Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018
|
|
- Branden Stone
- 5 years ago
- Views:
Transcription
1 Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd,
2 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance Facility: Hensel Phelps Herzog (HPH) 8.5-mile light-rail line 8 new stations: 3 underground 4 at-grade One aerial Project budget: $2.058 billion Scheduled Opening: Fall
3 Los Angeles County Metropolitan Transportation Authority Project Labor Agreement (PLA) / Construction Careers Policy (CCP) Update Crenshaw/LAX Transit Corridor Project Report Data Through January 2018 Reporting Period
4 Crenshaw/LAX Transit Corridor Project PLA Targeted Worker Attainment: Prime: Walsh/Shea No. of Work Hours* Report Data Through January 2018 Targeted Economically Disadvantaged Worker Utilization (%) Goal: 40% Apprentice Utilization (%) Goal: 20% 4,121, % 22.84% Based on Total Apprenticeable Work Hours Disadvantaged Worker Utilization (%) Goal: 10% 12.29% Percentage Project Complete Based on Worker Hours: 95.18% (rounded) Executive Order Demographic Summary No. of Work Hours* African American Utilization Asian/Pacific Islander Utilization Caucasian Utilization Hispanic Utilization Native American Utilization Other/Declined to state Minority Utilization Goal: 28.3% (rounded) Female Utilization Goal: 6.9% 4,121, % 1.25% 22.13% 60.88% 1.27% 2.14% 75.72% 3.48% *Cumulative Hours Through End of Noted Reporting Period as Reported by Prime Contractor. Data subject to change to reflect updates or audits.
5 Crenshaw/LAX Transit Project Southern Segment Update Four New Stations Three At-Grade One Aerial Five Aerial Structures One Underground Structure 5
6 Fairview Heights Station New station canopy placed 6
7 Downtown Inglewood Station New station canopy and platform 7
8 Activity Near Downtown Inglewood Station GUIDEWAY - Forming Catch Basin at Florence Ave. and Centinela Ave. 8
9 Bridge Construction View of La Bea Av (Southbound) 9
10 Bridge Construction - La Brea Av Track installation completed 10
11 Bridge Construction Over I-405 Bridge Electrical duct bank concrete prep, deck clean up, and grinding of deck for southbound track plinth pads. 11
12 Bridge Construction Over I-405 Bridge Southbound track plinth pad layout of fasteners. 12
13 Bridge Construction Under I-405 Bridge 13
14 Westchester/Veterans Station 14
15 Westchester/Veterans Station 15
16 Bridge Construction Century Bl Laying track and plinths (metal ties) 16
17 Aviation/Century Station Plaza level service building construction 17
18 Aviation/Century Station Stair No. 2 staircase formwork installation in progress. 18
19 Century/Aviation Station Conceptual Rendering A conceptual rendering of the Century/Aviation Station 19
20 Century/Aviation Station Canopy Progress 20
21 Underground Segment 1 Underground segment transitioning to bridge over 111 th St. 21
22 Underground Segment 1 (UG1) Underground segment adjacent to LAX tarmacs 22
23 Green Line Tie-In Activity 23
24 Green Line Tie-In Activity 24
25 Ongoing Bridge Construction Activity Scheduled Completion* Century Station (Gutters-Canopy) Century Station (Install Stairs) Green Line Bridge (Green Line tie-in track work) April 2018 * April 2018 * April 2018 * * Schedule is subject to change 25
26 Southern Segment Ongoing At-Grade Station Construction Activity Fairview Heights Station: Erect Structural Steel Canopy Downtown Inglewood Station: Glass Canopy Install Westchester Veterans Station: MEP Canopy Westchester Veterans Station: Install Gutters and Catwalks Scheduled Completion * April 2018* May 2018* April 2018* April 2018* * Schedule is subject to change 26
27 Upcoming Inglewood/Westchester Lane Restrictions and Closures Location Tentative Date: Florence Av/Centinela Av (Full Depth Paving) La Cienega Bl/Florence Av (Curb and Gutter) April 2018* April 2018* * Schedule is subject to change 27
28 Southwestern Yard Project Overview Approximately $172 Million Operation and Maintenance Facility 18-acre site located near Los Angeles International Airport Started in May 2016 Finishing in January 2019
29 Southwestern Yard Project Overview
30 Southwestern Yard Project Framing
31 Southern Segment Southwestern Maintenance Yard Construction Activity Scheduled Completion* Exterior Framing Level 1 Restroom Finishes Level 1 Office Finishes Comm. Room Turnover (Milestone) May 2018 * April 2018* April 2018* April 2018 * * Schedule is subject to change 31
