10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM

Save this PDF as:
 WORD  PNG  TXT  JPG

Size: px
Start display at page:

Download "10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM"

Transcription

1 10.1 INTRODUCTION Based on the findings from the Facility Requirements and the combined plan recommended in the Alternative Analysis, a capital improvement program for North Perry Airport has been developed and is presented in this chapter. Capital improvements that are anticipated to be primarily developed and funded by the private sector (i.e., T-hangars, maintenance hangars, aprons, and other related private development initiatives) have not been included in the Airport s capital improvement program. The recommended capital improvements are listed and depicted by planning horizon, namely: Short-term ( ); Mid-term ( ); and Long-term ( ). Projects have been placed in their respective planning horizons based on existing conditions, prioritization of issues, and typical facility rehabilitation needs. Projects may be expedited or delayed based on needs identified by Broward County Aviation Department (BCAD), and funding availability. Conceptual cost estimates for each of the development projects listed in the capital improvement program have been developed in 2007 dollars. Appendix H provides the conceptual estimate and project detailing for each phase of the proposed capital improvement program for North Perry Airport. The following comments are provided regarding the conceptual cost estimates: The conceptual estimates have been prepared for the purpose of providing cost feedback at an early stage in the project planning and programming process. The cost information will enable BCAD to modify the scope of work as needed to arrive at a design and scope that both satisfies the BCAD s needs and is within the budget. Asphalt prices are very volatile; costs for P-401 bituminous surface have been estimated to be $86.00 per ton in these estimates. The price of asphalt should be reviewed as appropriate to update any changes in pricing, which may present budget impacts. The estimates are based on conceptual assumptions contained in the project detailing. Only minimal data has been used to prepare these estimates. It is expected that the cost estimates will require additional refinement, adjustments in scope, price, and escalation prior to implementation. No design has been accomplished for the preparation of these estimates. The unit costs included in the conceptual estimates contain an imbedded 10 percent escalation for mobilization and an additional 5 percent increase for contractor detailing and pricing allowance. Estimates for project-related permitting; professional services (i.e., survey, design, testing, resident inspection); and contingencies are identified at the end of each estimate. Estimates have been rounded to nearest $100. The estimates do not take into consideration any special phasing, working around events or any work stoppage or delays. The estimates do not include any cost for tenant inconvenience or loss of facilities. No night-time construction has been assumed. Based on the recommended phased capital improvement program for North Perry Airport, the various project costs have been identified as eligible or non-eligible for FAA and/or FDOT grant funding as described in further detail in the next chapter (Financial Feasibility). The cost allocation presented from the various agencies does not imply that these funds are guaranteed for these projects. Funding from these sources will be subject to agency funds availability, agency priorities, and agency programs. August 11,

2 In addition, certain assumptions have been made in the determination of potential funding sources, these include the following: Although rehabilitation of airfield pavement, lighting, and marking is eligible for FAA funding, due to FAA funding constraints, the funding source allocation presented in this chapter assumes FAA funding only for the airport s primary runway (Runway 9R-27L) and associated parallel taxiways (Taxiway L & Taxiway M), and one cross-wind runway (Runway 18R-36L) and associated parallel taxiways (Taxiway B and proposed Taxiway A). The other two runways (Runway 9L-27R and Runway 18L-36R) and their associated taxiways have been assumed to not receive FAA funds, but to receive funds primarily from FDOT programs. Similarly, funding sources for upgrading of precision approach path indicators and windsocks have been assumed to be primarily funded by FAA for Runway 9R-27L and Runway 18R-36L with navigational aids for the other two runways being funded primarily by FDOT. Funding sources for security projects such as fencing and access control is anticipated at 100 percent by FDOT sources. Funding sources for roadway improvements and sewer improvements are assumed to be primarily by FDOT. Funding sources for apron rehabilitation is assumed to be primarily from FAA; apron seal coat projects would be primarily funded by FDOT; and new long-term aprons are assumed to be funded by private tenants. FAA funding has been assumed to be 90 percent, with 5 percent by FDOT, and 5 percent local share. Currently, the FAA program provides for funding up to 95 percent of eligible items; however, new FAA Airport Improvement Program legislation is anticipated to reduce the 95 percent funding to 90 percent funding. Funding assumptions can be updated as needed by BCAD based on final programs with FAA and FDOT. BCAD should review the information contained in the conceptual estimate and project detailing prior to inputting the detailed cost estimates into the Joint Automated Capital Improvement Program (JACIP) used by the FAA and FDOT to coordinate funding efforts. Special attention has been placed on the first five years (short-term) of the capital improvement program. These projects have been identified as the most critical to North Perry Airport in terms of correcting substandard facilities and developing facilities to attract new business to the Airport. The conceptual estimate and project detailing for the short-term projects provide information needed for input into the JACIP SHORT-TERM CAPITAL IMPROVEMENT PROJECTS The short-term planning period covers the years 2007 through Improvement projects listed in Table 10.1 for the short-term total $6.6 million over the five year period. The development phasing is presented on Figure August 11,

