STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

Size: px
Start display at page:

Download "STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D"

Transcription

1 STAFF REPORT SUBJECT: Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan MEETING DATE: AGENDA ITEM: 7D STAFF CONTACT: Peter Imhof, Andrew Orfila RECOMMENDATION: Adopt findings for the Santa Barbara Airport Master Plan (Attachment 1) and determine that the Master Plan and EIR are consistent with the Airport Land Use Plan for Santa Barbara. SUMMARY The draft Santa Barbara Airport Master Plan provides guidance for the Santa Barbara Airport s overall development for the next 20 years (2012 through 2032) and plans for how the Airport will meet forecast airport operations. While the draft Master Plan does envision certain major improvements on airport property (including extension of Taxiway H, consolidation of general aviation operations on the northeast portion of the airfield, and construction of a new Long Term Parking Lot south of the Airline Terminal and expansion of the Airline Terminal), these improvements would not result in changes to aircraft operations that would create off-airport impacts or affect factors relevant to the consistency determination. The Master Plan is not proposing any new or modified facilities or aircraft operating procedures that would result in modified aircraft traffic patterns or other changes in where or how high aircraft typically fly when approaching, departing, or flying near the airport. The draft Master Plan and associated Environmental Impact Report would therefore not materially affect runway layout, flight patterns, or noise contours and would not cause airport activity or aviation forecasts to exceed projections in the adopted Santa Barbara County 1993 Airport Land Use Plan (ALUP). By law, SBCAG, as the designated Airport Land Use Commission (ALUC) for Santa Barbara County, is required to evaluate the draft Santa Barbara Airport Master Plan for consistency with the criteria in the adopted ALUP within 60 days from the complete submittal. The 60-day ALUP review period ends on Monday, January 4, If the Board fails to act on a consistency determination within 60 days, then the project is automatically deemed consistent. An update of Santa Barbara County s 1993 ALUP is presently in process and staff anticipates completion of the update in the next year. When complete, the updated Airport Land Use

2 Compatibility Plan would incorporate and reflect the updated projections and assumptions of the Santa Barbara Airport Master Plan. DISCUSSION Introduction City of Santa Barbara Airport staff referred the draft Airport Master Plan and Environmental Impact Report to SBCAG on September 18, 2015 (see Attachments 2, 3, and 4) and submitted additional required information on October 8, SBCAG has 60 days from the completed submittal to review the project and make a determination of consistency with the adopted Airport Land Use Plan (ALUP). The 60-day ALUP review period ends on Monday, January 4, In making its consistency determination, the Board must evaluate the proposed Airport Master Plan for consistency with the criteria in the adopted Santa Barbara County ALUP. If the Board fails to act on a consistency determination within 60 days, then the project is deemed consistent. State law requires SBCAG, as the designated Airport Land Use Commission (ALUC), to develop and implement an airport land use plan for each general purpose airport. The purpose of the law is to prevent the creation of new noise and safety problems, and to protect public health, safety, and welfare by ensuring the orderly expansion of airports, and the adoption of land use measures that minimize the public s exposure to excessive noise and safety hazards State Aeronautics Act, Public Utilities Code 21670(a). As described in the ALUP, aircraft overflight exposes individuals in the community to potential hazards associated with aircraft accidents and noise impacts. Santa Barbara Airport Master Plan Background The Santa Barbara Airport is located in the City of Santa Barbara, approximately seven miles west of the City center. The City of Goleta borders the Airport property to the north and west. The University of California at Santa Barbara (UCSB) and the community of Isla Vista in unincorporated Santa Barbara County lie immediately south-southwest of the Airport. The Pacific Ocean lies directly south of the Airport. Attachment 5 provides an aerial photograph of the Airport and surrounding area. The Airport is owned and operated by the City of Santa Barbara. Primary regional access to the Airport is via Route 217, Hollister Avenue and Fairview Avenue. The Airport encompasses over 946 acres of land including approximately 350 acres of salt marsh (the Goleta Slough), 500 acres aviation-related and 100 acres non-aviation commercial and industrial land uses. The Airport has three runways in a cross configuration. The primary runway (7-25) is in an east-west direction with a length of 6,052 feet and a width of 150 feet. Two shorter parallel crosswind runways (15L/33R and 15R/33L) are in a north-south direction. Runway 15L/33R is 3,952 feet long and 75 feet wide and Runway 15R/33L is 4,183 feet long and 100 feet wide. The parallel crosswind runways are predominately used by general aviation aircraft. A system of fourteen taxiways provides access to the primary use areas. 2

