1 ATLANTA, GEORGIA 1

2 2 ATLANTA, GEORGIA Planning Session 4: Airside Capacity Analysis Tools and Techniques ACRP Project 03-17: Evaluating Airfield Capacity December 6, 2011 Bill Dunlay Director LeighFisher Inc.

3 Objectives of Research Present capacity modeling guidelines for Determining the appropriate level of modeling sophistication Applying models to specific airfield and airspace situations Develop Guidebook for airport planners All types of airports Runways, taxiways, and approach/departure procedures Assess existing modeling techniques beyond AC 150/ and FAA Airfield Capacity Model (ACM) Develop specifications and functional prototype for a new model Select one or more models for improvement or development An initial step toward updating Advisory Circular AC 150/5060-5, Airport Capacity and Delay 3

4 ACRP Project Panel Panel and ACRP Support Rick Busch, Denver Chair Greg Albjerg, HNTB Monica Alcabin, Boeing David Byers, FIT Nancy Dorighi, NASA Bruce Love, URS Scott Marsh, PANY&NJ ACRP Support Theresia Schatz, ACRP Joseph Snell, ACRP Liaison members Aimee McCormick, FAA Chris Oswald, ACI-NA Kent Duffy, FAA Don Guffey, FAA Richard Cunard, TRB Timmy RoIf Schindler, GAO 4

5 ACRP Project Team LeighFisher Bill Dunlay, PI, and Suzanne Akkoush, Project Manager Landrum & Brown Matt Lee, Deputy, PI, and Pam Keidel-Adams (WSA) University of California, Berkeley Mark Hansen George Mason University Lance Sherry Presentation & Design, Inc. Patti J. Douglas LeighFisher and Landrum & Brown decided to join forces for this project 5

6 ACRP Deliverables 1. Guidebook 2. Decision Hierarchy How to Choose a Level of Modeling Sophistication 3. New and Newly Available Tools a. Spreadsheet Tools b. MITRE runwaysimulator Initial Public Offering 4. Final Report Project deliverables will provide comprehensive tools for evaluating airfield capacity 6

7 Guidebook Outline Chapters 1. Introduction and Roadmap 2. Review of Airfield Capacity Concepts 3. Existing Airfield Capacity Evaluation Tools 4. New and Newly Available Capacity Evaluation Tools 5. How to Select the Level of Modeling Sophistication 6. Subsequent Uses of Capacity Information Appendices A. User s Guide for Spreadsheet Model B. Available Guidance on MITRE runwaysimulator C. Definitions of Terms D. Essential References and Data Sources E. Case Studies lessons learned 7

8 Chapter 1: Introduction and Roadmap 1. Introduction 2. Overview 3. Who Should Use This Guidebook? 4. Need for Updating Airfield Capacity Evaluation Methods and Guidance 8

9 9 Chapter 2: Review of Airfield Capacity Concepts 1. Airport and Airside Components 2. Airport and Airspace Operating Environment 3. Factors that Affect Capacity 4. Levels of Capacity Modeling Sophistication 21 Factors Airport Geometry Runway Exit Design Runway Entrance Taxiways Staging Pads/Taxiways Runway Crossings Parallel Taxiway Airport User Information Aircraft Fleet Mix Daily Demand Distribution Aircraft Performance Avionics Equipage Braking Action Random Variability Runway Use & ATC Procedures Applicability of Visual Flight Rules Wake Turbulence Weather Multiple Approach Technology Runway Specific Fleet Mix Human Factors Air Traffic Controller Workload Air-Ground Communications Random Variability Airspace Factors Departure Fix Restrictions Neighboring Airports Missed Approach

10 10 Levels of Modeling Sophistication

11 Chapter 3: Existing Airfield Capacity Evaluation Tools 1. Model Descriptions and Attributes: a. Applications and data requirements b. Model assumptions, inputs, outputs, and limitations c. Time, cost, and training requirements d. Model availability, limitations, and identified gaps 2. Existing Level 1, 2, 3, 4, and 5 Models 11

12 Chapter 4: New and Newly Available Capacity Evaluation Tools and Guidance 1. New Spreadsheet Models (Levels 1, 2, and 3) 2. Newly Available Level 4 Model MITRE runwaysimulator 3. Guidance on Estimating Capacity of Specialty Cases a. Effects of partial parallel taxiways and runway crossings b. Effects of staggered runway thresholds/runway ends c. Aircraft type runway-use restrictions d. Airports without an operating Airport Traffic Control Tower (ATCT) 12

13 13 Chapter 5: How to Select the Level of Modeling Sophistication 1. Hierarchy/Decision Tree (see next 6 slides)

14 14 Decision Hierarchy 1: Data Requirements / Availability Level 1 Level 2 Level 3 Level 4 Level 5 mix index mix index fleet mix fleet mix flight schedule runway runway layout simple runway-use complex runway-use airfield layout in CAD layout configuration configuration runway exit final approach speeds final approach speeds arrival-arrival separations locations percent arrivals AROT AROT departure-departure separations touch and go DROT DROT capture distance percent arrival-arrival separations arrival-arrival separations runway dependencies departure-departure departure-departure arrival flight tracks separations separations arrival-departure arrival-departure departure flight tracks separations separations runway dependencies runway usage/assignments

