning Monday (3/30), Tuesday (3/31)

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/5/2018 2:12:06 PM

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/5/2018 2:12:06 PM OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS Incidents/: 9/5/2018 2:12:06 PM ROUTE ORE99EB 2 3 @ Salem, Hyacinth/Verda Hwy100 15 22 7 Mi W of Ainsworth St Park Southbound

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 10/11/2018 5:24:09 PM

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 10/11/2018 5:24:09 PM OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS Incidents/: 10/11/2018 5:24:09 PM ROUTE Hwy100 15 22 7 Mi W of Ainsworth St Park Closure Information Westbound (Right

More information

Weekly East Tennessee Construction Report for May 31-June 6, 2018

Weekly East Tennessee Construction Report for May 31-June 6, 2018 Weekly East Tennessee Construction Report for May 31-June 6, 2018 Thursday, May 31, 2018 01:30pm ANDERSON COUNTY, SR 62 between Union Valley Road and SR 162: Motorists should be alert for possible lane

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Sierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS

Sierra Roadwork Schedule Sunday through Saturday, October 1-7, 2017 LONG-TERM PROJECTS Date: September 29, 2017 #17-292 District: District 3 - Marysville, www.dot.ca.gov/dist3 Amarjeet S. Benipal, District Director Contact: Liza Whitmore, liza.whitmore@dot.ca.gov Phone: Office: (530) 634-7640

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012 Today s Date: Friday, September 7, 2012, #12-255 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov 530. 741.4566

More information

Ohio Department of Transportation Construction Update

Ohio Department of Transportation Construction Update Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District

More information

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK

More information

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/14/ :00:05 PM

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/14/ :00:05 PM OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS Incidents/: 9/14/2018 10:00:05 PM ROUTE Hwy100 15 22 7 Mi W of Ainsworth St Park Closure Information Westbound (Right

More information

Important Lane Closures March 1 5, 2010

Important Lane Closures March 1 5, 2010 February 26, 2010 CONTACT: Marcia McAllister 703 572 0506 marcia.mcallister@dullesmetro.com Important Lane Closures March 1 5, 2010 C aisson Load Test Scheduled for Mar. 3 Crews will perform another load

More information

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT HIGHWAY ALERT VirginiaDOT.org CONTACT: Public Affairs Jan. 9, 2009 Richmondinfo@VirginiaDOT.org WEEKLY HIGHWAY ALERT RICHMOND DISTRICT COLONIAL HEIGHTS Road construction that is expected to cause delays

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

MEMORANDUM. FROM: John A. Bishop, AICP, Assistant Director - Transportation. May 22, 2017 Transportation Committee Meeting

MEMORANDUM. FROM: John A. Bishop, AICP, Assistant Director - Transportation. May 22, 2017 Transportation Committee Meeting COUNTY of FREDERICK Department of Planning and Development 540/ 665-5651 Fax: 540/ 665-6395 MEMORANDUM TO: Frederick County Transportation Committee FROM: John A. Bishop, AICP, Assistant Director - Transportation

More information

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT HIGHWAY ALERT VirginiaDOT.org CONTACT: Public Affairs Jan. 5, 2009 Richmondinfo@VirginiaDOT.org WEEKLY HIGHWAY ALERT RICHMOND DISTRICT COLONIAL HEIGHTS Road construction that is expected to cause delays

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties

* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties New York State Department of Transportation 2008 Highway/Bridge Construction Projects * Short term resurfacing projects are not included in this listing. Genesee 4T39.07 Project: Annual Rural County Sign

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

Florida Department of Transportation MIKE DEW SECRETARY

Florida Department of Transportation MIKE DEW SECRETARY RICK SCOTT GOVERNOR Florida Department of Transportation MIKE DEW SECRETARY July 5, 2018 JoAnn May, 239-225-1900 JoAnn.May@dot.state.fl.us DISTRICT ONE NORTHERN COUNTIES ROADWATCH REPORT #27 FOR WEEK OF

More information

October 31, 2014 Chuck McGinness, (954)

October 31, 2014 Chuck McGinness, (954) From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October

