1 The analyses completed in previous chapters evaluated development needs at McKinney National Airport (TKI or Airport) over the next 20 years, based on forecast activity, facility requirements, safety standards, and operational efficiency. This chapter will provide a description and overall cost for each project identified in the capital improvement program (CIP) and development schedule. The program has been evaluated from a variety of perspectives and represents a comparative analysis of basic budget factors, demand, and priority assignments. The presentation of the capital program has been organized into three sections. First, the Airport s capital program needs are identified by various categories ranging from meeting safety and design standards to satisfying demand. Second, the development schedule and CIP cost estimates are presented in narrative and graphic form. The CIP has been developed following Federal Aviation Administration (FAA) guidelines for Master Plans and identifies those projects that are likely eligible for FAA and Texas Department of Transportation Aviation Division (TxDOT) grant funding. Third, capital improvement funding sources on the federal, state, and local levels are identified and discussed. 6-1

2 AIRPORT DEVELOPMENT NEEDS In an effort to identify capital needs at TKI, this section provides analysis regarding the associated development needs of those projects included in the CIP. While some projects will be demand based, others will be dictated by design standards, safety, or rehabilitation needs. Each development need is categorized according to this schedule. The applicable category (or categories) included are presented on Exhibit 6A. The proposed projects can be categorized as follows: 1) Safety/Security (SS) these are capital needs considered necessary for operational safety and protection of aircraft and/or people and property on the ground near an airport. 2) Environmental (EN) these are capital needs which are identified to enable an airport to operate in an environmentally acceptable manner or meet needs identified in the Environmental Overview outlined in Chapter Five. 3) Maintenance (MN) these are capital needs required to maintain the existing infrastructure at an airport. 4) Efficiency (EF) these are capital needs intended to optimize aircraft ground operations or passengers use of the terminal building. 5) Demand (DM) these are capital needs required to accommodate levels of aviation demand. The implementation of these projects should only occur when demand for these needs is verified. 6) Opportunities (OP) these are capital needs intended to take advantage of opportunities afforded by an airport setting. Typically, this will involve improvements to property intended for lease to aviation or non aviation related development. AIRPORT DEVELOPMENT SCHEDULE AND COST SUMMARIES Now that the specific needs and improvements associated with the Master Plan Concept for TKI have been established, the next step is to determine a realistic schedule and the associated costs for implementing the plan. The capital program considers the interrelationships among the projects in order to determine an appropriate sequence of projects, while remaining within reasonable fiscal constraints. This section will examine the overall cost of each item in the capital program. The CIP, programmed by planning horizons, has been developed to cover the short (years 1 5), intermediate (years 6 10) and long term (years 11 20) planning horizons. By utilizing planning horizons instead of specific years, the City of McKinney will have greater flexibility to adjust capital needs as demand dictates. Table 6A summarizes the key milestones for each of the three planning horizons. 6-2

3 Project Number and Description1 Development Category Total Project Cost FAA or TxDOT Eligible Airport/ Local Share SHORT TERM PROGRAM (1-5 YEARS) 1 Construct FBO Facility, Reconfigure Terminal Area Vehicle Access/Parking, and Construct Conventional Hangar in Southwest Development Area (In Design Phase)2 DM/OP $16,000,000 $1,100,000 $14,900,000 2 Relocate Portion of Taxiway B3 to Meet Airfield Geometry Standards SS $1,221,300 $1,099,170 $122,130 3 Rehabilitate/Reconstruct Taxilane A (currently Taxiway A) MN $7,050,500 $6,345,450 $705,050 4 Acquire Approximately 48 Acres of Land on West Side of Airport (South of Industrial Boulevard) for Landside Development DM/OP $16,727,000 $15,054,300 $1,672,700 5 Relocate Hold Position Markings to 256' to Meet RDC D-III Design Standards SS $268,300 $241,470 $26,830 6 Acquire Approximately 326 Acres of Land on East Side of Airport for Future Landside Development DM/OP $28,401,100 $25,560,990 $2,840,110 7 Extend Hangar Access Taxilane (50' Wide) Approximately 500' West (Extension of Taxiway B5) and Reconstruct Existing Taxilane DM/OP $1,877,500 $1,689,750 $187,750 8 Extend Hangar Access Taxilane (50' Wide) Approximately 860' West (Extension of Taxiway B4) and Construct Five (5) T-Hangar Taxilanes (600' x 35') DM/OP $10,138,600 $9,124,740 $1,013,860 9 Acquire Property Interests for Ultimate Approach Protection on Runway (Approximately 49 Acres) SS $4,268,900 $3,842,010 $426, Extend Runway and Parallel Taxiway B 1,500' South (Include Relocation of PAPI-4 and Construction of Holding Bay) DM $16,951,500 $15,256,350 $1,695, Implement MALSR Serving Runway 36 SS $2,033,400 $1,830,060 $203, Acquire Approximately 38 Acres of Land on Northwest Side of Airport for Future Landside Development DM/OP $13,242,200 $11,917,980 $1,324, Acquire Approximately 14 Acres of Land on West Side of Airport (North of Industrial Boulevard) for Future Landside Development DM/OP $4,878,700 $4,390,830 $487, General Airfield Pavement Maintenance Projects MN $500,000 $450,000 $50, Conduct Miscellaneous Annual RAMP Projects SS/MN $500,000 $250,000 $250,000 SHORT TERM PROGRAM TOTAL $124,059,000 $98,153,100 $25,905,900 INTERMEDIATE TERM PROGRAM (6-10 YEARS) 1 Enhance Airfield Lighting (Runway and Taxiways) with LED Technology EF/MN $600,500 $540,450 $60,050 2 Construct Dedicated Airport Maintenance Facilities MN $1,300,000 $0 $1,300,000 3 Construct Hangar Access Taxilane (1,000' x 50') Immediately North of Existing Fuel Farm DM/OP $2,230,400 $2,007,360 $223,040 4 Expand Existing Fuel Farm (Jet A - 30,000 Gallons / 100LL - 12,000 Gallons)3 DM $2,153,000 $600,000 $1,553,000 5 Construct Four (4) T-Hangar/Linear Box Hangar Complexes on West Side of Airport4 DM $3,667,300 $0 $3,667,300 6 Remove 300-Series T-Hangar and 400-Series Linear Box Hangar Complexes on South Apron and Reconstruct Pavement for Aircraft Use DM/OP $7,110,500 $6,399,450 $711,050 7 Construct Hangar Access Taxilane (1,050' x 50') in West Landside Development Area DM/OP $4,544,300 $4,089,870 $454,430 8 Extend Hangar Access Taxilane (50' Wide) Approximately 400' West (Extension of Taxiway B2) and Construct Hangar Taxilane (50' Wide) DM/OP $3,823,600 $3,441,240 $382,360 9 Obtain Right-of-Way and Construct Vehicle Access Road Leading to Northwest Side of Airport DM/OP $3,313,400 $1,656,700 $1,656, Implement Infrastructure Development on East Side of Airport (Multiple Phases) DM/OP $7,149,900 $0 $7,149, General Airfield Pavement Maintenance Projects MN $500,000 $450,000 $50, Conduct Miscellaneous Annual RAMP Projects SS/MN $500,000 $250,000 $250,000 INTERMEDIATE TERM PROGRAM TOTAL $36,892,900 $19,435,070 $17,457,830 LONG TERM PROGRAM (11-20 YEARS) 1 Construct Three (3) T-Hangar Taxilanes (700' x 35') on Northwest Side of Airport - Phase I DM $4,718,600 $4,246,740 $471,860 2 Extend Roadway Access South of Industrial Boulevard and Construct Vehicle Parking DM/OP $5,827,500 $2,913,750 $2,913,750 3 Construct Ultimate General Aviation Terminal Building5 DM/OP/EF $5,736,600 $500,000 $5,236,600 4 Redevelop North Terminal Area (Removal of Facilities and Reconstruct Pavement) DM/OP $7,582,700 $6,553,800 $1,028,900 5 Acquire Property Interests for Ultimate Approach Protection on North and South Sides of Parallel Runway 18L-36R (Approximately 58 Acres) SS $5,053,000 $4,547,700 $505,300 6 Construct Parallel Runway 18L-36R (7,500' x 150') and Associated East Side Parallel Taxiway EN/DM $114,683,300 $103,214,970 $11,468,330 7 Implement Navigational Approach Aids on Parallel Runway System (PAPI-4s and REILs) SS $1,107,000 $996,300 $110,700 8 Construct Midfield Taxiway Network Serving the Parallel Runway System EF/DM $33,347,900 $30,013,110 $3,334,790 9 Construct Three (3) T-Hangar Taxilanes (700' x 35') on Northwest Side of Airport - Phase II DM $4,293,900 $3,864,510 $429, Construct Vehicle Access Serving East Side of Airport DM/OP $9,968,700 $4,984,350 $4,984, Construct Commercial Passenger Service Complex and Aircraft Parking Apron on East Side of Airport DM $146,700,500 $132,030,450 $14,670, Construct Vehicle Access and Parking Serving Commercial Passenger Terminal Complex DM $37,845,600 $34,061,040 $3,784, Construct Fuel Farm on East Side of Airport (Jet A - 30,000 Gallons / 100LL - 12,000 Gallons)3 DM $3,765,700 $600,000 $3,165, General Airfield Pavement Maintenance Projects MN $1,000,000 $900,000 $100, Construct Miscellaneous Annual RAMP Projects SS/MN $1,000,000 $500,000 $500,000 LONG TERM PROGRAM TOTAL $382,631,000 $329,926,720 $52,704,280 TOTAL PROGRAM COSTS $543,582,900 $447,514,890 $96,068, KEY AND NOTES Development Category SS - Safety/Security EN - Environmental MN - Maintenance EF - Efficiency DM - Demand OP - Opportunity AIRPORT MASTER PLAN 1 Project implementation is dependent on federal and state grant funding and availability. 2 FBO facility is eligible for up to $500,000 through TxDOT's terminal building program. Hangar development is eligible for NPE funds and would require the Airport to set aside up to four years of funding at $150,000 per year. 3 Fuel farm expansion is eligible for NPE funds and would require the Airport to set aside up to four years of funding at $150,000 per year. 4 For purposes of this study, it will be assumed that NPE funds will be utilized for other Airport projects in the Intermediate Term Program. 5 General aviation terminal facility is eligible for up to $500,000 through TxDOT's terminal building program. A detailed listing of acronyms are provided in Chapter Six of the Master Plan. Exhibit 6A CAPITAL IMPROVEMENT PROGRAM

