10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM

Size: px
Start display at page:

Download "10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM"

Transcription

1 10.1 INTRODUCTION Based on the findings from the Facility Requirements and the combined plan recommended in the Alternative Analysis, a capital improvement program for North Perry Airport has been developed and is presented in this chapter. Capital improvements that are anticipated to be primarily developed and funded by the private sector (i.e., T-hangars, maintenance hangars, aprons, and other related private development initiatives) have not been included in the Airport s capital improvement program. The recommended capital improvements are listed and depicted by planning horizon, namely: Short-term ( ); Mid-term ( ); and Long-term ( ). Projects have been placed in their respective planning horizons based on existing conditions, prioritization of issues, and typical facility rehabilitation needs. Projects may be expedited or delayed based on needs identified by Broward County Aviation Department (BCAD), and funding availability. Conceptual cost estimates for each of the development projects listed in the capital improvement program have been developed in 2007 dollars. Appendix H provides the conceptual estimate and project detailing for each phase of the proposed capital improvement program for North Perry Airport. The following comments are provided regarding the conceptual cost estimates: The conceptual estimates have been prepared for the purpose of providing cost feedback at an early stage in the project planning and programming process. The cost information will enable BCAD to modify the scope of work as needed to arrive at a design and scope that both satisfies the BCAD s needs and is within the budget. Asphalt prices are very volatile; costs for P-401 bituminous surface have been estimated to be $86.00 per ton in these estimates. The price of asphalt should be reviewed as appropriate to update any changes in pricing, which may present budget impacts. The estimates are based on conceptual assumptions contained in the project detailing. Only minimal data has been used to prepare these estimates. It is expected that the cost estimates will require additional refinement, adjustments in scope, price, and escalation prior to implementation. No design has been accomplished for the preparation of these estimates. The unit costs included in the conceptual estimates contain an imbedded 10 percent escalation for mobilization and an additional 5 percent increase for contractor detailing and pricing allowance. Estimates for project-related permitting; professional services (i.e., survey, design, testing, resident inspection); and contingencies are identified at the end of each estimate. Estimates have been rounded to nearest $100. The estimates do not take into consideration any special phasing, working around events or any work stoppage or delays. The estimates do not include any cost for tenant inconvenience or loss of facilities. No night-time construction has been assumed. Based on the recommended phased capital improvement program for North Perry Airport, the various project costs have been identified as eligible or non-eligible for FAA and/or FDOT grant funding as described in further detail in the next chapter (Financial Feasibility). The cost allocation presented from the various agencies does not imply that these funds are guaranteed for these projects. Funding from these sources will be subject to agency funds availability, agency priorities, and agency programs. August 11,

2 In addition, certain assumptions have been made in the determination of potential funding sources, these include the following: Although rehabilitation of airfield pavement, lighting, and marking is eligible for FAA funding, due to FAA funding constraints, the funding source allocation presented in this chapter assumes FAA funding only for the airport s primary runway (Runway 9R-27L) and associated parallel taxiways (Taxiway L & Taxiway M), and one cross-wind runway (Runway 18R-36L) and associated parallel taxiways (Taxiway B and proposed Taxiway A). The other two runways (Runway 9L-27R and Runway 18L-36R) and their associated taxiways have been assumed to not receive FAA funds, but to receive funds primarily from FDOT programs. Similarly, funding sources for upgrading of precision approach path indicators and windsocks have been assumed to be primarily funded by FAA for Runway 9R-27L and Runway 18R-36L with navigational aids for the other two runways being funded primarily by FDOT. Funding sources for security projects such as fencing and access control is anticipated at 100 percent by FDOT sources. Funding sources for roadway improvements and sewer improvements are assumed to be primarily by FDOT. Funding sources for apron rehabilitation is assumed to be primarily from FAA; apron seal coat projects would be primarily funded by FDOT; and new long-term aprons are assumed to be funded by private tenants. FAA funding has been assumed to be 90 percent, with 5 percent by FDOT, and 5 percent local share. Currently, the FAA program provides for funding up to 95 percent of eligible items; however, new FAA Airport Improvement Program legislation is anticipated to reduce the 95 percent funding to 90 percent funding. Funding assumptions can be updated as needed by BCAD based on final programs with FAA and FDOT. BCAD should review the information contained in the conceptual estimate and project detailing prior to inputting the detailed cost estimates into the Joint Automated Capital Improvement Program (JACIP) used by the FAA and FDOT to coordinate funding efforts. Special attention has been placed on the first five years (short-term) of the capital improvement program. These projects have been identified as the most critical to North Perry Airport in terms of correcting substandard facilities and developing facilities to attract new business to the Airport. The conceptual estimate and project detailing for the short-term projects provide information needed for input into the JACIP SHORT-TERM CAPITAL IMPROVEMENT PROJECTS The short-term planning period covers the years 2007 through Improvement projects listed in Table 10.1 for the short-term total $6.6 million over the five year period. The development phasing is presented on Figure August 11,

