Metro Gold Line Eastside Extension Review Advisory Committee October 9, 2008
|
|
- Marian Gordon
- 5 years ago
- Views:
Transcription
1 Review Advisory Committee October 9, Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within Budget Opens in 2009
2 Louise Martinez Beloved RAC Member Rest In Peace
3 Overall Construction Progress ACTIVITY J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Major Construction Activities Trackwork 1st/Boyle & 1st/Soto 1st/Alameda 1st/Utah Indiana 3rd/Ford 3rd/Mednik Pomona/Atlantic Station Architecture and Site Finishes Boyle Heights/Mariachi Plaza & Soto Stations Little Tokyo/Arts District Station Pico/Aliso Station Indiana Station Maravilla Station East LA Civic Station Atlantic Station Third Party Interfaces 1st Street Bridge Widening LAUSD Re-Build Ramona Opportunity High School Systems Installation & Testing/ Pre-Revenue Systems Installation & Integration Testing (Phases I & II) Pre-Revenue Operations Revenue Operations Date
4 Overall Construction Progress Construction began in July As of October 2008, the Project is over 89% complete. The Contractor has worked over 3.5 million hours without a lost-time accident. Trackwork installation along the entire six-mile alignment is complete. Construction of the two underground stations at 1st/Boyle and 1st/Soto is 83% complete. Construction of the six at-grade stations is 63% complete. Systems installation is 76% complete.
5 101 Freeway Light Rail Transit Bridge Union Station View looking southwest from Union Station towards Downtown Los Angeles. The tie-in to the Pasadena tracks was completed in September Installation of all the trackwork along the entire six-mile alignment is complete.
6 Light Rail Transit Stations LittleTokyo/ Arts District Pico/Aliso Boyle Heights/ Mariachi Plaza 1st/Soto Maravilla Indiana Station East Los Angeles Civic Center Pomona/Atlantic
7 At-Grade Station Construction 1 st /Alameda and 1 st /Utah Little Tokyo/Arts District Station - Northeast corner of 1st/Alameda. Pico/Aliso Station View east near 1 st /Utah towards Boyle Heights. Construction of the At-Grade stations along the west side of the alignment includes concrete sitework, canopy installation and systems installation.
8 Underground Station Construction 1 st /Boyle and 1 st /Soto Boyle Heights/Mariachi Plaza - Northeast corner of 1st/Boyle where the station entrance is being constructed adjacent to the Mariachi Plaza Kiosko. Soto Station Interior work in the underground rooms progresses as work on the station entrance structures above continues.
9 Underground Station Construction Boyle Heights/Mariachi Plaza Station Station entrance stairs are being constructed from the plaza to the mezzanine levels. Escalators are being installed to connect the various underground levels. Elevators will be installed within the next few months.
10 At-Grade Station Construction Indiana Station Maravilla Station Construction of the stations from 1st/Indiana and along 3rd Street in East Los Angeles is well underway where the erection of canopies and the installation architectural finishes has begun. East LA Civic Center Station Pomona/Atlantic Station
11 Surface Work and Street Restoration New crosswalks are being constructed at the 1 st Street and Lorena Street intersection near the east tunnel portal. The portion of the jogging path that was impacted by construction along the north side of 1 st Street between Lorena Street and Fresno Street has been replaced.
12 Surface Work and Street Restoration Final paving and striping is occurring along 3 rd Street where the track guideway has been completed. The U-Channel track guideway and barrier walls on 3 rd Street between Marianna Avenue and Downey Road have been completed.
13 Community Relations
14 City of Baltimore Tour with the RAC Metro hosted a Community Workshop between guests from the City of Baltimore and Eastside community Review Advisory Committee (RAC) members. City of Baltimore elected officials, community and business leaders asked Eastside community Review Advisory Committee members to share their experiences on the Metro Eastside Extension Project.
15 City of Baltimore Tour with the RAC Guests from the City of Baltimore and Eastside community Review Advisory Committee (RAC) members arrived at the future Boyle Heights/Mariachi Plaza Station after a tour of the Project. Guests received underground safety training and construction attire and equipment before going underground to tour the station and tunnels.