4 This page intentionally left blank 6-4

5 TABLE 6A Planning Horizon Activity Levels McKinney National Airport Base Year Short Term Intermediate Term Long Term BASED AIRCRAFT Single Engine Piston Multi Engine Piston Turboprop Jet Helicopter TOTAL BASED AIRCRAFT ANNUAL OPERATIONS Itinerant Air Carrier ,000 General Aviation 41,185 45,675 52,185 63,000 Other Air Taxi 2,628 2,940 3,465 4,725 Military Total Itinerant 43,858 48,668 55,703 70,778 Local General Aviation Military 82, , , , Total Local 82,635 89,197 99, ,437 TOTAL OPERATIONS* 126, , , ,215 * Total operations have been adjusted to account for the hours (10:00 p.m. 6:00 a.m.) when the ATCT is closed. The long term planning horizon includes potential air carrier operations as forecasted in Chapter Two. A key aspect of this planning document is the use of demand based planning milestones. The short term planning horizon contains items of highest need and/or priority. As short term horizon activity levels are reached, it will then be time to program for the intermediate term based upon the next activity milestones. Similarly, when the intermediate term milestones are reached, it will be time to program for the long term activity milestones. Many development items included in the recommended concept will need to follow demand indicators, which essentially establish triggers for specific improvements. For example, the alternatives analysis and Master Plan Concept includes new hangar development. Based aircraft necessitating the need for additional hangar development and the need to accommodate growth in overall activity will be the primary indicator for these projects. If based aircraft growth occurs as projected, additional hangars should be constructed to meet the demand. If growth slows or does not occur as forecasted, some projects may be delayed. As a result, capital expenditures are planned to be made on an as needed basis, which leads to a more responsible use of capital assets. Some development items do not depend on demand, such as pavement maintenance. These types of projects typically are associated with dayto day operations and should be monitored and identified by Airport management. At TKI, some hangars are owned and managed by the Airport and leased to individual tenants (mainly T hangars and linear box hangars), while others are privately owned and managed on land leased from the Airport. Because of economic realities, many airports rely on private developers to construct new 6-5

6 hangars. In some cases, private developers can keep construction costs lower, which, in turn, lowers the monthly lease rates necessary to amortize a loan. The CIP for the Airport assumes that all future hangars would be constructed through public/private partnerships. This assumption does not preclude the possibility of the Airport constructing new hangars. Ultimately, the City of McKinney will determine, based upon demand and the specific needs of a potential developer, whether to self fund hangar construction or to rely on private developers. It is important to note that the CIP does call for the construction of certain T hangar/linear box hangar facilities that could help replace the 300 series and 400 series hangar facilities as detailed in Chapter Five. The capital plan also provides for the Airport to construct apron, taxiway, and taxilane improvements leading to proposed hangar development, which is eligible for FAA and TxDOT grant funding, not individual (exclusive), use(s). Not all projects identified are necessary to meet projected demand. Other projects are necessary to enhance the safety of the Airport, maintain existing infrastructure, or meet FAA design standards. These projects need to be programmed in a timely manner regardless of changes in demand indicators. As a Master Plan is a conceptual document, implementation of the capital projects should only be undertaken after further refinement of their design and costs through architectural or engineering analyses. Moreover, some projects may require additional infrastructure improvements (i.e., drainage improvements, extension of utilities, etc.) that may increase the estimated cost of the project or increase the timeline for completion. Once a list of necessary projects was identified and refined, project specific cost estimates were prepared. These estimates include design, construction administration, and contingency costs that may arise on the project. Capital costs presented here should be viewed only as order of magnitude estimates subject to further refinement during engineering/architectural design. Nevertheless, they are considered sufficient for planning purposes. Cost estimates for each of the development projects in the CIP are based on present day construction, design, and administration costs. Adjustments will need to be applied over time to account for inflation. Specific detail for several project cost estimates is provided in Appendix B. Cost estimates for these projects were provided by RS&H, an engineering firm familiar with construction costs in the area. Exhibit 6A presents the proposed 20 year CIP for TKI. Two things must be considered. First, the proposed CIP is a point in time analysis which will change annually based on actual demand and changing needs. Second, an estimate of grant (federal and/or TxDOT) funding eligibility has been included, although actual funding is not guaranteed. For projects that are eligible for federal/state funding, Airport Improvement Program (AIP)/TxDOT grants provide up to 90 percent of the total project cost. The remaining 10 percent, or more, of project costs are funded locally by the City of McKinney. Other projects, such as the implementation of landside facilities associated with maintenance facilities and fuel farm expansion, are typically not eligible for AIP grants (outside of non primary entitlements) or would rank low on the priority scale. As a result, these projects should be planned for local funding or funding through specific TxDOT programs. 6-6