3 Project Description The proposed Master Plan provides guidance for the Airport s overall development for the next 20 years (2012 through 2032). No actual development projects are proposed at this time (the Draft EIR prepared for the Master Plan is programmatic). Any future development subsequent to approval of the Master Plan would be fully addressed under both the National Environmental Policy Act (NEPA) of 1969 and the California Environmental Quality Act (CEQA) and State of California (State) CEQA Guidelines. The Master Plan lays out a development concept in order to accommodate the growth forecast in the airfield, landside, and terminal areas at the airport. The Master Plan relies on Federal Aviation Administration (FAA)-approved forecasts (approval date: November 13, 2012) of aviation activity at the Airport and provides development scenarios for the short term (2017), intermediate term (2022) and long term (2032). If the growth assumptions made in the Master Plan are not fully realized, the Airport would adjust the phasing of the recommended improvements to meet the actual demand at the Airport. Attachment 6 illustrates the recommended Master Plan development concept. The major improvements recommended in the Master Plan to accommodate the forecast growth include the following: Airfield Recommendations: Extension of Taxiway H to the west, parallel to the main instrument runway, restriping of existing paved areas, paving light lanes along taxiway edges, and relocating entrances and exits from the taxiway system to comply with Federal Aviation Administration (FAA) recommendations. North Landside Recommendations: Consolidation of general aviation operations to facilitate two Fixed-Base Operator lease areas on the northeast portion of the airfield to provide tenant and visiting private aircraft services and facilities, and support facility changes including the relocation of the Airport Maintenance Yard. Terminal Area Recommendations: Construction of a new Long Term Parking Lot south of the Airline Terminal to accommodate 1,315 new or relocated parking spaces, expansion of the Airline Terminal, and relocation of the south side Fixed-Base Operator. Factors in the Consistency Evaluation of Airport Master Plan Components The review of an Airport Master Plan focuses on differences between the proposed Master Plan being reviewed and the Master Plan that was utilized to develop the planning assumptions within the adopted Airport Land Use Plan (in this case, the 1993 Santa Barbara County Airport Land Use Plan). According to the California Airport Land Use Planning Handbook: Fundamentally, the question to be examined is whether any components of the airport plan would result in greater noise and safety impacts on surrounding land uses than are assumed in the adopted Airport Land Use Compatibility Plan. This concept implies that the airport plan does not have to be identical with the Airport Land Use Compatibility Plan as long as the impacts are not increased or moved to previously less-impacted areas. 1 1 California Airport Land Use Planning Handbook, pp & 16, Caltrans Division of Aeronautices, October

4 The consistency evaluation of the Santa Barbara Airport Master Plan with the Airport Land Use Plan focuses on components that are associated with aircraft operations and have off-airport impact implications. The following section discusses each of these criteria. Activity Forecasts Comparison: Are the activity forecasts substantially higher than those in the Airport Land Use Compatibility Plan or do they include a higher proportion of larger or noisier aircraft, including helicopters? Activity forecasts for the Master Plan are compared with those in the adopted Airport Land Use Plan. It should be acknowledged that the adopted ALUP is over twenty years old, so the forecasts contained within the adopted ALUP are outdated. Therefore, when the prior Airport Master Plan (the Aviation Facilities Plan) was brought to the ALUC for a consistency review, the ALUC accepted the airport activity and forecasts for planning purposes moving forward. The Aviation Facilities Plan forecasts will be compared to the proposed Master Plan forecasts. Runway Layout: Are any new runways or helicopter takeoff and landing areas proposed? Are changes in runway length, landing threshold locations, or type of approach procedures planned? If so, what effect do any of these changes have on height limits placed on nearby property for the purposes of airspace protection? Flight Tracks: Will new or modified facilities or aircraft operating procedures result in different aircraft traffic patterns or other changes in where or how high aircraft typically fly when approaching, departing, or flying near the airport? Noise Impacts: Will changes in any of the above items result in significantly increased noise impacts on surrounding lands? Consistency Evaluation Airport Activity and Aviation Forecasts The Santa Barbara County Airport Land Use Plan was adopted in 1993 and was developed utilizing forecasts contained within the Santa Barbara Airport s 1990 Airport Master Plan and 1986 Part 150 Airport Noise Study. The 1990 Airport Master Plan contained forecasts of airport operations out to years 1995, 2000, and Therefore, a straightforward comparison of the forecasts in the Santa Barbara County Airport Land Use Plan with those contained in the proposed Santa Barbara Airport Master Plan is not feasible due to the outdated forecasts contained in the 1993 County Airport Land Use Plan. In March 2002, the SBCAG Board (acting as the County Airport Land Use Commission) reviewed the Santa Barbara Airport Aviation Facilities Plan and accepted the airport activity and forecasts contained within that document and subsequently directed staff to initiate an Airport Land Use Plan update. Table 1 compares the Aviation Facilities Plan forecast with the draft Airport Master Plan forecast. 4

5 Table 1 Forecast Comparison: Aviation Facilities Plan with the Draft Airport Master Plan 1999 (Baseline) Aviation Facilities Plan (Baseline) Airport Master Plan Enplanements 399, , , , , , , ,000 Operations (Total) 168, , , , , , , ,150 Air Carrier/ Commuter 44,900 40,000 46,000 53,000 26,180 27,540 28,400 31,800 GA/Military 123, , , ,000 82,100 85,450 91, ,350 Based Aircraft Figure 1 illustrates the enplanement forecast comparison in greater detail. Figure 1 Enplanement Forecast Comparison: Aviation Facilities Plan with the Draft Airport Master Plan AFP = Aviation Facilities Plan Table 1 and Figure 1 show that the proposed Santa Barbara Airport Master Plan activity and aviation forecast will not exceed those accepted by the Airport Land Use Commission for the prior Plan (the Aviation Facilities Plan in March 2002). For example, the horizon year in the Aviation Facilities Plan was 2015, for which the AFP forecast 750,000 enplanements. The proposed Santa Barbara Airport Master Plan, for the short-term year 2017 forecast, foresees 440,000 enplanements. It should be noted that the activity and aviation forecast contained in the proposed Santa Barbara Airport Master Plan was reviewed and approved by the Federal Aviation Administration on November 13, Santa Barbara Airport Master Plan, Ch. 2, pg