16 City of Baltimore Tour with the RAC
17 Community Relations Mitigation Mitigating construction related impacts. Coordinating construction activities to minimize disruptions. Notification of traffic detours and related activities through construction notices. Filing field reports for physical damages to the Contractor. Working with local businesses to promote them as part of the opening of the Metro Eastside Extension. Community Relations Field Office st Street Los Angeles, CA MGLEE HOTLINE (213)
18 Community Relations Mitigation Mariachi Directory Now Available! Public Libraries Local Chambers of Commerce Offices of Elected Officials For a complete list of locations:
19 End of Presentation
Metro Gold Line Eastside Extension Review Advisory Committee May 8, 2008
Review Advisory Committee May 8, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-Grade and 2 Underground) Park & Ride Facility at Pomona/Atlantic Direct Connection to the Pasadena Metro at Union
More informationItem # 28. Chief Capital Management Officer Report. November 20, 2008
Item # 28 Chief Capital Management Officer Report November 20, 2008 1 Metro Gold Line Eastside Extension Project Update November 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground)
More informationLos Angeles County Metropolitan Transportation Authority. Metro Rail Gold Line Eastside Extension - Operations
Los Angeles County Metropolitan Transportation Authority Metro Rail Gold Line Eastside Extension - Operations Metro Gold Line System Description The Metro Gold Line is currently a 13.6 mile, double track
More informationSCOPING INFORMATION PACKET
SCOPING INFORMATION PACKET Project Description The proposed project would provide a direct link connecting several light rail lines in operation or in construction, including the Metro Gold Line to Pasadena,
More informationExecutive Summary. See Figure ES-5 on page 9. Figure ES-6: Typical At-Grade Alignment. Figure ES-7: Typical Underground Alignment
Figure ES-5 shows all of the possible LRT routes and stations identified for study in the Draft EIS/EIR. The features and impacts of each of the build alternatives are described in the following section.
More informationThe Benefits of a Whittier Blvd. Alignment for the Metro Eastside Extension
The Benefits of a Whittier Blvd. Alignment for the Metro Eastside Extension by Bart Reed The Transit Coalition P.O. Box 567 San Fernando, CA 91341-0567 (818) 367-1661 1 Introduction Metro has released
More informationmetro.net See Inside Get 2 For 1 At MOCA Metro January 2010 monthly Save 50% To LA Clippers
See Inside Get For At MOCA metro.net Metro January 00 monthly Save 0% To LA Clippers Metro Gold Line train breaks through banner at official dedication of new light rail to East LA. Thousands Celebrate
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Project Status Update Meeting Culver City Senior Center Wednesday, July 16, 2008 Description 8.6 mile corridor from downtown to Culver City in West Los Angeles 1.3
More informationWest Santa Ana Branch Transit Corridor. Community Meetings March 12, 13, 17 & 19, 2018
West Santa Ana Branch Transit Corridor Community Meetings March 12, 13, 17 & 19, 2018 Purpose of this Meeting > Update on Public Scoping comments received > Why Metro is revisiting the Northern Alignments
More informationCrenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017
Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017 1 Project Overview Design-Build Contractors: Mainline - Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationLOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY BID TABULATION
FACILITY/LOCATION 36 MONTH BASE A. BUS DIVISIONS, TERMAINALS AND LAYOVER LOTS MONTHLY MONTHLY MONTHLY SAN FERNANDO $1,500.00 $1,459.00 $2,122.00 SAN GABRIEL VAL $1,500.00 $1,459.00 $2,122.00 DIVISION 1
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 1 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)