7 The FAA and TxDOT each utilize a national priority rating system to help objectively evaluate potential airport projects. Projects are weighted toward safety, infrastructure preservation, meeting design standards, and capacity enhancement. These entities will participate in the highest priority projects before considering lower priority projects, even if a lower priority project is considered a more urgent need by the local sponsor. Nonetheless, the project should remain a priority for the airport and funding support should continue to be requested in subsequent years. Several projects identified in the Master Plan Concept are not planned to be constructed within the time period covered in the CIP ( ). For example, the development of certain landside areas in various locations on the east and west sides of the Airport are not included in the CIP as these areas will not likely be needed to meet development needs for the next 20 years. As a result, connected projects, such as the construction of a taxiway/taxilane access to these areas, are also not included within the CIP. These projects are simply placeholders for developments that could occur beyond the scope of this Master Plan. Development projects that are not anticipated to occur during the scope of the CIP or that are anticipated to be funded privately, are identified on Exhibit 6B with white shading. Some projects identified in the CIP will require environmental documentation. The level of documentation necessary for each project must be determined in consultation with the FAA and TxDOT. There are three major levels of environmental review to be considered under the National Environmental Policy Act (NEPA) that include categorical exclusions (CatEx), Environmental Assessments (EA), and Environmental Impact Statements (EIS). Each level requires more time to complete and more detailed information. Guidance on what level of documentation is required for a specific project is provided in FAA Order F, Environmental Impacts: Policies and Procedures. The Environmental Overview presented in Chapter Five addresses NEPA and provides an evaluation of potential environmental impacts for TKI. The following sections will describe in greater detail the projects identified for the Airport over the next 20 years. The projects are grouped based upon a detailed evaluation of existing and projected demand, safety, rehabilitation needs, and local priority. While the CIP identifies the priority ranking of the projects, the list should be evaluated and revised on a regular basis. It is also important to note that certain projects, while listed separately for purposes of evaluation in this study, could be combined with other projects during time of construction/ implementation. SHORT TERM PROGRAM The short term program accounts for the first five years and considers 15 projects for the planning period as presented on Exhibit 6A and depicted on Exhibit 6B. The following provides a detailed breakdown of each project. 6-7

8 Project #1: Construct Fixed Base Operator (FBO) Facility, Reconfigure Terminal Area Vehicle Access/Parking, and Construct Conventional Hangar in Southwest Development Area (In Design Phase) Description: The Airport is in the process of designing a new facility in the terminal area that will accommodate FBO and Airport administration activities. Included with this project is the re design of terminal area vehicle access and parking. As part of this same project, a large conventional hangar is also to be constructed in the southwest area of the Airport. Funding Eligibility: FAA/TxDOT up to $1.1 million / Local remaining share. This project could be eligible for funding assistance through TxDOT s terminal building program, in which TxDOT would help with the construction of this facility on a 50/50 basis with the City of McKinney, up to a $1.0 million total project cost. In this case, $500,000 would be eligible for TxDOT funding, and the remaining share would be the responsibility of the City of McKinney. Regarding the conventional hangar, the Airport could pursue grant funding assistance for the construction of this facility and would require banking up to four years worth of non primary entitlement (NPE) funds ($600,000). The Airport sponsor could decide to bear the entire cost of constructing the hangar facility and associated infrastructure and utilize NPE funds for airside related projects dealing with the runway/taxiway/taxliane system. Project #2: Relocate Portion of Taxiway B3 to Meet Airfield Geometry Standards Description: Relocate the portion of Taxiway B3 between Taxiway A (currently Taxiway A) and Taxiway B approximately 200 feet south. In doing so, the opportunity for direct access from Runway and the aircraft parking apron will be eliminated. Project #3: Rehabilitate/Reconstruct Taxilane A (currently Taxiway A) Description: Rehabilitate/reconstruct Taxilane A that provides access to landside development on the west side of the Airport as this pavement is reaching its useful life. Project #4: Acquire Approximately 48 Acres of Land on West Side of the Airport (South of Industrial Boulevard) for Landside Development Description: This project calls for the acquisition of land on the west side of the Airport that could provide opportunities for an array of aviation related development potential as demand would dictate. This is one of the ideal areas of land adjacent to the Airport to be capable of accommodating short term development, given its proximity to existing Airport property and roadway access. The City of McKinney would be required to fund the upfront property acquisition costs and could be reimbursed by AIP grant funding over time as the property is utilized for aviation related development. Project #5: Relocate Hold Position Markings to 256 to Meet Runway Design Code (RDC) D III Design Standards Description: Relocate the hold lines on all entrance/exit taxiways associated with Runway to 256 feet in order to meet RDC D III design standards. 6-8