3 TABLE 10.1 SHORT-TERM CAPITAL IMPROVEMENT PROJECTS Costs are estimated in 2007 dollars August 11,

4 FIGURE 10.1 SHORT-TERM FOR NORTH PERRY AIRPORT Item No. Short Term (0-5 years) Project Description 1 SECURITY FENCING AND GATE UPGRADES 2 RUNWAY 18L-36R PAVEMENT REHABILITATION 3 LANDSCAPING PLAN & LANDSCAPING IMPROVEMENTS - PHASE 1 (South Areas) 4 UPGRADE ARFF VEHICLE (Not Shown) 5 LANDSCAPING IMPROVEMENTS - PHASE 2 (North & West Areas) 6 TAXIWAY 'N' PAVEMENT REHABILITATION 7 LIGHTED WINDSOCKS PROJECT (Not Shown) 8 DEMOLISH MISC. BUILDINGS (Not Shown) 9 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 1 (South Area) 10 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 2 (North & West Areas) 11 NW APRON PAVEMENT OVERLAY 12 SE APRON PAVEMENT OVERLAY 13 SEWER CONNECTION STUDY 14 AIRPORT ROAD REALIGNMENT 15 STORMWATER MANAGEMENT PLAN (Not Shown) 16 ENVIRONMENTAL ASSESSMENT FOR RUNWAY 9R-27L ADDITIONAL PAVEMENT (Not Shown) 17 AIRPORT WAYFINDING SIGN PROJECT (Not Shown) 18 INSTALLATION OF RELOCATED VOR August 11,

5 10.3 MID-TERM CAPITAL IMPROVEMENT PROJECTS The mid-term planning period covers years 2012 through Improvement projects listed in Table 10.2 for the mid-term total $13.3 million over the five year period. The development phasing is presented on Figure TABLE 10.2 MID-TERM CAPITAL IMPROVEMENT PROJECTS, Inc. Costs are estimated in 2007 dollars August 11,

6 FIGURE 10.2 MID-TERM FOR NORTH PERRY AIRPORT Item No. Mid-Term (6-10 years) Project Description 19 TAXIWAY 'P' REHABILITATION 20 RUNWAY 9L-27R REHABILITATION 21 UPDATE LANDSCAPING IMPROVEMENTS & SIGNAGE PLAN (Not Shown) 22 CONSTRUCT ADDITIONAL PAVEMENT TAXIWAY 'A' - PHASE CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 9R END AND EXTEND TAXIWAY 'L' TO NEW TAKEOFF END CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 27L END AND EXTEND TAXIWAYS 'L' TO NEW TAKEOFF END 25 CONSTRUCT TAXIWAY 'M' REHABILITATION 26 REPLACE PAPI's FOR RUNWAY 9R-27L (NOT SHOWN) 27 UPGRADE PAPI'S RUNWAYS 18R-36L (NOT SHOWN) 28 REPLACE PAPI's FOR RUNWAY 9L-27R (NOT SHOWN) 29 UPGRADE PAPI'S RUNWAYS 18L-36R (NOT SHOWN) 30 NW APRON PAVEMENT SEALCOAT 31 SE APRON PAVEMENT SEALCOAT 32 LIGHT TAXIWAYS 'N' 33 LIGHT TAXIWAY 'L' 34 INSTALL REFLECTORS ON UNLIT TAXIWAYS (NOT SHOWN) 36 LANDSCAPING AND SIGNAGE IMPROVEMENTS (NOT SHOWN) 35 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 37 DEMOLISH MISCELLANEOUS BUILDINGS - PHASE 2 (NOT SHOWN) 38 SEWER CONNECTION PROJECT PHASE 1 NORTH SIDE (NOT SHOWN) 39 SEWER CONNECTION PROJECT PHASE 2 SOUTH SIDE (NOT SHOWN) 40 (NOT SHOWN) August 11,