3 TABLE 10.1 SHORT-TERM CAPITAL IMPROVEMENT PROJECTS Costs are estimated in 2007 dollars August 11,

4 FIGURE 10.1 SHORT-TERM FOR NORTH PERRY AIRPORT Item No. Short Term (0-5 years) Project Description 1 SECURITY FENCING AND GATE UPGRADES 2 RUNWAY 18L-36R PAVEMENT REHABILITATION 3 LANDSCAPING PLAN & LANDSCAPING IMPROVEMENTS - PHASE 1 (South Areas) 4 UPGRADE ARFF VEHICLE (Not Shown) 5 LANDSCAPING IMPROVEMENTS - PHASE 2 (North & West Areas) 6 TAXIWAY 'N' PAVEMENT REHABILITATION 7 LIGHTED WINDSOCKS PROJECT (Not Shown) 8 DEMOLISH MISC. BUILDINGS (Not Shown) 9 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 1 (South Area) 10 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 2 (North & West Areas) 11 NW APRON PAVEMENT OVERLAY 12 SE APRON PAVEMENT OVERLAY 13 SEWER CONNECTION STUDY 14 AIRPORT ROAD REALIGNMENT 15 STORMWATER MANAGEMENT PLAN (Not Shown) 16 ENVIRONMENTAL ASSESSMENT FOR RUNWAY 9R-27L ADDITIONAL PAVEMENT (Not Shown) 17 AIRPORT WAYFINDING SIGN PROJECT (Not Shown) 18 INSTALLATION OF RELOCATED VOR August 11,

5 10.3 MID-TERM CAPITAL IMPROVEMENT PROJECTS The mid-term planning period covers years 2012 through Improvement projects listed in Table 10.2 for the mid-term total $13.3 million over the five year period. The development phasing is presented on Figure TABLE 10.2 MID-TERM CAPITAL IMPROVEMENT PROJECTS, Inc. Costs are estimated in 2007 dollars August 11,

6 FIGURE 10.2 MID-TERM FOR NORTH PERRY AIRPORT Item No. Mid-Term (6-10 years) Project Description 19 TAXIWAY 'P' REHABILITATION 20 RUNWAY 9L-27R REHABILITATION 21 UPDATE LANDSCAPING IMPROVEMENTS & SIGNAGE PLAN (Not Shown) 22 CONSTRUCT ADDITIONAL PAVEMENT TAXIWAY 'A' - PHASE CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 9R END AND EXTEND TAXIWAY 'L' TO NEW TAKEOFF END CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 27L END AND EXTEND TAXIWAYS 'L' TO NEW TAKEOFF END 25 CONSTRUCT TAXIWAY 'M' REHABILITATION 26 REPLACE PAPI's FOR RUNWAY 9R-27L (NOT SHOWN) 27 UPGRADE PAPI'S RUNWAYS 18R-36L (NOT SHOWN) 28 REPLACE PAPI's FOR RUNWAY 9L-27R (NOT SHOWN) 29 UPGRADE PAPI'S RUNWAYS 18L-36R (NOT SHOWN) 30 NW APRON PAVEMENT SEALCOAT 31 SE APRON PAVEMENT SEALCOAT 32 LIGHT TAXIWAYS 'N' 33 LIGHT TAXIWAY 'L' 34 INSTALL REFLECTORS ON UNLIT TAXIWAYS (NOT SHOWN) 36 LANDSCAPING AND SIGNAGE IMPROVEMENTS (NOT SHOWN) 35 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 37 DEMOLISH MISCELLANEOUS BUILDINGS - PHASE 2 (NOT SHOWN) 38 SEWER CONNECTION PROJECT PHASE 1 NORTH SIDE (NOT SHOWN) 39 SEWER CONNECTION PROJECT PHASE 2 SOUTH SIDE (NOT SHOWN) 40 (NOT SHOWN) August 11,

7 10.4 LONG-TERM CAPITAL IMPROVEMENT PROJECTS The long-term planning period covers years 2017 through Improvement projects listed in Table 10.3 for the long-term total $11.3 million over the ten year period. The development phasing is presented on Figure TABLE 10.3 LONG-TERM CAPITAL IMPROVEMENT PROJECTS, Inc. Costs are estimated in 2007 dollars August 11,

8 FIGURE 10.3 LONG-TERM FOR NORTH PERRY AIRPORT Item No. Long-Term (11-20 years) Project Description 41 RUNWAY 9R-27L PAVEMENT REHABILITATION 42 RUNWAY 18R-36L REHABILITATION 43 TAXIWAY 'D' REHABILITATION 44 TAXIWAY 'E' REHABILITATION 45 TAXIWAY 'L' REHABILITATION 46 UPGRADE AIR TRAFFIC CONTROL TOWER/UPS (Not Shown) 47 CONSTRUCT HELIPAD 48 SEAL-COAT NW APRON 49 SEAL-COAT SE APRON 50 LANDSCAPING IMPROVEMENTS 51 OVERLAY AIRPORT ROADWAYS 52 EXTEND AIRPORT PERIMETER ROAD TO SE QUADRANT 53 CONSTRUCT TAXIWAY 'A' - PHASE 2 54 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 55 (NOT SHOWN) 56 UPGRADE ARFF VEHICLE (Not Shown) 57 REPLACE ROTATING BEACON (Not Shown) 58 TAXIWAY 'B' REHABILITATION August 11,