6 Since the aviation and activity forecast in the proposed Airport Master Plan would not exceed those previously accepted by the Airport Land Use Commission (the forecast contained in the Aviation Facilities Plan), staff recommends the Board accept the new airport activity and forecasts for Santa Barbara Airport in the proposed Airport Master Plan. Subsequently, the Santa Barbara Airport Master Plan aviation and activity forecast will be incorporated into the pending Santa Barbara County Airport Land Use Compatibility Plan update. Staff anticipates completion of the Airport Land Use Compatibility Plan update in the next year. Runway Layout The proposed Master Plan development concept is shown on Attachment 5. As discussed in the project description, the Master Plan is a 20-year forecast of demand on the airfield, landside, and terminal areas and includes a capacity analysis to assess how the airport can accommodate the forecast demand. The proposed Master Plan concluded that forecast growth in enplanements and operations did not warrant additional runway capacity or helicopter takeoff and landing areas. The Master Plan notes that Runway 15L currently has a 217-foot displaced threshold. This displacement was applied due to a building obstructing the approach surface north of Hollister Avenue. The building causing the obstruction was recently demolished. Therefore, the Runway 15L threshold could be relocated to the north edge of runway pavement if approved by the FAA. As a result, the full length of Runway 15L-33R would be usable for landing operations. 3 The Master Plan shows a proposed avigation easement over this parcel. The avigation easement would (generally) allow for the right of flight in the airspace above the property, allow the generation of noise and other impacts associated with aircraft overflight, restrict the height of structures, trees and other objects, permit access to the property for the removal or aeronautical marking of objects exceeding the established height limit and prohibit electrical interference, glare, and other potential hazards to flight from being created on the property. The adopted 1993 Airport Land Use Plan was prepared prior to the completion of the Santa Barbara Airport s Runway Safety Area extension on Runway 7-25, which shifted the runway approximately 800 feet to the west. When the Aviation Facilities Plan was brought to ALUC staff for a consistency determination, staff recommended updated Clear Zone and Approach Zone boundaries for Runway The ALUC accepted the staff recommendation and determined the Aviation Facilities Plan, including the runway extension, to be consistent with the adopted 1993 ALUP in March The current Runway 7-25 configuration will be included in the pending Airport Land Use Compatibility Plan update. Given no new runways or helicopter takeoff and landing areas and the City s proposed avigation easement north of Runway 15L, staff recommends that the ALUC determine that the runway layout in the proposed Airport Master Plan is consistent with that contained in the Airport Land Use Plan. Aircraft Traffic Pattern Runway 7-25 is the primary runway for all air carrier and computer aircraft operations. Most general aviation operations use the parallel crosswind runways (15L/33R and 15R/33L) with departures toward the ocean (south) and arrivals from the north. Prevailing winds at the Airport are from the west and the majority of operations at Santa Barbara Airport are conducted on 3 Santa Barbara Airport Master Plan, pg

7 Runway Approximately 60 percent of all air carrier and general aviation turbojet aircraft arrive to and depart from Runway 25. The remaining approximate 40 percent arrive and depart to Runway 7. More than a third of GA prop aircraft use Runway 15L for arrivals and departures. The remaining GA prop aircraft arrivals and departures are distributed among the Airport s other runways with approximately 28 percent using Runway 25 for arrivals and departures, 29 percent using Runway 15R for arrivals and departures, and one percent using Runways 33R/L for arrivals and departures. The existing flight tracks, as depicted in the proposed Master Plan environmental document, are illustrated on Attachment 7. The Master Plan is not proposing any new or modified facilities or aircraft operating procedures that would result in modified aircraft traffic patterns or other changes in where or how high aircraft typically fly when approaching, departing, or flying near the airport. Therefore, staff recommends that the ALUC find that the aircraft traffic pattern and operational procedures contained in the proposed Master Plan and environmental document are similar to those contained in the current Airport Land Use Plan (Attachment 8). Airport Noise Contours As it is the largest commercial service airport in the county, the area surrounding the Santa Barbara Airport is subject to the highest noise levels generated by aircraft operations when compared with other airports around the County. In order to achieve noise compatibility for its existing operations and to foster an on-going dialogue with the surrounding community, the Santa Barbara Airport considers public input through its Noise Abatement Committee and implements measures through its Noise Abatement Program: The Draft Santa Barbara Airport Master Plan EIR contains an Initial Study that includes a noise analysis. The analysis incorporates the Master Plan s anticipated future growth at the Airport and noise contours associated with the Airport have been modeled using the FAA s most recently approved noise model, INM Version 7.0d, for the future years 2017 and The 2032 noise contour for the Santa Barbara Airport, as shown in the Santa Barbara Airport Master Plan Initial Study, is illustrated on Attachment 9. SBCAG s adopted Airport Land Use Plan includes noise contours based on a 1986 study. As part of the FAA comprehensive planning program, the Airport prepared the Federal Aviation Regulations (FAR) Part 150 Noise Compatibility Study in September The 1986 Study incorporated recommendations for land use development criteria within the CNEL 65 and the CNEL noise contours for Santa Barbara Airport. The noise contours depicted in the Santa Barbara County Airport Land Use Plan are shown on Attachment 10. In 2004, the Santa Barbara Airport completed an updated Part 150 Noise Compatibility Study. ALUC staff has been utilizing the updated Part 150 study for consistency reviews within the Airport Influence Area. The updated Part 150 Study utilized the aviation and activity forecasts contained in the Aviation Facilities Plan, but included an extended forecast out to the year Attachment 11 illustrates the the year 2025 noise contour as depicted in the Part 150 noise study. Based on staff s review of the Draft EIR and Initial Study, the noise contours presented in the Initial Study represent the most accurate prediction of the future noise contours within the Airport Influence Area. These contours are significantly smaller than the noise contours in the 7

