Northeast Corridor Transportation Update
|
|
- Benedict Turner
- 5 years ago
- Views:
Transcription
1 Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014
2 Today s presentation includes: I-485 Outer Loop Completion Piedmont Improvement Program/Double Track Project Grier Road Grade Separation Sugar Creek Grade Separation Graham Street Extension Bridges on U.S. 29 over Mallard Creek Intersection Improvements ~ N.C. 49/Cameron Boulevard UNC Charlotte Leftover at Alumni Way
3 Street Closures Related to Rail & BLE Construction Grier Road grade separation North Tryon Street bridge replacement over Mallard Creek Eastway Drive bridge closure Sugar Creek Road closure 36 th Street closure Craighead Road permanent closure Eastern Circumferential grade separation Newell Hickory Grove Rd permanent closure Roadway Projects (CDOT & NCDOT) I-485 outer loop I-85 / I-485 interchange Graham Street extension Orr Road extension* City Boulevard extension Rocky River Road West Back Creek Church Road University Pointe Boulevard extension (I-85 South Bridge)* I-85 North Bridge* McCullough Drive streetscape/extension* JW Clay Boulevard streetscape*
4 4
5 I-485 Outer Loop ~ Mecklenburg County When complete, the 67-mile loop will connect to I-85 and I-77 from the north and south
6 I-485/Charlotte Outer Loop Completion
7 Adding 12 miles of second track Charlotte to Harrisburg Project improvements include: Realigning railroad curves north of Rocky River Road in Concord to Orr Road in Charlotte Improves travel time Upgrading crossings Back Creek Church, McLean and Orr Roads Improves safety Double Track Project (P-5208ACG) Project completion scheduled for Spring 2017
8 Grier Road Grade Separation at Old Concord Road Construct bridge on Grier Road over NCRR Raise Old Concord Road to meet the new Grier Road bridge Close at-grade NCRR track crossing at Newell-Hickory Grove Road Improve Orr Road, Grierview Lane, Branch Hill Circle, Lauren Village Drive and Farmfield Lane Grier Road Grade Separation (P-5208H) Project completion scheduled for December 2015
9 9
10 Sugar Creek Road Grade Separation New structure will carry Sugar Creek Road over existing and future railroad tracks Blue Line Extension will also travel under the new grade separation
11 Approximately three miles between Sugar Creek Road and WT Harris Boulevard, some on new location Four-lane divided roadway, curb/gutter, bike lanes, raised concrete medians, concrete turnouts for CATS buses Scheduled completion April 30, 2017 Graham Street Extension
12 Bridge Replacements ~ U.S. 29 south of Mallard Creek Church Road
13 Intersection Improvements ~ N.C. 49 at Cameron Boulevard 13
14 UNC Charlotte Left-over at Alumni Way
15 Charlotte Area Transit System LYNX Blue Line Extension
16 LYNX Blue Line Extension Project Overview 9.3 miles, 11 stations 4 park and ride facilities Approximately 3,100 parking spaces Accommodates 3-car trains 25,000+ daily riders Improvements to North Tryon St. Connects UNC Charlotte campuses 22 minute commute from Uptown to UNC Charlotte Initial peak period service 7.5 minute frequency Connecting bus services Revenue service in 2017
17 What s happening out there? Private utility relocation Retaining walls Widening the roadway Temporary bridge over Toby Creek Access road into UNC Charlotte campus Temporary sidewalk built in front of CMC University Temporary sidewalk near Institute Circle
18 W. T. Harris Boulevard Bridge University Place Station Hospital
19 Charlotte Research Institute UNC Charlotte entrance BLE travels under North Tryon to access campus Northbound traffic shifts to southbound side of North Tryon during tunnel construction
20 Maintaining Access Temporary signage Detour signs Temporary driveway access Temporary asphalt sidewalks Temporary pedestrian lane
21 Rocky River Road West Improvements ¾-mile streetscape along Rocky River Road West from North Tryon Street to Batavia Lane Provides connection for several neighborhoods to access the LYNX BLE stations 2-lane section with bike lanes, planting strip and sidewalk
22 Northeast Corridor Bridges over I-85 New Bridges over I-85: 1. South: University Pointe Blvd. Extension, from Ikea Blvd. to IBM Dr North: From Research Dr. to J.W. Clay Blvd. 1 22
23 Southern Bridge: IBM Drive to Ikea Blvd. Partially funded in 2008 bond (design and real estate acquisition) Construction funding proposed in 2014 bond o Start construction: Summer 2015 o Open to traffic: Spring 2017 Includes offsite work on W. T. Harris Blvd. in University Research Park as well Approximately $15,000,000 total