9 10.5 SUMMARY OF CAPITAL IMPROVEMENT PROJECTS Combined, the 20-year CIP for North Perry Airport totals $31.2 million, as summarized in Table The development phasing is presented on Figure TABLE 10.4 SUMMARY OF FOR NORTH PERRY AIRPORT Costs are estimated in 2007 dollars August 11,

10 FIGURE 10.4 COMBINED FOR NORTH PERRY AIRPORT Item No. Short Term (0-5 years) Project Description 1 SECURITY FENCING AND GATE UPGRADES 2 RUNWAY 18L-36R PAVEMENT REHABILITATION 3 LANDSCAPING PLAN & LANDSCAPING IMPROVEMENTS - PHASE 1 (South Areas) 4 UPGRADE ARFF VEHICLE (Not Shown) 5 LANDSCAPING IMPROVEMENTS - PHASE 2 (North & West Areas) 6 TAXIWAY 'N' PAVEMENT REHABILITATION 7 LIGHTED WINDSOCKS PROJECT (Not Shown) 8 DEMOLISH MISC. BUILDINGS (Not Shown) 9 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 1 (South Area) 10 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 2 (North & West Areas) 11 NW APRON PAVEMENT OVERLAY 12 SE APRON PAVEMENT OVERLAY 13 SEWER CONNECTION STUDY 14 AIRPORT ROAD REALIGNMENT 15 STORMWATER MANAGEMENT PLAN (Not Shown) 16 ENVIRONMENTAL ASSESSMENT FOR RUNWAY 9R-27L ADDITIONAL PAVEMENT (Not Shown) 17 AIRPORT WAYFINDING SIGN PROJECT (Not Shown) 18 INSTALLATION OF RELOCATED VOR Item No. Mid-Term (6-10 years) Project Description 19 TAXIWAY 'P' REHABILITATION 20 RUNWAY 9L-27R REHABILITATION 21 UPDATE LANDSCAPING IMPROVEMENTS & SIGNAGE PLAN (Not Shown) 22 CONSTRUCT ADDITIONAL PAVEMENT TAXIWAY 'A' - PHASE 1 23 CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 9R END AND EXTEND TAXIWAY 'L' TO NEW TAKEOFF END 24 CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 27L END AND EXTEND TAXIWAYS 'L' TO NEW TAKEOFF END 25 CONSTRUCT TAXIWAY 'M' REHABILITATION 26 REPLACE PAPI's FOR RUNWAY 9R-27L (NOT SHOWN) 27 UPGRADE PAPI'S RUNWAYS 18R-36L (NOT SHOWN) 28 REPLACE PAPI's FOR RUNWAY 9L-27R (NOT SHOWN) 29 UPGRADE PAPI'S RUNWAYS 18L-36R (NOT SHOWN) 30 NW APRON PAVEMENT SEALCOAT 31 SE APRON PAVEMENT SEALCOAT 32 LIGHT TAXIWAYS 'N' 33 LIGHT TAXIWAY 'L' 34 INSTALL REFLECTORS ON UNLIT TAXIWAYS (NOT SHOWN) 35 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 36 LANDSCAPING AND SIGNAGE IMPROVEMENTS (NOT SHOWN) 37 DEMOLISH MISCELLANEOUS BUILDINGS - PHASE 2 (NOT SHOWN) 38 SEWER CONNECTION PROJECT PHASE 1 NORTH SIDE (NOT SHOWN) 39 SEWER CONNECTION PROJECT PHASE 2 SOUTH SIDE (NOT SHOWN) 40 (NOT SHOWN) Item No. Long-Term (11-20 years) Project Description 41 RUNWAY 9R-27L PAVEMENT REHABILITATION 42 RUNWAY 18R-36L REHABILITATION 43 TAXIWAY 'D' REHABILITATION 44 TAXIWAY 'E' REHABILITATION 45 TAXIWAY 'L' REHABILITATION 46 UPGRADE AIR TRAFFIC CONTROL TOWER/UPS (Not Shown) 47 CONSTRUCT HELIPAD 48 SEAL-COAT NW APRON 49 SEAL-COAT SE APRON 50 LANDSCAPING IMPROVEMENTS 51 OVERLAY AIRPORT ROADWAYS 52 EXTEND AIRPORT PERIMETER ROAD TO SE QUADRANT 53 CONSTRUCT TAXIWAY 'A' - PHASE 2 54 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 55 (NOT SHOWN) 56 UPGRADE ARFF VEHICLE (Not Shown) 57 REPLACE ROTATING BEACON (Not Shown) 58 TAXIWAY 'B' REHABILITATION August 11, 2009 Page 10-10

