Item # 28. Chief Capital Management Officer Report. November 20, 2008

Size: px
Start display at page:

Download "Item # 28. Chief Capital Management Officer Report. November 20, 2008"

Transcription

1 Item # 28 Chief Capital Management Officer Report November 20,

2 Metro Gold Line Eastside Extension Project Update November Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro Gold Line $898.8 million On-Time/Within Budget Opens in 2009 Gold Line 2

3 Metro Gold Line Eastside Extension Overall Construction Progress ACTIVITY J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Major Construction Activities Trackwork 1st/Boyle & 1st/Soto 1st/Alameda 1st/Utah Indiana 3rd/Ford 3rd/Mednik Pomona/Atlantic Station Architecture and Site Finishes Boyle Heights/Mariachi Plaza & Soto Stations Little Tokyo/Arts District Station Pico/Aliso Station Indiana Station Maravilla Station East LA Civic Station Atlantic Station Third Party Interfaces 1st Street Bridge Widening LAUSD Re-Build Ramona Opportunity High School Systems Installation & Testing/ Pre-Revenue Systems Installation & Integration Testing (Phases I & II) Pre-Revenue Operations Revenue Operations Date 3

4 Metro Gold Line Eastside Extension Overall Construction Progress Construction began in July As of mid-november 2008, the Project is over 90% complete. The Contractor has worked over 3.6 million hours without a lost-time accident. Trackwork installation along the entire six-mile alignment is complete. Construction of the two underground stations at 1st/Boyle and 1st/Soto is 84% complete. Construction of the six at-grade stations is 68% complete. Systems installation is 80% complete. Gold Line 4

5 Metro Gold Line Eastside Extension 101 Freeway Light Rail Transit Bridge Union Station View looking southwest from Union Station towards Downtown Los Angeles. The tie-in to the Pasadena Gold Line tracks was completed in September Installation of all the trackwork along the entire six-mile alignment is complete. Gold Line 5

6 Metro Gold Line Eastside Extension Light Rail Transit Stations LittleTokyo/ Arts District Pico/Aliso Boyle Heights/ Mariachi Plaza 1st/Soto Maravilla Indiana Station East Los Angeles Civic Center Pomona/Atlantic Gold Line 6

7 Metro Gold Line Eastside Extension At-Grade Station Construction 1 st /Alameda and 1 st /Utah Little Tokyo/Arts District Station - Northeast corner of 1st/Alameda. Pico/Aliso Station View east near 1 st /Utah towards Boyle Heights. Construction of the at-grade stations along the west side of the alignment includes concrete site work, canopy installation and systems installation. Gold Line 7

8 Metro Gold Line Eastside Extension Underground Station Construction Boyle Heights/Mariachi Plaza Station Decorative concrete masonry walls are being constructed on the plaza along the adjacent property. A portion of the Station Entrance Plaza near the Mariachi Kiosk is being constructed prior to the November Annual Mariachi Festival. Gold Line 8

9 Metro Gold Line Eastside Extension Underground Station Construction Boyle Heights/Mariachi Plaza Station Station entrance stairs are being constructed from the plaza to the mezzanine levels. Escalators are being installed to connect the various underground levels. Elevators will be installed within the next few months. Gold Line 9

10 Metro Gold Line Eastside Extension Underground Station Construction 1 st /Soto Station Soto Station - Southwest corner of 1st/Soto where the station entrance is being constructed on the plaza level. Soto Station Interior work in the underground rooms progresses as work on the surface structures continues. Gold Line 10

11 Metro Gold Line Eastside Extension At-Grade Station Construction Indiana Station Maravilla Station Construction of the stations from 1st/Indiana and along 3rd Street in East Los Angeles is well underway where the erection of canopies and the installation architectural finishes has begun. East LA Civic Center Station Pomona/Atlantic Station Gold Line 11

12 Metro Gold Line Eastside Extension Pomona/Atlantic Construction Mitigation and Potential Parking Sites Vacant National Core Kaiser Permanente Pomona/Atlantic Parking Site ELA Civic Center Station Pep Boys Auto Parts Pomona/Atlantic Station Vacant Church Parking Lot Gold Line 12

13 Metro Gold Line Eastside Extension Pomona/Atlantic Station Parking A design-build solicitation package for a 258 car parking structure was advertised on July 15, Three bids were received on September 30, 2008 as follows: 1. W. M. Klorman Construction $8,145, ARB Structures, Inc. $8,218, Bomel Construction Company, Inc. $8,445,000 The recommendation is to award the contract to the lowest responsible/responsive bidder, W. M. Klorman Construction in the amount of $8,145,150 was presented to the Metro Board on October 23,2008. However, due to the lack of voting members the Board Item is being carried over for Metro Board approval in December Construction NTP is scheduled for December The parking structure will not be completed until after the forecast July 2009 Revenue Operations Date (ROD) for the Metro Gold Line Eastside Extension Project. Based on our current schedule the parking structure will open up six months after the July 2009 ROD. A contingency plan for interim temporary parking is being established to lease spaces from nearby property owners. Gold Line 13