More information

El Dorado County / Tahoe Roadwork Schedule

El Dorado County / Tahoe Roadwork Schedule Today s Date: October 28, 2011 #11-267 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov (530) 741-4566 desk

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road T 1800 997 057 (free call) E enquiries@northconnex.com.au PO Box 343 Pennant Hills NSW 1715 northconnex.com.au 28 April 2017 Ref: N0075M Night work update: and westbound on ramp at Dear resident, NorthConnex

More information

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness, From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY

More information

State Project Reconstruction I-84

State Project Reconstruction I-84 State Project 151-273 Reconstruction I-84 Waterbury, Connecticut FROM WASHINGTON STREET TO PIERPONT ROAD I-84 Constructors J.V. Robert Turner Area Engineer Ken Fargnoli District Engineer John Dunham Assistant

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Florida Department of Transportation ERIK FENNIMAN INTERIM SECRETARY

Florida Department of Transportation ERIK FENNIMAN INTERIM SECRETARY RICK SCOTT GOVERNOR Florida Department of Transportation ERIK FENNIMAN INTERIM SECRETARY November 29, 2018 Brian R. Rick, 863-519-2828 Brian.Rick@dot.state.fl.us DISTRICT ONE NORTHERN COUNTIES ROADWATCH

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane

More information

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

MONTANA CONSTRUCTION REPORT 06 / 14 / 2016

MONTANA CONSTRUCTION REPORT 06 / 14 / 2016 MONTANA CONSTRUCTION REPORT 06 / 14 / 2016 ROAD INCIDENTS DUE TO FIRES AND FLOODING PLEASE CHECK OUR WEBSITE FOR MORE UP TO DATE CLOSURES AND INFORMATION http://www.mdt.mt.gov/travinfo/scripts/alerts.pl

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

WEEKLY PROVINCIAL HIGHWAY CONSTRUCTION UPDATE FOR THURS., AUG. 25, 2016 The law is black and white. Slow to 60 km/hr in Work Zones.

WEEKLY PROVINCIAL HIGHWAY CONSTRUCTION UPDATE FOR THURS., AUG. 25, 2016 The law is black and white. Slow to 60 km/hr in Work Zones. WEEKLY PROVINCIAL HIGHWAY CONSTRUCTION UPDATE FOR THURS., AUG. 25, 2016 The law is black and white. Slow to 60 km/hr in Work Zones. NEW WORK PROJECT/WORK: Highway 1 near Belle Plaine ESTIMATED COST: $5.1

More information

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County Construction Update Contact: The District Two Public Information Office at (419) 373-4428 or email D02.PIO@dot.ohio.gov For Immediate Release Thursday, October 18, 2018 ODOT District Two Construction Update

More information

2 Construction Program

2 Construction Program 2018 C P 2018 Districtonstruction 2 Construction Program rogram district 2 Governor John Kasich ODOT Director Jerry Wray District Deputy Director Pat McColley, PE, SI 2018 Construction Program Thank you

More information

Ocean Way at U.S. #1 (Town of Jupiter) Installation of a new traffic signal.

Ocean Way at U.S. #1 (Town of Jupiter) Installation of a new traffic signal. PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: FEBRUARY 13, 2013 STATUS FOR FEBRUARY 18, 2013 THROUGH FEBRUARY 24, 2013 *** CONSTRUCTION WORK ZONES ADDED

More information

Ohio Department of Transportation Traffic Advisory. District 4 Allen C. Biehl, P.E., Deputy Director S. Arlington Road.

Ohio Department of Transportation Traffic Advisory. District 4 Allen C. Biehl, P.E., Deputy Director S. Arlington Road. Ohio Department of Transportation Traffic Advisory District 4 Allen C. Biehl, P.E., Deputy Director 2088 S. Arlington Road. Akron, Ohio 44306 www.transportation.ohio.gov/dist4 Friday, September 18, 2015

More information

WEEKLY PROVINCIAL HIGHWAY CONSTRUCTION UPDATE FOR THURSDAY, OCTOBER 6, 2016 The law is black and white. Slow to 60 km/hr in Work Zones.