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM PORT OF PORTLAND Chapter Seven CAPITAL IMPROVEMENT PROGRAM CHAPTER SEVEN PORT OF PORTLAND CAPITAL IMPROVEMENT PROGRAM The analyses conducted in the previous chapters evaluated airport development needs

More information

Punta Gorda Airport Master Plan Update

Punta Gorda Airport Master Plan Update Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,

More information

Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot

Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot community Airport Advisory Board meetings Elected Officials

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington

More information

General Aviation Master Plan Update

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System

More information

Request for Scoping Comments Regarding Environmental Issues of Concern

Request for Scoping Comments Regarding Environmental Issues of Concern March 16, 2009 Request for Scoping Comments Regarding Environmental Issues of Concern Environmental Assessment for Proposed Airport Land Lease and Airport Construction Pahrump Valley General Aviation Airport,

More information

Ted Stevens Anchorage International Airport

Ted Stevens Anchorage International Airport Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the

More information

Passenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico.

Passenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico. Passenger Facility Charge: No. 7 Application December 2013 Public Notice Materials Luis Muñoz Marín International Airport San Juan Puerto Rico INTRODUCTION Aerostar Airport Holdings has initiated the process

More information

Finance and Implementation

Finance and Implementation 5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter

More information

INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE

INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE BRIEFING ON RONALD REAGAN WASHINGTON NATIONAL AND WASHINGTON DULLES INTERNATIONAL AIRPORTS CAPITAL CONSTRUCTION PROGRAM APRIL 2015 2015 Use & Lease

More information

Los Angeles International Airport (LAX) Airside $907M

Los Angeles International Airport (LAX) Airside $907M Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking

More information

3.1 CRITICAL AIRCRAFT

3.1 CRITICAL AIRCRAFT The purpose of the demand capacity analysis is to determine an airport s capacity and its ability to support the forecasted aviation demand. Facility requirements identify development, replacement, and/or

More information

RESOLUTION NO

RESOLUTION NO RESOLUTION NO. 2015-15 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MARINA AUTHORIZING SUBMISSION OF A GRANT APPLICATION TO THE FEDERAL AVIATION ADMINISTRATION (FAA) FOR PARTICIPATION IN THE 2015 MILITARY

More information

North Perry Airport Master Plan

North Perry Airport Master Plan North Perry Airport Master Plan North Perry Master Plan May 30, 2007 TAC Invitees County Representatives Bob Bielek, Interim Director of Aviation, BCAD Nina Demeo, Airport Manager, BCAD Darlene Duecker,

More information

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS P U B L I C N O T I C E MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application 10-07-C-00-MBS INTRODUCTION: This Public Notice is issued as part of a Federal Aviation

More information

Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES

Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES Airport Layout Plan Report In this chapter, existing components of the Airport are evaluated so that the capacities of the overall system are identified.

More information

Fort Lauderdale Hollywood International Airport

Fort Lauderdale Hollywood International Airport ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County

More information

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Pursuant to 14 CFR Part 158.24(a) (1) (III), the Broward County

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary. TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...

More information

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include: 4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity

More information

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013 New York State Department of Transportation Safety, Infrastructure, and Tenant Improvement Project Public Hearing Informational Brochure February 26, 2013 This DEIS/Draft EA evaluates the potential impacts

More information

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four Airport Development Alternatives Prior to formulating a development program for Ryan Airfield, it is important to consider development potential

More information

PUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application

PUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application PUBLIC NOTICE ***************************** New Castle Airport Intention to File a Passenger Facility Charge (PFC) Application The Delaware River & Bay Authority (DRBA), the sponsor of the New Castle Airport

More information

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

PLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016

PLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016 PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016 Meeting Agenda 1. Introductions and Contacts [10 Minutes] 2. Plan Overview and MPAC Role [20 Minutes] 3. MPAC Visioning

More information

RIO VISTA MUNICIPAL AIRPORT

RIO VISTA MUNICIPAL AIRPORT DRAINAGE TECHNICAL MEMORANDUM RIO VISTA MUNICIPAL AIRPORT RIO VISTA, CALIFORNIA Prepared for: City of Rio Vista 1 Main Street Rio Vista, CA 94571 (707) 374-5337 Prepared by: August 2012 Copyright 2012

More information

Aviation Summit Design and Construction Services

Aviation Summit Design and Construction Services Aviation Summit 2017 Design and Construction Services Agenda: Terminal 3 Modernization PHX Sky Train Stage 2 Terminal 4 S1 Concourse & Apron Other Capital Program Projects Terminal 3 Modernization Processor

More information

AIRPORT FUND. Description. Summary

AIRPORT FUND. Description. Summary Description In March 1941 construction started for the airport at its present site. After Pearl Harbor, the airport, known as Pinellas Army Airfield, was used as a military flight-training base. After

More information

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017 INDIANAPOLIS AIRPORT AUTHORITY 2018 APPROPRIATION BUDGET ORDINANCE NO. 1-2017 BOARD APPROVED AUGUST 18, 2017 2018 Appropriation Budget Table of Contents Board Approved August 18, 2017 1 Appropriation Summary

More information

EXECUTIVE SUMMARY. Master Plan Update Phase 2/3 FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT 1. INTRODUCTION 2.