14 Metro Gold Line Eastside Extension Division 21 Metro Gold Line Midway Yard Body Repair Shop Cornfield Los Angeles River Elysian Park Conversion of Existing Storage Building to Body Repair Shop Division 21 Midway Yard and Shops The existing Storage Building at the Division 21 Metro Gold Line Midway Yard will be converted into a Body Repair Shop for the new 2550 Light Rail Transit Vehicles. The modifications are being planned within the building footprint area. A replacement Storage Building will be constructed at the Division 20 Metro Red Line Yards and Shops site. NORTH Gold Line 14

15 I-405 Sepulveda Pass Widening Project Project Update November

16 I-405 Sepulveda Pass Project Summary Schedule Calendar Year Environmental Preliminary Engineering ROD PE Complete Legend Completed Planned D/B Procurement RFQ IFB Contract Award ROW Acquisitions Start ROW Complete ROW Utility Relocations Start Relocations Complete Relocations D/B Construction NTP Complete Construction 11/08 16

17 I-405 Sepulveda Pass Project Recent Accomplishments Issued IFB on October 10, Issued Amendment No. 1 to the IFB on November 7, Continue informal meetings with qualified bidders to address areas of concern. Selected Metro Project Director, subject to Board approval. Negotiating with Caltrans to finalize field staffing levels. 17

18 I-405 Sepulveda Pass Project Areas of Concern Estimated Project Budget may exceed funding. Significant utility issues (i.e., MWD water line). FHWA/Caltrans design approval process may cause schedule delays. Contractor s concerns about Caltrans/LACMTA. processes could result in more expensive bids. Lawsuits could delay project. 18

19 Expo Line Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update November 20,

20 Expo Line Transit Project PHASE 1 20

21 Expo Line Transit Project Phase 1 Project Status Design Baseline Design is approximately 95% complete Venice/Robertson design is approximately 40% complete Construction Construction is approximately 20% complete Construction Packages Negotiated 14 of the 19 construction packages Third Party Agreements Executed 5 of the 8 third party agreements 21

22 Expo Line Transit Project Phase 1 Project Status CPUC Grade Crossing Applications October 22 nd : ALJ issued his proposed decision denying the pending applications at Harvard and Farmdale in favor of constructing pedestrian overcrossings at these two locations. November 21 st : CPUC Commission Decision 22

23 Expo Line Transit Project Construction Progress Continued Excavation of Trench Structure 23

24 Expo Line Transit Project Construction Progress Trench Structure Roof Slab Concrete Placement 24

25 Expo Line Transit Project Construction Progress National Blvd Bridge Abutment 1 Concrete Placement 25

26 Expo Line Transit Project Construction Progress La Brea Aerial Structure CIDH Pile Installation 26

27 Expo Line Transit Project Construction Progress Installation of 6-Way Ductbank in Segment B 27

28 Expo Line Transit Project Phase 1 Project Status Project Budget Summary Construction Budget 14 of 19 construction packages have been negotiated in an amount totaling $347 million Currently within the revised construction budget Project Budget All tasks are within the overall project budget Remaining significant risks to the budget include: - Contracts yet to be negotiated (including Storage and Inspection Facility) - Any significant contractor claims - Changes to the Farmdale and Harvard crossings - Any significant owner related project delays 28

29 Expo Line Transit Project PHASE 2 29

30 Expo Line Transit Project Phase 2 Project Status Phase 2 Milestones Activity Scheduled Completion Date Forecast Completion Date Status Comments Scoping Meetings & Report Mar-07 May-07 Complete Screening of Alternatives May-07 Oct-07 Complete Delay in receiving ridership model from Metro Administrative Draft to FTA Oct-07 Nov-08 Delay due to need to recalibrate model received from Metro. Additional delays in grade crossing and other technical analyses as well as in preparing the Draft document. Start Public Hearings on Draft DEIS/DEIR Board Adoption of LPA May-08 Winter-09 Feb-08 Winter-09 FTA must sign off on Draft DEIS before document can be circulated Request to enter Preliminary Engineering (PE) May-08 Winter-09 30

Metro Gold Line Eastside Extension Review Advisory Committee October 9, 2008

Metro Gold Line Eastside Extension Review Advisory Committee October 9, 2008 Review Advisory Committee October 9, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within

More information

Metro Gold Line Eastside Extension Review Advisory Committee May 8, 2008

Metro Gold Line Eastside Extension Review Advisory Committee May 8, 2008 Review Advisory Committee May 8, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-Grade and 2 Underground) Park & Ride Facility at Pomona/Atlantic Direct Connection to the Pasadena Metro at Union

More information

Los Angeles County Metropolitan Transportation Authority. Metro Rail Gold Line Eastside Extension - Operations

Los Angeles County Metropolitan Transportation Authority. Metro Rail Gold Line Eastside Extension - Operations Los Angeles County Metropolitan Transportation Authority Metro Rail Gold Line Eastside Extension - Operations Metro Gold Line System Description The Metro Gold Line is currently a 13.6 mile, double track

More information

Executive Summary. See Figure ES-5 on page 9. Figure ES-6: Typical At-Grade Alignment. Figure ES-7: Typical Underground Alignment

Executive Summary. See Figure ES-5 on page 9. Figure ES-6: Typical At-Grade Alignment. Figure ES-7: Typical Underground Alignment Figure ES-5 shows all of the possible LRT routes and stations identified for study in the Draft EIS/EIR. The features and impacts of each of the build alternatives are described in the following section.