24 Photo circa 2010 Southern Bridge: IBM Drive to Ikea Blvd. New Bridge Completed View from Martin Middle School
25 How You Can Stay Informed
UNIVERSITY CITY TOMORROW S URBAN CENTER
UNIVERSIT Y CIT Y TO M O R R O W S U R B A N C E N T E R ABOUT University City: Tomorrow s Urban Center University City is poised to begin a new chapter as the opening of Charlotte s LYNX Blue Line Extension
More informationMALLARD POINTE MALLARD POINTE. Shopping Center. Highway 29 & J.W. Clay Boulevard. Charlotte, North Carolina. 1,500 sf, 12,000 * sf and 80,684 * sf
Charlotte, North Carolina MALLARD POINTE Shopping Center Highway 29 & J.W. Clay Boulevard Charlotte, North Carolina, 12,000 * sf and 80,684 * sf *can subdivide FOR LEASE 831 E. Morehead Street, Suite 245,
More informationCabarrus County line. Overland Connector. to Newell Park. Overland Connector
Back Creek Back Creek is a east-west trail corridor proposed within the East Park District. The corridor s endpoints are the Cabarrus County line to the east and Reedy Creek Park to the southwest. The
More informationPublic Information Center August 12, 2010
Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General
More informationFDOT Treasure Coast Traffic Report through
FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;
More informationAVAILABLE FOR LEASE MALLARD POINTE. Shopping Center CHARLOTTE, NORTH CAROLINA. Highway 29 & J.W. Clay Boulevard Charlotte, North Carolina
CHARLOTTE, NORTH CAROLINA MALLARD POINTE Shopping Center Highway 29 & J.W. Clay Boulevard Charlotte, North Carolina 1,500 SF, 12,000 * SF and 80,684 * SF *CAN SUBDIVIDE FOR LEASE 831 E. Morehead Street,
More informationEXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015
EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage
More informationEXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015
EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley
More informationEast Link Project Update. Maintenance of Traffic During Construction. April 21, 2015
East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities
More informationFDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015
From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction
More informationNovember 21, 2012 Barbara Kelleher, (954)
November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related
More informationFDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016
March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related
More informationState Route 8 Corridor. Northern Summit County s Path to Success
State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity
More information25 th Avenue Grade Separation. September 13, 2017
25 th Avenue Grade Separation September 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25
More informationGuide to. Road Construction Projects
Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or
More informationFDOT Treasure Coast Traffic Impact Report
July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane
More informationCONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018
FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures
More informationRoute 29 Solutions Projects
Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement
More informationFuller Road/Fuller Heights Road Improvements
Transportation Fuller Road/Fuller Heights Road Improvements Total Project Cost - $4.4M This project will widen Fuller Road, which is the entrance road serving the Quantico Marine Corps Base, the Town of
More informationApril 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014
April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures
More informationTransportation TRANSPORTATION PROJECTS
Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William
More informationFDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015
June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane
More informationAs the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.
REPORT FOR ACTION Construction Staging Area - 81 Bay Street Date: December 11, 2017 To: Toronto and East York, Community Council From: Acting Director, Transportation Services Toronto and East York District
More informationFDOT Treasure Coast Traffic Impact Report
July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane
More informationConstruction Update. Local Officials Briefing March 2016
Construction Update Local Officials Briefing March 2016 1 History: Chicago-St. Louis Corridor Since 1980 s IDOT has been looking at this corridor for high-speed service 1992 Designated a HSR Corridor EIS
More informationUS 19 Sunset Point Rd to Countryside Blvd.
Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started
More informationLake Erie Commerce Center Traffic Analysis
LOCATION: East of NYS Route 5 at Bayview Road Town of Hamburg Erie County, New York PREPARED BY: Wendel Companies 140 John James Audubon Parkway Suite 200 Amherst, New York 14228 January 2012 i ii Table
More informationCONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND
BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK
More informationOctober 31, 2014 Chuck McGinness, (954)
From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October
More informationPalm Beach County Traffic Report July 13 through July 20, 2012
For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be
More informationSite Location and Setting
Memorandum Date: To: From: Subject: Kristy Le, Gary Black Steve Orem Santa Teresa County Park Historic Area Traffic and Parking Study Hexagon Transportation Consultants, Inc. has completed a traffic and
More informationProposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street
STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure
More informationRoute 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.
EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in
More informationAGENCY NAME TRANSPORTATION
TRANSPORTATION TRANSPORTATION AGENCY NAME Prince William County FY 2015 BUDGET CIP-TRANSPORTATION 561 Fuller Road/Fuller Heights Road Improvements Total Project Cost - $4.4 M This project will widen Fuller
More information35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS
35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration
More informationPROGRESS PARK CONNECTOR
PROGRESS PARK CONNECTOR Project No. 9999 098 R65, P102 ALTERNATIVES ANALYSIS 6 April 2015 Revised for updated dates PROGRESS PARK CONNECTOR ROAD ALTERNATIVES ALTERNATIVE # 1 West from the intersection
More informationMay 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015
May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing
More informationSouthwest LRT Alignment Video Narration
Southwest LRT Alignment Video Narration September 2015 Southwest Light Rail Transit, a proposed extension of the METRO Green Line, will serve Minneapolis, St. Louis Park, Hopkins, Minnetonka and Eden Prairie.
More informationG Street Undercrossing. City Council Meeting Date: November 3, 2008
G Street Undercrossing City Council Meeting Date: November 3, 2008 Introduction G Street undercrossing Long-term goal of the City In General Plan since 1997 In City s Public Facilities Financing Plan
More informationSOLECTRON DRIVE CHARLOTTE, NC
6800@URP 6800 SOLECTRON DRIVE CHARLOTTE, NC 1 A Vision Created With You In Mind Originally designed to IBM s highest standards for manufacturing and office uses, the property is undergoing a major revitalization
More informationWork in 2015 and Annual Mobility- Management Plan
Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector
More information16. Other Transportation Modes
Charlotte-Douglas International Airport ranks as one of the top ten airports in the country by many metrics. 16. Other Transportation Modes The transportation needs of the residents and workers within,
More informationCreating Sustainable Communities Through Public Transportation
Creating Sustainable Communities Through Public Transportation 21 st Transportation Committee January 16, 2008 Keith T. Parker Chief Executive Officer Charlotte Area Transit System (CATS) Charlotte Mecklenburg
More informationBROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,
From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY
More informationMay 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015
From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015
More informationChapter 2: Entire US287 Corridor
Chapter 2: Entire US287 Corridor The US287 Study Area spans four incorporated jurisdictions and two counties. Due to the length and density of infrastructure along the US287 Study Area, corridor-wide maps
More informationRoute 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016
Route 141 and I-44 Design-Build Project Community Involvement Group March 21, 2016 Purpose of CIG 1. Share information with major stakeholders 2. Keep stakeholders informed of the process 3. Reduce uncertainty
More informationONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1