More informationHaving trouble reading this ? View it in your browser. Welcome
Page 1 of 6 Having trouble reading this email? View it in your browser. IN THIS ISSUE Remembering 2011 and Preparing for 2012 Copper Thefts Increase on West Rail Eiber Neighborhood Resident Recieves "Most
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017
Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 1 Project Overview Mainline Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More information,000 SF 23,109 SF S SANTA FE AVENUE LOS ANGELES CALIFORNIA ,000 SF & 7,000 SF FOR SALE OF BUILDINGS ON OF LAND 2 BUILDINGS
FOR SALE 3819-3821 S SANTA FE AVENUE LOS ANGELES CALIFORNIA 90058 15,000 SF OF BUILDINGS ON 23,109 SF OF LAND 2 BUILDINGS 8,000 SF & 7,000 SF FOR SALE 3819-3821 S SANTA FE AVENUE LOS ANGELES CALIFORNIA
More informationRETAIL FOR LEASE. 807 Flower Street
RETAIL FOR LEASE 807 Flower Street F I N A N C I A L D I S T R I C T D T L A Ea site plan retail space ± 7,350 SF* *rate negotiable th Elevation West Elevation 46.535 Flower Street Alley 14.905 2.782 North
More informationCOMING SOON! 801 S. Olive Street
COMING SOON! 801 S. Olive Street F I N A N C I A L D I S T R I C T D T L A site plan retail space ± 9,140 SF* *rate negotiable Residential Lobby Retail 1 6127 SF 8th Street Retail 2 3013 SF Olive Street
More information801 S. OLIVE STREET GROUND FLOOR RETAIL
801 S. OLIVE STREET GROUND FLOOR RETAIL SITE PLAN RETAIL SPACE ± 3,086 SF* *RATE NEGOTIABLE Residential Lobby 8TH STREET Retail D 1344 SF Retail C 1742 SF Retail B 3155 SF Olive Street OLIVE STREET THE
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance Facility:
More informationAbout the Foothill Gold Line
About the Foothill Gold Line Board of Directors Marisol Rodriguez Member (Los Angeles Appointee) John Fasana Member (Metro Appointee) Doug Tessitor Chair (Pasadena Appointee) Sam Pedroza Vice Chair (SGVCOG
More informationRestoration of Historic Streetcar Services in Downtown Los Angeles
Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting November 3, 2011 Introduction Local lead agency: Metro Federal lead agency: Federal Transit
More informationTransportation Supporting Dulles Airport
Transportation Supporting Dulles Airport Committee for Dulles Economic Development and Transportation Committee July 12, 2018 Tom Biesiadny, Director Fairfax County Multiple Transportation Improvements
More informationDufferin Jog Elimination Project
Project Project Status Update November 14 2007 Project History Planning Alternatives Criteria Measured Project Benefits Structural Configurations Considered Structural Design Considerations The Preferred
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017
Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationExpo E-News. Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2. Keeping Our Community Informed
Expo E-News Keeping Our Community Informed Winter 2014 Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2 In this Issue : Page 4: Construction Update Page 6: Artist Profiles For more information
More informationBUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018
BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO
More informationGardner: overview. Santa Fe, Oregon, and California National Historic Trails UNINCORPORATED JOHNSON COUNTY OLATHE UNINCORPORATED JOHNSON COUNTY
Santa Fe, Oregon, and California ational Historic Trails : overview 99: p.134 100: p.135 GARDER JUCTIO 102: p.137 56: p.126 EDGERTO Burlington orthern Intermodal and Logistics 98: p.133 101: p.136 S Waverly
More informationSouth Bay Metro Light Rail Extension. Summer/Fall 2017 Project Briefings
South Bay Metro Light Rail Extension Summer/Fall 2017 Project Briefings Meeting Agenda 2 Project History Project Development Schedule Feedback 3 Project History Alternatives Analysis Measure R $272M 2008