32 AMC-Airport Metro Connector Project The proposed project includes a new multi-modal transportation center to connect LAX to the regional bus and rail transit system. Project components include: Three at-grade LRT platforms to be served by the Crenshaw/LAX Line and a service extension of the Metro Green Line Bus plaza and terminal facility for Metro and municipal buses Bicycle hub with secured parking Pedestrian plaza Passenger vehicle pick-up and drop-off area Metro transit center/terminal building ( Metro Hub )that connects passengers between the various modes of transportation 32
33 AMC-Airport Metro Connector Project Conceptual Rendering A r b o r V i t a e S t Aviation Bl 33
34 AMC-Station Naming Preliminary outreach in form of briefings and presentation will be held with key stakeholder to inform and educate them about the station naming process and timeline. Outreach briefings will begin in early April 2018 and conclude in early May Key stakeholders include (but not limited to): Metro Directors LA Councilman Mike Bonin/Inglewood Mayor James Butts Los Angeles World Airports (LAWA) LAX Coastal Chamber of Commerce Inglewood Stakeholders (Chamber, Commissions, Block Clubs) Westchester/Playa Del Rey Neighborhood Council Crenshaw/LAX Community Leadership Council 34
35 First/Last Mile Outreach First/Last Mile seeks to improve the experience of current, former, and future transit riders accessing our system through walking and biking infrastructure and other mobility support services through an open and community-based process. Public meetings to be scheduled Spring
36 Crenshaw/LAX Transit Project Northern Segment Update Northern Segment - Expo/Crenshaw Bl to 67 th St Four new stations Three underground One at-grade Underground structures Duel parallel bored tunnels Cut and Cover tunnel One mile at-grade segment 36
37 Underground Station Construction Station construction ongoing: Expo/Crenshaw Station MLK Jr. Station Leimert Park Station Construction work activities: Concrete pours of station floors and walls Concourse level installation Installation of station facilities *Anticipated completion in 2019 Concrete finish for the SB Tunnel Walkway. 37
38 Underground Station Construction (cont.) Upcoming street restoration and backfill for underground stations/structures Anticipated to begin Summer 2018 Preliminary schedule calls for extended closures in the following areas: Expo/Crenshaw Station Exposition Bl to Coliseum MLK Jr. Station King Bl to Stocker Leimert Park Station 43 rd St/Homeland to Vernon Av Station portal in Leimert Park 43 rd St/Homeland to 48 th St 38
39 Underground Station Construction Expo/Crenshaw Station Installing rebar for invert level wall section 39
40 Expo/Crenshaw Station Conceptual Rendering Crenshaw/Expo Station 40
41 Underground Station Construction MLK/Crenshaw Station Installing waterproofing along the west concourse level walls 41
42 Crenshaw/MLK Jr Station Conceptual Rendering Crenshaw/MLK Jr Station 42
43 Underground Station Construction Leimert Park Station Newly formed concourse level columns and walls Installation of formwork for center wall section of tunnel south of Leimert Park Station 43
44 Underground Station Construction Leimert Park Station Backfill and compaction activities behind wall section. 44
45 Leimert Park Station Conceptual Rendering * Leimert Park Station 45
46 Tunnel between MLK Station and Leimert Park Station 46
47 Cross Passage Construction Five total cross passages for underground tunnel Underground access for emergency and maintenance Located between Rodeo Pl and 43 rd St 47
48 Cross Passage Construction Installation of handrail along the tunnel adjacent to cross passage #4. 48
49 At Grade Segment - Park Mesa Heights North and Central Segments: 48 th St to 59 th St Future Hyde Park station platform work activities. Scope of Work: New sidewalks and driveways Updated/new street lights and traffic signals New roadway surface/rehabilitation New Hyde Park Station New landscaped center medians Rail safety enhancements Crenshaw Bl Streetscape Plan elements: New sidewalk trees New lighting New crosswalks 49
