1 INDEPENDENCE STATE AIRPORT (7S5) Airport Master Plan Update 2018 Planning Advisory Committee PAC Meeting #3 April 11,

2 AGENDA The second PAC workshop will cover the following topics: Recap of Planning Team/PAC Roles and Responsibilities Scenario Exercise Summary Alternative Concepts Group Discussion and Report Out Next Steps Public Comments

3 PAC ROLES AND RESPONSIBILITIES The PAC is an advisory committee to the State, the State has final authority over the Master Plan PAC Members should: Participate 8 meetings over 18 months Provide input Share ideas Express concerns Help disseminate accurate information about the plan to the public

4 CONSULTANT RESPONSIBILITIES Consultant should: Facilitate meetings Keep them on-topic and moving forward Develop meeting materials Listen to public stakeholders Serve as a technical expert Develop narrative reports and documents for review and approval

5 ELEMENTS OF A MASTER PLAN This Airport Master Plan consists of 11 essential elements 1. Public Involvement 2. Project Introduction 3. Issues and Opportunities 4. Existing Conditions 5. Aeronautical Activity Forecast 6. Facility Goals and Requirements 7. Airport Development Alternatives Analysis 8. Recycling and Solid Waste Management Plan 9. Airport Layout Plan Drawing Set 10.Implementation Plan (Capital Improvement Plan) 11.AGIS Survey

6 PROJECT SCHEDULE

7 GA National Trends ( ) Expected to Grow: Turboprop/Turbojet (1.4%/2.3%) Helicopter (1.6%) Experimental Aircraft (1%) Sport Aircraft (4.1%) Aircraft Utilization Expected to Decline: Piston Fixed-wing (-0.8%) Piston Utilization Things to Consider: Class III Med. Reform AVgas Replacement Electric/Hybrid Technologies Growing Sport A/C Market Growing Business A/C Market

8 In 2037 there may be 74 new based aircraft 40% more operations About 40 turbine aircraft operations per month About 200 OPBA

9 Keeping up with a volatile aviation market Negative External Events - Funding of airfield facilities expansion questionable - Existing business class turbine aircraft accommodated at Independence State Airport but they rarely come - Declining number of recreational/sport aircraft due to limited supply of Avgas - Airpark Residential included on Westside but development never realized due to costs and funding - Minor changes of airfield facilities to meet standards - Existing business class turbine aircraft not accommodated and directed to Salem/McNary Field - More recreational/sport aircraft in existing Airport hangars and Airpark homes only - Limited commercial/industrial development growth on Westside due to limited funding availability - No Airpark Residential in Westside AD Zone Airport Role Evolves (JetA, IAP, and Facilities Upgrade to B-II) - Expansion of airfield facilities - Nationally growing business class turbine aircraft accommodated at Independence State Airport - Growth of recreational/sport aircraft and electric aircraft have entered the market - Aeronautical commercial/industrial development growth on Westside - Airpark Residential growth on Westside - Minor changes in airfield facilities to meet standards - Nationally growing business class turbine aircraft not accommodated and directed to Salem/McNary Field - Growth of new recreational/sport aircraft stored primarily in Airport hangars on Westside - No Airpark Residential in Westside AD Zone Let s get out in front and be ready for what could be coming Positive External Events The Airport has gone down hill, let s go somewhere else Airport Role Status Quo It s our Airport, and we like it the way it is

10 1. Where do you put 70 new hangars and 20,000 SY of new apron space? Scenario Planning Matrix Airport Role Evolves (JetA, IAP, and Facilities Upgrade to B-II) 2. Are there future RTTF access points? If so, Where? 3. Where does future security fencing begin and end? Keeping up with a volatile aviation market Let s get out in front and be ready for what could be coming 4. Is there an Instrument Approach? If so, is it lower than 1 mile visibility? 5. Is there a grass landing area? Where? Negative External Events Positive External Events 6. How do we address the RPZ, displaced threshold, and get a runway length of 3,600? The Airport has gone down hill, let s go somewhere else Airport Role Status Quo It s our Airport, and we like it the way it is

11 ALTERNATIVE CONCEPTS Three draft concepts prepared Each meet facility requirements for future growth Incorporate and address key issues where able o o o o Turf runway/alternate landing area Long range development on west side Flexible for meeting B-II (larger aircraft) in the future Stormwater/drainage reserve areas