More information

West Santa Ana Branch Transit Corridor. Community Meetings March 12, 13, 17 & 19, 2018

West Santa Ana Branch Transit Corridor. Community Meetings March 12, 13, 17 & 19, 2018 West Santa Ana Branch Transit Corridor Community Meetings March 12, 13, 17 & 19, 2018 Purpose of this Meeting > Update on Public Scoping comments received > Why Metro is revisiting the Northern Alignments

More information

Measure R Program Update

Measure R Program Update Item 1 Program Update March 17, 2011 Independent Taxpayers Oversight Committee February 18 th Meeting held: Reviewed Audits of FY10 Expenditures Set Public Hearing Date on Audit Findings for April 18th

More information

SCOPING INFORMATION PACKET

SCOPING INFORMATION PACKET SCOPING INFORMATION PACKET Project Description The proposed project would provide a direct link connecting several light rail lines in operation or in construction, including the Metro Gold Line to Pasadena,

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Go Local Fixed-Guideway Program History and Project Update. PowerPoint 3

ORANGE COUNTY TRANSPORTATION AUTHORITY. Go Local Fixed-Guideway Program History and Project Update. PowerPoint 3 ORANGE COUNTY TRANSPORTATION AUTHORITY Go Local Fixed-Guideway Program History and Project Update PowerPoint 3 Santa Ana-Garden Grove Fixed Guideway Project OCTA Board of Directors September 26, 2011 Project

More information

Silver Line Rail Project Update

Silver Line Rail Project Update Silver Line Rail Project Update April 2013 Project Map 2 Silver Line, Phase 1 Service Pattern 3 Project Overview Silver Line Dulles Metrorail is a 23-mile extension of the existing Orange Line Total Project

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2014 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2015 Introduction The

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting November 3, 2011 Introduction Local lead agency: Metro Federal lead agency: Federal Transit

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting Culver City Senior Center Wednesday, July 16, 2008 Description 8.6 mile corridor from downtown to Culver City in West Los Angeles 1.3

More information

Link Union Station (LINK US)

Link Union Station (LINK US) Link Union Station (LINK US) Presentation for LAUS Master Commercial Developer Industry Forum October 13 th 2017 Jeanet Owens, PE Senior Executive Officer Program Management / Regional Rail Project Overview

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)

More information

metro.net See Inside Get 2 For 1 At MOCA Metro January 2010 monthly Save 50% To LA Clippers

metro.net See Inside Get 2 For 1 At MOCA Metro January 2010 monthly Save 50% To LA Clippers See Inside Get For At MOCA metro.net Metro January 00 monthly Save 0% To LA Clippers Metro Gold Line train breaks through banner at official dedication of new light rail to East LA. Thousands Celebrate

More information

Claremont Project Background and Update Community Meeting September 11, 2017

Claremont Project Background and Update Community Meeting September 11, 2017 Claremont Project Background and Update Community Meeting September 11, 2017 Topics Project Background Claremont Segment Information Project Timeline Upcoming Discussion Items Upcoming Meetings Questions

More information

LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY BID TABULATION

LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY BID TABULATION FACILITY/LOCATION 36 MONTH BASE A. BUS DIVISIONS, TERMAINALS AND LAYOVER LOTS MONTHLY MONTHLY MONTHLY SAN FERNANDO $1,500.00 $1,459.00 $2,122.00 SAN GABRIEL VAL $1,500.00 $1,459.00 $2,122.00 DIVISION 1

More information

Transportation Supporting Dulles Airport

Transportation Supporting Dulles Airport Transportation Supporting Dulles Airport Committee for Dulles Economic Development and Transportation Committee July 12, 2018 Tom Biesiadny, Director Fairfax County Multiple Transportation Improvements

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2011 Metropolitan Washington Airports Authority 1593 Spring Hill Road, Suite 300 Vienna, Virginia 22182 JANUARY 2012 Introduction The

More information

Sound Transit Operations March 2018 Service Performance Report. Ridership

Sound Transit Operations March 2018 Service Performance Report. Ridership March 218 Service Performance Report Ridership Total Boardings by Mode Mar-17 Mar-18 % YTD-17 YTD-18 % ST Express 1,622,116 1,47,79-4.6% 4,499,798 4,428,14-1.6% Sounder 393,33 39,6.% 1,74,96 1,163,76 8.3%

More information

Dulles Corridor Metrorail Project Update Dulles Area Transportation Association August 25, 2009

Dulles Corridor Metrorail Project Update Dulles Area Transportation Association August 25, 2009 Dulles Corridor Metrorail Project Update Dulles Area Transportation Association August 25, 2009 Patty Nicoson President Dulles Corridor Rail Association Proposed Toll Rate Increase on Dulles Toll Road