50 At Grade Segment - Park Mesa Heights North and Central Segments: 48 th St to 59 th St (cont.) Remaining Construction Work Slauson Widening ongoing Hyde Park Station and guideway construction on-going Some on-going utility and electrical work At-grade crossings at all intersections Street resurfacing/full depth construction Landscaping Impacts Long term traffic reconfiguration Frequent lane closures Pedestrian access occasionally restricted & rerouted Temporary bus stop/route relocations Park Mesa backfill along northbound ballast walls 48 th - 59 th 50
51 At Grade Segment - Park Mesa Heights North and Central Segments: 48 th St to 59 th St (cont.) At-grade Crossings Rail track placement across all intersections Utility protection Overhead cable installation Impacts Cross traffic restriction across Crenshaw Bl Some Crenshaw lane closures Pedestrian sidewalk closures and detours Bus route relocations 51
52 At Grade Segment - Park Mesa Heights North and Central Segments: 48 th St to 59 th St (cont.) Placement of storm drain invert at manhole at Slauson Ave Placement of OCS foundation at 57th St. for the Hyde Park Station 52
53 At Grade Segment - Park Mesa Heights North and Central Segments: 48 th St to 59 th St (cont.) (Placement of curb and gutters at 59 th St) 53
54 At Grade Segment - Park Mesa Heights North and Central Segments: 48 th St to 59 th St (cont.) Typical street block 54
55 At Grade Segment - Park Mesa Heights North and Central Segments: 48 th St to 59 th St (cont.) Slauson Avenue Intersection Widening Slauson Ave. Crenshaw Blvd. 55
56 Hyde Park Station Conceptual Rendering * Hyde Park Station 56
57 Hyde Park Station Canopy Installation 57
58 Hyde Park (59 th to 67 th St.) Tunnel/Cut and Cover Construction Current Construction: Stage C Ongoing tunnel construction, concrete pours, and staging in the center of Crenshaw Bl Frequent lane closures Restoration/backfilling - weekend street closures Scheduled completion:
59 Hyde Park (59 th to 67 th St.) Tunnel/Cut and Cover Construction Installation of rebar dowels for southbound emergency walkway. 59
60 63 th St 60 th St 59 th St Hyde Park (59 th to 67 th St.) Tunnel/Cut and Cover Construction (cont.) Stage C N Insert Table Crenshaw Crenshaw Bl Bl Tunnel construction At-Grade Station 60
61 Hyde Park (59 th to 67 th St.) Tunnel/Cut and Cover Construction (cont.) Cut and cover tunnel merging westward toward Inglewood Cut and cover tunnel in Hyde Park 61
62 Hyde Park Tunnel/Cut and Cover Construction Victoria Av Permanent Closure New cul-de-sac at Victoria Av 62 62
63 Hyde Park Tunnel/Cut and Cover Construction Bynhurst Grade Crossing Grade Crossing 63 63
64 Metro Small Business Pilot Programs Help small mom and pop businesses continue to thrive throughout construction and post construction Metro Business Solution Center (BSC) Metro Business Interruption Fund (BIF) 64
65 Business Solution Center Crenshaw/LAX Transit Project BSC Program Statistics February 23, 2018: Number of business Contacts: 442 Number of business Intakes/Assessments: 335 Number of business referrals: 1088 BSC Business Resources: Hands-on business development Expert business advice and coaching Technical assistance Referrals to expert professionals BSC Areas of Focus: Long term business planning Increasing business access to technology Website development Assessment of IT infrastructure and IT systems Workshops and Events Build Your Business Plan, Yelp 101, Get Your Business Online (sponsored by Google), Accounting Management Learn More: Financial readiness Access to financial capital 65
66 Business Interruption Fund Crenshaw/LAX Transit Project BIF Program Statistics March 16, 2018: BIF applications submitted: 844 BIF applications approved/awarded: 624 BIF applications pending financials: 135 BIF applications deemed not eligible: 83 BIF applications denied: 2 BIF Application Approval Rate: 82.21% BIF Grant Payments: $13,738, Crenshaw/LAX BIF Statistics: 345 grants awarded to C/LAX Total amount: $7,256, small businesses received a grant BIF Project Updates and Areas of Focus: Continued outreach along Crenshaw Corridor areas of: Park Mesa Heights Hyde Park Baldwin Hills Crenshaw Mall Inglewood/Southern Section Ongoing education of program requirements and application process through: application sessions and one-onone meetings Learn More: 66