9 SHORT TERM PROGRAM (1-5 YEARS) 10 B1 6 6 B2 5 B3 13 Acquire Airport Rd. 9 Obtain Right-of-Way and Construct Vehicle Access Road Leading to Northwest Side of Airport 10 Implement Infrastructure Development on East Side of Airport (Multiple Phases) - NP 11 General Airfield Pavement Maintenance Projects - NP 12 Conduct Miscellaneous Annual RAMP Projects - NP LONG TERM PROGRAM (11-20 YEARS) 1 Construct Three (3) T-Hangar Taxilanes (700' x 35') on Northwest Side of Airport - Phase I 2 Extend Roadway Access South of Industrial Boulevard and Construct Vehicle Parking 3 Construct Ultimate General Aviation Terminal Building 4 Redevelop North Terminal Area (Removal of Facilities and Reconstruct Pavement) 5 Acquire Property Interests for Ultimate Approach Protection on North and South Sides of Parallel Runway 18L-36R (Approximately 58 Acres) 6 Construct Parallel Runway 18L-36R (7,500' x 150') and Associated East Side Parallel Taxiway 8 +/- 14 acres B4 Taxilane A /- 48 acres 10 A3 B5 1 7 FM Road 546 ) 546 FM (. d Blv lop l i K Mc rry Ha 5 4 Acquire +/- 48 acres 7 Implement Navigational Approach Aids on Parallel Runway System (PAPI-4s and REILs) 8 Construct Midfield Taxiway Network Serving the Parallel Runway System 9 Construct Three (3) T-Hangar Taxilanes (700' x 35') on Northwest Side of Airport - Phase II 10 Construct Vehicle Access Serving East Side of Airport 11 Construct Commercial Passenger Service Complex and Aircraft Parking Apron on East Side of Airport 12 Construct Vehicle Access and Parking Serving Commercial Passenger Terminal Complex 13 Construct Fuel Farm on East Side of Airport (Jet A - 30,000 Gallons / 100LL - 12,000 Gallons) 14 General Airfield Pavement Maintenance Projects - NP 15 Conduct Miscellaneous Annual RAMP Projects - NP NP - Not Pictured White - Private development/beyond planning period 6-9 B B B3 1 ia l Blvd B us t r Taxilane A +/- 32 acres B3 Ind 9 B2 B2 Acquire +/- 38 acres 6 8 B A Runway (7,002 x 150 ) Ultimate Runway 18R-36L (8,502 x 150 ) Ultimate Runway 18L-36R (7,500 x 150 ) 8 B1 A1 +/- 11 acres L e lo En 1200 Future Aviation Reserve +/- 45 acres Commercial Passenger Terminal Complex 7 8 ad Ro 0 Sp ur 39 9E xt en sio n /- 11 acres Acquire +/- 1 acre 10 Future Fu F Fut Futu uttu East Airport Drive u utu 13 SCALE IN FEET Acquire 7 12 NORTH R +/- 26 acres 6 Future Aviation Reserve +/- 46 acres +/- 326 acres 5 Terminal Expansion Reserve Old Mill Rd. 1 Enhance Airfield Lighting (Runway and Taxiways) with LED Technology - NP 2 Construct Dedicated Airport Maintenance Facilities 3 Construct Hangar Access Taxilane (1,000' x 50') Immediately North of Existing Fuel Farm 4 Expand Existing Fuel Farm (Jet A - 30,000 Gallons / 100LL - 12,000 Gallons) 5 Construct Four (4) T-Hangar/Linear Box Hangar Complexes on West Side of Airport 6 Remove 300-Series T-Hangar and 400-Series Linear Box Hangar Complexes on South Apron and Reconstruct Pavement for Aircraft Use 7 Construct Hangar Access Taxilane (1,050' x 50') in West Landside Development Area 8 Extend Hangar Access Taxilane (50' Wide) Approximately 400' West (Extension of Taxiway B2) and Construct Hangar Taxilane (50' Wide) ed L INTERMEDIATE TERM PROGRAM (6-10 YEARS) m na n U ay dw a o DR R 1 Construct FBO Facility, Reconfigure Terminal Area Vehicle Access/Parking, and Construct Conventional Hangar in Southwest Development Area (In Design Phase) 2 Relocate Portion of Taxiway B3 to Meet Airfield Geometry Standards 3 Rehabilitate/Reconstruct Taxilane A (currently Taxiway A) 4 Acquire Approximately 48 Acres of Land on West Side of Airport (South of Industrial Boulevard) for Landside Development 5 Relocate Hold Position Markings to 256' to Meet RDC D-III Design Standards 6 Acquire Approximately 326 Acres of Land on East Side of Airport for Future Landside Development 7 Extend Hangar Access Taxilane (50' Wide) Approximately 500' West (Extension of Taxiway B5) and Reconstruct Existing Taxilane 8 Extend Hangar Access Taxilane (50' Wide) Approximately 860' West (Extension of Taxiway B4) and Construct Five (5) T-Hangar Taxilanes (600' x 35') 9 Acquire Property Interests for Ultimate Approach Protection on Runway (Approximately 49 Acres) 10 Extend Runway and Parallel Taxiway B 1,500' South (Include Relocation of PAPI-4 and Construction of Holding Bay) 11 Implement MALSR Serving Runway Acquire Approximately 38 Acres of Land on Northwest Side of Airport for Future Landside Development 13 Acquire Approximately 14 Acres of Land on West Side of Airport (North of Industrial Boulevard) for Future Landside Development 14 General Airfield Pavement Maintenance Projects - NP 15 Conduct Miscellaneous Annual RAMP Projects - NP Terminal Expansion Reserve AIRPORT MASTER PLAN Aerial Photo: Google Earth LEGEND B Existing Airport Property Line Ultimate Airport Property Line Taxiway Name Runway Protection Zone Short Term Projects Intermediate Projects Long Term Projects To Be Removed Non-Airport Development (see note below) Note: As of the date of this document, the roadways shown are part of a draft Master Thoroughfare Plan that, has been reviewed, but not adopted by the McKinney City Council. The draft Master Thoroughfare Plan provides generalized locations, not precise alignments, of future thoroughfares. Alignments shown may shift as roads are engineered and designed. As of the date of this document, location(s) for a Limited Access Roadway (LARs) in close proximity to the McKinney National Airport are being considered by the Texas Department of Transportation (TxDOT); however, have not been identified, finalized or approved and are not shown here. Exhibit 6B CIP DEVELOPMENT STAGING

10 This page intentionally left blank 6-10

11 Project #6: Acquire Approximately 326 Acres of Land on East Side of Airport for Future Landside Development Description: In order to allow opportunities for TKI to expand its airside and landside development capabilities, the acquisition of approximately 326 acres of land is programmed adjacent to the east side of existing Airport property. Acquisition of east side property will not likely be justified in the short term; however, the plan is offering a proactive schedule to ensure that the Airport is protected. It should be noted that one residential property parcel is included in this proposed land acquisition. The City of McKinney would be required to fund the upfront property acquisition cost and could be reimbursed by AIP grant funding over time as the property is utilized for aviation related development. Project #7: Extend Hangar Access Taxilane (50 Wide) Approximately 500 West (Extension of Taxiway B5) and Reconstruct Existing Taxilane Description: In order to provide access for continued landside development in the southwest area of TKI, this project entails the extension of a taxilane farther west that would provide access to future private hangar development. In addition, the existing pavement would be reconstructed to better meet projected aircraft demand planned for this area. Project #8: Extend Hangar Access Taxilane (50 Wide) Approximately 860 West (Extension of Taxiway B4) and Construct Five (5) T Hangar Taxilanes (600 x 35 ) Description: Once the acquisition of the 48 acre parcel is complete, taxilane access could be extended farther west to provide the opportunity for landside development in the form of T hangars/linear box hangars, and larger conventional hangars. This project would also include the construction of taxilanes leading directly to T hangar/linear box hangar development. Project #9: Acquire Property Interests for Ultimate Approach Protection on Runway (Approximately 49 Acres) Description: This project calls for the purchase of approximately 48 acres on the south side of Runway and one acre on the north side of the runway to allow the Airport to control the runway protection zones (RPZs), which is highly recommended by the FAA. The proposed land acquisition on the south side of the Airport would encompass the RPZ associated with a 1,500 foot runway extension and ½ mile visibility minimum approach. The associated cost estimate includes fee simple acquisition over this property. There is one residential property parcel included in this proposed land acquisition. Project #10: Extend Runway and Parallel Taxiway B 1,500 South (Include Relocation of Four Box Precision Approach Path Indicators [PAPI 4] and Construction of Holding Bay) Description: This project extends Runway ,500 feet to the south so that the runway can better accommodate landing and takeoff operations by larger business jet aircraft and potential commercial service aircraft. Associated with this project is the extension of parallel Taxiway B and the relocation of navigational approach aids. 6-11

12 Project #11: Implement Medium Intensity Approach Lighting System with Runway Alignment Indicator Lights (MALSR) Serving Runway 36 Description: In association with the proposed runway extension, this project includes the implementation of a MALSR serving Runway 36. This system is similar to the existing medium intensity approach lighting system (MALS) that currently serves Runway 36, except that it provides a light lane that extends farther south, allowing for increased visibility of the runway system. Project #12: Acquire Approximately 38 Acres of Land on Northwest Side of Airport for Future Landside Development Description: In an effort to allow the Airport to meet future aviation demand potential, this project includes the acquisition of approximately 38 acres of land on the northwest side of TKI. Future landside development could be granted airfield access via Taxilane A immediately to the east. The Airport would be required to fund the upfront property acquisition cost and could be reimbursed by AIP grant funding over time as the property is utilized for aviation related development. Project #13: Acquire Approximately 14 Acres of Land on West Side of Airport (North of Industrial Boulevard) for Future Landside Development Description: Similar to the project above, additional land acquisition is programmed on the west side of the Airport that includes approximately 14 acres immediately north of Industrial Boulevard. The Airport would be required to fund property acquisition costs and would be reimbursed by AIP grant funding over time as the property is utilized for aviation related development. Project #14: General Airfield Pavement Maintenance Projects Description: This includes a line item in the CIP that allocates a certain amount of funding for the general maintenance of various pavements not specifically identified by project in the CIP and could include crack sealing and other routine maintenance. Funding Eligibility: FAA/TxDOT 90 percent / Local 10 percent Project #15: Conduct Miscellaneous Annual Routine Airport Maintenance Program (RAMP) Projects Description: The final project listed in the short term program includes miscellaneous projects which could be funded through TxDOT s RAMP. Each year, TxDOT offers RAMP funds of up to $50,000, providing the airport sponsor furnishes a 50 percent match ($50,000). Thus, an airport can have up to $100,000 available for pavement maintenance or other general or routine maintenance projects that may arise during the term. This CIP considers TKI utilizing this source of funding to the maximum extent possible each year. Funding Eligibility: TxDOT 50 percent / Local 50 percent. 6-12