ONONDAGA CREEKWALK PHASE II Public Information Meeting Series 1 Andrew Maxwell Director, Syracuse-Onondaga County Planning Agency Owen Kerney Assistant Director for City Planning Russell Houck, PE City
More informationWelcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,
Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program, updates on construction to be held in this area, and how
More informationDULLES AREA HIGHLIGHTS. Gary Garczynski Commonwealth Transportation Board Northern Virginia District. Committee for Dulles August 4, 2016
DULLES AREA HIGHLIGHTS Gary Garczynski Commonwealth Transportation Board Northern Virginia District Committee for Dulles August 4, 2016 Smart Scale (formerly HB2) Overview Round 1 completed with the adoption
More information5.1 Traffic and Transportation
5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the
More informationHospital Link Project Project Update Winter 2018
Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open
More informationNAIOP. Marcia McAllister Metropolitan Washington Airports Authority
NAIOP Marcia McAllister Metropolitan Washington Airports Authority 1 The Vision Realized Northern Virginia Today Tysons Corner is the largest employment center in the Commonwealth Larger than central business
More informationSAN RAFAEL City Council January 20, 2015
SONOMA MARIN AREA RAIL TRANSIT SMART CENTRAL SAN RAFAEL STATUS UPDATE SAN RAFAEL City Council January 20, 2015 CENTRAL SAN RAFAEL SMART SOUTH OF PUERTO SUELLO TUNNEL 1. Active Construction 2. Construction
More informationCity of Shenandoah Transportation Projects. September 20, 2018 By: Derek Wind, PE, CFM
City of Shenandoah Transportation Projects September 20, 2018 By: Derek Wind, PE, CFM Shenandoah Proposed Improvements Montgomery County Precinct Boundary Precinct 2 North West side of I-45 and Research
More informationBasic Project Information
FY 2015-16 PROJECT DESCRIPTION FORM (2C) Submitting Agency: Loudoun County Basic Project Information Project Title: Loudoun County Parkway (VA Route 607) U.S. 50 to Creighton Rd. (2C) Project Type (check
More informationSTAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk
STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route
More information4. Safety Concerns Potential Short and Medium-Term Improvements
NH Route 104 Access Management Study Page 19 4. Safety Concerns Potential Short and Medium-Term Improvements Potential safety improvement strategies are listed by priority based on field observations by
More information1.2 Corridor History and Current Characteristics
SECTION 1 Description and Background of Study Area 1.1 Introduction This preliminary engineering report was prepared for the Alaska Department of Transportation and Public Facilities (ADOT&PF). It is part
More information2009 Regional Solicitation Selected Projects*
2009 Regional Solicitation Selected Projects* Special Federal Allocation from the MPO Mn/DOT I-494/TH169 Interchange Reconstruction $34,000,000 Surface Transportation Program - Urban Guarantee AR-09-10
More information* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties
New York State Department of Transportation 2008 Highway/Bridge Construction Projects * Short term resurfacing projects are not included in this listing. Genesee 4T39.07 Project: Annual Rural County Sign
More informationMain Street Station Upgrades
Main Street Station Upgrades Public Meeting Hope United Church 1 Main Street Station Upgrades Bus diversions Planned improvements Construction staging Pedestrian flows 2 Main Street Station Aerial Bar
More informationSpringettsbury Township. Road Improvement Projects
Springettsbury Township Road Improvement Projects 2009 2016 2016 Township Road Improvement Projects Springettsbury Township is divided into the following 4 Sectors: Northwest Sector Sherman Street Route
More informationCorridor Management Committee Meeting. April 2, 2014
Corridor Management Committee Meeting April 2, 2014 1 Today s Topics Welcome Approval of Minutes Resolutions Response to March 26 CMC Questions Staff Recommendation on Project Scope and Budget Public Testimony
More informationTRANSPORTATION ELEMENT
Transportation TRANSPORTATION ELEMENT Data, Inventory, and Analysis Prepared by Contents 1.0 INTRODUCTION... 1 2.0 EXISTING CONDITIONS... 1 2.1 Roadways... 1 2.1.1 Jurisdiction... 1 2.1.2 Functional Classification...
More informationRoad widening from 2 lanes to 4 lanes. Bridge removal and piping of the canal. Lane closures are not expected.