More informationNorthern Rail Extension, Phase One
General Project and Funding 1. Where does Phase One start? The rail line for Phase One begins roughly at the northern boundary of the former Bradbury property, but also includes work along Tom Bear Trail
More informationLathrop Industrial Complex
A Project by: AVAILABLE FOR SALE OR LEASE three overhead cranes heavy power yard/trailer parking rail served EXCLUSIVE BROKERS - INDUSTRIAL SERVICES TEAM: MIKE GOLDSTEIN, SIOR Executive Managing Director
More informationSilver Line Rail Project Update
Silver Line Rail Project Update April 2013 Project Map 2 Silver Line, Phase 1 Service Pattern 3 Project Overview Silver Line Dulles Metrorail is a 23-mile extension of the existing Orange Line Total Project
More informationSouth Bay Light Rail Extension Summer/Fall 2017 Project Briefing
South Bay Light Rail Extension Summer/Fall 2017 Project Briefing Meeting Agenda 2 Project History Project Development Schedule Feedback Study Area Project History 4 Alternatives Analysis 2008 Measure R
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting January 31 st, 2018 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationLong water shutdown scheduled for Tuesday, September 18
Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility
More informationVasona Light Rail Signal Design Challenges. Hugh D. MacGillivray, Hatch Mott MacDonald Dennis Mellon, Santa Clara County Transportation Authority
Vasona Light Rail Signal Design Challenges Hugh D. MacGillivray, Hatch Mott MacDonald Dennis Mellon, Santa Clara County Transportation Authority Abstract The Vasona line is the most recent extension of
More informationPRICE RECUDED! VACANT IN 60 DAYS! 13,265 SF INDUSTRIAL BUILDING 23,087 SF OF LAND FOR SALE OR LEASE 3817 S SANTA FE AVE VERNON CALIFORNIA 90058
PRICE RECUDED! VACANT IN 60 DAYS! 13,265 SF INDUSTRIAL BUILDING 23,087 SF OF LAND 3817 S SANTA FE AVE VERNON CALIFORNIA 90058 3817 S SANTA FE AVE VERNON CALIFORNIA 90058 PROPERTY HIGHLIGHTS Excellent Clear
More informationJune 2017: 700 Piles 9 Weeks and 3 Days Pile Caps / Tie Beams Roof Foundations
Welcome FAA FAA October 2016: Broke Ground October 2016 Excavated 6.2 Million Cubic Yards Excavated 100,000 Cubic Yards in one day at peak 36 30 Yard Scrappers 10 30 Yard Dump Trucks 85 Days to Complete
More informationS. FIGUEROA. Financial District DTLA
8 0 0 S. FIGUEROA restaurant retail Financial District DTLA Existing Condition The Site Space can accomodate retail or restaurant Restaurant infrastructure in place CUP Allowing for Beer & Wine At the
More informationSouthwest LRT Alignment Video Narration
Southwest LRT Alignment Video Narration September 2015 Southwest Light Rail Transit, a proposed extension of the METRO Green Line, will serve Minneapolis, St. Louis Park, Hopkins, Minnetonka and Eden Prairie.
More informationWAKABA 232 E. 2ND STREET LITTLE TOKYO
WAKABA 232 E. 2ND STREET LITTLE TOKYO GROUND FLOOR RETAIL FOR LEASE JOIN Site Plan 2ND STREET SPACE HIGHLIGHTS RATE: $4.25/SF NNN TERM: 5-10 YEARS RETAIL BELOW 240 LUXURY RESIDENTIAL UNITS GROUND LEVEL
More informationIII. ENVIRONMENTAL SETTING
III. ENVIRONMENTAL SETTING A. OVERVIEW OF ENVIRONMENTAL SETTING Regional Setting The project site is located in Los Angeles County, within the Hollywood community of the City of Los Angeles (see Figure
More informationFLINDERS STREET STATION DESIGN COMPETITION STATEMENT OF KEY OBJECTIVES
FLINDERS STREET STATION DESIGN COMPETITION STATEMENT OF KEY OBJECTIVES Page 2 of 28 Flinders Street Station and environs (looking west) INTRODUCTION Page 3 of 28 First built in 1854, Flinders Street Station
More informationSTATION TYPOLOGIES. Typology Matrix 35
3 STATION TYPOLOGIES Typology Matrix 35 Typologies The TOD Framework Master Plan classifies the various stations along the MetroLink system in a series of typologies as outlined on the pages that follow.