8 adopted Airport Land Use Plan. However, as noted in the section above, the activity forecasts contained in the adopted Airport Land Use Plan are outdated. The noise contour for the proposed Master Plan (year 2032) was overlaid with the noise contour for the Part 150 study (year 2025) to determine if there were would be any major noise increases associated with the Master Plan (Attachment 12). As shown, there would be some very minor increases to the west of the airport, and some minor decreases east of the airport. Given these minor changes and the lower activity forecasts, as shown in Table 1, staff recommends that the ALUC determine that the proposed Airport Master Plan will not generate noise impacts to surrounding land uses over and above those foreseen in the adopted Airport Land Use Plan and that the ALUC determine the noise contours contained in the EIR/Initial Study to be consistent with the ALUP. CONCLUSION The proposed Santa Barbara Airport Master Plan and the Draft Environmental Impact Report will assure Santa Barbara Airport remains ready to meet future air traffic demands and continues to make a vital contribution to the Santa Barbara region s economy. Staff recommends that the Board adopt findings (Attachment 1) and determine that the Master Plan and EIR are consistent with the Airport Land Use Plan for Santa Barbara County and direct staff to incorporate the Airport Master Plan aviation and activity forecast into the countywide Airport Land Use Plan update. ATTACHMENTS 1. Findings of Consistency 2. City of Santa Barbara Letter of Referral 3. Santa Barbara Airport Master Plan (web posting only): 4. Santa Barbara Airport Master Plan Draft Environmental Impact Report (web posting only): 5. Santa Barbara Airport Aerial Photograph 6. Santa Barbara Airport Master Plan Development Concept 7. Santa Barbara Airport Arrival / Departure Flight Tracks: Santa Barbara Airport Master Plan Initial Study 8. Santa Barbara Airport Arrival / Departure Flight Tracks: Santa Barbara County Airport Land Use Plan 9. Santa Barbara Airport Master Plan Intial Study Year 2032 Noise Contours 10. Santa Barbara County Airport Land Use Plan Noise Contours 11. Santa Barbara Airport Part 150 Noise Compatibility Study Year 2025 Noise Contours 12. SBA Part 150 Noise Compatibility Study Noise Contour (Year 2025) Comparison with Proposed Santa Barbara Airport Master Plan Noise Contour (Year 2032) 8

9 ATTACHMENT 1: FINDINGS 1. The proposed Santa Barbara Airport Master Plan provides guidance for the Airport s overall development for the next 20 years (2012 through 2032) and relies on Federal Aviation Administration (FAA)-approved forecasts (approval date: November 13, 2012) of aviation activity. These forecasts provide the basis for demand-based recommendations on the airfield, north landside, and terminal area. 2. The Airport Land Use Commission has considered the City of Santa Barbara s draft Santa Barbara Airport Master Plan and draft Environmental Impact Report for the proposed Master Plan in making its consistency determination. 3. The Santa Barbara Airport is located in the City of Santa Barbara, approximately seven miles west of the City center. The City of Goleta borders the Airport property to the north and west. The University of California Santa Barbara (UCSB) and the community of Isla Vista in unincorporated Santa Barbara County, lie immediately south-southwest of the Airport. The Pacific Ocean lies directly south of the Airport. The Airport is owned and operated by the City of Santa Barbara. 4. The Santa Barbara County Airport Land Use Plan was adopted in 1993 and was developed utilizing forecasts contained within the Santa Barbara Airport s 1990 Airport Master Plan and 1986 Part 150 Airport Noise Study. The 1990 Airport Master Plan contained forecasts of airport operations out to years 1995, 2000, and Therefore, a straightforward comparison of the forecasts in the Santa Barbara County Airport Land Use Plan with those contained in the draft Santa Barbara Airport Master Plan is not feasible due to the outdated forecasts contained in the County Airport Land Use Plan. 5. In March 2002, the SBCAG Board (acting as the County Airport Land Use Commission) reviewed the Santa Barbara Airport Aviation Facilities Plan and accepted the airport activity and forecasts contained within that document. 6. The horizon year in the Aviation Facilities Plan was 2015, for which the forecast was 750,000 enplanements. The proposed Santa Barbara Airport Master Plan, for the short-term year 2017 forecast, foresees 440,000 enplanements. Therefore, the proposed Santa Barbara Airport Master Plan activity and aviation forecast will not exceed those accepted by the Airport Land Use Commission for the prior Plan. 7. The proposed Master Plan concludes that forecast growth in enplanements and operations does not warrant additional runway capacity or helicopter takeoff and landing areas. Therefore, the proposed Master Plan does not result in changes to runway lengths, landing threshold locations, approach procedures, or nearby property height limits. 8. The Master Plan is not proposing any new or modified facilities or aircraft operating procedures that would result in modified aircraft traffic patterns or other changes in where or how high aircraft typically fly when approaching, departing, or flying near the airport. 9. The noise contours presented in the Santa Barbara Airport Master Plan Initial Study (Year 2032) are significantly smaller than the noise contours shown in the adopted Airport Land Use Plan. These contours are significantly smaller than the noise contours in the adopted Airport Land Use Plan. However, as noted in the section above, the activity forecasts 9