15 Decision Hierarchy 2: Checklist Items (1 of 3) CRITERION VALUE Level 1 Level 2 Level 3 Level 4 Level 5 How much time/budget is available? Hours/<$5k Days/<$25k Weeks/<$50k Months/$100k+ CRITERION VALUE Level 1 Level 2 Level 3 Level 4 Level 5 Purpose of the capacity analysis? Airfield changes New Runway New Taxiway/Apron/Gates Runway crossings NAVAID critical areas Effects of air traffic control towers Airspace Changes Changes in flight procedures Noise abatement procedures In-trail terminal airspace restrictions Multiple approach procedures Changes in ATC rules and separations ATC workload and human factors NextGen benefits Aircraft Changes Aircraft fleet mix and stage length changes To estimate aircraft delay To estimate ASV/hourly capacity To compare with hourly demand To benchmark with other airports To evaluate flight schedules To compare alternative improvements To provide data for follow-on environmental studies 15

16 16 Decision Hierarchy 2: Checklist Items (2 of 3) CRITERION VALUE Level 1 Level 2 Level 3 Level 4 Level 5 What data do you have avaliable? Airfield Data runway usage/assignments runway layout runway exit locations runway dependencies AROT DROT airfield layout in CAD Aircraft Data percent arrivals mix index flight schedule fleet mix final approach speeds Airspace Data departure-departure separations departure-departure separations departure flight tracks capture distance arrival-departure separations arrival-arrival separations arrival-arrival separations arrival flight tracks

17 17 Decision Hierarchy 2: Checklist Items (3 of 3) CRITERION VALUE Level 1 Level 2 Level 3 Level 4 Level 5 What factors do you need to capture? Geometry Impact of runway exit taxiway location Supporting Taxiways Departure queue sequencing Runway crossings Parallel taxiway Aircraft performance Impact of runway occupancy time Runway Use Runway-specific fleet mix (due to noise or length) Multiple approach technology Airspace Departure fix restrictions Limited departure headings CRITERION VALUE Level 1 Level 2 Level 3 Level 4 Level 5 Public scrutiny by or challenge from airport Public Scrutiny and/or its stakeholders? Little or no scrutiny or challenge Low level of scrutiny or challenge Moderate level of scrutiny or challenge Intense level of scrutiny or challenge

18 18 Decision Hierarchy 3: Questionnaire (1 of 2) LEVEL 1 1 Do the standard default assumptions in the lookup differ from your situation? (i.e., parallel taxiway, ILS runway, etc) 2 Do you need to take a specific runway use into account? If you answered NO to all of these questions, use a Level 1 model If you answered YES to any of these questions, go to Level 2 section LEVEL 2 1 Do you have three or more runways? 2 Do you have a dependent arrival/departure runway operation? 3 Will the results be subject to a high level of scrutiny, challenge, or controversy? 4 Do you need to represent the fleet mix in more detail than the "mix index"? 5 Do you need to consider detailed runway occupancy time data? 6 Do you need to reflect a change in aircraft separations? (i.e., improved approach procedure) 7 Do you have runway crossings which interrupt your arrival/departure flow? 8 Are you assessing operations during weather conditions other than VMC or IMC? If you answered NO to all of these questions, use a Level 2 model If you answered YES to any of these questions, go to Level 3 section

19 LEVEL 4 1 Do you need to consider a detailed matched flight schedule? 2 Do you need to model the full airport system, including gates, apron,and taxilanes? 3 Are you considering taxiways, other than runway exit taxiways or full-length parallel taxiways? 4 Do you have airspace conflicts with neighboring airports, restricted airspace, etc.? 5 Do you need to model the terminal airspace? 6 Will there be a need to demonstrate and/or validate the baseline results to stakeholders If you answered NO to all of these questions, use a Level 4 model If you answered YES to any of these questions, use a Level 5 model 19 Decision Hierarchy 3: Questionnaire (2 of 2) LEVEL 3 1 Is the usage of the runway(s) restricted to certain aircraft types (i.e., due to noise abatement or other)? 2 Does the availability of departure fixes/headings restrict operations? 3 Does arrival track geometry impact aircraft separations? 4 Do you have a dependent or converging arrival runway operation? If you answered NO to all of these questions, use a Level 3 model If you answered YES to any of these questions, go to Level 4 section

20 Chapter 6: Subsequent Uses of Capacity Information 1. Demand-Capacity Comparisons 2. Aircraft Delay Estimation 3. Reference ACRP Project 03-20, Defining and Measuring Aircraft Delay and Airport Capacity Thresholds APPENDICES A. User s Guide for Spreadsheet Model B. Available Guidance on MITRE runwaysimulator C. Definitions of Terms D. Essential References and Data Sources E. Case Studies lessons learned 20

21 21 Levels of Modeling

22 New Spreadsheet Tool Addresses 3 levels of modeling sophistication in 1 tool Macro-enabled Excel-based file using tabs Will have 3 model options Single runway Parallel runways Intersecting runways Can calculate hourly capacity and Annual Service Volume (ASV) as defined in FAA AC 150/5060-5, Airport Capacity and Delay 22