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 29, 2009 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION PROJECT STEELES WEST STATION APPROVAL OF CONCEPTUAL DESIGN
More informationMetro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements
Metro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements Jan Perry Councilwoman, District 9 Welcome Remarks Arthur T. Leahy Chief Executive Officer, Metro Metro ExpressLanes Overview
More informationTrails, steps, & P-Patch to be south of I- 5 Colonnade
UW Campus Trails, steps, & P-Patch to be south of I- 5 Colonnade Blaine and Howe Street steps REI N new lighting existing features connector trail new features or improvements overhead freeway and support
More informationSEVAN BARSEGHIAN'S PORTFOLIO GLENDALE COMMUNITY COLLEGE
SEVAN BARSEGHIAN'S PORTFOLIO GLENDALE COMMUNITY COLLEGE SEVAN BARSEGHIAN EMAIL: SEVAN.BARSEGHIAN@YAHOO.COM PORTFOLIO DIRECTORY EDUCATION GLENDALE COMMUNITY COLLEGE, CA ARCHITECTURE PROGRAM (2011-2013)
More information28,765 SF INDUSTRIAL BUILDING FOR LEASE LOS ANGELES, CA 90021
28,765 SF INDUSTRIAL BUILDING FOR LEASE LOS ANGELES, CA 90021 28,765 SF INDUSTRIAL BUILDING FOR LEASE PROPERTY HIGHLIGHTS Excellent Warehouse or Manufacturing Building 15th at Alameda Street 19 Clearance
More informationNAIOP. Marcia McAllister Metropolitan Washington Airports Authority
NAIOP Marcia McAllister Metropolitan Washington Airports Authority 1 The Vision Realized Northern Virginia Today Tysons Corner is the largest employment center in the Commonwealth Larger than central business
More informationLink Union Station (LINK US)
Link Union Station (LINK US) Presentation for LAUS Master Commercial Developer Industry Forum October 13 th 2017 Jeanet Owens, PE Senior Executive Officer Program Management / Regional Rail Project Overview
More informationNOW OPEN: WAKABA 232 E. 2nd STREET DTLA Little Tokyo
GROUND FLOOR RETAIL FOR LEASE 100% OCCUPANCY BY MAY 2017 JOIN RETAILERS: NOW OPEN: WAKABA 232 E. 2nd STREET DTLA Little Tokyo JOIN: Space Highlights Rate: $4.25/SF NNN Term: 5-10 Years Parking: Onsite
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: November 18, 2013 SUBJECT: YONGE-EGLINTON AND EGLINTON WEST INTERCHANGE STATIONS METROLINX EGLINTON CROSSTOWN LIGHT RAIL TRANSIT PROJECT
More informationSpencer Environmental Appendix A: Alternative Analysis for Construction Access Route
Spencer Environmental Appendix A: Alternative Analysis for Construction Access Route February 2015 Valley ine-stage 1 RT EISA Update FINA REPORT Page A1 Memorandum AECOM ConnectEd Transit Partnership 10235
More informationNortheast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015
Northeast Anthony Henday Drive Edmonton Ring Road Update Strathcona Chamber of Commerce March 18, 2015 Project Background 2 Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest
More informationCorridor Management Committee Meeting. April 2, 2014
Corridor Management Committee Meeting April 2, 2014 1 Today s Topics Welcome Approval of Minutes Resolutions Response to March 26 CMC Questions Staff Recommendation on Project Scope and Budget Public Testimony
More informationMetrolinx Projects: Temporary Delegation for Long- Term Road Closures
PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation
More information8,251 SF INDUSTRIAL BUILDING FOR LEASE OR SALE
LEE-ASSOCIATES.COM TEAM-CLINE.COM LOCAL EXPERTISE. INTERNATIONAL REACH. WORLD CLASS. PROPERTY HIGHLIGHTS Central El Sereno Location Compliant Location for LA City Dispensary HVAC Throughout with Heavy
More informationPossible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar
Possible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar A construction truck drives along the newly paved westbound 60 freeway Lemon Avenue on-ramp in City of
More informationEast Link Extension. Redmond stations Open House November 17, 2016
East Link Extension Redmond stations Open House November 17, 2016 Presentation agenda Overview of East Link Extension light rail project and two stations in Redmond s Overlake area Overlake Village Station
More informationMPRB: Southwest LRT Community Advisory Committee Issues and Outcomes by Location Current to: 12 November 2010