67 Business Interruption Fund Transit Project Corridors $7,256, Value of BIF Grants Awarded (as of 3/16/18) $3,625, $198, $1,708, $950, Crenshaw/LAX Transit Project 100% Purple Line Extension, Section 1 BIF Measures of Effectiveness (as of CY 2017 Q3) 96% Purple Line Extension, Section 2 88% Regional Connector, Little Tokyo Area Regional Connector, 2nd/Broadway Segment 90% 91% Businesses referred to support services Applications processed within 9 business days Clients satisfaction rating Businesses remaining open after 6 months of grant award Businesses remaining open after 1 year of grant award 67
68 Crenshaw/LAX Transit Project Connect with us Hotline: Web: metro.net/crenshaw Facebook: facebook.com/crenshawrail Twitter: twitter.com/crenshawrail WSCC: 68
Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017
Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 1 Project Overview Mainline Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017
Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationCrenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017
Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017 1 Project Overview Design-Build Contractors: Mainline - Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 1 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)
More informationJune 2017: 700 Piles 9 Weeks and 3 Days Pile Caps / Tie Beams Roof Foundations
Welcome FAA FAA October 2016: Broke Ground October 2016 Excavated 6.2 Million Cubic Yards Excavated 100,000 Cubic Yards in one day at peak 36 30 Yard Scrappers 10 30 Yard Dump Trucks 85 Days to Complete
More informationINVESTMENT HIGHLIGHTS
6821 VICTORIA AVE EXECUTIVE SUMMARY We are pleased to offer for sale a freestanding industrial property located at 6821-6815 S. Victoria avenue in Los Angeles. It was built in 1946 as an electrical components
More informationCRENSHAW BOULEVARD LOS ANGELES, CA 90008
4287 CRENSHAW BOULEVARD LOS ANGELES, CA 90008 HIGHLY VISIBLE RETAIL RESTAURANT FOR SALE COMMERCIAL PROPERTY SUBJECT PROPERTY Back Alley Homeland Drive Crenshaw Boulevard CONTACT: CHARLES DUNN COMPANY,
More informationClaremont Project Background and Update Community Meeting September 11, 2017
Claremont Project Background and Update Community Meeting September 11, 2017 Topics Project Background Claremont Segment Information Project Timeline Upcoming Discussion Items Upcoming Meetings Questions
More informationNew Mixed Use Development BETWEEN EXPOSITION AND JEFFERSON CRENSHAW BOULEVARD LOS ANGELES, CA
FOR LEASE FOR LEASE PROPERTY FEATURES Available: Asking Rate: ±1,200 SF - 4,500 SF Negotiable APN: 5046-001-021 Zoning: LAC1.5 PROPERTY HIGHLIGHTS + + Fantastic retail opportunity: Ideal location for coffee,
More informationDecember 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program
December 2012 Update I-95 New Haven Harbor Crossing Corridor Improvement Program Prepared by: Connecticut Department of Transportation District 3A 424 Chapel Street New Haven, CT 06511 Prepared for: South
More informationMetrolinx Projects: Temporary Delegation for Long- Term Road Closures
PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation
More informationSecond Street Improvements Project Project Update Archive
Second Street Improvements Project Project Update Archive 12/03/18: In observance of the Holiday Moratorium, crews have paused a majority of construction activity on 2nd Street until January 2, 2019. A
More informationRegional Connector Transit Project Community Leadership Council
Regional Connector Transit Project Community Leadership Council Grand Av Arts/Bunker Hill Station & Flower St/Financial District Committees May 9, 2017 1 COMMUNITY LEADERSHIP COUNCIL UPDATE 2 CLC Executive
More informationAGENDA ITEM I-6 Public Works
AGENDA ITEM I-6 Public Works STAFF REPORT City Council Meeting Date: 8/6/2018 Staff Report Number: 18-150-CC Informational Item: Update on the Willow Road and highway 101 interchange construction, upcoming
More informationHospital Link Project Project Update Winter 2018
Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open
More informationExecutive Summary. See Figure ES-5 on page 9. Figure ES-6: Typical At-Grade Alignment. Figure ES-7: Typical Underground Alignment
Figure ES-5 shows all of the possible LRT routes and stations identified for study in the Draft EIS/EIR. The features and impacts of each of the build alternatives are described in the following section.