23 23 Spreadsheet Model Airfield Capacity Estimation using Spreadsheet Models Use the spreadsheet model to quickly estimate airfield capacities for Arrivals only, Departures only and Mixed Operations. ENTER OR ADJUST MODEL INPUTS OBSERVE AND EVALUATE OUTPUTS USE RESET BUTTON TO RETURN INPUTS TO DEFAULT SETTINGS INPUTS Light Green fill, with Bold Green text OUTPUTS Blue fill, with Bold White text Reset Inputs Grey fill, with Bold Red text Calculated/Linked Values & Descriptions have white backgrounds Calculated Values Linked Values Comments are attached to Input descriptions to provide understanding/definitions to input titles

24 Partial Input Screen INPUTS Meteorological Conditions VMC, % Occurrence 90% IMC, % Occurrence 10% VMC-Departure-Arrival Separation 2.0 nm Arrival - Arrival Std. Dev sec IMC-Departure-Arrival Separation 2.0 nm Departure ROT Std. Dev. 6.0 sec Length of Common Approach 7.0 nm Z-Value, 95% Confidence Operations Assumption on Touch -N- Go's 0% T-Factor (Touch-N-Go's) 1.00 RESET INPUTS Aircraft Classification New Category Small - S Small - T Small + Large-TP Large-Jet Large-757 Heavy Previous FAA Category A B C C C C D Maximum Gross Takeoff Weight (MTOW) Less than 12,500 lbs (Single Engine) Less than 12,500 lbs (Twin Engine) Between 12,500 lbs and 41,000 lbs Between 41,000 lbs and 255,000 lbs Between 41,000 lbs and 255,000 lbs Boeing 757 Series More than 300,000 lbs Fleet Mix Enter the actual or expected % share each aircraft class Share Allocations 0.0% 0.0% 0.0% 0.0% 100.0% 0.0% 0.0% Arrival Runway Occupancy Time Enter the estimated time from touchdown to runway clearance Time in Seconds Average Approach Speeds Enter the average suggested manufacturers final approach speed under normal conditions Velocity in Knots Runway Exit Availability Excellent (4 or more Exits) 100% Runway Crossing Demand No 0 Full Parallel Taxiway ACRP 03-17: Full Evaluating Taxiway 1.00Airfield Approach Capacity Control Radar Yes Availability Use Advanced Settings to change ATC procedures and adjust Arrival/Departure mix and priority 24

25 Advanced Features Example Use Advanced Settings to change ATC procedures and adjust Arrival/Departure mix and priority Arrival Gap Spacing Buffer 0.0 sec <----OR----> Arrival Gap Spacing Buffer 1.0 nmiles Departure Hold Buffer 0.0 sec Arrival-Arrival Separation Requirements Distance in Nautical Miles (nm) Trailing Aircraft Leading Aircraft VMC IMC Small-S --- Heavy Small-S, Small-T Alternate IMC Minimum Small-S --- Small+ Small (if Observed AROT < 50 Seconds) Large --- Heavy Small Use 2.5 nm in place of 3.0 nm? Small-S --- Small+ Large-TP, Jet No Large --- Heavy Large-TP, Jet Small-S --- Small+ Large Large --- Heavy Large Small-S --- Small-T Heavy Small Heavy Heavy Heavy Departure - Departure Separation Requirements Time in Seconds Trailing Aircraft Leading Aircraft VMC IMC Small-S --- Small + Small-S- Small Large -TP --- Large 757 Small-S- Small Heavy Small-S- Small Small-S --- Small+ Large Large --- Heavy Large Small-S --- Large 757 Heavy Heavy Heavy

26 Arrivals/Hour Partial Output Screen OUTPUTS VMC IMC Average Arrivals Only Capacity Arrivals Only Capacity (including TNG's) Departures Only Capacity Mixed Ops - Departure Capacity (including TNG's) Total Mixed Operations Capacity Arrivals Percentage 50% 50% 50% Capacity estimates for: Arrival priority Departure priority Various percentages of arrivals Pareto Frontier Chart Selection VMC 40 VMC Arrival -Departure Ca Save - 35 Used for Graphing only! 34, , 34 Used in Graph Departures 25 Arrivals Departures Arrivals Departures Arrivals VMC IMC Average 10 5 VMC Arrival -Departure Capacity Frontier 60, 0 Similar to capacity charts in the FAA Airport Capacity Benchmark Report 2004 (and upcoming 2011) Departures/Hour 26

27 MITRE runwaysimulator Initial Public Offering in 2012 The runwaysimulator model is now the FAA s primary runway capacity analysis tool FACT 3 Study 2011 Airport Capacity Benchmark Report MITRE plans to make this model publicly available in 2012 ACRP Project will provide an independent assessment of the runwaysimulator for purposes of airfield capacity evaluation Pete Kuzminski of MITRE will cover this model in more detail 27

28 28 Next Steps 1. Submit draft Guidebook, draft Final Report, and results of modeling tasks to ACRP Panel for review in December Submit final Project deliverables to ACRP by end of January Expect publication of final ACRP Report a few months thereafter