MPRB: Southwest LRT Community Advisory Committee Issues and Outcomes by Location Current to: 12 November 2010 This is a compilation of issues and outcomes identified by the CAC. It is a work in progress,
More informationCell: (408) Release MA June 25, 2012
VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara
More informationDOWNTOWN BRT ALTERNATIVE - 19th AVE
DOWNTOWN BRT ALTERNATIVE - 9th AVE New Route and Increased Service in Mixed Traffic Existing Route and Service in Mixed Traffic Light Rail Line / New Route and Increased in Exclusive Guideway Existing
More informationPlaza Business Park Hotel, Office, and Restaurant Sites
Plaza Business Park Hotel, Office, and Restaurant Sites The Plaza Business Park is designed A 115-room hotel, a 3,500-7,500 SF fast food restaurant sites with drive to accommodate the following: restaurant,
More informationClaremont Project Background and Update Community Meeting September 11, 2017
Claremont Project Background and Update Community Meeting September 11, 2017 Topics Project Background Claremont Segment Information Project Timeline Upcoming Discussion Items Upcoming Meetings Questions
More informationmetro.net See Inside Bus Service Public Hearings Feb Metro February 2010 monthly Get $3 Off Chinatown Firecracker 5K/10K
See Inside Bus Service Public Hearings Feb. -0 metro.net Metro February 00 monthly Get $ Off Chinatown Firecracker K/0K For convenient connections to the Go Metro Destination Discounts listed here, check
More informationBUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019
BUILD CONSTRUCTION Update FEBRUARY 2019 In this issue: ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEATURED PROJECT: KENT AVENUE * Featured Project KENT AVENUE CP 2-3 CONSTRUCTION UPDATE February 2019 At
More informationBENEFITS OF YOUR FUTURE RIDE
BENEFITS OF YOUR FUTURE RIDE How long will my trip from Lynnwood take? One train every 4MINUTES during peak weekday commutes EAST 50 MINUTES 60 MINUTES LYNNWOOD 20 MINUTES 28 MINUTES DOWNTOWN BELLEVUE
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: February 2, 2011 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION PROJECT STEELES WEST STATION APPROVAL OF FINAL DESIGN, FINISHES
More informationCounty of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation
Silver Line Update Committee for Dulles March 2, 2017 Mark Canale Fairfax County Department of Transportation Phase 1 Summary Old Meadow Road Realignment design work proceeding, construction to be completed
More informationCLOSE WINDOW. December 2002
CLOSE WINDOW December 2002 AROUND THE PORT... After more than six years with the Port of Long Beach, Harbor Commissioner John E. Kashiwabara has announced his retirement effective Jan. 31. Kashiwabara
More informationSpadina Avenue which would include two new underground stations located at Yonge Street and at University Avenue.
TORONTO TRANSIT COMMISSION REPORT No S7 MEETING DATE June 4, 1968 FROM: General Manager Subway Construction Date June 3, 1968 Subject: QUEEN STREET SUBWAY FOR STREETCAR OPERATION The Commission, at its
More informationPRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction
PRESENTED TO Town of Middlebury, VT PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction Meeting with you today Brian Carpenter, Middlebury Selectboard Chair Jim Gish, Middlebury
More informationORANGE COUNTY TRANSPORTATION AUTHORITY. Go Local Fixed-Guideway Program History and Project Update. PowerPoint 3
ORANGE COUNTY TRANSPORTATION AUTHORITY Go Local Fixed-Guideway Program History and Project Update PowerPoint 3 Santa Ana-Garden Grove Fixed Guideway Project OCTA Board of Directors September 26, 2011 Project
More information13,265 SQ. FT. INDUSTRIAL BUILDING ON 23,087 SQ. FT. OF LAND FOR SALE S SANTA FE AVE VERNON CA 90058
FOR SALE 3817 S SANTA FE AVE VERNON CA 90058 13,265 SQ. FT. INDUSTRIAL BUILDING ON 23,087 SQ. FT. OF LAND FOR SALE 3817 S SANTA FE AVE VERNON CA 90058 PROPERTY HIGHLIGHTS Excellent Clear Span, Bow Truss
More informationWEEKLY PROVINCIAL HIGHWAY CONSTRUCTION UPDATE FOR THURSDAY, OCTOBER 6, 2016 The law is black and white. Slow to 60 km/hr in Work Zones.