13 Short Term Program Summary The short term CIP includes projects that enhance the overall safety, efficiency, and maintenance of the airfield, while also positioning TKI to meet future aviation demand through the acquisition of various properties adjacent to the Airport. The total investment necessary for the short term CIP is approximately $124.1 million. Approximately $98.2 million is programmed for federal/state funding assistance. The remaining $25.9 million is to be provided through local funding outlets. As previously detailed, the financial responsibility of acquiring property for landside development potential would initially fall to the City of McKinney and, over time, AIP grant funding could be made available for reimbursement as the properties are developed for aviation related purposes. INTERMEDIATE TERM PROGRAM The intermediate term projects are those that are anticipated to be necessary in years six through 10 of the Master Plan. These projects have been prioritized so that Airport management has the flexibility to determine when they need to be pursued based on current conditions. It is not unusual for certain projects to be delayed or advanced based on changing conditions, such as funding availability or changes in the aviation industry. This planning horizon includes 12 projects for the five year timeframe as listed on Exhibit 6A and depicted on Exhibit 6B. The following section includes a description of each project. Project #1: Enhance Airfield Lighting (Runway and Taxiways) with Light Emitting Diode (LED) Technology Description: Implement LED lighting on appropriate runway and taxiway edge lighting and signage systems. As previously discussed, this project could be broken out and programmed with the reconstruction/rehabilitation of runway and taxiway pavements on the airfield. Projects #2: Construct Dedicated Airport Maintenance Facilities Description: Construct maintenance facilities and associated staging area adjacent to the east side of the fuel farm. In doing so, the existing area dedicated to maintenance equipment/storage can be redeveloped over time to accommodate aviation demand. Funding Eligibility: Local 100 percent. These facilities would rank low for AIP grant eligibility. It is possible that TxDOT RAMP funding could be available for the construction of the maintenance facilities, but only up to $50,000 annually would be available for use. As such, these facilities are programmed for local funding only. Project #3: Construct Hangar Access Taxilane (1,000 x 50 ) Immediately North of Existing Fuel Farm Description: Construct a taxilane extending west from Taxilane A (currently Taxiway A) that would could provide access to future private executive hangar development. 6-13

14 Project #4: Expand Existing Fuel Farm (Jet A 30,000 Gallons / 100LL 12,000 Gallons) Description: This project would be demand based and entail expanding the existing fuel farm on the west side of the Airport. Currently, the fuel farm has the capability of accommodating six additional storage tanks. Funding Eligibility: FAA/TxDOT up to $600,000 / Local remaining share. The Airport could pursue grant funding assistance for the expansion of the fuel farm and would require banking up to four years worth of NPE funds in order to do so. Project #5: Construct Four (4) T Hangar/Linear Box Hangar Complexes on West Side of Airport Description: This project could entail replacing aircraft storage displaced as a result of the City owned 300 series and 400 series hangar complexes planned for removal in an effort to redevelop the south aircraft parking apron area (next project). The construction of four T hangar/linear box hangar complexes are proposed to help accommodate aircraft storage that currently utilize the 300 series and 400 series hangars, as well as meet the demand for new based aircraft storage. Funding Eligibility: Local 100 percent. The Airport could pursue grant funding assistance for the construction of these hangars and would require banking up to four years worth of NPE funds. For purposes of this study, it is assumed that the Airport sponsor will bear the entire cost of constructing the hangar facilities and associated infrastructure, and utilize NPE funds for other eligible projects such as the expansion of the fuel farm as previously detailed. If the hangar development project is not constructed by the Airport, it can be assumed that the City of McKinney will pursue private development of these proposed aircraft storage hangars. Project #6: Remove 300 Series T Hangar and 400 Series Linear Box Hangar Complexes on South Apron and Reconstruct Pavement for Aircraft Use Description: In an effort to increase aircraft parking apron space and enhance terminal area services, the removal of the 300 series and 400 series hangar complexes is programmed at this time. The reconstruction of this pavement area would also be needed in order to support aircraft operations planned for this area. Project #7: Construct Hangar Access Taxilane (1,050 x 50 ) in West Landside Development Area Description: Extend taxilane access in the 48 acre acquisition parcel that would allow access to private conventional hangar development, which could accommodate an array of aviation activities. Project #8: Extend Hangar Access Taxilane (50 Wide) Approximately 400 West (Extension of Taxiway B2) and Construct Hangar Taxilane (50 Wide) Description: This project is dependent on the proposed acquisition of 14 acres north of Industrial Boulevard and includes extending taxilane access to future hangar development as demand would dictate. 6-14

15 Project #9: Obtain Right of Way and Construct Vehicle Access Road Leading to Northwest Side of Airport Description: As demand would dictate, a vehicle roadway should be planned extending east from Airport Road that would provide access to future aviation related development. At a minimum, a right of way easement would be needed to construct the roadway through private property adjacent to the northwest side of TKI. Funding Eligibility: FAA/TxDOT 50 percent / Local 50 percent. The access roadway could be eligible for AIP funding assistance as they would serve aviation related activities, and are eligible on a 50/50 basis with TxDOT. Project #10: Implement Infrastructure Development on East Side of Airport (Multiple Phases) Description: Pending property acquisition as called for in the short term planning horizon, the implementation of infrastructure development could be needed as aviation demand dictates in the east area of the Airport. Funding Eligibility: Local 100 percent. Similar to other landside development, these landside enhancements are not typically eligible for AIP funding assistance. It is possible that TxDOT RAMP funding could be eligible for infrastructure development, but given the scope of this phased development, these projects are programmed for local funding only. Project #11: General Airfield Pavement Maintenance Projects Description: This includes a line item in the CIP that allocates a certain amount of funding for the general maintenance of various pavements not specifically identified by project in the CIP and could include crack sealing and other routine maintenance. Funding Eligibility: FAA/TxDOT 90 percent / Local 10 percent Project #12: Conduct Miscellaneous Annual RAMP Projects Description: Similar to the short term CIP, participation in the RAMP is assumed in each year of the intermediate term program with full utilization of $100,000 annually. Funding Eligibility: TxDOT 50 percent / Local 50 percent. Intermediate Term Program Summary The total costs associated with the intermediate term program are estimated at $36.9 million. Of this total, approximately $19.4 million could be eligible for federal/state funding, and the local share is projected at $17.5 million. LONG TERM PROGRAM Long term projects are those that likely extend into years 11 through 20 of this study and continue to call for landside development potential on the west side of the Airport. A proposed parallel runway is also considered during this timeframe which could provide opportunities for development on the east 6-15