ACRP Project Evaluating Airfield Capacity

ACRP Project Evaluating Airfield Capacity DEN572 PRESENTATION ACRP Project 03-17 Evaluating Airfield Capacity Presented by Pam Keidel-Adams, Landrum & Brown Brian Poe, Landrum & Brown February 13, 2012 Objectives of Research Develop Guidebook

More information

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include: 4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity

More information

ACRP EVALUATING AIRFIELD CAPACITY. Contractor s Final Report

ACRP EVALUATING AIRFIELD CAPACITY. Contractor s Final Report ACRP 03-17 EVALUATING AIRFIELD CAPACITY Contractor s Final Report Prepared for Airport Cooperative Research Program Transportation Research Board of The National Academies LeighFisher in association with

More information

Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update

Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update Ultimate ASV, Runway Use and Flight Tracks 4th Working Group Briefing 8/13/18 Meeting Purpose Discuss Public Workshop input

More information

Airfield Capacity Prof. Amedeo Odoni

Airfield Capacity Prof. Amedeo Odoni Airfield Capacity Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Air Transportation Systems and Infrastructure Module 10 May 27, 2015 Airfield Capacity Objective:

More information

Analysis of Air Transportation Systems. Airport Capacity

Analysis of Air Transportation Systems. Airport Capacity Analysis of Air Transportation Systems Airport Capacity Dr. Antonio A. Trani Associate Professor of Civil and Environmental Engineering Virginia Polytechnic Institute and State University Fall 2002 Virginia

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

APPENDIX D MSP Airfield Simulation Analysis

APPENDIX D MSP Airfield Simulation Analysis APPENDIX D MSP Airfield Simulation Analysis This page is left intentionally blank. MSP Airfield Simulation Analysis Technical Report Prepared by: HNTB November 2011 2020 Improvements Environmental Assessment/

More information

SIMMOD Simulation Airfield and Airspace Simulation Report. Oakland International Airport Master Plan Preparation Report. Revised: January 6, 2006

SIMMOD Simulation Airfield and Airspace Simulation Report. Oakland International Airport Master Plan Preparation Report. Revised: January 6, 2006 Table of Contents SIMMOD Simulation Airfield and Airspace Simulation Report Oakland International Airport Master Plan Preparation Report Revised: January 6, 2006 Produced For: 1. Simmod PRO! Description...

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

TRANSPORTATION RESEARCH BOARD. Preparing and Using Airport Design Day Flight Schedules. Wednesday, July 18, :00-3:30 PM ET

TRANSPORTATION RESEARCH BOARD. Preparing and Using Airport Design Day Flight Schedules. Wednesday, July 18, :00-3:30 PM ET TRANSPORTATION RESEARCH BOARD Preparing and Using Airport Design Day Flight Schedules Wednesday, July 18, 2018 2:00-3:30 PM ET Purpose Discuss research from the Airport Cooperative Research Program (ACRP)

More information

RUNWAY OPERATIONS: Computing Runway Arrival Capacity

RUNWAY OPERATIONS: Computing Runway Arrival Capacity RUNWAY OPERATIONS: Computing Runway Arrival Capacity SYST 560/460 USE Runway Capacity Spreadsheet Fall 2008 Lance Sherry 1 CENTER FOR AIR TRANSPORTATION SYSTEMS RESEARCH Background Air Transportation System

More information

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration Chapter 4 Page 65 AIRPORT DEMAND CAPACITY The purpose of this Demand/Capacity Analysis is to examine the capability of the Albert Whitted Airport (SPG) to meet the needs of its users. In doing so, this

More information

Time-Space Analysis Airport Runway Capacity. Dr. Antonio A. Trani. Fall 2017

Time-Space Analysis Airport Runway Capacity. Dr. Antonio A. Trani. Fall 2017 Time-Space Analysis Airport Runway Capacity Dr. Antonio A. Trani CEE 3604 Introduction to Transportation Engineering Fall 2017 Virginia Tech (A.A. Trani) Why Time Space Diagrams? To estimate the following:

More information

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016 Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand

More information

Analysis of Operational Impacts of Continuous Descent Arrivals (CDA) using runwaysimulator

Analysis of Operational Impacts of Continuous Descent Arrivals (CDA) using runwaysimulator Analysis of Operational Impacts of Continuous Descent Arrivals (CDA) using runwaysimulator Camille Shiotsuki Dr. Gene C. Lin Ed Hahn December 5, 2007 Outline Background Objective and Scope Study Approach

More information

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION 1.1.3 Taxiways EWN has an extensive network of taxiways and taxilanes connecting the terminal, air cargo, and general aviation areas with the runways as listed in Figure 1-15. A 50-foot wide parallel taxiway

More information

APPENDIX X: RUNWAY LENGTH ANALYSIS

APPENDIX X: RUNWAY LENGTH ANALYSIS APPENDIX X: RUNWAY LENGTH ANALYSIS Purpose For this Airport Master Plan study, the FAA has requested a runway length analysis to be completed to current FAA AC 150/5325-4B, Runway Length Requirements for

More information

Defining and Managing capacities Brian Flynn, EUROCONTROL

Defining and Managing capacities Brian Flynn, EUROCONTROL Defining and Managing capacities Brian Flynn, EUROCONTROL Some Capacity Guidelines Capacity is what you know you can handle today Capacity = safe throughput capability of an individual or small team All