WEEKLY PROVINCIAL HIGHWAY CONSTRUCTION UPDATE FOR THURSDAY, OCTOBER 6, 2016 The law is black and white. Slow to 60 km/hr in Work Zones. NEW WORK PROJECT/WORK: Highway 354 near Dilke ESTIMATED COST: $3.4M START OF THIS YEAR'S CONSTRUCTION: October 1, 2016 DESCRIPTION: About 17 km of surfacing on Highway 354 from the junction with Highway

More information

Culpeper District. Albemarle County Monthly Report December 2011

Culpeper District. Albemarle County Monthly Report December 2011 Culpeper District Albemarle County Monthly Report Special Issues Construction Significant Accomplishments (as of 11/15/11) Georgetown Road completed on November 8. I-64 Eastbound Shadwell Exit completed

More information

Culpeper District. Albemarle County Monthly Report. September 2012

Culpeper District. Albemarle County Monthly Report. September 2012 Culpeper District Albemarle County Monthly Report September 2012 Special Issues Bridges on Route 745, Arrowhead Valley Road The road will be closed at the Rail Road Bridge on the southern end of the road

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015 From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015

More information

Road widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected.

Road widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected. PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: SEPTEMBER 12, 2012 STATUS FOR SEPTEMBER 17, 2012 THROUGH SEPTEMBER 23, 2012 *** CONSTRUCTION WORK ZONES ADDED

More information

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April New M5 Work notification 4 April 2018 Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April A significant amount

More information

Florida Department of Transportation Daniels Parkway Fort Myers, FL 33913

Florida Department of Transportation Daniels Parkway Fort Myers, FL 33913 RICK SCOTT GOVERNOR Florida Department of Transportation 10041 Daniels Parkway Fort Myers, FL 33913 MIKE DEW SECRETARY July 27, 2017 JoAnn May, 239-225-1900 JoAnn.May@dot.state.fl.us DISTRICT ONE DISTRICTWIDE

More information

District Construction Progr am. John R. Kasich, Ohio Governor Jerry Wray, ODOT Director Steve Mary, P.E., District Deputy Director

District Construction Progr am. John R. Kasich, Ohio Governor Jerry Wray, ODOT Director Steve Mary, P.E., District Deputy Director District 8 2014 Construction Progr am Preble Greene Butler Warren Clinton Lebanon Hamilton Clermont Serving Butler, Clermont, Clinton, Greene, Hamilton, Preble and Warren Counties. John R. Kasich, Ohio

More information

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage

More information

Attachment A - FY 2018 Revenue Sharing Program Allocations - Approved

Attachment A - FY 2018 Revenue Sharing Program Allocations - Approved Attachment A - - Approved Name Bristol District Wytheville Town East Main Street 107236 $315,000 Lithia Road Withers Road/Cassell Road Wytheville Town (summary) $315,000 Culpeper District Charlottesville

More information

5.1 Traffic and Transportation

5.1 Traffic and Transportation 5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the

More information

PROGRESS PARK CONNECTOR

PROGRESS PARK CONNECTOR PROGRESS PARK CONNECTOR Project No. 9999 098 R65, P102 ALTERNATIVES ANALYSIS 6 April 2015 Revised for updated dates PROGRESS PARK CONNECTOR ROAD ALTERNATIVES ALTERNATIVE # 1 West from the intersection

More information

Springettsbury Township. Road Improvement Projects

Springettsbury Township. Road Improvement Projects Springettsbury Township Road Improvement Projects 2009 2016 2016 Township Road Improvement Projects Springettsbury Township is divided into the following 4 Sectors: Northwest Sector Sherman Street Route

More information

AWARD INTERSTATE. Bid Amount: Less Than 5 Million. Report created on : 4/20/18. Letting Date: 3/28/2018. Estimated Construction Cost.