EXECUTIVE SUMMARY. Master Plan Update Phase 2/3 FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT 1. INTRODUCTION 2. MASTER PLAN UPDATE Phase 2/3 Draft Final Summary Report Report Issued 2010 in association with Prepared for Broward County Aviation Department Main Office 555 Airport Blvd., Suite 300 Burlingame, CA 94010

More information

Blue Grass Airport (LEX) serves the needs of a multi-county area that

Blue Grass Airport (LEX) serves the needs of a multi-county area that SUMMARY BACKGROUND This Master Plan Update balances needed airport improvements with the goals of the community and arrived at a consensus on how to best meet future demand without sacrificing those natural

More information

PFC Quarterly Status Report September 30, 2016

PFC Quarterly Status Report September 30, 2016 PFC Quarterly Status Report September 0, 06 Public Agency: Greater Orlando Aviation Authority Use Airport: Orlando International Airport (MCO) Charge Expiration Date: $4.50 8//08 Total Collection Authority

More information

CHAPTER 5 - FACILITY REQUIREMENTS

CHAPTER 5 - FACILITY REQUIREMENTS CHAPTER 5 - FACILITY REQUIREMENTS This chapter identifies the requirements for airfield and landside facilities to accommodate the forecast demand level. Facility requirements have been developed for the

More information

Fort Wayne International Airport Master Plan Study. Executive Summary

Fort Wayne International Airport Master Plan Study. Executive Summary Fort Wayne International Airport Master Plan Study Executive Summary March 2012 Introduction Airport Background Forecast of Aviation Activity Development Plans Recommended Airfield & Access Development

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY STUDY PURPOSE The Airport Master Plan for the Duluth International Airport (DLH) is the Duluth Airport Authority s strategy for future development of the Airport. The master

More information

Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting

Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting 10.27.16 Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting Agenda Welcome / Introductions DFW

More information

Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017 Airport Master Plan Update June 15, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017 Airport Master Plan Update June 15, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

Dallas Love Field Capital Program. September 16, 2015

Dallas Love Field Capital Program. September 16, 2015 Dallas Love Field Capital Program September 16, 2015 1 The Dallas Airport System Dallas Love Field, Dallas Executive Airport, Downtown Vertiport A $86 million City of Dallas enterprise Operated by the

More information

AIRPORT CAPITAL DEVELOPMENT NEEDS

AIRPORT CAPITAL DEVELOPMENT NEEDS AIRPORT CAPITAL DEVELOPMENT NEEDS 2013-2017 January 2013 TABLE OF CONTENTS BACKGROUND... 1 RESULTS IN BRIEF... 2 ACI-NA ESTIMATE OF CAPITAL DEVELOPMENT NEEDS... 4 PROJECT DEVELOPMENT COSTS BY LOCATION

More information

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015 Dallas Love Field Update Dallas City Council Briefing February 18, 2015 Purpose Construction Update Impacts of Wright Amendment Repeal Increase in operations/passengers/ projections Concessions performance

More information

Savannah / Hilton Head International Airport Master Plan Update

Savannah / Hilton Head International Airport Master Plan Update EXECUTIVE SUMMARY Savannah / Hilton Head International Airport Master Plan Update Prepared for: The Savannah Airport Commission Prepared by: URS Corporation In Association With: RS&H and Ruth and Associates,

More information

THE CASE OF A SUCCESSFUL PFC APPLICATION

THE CASE OF A SUCCESSFUL PFC APPLICATION THE CASE OF A SUCCESSFUL PFC APPLICATION 1 Chapter One: Scene of the case study 2 Chapter One: The Scene Spokane, WA Home of the RED TURF at Eastern WA University (and Gonzaga) 3 Chapter One: The Scene

More information

Rio Vista Municipal Airport Potential Alternatives for the Future Ownership, Operation and Maintenance of the Airport

Rio Vista Municipal Airport Potential Alternatives for the Future Ownership, Operation and Maintenance of the Airport Rio Vista Municipal Airport Potential Alternatives for the Future Ownership, Operation and Maintenance of the Airport Prepared for City of Rio Vista Prepared by Aries Consultants Ltd. March 2015 Rio Vista

More information

SAN FRANCISCO INTERNATIONAL AIRPORT

SAN FRANCISCO INTERNATIONAL AIRPORT 1 SAN FRANCISCO INTERNATIONAL AIRPORT Runway Safety Area Program ACI-NA Operations and Technical Affairs Conference April 7, 2011 RSA Status Completed RSA Studies Environmental Assessment ongoing and on

More information

MassDOT Aeronautics Division Capital Improvements Presentation

MassDOT Aeronautics Division Capital Improvements Presentation MassDOT Aeronautics Division Capital Improvements Presentation MassDOT Board Retreat October 27, 2011 Presentation Agenda Capital Improvement Plan (CIP) Overview Airports Capital Improvement Plan (ACIP)