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 1 - Introduction This report describes the development and analysis of concept alternatives that would accommodate

More information

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Problem Statement 17-03-09 Recommended Allocation: $500,000 Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Staff Comments This is one of four UAS-themed problem statements

More information

LONG BEACH, CALIFORNIA

LONG BEACH, CALIFORNIA LONG BEACH, CALIFORNIA 1 LONG BEACH, CALIFORNIA Airside Capacity Evaluation Techniques Matt Davis Assistant Director of Planning Hartsfield-Jackson Atlanta International Airport Matt.Davis@Atlanta-Airport.com

More information

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by:

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by: Draft AIRPORT MASTER PLAN Newport State Airport () Prepared for: 2000 Post Road Warwick, Rhode Island 02886-1533 THE Louis Berger Group, INC. 20 Corporate Woods Boulevard Albany, New York 12211-2370 Prepared

More information

Wake Turbulence Research Modeling

Wake Turbulence Research Modeling Wake Turbulence Research Modeling John Shortle, Lance Sherry Jianfeng Wang, Yimin Zhang George Mason University C. Doug Swol and Antonio Trani Virginia Tech Introduction This presentation and a companion

More information

Validation of Runway Capacity Models

Validation of Runway Capacity Models Validation of Runway Capacity Models Amy Kim & Mark Hansen UC Berkeley ATM Seminar 2009 July 1, 2009 1 Presentation Outline Introduction Purpose Description of Models Data Methodology Conclusions & Future

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

Surveillance and Broadcast Services

Surveillance and Broadcast Services Surveillance and Broadcast Services Benefits Analysis Overview August 2007 Final Investment Decision Baseline January 3, 2012 Program Status: Investment Decisions September 9, 2005 initial investment decision:

More information

Hartford-Brainard Airport Potential Runway Closure White Paper

Hartford-Brainard Airport Potential Runway Closure White Paper Hartford-Brainard Airport Potential Runway 11-29 Closure White Paper June 2012 In recent years there has been discussion regarding the necessity of Runway 11-29 to the Hartford- Brainard Airport (HFD)

More information

DEMAND/CAPACITY ANALYSIS St. Petersburg-Clearwater International Airport

DEMAND/CAPACITY ANALYSIS St. Petersburg-Clearwater International Airport DEMAND/CAPACITY ANALYSIS St. Petersburg-Clearwater International Airport 5.1 GENERAL OVERVIEW The next step in the Master Plan process is analyzing the capacity of existing airport facilities against forecasted

More information

SPADE-2 - Supporting Platform for Airport Decision-making and Efficiency Analysis Phase 2

SPADE-2 - Supporting Platform for Airport Decision-making and Efficiency Analysis Phase 2 - Supporting Platform for Airport Decision-making and Efficiency Analysis Phase 2 2 nd User Group Meeting Overview of the Platform List of Use Cases UC1: Airport Capacity Management UC2: Match Capacity

More information

Assignment 10: Final Project

Assignment 10: Final Project CEE 4674: Airport Planning and Design Spring 2017 Assignment 10: Final Project Due: May 4, 2017 (via email and PDF) Final Exam Time is May 5 Requirements for this assignment are: a) Slide presentation

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

Cockpit Display of Traffic Information (CDTI) Assisted Visual Separation (CAVS)

Cockpit Display of Traffic Information (CDTI) Assisted Visual Separation (CAVS) Cockpit Display of Traffic Information (CDTI) Assisted Visual Separation (CAVS) Randall Bone 6 th USA / Europe ATM 2005 R&D Seminar Baltimore, Maryland June 2005 Overview Background Automatic Dependent

More information

STUDY WORK GROUP MEETING No. 3. November 29, 2016

STUDY WORK GROUP MEETING No. 3. November 29, 2016 STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity

More information

Key Purpose & Need Issues

Key Purpose & Need Issues Key Purpose & Need Issues Efficiently meet demand through the 2025 planning horizon 864,000+ annual operations 180-200 operations during peak daytime hours Balance peak hour arrival/departure capability

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the

More information

! Figure 1. Proposed Cargo Ramp at the end of Taxiway Echo.! Assignment 7: Airport Capacity and Geometric Design. Problem 1

! Figure 1. Proposed Cargo Ramp at the end of Taxiway Echo.! Assignment 7: Airport Capacity and Geometric Design. Problem 1 CEE 4674: Airport Planning and Design Spring 2014 Assignment 7: Airport Capacity and Geometric Design Solution Instructor: Trani Problem 1 An airport is designing a new ramp area to accommodate three Boeing

More information

Airport Engineering Lectures

Airport Engineering Lectures Airport II- Airport. II-1 Definitions System capacity: Ability efficiently process the transported units. Aircrafts Passengers Baggage cargo Public access facilitation Runway Taxiway Gate Terminal Building

More information

Appendix 6.1: Hazard Worksheet

Appendix 6.1: Hazard Worksheet Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp

More information

Automated Integration of Arrival and Departure Schedules

Automated Integration of Arrival and Departure Schedules Automated Integration of Arrival and Departure Schedules Topics Concept Overview Benefits Exploration Research Prototype HITL Simulation 1 Lessons Learned Prototype Refinement HITL Simulation 2 Summary

More information

ARCHERFIELD AIRPORT MASTER PLAN TECHNICAL PAPER TP 03/10 RUNWAY CAPACITY

ARCHERFIELD AIRPORT MASTER PLAN TECHNICAL PAPER TP 03/10 RUNWAY CAPACITY ARCHERFIELD AIRPORT MASTER PLAN TECHNICAL PAPER TP 03/10 (Revision 2) RUNWAY CAPACITY An Investigation of Practical Capacity with Class D Airspace Procedures and the Proposed Runway Configuration JULY

More information

TRB and ACRP Research Updates: Practical Application

TRB and ACRP Research Updates: Practical Application TRB and ACRP Research Updates: Practical Application 2014 ACI Environmental Affairs Conference Danielle J. Rinsler, AICP FAA Office Airports, Airport Planning and Environmental Division Baltimore, MD Advisory

More information

CAUTION: WAKE TURBULENCE

CAUTION: WAKE TURBULENCE CAUTION: WAKE TURBULENCE This was the phrase issued while inbound to land at Boeing Field (BFI) while on a transition training flight. It was early August, late afternoon and the weather was clear, low

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

CATCODE ] CATCODE

CATCODE ] CATCODE Runways. FAC: 1111 CATCODE: 111111 OPR: AFCEC/COS OCR: AF/A3O-A 1.1. Description. The runway is the paved surface provided for normal aircraft landings and take offs. Runways are classified as either Class

More information

ARP Forecast Review Critical Aircraft Data Sources

ARP Forecast Review Critical Aircraft Data Sources ARP Forecast Review Critical Aircraft Data Sources Kent Duffy FAA Office of Airports National Planning & Environmental Division, APP-400 December 14, 2015 Aviation Forecasts Airport sponsors

More information

Evidence for the Safety- Capacity Trade-Off in the Air Transportation System

Evidence for the Safety- Capacity Trade-Off in the Air Transportation System Evidence for the Safety- Capacity Trade-Off in the Air Transportation System G. L. Donohue R. C. Haynie D. Wang J. F. Shortle Dept. of Systems Engineering & Operations Research George Mason University

More information

Chapter 1 Introduction and Project Overview

Chapter 1 Introduction and Project Overview EPHRATA MUNICIPAL AIRPORT Chapter 1 Introduction and Project Overview The Port of Ephrata in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Ephrata Municipal

More information

Runway Length Analysis Prescott Municipal Airport

Runway Length Analysis Prescott Municipal Airport APPENDIX 2 Runway Length Analysis Prescott Municipal Airport May 11, 2009 Version 2 (draft) Table of Contents Introduction... 1-1 Section 1 Purpose & Need... 1-2 Section 2 Design Standards...1-3 Section

More information

Las Vegas McCarran International Airport. Capacity Enhancement Plan

Las Vegas McCarran International Airport. Capacity Enhancement Plan Las Vegas McCarran International Airport Capacity Enhancement Plan Las Vegas McCarran International Airport Capacity Enhancement Plan September 1994 Prepared jointly by the U.S. Department of Transportation,

More information

JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM. April 10 th 2017

JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM. April 10 th 2017 JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM April 10 th 2017 1 Agenda Recap Potential Mitigation Response to Stakeholder Questions Next Steps 2 Recap 3 Background Master Plan considered the runway

More information

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on

More information

a. Aeronautical charts DID THIS IN LESSON 2

a. Aeronautical charts DID THIS IN LESSON 2 AIRMAN CERTIFICATION STANDARDS: REMOTE PILOT SMALL: You will know and be able to explain in writing or oral form the below tasks regarding AIRPORT OPERATIONS Task References Objective Task B. Airport Operations

More information

TABLE OF CONTENTS 1.0 INTRODUCTION...

TABLE OF CONTENTS 1.0 INTRODUCTION... Advisory Circular Subject: Publication of the Level of Service with Respect to Departure Below RVR 2600 (½ Statute Mile) Issuing Office: Civil Aviation, Standards Document No.: AC 302-001 File Classification

More information

Chapter 5 Facility Requirements

Chapter 5 Facility Requirements Chapter 5 Facility Requirements 50 INTRODUCTION This chapter describes the airside and landside facility requirements necessary to accommodate existing and forecasted demand in accordance with Federal

More information

Chapter 5 Facility Requirements

Chapter 5 Facility Requirements Chapter 5 Facility Requirements 5.0 INTRODUCTION The Facility Requirements chapter of this Sustainable Master Plan Update describes airside and landside facilities, which are needed to accommodate existing

More information

IFR SEPARATION USING RADAR

IFR SEPARATION USING RADAR IFR SEPARATION USING RADAR 1. Introduction When flying IFR inside controlled airspace, air traffic controllers either providing a service to an aircraft under their control or to another controller s traffic,

More information

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3 This is the presentation for the third Master Plan Update Working Group Meeting being conducted for the Ted Stevens Anchorage International Airport Master Plan Update. It was given on Thursday March 7