7 10.4 LONG-TERM CAPITAL IMPROVEMENT PROJECTS The long-term planning period covers years 2017 through Improvement projects listed in Table 10.3 for the long-term total $11.3 million over the ten year period. The development phasing is presented on Figure TABLE 10.3 LONG-TERM CAPITAL IMPROVEMENT PROJECTS, Inc. Costs are estimated in 2007 dollars August 11,

8 FIGURE 10.3 LONG-TERM FOR NORTH PERRY AIRPORT Item No. Long-Term (11-20 years) Project Description 41 RUNWAY 9R-27L PAVEMENT REHABILITATION 42 RUNWAY 18R-36L REHABILITATION 43 TAXIWAY 'D' REHABILITATION 44 TAXIWAY 'E' REHABILITATION 45 TAXIWAY 'L' REHABILITATION 46 UPGRADE AIR TRAFFIC CONTROL TOWER/UPS (Not Shown) 47 CONSTRUCT HELIPAD 48 SEAL-COAT NW APRON 49 SEAL-COAT SE APRON 50 LANDSCAPING IMPROVEMENTS 51 OVERLAY AIRPORT ROADWAYS 52 EXTEND AIRPORT PERIMETER ROAD TO SE QUADRANT 53 CONSTRUCT TAXIWAY 'A' - PHASE 2 54 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 55 (NOT SHOWN) 56 UPGRADE ARFF VEHICLE (Not Shown) 57 REPLACE ROTATING BEACON (Not Shown) 58 TAXIWAY 'B' REHABILITATION August 11,

9 10.5 SUMMARY OF CAPITAL IMPROVEMENT PROJECTS Combined, the 20-year CIP for North Perry Airport totals $31.2 million, as summarized in Table The development phasing is presented on Figure TABLE 10.4 SUMMARY OF FOR NORTH PERRY AIRPORT Costs are estimated in 2007 dollars August 11,