More information

Sound Transit Operations January 2018 Service Performance Report. Ridership

Sound Transit Operations January 2018 Service Performance Report. Ridership January 218 Service Performance Report Ridership Total Boardings by Mode Jan-17 Jan-18 % YTD-17 YTD-18 % ST Express 1,3,33 1,7,91.3% 1,3,33 1,7,91.3% Sounder 367,33 416,8 13.3% 367,33 416,8 13.3% Tacoma

More information

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation Silver Line Update Committee for Dulles March 2, 2017 Mark Canale Fairfax County Department of Transportation Phase 1 Summary Old Meadow Road Realignment design work proceeding, construction to be completed

More information

About the Foothill Gold Line

About the Foothill Gold Line About the Foothill Gold Line Board of Directors Marisol Rodriguez Member (Los Angeles Appointee) John Fasana Member (Metro Appointee) Doug Tessitor Chair (Pasadena Appointee) Sam Pedroza Vice Chair (SGVCOG

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: November 18, 2013 SUBJECT: YONGE-EGLINTON AND EGLINTON WEST INTERCHANGE STATIONS METROLINX EGLINTON CROSSTOWN LIGHT RAIL TRANSIT PROJECT

More information

? 0-? WA", ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1-

? 0-? WA, ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1- I 1 RW MT BOARD 0*1-.04 11 Los Angeles World Airports REPORT TO THE 0 AIRPORT COMMISSIONERS Meeting Date: Approved /by: Dave Jone - Airline Prop nd Concession Services ) 7/13/2017 Reviewed by:.',...ek

More information

CITY COUNCIL AGENDA MEMORANDUM

CITY COUNCIL AGENDA MEMORANDUM To: Mayor and City Council From: Charles Ozaki, City and County Manager Prepared By: Kevin Standbridge, Deputy City and County Manager Katie Allen, City and County Engineer David Shinneman, Community Development

More information

South Bay Metro Light Rail Extension. Summer/Fall 2017 Project Briefings

South Bay Metro Light Rail Extension. Summer/Fall 2017 Project Briefings South Bay Metro Light Rail Extension Summer/Fall 2017 Project Briefings Meeting Agenda 2 Project History Project Development Schedule Feedback 3 Project History Alternatives Analysis Measure R $272M 2008

More information

Capital Programs Update

Capital Programs Update Capital Programs Update Capital Programs Summary 2 Grade Separations - Overview Seven grade separation projects planned on the BNSF Orangethorpe corridor Cost: from $65 to $117 million Current Status:

More information

Expo E-News. Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2. Keeping Our Community Informed

Expo E-News. Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2. Keeping Our Community Informed Expo E-News Keeping Our Community Informed Winter 2014 Santa Monica s Getting Ready for Expo! Phase 2 Update Page 2 In this Issue : Page 4: Construction Update Page 6: Artist Profiles For more information

More information

Sound Transit Operations January 2017 Service Performance Report. Ridership. Total Boardings by Mode

Sound Transit Operations January 2017 Service Performance Report. Ridership. Total Boardings by Mode January 217 Service Performance Report Ridership ST Express Sounder Tacoma Link Link Paratransit Jan-16 Jan-17 % 1,433,7 1,3,33 4.9% 331,27 7,121 98,411 3,633 Total Boardings by Mode 363,6 74,823 1,76,914

More information

South Bay Light Rail Extension Summer/Fall 2017 Project Briefing

South Bay Light Rail Extension Summer/Fall 2017 Project Briefing South Bay Light Rail Extension Summer/Fall 2017 Project Briefing Meeting Agenda 2 Project History Project Development Schedule Feedback Study Area Project History 4 Alternatives Analysis 2008 Measure R

More information

Regional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017

Regional Connector Transit Project Community Leadership Council. 2 nd Hope Station & Flower St Committees January 17, 2017 Regional Connector Transit Project Community Leadership Council 2 nd Hope Station & Flower St Committees January 17, 2017 1 EAT SHOP PLAY LOCAL 2 Eat Shop Play Local > Free Metro marketing campaign > Make

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 1 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)

More information

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering City Council Report To: From: Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering City Council Meeting: February 28, 2017 Agenda Item: 3.H Subject: Award of Feasibility/Design-Build

More information

BOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS

BOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS 1 [1 11 BOARD ITO Aide 001:4 Los Angeles World Airports REPORT TO THE Approved by: Justin rbacci - hief Innovation and Commercial St tegy Officer (--(AtSotA_ /1//r/'(10 PV Reviewed by: Samson Mengistu

More information

The Benefits of a Whittier Blvd. Alignment for the Metro Eastside Extension

The Benefits of a Whittier Blvd. Alignment for the Metro Eastside Extension The Benefits of a Whittier Blvd. Alignment for the Metro Eastside Extension by Bart Reed The Transit Coalition P.O. Box 567 San Fernando, CA 91341-0567 (818) 367-1661 1 Introduction Metro has released