More information

CHAPTER 4 DEMAND/CAPACITY ANALYSIS

CHAPTER 4 DEMAND/CAPACITY ANALYSIS CHAPTER DEMAND/CAPACITY ANALYSIS INTRODUCTION The demand/capacity analysis examines the capability of the airfield system at Blue Grass Airport (LEX) to address existing levels of activity as well as determine

More information

Assignment 7: Airport Geometric Design Standards

Assignment 7: Airport Geometric Design Standards CEE 4674: Airport Planning and Design Spring 2018 Date Due: March 23, 2018 Instructor: Trani Problem 1 Assignment 7: Airport Geometric Design Standards An airport is designing a new pier terminal to accommodate

More information

RSAT RUNUP ANALYSIS 1. INTRODUCTION 2. METHODOLOGY

RSAT RUNUP ANALYSIS 1. INTRODUCTION 2. METHODOLOGY RSAT RUNUP ANALYSIS 1. INTRODUCTION The FAA Runway Safety Action Team (RSAT) is a team of FAA staff that works with airports to address existing and potential runway safety problems and issues. The RSAT

More information

Chapter III - Demand/Capacity and Facility Requirements

Chapter III - Demand/Capacity and Facility Requirements Chapter III - Demand/Capacity and Facility Requirements The facility requirements identified in this chapter are summarized on Exhibit III.1. The future requirements serve to determine which airport facilities

More information

Operational Performance and Capacity Assessment for Perth Airport

Operational Performance and Capacity Assessment for Perth Airport Operational Performance and Capacity Assessment for Perth Airport Version - 4.1 25 July 2012 Prepared by: NATS Consultancy Page 1 The recipient of this material relies upon its content at their own risk,

More information

Facility Requirements

Facility Requirements 4. This chapter presents the airside and landside facility requirements necessary to accommodate existing and forecasted demand at Erie International Airport (ERI or the Airport) in accordance with Federal

More information

JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017

JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017 JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017 1 Agenda Program Description Runway Incursions Design and Geometry Deficiencies Runway 8/26 Operations Potential Mitigation Next Steps

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

Agenda: SASP SAC Meeting 3

Agenda: SASP SAC Meeting 3 Agenda: SASP SAC Meeting 3 Date: 04/12/18 Public Involvement Plan Update Defining the System Recommended Classifications Discussion Break Review current system Outreach what we heard Proposed changes Classification

More information

USA Near-Term Progress for Closely Spaced Parallel Runways

USA Near-Term Progress for Closely Spaced Parallel Runways 2005 The MITRE Corporation. All rights reserved. USA Near-Term Progress for Closely Spaced Parallel Runways Wakenet 2 Europe November 30, 2005 This is the copyright work of The MITRE Corporation, and was

More information

The pilot and airline operator s perspective on runway incursion hazards and mitigation options. Session 3 Presentation 1

The pilot and airline operator s perspective on runway incursion hazards and mitigation options. Session 3 Presentation 1 The pilot and airline operator s perspective on runway incursion hazards and mitigation options Session 3 Presentation 1 Operational Hazards Workload issues during taxiing that can result in a loss of

More information

Developing an Aircraft Weight Database for AEDT

Developing an Aircraft Weight Database for AEDT 17-02-01 Recommended Allocation: $250,000 ACRP Staff Comments This problem statement was also submitted last year. TRB AV030 supported the research; however, it was not recommended by the review panel,

More information

Planning and Designing Airport Infrastructure to Support GPS and PBN Approach Development

Planning and Designing Airport Infrastructure to Support GPS and PBN Approach Development ACRP Problem Statement 16-07-04 Recommended Allocation: -- Planning and Designing Airport Infrastructure to Support GPS and PBN Approach Development ACRP Staff Comments -- TRB Aviation Committee Comments

More information

Chapter 3. Demand/Capacity & Facility Requirements

Chapter 3. Demand/Capacity & Facility Requirements Chapter 3. Demand/Capacity & Facility Requirements Chapter 3. DEMAND/CAPACITY & FACILITY REQUIREMENTS This chapter provides an assessment of future airport development requirements based upon the forecasts

More information

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906 Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT DRAFT

FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT DRAFT D.3 RUNWAY LENGTH ANALYSIS Appendix D Purpose and Need THIS PAGE INTENTIONALLY LEFT BLANK Appendix D Purpose and Need APPENDIX D.3 AIRFIELD GEOMETRIC REQUIREMENTS This information provided in this appendix

More information

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i TABLE OF CONTENTS Chapter 1 Overview... 1-1 1.1 Background... 1-1 1.2 Overview of 2015 WASP... 1-1 1.2.1 Aviation System Performance... 1-2 1.3 Prior WSDOT Aviation Planning Studies... 1-3 1.3.1 2009 Long-Term

More information

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

Feasibility and Benefits of a Cockpit Traffic Display-Based Separation Procedure for Single Runway Arrivals and Departures

Feasibility and Benefits of a Cockpit Traffic Display-Based Separation Procedure for Single Runway Arrivals and Departures Feasibility and Benefits of a Cockpit Traffic Display-Based Separation Procedure for Single Runway Arrivals and Departures Implications of a Pilot Survey and Laboratory Simulations Dr. Anand M. Mundra

More information

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012 1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley

More information

Master Plan Update Technical Advisory Committee Meeting

Master Plan Update Technical Advisory Committee Meeting Nashville International Airport Master Plan Update Technical Advisory Committee Meeting February 14, 2019 Agenda Welcome and Introductions Aviation Activity Forecast Facility Requirements Alternatives

More information

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.