10 FIGURE 10.4 COMBINED FOR NORTH PERRY AIRPORT Item No. Short Term (0-5 years) Project Description 1 SECURITY FENCING AND GATE UPGRADES 2 RUNWAY 18L-36R PAVEMENT REHABILITATION 3 LANDSCAPING PLAN & LANDSCAPING IMPROVEMENTS - PHASE 1 (South Areas) 4 UPGRADE ARFF VEHICLE (Not Shown) 5 LANDSCAPING IMPROVEMENTS - PHASE 2 (North & West Areas) 6 TAXIWAY 'N' PAVEMENT REHABILITATION 7 LIGHTED WINDSOCKS PROJECT (Not Shown) 8 DEMOLISH MISC. BUILDINGS (Not Shown) 9 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 1 (South Area) 10 PERIMETER ROAD SECURITY LIGHTING PROJECT PHASE 2 (North & West Areas) 11 NW APRON PAVEMENT OVERLAY 12 SE APRON PAVEMENT OVERLAY 13 SEWER CONNECTION STUDY 14 AIRPORT ROAD REALIGNMENT 15 STORMWATER MANAGEMENT PLAN (Not Shown) 16 ENVIRONMENTAL ASSESSMENT FOR RUNWAY 9R-27L ADDITIONAL PAVEMENT (Not Shown) 17 AIRPORT WAYFINDING SIGN PROJECT (Not Shown) 18 INSTALLATION OF RELOCATED VOR Item No. Mid-Term (6-10 years) Project Description 19 TAXIWAY 'P' REHABILITATION 20 RUNWAY 9L-27R REHABILITATION 21 UPDATE LANDSCAPING IMPROVEMENTS & SIGNAGE PLAN (Not Shown) 22 CONSTRUCT ADDITIONAL PAVEMENT TAXIWAY 'A' - PHASE 1 23 CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 9R END AND EXTEND TAXIWAY 'L' TO NEW TAKEOFF END 24 CONSTRUCT ADDITIONAL PAVEMENT AT RUNWAY 27L END AND EXTEND TAXIWAYS 'L' TO NEW TAKEOFF END 25 CONSTRUCT TAXIWAY 'M' REHABILITATION 26 REPLACE PAPI's FOR RUNWAY 9R-27L (NOT SHOWN) 27 UPGRADE PAPI'S RUNWAYS 18R-36L (NOT SHOWN) 28 REPLACE PAPI's FOR RUNWAY 9L-27R (NOT SHOWN) 29 UPGRADE PAPI'S RUNWAYS 18L-36R (NOT SHOWN) 30 NW APRON PAVEMENT SEALCOAT 31 SE APRON PAVEMENT SEALCOAT 32 LIGHT TAXIWAYS 'N' 33 LIGHT TAXIWAY 'L' 34 INSTALL REFLECTORS ON UNLIT TAXIWAYS (NOT SHOWN) 35 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 36 LANDSCAPING AND SIGNAGE IMPROVEMENTS (NOT SHOWN) 37 DEMOLISH MISCELLANEOUS BUILDINGS - PHASE 2 (NOT SHOWN) 38 SEWER CONNECTION PROJECT PHASE 1 NORTH SIDE (NOT SHOWN) 39 SEWER CONNECTION PROJECT PHASE 2 SOUTH SIDE (NOT SHOWN) 40 (NOT SHOWN) Item No. Long-Term (11-20 years) Project Description 41 RUNWAY 9R-27L PAVEMENT REHABILITATION 42 RUNWAY 18R-36L REHABILITATION 43 TAXIWAY 'D' REHABILITATION 44 TAXIWAY 'E' REHABILITATION 45 TAXIWAY 'L' REHABILITATION 46 UPGRADE AIR TRAFFIC CONTROL TOWER/UPS (Not Shown) 47 CONSTRUCT HELIPAD 48 SEAL-COAT NW APRON 49 SEAL-COAT SE APRON 50 LANDSCAPING IMPROVEMENTS 51 OVERLAY AIRPORT ROADWAYS 52 EXTEND AIRPORT PERIMETER ROAD TO SE QUADRANT 53 CONSTRUCT TAXIWAY 'A' - PHASE 2 54 UPGRADE SECURITY FENCING & ACCESS CONTROL GATES 55 (NOT SHOWN) 56 UPGRADE ARFF VEHICLE (Not Shown) 57 REPLACE ROTATING BEACON (Not Shown) 58 TAXIWAY 'B' REHABILITATION August 11, 2009 Page 10-10

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction

More information

Collier County Airport Authority. Joint Automated Capital Improvement Program

Collier County Airport Authority. Joint Automated Capital Improvement Program Collier County Airport Authority Joint Automated Capital Improvement Program Joint Automated Capital Improvement Program (JACIP) What is the JACIP? Financial planning process supported by Web-based computer

More information

Chapter 9 Airport Financial Plan

Chapter 9 Airport Financial Plan Chapter 9 Airport Financial Plan Introduction The purpose of this chapter is to present the projects identified in the twenty-year Airport Capital Improvement Program (ACIP) that have been developed and

More information

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM

PORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM PORT OF PORTLAND Chapter Seven CAPITAL IMPROVEMENT PROGRAM CHAPTER SEVEN PORT OF PORTLAND CAPITAL IMPROVEMENT PROGRAM The analyses conducted in the previous chapters evaluated airport development needs

More information

Chapter 8.0 Implementation Plan

Chapter 8.0 Implementation Plan Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.

More information

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP) 6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement

More information

Punta Gorda Airport Master Plan Update

Punta Gorda Airport Master Plan Update Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information

JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007

JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007 JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 27 11242 1 of 14 Sponsor: City of Naples Airport Authority NPIAS No.: 12-53 Sponsor ID: 122 Airport ID: APF Site No.: 3379.*A 11242 Airport Project ID: 1

More information

DALLAS LOVE FIELD MAY 2015 DRAFT

DALLAS LOVE FIELD MAY 2015 DRAFT 8. Funding Plan This section presents a potential funding plan for implementing the CIP projects recommended in the Master Plan Update, along with an assessment of the ability of the Airport sponsor (i.e.,