More information

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering Subject: Airport Runway Shortening Options

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering Subject: Airport Runway Shortening Options City Council Report To: From: Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering Subject: Airport Runway Shortening Options City Council Meeting: May 24, 2017 Agenda Item: 8.A

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 1 - Introduction This report describes the development and analysis of concept alternatives that would accommodate

More information

EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE

EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE SECTION I - DEFINITIONS The following words, terms and phrases used in this Exhibit E shall have the

More information

BUSH INTERCONTINENTAL AIRPORT

BUSH INTERCONTINENTAL AIRPORT JULY 2014 BUSH INTERCONTINENTAL AIRPORT Project 500N-Terminal D, Phase III-Gate D9 A380 Conversion Project Manager: Randy Williams Everything is Bigger Terminal D at IAH The saying everything is bigger

More information

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment PUBLIC NOTICE The Dallas Department of Aviation (the Department) intends to file an amendment application to increase the PFC amount of one previously approved project at Dallas Love Field Airport (the

More information

Metropolitan Airports Commission. Lake Elmo Airport (21D)

Metropolitan Airports Commission. Lake Elmo Airport (21D) Metropolitan Airports Commission Lake Elmo Airport (21D) Table of Contents Table of Contents... i List of Tables... v List of Figures... vii Executive Summary... viii ES.1 Report Organization... viii ES.2

More information

MARION COUNTY BOARD OF COUNTY COMMISSIONERS. Marion County Airport Business Plan

MARION COUNTY BOARD OF COUNTY COMMISSIONERS. Marion County Airport Business Plan MARION COUNTY BOARD OF COUNTY COMMISSIONERS Marion County Airport Business Plan Marion County Airport External Website Marion County Airport Business Plan Marion County Airport 15070 SW 111 th Dunnellon,

More information

Airport Advisory Board Meeting Minutes June 26, 2017

Airport Advisory Board Meeting Minutes June 26, 2017 Board Members Present: Robert Spivey John Barber Jr Ronald Stutes James Wynne III Joshua Ebright Board Members Absent: Lindsey Birdsong Kelly Walker Others Attending: Davis Dickson, Airport Manager, COT

More information

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #1 September 24, Peter O. Knight Airport

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #1 September 24, Peter O. Knight Airport Peter O. Knight Airport Public Meeting #1 Peter O. Knight Airport 1 Agenda Welcome and Introductions The Master Plan Update Questions and Comments 2 Hillsborough County Aviation Authority Enabling Legislation

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

Current Airport Roles

Current Airport Roles Chapter Four: Current Airport Roles Introduction Current airport roles are defined differently from national, state, and local perspectives. The Federal Aviation Administration (FAA) has established two

More information

TRANSPORTATION: Airports and Aviation Services

TRANSPORTATION: Airports and Aviation Services TRANSPORTATION: Airports and Aviation Services Profile Our background GIBB is a leading multi-disciplinary engineering consulting firm based in South Africa with 67% Black ownership. The firm has a strong

More information

CHAPTER 5: Landside Facility Requirements and Development Concepts

CHAPTER 5: Landside Facility Requirements and Development Concepts CHAPTER 5: Landside Facility Requirements and Development Concepts Overview Implementation of the preferred intermediate-term (10-year) and long-term (20-year) airside alternatives will have a significant

More information

New PFC Application #13

New PFC Application #13 PUBLIC CONSULTATION New PFC Application #13 Buffalo, NY December 16, 2015 Agenda PFC Program at Notice to Carriers and Consultation Meeting Class of Carrier Not Required to Collect PFC Air Carrier Requirements

More information

Five-Year Capital Plan

Five-Year Capital Plan Five-Year Capital Plan Fiscal Year 2015/16 - Fiscal Year 2019/20 City and County of San Francisco Edwin M. Lee, Mayor Airport Commission Larry Mazzola, President Linda S. Crayton, Vice President Eleanor

More information

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Overview of the FAA s Office of Airports Prepared for: Presented by: 2016 ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Eduardo Angeles Associate Administrator for Airports Date:

More information

Thursday, May 2 nd, 2013 South St. Paul Municipal Airport Meeting Room 4:00 p.m. 5:30 p.m. MEETING NOTES

Thursday, May 2 nd, 2013 South St. Paul Municipal Airport Meeting Room 4:00 p.m. 5:30 p.m. MEETING NOTES SOUTH ST. PAUL MUNICIPAL AIRPORT FLEMING FIELD MASTER PLAN ADVISORY GROUP MEETING #2 Thursday, May 2 nd, 2013 South St. Paul Municipal Airport Meeting Room 4:00 p.m. 5:30 p.m. MEETING NOTES The purpose

More information

Chapter One INVENTORY

Chapter One INVENTORY Chapter One INVENTORY Airport Layout Plan Report The initial step in the preparation of the Airport Layout Plan Report for is the collection of information pertaining to the Airport and the area it serves.