More information

CHAPTER 5 - FACILITY REQUIREMENTS

CHAPTER 5 - FACILITY REQUIREMENTS CHAPTER 5 - FACILITY REQUIREMENTS This chapter identifies the requirements for airfield and landside facilities to accommodate the forecast demand level. Facility requirements have been developed for the

More information

Appendix C AIRPORT LAYOUT PLANS

Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development

More information

Integrated Optimization of Arrival, Departure, and Surface Operations

Integrated Optimization of Arrival, Departure, and Surface Operations Integrated Optimization of Arrival, Departure, and Surface Operations Ji MA, Daniel DELAHAYE, Mohammed SBIHI ENAC École Nationale de l Aviation Civile, Toulouse, France Paolo SCALA Amsterdam University

More information

AIRFIELD CAPACITY AND FACILITY REQUIREMENTS

AIRFIELD CAPACITY AND FACILITY REQUIREMENTS CHAPTER FOUR: AIRFIELD CAPACITY AND FACILITY REQUIREMENTS 4.1 INTRODUCTION A key step in the Airport Master Plan Update (AMPU) process is determining future requirements for airport facilities that will

More information

The pilot and airline operator s perspective on runway incursion hazards and mitigation options. Session 2 Presentation 2

The pilot and airline operator s perspective on runway incursion hazards and mitigation options. Session 2 Presentation 2 The pilot and airline operator s perspective on runway incursion hazards and mitigation options Session 2 Presentation 2 Operational Hazards Workload issues during taxi that can result in a loss of situational

More information

Airports and UAS: Managing UAS Operations in the Airport Vicinity

Airports and UAS: Managing UAS Operations in the Airport Vicinity ACRP Problem Statement 17-10-09 Recommended Allocation: $350,000 Airports and UAS: Managing UAS Operations in the Airport Vicinity ACRP Staff Comments This is one of four UAS-themed problem statements

More information

Aviation Safety Information Analysis and Sharing ASIAS Overview PA-RAST Meeting March 2016 ASIAS Proprietary Do Not Distribute

Aviation Safety Information Analysis and Sharing ASIAS Overview PA-RAST Meeting March 2016 ASIAS Proprietary Do Not Distribute Aviation Safety Information Analysis and Sharing ASIAS Overview PA-RAST Meeting March 2016 ASIAS Proprietary Do Not Distribute Updated: March 2016 2 12 How can safety be improved in an environment of near-zero

More information

DRAFT MASTER PLAN UPDATE

DRAFT MASTER PLAN UPDATE DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS

More information

The demand/capacity analysis was performed utilizing Federal Aviation Administration (FAA) publications, including the following:

The demand/capacity analysis was performed utilizing Federal Aviation Administration (FAA) publications, including the following: Chapter Three To properly plan for the future of Monterey Regional Airport, it is necessary to examine the capacities of the key airport systems. This chapter uses the results of the forecasts prepared

More information

ACTION TRANSMITTAL

ACTION TRANSMITTAL Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED

More information

Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7. European Airspace Concept Workshops for PBN Implementation

Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7. European Airspace Concept Workshops for PBN Implementation Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7 European Airspace Concept Workshops for PBN Implementation Design in Context TFC Where does the traffic come from? And when? RWY Which

More information

INTRODUCTION. General

INTRODUCTION. General CHAPTER FOUR Airfield Demand/Capacity Analysis & Facility Requirements INTRODUCTION A key step in the master plan process is the determination of airport facility requirements to allow airside and landside

More information

Simulation Analysis of Dual CRDA Arrival Streams to Runways 27 and 33L at Boston Logan International Airport

Simulation Analysis of Dual CRDA Arrival Streams to Runways 27 and 33L at Boston Logan International Airport MTR 00W0000128 MITRE TECHNICAL REPORT Simulation Analysis of Dual CRDA Arrival Streams to Runways 27 and 33L at Boston Logan International Airport November 2000 Brian Simmons Linda Boan Dr. Patricia Massimini

More information

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) MEETING #4 AGENDA & ACTION ITEMS Date/Time: Location: Monday, March 19, 2018 from 1:30-3:30 p.m. Thun Field Airport

More information

Airspace Complexity Measurement: An Air Traffic Control Simulation Analysis

Airspace Complexity Measurement: An Air Traffic Control Simulation Analysis Airspace Complexity Measurement: An Air Traffic Control Simulation Analysis Parimal Kopardekar NASA Ames Research Center Albert Schwartz, Sherri Magyarits, and Jessica Rhodes FAA William J. Hughes Technical

More information

3.1 CRITICAL AIRCRAFT

3.1 CRITICAL AIRCRAFT The purpose of the demand capacity analysis is to determine an airport s capacity and its ability to support the forecasted aviation demand. Facility requirements identify development, replacement, and/or

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information