More information

METRO OPERATIONS COMMITTEE

METRO OPERATIONS COMMITTEE Los Angeles County Metropolitan Transportation Authority Item 1 CHIEF OPERATIONS OFFICER S S REPORT METRO OPERATIONS COMMITTEE Lonnie Mitchell Chief Operations Officer May 19, 20 1 Employee Recognition

More information

November 9, Society of American Military Engineers

November 9, Society of American Military Engineers November 9, 2016 Society of American Military Engineers Transit Operator Transportation Planner Transportation Infrastructure Builder Transportation Funding Overseer 2 1,433 square-mile service area (nearly

More information

Vasona Light Rail Signal Design Challenges. Hugh D. MacGillivray, Hatch Mott MacDonald Dennis Mellon, Santa Clara County Transportation Authority

Vasona Light Rail Signal Design Challenges. Hugh D. MacGillivray, Hatch Mott MacDonald Dennis Mellon, Santa Clara County Transportation Authority Vasona Light Rail Signal Design Challenges Hugh D. MacGillivray, Hatch Mott MacDonald Dennis Mellon, Santa Clara County Transportation Authority Abstract The Vasona line is the most recent extension of

More information

Capital Metropolitan Transportation Authority. Monthly Performance Report

Capital Metropolitan Transportation Authority. Monthly Performance Report Capital Metropolitan Transportation Authority Monthly Performance Report AUGUST 2010 Ridership Report August 23, 2010 Budget to Actual Ridership Budget Target: 2,290,590 Actual: 2,300,796 Ridership Comparison

More information

Sound Transit Operations February 2018 Service Performance Report. Ridership

Sound Transit Operations February 2018 Service Performance Report. Ridership February 218 Service Performance Report Ridership Total Boardings by Mode Feb-17 Feb-18 % YTD-17 YTD-18 % ST Express 1,373,96 1,372,88 -.1% 2,877,294 2,88,719.1% Sounder 314,96 32,187 11.9% 681,923 768,69

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 1 Project Overview Mainline Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017

Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017 Crenshaw/LAX Transit Project Construction Update Community Meeting November 29 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

RETAIL FOR LEASE. 807 Flower Street

RETAIL FOR LEASE. 807 Flower Street RETAIL FOR LEASE 807 Flower Street F I N A N C I A L D I S T R I C T D T L A Ea site plan retail space ± 7,350 SF* *rate negotiable th Elevation West Elevation 46.535 Flower Street Alley 14.905 2.782 North

More information

June 2017: 700 Piles 9 Weeks and 3 Days Pile Caps / Tie Beams Roof Foundations

June 2017: 700 Piles 9 Weeks and 3 Days Pile Caps / Tie Beams Roof Foundations Welcome FAA FAA October 2016: Broke Ground October 2016 Excavated 6.2 Million Cubic Yards Excavated 100,000 Cubic Yards in one day at peak 36 30 Yard Scrappers 10 30 Yard Dump Trucks 85 Days to Complete

More information

Selection of a Locally Preferred Alternative for the Interstate 405 Improvement Project Between State Route 55 and Interstate 605.

Selection of a Locally Preferred Alternative for the Interstate 405 Improvement Project Between State Route 55 and Interstate 605. ORANGE COUNTY TRANSPORTATION AUTHORITY Selection of a Locally Preferred Alternative for the Interstate 405 Improvement Project Between State Route 55 and Interstate 605 PowerPoint San Diego Freeway (Interstate

More information

EXHIBIT 1. BOARD AUTHORIZATION FOR PUBLIC HEARING AND SUBSEQUENT ISSUANCE OF A JOINT DEVELOPMENT SOLICITATION

EXHIBIT 1. BOARD AUTHORIZATION FOR PUBLIC HEARING AND SUBSEQUENT ISSUANCE OF A JOINT DEVELOPMENT SOLICITATION EXHIBIT 1. BOARD AUTHORIZATION FOR PUBLIC HEARING AND SUBSEQUENT ISSUANCE OF A JOINT DEVELOPMENT SOLICITATION Washington Metropolitan Area Transit Authority Board Action/Information Summary @Action O Information

More information

Establishes a fare structure for Tacoma Link light rail, to be implemented in September 2014.

Establishes a fare structure for Tacoma Link light rail, to be implemented in September 2014. RESOLUTION NO. R2013-24 Establish a Fare Structure and Fare Level for Tacoma Link MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE: Board 09/26/2013 Final Action Ric Ilgenfritz, Executive Director,

More information

Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017

Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017 Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017 1 Project Overview Design-Build Contractors: Mainline - Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Northwest Corridor LRT Line to Irving/DFW

Northwest Corridor LRT Line to Irving/DFW Northwest Corridor LRT Line to Irving/DFW AGENCY SCOPING May 25, 2005 NW to Irving/DFW Agenda: Introductions Project Development Process Project Update Federal Involvement Scoping Project Schedule Decisions

More information

Implications of Construction Cost Escalation

Implications of Construction Cost Escalation Implications of Construction Cost Escalation 2007 ACI-NA Economics and Finance Conference James Gill, CPA Deputy Airport Director Finance, Business & Administration Raleigh-Durham Airport Authority Presentation

More information

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the

More information

WATERFRONT PROGRAM PROGRESS REPORT

WATERFRONT PROGRAM PROGRESS REPORT WATERFRONT PROGRAM PROGRESS REPORT 2016 (April - June) Highlights from 2016 In April, released the Supplemental Draft Environmental Impact Statement (EIS) for the Alaskan Way, Promenade, and Overlook Walk.