More informationFirst rail. August 2011
August 2011 First rail A downtown resident showed his son in early August the first completed section of embedded track on Fourth Street in front of the Farmer s Market. During July, the Central Corridor
More informationHospital Link Project Project Update September 2015
Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service
More informationRegional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017
Regional Connector Transit Project Community Leadership Council 2 nd Hope Station & Flower St Committees January 17, 2017 1 EAT SHOP PLAY LOCAL 2 Eat Shop Play Local > Free Metro marketing campaign > Make
More informationLESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation
LESLIE BARNS & CONNECTION TRACK Project Update Construction and Traffic Management Consultation PRESENTATION SUMMARY Part 1 Brief Project Update (New Streetcars & Streetscape Improvements) Part 2 Construction
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Project Status Update Meeting Culver City Senior Center Wednesday, July 16, 2008 Description 8.6 mile corridor from downtown to Culver City in West Los Angeles 1.3
More informationNovember 9, Society of American Military Engineers
November 9, 2016 Society of American Military Engineers Transit Operator Transportation Planner Transportation Infrastructure Builder Transportation Funding Overseer 2 1,433 square-mile service area (nearly
More informationHead to University Avenue and save!
April 2011 Head to University Avenue and save! Liberty Tax Service at 1731 University Ave. W. in is offering a special for first-time customers who drive through the construction zone to get their taxes
More informationExpo E-News. Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2. Keeping Our Community Informed
Expo E-News Keeping Our Community Informed Winter 2014 Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2 In this Issue : Page 4: Construction Update Page 6: Artist Profiles For more information
More informationPublic Information Center August 12, 2010
Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General
More informationEXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015
EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley
More informationLong water shutdown scheduled for Tuesday, September 18
Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility
More informationMetro Gold Line Eastside Extension Review Advisory Committee October 9, 2008
Review Advisory Committee October 9, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within
More informationRoute 29 Solutions Projects
Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement
More informationMetro Gold Line Eastside Extension Review Advisory Committee May 8, 2008
Review Advisory Committee May 8, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-Grade and 2 Underground) Park & Ride Facility at Pomona/Atlantic Direct Connection to the Pasadena Metro at Union
More informationCarlisle Connectivity Projects Communication Plan and Project Status
Carlisle Connectivity Projects Communication Plan and Project Status Overview Communication Plan Communication Plan Communication Plan Objective The Borough staff will develop and execute timely and effective
More informationLOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017
LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20
More informationHaving trouble reading this ? View it in your browser. Welcome
Page 1 of 6 Having trouble reading this email? View it in your browser. IN THIS ISSUE Remembering 2011 and Preparing for 2012 Copper Thefts Increase on West Rail Eiber Neighborhood Resident Recieves "Most
More informationLAX Specific Plan Amendment Study (SPAS) Final EIR and Related Actions. Board of Airport Commissioners February 5, 2013
LAX Specific Plan Amendment Study (SPAS) Final EIR and Related Actions Board of Airport Commissioners February 5, 2013 1 Background The LAX Master Plan Program serves as the airport s long range development
More informationSouth Bay Metro Light Rail Extension. Summer/Fall 2017 Project Briefings
South Bay Metro Light Rail Extension Summer/Fall 2017 Project Briefings Meeting Agenda 2 Project History Project Development Schedule Feedback 3 Project History Alternatives Analysis Measure R $272M 2008
More informationTransportation Supporting Dulles Airport
Transportation Supporting Dulles Airport Committee for Dulles Economic Development and Transportation Committee July 12, 2018 Tom Biesiadny, Director Fairfax County Multiple Transportation Improvements
More informationBE VE R LY HILLS CITY OF BEVERLY HILLS HUMAN SERVICES DIVISION MEMORANDUM TO: Human Relations Commission FROM:
October October November November4-5, November Metro 2017-18 BE VE R LY HILLS C CITY OF BEVERLY HILLS HUMAN SERVICES DIVISION MEMORANDUM TO: FROM: DATE: SUBJECT: ATTACHMENT: Human Relations Commission
More informationCell: (408) Release MA June 25, 2012
VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara
More informationWelcome. Green Line in Your Community
Welcome Green Line in Your Community Today s session will provide you with information on options The City is exploring for connecting the Green Line in the Beltline to the future Inglewood/Ramsay station.