16 side of the Airport as well. As such, these projects are demand driven and involve the following, as further outlined on Exhibit 6A and illustrated on Exhibit 6B. Project #1: Construct Three (3) T Hangar Taxilanes (700 x 35 ) on Northwest Side of Airport Phase I Description: The construction of these taxilanes could serve T hangar/linear box hangar complexes that would accommodate small aircraft storage. Project #2: Extend Roadway Access South of Industrial Boulevard and Construct Vehicle Parking Description: In order to expand the ultimate general aviation terminal area, a vehicle roadway is extended south from Industrial Boulevard that would provide access to a vehicle parking area and proposed terminal/hangar development. Funding Eligibility: FAA/TxDOT 50 percent / Local 50 percent. The access roadway and parking lot could be eligible for AIP funding assistance as they would serve aviation related activities, and are eligible on a 50/50 basis with TxDOT. Project #3: Construct Ultimate General Aviation Terminal Building Description: This project includes the construction of a terminal building adjacent to the west side of the south aircraft parking apron that could enhance services offered to general aviation users. Funding Eligibility: FAA/TxDOT up to $500,000 / Local remaining share. This project could be eligible for funding assistance through TxDOT s terminal building program, in which TxDOT would help with the construction of this facility on a 50/50 basis with the City of McKinney, up to a $1.0 million total project cost. In this case, $500,000 would be eligible for TxDOT funding, and the remaining share would be the responsibility of the City of McKinney. Project #4: Redevelop North Terminal Area (Removal of Facilities and Reconstruct Pavement) Description: With the focus on expanding general aviation terminal services to the south, the existing terminal area could ultimately be redeveloped to meet future aviation demands. This could include razing existing facilities and implementing an assortment of hangar facilities and aircraft parking apron space. As detailed in Chapter Five, it is recommended that a separate study be conducted to assess the redevelopment potential for this area. Funding Eligibility: FAA/TxDOT 90 percent for eligible work items / Local remaining share. The federal/state share includes items related to the reconstruction/rehabilitation of pavements for planned aircraft utilization. Ineligible items include those associated with the removal of facilities in the existing terminal area. Project #5: Acquire Property Interests for Ultimate Approach Protection on North and South Sides of Parallel Runway 18L 36R (Approximately 58 Acres) Description: This is the first of four consecutive projects that are related to the construction of a parallel runway at TKI. This particular project calls for the acquisition of property to help protect ultimate RPZs and approach areas that could be associated with the construction of a parallel runway (next project). There are five residential property parcels on the south side of the Airport included in this proposed property acquisition. 6-16

17 Project #6: Construct Parallel Runway 18L 36R (7,500 x 150 ) and Associated East Side Parallel Taxiway Description: The construction of a parallel runway is programmed during the long term that calls for an ultimate length of 7,500 feet. As detailed in the previous chapter, this project could be split into multiple phases that would be dependent on justification and funding availability. Extensive environmental documentation would also be needed for a project of this magnitude. The construction of a parallel taxiway is associated with the proposed runway. Project #7: Implement Navigational Approach Aids on Parallel Runway System (PAPI 4s and Runway End Identification Lights [REILs]) Description: To enhance the utilization of the parallel runway, the implementation of PAPI 4s and REILs is programmed on each runway end. Project #8: Construct Midfield Parallel Taxiway Network Serving the Parallel Runway System Description: This project would likely be associated with the proposed implementation of the parallel runway and would include the construction of a midfield taxiway network connecting both runways and, ultimately, the east and west sides of the Airport. Project #9: Construct Three (3) T Hangar Taxilanes (700 x 35 ) on Northwest Side of Airport Phase II Description: The Phase II construction of these taxilanes could serve T hangar/linear box hangar complexes that would accommodate small aircraft storage as demand dictates. Project #10: Construct Vehicle Access Serving East Side of Airport Description: This is the first of four projects that deal with enhancing landside development on the east side of TKI. In order to provide for development opportunities, this project would provide vehicle access to the area. The proposed roadway(s) are dependent on the ultimate alignment of future roads being studied by the City of McKinney and are subject to change. Funding Eligibility: FAA/TxDOT 50 percent / Local 50 percent. The access roadway could be eligible for AIP funding assistance as they would serve aviation related activities, and are eligible on a 50/50 basis with TxDOT. Project #11: Construct Commercial Passenger Service Complex and Aircraft Parking Apron on East Side of Airport Description: This project is dependent on the demand for commercial service operations being realized at TKI in the future. A detailed analysis of potential commercial aircraft activity at the Airport was prepared earlier in this Master Plan. This project includes the building infrastructure and aircraft parking apron and would likely be separated into multiple phases if ever realized. Furthermore, it is likely that a specific terminal area study would be undertaken prior to the design and construction of future terminal facilities in this area. 6-17

18 Project #12: Construct Vehicle Access and Parking Serving Commercial Passenger Terminal Complex Description: Based upon the scope and phasing of a potential commercial service complex, this project entails the construction of support facilities in the form of vehicle access and parking and would likely be phased over several projects if ever realized. This project is related to vehicle roadway and parking associated with commercial service activities, and would not be eligible for TxDOT funding assistance. The access roadway and parking lot could be eligible for AIP funding assistance as they would serve aviation related activities leading directly to the proposed commercial terminal complex. In the event that the Airport were to implement a pay for parking program, vehicle parking would not be eligible for AIP funds. Project #13: Construct Fuel Farm on East Side of Airport (Jet A 30,000 Gallons / 100LL 12,000 Gallons) Description: Based on the demand for landside development on the east side of the Airport, the implementation of a fuel farm could provide for a safer and more efficient airfield operating environment. Funding Eligibility: FAA/TxDOT up to $600,000 / Local remaining share. The Airport could pursue grant funding assistance for the expansion of the fuel farm and would require banking up to four years worth of NPE funds in order to do so. Project #14: Conduct General Pavement Maintenance Description: Similar to being programmed in the short and intermediate term planning horizons, this includes a line item in the long term CIP that allocates a certain amount of funding for the general maintenance of various pavements not specifically identified by project in the CIP and could include crack sealing and other routine maintenance. Project #15: Conduct Miscellaneous Annual RAMP Projects Description: Participation in the RAMP is assumed in each year of the long term program with full utilization of $100,000 annually. Funding Eligibility: TxDOT 50 percent / Local 50 percent. Long Term Program Summary The total costs associated with the long term program are estimated at $382.6 million. Of this total, over $330 million is associated with demand driven projects associated with a parallel runway system and commercial service operations. Approximately $329.9 million could be eligible for federal/state funding. The local matching share is projected at $52.7 million. 6-18

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM PORT OF PORTLAND Chapter Seven CAPITAL IMPROVEMENT PROGRAM CHAPTER SEVEN PORT OF PORTLAND CAPITAL IMPROVEMENT PROGRAM The analyses conducted in the previous chapters evaluated airport development needs

More information

Chapter 8.0 Implementation Plan

Chapter 8.0 Implementation Plan Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.

More information

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

Punta Gorda Airport Master Plan Update

Punta Gorda Airport Master Plan Update Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,

More information

10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM

10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM 10.1 INTRODUCTION Based on the findings from the Facility Requirements and the combined plan recommended in the Alternative Analysis, a capital improvement program for North Perry Airport has been developed

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

Finance and Implementation

Finance and Implementation 5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter

More information

MASTER PLAN CONCEPT 1 DRAFT

MASTER PLAN CONCEPT 1 DRAFT The Airport Master Plan Update for Dallas Executive Airport has included the development of aviation demand forecasts, an assessment of future facility needs, and the evaluation of airport development

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport

More information

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP) 6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Project Team Kittitas County, WA Airport Owner (Sponsor) and Operator, Land Use Century West

More information

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES 5.1 INTRODUCTION This section investigates Airfield Development Alternatives, generalized Land Use Alternatives, and more detailed General Aviation Alternatives.