More information

COMING SOON! 801 S. Olive Street

COMING SOON! 801 S. Olive Street COMING SOON! 801 S. Olive Street F I N A N C I A L D I S T R I C T D T L A site plan retail space ± 9,140 SF* *rate negotiable Residential Lobby Retail 1 6127 SF 8th Street Retail 2 3013 SF Olive Street

More information

Sound Transit Operations March 2017 Service Performance Report. Ridership. Total Boardings by Mode

Sound Transit Operations March 2017 Service Performance Report. Ridership. Total Boardings by Mode March 217 Service Performance Report Ridership ST Express Sounder Tacoma Link Link Paratransit Mar-16 Mar-17 % 1,83,4 1,621,49 2.4% 37,496 82,631 1,264,47 3,821 Total Boardings by Mode 389,98 87,39 1,89,43,297

More information

BOARD OF AIRPORT COMMISSIONERS

BOARD OF AIRPORT COMMISSIONERS 1 8/17/2018 8/21/2018 8/16/2018 i ElY MY Y I : JH MT BY...01,, III1*.ji,"1.111Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: la Approved by: e1. "ampbell, Chief Airports

More information

25 th Avenue Grade Separation. Community Meeting November 13, 2018

25 th Avenue Grade Separation. Community Meeting November 13, 2018 25 th Avenue Grade Separation Community Meeting November 13, 2018 Agenda I. Project Need II. Project Benefits III. Project Description IV. Funding V. Schedule VI. Construction VII. Next Steps 2 Project

More information

BOARD OF LOS ANGELES CONVENTION & TOURISM DEVELOPMENT and LOS ANGELES CONVENTION & EXHIBITION CENTER AUTHORITY JOINT COMMISSION MEETING MINUTES

BOARD OF LOS ANGELES CONVENTION & TOURISM DEVELOPMENT and LOS ANGELES CONVENTION & EXHIBITION CENTER AUTHORITY JOINT COMMISSION MEETING MINUTES BOARD OF LOS ANGELES CONVENTION & TOURISM DEVELOPMENT and LOS ANGELES CONVENTION & EXHIBITION CENTER AUTHORITY JOINT COMMISSION MEETING MINUTES 9:00 a.m. The Board of Los Angeles Convention and Tourism

More information

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015 East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities

More information

2018 Service Implementation Plan Executive Summary

2018 Service Implementation Plan Executive Summary 2018 Service Implementation Plan Executive Summary March 2018 2018 SERVICE IMPLEMENTATION PLAN Executive Summary 2018 Service Implementation Plan Each year, Sound Transit prepares a Service Implementation

More information

Welcome. Sign in Pick up comment form Visit stations to learn more Submit your comment form

Welcome. Sign in Pick up comment form Visit stations to learn more Submit your comment form PROPOSED FARE CHANGES Welcome Sign in Pick up comment form Visit stations to learn more Submit your comment form We re considering a new fare policy The Sound Transit Board of Directors is considering

More information

PROGRESS REPORT WATERFRONT PROGRAM. Q (January - March) Highlights from Q1 2018

PROGRESS REPORT WATERFRONT PROGRAM. Q (January - March) Highlights from Q1 2018 WATERFRONT PROGRAM PROGRESS REPORT Q1 2018 (January - March) Highlights from Q1 2018 Advanced Pier 62 Rebuild construction including completion of Pier 62 demolition in February 2018. Prepared for the

More information

Sound Transit Operations January 2014 Service Performance Report. Ridership

Sound Transit Operations January 2014 Service Performance Report. Ridership Ridership Total Boardings by Mode Mode Jan-13 Jan-14 % YTD-13 YTD-14 % ST Express 1,343,290 1,426,928 6.2% 1,343,290 1,426,928 6.2% Sounder 245,135 256,775 4.7% 245,135 256,775 4.7% Tacoma Link 86,229

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 1, 2012 SUBJECT: LRT PROJECTS IN TORONTO - STATUS REPORT INFORMATION ITEM RECOMMENDATION It is recommended that the Commission

More information

Front Carport Design Standards, Requirements & Application

Front Carport Design Standards, Requirements & Application Front Carport Design Standards, Requirements & Application THIS PAGE INTENTIONALLY LEFT BLANK. Carport: A structure designed or used to shelter vehicles that is open on at least two sides. Carport shall

More information

Corridor Management Committee Meeting. April 2, 2014

Corridor Management Committee Meeting. April 2, 2014 Corridor Management Committee Meeting April 2, 2014 1 Today s Topics Welcome Approval of Minutes Resolutions Response to March 26 CMC Questions Staff Recommendation on Project Scope and Budget Public Testimony