More information

Financial Plan/Capital Improvements - DRAFT 6-1

Financial Plan/Capital Improvements - DRAFT 6-1 The analyses completed in previous chapters evaluated development needs at McKinney National Airport (TKI or Airport) over the next 20 years, based on forecast activity, facility requirements, safety standards,

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Project Team Kittitas County, WA Airport Owner (Sponsor) and Operator, Land Use Century West

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP) 2018 Airport Master Plan Overview of Development Concepts Greg Ballentine (WSP) Thank You Stakeholder and community consultation has included discussions with over 40 stakeholder groups including airport

More information

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot

Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot community Airport Advisory Board meetings Elected Officials

More information

Grants Pass Airport Master Plan & Airport Layout Plan Update

Grants Pass Airport Master Plan & Airport Layout Plan Update Attendees: Grants Pass Airport Master Plan & Airport Layout Plan Update Meeting #3 January 26, 2010 Merlin Community Center 100 Acorn Street, Merlin 5:45 7:15 p.m. Josephine County Department of Airports:

More information

Ted Stevens Anchorage International Airport

Ted Stevens Anchorage International Airport Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the

More information

Ted Stevens Anchorage International Airport

Ted Stevens Anchorage International Airport Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the

More information

General Aviation Master Plan Update

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

RECONSTRUCT/REHABILITATE TRANSIENT APRON AND TAXIWAY 'A' PHASING PLAN - PHASE 1

RECONSTRUCT/REHABILITATE TRANSIENT APRON AND TAXIWAY 'A' PHASING PLAN - PHASE 1 PHASING PLAN - PHASE 1 2 Weeks PHASE 1 SCOPE OF WORK Phase 1 consists of the reconstruction of a portion of Taxiway 'A' and the crack seal and seal coat of the North Apron. The portion of Taxiway 'A' to

More information

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

Chapter 4.0 Alternatives Analysis

Chapter 4.0 Alternatives Analysis Chapter 4.0 Alternatives Analysis Chapter 1 accumulated the baseline of existing airport data, Chapter 2 presented the outlook for the future in terms of operational activity, Chapter 3 defined the facilities

More information

CHAPTER 1 BACKGROUND AND PROPOSED ACTION

CHAPTER 1 BACKGROUND AND PROPOSED ACTION CHAPTER 1 BACKGROUND AND PROPOSED ACTION 1.0 INTRODUCTION An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance

More information

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor June 11, :30 a.m.

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor June 11, :30 a.m. AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting May 14, 2014 Approval of Minutes: Special

More information

RESOLUTION NO

RESOLUTION NO RESOLUTION NO. 2015-15 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MARINA AUTHORIZING SUBMISSION OF A GRANT APPLICATION TO THE FEDERAL AVIATION ADMINISTRATION (FAA) FOR PARTICIPATION IN THE 2015 MILITARY

More information

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update

Chapter Seven Implementation Plan. Tacoma Narrows Airport. Master Plan Update Chapter Seven Implementation Plan Master Plan Update This chapter presents the 20-year improvement program for the continued development of the. The objectives of this chapter are to identify projects

More information

Yakima Air Terminal/McAllister Field Airport Master Plan Update

Yakima Air Terminal/McAllister Field Airport Master Plan Update Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used

More information

6.0 DEVELOPMENT PLAN/FINANCIAL OVERVIEW

6.0 DEVELOPMENT PLAN/FINANCIAL OVERVIEW 6.0 DEVELOPMENT PLAN/FINANCIAL OVERVIEW A goal of this Airport Master Plan was to review the requirements and alternatives necessary for the to meet their identified current and future demand. With this

More information

Financial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority

Financial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority Financial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority September 12, 2017 Contents 1. Funding Sources for Airport Projects 2. Financial Metrics 3. CIP Summary and Funding

More information

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35 Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements

More information

Passenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico.

Passenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico. Passenger Facility Charge: No. 7 Application December 2013 Public Notice Materials Luis Muñoz Marín International Airport San Juan Puerto Rico INTRODUCTION Aerostar Airport Holdings has initiated the process

More information

Request for Scoping Comments Regarding Environmental Issues of Concern

Request for Scoping Comments Regarding Environmental Issues of Concern March 16, 2009 Request for Scoping Comments Regarding Environmental Issues of Concern Environmental Assessment for Proposed Airport Land Lease and Airport Construction Pahrump Valley General Aviation Airport,

More information

6.1 INTRODUCTION 6.2 AIRSIDE ALTERNATIVES NORTH PERRY AIRPORT MASTER PLAN UPDATE RUNWAY LENGTH REQUIREMENTS SECTION 6: ALTERNATIVES ANALYSIS

6.1 INTRODUCTION 6.2 AIRSIDE ALTERNATIVES NORTH PERRY AIRPORT MASTER PLAN UPDATE RUNWAY LENGTH REQUIREMENTS SECTION 6: ALTERNATIVES ANALYSIS 6.1 INTRODUCTION In the previous chapter, facility needs for the 20-year planning horizon were identified. The next step in the planning process is to identify and evaluate the various ways certain facilities

More information

EXECUTIVE SUMMARY INTRODUCTION EXISTING CONDITIONS CECIL FIELD MASTER PLAN UPDATE

EXECUTIVE SUMMARY INTRODUCTION EXISTING CONDITIONS CECIL FIELD MASTER PLAN UPDATE ES-1 INTRODUCTION Cecil Field opened as a military airfield to train and serve as a home base for U.S. Navy and Army aviators during World War II. It continued in a military role until 1999 when it was

More information

Los Angeles International Airport (LAX) Airside $907M

Los Angeles International Airport (LAX) Airside $907M Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking

More information

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include: 4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity

More information

City of Tallahassee, FL Department of Aviation

City of Tallahassee, FL Department of Aviation City of Tallahassee, FL Department of Aviation Proposed Application to Federal Aviation Administration For Authority to Impose a Passenger Facility Charge (PFC) at Tallahassee International Airport and

More information

MOST aircraft need a runway for landing and takeout.

MOST aircraft need a runway for landing and takeout. 38th Annual Concrete Paving Workshop Upcoming Airport Projects January 17, 2017 MOST aircraft need a runway for landing and takeout. 1 Airport Improvement Program AIP Eligibility The federal AIP grants

More information

CHAPTER FOUR AIRPORT ALTERNATIVES

CHAPTER FOUR AIRPORT ALTERNATIVES 4.0 INTRODUCTION CHAPTER FOUR The goal of the master planning process is to provide the City of New Smyrna Beach with an assessment of the adequacy and capabilities of the Airport as well as to identify

More information

Finance and Implementation

Finance and Implementation 5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter

More information

Aviation Trust Fund. The Results of Senate Bill 526

Aviation Trust Fund. The Results of Senate Bill 526 Aviation Trust Fund The Results of Senate Bill 526 Nevada Aviation Trust Fund Page 2 Inside: Background Funding Opportunities and Issues Senate Bill 526 2005 Aviation Trust Fund Results Airport Projects

More information

3.1 CRITICAL AIRCRAFT

3.1 CRITICAL AIRCRAFT The purpose of the demand capacity analysis is to determine an airport s capacity and its ability to support the forecasted aviation demand. Facility requirements identify development, replacement, and/or

More information

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business Plan Steering Committee December 14, 2006 Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business

More information

Trick or Treat Process M

Trick or Treat Process M AIP Design Lessons Trick or Treat Halloween Sharing October 25, 2017 By: FAA DMA ADO staff Dave P. Anderson Brian P. Schuck Mark J. Holzer 1 Trick or Treat Process M FAA staff of Dave, Brian and Mark shall

More information

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally

More information

Aviation Planning in Maine and Our Region. Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011

Aviation Planning in Maine and Our Region. Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011 Aviation Planning in Maine and Our Region Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011 Overview The National Aviation System Maine s Economic Dependence

More information

Introduction DRAFT March 9, 2017

Introduction DRAFT March 9, 2017 Chapter Overview The City of Redmond (City) initiated an update to the Airport Master Plan ( Plan ) to assess the facility and service needs of the Redmond Municipal Airport ( the Airport ) throughout

More information

PENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN

PENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN PENSACOLA INTERNATIONAL AIRPORT MASTER PLAN UPDATE WORKING PAPER 8 FINANCIAL PLAN OCTOBER 2018 T A B L E O F C O N T E N T S Table of Contents Chapter 8 Financial Plan 8.1 Introduction... 8-1 8.2 Enplanement