10 contained in the adopted Airport Land Use Plan are outdated. Therefore, these proposed Master Plan noise contours cannot be compared to the adopted Airport Land Use Plan noise contours. 10. A comparison of the noise contour for the proposed Master Plan (year 2032) with the noise contour completed for the Part 150 Noise Compatibility Study (year 2025) shows very minor noise increases to the west of the airport, and some minor noise decreases east of the airport. Given these minor changes and the lower activity forecasts, as shown in Table 1, the Master Plan would not result in significantly higher increased noise levels for surrounding land uses. 11. Because the draft Master Plan and associated Environmental Impact Report would not materially affect runway layout, flight patterns, or noise contours, would not cause airport activity or aviation forecasts to exceed projections in the adopted Santa Barbara County 1993 Airport Land Use Plan, and would not result in changes to aircraft operations that would create off-airport impacts, the Airport Land Use Commission finds that the proposed Santa Barbara Airport Master Plan is consistent with the adopted Santa Barbara County Airport Land Use Plan. 10

11 Attachment 2 Project Referral Letter City of Santa Barbara 11

12 12

13 Attachment 5 Santa Barbara Airport (Aerial Photograph) Source: Santa Barbara County Draft Airport Land Use Compatibility Plan. 13

14 Attachment 6 Recommended Airport Master Plan Development Concept Overview Source: Santa Barbara Airport Master Plan 14

15 Attachment 7A Existing and Future Departure Tracks 15

16 Attachment 7B Existing and Future Arrival Tracks 16

17 Attachment 7C Existing and Future Arrival Helicopter and Touch and Go Tracks 17

18 Attachment 8 - Santa Barbara Airport Arrival / Departure Flight Tracks: Santa Barbara County Airport Land Use Plan 18

19 Attachment 9 Santa Barbara Airport Master Plan: Year 2032 Noise Contours 19

20 Attachment 10 Santa Barbara County Airport Land Use Plan Noise Contours 20

21 Attachment 11 - Santa Barbara Airport Part 150 Noise Compatibility Study Year 2025 Noise Contours 21

22 Attachment 12 SBA Part 150 Noise Compatibility Study Noise Contour (Year 2025) Comparison with Proposed Santa Barbara Airport Master Plan Noise Contour (Year 2032) 22

STAFF REPORT. Airport Land Use Plan Consistency Review: Old Town Village Mixed Use Project City of Goleta. MEETING DATE: June 18, 2015 AGENDA ITEM: 5M

STAFF REPORT. Airport Land Use Plan Consistency Review: Old Town Village Mixed Use Project City of Goleta. MEETING DATE: June 18, 2015 AGENDA ITEM: 5M STAFF REPORT SUBJECT: Airport Land Use Plan Consistency Review: Old Town Village Mixed Use Project City of Goleta MEETING DATE: AGENDA ITEM: 5M STAFF CONTACT: Peter Imhof, Andrew Orfila RECOMMENDATION:

More information

STAFF REPORT. Airport Land Use Consistency Determination Betteravia Plaza. MEETING DATE: January 21, 2016 AGENDA ITEM: 8D

STAFF REPORT. Airport Land Use Consistency Determination Betteravia Plaza. MEETING DATE: January 21, 2016 AGENDA ITEM: 8D STAFF REPORT SUBJECT: Airport Land Use Consistency Determination Betteravia Plaza MEETING DATE: AGENDA ITEM: 8D STAFF CONTACT: Andrew Orfila RECOMMENDATION: Adopt findings for the Betteravia Plaza project

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

at: Accessed May 4, 2011.

at:   Accessed May 4, 2011. 3.11 SAFETY 3.11.1 Background and Methodology As with other forms of transportation, there is risk associated with aviation activities. This section focuses on risk to those on the ground near airports.

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport

More information

APPENDIX K LAND USE. Charles M. Schulz - Sonoma County Airport Draft Environmental Impact Report July 2011 K-1

APPENDIX K LAND USE. Charles M. Schulz - Sonoma County Airport Draft Environmental Impact Report July 2011 K-1 APPENDIX K LAND USE Charles M. Schulz - Sonoma County Airport Draft Environmental Impact Report July 2011 K-1 Appendix K Land Use THIS PAGE INTENTIONALLY LEFT BLANK Charles M. Schulz - Sonoma County Airport

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the

More information

ACTION TRANSMITTAL

ACTION TRANSMITTAL Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

Comparison Between Old and New ALUC Plans

Comparison Between Old and New ALUC Plans A P P E N I X H Comparison Between Old and New ALUC Plans OVERVIEW This Placer County Airport Land Use Compatibility Plan (ALUCP) sets forth land use compatibility criteria for the environs of Auburn Municipal,

More information

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the

More information

Finance and Implementation

Finance and Implementation 5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter

More information

Background Data: Blue Canyon Airport and Environs

Background Data: Blue Canyon Airport and Environs 5 Background Data: and Environs INTRODUCTION serves as an important emergency landing field amid mountainous terrain. The airport has existed on the site since the 1930s or 40s. The facility was operated

More information

Appendix C AIRPORT LAYOUT PLANS

Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development

More information

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item.