More information

Why we re here: For educational purposes only

Why we re here: For educational purposes only Transportation 2050 Why we re here: For educational purposes only Transportation 2050 Bus Elements PUBLIC TRANSIT DEPARTMENT City of Phoenix Citizens Committee on the Future of Phoenix Transportation (CCFPT)

More information

Sound Transit. Tunnels and Underground Structures Committee January 24, 2011

Sound Transit. Tunnels and Underground Structures Committee January 24, 2011 Sound Transit 1 Tunnels and Underground Structures Committee January 24, 2011 Presentation Outline Overview of ST Construction Completed to date ST2 Plan Summary Construction Underway Commuter Rail Facilities

More information

Port MacKenzie Rail Extension

Port MacKenzie Rail Extension Port MacKenzie Rail Extension Project The Matanuska-Susitna Borough (MSB) and the Alaska Railroad Corporation (ARRC) jointly propose construction and operation of a new rail line to connect the Borough

More information

801 S. OLIVE STREET GROUND FLOOR RETAIL

801 S. OLIVE STREET GROUND FLOOR RETAIL 801 S. OLIVE STREET GROUND FLOOR RETAIL SITE PLAN RETAIL SPACE ± 3,086 SF* *RATE NEGOTIABLE Residential Lobby 8TH STREET Retail D 1344 SF Retail C 1742 SF Retail B 3155 SF Olive Street OLIVE STREET THE

More information

Port MacKenzie Rail Extension

Port MacKenzie Rail Extension Port MacKenzie Rail Extension Project The Matanuska-Susitna Borough (MSB) and the Alaska Railroad Corporation (ARRC) jointly propose construction and operation of a new rail line to connect the Borough

More information

Madison Metro Transit System

Madison Metro Transit System Madison Metro Transit System 1101 East Washington Avenue Madison, Wisconsin, 53703 Administrative Office: 608 266 4904 Fax: 608 267 8778 TO: FROM: SUBJECT: Plan Commission Timothy Sobota, Transit Planner,

More information

E-Newsletter Keeping Our Community Informed Volume 1, Issue 4

E-Newsletter Keeping Our Community Informed Volume 1, Issue 4 W ith the Expo Light Rail Line under heavy construction for almost two years now, a variety of construction activities are taking place up and down the whole alignment. In Downtown Los Angeles utility

More information

Public Open House. Chief Peguis Trail Project

Public Open House. Chief Peguis Trail Project Public Open House Chief Peguis Trail Project CHIEF PEGUIS TRAIL OPEN HOUSE Welcome! Please browse the display boards Project Engineers and City of Winnipeg representatives are available to address your

More information

Preliminary Agenda Indianapolis Airport Authority August 3, :30 a.m. 2. Approve Minutes of the Regular Meeting of July 20, 2007.

Preliminary Agenda Indianapolis Airport Authority August 3, :30 a.m. 2. Approve Minutes of the Regular Meeting of July 20, 2007. Preliminary Agenda Indianapolis Airport Authority August 3, 2007 8:30 a.m. 1. Call to order. 2. Approve Minutes of the Regular Meeting of July 20, 2007. 3. Ordinances and Resolutions PUBLIC HEARING ON

More information

Central Broward Transit (CBT) Phase 1 Public Open House January 21, 2016

Central Broward Transit (CBT) Phase 1 Public Open House January 21, 2016 Central Broward Transit (CBT) Phase 1 Public Open House January 21, 2016 CBT Phase 1/Wave Extensions AGENDA What is the CBT Phase 1 Project? Who are the Project Partners? Where is the Project Located?

More information

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018 COUNTY OF INYO REQUEST FOR QUALIFICATIONS For Airport Environmental Services Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018 County of Inyo Public Works Department P.O.

More information

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation

More information

Memorandum. Pauline Medrano Mitchell Rasansky Steve Salazar. Power Transmission Lines in the Trinity River Corridor Follow-up CITY OF DALLAS

Memorandum. Pauline Medrano Mitchell Rasansky Steve Salazar. Power Transmission Lines in the Trinity River Corridor Follow-up CITY OF DALLAS Memorandum CITY OF DALLAS DATE April 18, 2008 TO Trinity River Corridor Project Committee Members: David A. Neumann (Chairman) Mayor Pro Tern Dr. Elba Garcia (Vice-Chair) Deputy Mayor Pro Tern Dwaine Caraway

More information

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018 BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO

More information

A. CONCLUSIONS OF THE FGEIS

A. CONCLUSIONS OF THE FGEIS Chapter 11: Traffic and Parking A. CONCLUSIONS OF THE FGEIS The FGEIS found that the Approved Plan will generate a substantial volume of vehicular and pedestrian activity, including an estimated 1,300

More information

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651)

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651) DATE: March 27, 2012 METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN 55101 Phone (651) 602-1000 TDD (651) 291-0904 TO: Metropolitan Parks and Open Space Commission FROM: Arne Stefferud, Planning

More information

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Form PDES 8 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Summary of Duties: A Senior Airport Engineer performs the more difficult and