More information

6.4 Aviation AVIATION FACILITIES AND SERVICES

6.4 Aviation AVIATION FACILITIES AND SERVICES 2035 Transportation Plan 6.4 Aviation This chapter describes existing aviation facilities and services in Placer County and projected needs. This chapter also discusses potential aviation issues related

More information

JOHNSTON COUNTY AIRPORT AUTHORITY

JOHNSTON COUNTY AIRPORT AUTHORITY JOHNSTON COUNTY AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS FOR AIRPORT PLANNING SERVICES For JOHNSTON REGIONAL AIRPORT (JNX) 3149 Swift Creek Rd. Smithfield, NC 27577 PHIL LANIER AIRPORT DIRECTOR (919)

More information

STUDY WORK GROUP MEETING No. 3. November 29, 2016

STUDY WORK GROUP MEETING No. 3. November 29, 2016 STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity

More information

Aviation Department Board Workshop. December 7, 2010

Aviation Department Board Workshop. December 7, 2010 Aviation Department Board Workshop December 7, 2010 1 Agenda North Perry Airport (HWO) FLL Economic Impact & Traffic Update Terminal Area Forecast FLL Airport Layout Plan & Master Plan Update Runway 9R/27L

More information

INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE

INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE BRIEFING ON RONALD REAGAN WASHINGTON NATIONAL AND WASHINGTON DULLES INTERNATIONAL AIRPORTS CAPITAL CONSTRUCTION PROGRAM APRIL 2015 2015 Use & Lease

More information

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN LAST UPDATE JULY 2013 Acknowledgements The preparation of this document was financed in part by a grant from the Federal Aviation Administration (Project No: 3-27-0000-07-10), with the financial support

More information

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS P U B L I C N O T I C E MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application 10-07-C-00-MBS INTRODUCTION: This Public Notice is issued as part of a Federal Aviation

More information

Beginning balance available for Priority I Projects: $1,737,029

Beginning balance available for Priority I Projects: $1,737,029 2016 COAR Grant Cycle Priority I Projects Airport Name Project Name Requested Grant Amount Match % of Grant Match Total Project Cost or Total FAA Grant Match Amount required RUNNING TOTAL (Available Balance)

More information

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering

City Council Report. Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering City Council Report To: From: Mayor and City Council Susan Cline, Director, Public Works, Civil Engineering City Council Meeting: February 28, 2017 Agenda Item: 3.H Subject: Award of Feasibility/Design-Build

More information

North Perry Airport Master Plan

North Perry Airport Master Plan North Perry Airport Master Plan North Perry Master Plan May 30, 2007 TAC Invitees County Representatives Bob Bielek, Interim Director of Aviation, BCAD Nina Demeo, Airport Manager, BCAD Darlene Duecker,

More information

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES 5.1 INTRODUCTION This section investigates Airfield Development Alternatives, generalized Land Use Alternatives, and more detailed General Aviation Alternatives.

More information

Agenda: SASP SAC Meeting 3

Agenda: SASP SAC Meeting 3 Agenda: SASP SAC Meeting 3 Date: 04/12/18 Public Involvement Plan Update Defining the System Recommended Classifications Discussion Break Review current system Outreach what we heard Proposed changes Classification

More information

BOARD OF AIRPORT COMMISSIONERS

BOARD OF AIRPORT COMMISSIONERS 1 8/17/2018 8/21/2018 8/16/2018 i ElY MY Y I : JH MT BY...01,, III1*.ji,"1.111Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: la Approved by: e1. "ampbell, Chief Airports

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

MELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of March 23, :30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM

MELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of March 23, :30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM MELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of March 23, 2011 8:30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM Pledge of Allegiance ACTION ITEMS APPROVAL OF MINUTES of the Regular Meeting of

More information

SACRAMENTO COUNTY AIRPORT SYSTEM - OVERALL EXECUTIVE SUMMARY

SACRAMENTO COUNTY AIRPORT SYSTEM - OVERALL EXECUTIVE SUMMARY SACRAMENTO COUNTY AIRPORT SYSTEM - OVERALL EXECUTIVE SUMMARY Executive Summary The Sacramento County Airport System Capital Improvement Plan (CIP) is comprised of projects that were identified and evaluated

More information

MASTER PLAN CONCEPT 1 DRAFT

MASTER PLAN CONCEPT 1 DRAFT The Airport Master Plan Update for Dallas Executive Airport has included the development of aviation demand forecasts, an assessment of future facility needs, and the evaluation of airport development

More information

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013 New York State Department of Transportation Safety, Infrastructure, and Tenant Improvement Project Public Hearing Informational Brochure February 26, 2013 This DEIS/Draft EA evaluates the potential impacts

More information

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary. TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...