PALM BEACH COUNTY TRAFFIC DIVISION UPDATE OF ROAD AND BRIDGE CONSTRUCTION LIST DATE OF ISSUE: SEPTEMBER 12, 2012 STATUS FOR SEPTEMBER 17, 2012 THROUGH SEPTEMBER 23, 2012 *** CONSTRUCTION WORK ZONES ADDED
More informationPalm Beach County Traffic Report August 24 through August 31, 2012
For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will
More informationCell: (408) Release MA June 25, 2012
VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara
More informationROUTE 630 DIVERGING DIAMOND INTERCHANGE
ROUTE 630 DIVERGING DIAMOND INTERCHANGE Virginia Department of Transportation Contract Value and Dates Contract Value: $99,949,969.50 Start of Construction: Summer 2017 Final Completion Date: July 31,
More informationNCDOT, DIVISION SIX HIGHWAY INCIDENT MANAGEMENT PROGRAM
NCDOT, DIVISION SIX HIGHWAY INCIDENT MANAGEMENT PROGRAM CONSTRUCTION/BRIDGE/MAINTENANCE PROJECT STATUS REPORT DATE: 9-7-17 COUNTY: Cumberland TIP # ROUTE LOCATION WORK DESCRIPTION START DATE END DATE CONTACT
More informationFuller/Fuller Heights Road Improvements
Fuller/Fuller Heights Road Improvements Total Project Cost - $4.4M Project Description This project will construct a mini-roundabout at the intersection of Fuller Heights Road and Old Triangle Road to
More informationLESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation
LESLIE BARNS & CONNECTION TRACK Project Update Construction and Traffic Management Consultation PRESENTATION SUMMARY Part 1 Brief Project Update (New Streetcars & Streetscape Improvements) Part 2 Construction
More informationOhio Department of Transportation Construction Update
Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District
More informationU.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County
U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE
More informationProject Location MP A44.5 MP A38 PRELIMINARY. A A57 (Future Project) A42 - A44.5 (Fall Fall 2019) A38 - A42. A31 - A38 - In Design
RECONSTRUCTION AND WIDENING PROJECT Project Location A44.5 - A57 (Future Project) MP A44.5 Steinsburg Road (Fall 2015 - Fall 2016) John Fries Highway (Fall 2017 - Fall 2019) A42 - A44.5 (Fall 2017 - Fall
More informationConstruction underway. STATUS: 229 5,190 5,419 5,305 STIP REFERENCE #FR /01/2013
FREDERICK COUNTY STATE HIGHWAY ADMINISTRATION -- Frederick County -- Line 1 PROJECT: I-7, Baltimore National Pike INTERSTATE CONSTRUCTION PROGRAM DESCRIPTION: Widen I-7 east of MD 355 to east of MD 144
More informationCheshire Pointe 6316 Old Sugar Creek Rd, Charlotte, NC 28269
Contact: Philip Corriher Mobile: (704) 619-7108 phil@chambers-group.com Cheshire Pointe 6316 Old Sugar Creek Rd, Charlotte, NC 28269 Demographics 1 Mile 3 Mile 5 Mile Population 11,251 62,918 159,570 Average
More informationScore. Category. Access Aesthetics Community Resources
NO BUILD ALTERNATIVE The No Build Alternative is the do nothing option that is used for comparison to the build alternatives. The screening assumes no new facilities are constructed as part of the I-93
More informationLong water shutdown scheduled for Tuesday, September 18
Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility
More informationLESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #6 January 30, 2014
LESLIE BARNS & CONNECTION TRACK Construction Liaison Group Meeting #6 January 30, 2014 Construction Liaison Group Jan 30 2014 1 OVERVIEW HAPPY BELATED NEW YEAR Works to Date Underground Utilities Bell
More information25 th Avenue Grade Separation. December 13, 2017
25 th Avenue Grade Separation December 13, 2017 Agenda I. Overview II. III. IV. Project Description Project Benefits Project Construction V. Next Steps VI. Questions 2 Overview Project Location 4 E. 25
More informationFor Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS
TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane
More informationRELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)
RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,
More informationThe Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP).
The Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP). A 7-day public comment period regarding the amendment begins January
More informationMacleod Trail Corridor Study. Welcome. Macleod Trail Corridor Study Open House. Presentation of Proposed Design Concepts
Macleod Trail Corridor Study Welcome Macleod Trail Corridor Study Open House Presentation of Proposed Design Concepts Study Purpose Develop a corridor plan for Macleod Trail that aligns with The City s:
More information1.0 Purpose and Organization of the Community Impact Assessment Addendum
Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Carie Montero, Senior Project Manager/Environmental Lead, Parsons Transportation Group Parag Mehta, Kimley Horn Date: September 24,
More informationA. CONCLUSIONS OF THE FGEIS
Chapter 11: Traffic and Parking A. CONCLUSIONS OF THE FGEIS The FGEIS found that the Approved Plan will generate a substantial volume of vehicular and pedestrian activity, including an estimated 1,300
More informationPr im e lo cat ion at Ma l l a rd Cre e k R d & I C harlotte, NC
M I X E D -U S E SI T E Pr im e lo cat ion at Ma l l a rd Cre e k R d & I -4 8 5 C harlotte, NC SUMMARY Due it s regional location just off I-85 and I-485, Concord Mills Blvd is a wellestablished retail
More informationWest Charlotte CORRIDOR STUDY
West Charlotte CORRIDOR STUDY EXECUTIVE SUMMARY... 3 A. West Summit Avenue (Crossing # 716 172N)... 5 1. Short-Term... 5 2. Long-Term... 5 B. Berryhill Road (Crossing # 716 176R)... 5 1. Short-Term...
More informationCharlotte Regional Express Lane Facilities: I-485 and US 74. North Carolina Turnpike Authority March 21, 2018
Charlotte Regional Express Lane Facilities: I-485 and US 74 North Carolina Turnpike Authority March 21, 2018 NC Turnpike Authority Overview Created in 2002 by the General Assembly Authorized to design,
More informationChicago St. Louis High-Speed Rail. Enos Park Neighborhood Association May 13, 2014
Chicago St. Louis High-Speed Rail Enos Park Neighborhood Association May 13, 2014 1 Illinois High-Speed Rail Program 2 Chicago-St. Louis Corridor» IDOT has actively developed the corridor since the mid1980
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT
RELEASE: IMMEDIATE Aug. 10, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT August 12 August 18, 2018 All
More information2017 Work and Launch of the Next Phase. Information meeting, Montréal-Ouest September 14, 2017
2017 Work and Launch of the Next Phase Information meeting, Montréal-Ouest September 14, 2017 2 Presentation Outline Work progress Launch of the next phase Mitigation measures Dismantling Communications
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT
RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT
RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work
More informationNeed County Priority Needs Identification Major Projects/Emerging Taking Care of the System (TCOS) 1=High 2=Medium 3=Low
PIONEER TRAILS REGIONAL PLANNING COMMISSION TRANSPORTATION NEEDS -- 2015 TRANSPORTATION PLANNING GOALS BY MODOT CATEGORIES Pioneer Trails transportation needs are listed according to MoDOT s two major
More informationDistrict Construction Progr am. John R. Kasich, Ohio Governor Jerry Wray, ODOT Director Steve Mary, P.E., District Deputy Director
District 8 2014 Construction Progr am Preble Greene Butler Warren Clinton Lebanon Hamilton Clermont Serving Butler, Clermont, Clinton, Greene, Hamilton, Preble and Warren Counties. John R. Kasich, Ohio
More informationN. Central St. & W. Jackson Ave. Streetscape Projects
N. Central St. & W. Jackson Ave. Streetscape Projects October 13, 2016 Meeting Overview North Central Street City of Knoxville KUB History & Vision Plan Timing Project Area Overview Schedule Communications
More informationMemorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description
Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Analette Ochoa and Wana Chiu, WRECO Parag Mehta, Kimley Horn Date: November 7, 2017 Re: Santa Cruz Route 1 Tier I and Tier II HOV
More informationCOMMUNITY MEETING FORM PETITION NUMBER Durban Group- Sugar Creek Road
COMMUNITY MEETING FORM PETITION NUMBER Durban Group- Sugar Creek Road Date of original contact: November 21, 2015 Persons and Organizations contacted with date and explanation of how contacted: City supplied
More information