More informationEast Link Project Update. Maintenance of Traffic During Construction. April 21, 2015
East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities
More informationItem # 28. Chief Capital Management Officer Report. November 20, 2008
Item # 28 Chief Capital Management Officer Report November 20, 2008 1 Metro Gold Line Eastside Extension Project Update November 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground)
More informationONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1
ONONDAGA CREEKWALK PHASE II Public Information Meeting Series 1 Andrew Maxwell Director, Syracuse-Onondaga County Planning Agency Owen Kerney Assistant Director for City Planning Russell Houck, PE City
More informationSouth Bay Light Rail Extension Summer/Fall 2017 Project Briefing
South Bay Light Rail Extension Summer/Fall 2017 Project Briefing Meeting Agenda 2 Project History Project Development Schedule Feedback Study Area Project History 4 Alternatives Analysis 2008 Measure R
More informationDesign Meeting Presentation
Contract No. 17ECS-TI-05SP April November 2017 Design Meeting Presentation November 2015 Agenda Items: Introduction (5 min) Overview (10 min) Scope of work (60 min): Schedule and Traffic Staging / Closures
More informationCounty of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation
Silver Line Update Committee for Dulles March 2, 2017 Mark Canale Fairfax County Department of Transportation Phase 1 Summary Old Meadow Road Realignment design work proceeding, construction to be completed
More informationNortheast Corridor Transportation Update
Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer
More informationAs the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.
REPORT FOR ACTION Construction Staging Area - 81 Bay Street Date: December 11, 2017 To: Toronto and East York, Community Council From: Acting Director, Transportation Services Toronto and East York District
More informationEast Link Extension. Redmond stations Open House November 17, 2016
East Link Extension Redmond stations Open House November 17, 2016 Presentation agenda Overview of East Link Extension light rail project and two stations in Redmond s Overlake area Overlake Village Station
More informationSCOPING INFORMATION PACKET
SCOPING INFORMATION PACKET Project Description The proposed project would provide a direct link connecting several light rail lines in operation or in construction, including the Metro Gold Line to Pasadena,
More informationAstoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019
Astoria Boulevard ADA Upgrade and Station Renewal January 7, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two Mezzanine-to-Platform
More informationMacleod Trail Corridor Study. Welcome. Macleod Trail Corridor Study Open House. Presentation of Proposed Design Concepts
Macleod Trail Corridor Study Welcome Macleod Trail Corridor Study Open House Presentation of Proposed Design Concepts Study Purpose Develop a corridor plan for Macleod Trail that aligns with The City s:
More informationJANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS
For Immediate Release January 2, 2018 Contact: Charles H. Pannunzio (424) 646-5260 JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS Access to Parking Structure 4 from the Upper/Departure
More informationAbout the Foothill Gold Line
About the Foothill Gold Line Board of Directors Marisol Rodriguez Member (Los Angeles Appointee) John Fasana Member (Metro Appointee) Doug Tessitor Chair (Pasadena Appointee) Sam Pedroza Vice Chair (SGVCOG
More informationMain Street Station Upgrades
Main Street Station Upgrades Public Meeting Hope United Church 1 Main Street Station Upgrades Bus diversions Planned improvements Construction staging Pedestrian flows 2 Main Street Station Aerial Bar
More informationNational Society of Professional Engineers. Charles S. Carnaggio, PE Project Director July 2, 2014
National Society of Professional Engineers Charles S. Carnaggio, PE Project Director July 2, 2014 Phase 1 Opening Date: July 26, 2014 Dulles Corridor Metrorail Project At-a-Glance Seamless integration
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 29, 2009 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION PROJECT STEELES WEST STATION APPROVAL OF CONCEPTUAL DESIGN
More informationDowntown to Defiance Trolley Key Messages Jan. 2017
Downtown to Defiance Trolley Key Messages Jan. 2017 Overarching Messages This is a demonstration (pilot) project for one summer. We will evaluate how it went to see if we can offer it again in the future.