NEW WORK PROJECT/WORK: Highway 354 near Dilke ESTIMATED COST: $3.4M START OF THIS YEAR'S CONSTRUCTION: October 1, 2016 DESCRIPTION: About 17 km of surfacing on Highway 354 from the junction with Highway
More informationWelcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,
Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program, updates on construction to be held in this area, and how
More informationAstoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019
Astoria Boulevard ADA Upgrade and Station Renewal January 7, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two Mezzanine-to-Platform
More informationHARP AUTHORITY GATEWAY CENTER BOATHOUSE & CHANNEL EXTENSION TO SANTA FE AVENUE. Pueblo City Council Presentation September 17, 2018
HARP AUTHORITY GATEWAY CENTER BOATHOUSE & CHANNEL EXTENSION TO SANTA FE AVENUE Pueblo City Council Presentation September 17, 2018 PROJECT: 1A HARP Expansion FUNDING 1A Ballot Issue Pueblo County : $3,000,000
More informationAdd-A-Lane Contract V. along a Section of I-95 includes 6 Bridges
Newton Needham Chamber of Commerce Add-A-Lane Contract V along a Section of I-95 includes 6 Bridges Project File No. 603711 July 29, 2014 1 Agenda Project Update Overview Bid and Contract Award Schedule
More information2018 Service Implementation Plan Executive Summary
2018 Service Implementation Plan Executive Summary March 2018 2018 SERVICE IMPLEMENTATION PLAN Executive Summary 2018 Service Implementation Plan Each year, Sound Transit prepares a Service Implementation
More informationConstruction Update. Local Officials Briefing March 2016
Construction Update Local Officials Briefing March 2016 1 History: Chicago-St. Louis Corridor Since 1980 s IDOT has been looking at this corridor for high-speed service 1992 Designated a HSR Corridor EIS
More information2nd St St Little Tokyo Restaurant/Retail Opportunity
FOR FOR LEASE LEASE 2nd St St Little Tokyo Restaurant/Retail Opportunity 120 120 S. SAN S. SAN PEDRO PEDRO STREET, STREET, LOS LOS ANGELES, ANGELES, CA 90012 CA 90012 PROPERTY OFFERING PREMIER LITTLE TOKYO
More informationProposed Metro Service Changes. Proposed changes to Metro Bus Services effective June 29, 2008 or later. Union Station / Gateway February 9, 2008
Proposed Metro Service Changes Proposed changes to Metro Bus Services effective June 29, 2008 or later. Union Station / Gateway February 9, 2008 Metro San Gabriel Valley Service Sector Proposed changes
More informationVERNON, CA ,640 SF OF INDUSTRIAL BUILDING FOR SALE OR LEASE
VERNON, CA 90058 224,640 SF OF INDUSTRIAL BUILDING FOR SALE OR LEASE LAINDUSTRIALGROUP.COM TEAM-CLINE.COM 224,640 SF OF INDUSTRIAL BUILDING FOR SALE OR LEASE VERNON, CA 90058 PROPERTY HIGHLIGHTS Central
More informationLake Erie Commerce Center Traffic Analysis
LOCATION: East of NYS Route 5 at Bayview Road Town of Hamburg Erie County, New York PREPARED BY: Wendel Companies 140 John James Audubon Parkway Suite 200 Amherst, New York 14228 January 2012 i ii Table
More informationITA AITES WORLD TUNNEL CONGRESS 2009
ITA AITES WORLD TUNNEL CONGRESS 2009 Budapest, Hungary, May 23 29, 2009 OF SAFE AND EFFICIENT UNDERGROUND URBAN ROAD AND RAIL INFRASTRUCTURES Manuel Arnáiz Ronda PhD. Civil Engineering President of AETOS
More informationPhoenix Sky Harbor transit guideway bridge
Phoenix Sky Harbor transit guideway bridge by David A. Burrows, Gannett Fleming The evolution of the PHX Sky Train s crossing of Taxiway Romeo At one of the 10 busiest airports in the United States, cast-in-place,