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013 New York State Department of Transportation Safety, Infrastructure, and Tenant Improvement Project Public Hearing Informational Brochure February 26, 2013 This DEIS/Draft EA evaluates the potential impacts

More information

Chapter 9 Airport Financial Plan

Chapter 9 Airport Financial Plan Chapter 9 Airport Financial Plan Introduction The purpose of this chapter is to present the projects identified in the twenty-year Airport Capital Improvement Program (ACIP) that have been developed and

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the

More information

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four Airport Development Alternatives Prior to formulating a development program for Ryan Airfield, it is important to consider development potential

More information

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet

More information

Grants Pass Airport Master Plan & Airport Layout Plan Update

Grants Pass Airport Master Plan & Airport Layout Plan Update Attendees: Grants Pass Airport Master Plan & Airport Layout Plan Update Meeting #3 January 26, 2010 Merlin Community Center 100 Acorn Street, Merlin 5:45 7:15 p.m. Josephine County Department of Airports:

More information

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update Chapter Seven Implementation Plan Master Plan Update This chapter presents the 20-year improvement program for the continued development of the. The objectives of this chapter are to identify projects

More information

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Project Team Century West Engineering Northwest firm founded in 1969 500+ airport projects completed throughout the Pacific

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9

More information

Technical Memorandum. Synopsis. Steve Carrillo, PE. Bryan Oscarson/Carmen Au Lindgren, PE. April 3, 2018 (Revised)

Technical Memorandum. Synopsis. Steve Carrillo, PE. Bryan Oscarson/Carmen Au Lindgren, PE. April 3, 2018 (Revised) Appendix D Orange County/John Wayne Airport (JWA) General Aviation Improvement Program (GAIP) Based Aircraft Parking Capacity Analysis and General Aviation Constrained Forecasts Technical Memorandum To:

More information

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017 Lopez Island Airport Master Plan Update Public Meeting June 15, 2017 Master Plan Update Team Reid Middleton/Everett, WA Shannon Kinsella, Project Manager Melania Haagsma, Project Engineer Mead & Hunt/Tulsa,

More information

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on

More information

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

Chapter 5 Airport Development Alternatives

Chapter 5 Airport Development Alternatives Chapter 5 Airport Development Alternatives Introduction CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-1 Evaluation Process No-Action Alternative CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-2

More information

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

CHAPTER 1 BACKGROUND AND PROPOSED ACTION

CHAPTER 1 BACKGROUND AND PROPOSED ACTION CHAPTER 1 BACKGROUND AND PROPOSED ACTION 1.0 INTRODUCTION An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance

More information

Airport Master Plan Open House Front Range Airport February 23, 2017

Airport Master Plan Open House Front Range Airport February 23, 2017 Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future

More information

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

Lake Tahoe Airport Master Plan

Lake Tahoe Airport Master Plan Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development

More information

CHAPTER 1 INTRODUCTION AND BACKGROUND

CHAPTER 1 INTRODUCTION AND BACKGROUND CHAPTER 1 INTRODUCTION AND BACKGROUND An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance with the National

More information

Appendix C AIRPORT LAYOUT PLANS

Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

CHAPTER FOUR AIRPORT ALTERNATIVES

CHAPTER FOUR AIRPORT ALTERNATIVES 4.0 INTRODUCTION CHAPTER FOUR The goal of the master planning process is to provide the City of New Smyrna Beach with an assessment of the adequacy and capabilities of the Airport as well as to identify

More information

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East

More information

Blue Grass Airport (LEX) serves the needs of a multi-county area that

Blue Grass Airport (LEX) serves the needs of a multi-county area that SUMMARY BACKGROUND This Master Plan Update balances needed airport improvements with the goals of the community and arrived at a consensus on how to best meet future demand without sacrificing those natural

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

chapter 5 Recommended Master Plan Concept airport master plan MASTER PLAN CONCEPT

chapter 5 Recommended Master Plan Concept airport master plan MASTER PLAN CONCEPT chapter 5 Recommended Master Plan Concept airport master plan The planning process for Coolidge Municipal Airport has included several analytical efforts in the previous chapters intended to project potential

More information

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment PUBLIC NOTICE The Dallas Department of Aviation (the Department) intends to file an amendment application to increase the PFC amount of one previously approved project at Dallas Love Field Airport (the

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

DALLAS LOVE FIELD MAY 2015 DRAFT

DALLAS LOVE FIELD MAY 2015 DRAFT 8. Funding Plan This section presents a potential funding plan for implementing the CIP projects recommended in the Master Plan Update, along with an assessment of the ability of the Airport sponsor (i.e.,

More information

Chapter 4.0 Alternatives Analysis

Chapter 4.0 Alternatives Analysis Chapter 4.0 Alternatives Analysis Chapter 1 accumulated the baseline of existing airport data, Chapter 2 presented the outlook for the future in terms of operational activity, Chapter 3 defined the facilities

More information

CHAPTER 5: Landside Facility Requirements and Development Concepts

CHAPTER 5: Landside Facility Requirements and Development Concepts CHAPTER 5: Landside Facility Requirements and Development Concepts Overview Implementation of the preferred intermediate-term (10-year) and long-term (20-year) airside alternatives will have a significant

More information

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012 1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 1 - Introduction This report describes the development and analysis of concept alternatives that would accommodate

More information

3.9 AIRPORT SUPPORT FACILITIES

3.9 AIRPORT SUPPORT FACILITIES 3.9 AIRPORT SUPPORT FACILITIES This section details additional airfield facilities that may be required over the next 20 years. 3.9.1 Airport Rescue and Fire Fighting (ARFF) Station GEG is certified under

More information

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan Technical Report #7 Palm Beach International Airport Layout Plan Palm Beach International Airport Prepared for Palm Beach County

More information

Alternatives. Introduction. Range of Alternatives

Alternatives. Introduction. Range of Alternatives Alternatives Introduction Federal environmental regulations concerning the environmental review process require that all reasonable alternatives, which might accomplish the objectives of a proposed project,

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

Chapter 2 FINDINGS & CONCLUSIONS

Chapter 2 FINDINGS & CONCLUSIONS Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued

More information

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment 1.0 INTRODCTION Morristown Municipal Airport (hereinafter referred to as MM or Airport ) is a busy general aviation reliever airport owned by the Town of Morristown and operated by DM AIRPORTS, LTD. (hereinafter

More information

Existing Conditions AIRPORT PROFILE Passenger Terminal Complex 57 air carrier gates 11,500 structured parking stalls Airfield Operations Area 9,000 North Runway 9L-27R 6,905 Crosswind Runway 13-31 5,276

More information

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item.