More informationOhio Department of Transportation Construction Update
Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District
More informationAstoria Boulevard ADA and Station Renewal Track Improvements. January 30, 2019
Astoria Boulevard ADA and Station Renewal Track Improvements January 30, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two
More informationWest Santa Ana Branch Transit Corridor. Community Meetings March 12, 13, 17 & 19, 2018
West Santa Ana Branch Transit Corridor Community Meetings March 12, 13, 17 & 19, 2018 Purpose of this Meeting > Update on Public Scoping comments received > Why Metro is revisiting the Northern Alignments
More informationE-Newsletter Keeping Our Community Informed Volume 1, Issue 4
W ith the Expo Light Rail Line under heavy construction for almost two years now, a variety of construction activities are taking place up and down the whole alignment. In Downtown Los Angeles utility
More informationYork Region Rapid Transit Corporation. City of Vaughan Committee of the Whole June 1, 2016
York Region Rapid Transit Corporation City of Vaughan Committee of the Whole June 1, 2016 0 Agenda Future rapid transit projects > Yonge North Subway Extension [YNSE] > Regional Express Rail [RER] Current
More informationPRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction
PRESENTED TO Town of Middlebury, VT PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction Meeting with you today Brian Carpenter, Middlebury Selectboard Chair Jim Gish, Middlebury
More informationWHO IS METROLINX?
CROSSTOWN LRT WHO IS METROLINX? Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate
More informationCRENSHAW COLISEUM CENTER
CRENSHAW COLISEUM CENTER RODEO RD EXPO/CRENSHAW METRO LINE District Square Approved Mixed use development STARBUCKS CRENSHAW BLVD Chase HIGHLIGHTS + + ±65,000 SF Softgoods & Drug Store Anchored Center
More informationSAN RAFAEL City Council January 20, 2015
SONOMA MARIN AREA RAIL TRANSIT SMART CENTRAL SAN RAFAEL STATUS UPDATE SAN RAFAEL City Council January 20, 2015 CENTRAL SAN RAFAEL SMART SOUTH OF PUERTO SUELLO TUNNEL 1. Active Construction 2. Construction
More informationMEMORANDUM VILLAGE OF NORTHBROOK
MEMORANDUM VILLAGE OF NORTHBROOK TO: Staff COPY: Village President & Board of Trustees Department Heads FROM: Richard Nahrstadt, Village Manager DATE: April 29, 2016 SUBJECT: STAFF BRIEFING WEEK OF April
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.4 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving various parking and traffic modifications associated
More information25 th Avenue Grade Separation. September 13, 2017
25 th Avenue Grade Separation September 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25
More informationPalm Beach County Traffic Report July 13 through July 20, 2012
For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be
More informationSite Location and Setting
Memorandum Date: To: From: Subject: Kristy Le, Gary Black Steve Orem Santa Teresa County Park Historic Area Traffic and Parking Study Hexagon Transportation Consultants, Inc. has completed a traffic and
More informationMetro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements
Metro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements Jan Perry Councilwoman, District 9 Welcome Remarks Arthur T. Leahy Chief Executive Officer, Metro Metro ExpressLanes Overview
More informationCrystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.