More informationTRAFFIC IMPACT STUDY REPORT FOR PROPOSED OFFICE PROJECT AT 959 SEWARD STREET IN HOLLYWOOD SNYDER PARTNERS
DRAFT TRAFFIC IMPACT STUDY REPORT FOR PROPOSED OFFICE PROJECT AT 959 SEWARD STREET IN HOLLYWOOD Prepared for: SNYDER PARTNERS Prepared by: Crain & Associates 2007 Sawtelle Boulevard, Suite 4 Los Angeles,
More informationArea of Potential Effect Report
Area of Potential Effect Report Southeastern Pennsylvania Transportation Authority (SEPTA) King of Prussia Rail, Extension of the Norristown High Speed Line Upper Merion Township, Montgomery County, and
More informationDesign Meeting Presentation
Contract No. 17ECS-TI-05SP April November 2017 Design Meeting Presentation November 2015 Agenda Items: Introduction (5 min) Overview (10 min) Scope of work (60 min): Schedule and Traffic Staging / Closures
More information3. COLTA / HUGA CONNECTIONS - PRELIMINARY
9 3. COLTA / HUGA CONNECTIONS - PRELIMINARY 3.1 COLTA The Chain of Lakes Trail Association (COLTA) trail, formerly identified as the Chester Spur Line, was completed and opened for use in June 2011. The
More informationSound Transit. Tunnels and Underground Structures Committee January 24, 2011
Sound Transit 1 Tunnels and Underground Structures Committee January 24, 2011 Presentation Outline Overview of ST Construction Completed to date ST2 Plan Summary Construction Underway Commuter Rail Facilities
More informationSLC Airport Project Adds New Scope; Teams Scramble to Stay on Schedule
SLC Airport Project Adds New Scope; Teams Scramble to Stay on Schedule Two sky bridges will connect the parking garage to the second level of the terminal, while an elevated roadway for depa will access
More informationCrystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.
Table 1: South Entrance Table 2: North Entrance 20th St. S 18th St. S Proposed Second Entrance Crystal Drive Existing Station Location Platform Future 4 th Track Future New Airport Connection (by others)
More informationSpadina Avenue Built Form Study Preliminary Report
STAFF REPORT ACTION REQUIRED Spadina Avenue Built Form Study Preliminary Report Date: July 9, 2014 To: From: Wards: Reference Number: Toronto and East York Community Council Director, Community Planning,
More informationA CASE FOR COMPLETING THE JORDAN RIVER PARKWAY: A
A CASE FOR COMPLETING THE JORDAN RIVER PARKWAY: A safe crossing at 9000 South and 850 West Proposed 9000 South Underpass Parkway Timeline Parkway, Trail, and Tourism Facts Blueprint Jordan River 1971 1973
More informationThe 710 Tunnel Threatens Pasadena. March, 2013
The 710 Tunnel Threatens Pasadena March, 2013 Metro Route 710 Study Metro Route 710 Study Metro Study Alternatives Bus Rapid Transit (BRT-6) Light Rail (LRT-4) Metro Study Alternatives Bus Service Transportation
More informationPortland - Milwaukie Light Rail Willamette River Bridge
Willamette River Transit Bridge Portland - Milwaukie Light Rail Willamette River Bridge Design Workshop kh 07.02.09 Proposed Bridge Alignment Willamette River Transit Bridge Marquam Ross Island Cable Stayed
More information9 VIVA DIRECT UNDERGROUND CONNECTION TO THE TORONTO-YORK SPADINA SUBWAY EXTENSION AT THE VAUGHAN METROPOLITAN CENTRE
9 VIVA DIRECT UNDERGROUND CONNECTION TO THE TORONTO-YORK SPADINA SUBWAY EXTENSION AT THE VAUGHAN METROPOLITAN CENTRE The Finance and Administration Committee recommends the adoption of the recommendations
More information