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item. Committee Report Business Item No. 2017-191 Transportation Committee For the Metropolitan Council meeting of September 13, 2017 Subject: Final Crystal Airport 2035 Long Term Comprehensive Plan (LTCP) Proposed

More information

Notice of Extended Comment Period for an Intent to Adopt a Negative Declaration

Notice of Extended Comment Period for an Intent to Adopt a Negative Declaration County of Santa Clara Department of Planning and Development Planning Office County Government Center, East Wing, 7 th Floor 70 West Hedding Street San Jose, California 95110-1705 (408) 299-5770 FAX (408)

More information

Airport Background Data and Assumptions Report New Cuyama Airport. Santa Barbara County Airport Land Use Compatibility Plan Update

Airport Background Data and Assumptions Report New Cuyama Airport. Santa Barbara County Airport Land Use Compatibility Plan Update Airport Background Data and Assumptions Report Santa Barbara County Airport Land Use Compatibility Plan Update June 25, 212 Updated August 17, 217 Airport Background Data and Assumptions Report 1. Introduction

More information

CHAPTER 6 NOISE EXPOSURE

CHAPTER 6 NOISE EXPOSURE CHAPTER 6 NOISE EXPOSURE FAA requires that the NEM submitted for review represent the aircraft noise exposure for the year of submittal (in this case 2008) and for a future year (2013 for OSUA). However,

More information

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

APPENDIX H 2022 BASELINE NOISE EXPOSURE CONTOUR

APPENDIX H 2022 BASELINE NOISE EXPOSURE CONTOUR APPENDIX H 2022 BASELINE NOISE EXPOSURE CONTOUR This appendix sets forth the detailed input data that was used to prepare noise exposure contours for 2022 Baseline conditions. H.1 DATA SOURCES AND ASSUMPTIONS

More information

Lake Tahoe Airport Master Plan

Lake Tahoe Airport Master Plan Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development

More information

Existing Conditions AIRPORT PROFILE Passenger Terminal Complex 57 air carrier gates 11,500 structured parking stalls Airfield Operations Area 9,000 North Runway 9L-27R 6,905 Crosswind Runway 13-31 5,276

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

Flying Cloud Airport Joint Airport Zoning Board. 27 February 2018 Public Hearing #1 Overview of Proposed Airport Zoning Ordinance

Flying Cloud Airport Joint Airport Zoning Board. 27 February 2018 Public Hearing #1 Overview of Proposed Airport Zoning Ordinance Flying Cloud Airport Joint Airport Zoning Board 27 February 2018 Public Hearing #1 Overview of Proposed Airport Zoning Ordinance Presentation Agenda Purpose & Goals Review of FCM Zoning Historical Timeline

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

Chapter 1 Introduction and Project Overview

Chapter 1 Introduction and Project Overview Chapter 1 Introduction and Project Overview Kittitas County in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Bowers Field Airport (FAA airport identifier

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

Planning, Development and Environment Committee

Planning, Development and Environment Committee Page 1 of 7 MEMORANDUM TO: Planning, Development and Environment Committee FROM: Neil Ralston, Airport Planner Airport Development (726-8129) SUBJECT: 2035 MSP LONG TERM COMPREHENSIVE PLAN FORECAST, FACILITY

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land

More information

Forecast of Aviation Activity

Forecast of Aviation Activity DETROIT METROPOLITAN WAYNE COUNTY AIRPORT FAR PART 150 NOISE COMPATIBILITY STUDY UPDATE CHAPTER B FORECAST OF AVIATION ACTIVITY Forecast of Aviation Activity Introduction This chapter summarizes past aviation

More information

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update

Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update Ultimate ASV, Runway Use and Flight Tracks 4th Working Group Briefing 8/13/18 Meeting Purpose Discuss Public Workshop input

More information

Draft Palo Alto Airport Master Plan Report County of Santa Clara, California October 2005

Draft Palo Alto Airport Master Plan Report County of Santa Clara, California October 2005 Draft Palo Alto Airport Master Plan Report County of Santa Clara, California October 2005 County of Santa Clara Board of Supervisors Donald F. Gage Blanca Alvarado Peter A. McHugh James T. Beall, Jr. Liz

More information

Preliminary Findings of Proposed Alternative

Preliminary Findings of Proposed Alternative Preliminary Findings of Proposed Alternative The attached drawing provides a schematic layout of the proposed alternative that will be discussed on July 27, 2010. A full report will follow and should be

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS EXECUTIVE SUMMARY ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS PAGE NO. CHAPTER 1-INTRODUCTION... 1-1 1.01 General...1-1 1.02 Purpose and Scope of Study...1-1 1.03 The Planning Process...1-2

More information

Punta Gorda Airport Master Plan Update

Punta Gorda Airport Master Plan Update Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,

More information

Norfolk International Airport

Norfolk International Airport Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 1 - Introduction This report describes the development and analysis of concept alternatives that would accommodate

More information

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration Chapter 4 Page 65 AIRPORT DEMAND CAPACITY The purpose of this Demand/Capacity Analysis is to examine the capability of the Albert Whitted Airport (SPG) to meet the needs of its users. In doing so, this

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35 Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements

More information

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together Bringing g the PUBLIC WORKSHOP Venice Municipal Airport New Opportunities Presented for Venice City Council & Citizens of Venice September 25, 2009 Slide 1 Bringing g the Welcome & Introductions May 12th

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

Sunshine Coast Airport Master Plan September 2007

Sunshine Coast Airport Master Plan September 2007 Sunshine Coast Airport Master Plan September 2007 Contents CONTENTS... I ACKNOWLEDGEMENT... II DISCLAIMER... III 1 EXECUTIVE SUMMARY...IV 1 INTRODUCTION... 1 2 AVIATION DEMAND FORECAST... 5 3 AIRCRAFT

More information

AIR TRANSPORTATION ELEMENT

AIR TRANSPORTATION ELEMENT AIR TRANSPORTATION ELEMENT Sonoma County Permit and Resource Management Department 2550 Ventura Avenue Santa Rosa, CA 95403 Adopted by Resolution No. 08-0808 of the Sonoma County Board of Supervisors September

More information

Memorandum. Federal Aviation Administration. Date: June 19, Richard Doucette, Environmental Protection Specialist. From: To:

Memorandum. Federal Aviation Administration. Date: June 19, Richard Doucette, Environmental Protection Specialist. From: To: Federal Aviation Administration Memorandum Date: June 19, 2008 From: To: Subject: Richard Doucette, Environmental Protection Specialist LaVerne Reid, Airports Division Manager John Donnelly, Regional Counsel

More information

Chapter 4.0 Alternatives Analysis

Chapter 4.0 Alternatives Analysis Chapter 4.0 Alternatives Analysis Chapter 1 accumulated the baseline of existing airport data, Chapter 2 presented the outlook for the future in terms of operational activity, Chapter 3 defined the facilities

More information

Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017 Airport Master Plan Update June 15, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1

HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1 HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1 Feb. 27, 2017 HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Welcome Curtis Robinhold, Port of Portland 1 HILLSBORO

More information

City of Upland, California September 2014 Draft

City of Upland, California September 2014 Draft Cable Airport Land Use Compatibility Plan City of Upland, California September 2014 Draft Cable Airport Land Use Compatibility Plan September 2014 Draft Prepared for City of Upland, California Prepared

More information

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington

Vista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington

More information

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update Chapter Six ALP Drawings Master Plan Update The master planning process for the (Airport) has evolved through efforts in the previous chapters to analyze future aviation demand, establish airside and landside

More information

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business Plan Steering Committee December 14, 2006 Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business

More information

AIRPORT WITH NO RUNWAYS IS A MALL

AIRPORT WITH NO RUNWAYS IS A MALL RUNWAY EXTENSION INITIATIVE AT FT. LAUDERDALE HOLLYWOOD INTERNATIONAL AIRPORT ISMAEL IZZY BONILLA DEPUTY DIRECTOR BROWARD COUNTY AVIATION AUTHORITY AIRPORT WITH NO RUNWAYS IS A MALL Runway Business Case

More information

Master Plan & Noise Compatibility Study Update

Master Plan & Noise Compatibility Study Update Working Document-Subject to Change, March 2010 Master Plan & Noise Compatibility Study Update (14 CFR Part 150) TECHNICAL ADVISORY COMMITTEE March 24, 2010 Working Document-Subject to Change, March 2010

More information

Chapter 1. Introduction. Placer County Airport Land Use Compatibility Plan

Chapter 1. Introduction. Placer County Airport Land Use Compatibility Plan Chapter 1 Introduction Placer County Airport Land Use Compatibility Plan 1 Introduction OVERVIEW This Placer County Airport Land Use Compatibility Plan (ALUCP) contains the individual Compatibility Plan

More information

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.

More information

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013 New York State Department of Transportation Safety, Infrastructure, and Tenant Improvement Project Public Hearing Informational Brochure February 26, 2013 This DEIS/Draft EA evaluates the potential impacts

More information

Master Plan Update Community Advisory Committee Kick-off Meeting

Master Plan Update Community Advisory Committee Kick-off Meeting Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision

More information

FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT DRAFT

FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT DRAFT D.3 RUNWAY LENGTH ANALYSIS Appendix D Purpose and Need THIS PAGE INTENTIONALLY LEFT BLANK Appendix D Purpose and Need APPENDIX D.3 AIRFIELD GEOMETRIC REQUIREMENTS This information provided in this appendix

More information

Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017 Airport Master Plan Update June 15, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015 THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015 Pursuant to the California Department of Transportation

More information

BNA Master Plan Update Community Advisory Committee Meeting No. 5

BNA Master Plan Update Community Advisory Committee Meeting No. 5 A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,

More information

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East

More information

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3 This is the presentation for the third Master Plan Update Working Group Meeting being conducted for the Ted Stevens Anchorage International Airport Master Plan Update. It was given on Thursday March 7

More information

Preferred Alternative Summary

Preferred Alternative Summary Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative

More information

Airport Protection Area

Airport Protection Area APPENDIX H Airport Protection Area The Airport Land Use Commission of Alameda County Hayward, California Resolution 93-01 At a meeting held January 13, 1993 Introduced by Commissioner Maestas Seconded

More information

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i TABLE OF CONTENTS Chapter 1 Overview... 1-1 1.1 Background... 1-1 1.2 Overview of 2015 WASP... 1-1 1.2.1 Aviation System Performance... 1-2 1.3 Prior WSDOT Aviation Planning Studies... 1-3 1.3.1 2009 Long-Term

More information

Background Data: Blue Canyon Airport and Environs

Background Data: Blue Canyon Airport and Environs Chapter 8 Background ata: and Environs Placer County Airport Land Use Compatibility Plan 8 Background ata: and Environs INTROUCTION serves as an important emergency landing field amid mountainous terrain.

More information

NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures

NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures DFW International Airport Sandy Lancaster, Manager Noise Compatibility October 13, 2008 OUTLINE About DFW Airport

More information

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES Over the term of the Master Amendment to the Airline Use and Lease Agreement, the Kansas City Aviation Department

More information

Beale Air Force Base Land Use Compatibility Plan

Beale Air Force Base Land Use Compatibility Plan Beale Air Force Base Land Use Compatibility Plan Airport Land Use Commission for Sacramento, Sutter, Yolo, and Yuba Counties Sacramento Area Council of Governments Yuba County, California September 2010

More information

Buchanan Field. Airport Planning Program. FAR Part 150 Meeting. September 28, Master Plan FAR Part 150 Noise Study Strategic Business Plan