Table 1: South Entrance Table 2: North Entrance 20th St. S 18th St. S Proposed Second Entrance Crystal Drive Existing Station Location Platform Future 4 th Track Future New Airport Connection (by others)
More informationBUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018
BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO
More information- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule
Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and
More informationTrain to Plane Connection Construction of the Burbank Airport North Metrolink Station
Train to Plane Connection Construction of the Burbank Airport North Metrolink Station Community Meeting - March 13, 2017 1 Community Meeting Agenda 6:00 6:30 PM Open House 6:30 7:15 PM Presentation 7:15
More information3. COLTA / HUGA CONNECTIONS - PRELIMINARY
9 3. COLTA / HUGA CONNECTIONS - PRELIMINARY 3.1 COLTA The Chain of Lakes Trail Association (COLTA) trail, formerly identified as the Chester Spur Line, was completed and opened for use in June 2011. The
More informationEXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015
EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: November 18, 2013 SUBJECT: YONGE-EGLINTON AND EGLINTON WEST INTERCHANGE STATIONS METROLINX EGLINTON CROSSTOWN LIGHT RAIL TRANSIT PROJECT
More informationCONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND
BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK
More informationAtlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)
Atlantic Street Bridge Project Update CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement Track & Station Infrastructure Improvements City
More informationNFTA Access Enhancement Study for Canalside and Cobblestone Alternatives Discussion. Alternative A South Park Avenue
Alternative A South Park Avenue Alternative A Summary Alternative A extends Metro Rail service around the foot of Main Street east along South Park Avenue to serve a new station platform located along
More informationCommonwealth Avenue Bridge Deck Replacement Project. Legislative and Stakeholder Briefing. April 13, 2017
Commonwealth Avenue Bridge Deck Replacement Project Legislative and Stakeholder Briefing April 13, 2017 1 Project Team Contractor Walsh Construction Company Design Team HDR Lead City Point Partners, LLC
More informationMeasure R Program Update
Item 1 Program Update March 17, 2011 Independent Taxpayers Oversight Committee February 18 th Meeting held: Reviewed Audits of FY10 Expenditures Set Public Hearing Date on Audit Findings for April 18th
More informationAPPENDIX H MILESTONE 2 TRAFFIC OPERATIONS ANALYSIS OF THE AT-GRADE CROSSINGS
Draft Environmental Impact Statement/Environment Impact Report Appendix H Milestone 2 Traffic Operations Analysis of the At-Grade Crossings APPENDIX H MILESTONE 2 TRAFFIC OPERATIONS ANALYSIS OF THE AT-GRADE
More informationWelcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,
Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program, updates on construction to be held in this area, and how
More informationWATERFRONT PROGRAM PROGRESS REPORT
WATERFRONT PROGRAM PROGRESS REPORT 2016 (April - June) Highlights from 2016 In April, released the Supplemental Draft Environmental Impact Statement (EIS) for the Alaskan Way, Promenade, and Overlook Walk.
More informationNorth Metro Rail Line Elected Officials Briefing. November 16, 2017
North Metro Rail Line Elected Officials Briefing November 16, 2017 Henry Stopplecamp, RTD Assistant General Manager, Capital Programs Eagle P3 Project The first transit project of its kind in the U.S.
More informationPROGRESS REPORT. OCTOBER and NOVEMBER 2013
PROGRESS REPORT OCTOBER and NOVEMBER 2013 Published December 20, 2013 The Banks Project Results to Date Bid Package #12 Progress Part 1 Elements (TC-30) Reconstruction of Freedom Way, Rosa Parks Street
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: KENNEDY INTERCHANGE STATION: METROLINX EGLINTON CROSSTOWN LIGHT RAIL TRANSIT PROJECT - PRELIMINARY CONCEPT
More informationLOS ANGELES WORLD AIRPORTS' AUTOMATED PEOPLE MOVER
One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net 31 PLANNING AND PROGRAMMING COMMITTEE SEPTEMBER 17,2014 CONSTRUCTION COMMITTEE SEPTEMBER 18,2014 SUBJECT: ACTION: LOS ANGELES WORLD
More informationBuilding the transportation network we need for the future in Niagara Region
Building the transportation network we need for the future in Niagara Region Niagara@metrolinx.com Metrolinx.com/Niagara Metrolinxengage.com INSERT FOOTER 1 WHO IS METROLINX? Metrolinx was created in 2006
More informationTECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018
TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018 2018-2019 SCHEDULE Project progress Contract signed with the winning consortia on April 12, 2018 Project office set up for the
More informationUS 19 Sunset Point Rd to Countryside Blvd.
Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started
More informationGuide to. Road Construction Projects
Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or
More informationLAX Specific Plan Amendment Study (SPAS) Update. December 3, 2012
LAX Specific Plan Amendment Study (SPAS) Update December 3, 2012 Response to the Draft Environmental Impact Report Draft EIR Release and Public Comment Official Comment Period was July 27, 2012 through
More information35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS
35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration
More informationStage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge
Stage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge Public Consultation Centre (PCC) No. 3 Please Sign-in Cambridge City Hall November 21, 2017 2:00 to 8:00pm Preston Memorial Auditorium
More information