More information

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East

More information

Venice Aviation Society, Inc. (VASI) 1335 Horizon Rd. Venice, Florida

Venice Aviation Society, Inc. (VASI) 1335 Horizon Rd. Venice, Florida Venice Aviation Society, Inc. (VASI) 1335 Horizon Rd. Venice, Florida 34293 www.veniceaviationsociety.com September 24, 2009 Mr. Bart Vernace Assistant Manager FAA Orlando Airport District Office 5950

More information

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration Chapter 4 Page 65 AIRPORT DEMAND CAPACITY The purpose of this Demand/Capacity Analysis is to examine the capability of the Albert Whitted Airport (SPG) to meet the needs of its users. In doing so, this

More information

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) MEETING #4 AGENDA & ACTION ITEMS Date/Time: Location: Monday, March 19, 2018 from 1:30-3:30 p.m. Thun Field Airport

More information

Public Notice July 14, 2017

Public Notice July 14, 2017 Public Notice July 14, 2017 PROPOSED IMPLEMENTATION OF PFC 13 NOTICE TO AIR CARRIERS AND CONSULTATION MEETING Implementation of PFC On June 14, 2017 the Omaha Airport Authority provided written notice

More information

Master Plan Update. Palm Beach County Park Airport. Master Plan Update. Ricondo & Associates, Inc.

Master Plan Update. Palm Beach County Park Airport. Master Plan Update. Ricondo & Associates, Inc. Master Plan Update Palm Beach County Park Airport Master Plan Update Prepared for Palm Beach County Department of Airports TB102006004WPB October 31, 2006 Prepared by In association Ricondo & Associates,

More information

ARIZONA DEPARTMENT OF TRANSPORTATION Aeronautics Division FIVE-YEAR AIRPORT DEVELOPMENT PROGRAM FY

ARIZONA DEPARTMENT OF TRANSPORTATION Aeronautics Division FIVE-YEAR AIRPORT DEVELOPMENT PROGRAM FY ARIZONA DEPARTMENT OF TRANSPORTATION Aeronautics Division FIVE-YEAR AIRPORT DEVELOPMENT PROGRAM FY 2005 2009 Kearny Airport Airport of the Year-2003 Arizona Department of Transportation Aeronautics Division

More information

TXDOT AVIATION DIVISION

TXDOT AVIATION DIVISION TXDOT AVIATION DIVISION Airport Project Development & Selection Process Today s Topics Project Development Process Working with TxDOT Aviation Division Funding Sources National Plan of Integrated Airports

More information

FY Five Year Airport Capital Plan Supplemental Project List As of 12/12/16

FY Five Year Airport Capital Plan Supplemental Project List As of 12/12/16 Cost Center Project Name REVIEW Tax Status 5-Year Total Supplemental CAC047 - Airfield 10507 Advanced Visual Docking Guidance System (A-VDGS) NOT APPLICABLE AMT 7,000,000 3,993,664 Project has existing

More information

Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017

Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017 Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY Agenda (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR

More information

Appendix B PAVEMENT CONDITION AND HISTORY

Appendix B PAVEMENT CONDITION AND HISTORY Appendix B PAVEMENT CONDITION AND HISTORY The Sunport maintains a pavement management program (PMP) in order monitor the condition of pavements and to plan for repair/replacement in a timely manner. The

More information

CHAPTER 2 INVENTORY EXISTING CONDITIONS 2.1 AIRFIELD FACILITIES Airspace

CHAPTER 2 INVENTORY EXISTING CONDITIONS 2.1 AIRFIELD FACILITIES Airspace OF EXISTING CONDITIONS The inventory phase of the planning process provides an overview of the various facilities located at Cecil Field (VQQ). A variety of information sources were utilized in compiling

More information

Appendix D Airfield Ongoing Projects Alternatives

Appendix D Airfield Ongoing Projects Alternatives Appendix D Appendix D D.1 Introduction The set of alternatives for each of the airfield facilities was compared with respect to each other and the existing condition. 1 The screening and evaluation process

More information

8.0 AIRPORT LAYOUT PLANS

8.0 AIRPORT LAYOUT PLANS 8.0 AIRPORT LAYOUT PLANS This chapter presents a detailed graphic and narrative description of the selected development concept for General Mitchell International Airport (MKE). The plans package presented

More information

CHAPTER 2.0 ALTERNATIVES

CHAPTER 2.0 ALTERNATIVES CHAPTER 2.0 ALTERNATIVES 2.1 INTRODUCTION 2.1.1 SCOPE OF THE ALTERNATIVES ANALYSIS This chapter summarizes the screening analysis conducted to identify the range of reasonable and practicable alternatives

More information

AVIATION AND SPACEPORT OFFICE DISTRICT 3 REPORT J UNE 2015 STATEWIDE. Airfield. Pavement Management

AVIATION AND SPACEPORT OFFICE DISTRICT 3 REPORT J UNE 2015 STATEWIDE. Airfield. Pavement Management F L O R I D A D E PA R T M E N T O F T R A N S P O R T A T I O N AVIATION AND SPACEPORT OFFICE DISTRICT 3 REPORT J UNE 2015 STATEWIDE Airfield Pavement Management P R O G R A M Pavement Evaluation Report