More information

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Pursuant to 14 CFR Part 158.24(a) (1) (III), the Broward County

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES

Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES Airport Layout Plan Report In this chapter, existing components of the Airport are evaluated so that the capacities of the overall system are identified.

More information

Salt Lake City International Airport April 23, 2013 Budget Briefing. Page 1

Salt Lake City International Airport April 23, 2013 Budget Briefing. Page 1 Budget Briefing Fiscal Year 2014 Budget Honorable Members of the City Council April 23, 2013 Page 1 FY 2014 Budget Goals and Objectives Develop and implement a plan of execution for the terminal redevelopment

More information

Chapter 5 Airport Development Alternatives

Chapter 5 Airport Development Alternatives Chapter 5 Airport Development Alternatives Introduction CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-1 Evaluation Process No-Action Alternative CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-2

More information

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February

More information

Fort Lauderdale Hollywood International Airport

Fort Lauderdale Hollywood International Airport ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County

More information

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four Airport Development Alternatives Prior to formulating a development program for Ryan Airfield, it is important to consider development potential

More information

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION 1.1.3 Taxiways EWN has an extensive network of taxiways and taxilanes connecting the terminal, air cargo, and general aviation areas with the runways as listed in Figure 1-15. A 50-foot wide parallel taxiway

More information

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Project Team Century West Engineering Northwest firm founded in 1969 500+ airport projects completed throughout the Pacific

More information

Chapter 9: Financial Plan Draft

Chapter 9: Financial Plan Draft Chapter 9: Draft TABLE OF CONTENTS 9... 5 9.2.1 ABIA Accounting... 6 9.2.2 Legal Environment... 6 9.2.3 Governing Documents... 8 9.3.1 FAA AIP Grants... 13 9.3.2 Local ABIA Funds... 14 9.4.1 Defer or Delay

More information

Airport Master Plan Open House Front Range Airport February 23, 2017

Airport Master Plan Open House Front Range Airport February 23, 2017 Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future

More information

2017 Appropriation Budget Table of Contents Board Approved August 19, 2016

2017 Appropriation Budget Table of Contents Board Approved August 19, 2016 INDIANAPOLIS AIRPORT AUTHORITY 2017 APPROPRIATION BUDGET ORDINANCE NO. 2-2016 BOARD APPROVED AUGUST 19, 2016 2017 Appropriation Budget Table of Contents Board Approved August 19, 2016 1 Appropriation Summary

More information

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on

More information

Port of Friday Harbor

Port of Friday Harbor REQUEST FOR STATEMENTS OF QUALIFICATIONS (RFQ) TO PROVIDE ENGINEERING / CONSULTANT SERVICES AT FRIDAY HARBOR AIRPORT Dated: February 15, 2018 Pursuant to RCW, Chapter 39.80 and FAA AC 150/5100-14E, the

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

ACTION TRANSMITTAL

ACTION TRANSMITTAL Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED

More information

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906 Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement

More information

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017

2018 Appropriation Budget Table of Contents Board Approved August 18, 2017 INDIANAPOLIS AIRPORT AUTHORITY 2018 APPROPRIATION BUDGET ORDINANCE NO. 1-2017 BOARD APPROVED AUGUST 18, 2017 2018 Appropriation Budget Table of Contents Board Approved August 18, 2017 1 Appropriation Summary

More information

CHAPTER 7 IMPLEMENTATION PLAN

CHAPTER 7 IMPLEMENTATION PLAN CHAPTER 7 IMPLEMENTATION PLAN INTRODUCTION An implementation plan for Blue Grass Airport (LEX) has been prepared based upon the facility needs identified in the Facility Requirements and the Alternatives

More information

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. Connecting People Building Opportunities 198 Brisbane Airport Corporation CHAPTER 10

More information