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item. Committee Report Business Item No. 2017-191 Transportation Committee For the Metropolitan Council meeting of September 13, 2017 Subject: Final Crystal Airport 2035 Long Term Comprehensive Plan (LTCP) Proposed

More information

Appendix 6.1: Hazard Worksheet

Appendix 6.1: Hazard Worksheet Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp

More information

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February

More information

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3 This is the presentation for the third Master Plan Update Working Group Meeting being conducted for the Ted Stevens Anchorage International Airport Master Plan Update. It was given on Thursday March 7

More information

6.1 INTRODUCTION 6.2 AIRSIDE ALTERNATIVES NORTH PERRY AIRPORT MASTER PLAN UPDATE RUNWAY LENGTH REQUIREMENTS SECTION 6: ALTERNATIVES ANALYSIS

6.1 INTRODUCTION 6.2 AIRSIDE ALTERNATIVES NORTH PERRY AIRPORT MASTER PLAN UPDATE RUNWAY LENGTH REQUIREMENTS SECTION 6: ALTERNATIVES ANALYSIS 6.1 INTRODUCTION In the previous chapter, facility needs for the 20-year planning horizon were identified. The next step in the planning process is to identify and evaluate the various ways certain facilities

More information

DRAFT MASTER PLAN UPDATE

DRAFT MASTER PLAN UPDATE DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS

More information

Regular Board Meeting August 4, 2015

Regular Board Meeting August 4, 2015 Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956 PUBLIC COMMENT FY 16 Rates & Charges FY 16 Budget Approval Rates & Charges will provide the Board the ability to operate

More information

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D STAFF REPORT SUBJECT: Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan MEETING DATE: AGENDA ITEM: 7D STAFF CONTACT: Peter Imhof, Andrew Orfila RECOMMENDATION: Adopt findings

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

Technical Advisory Committee Meeting February 29, 2016

Technical Advisory Committee Meeting February 29, 2016 Technical Advisory Committee Meeting February 29, 2016 Meeting Agenda Introduction Recap of Planning Process Project Status Goals and Objectives Forecasts of Aviation Demand Overview of Facility Requirements

More information

Introduction DRAFT March 9, 2017

Introduction DRAFT March 9, 2017 Chapter Overview The City of Redmond (City) initiated an update to the Airport Master Plan ( Plan ) to assess the facility and service needs of the Redmond Municipal Airport ( the Airport ) throughout

More information

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35 Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements

More information

Chapter 1 Introduction and Project Overview

Chapter 1 Introduction and Project Overview Chapter 1 Introduction and Project Overview Kittitas County in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Bowers Field Airport (FAA airport identifier

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

Business Plan INTRODUCTION AIRPORT ENTERPRISE FUND OVERVIEW. Master Plan Guiding Principles

Business Plan INTRODUCTION AIRPORT ENTERPRISE FUND OVERVIEW. Master Plan Guiding Principles 5 Business Plan INTRODUCTION Just as previous chapters have outlined plans for the airport s physical development, this chapter outlines a plan for the airport s financial development. More specifically,

More information

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally

More information

CHAPTER 4: ALTERNATIVES

CHAPTER 4: ALTERNATIVES MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures

NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures DFW International Airport Sandy Lancaster, Manager Noise Compatibility October 13, 2008 OUTLINE About DFW Airport

More information

6.0 DEVELOPMENT PLAN/FINANCIAL OVERVIEW

6.0 DEVELOPMENT PLAN/FINANCIAL OVERVIEW 6.0 DEVELOPMENT PLAN/FINANCIAL OVERVIEW A goal of this Airport Master Plan was to review the requirements and alternatives necessary for the to meet their identified current and future demand. With this

More information

INDEPENDENCE STATE AIRPORT (7S5)

INDEPENDENCE STATE AIRPORT (7S5) INDEPENDENCE STATE AIRPORT (7S5) Airport Master Plan Update 2018 Planning Advisory Committee PAC Meeting #3 April 11, 2018 1994-2016 AGENDA The second PAC workshop will cover the following topics: Recap

More information

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018 COUNTY OF INYO REQUEST FOR QUALIFICATIONS For Airport Environmental Services Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018 County of Inyo Public Works Department P.O.

More information

Dallas Executive Airport

Dallas Executive Airport 648 DECLARED DISTANCE OPTION 1a DISPLACE 31 THRESHOLD BY 97 Considers RSA Limiting Factor No runway extensions 13 31 TORA 6,451 6,451 TODA 6,451 6,451 ASDA 5,958 6,451 LDA 5,958 6,354 Runway 17-35 (3,8

More information

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN LAST UPDATE JULY 2013 Acknowledgements The preparation of this document was financed in part by a grant from the Federal Aviation Administration (Project No: 3-27-0000-07-10), with the financial support

More information

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California Yolo County Airport ALP Narrative Report April 2016 Prepared by Mead & Hunt, Inc. for the County of Yolo, California Yolo County Airport ALP Narrative Report Prepared for the County of Yolo Mindi Nunes,

More information

Collier County Airport Authority. Joint Automated Capital Improvement Program

Collier County Airport Authority. Joint Automated Capital Improvement Program Collier County Airport Authority Joint Automated Capital Improvement Program Joint Automated Capital Improvement Program (JACIP) What is the JACIP? Financial planning process supported by Web-based computer

More information

Dallas Executive Airport Town Hall Meeting April 3, 2014

Dallas Executive Airport Town Hall Meeting April 3, 2014 Dallas Executive Airport Town Hall Meeting April 3, 2014 Background 1,040 acre general aviation facility owned and operated by the City of Dallas 150 based aircraft including business jets and helicopters,

More information

CASE STUDY The New Guayaquil International Airport

CASE STUDY The New Guayaquil International Airport www.jacobs.com worldwide CASE STUDY The New Guayaquil International Airport Prepared for ICAO Airport Planning Seminar for the SAM Region Lima, Peru 10-14 Sep. 2018 September 11, 2018 Outline Existing

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) MEETING #4 AGENDA & ACTION ITEMS Date/Time: Location: Monday, March 19, 2018 from 1:30-3:30 p.m. Thun Field Airport

More information

Yakima Air Terminal/McAllister Field Airport Master Plan Update

Yakima Air Terminal/McAllister Field Airport Master Plan Update Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used

More information

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS AIRSIDE CAPACITY AND FACILITY REQUIREMENTS This Section investigates the capacity of the airport, its ability to meet current demand, and the facilities required to meet forecasted needs as established

More information

Airlake Airport 2035 Long Term Comprehensive Plan (LTCP)

Airlake Airport 2035 Long Term Comprehensive Plan (LTCP) Airlake Airport 2035 Long Term Comprehensive Plan (LTCP) Public Informational Meetings August 9 & 10, 2017 Draft LTCP Overview Briefing Agenda Airport Role & Context Existing Conditions & Previous Plan

More information

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016 Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand

More information

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by:

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by: Draft AIRPORT MASTER PLAN Newport State Airport () Prepared for: 2000 Post Road Warwick, Rhode Island 02886-1533 THE Louis Berger Group, INC. 20 Corporate Woods Boulevard Albany, New York 12211-2370 Prepared

More information

JOHNSTON COUNTY AIRPORT AUTHORITY

JOHNSTON COUNTY AIRPORT AUTHORITY JOHNSTON COUNTY AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS FOR AIRPORT PLANNING SERVICES For JOHNSTON REGIONAL AIRPORT (JNX) 3149 Swift Creek Rd. Smithfield, NC 27577 PHIL LANIER AIRPORT DIRECTOR (919)

More information

TXDOT AVIATION DIVISION

TXDOT AVIATION DIVISION TXDOT AVIATION DIVISION Airport Project Development & Selection Process Today s Topics Project Development Process Working with TxDOT Aviation Division Funding Sources National Plan of Integrated Airports

More information

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4 MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis

More information

Fort Wayne International Airport Master Plan Study. Executive Summary

Fort Wayne International Airport Master Plan Study. Executive Summary Fort Wayne International Airport Master Plan Study Executive Summary March 2012 Introduction Airport Background Forecast of Aviation Activity Development Plans Recommended Airfield & Access Development

More information

Chapter 4 Airport Facility Requirements

Chapter 4 Airport Facility Requirements Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT

More information