More information

Project Descriptions, Justifications and Other Supporting Information Provided for Notice Inviting Public Comment to PFC Application C-00-VPS

Project Descriptions, Justifications and Other Supporting Information Provided for Notice Inviting Public Comment to PFC Application C-00-VPS NOTICE INVITING PUBLIC COMMENT OKALOOSA COUNTY, FLORIDA NORTHWEST FLORIDA REGIONAL AIRPORT APPLICATION TO IMPOSE AND USE PFCS PFC APPLICATION NO. 14-06-C-00-VPS Pursuant to Section 158.24 of the Passenger

More information

ESTIMATION OF ECONOMIC IMPACTS FOR AIRPORTS IN HAWTHORNE, EUREKA, AND ELY, NEVADA

ESTIMATION OF ECONOMIC IMPACTS FOR AIRPORTS IN HAWTHORNE, EUREKA, AND ELY, NEVADA TECHNICAL REPORT UCED 97/98-14 ESTIMATION OF ECONOMIC IMPACTS FOR AIRPORTS IN HAWTHORNE, EUREKA, AND ELY, NEVADA UNIVERSITY OF NEVADA, RENO ESTIMATION OF ECONOMIC IMPACTS FOR AIRPORTS IN HAWTHORNE, EUREKA

More information

AIRPORT DEVELOPMENT ALTERNATIVES

AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four AIRPORT DEVELOPMENT ALTERNATIVES Prior to defining the development program for Telluride Regional Airport, it is important to consider development potential and constraints at the airport.

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

Chapter 1 EXECUTIVE SUMMARY

Chapter 1 EXECUTIVE SUMMARY Chapter 1 EXECUTIVE SUMMARY Contents Page Aviation Growth Scenarios................................................ 3 Airport Capacity Alternatives.............................................. 4 Air Traffic

More information

THE PURPOSE OF THIS BUSINESS PLAN FOR Lee s Summit Municipal Airport is to assess potential

THE PURPOSE OF THIS BUSINESS PLAN FOR Lee s Summit Municipal Airport is to assess potential Business Plan June, 2008 1. INTRODUCTION DRAFT TECHNICAL REPORT Lee s Summit Municipal Airport Business Plan THE PURPOSE OF THIS BUSINESS PLAN FOR Lee s Summit Municipal Airport is to assess potential

More information

Session 6 Airport Finance 101 Funding Sources for Airports

Session 6 Airport Finance 101 Funding Sources for Airports Session 6 Airport Finance 101 Funding Sources for Airports 31 st Annual AAAE Basics of Airport Law Workshop and 2015 Legal Update November 1-3, 2015 Desk Reference Chapters 2, 19, 22 Frank J. San Martin

More information

Runway Length Analysis Prescott Municipal Airport

Runway Length Analysis Prescott Municipal Airport APPENDIX 2 Runway Length Analysis Prescott Municipal Airport May 11, 2009 Version 2 (draft) Table of Contents Introduction... 1-1 Section 1 Purpose & Need... 1-2 Section 2 Design Standards...1-3 Section

More information

COUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fee for FY18 October 1, 2017 through September 30, 2018

COUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fee for FY18 October 1, 2017 through September 30, 2018 COUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fee for FY18 October 1, 2017 through September 30, 2018 GROUND & FACILITY LEASE RATES Ground Lease Rate Bare ground for development Per Individual

More information

Regional Jets ,360 A319/ , , , ,780

Regional Jets ,360 A319/ , , , ,780 Excel Tab Name: Seats (18 MAP) PASSENGER AIRLINE FLIGHT SCHEDULE CALCULATION RECORD Summary 17.2 MAP flight schedule* (with Southwest Airlines B737-800s changed to B737-700s) Number of Total Seats Avg.

More information

Airfield Design OVERVIEW BASIC DESIGN FACTORS. Airport Role

Airfield Design OVERVIEW BASIC DESIGN FACTORS. Airport Role 3 Airfield Design OVERVIEW Due to the presence of significant physical constraints, little change to the existing airfield is anticipated. The emphasis in this plan is on identifying airfield improvements

More information

Appendix D August 2001 RUNWAY SAFETY Revised March 2002 AREA DETERMINATION RUNWAY 17-35

Appendix D August 2001 RUNWAY SAFETY Revised March 2002 AREA DETERMINATION RUNWAY 17-35 Appendix D August 2001 RUNWAY SAFETY Revised March 2002 AREA DETERMINATION Master Plan Update RUNWAY 17-35 Hector International Airport SUFFICIENCY ANALYSIS Near the completion of the Master Plan Update

More information

Metropolitan Airports Commission. Flying Cloud Airport (FCM)

Metropolitan Airports Commission. Flying Cloud Airport (FCM) Metropolitan Airports Commission Flying Cloud Airport (FCM) Flying Cloud Airport Long Term Comprehensive Plan Update FINAL October 2010 Metropolitan Council Determination April 2010 Final Adoption by MAC

More information