Buchanan Field. Airport Planning Program. FAR Part 150 Meeting. September 28, Master Plan FAR Part 150 Noise Study Strategic Business Plan Airport Planning Program Master Plan FAR Part 150 ise Study Strategic Business Plan FAR Part 150 Meeting September 28, 2006 Agenda Introduction Part 150 Study Working Paper Two Operational Alternatives

More information

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on

More information

Background Data: Lincoln Regional Airport and Environs

Background Data: Lincoln Regional Airport and Environs 6 Background Data: and Environs INTRODUCTION /Karl Harder Field is a former military training airfield built during World War II on a mile-square section of open rangeland some three miles west of central

More information

Las Vegas McCarran International Airport. Capacity Enhancement Plan

Las Vegas McCarran International Airport. Capacity Enhancement Plan Las Vegas McCarran International Airport Capacity Enhancement Plan Las Vegas McCarran International Airport Capacity Enhancement Plan September 1994 Prepared jointly by the U.S. Department of Transportation,

More information

MASTER PLAN CONCEPT 1 DRAFT

MASTER PLAN CONCEPT 1 DRAFT The Airport Master Plan Update for Dallas Executive Airport has included the development of aviation demand forecasts, an assessment of future facility needs, and the evaluation of airport development

More information

Runway Length Analysis Prescott Municipal Airport

Runway Length Analysis Prescott Municipal Airport APPENDIX 2 Runway Length Analysis Prescott Municipal Airport May 11, 2009 Version 2 (draft) Table of Contents Introduction... 1-1 Section 1 Purpose & Need... 1-2 Section 2 Design Standards...1-3 Section

More information

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY FIRST QUARTER 2015

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY FIRST QUARTER 2015 THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY FIRST QUARTER 2015 Pursuant to the California Department of Transportation

More information

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include: 4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity

More information

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 4g ACTION ITEM Date of Meeting February 9, 2016

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 4g ACTION ITEM Date of Meeting February 9, 2016 PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 4g ACTION ITEM Date of Meeting February 9, 2016 DATE: TO: FROM: Michael Ehl, Director, Airport Operations Wayne Grotheer, Director, Aviation Project

More information

AVIATION. MichiganReportCard.com 5

AVIATION. MichiganReportCard.com 5 MichiganReportCard.com 5 GRADE C AVIATION OVERVIEW Michigan s 200+ airports bring $4.3 billion into the economy each year. The state s Tier 1 and Tier 2 airports were evaluated based on six key infrastructure

More information

> Aircraft Noise. Bankstown Airport Master Plan 2004/05 > 96

> Aircraft Noise. Bankstown Airport Master Plan 2004/05 > 96 Bankstown Airport Master Plan 2004/05 > 96 24.1 Why Is Aircraft Noise Modelled? Modelling of the noise impact of aircraft operations has been undertaken as part of this MP. Such modelling is undertaken

More information

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Problem Statement 17-03-09 Recommended Allocation: $500,000 Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Staff Comments This is one of four UAS-themed problem statements

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

Santa Barbara County Airport Land Use Compatibility Plan Update. February 6, 2017

Santa Barbara County Airport Land Use Compatibility Plan Update. February 6, 2017 Santa Barbara County Airport Land Use Compatibility Plan Update February 6, 2017 1 Welcome Santa Maria Public Airport New Cuyama Airport Vandenberg Air Force Base Lompoc Airport Santa Ynez Valley Airport

More information

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2017

THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2017 THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2017 Pursuant to the California Department of Transportation

More information

Butte County. Airport land use. compatibility plan OROVILLE MUNICIPAL, CHICO MUNICIPAL, RANCHAERO AIRPORTS PARADISE AND

Butte County. Airport land use. compatibility plan OROVILLE MUNICIPAL, CHICO MUNICIPAL, RANCHAERO AIRPORTS PARADISE AND CHICO MUNICIPAL, OROVILLE MUNICIPAL, PARADISE AND RANCHAERO AIRPORTS Butte County Airport land use compatibility plan Prepared for the BUTTE COUNTY AIRPORT LAND USE COMMISSION Adopted November 15, 2017

More information

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906 Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement

More information

DRAFT MASTER PLAN UPDATE

DRAFT MASTER PLAN UPDATE DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS

More information

Chapter 1 Introduction and Project Overview

Chapter 1 Introduction and Project Overview EPHRATA MUNICIPAL AIRPORT Chapter 1 Introduction and Project Overview The Port of Ephrata in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Ephrata Municipal

More information

AIRPORT LAND USE COMPATILIBILTY AIRPORT LAND USE COMPATIBILIITY

AIRPORT LAND USE COMPATILIBILTY AIRPORT LAND USE COMPATIBILIITY CHAPTER 7 AIRPORT LAND USE COMPATILIBILTY CHAPTER 7 AIRPORT LAND USE COMPATIBILIITY 7.0 INTRODUCTION On airport aviation related development is typically compatible with aircraft operations. On airport

More information

Public Information Meeting. September 2015

Public Information Meeting. September 2015 W ki P O & T / Working Papers One & Two/ Public Information Meeting September 2015 Agenda Introductions and Opening Comments Project Overview, Process, and Schedule Review Materials from Working Papers

More information

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet

More information

26 October 2017 JAZB Meeting #2. Flying Cloud Airport Joint Airport Zoning Board

26 October 2017 JAZB Meeting #2. Flying Cloud Airport Joint Airport Zoning Board 26 October 2017 JAZB Meeting #2 Flying Cloud Airport Joint Airport Zoning Board Meeting Agenda Approval of Minutes from September 21, 2017 JAZB Meeting Introduction of new JAZB member (Eden Prairie representative)

More information