More information

metro.net See Inside Bus Service Public Hearings Feb Metro February 2010 monthly Get $3 Off Chinatown Firecracker 5K/10K

metro.net See Inside Bus Service Public Hearings Feb Metro February 2010 monthly Get $3 Off Chinatown Firecracker 5K/10K See Inside Bus Service Public Hearings Feb. -0 metro.net Metro February 00 monthly Get $ Off Chinatown Firecracker K/0K For convenient connections to the Go Metro Destination Discounts listed here, check

More information

ENVIRONMENT, TRANSPORTATION & PUBLIC SAFETY STANDING COMMITTEE CONSOLIDATED AGENDA

ENVIRONMENT, TRANSPORTATION & PUBLIC SAFETY STANDING COMMITTEE CONSOLIDATED AGENDA Members: ENVIRONMENT, TRANSPORTATION & PUBLIC SAFETY STANDING COMMITTEE CONSOLIDATED AGENDA (available also at www.citywindsor.ca) Wednesday, September 27, 2017 4:30 o clock p.m. Council Chambers, 3rd

More information

2 YORK REGION TRANSIT VEOLIA AGREEMENT AMENDMENT 91 CALDARI ROAD

2 YORK REGION TRANSIT VEOLIA AGREEMENT AMENDMENT 91 CALDARI ROAD 2 YORK REGION TRANSIT VEOLIA AGREEMENT AMENDMENT 91 CALDARI ROAD The Transit Committee recommends the following: 1. Receipt of the presentation by Rick Takagi, Manager, Operations, York Region Transit;

More information

Spadina Avenue which would include two new underground stations located at Yonge Street and at University Avenue.

Spadina Avenue which would include two new underground stations located at Yonge Street and at University Avenue. TORONTO TRANSIT COMMISSION REPORT No S7 MEETING DATE June 4, 1968 FROM: General Manager Subway Construction Date June 3, 1968 Subject: QUEEN STREET SUBWAY FOR STREETCAR OPERATION The Commission, at its

More information

25 th Avenue Grade Separation. December 13, 2017

25 th Avenue Grade Separation. December 13, 2017 25 th Avenue Grade Separation December 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25

More information

Phoenix Sky Harbor transit guideway bridge

Phoenix Sky Harbor transit guideway bridge Phoenix Sky Harbor transit guideway bridge by David A. Burrows, Gannett Fleming The evolution of the PHX Sky Train s crossing of Taxiway Romeo At one of the 10 busiest airports in the United States, cast-in-place,

More information

Metro Green Line to LAX. January, 2012

Metro Green Line to LAX. January, 2012 Metro Green Line to LAX 2 Agenda Context Airport Connection Types Project Process Questions and Discussion Los Angeles Lacks a Strong Airport Transit Connection 3 Airports in the U.S. with current or planned

More information

Crystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.

Crystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S. Table 1: South Entrance Table 2: North Entrance 20th St. S 18th St. S Proposed Second Entrance Crystal Drive Existing Station Location Platform Future 4 th Track Future New Airport Connection (by others)

More information

National Society of Professional Engineers. Charles S. Carnaggio, PE Project Director July 2, 2014

National Society of Professional Engineers. Charles S. Carnaggio, PE Project Director July 2, 2014 National Society of Professional Engineers Charles S. Carnaggio, PE Project Director July 2, 2014 Phase 1 Opening Date: July 26, 2014 Dulles Corridor Metrorail Project At-a-Glance Seamless integration

More information

Planned Procurement Opportunities Report. June 2017

Planned Procurement Opportunities Report. June 2017 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016 PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016 DATE: TO: FROM: Michael Ehl, Director, Airport Operations Wayne Grotheer, Director, Aviation Project

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: SUBJECT: Resubmitted December 19, 2012 November 21, 2012 MODERNIZING THE TTC A NEW APPROACH TO COMMUNICATIONS, COMMUNITY

More information

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015 THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015 Pursuant to the California Department of Transportation

More information

Metro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements

Metro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements Metro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements Jan Perry Councilwoman, District 9 Welcome Remarks Arthur T. Leahy Chief Executive Officer, Metro Metro ExpressLanes Overview

More information

Others in Attendance: Airport Manager, Billie Jo Grafton, Airport Clerk, Claudia Chavarria.

Others in Attendance: Airport Manager, Billie Jo Grafton, Airport Clerk, Claudia Chavarria. International Airport Commission Meeting Minutes Airport Terminal Building City of Del Rio, Texas 1104 West 10 th St. Del Rio, Texas 78840 Wednesday August 24, 2011 6:00 P.M. ************************************************************************

More information

Spokane Airports 9000 W. Airport Dr. #204 Spokane, WA (509) SPOKANE AIRPORT BOARD

Spokane Airports 9000 W. Airport Dr. #204 Spokane, WA (509) SPOKANE AIRPORT BOARD Spokane Airports 9000 W. Airport Dr. #204 Spokane, WA 99224 (509) 455-6455 www.spokaneairports.net SPOKANE AIRPORT BOARD Chair: Vice Chair: Secretary: Nancy Vorhees Ezra Eckhardt Jennifer West Board Members:

More information