AWARD INTERSTATE. Bid Amount: Less Than 5 Million. Report created on : 4/20/18. Letting Date: 3/28/2018. Estimated Construction Cost. : Less Than 5 Million INTERSTATE 202 112417 LOCATION: VARIOUS (NFO)PM2N-060-F18, P401 ADAMS CONSTRUCTION COMPANY 1 $1,418,249.41 $1,440,244.38 ROANOKE PM02458 MONTGOMERY VA SALEM DISTRICT SGR - 2018 PLANT

More information

Weekly construction update

Weekly construction update November 4, 2011 For more information, contact: Kim A. Rudat, Regional Communications Manager Kim.Rudat@dot.wi.gov, (920) 492-5743 For US 41 Expansion Project information, contact: Kris Schuller, US 41

More information

MEMORANDUM VILLAGE OF NORTHBROOK

MEMORANDUM VILLAGE OF NORTHBROOK MEMORANDUM VILLAGE OF NORTHBROOK TO: Staff COPY: Village President & Board of Trustees Department Heads FROM: Richard Nahrstadt, Village Manager DATE: April 29, 2016 SUBJECT: STAFF BRIEFING WEEK OF April

More information

Hospital Link Project Project Update Winter 2018

Hospital Link Project Project Update Winter 2018 Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open

More information

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO Welcome to the Business Owners Task Force Perry Leonard Blagg Tire and Service President/COO Safety: West Nile Virus Alyssa Tenorio NorthGate Constructors Public Information Manager West Nile Virus Carried

More information

DISTRICT CONSTRUCTION PROGRAM PROGRAM DISTRICT CONSTRUCTION

DISTRICT CONSTRUCTION PROGRAM PROGRAM DISTRICT CONSTRUCTION ODOT ODOT DISTRICT 7 2018 CONSTRUCTION DISTRICT 7 PROGRAM 2018 CONSTRUCTION PROGRAM SERVING AUGLAIZE, CHAMPAIGN, CLARK, DARKE, LOGAN, MERCER, MIAMI, MONTGOMERY & SHELBY COUNTIES JOHN R. KASICH, OHIO GOVERNOR

More information

SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER

SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER Proposal to Eliminate Traffic Gridlock in South North York Centre Area With Southbound Yonge Street to Eastbound Highway 401 Fly-UNDER A much

More information

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 May 16, 2014 Chuck McGinness, (954) 777-4090 chuck.mcginness@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 FORT LAUDERDALE -- Construction and maintenance-related lane

More information

3529 Souris River Flood Plan (Phase MI-1)

3529 Souris River Flood Plan (Phase MI-1) Date: September 28, 2018 To: Derek Hackett, Public Information Officer From: Grant Goldader, Civil Engineering Specialist Re: Traffic Control Report for the week of 10/01/2018 3529 Souris River Flood Plan

More information

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE

More information

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects Pittsburgh - PennDOT is pleased to announce the 2016 Allegheny County transportation improvement project list for state-owned

More information

SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY

SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY WEEK ENDING FEBRUARY 1, 2019 SECTION 55A1 ROBINSON TOWNSHIP IN WASHINGTON COUNTY Contractor: Independence Excavating Inc. 1. Work Shift Day shift (M-F), with Saturday as a makeup day. 2. Traffic The new

More information

ODOT DISTRICT CONSTRUCTION PROGRAM JOHN R. KASICH, OHIO GOVERNOR JERRY WRAY, ODOT DIRECTOR HOWARD HUEBNER, DISTRICT DEPUTY DIRECTOR

ODOT DISTRICT CONSTRUCTION PROGRAM JOHN R. KASICH, OHIO GOVERNOR JERRY WRAY, ODOT DIRECTOR HOWARD HUEBNER, DISTRICT DEPUTY DIRECTOR ODOT DISTRICT 3 2017 CONSTRUCTION PROGRAM Crawford Richland SERVING ASHLAND, CRAWFORD, ERIE, HURON, LORAIN, MEDINA, RICHLAND AND WAYNE COUNTIES Erie Lorain Huron Medina Ashland Wayne JOHN R. KASICH, OHIO

More information

PennDOT MAJOR ROAD PROJECTS

PennDOT MAJOR ROAD PROJECTS 1 file:lancastercountyroadwork Revision #1 Page 1. Lancaster County Road Work Mar 03 through Mar 07 www.co.lancaster.pa.us/planning Prepared by LCPC - Transportation Division Notes: >Headlights: Must be

More information