12

13 Alternative 1 Shift runway north to maintain runway length of 3,142 Relocate connectors to meet criteria Prepare alternate landing area o Relocate lighted windcone/segmented circle o Remove PAPI system Acquire land to the west for future airport development (33 acres) Acquire land to the south for RPZ and approach protection (6 acres) Construct full length parallel taxiway on west side including taxiway lighting and drainage improvements Construct apron and taxilanes for west side hangar development Construct access road north from Hoffman Road Install fencing for security and wildlife control Depict future airpark uses only to west within UGB, no development to north Rough Order Magnitude Cost Estimate: Approx $9.3M to $10.0M Includes soft costs and 15% contingencies. Range accounts for land acquisition uncertainties and inflation.

14

15 Alternative 2 Shift runway north and extend to future runway length of 3,436 Relocate connectors to meet criteria Acquire land to the west for future airport development (34 acres) Acquire land to the south for RPZ and approach protection (6 acres) Construct full length parallel taxiway on west side including taxiway lighting and drainage improvements Construct apron and taxilanes for west side hangar development Construct access road north from Hoffman Road Install fencing for security and wildlife control Depict future airpark uses and UGB expansion only to north, airport development to west Rough Order Magnitude Cost Estimate: Approx $10.5M to $11.5M Includes soft costs and 15% contingencies. Range accounts for land acquisition uncertainties and inflation.

16

17 Alternative 3 Relocate Runway 34 threshold for a future runway length of 3,001 Relocate connectors to meet criteria Acquire land to the west for future airport development (64 acres) Acquire land to the south for RPZ and approach protection (6 acres) Construct full length parallel taxiway on west side including taxiway lighting, drainage improvements, and environmental mitigation Construct turf runway at a future length of 1,700 including environmental mitigation Construct apron and taxilanes for west side hangar development Construct access road north from Hoffman Road Install fencing for security and wildlife control Do not depict any future airpark development Rough Order Magnitude Cost Estimate: Approx $9.2M to $10.5M Includes soft costs and 15% contingencies. Range accounts for land acquisition uncertainties and inflation.

18 DISCUSSION AND REPORT OUT 1. What are key advantages or drawbacks to each alternative? 2. Do you believe any facilities are missing or underrepresented? 3. Do you believe any facilities that FAA would not financially support would be worth local investment? 4. Which alternative best represents your vision for the airport?

19 PUBLIC COMMENTS Three minutes for each speaker

20 NEXT STEPS PAC #4 and Open House June 2018

21 PUBLIC COMMENTS Matt Maass Jeff Caines Dave Nafie

INDEPENDENCE STATE AIRPORT (7S5)

INDEPENDENCE STATE AIRPORT (7S5) INDEPENDENCE STATE AIRPORT (7S5) Airport Master Plan Update 2018 Planning Advisory Committee PAC Meeting #1 December 6, 2017 AGENDA The first PAC workshop will cover the following topics: Planning Team/PAC

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the

More information

CHAPTER 1. INTRODUCTION

CHAPTER 1. INTRODUCTION CHAPTER 1. INTRODUCTION An Airport Master Plan Update serves as an opportunity for airport sponsors, airport users, and other stakeholders to discuss the existing challenges and uncertain futures surrounding

More information

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Project Team Century West Engineering Northwest firm founded in 1969 500+ airport projects completed throughout the Pacific

More information

Airlake Airport 2035 Long Term Comprehensive Plan (LTCP)

Airlake Airport 2035 Long Term Comprehensive Plan (LTCP) Airlake Airport 2035 Long Term Comprehensive Plan (LTCP) Public Informational Meetings August 9 & 10, 2017 Draft LTCP Overview Briefing Agenda Airport Role & Context Existing Conditions & Previous Plan

More information

Independence State Airport Master Plan Update

Independence State Airport Master Plan Update Attendees: Planning Advisory Committee Meeting #1 Issues & Opportunities, Existing Conditions, and Aviation Forecasts December 6, 2017 City of Independence Library: Independence, Oregon 6:00 to 8:30 p.m.

More information

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017 Lopez Island Airport Master Plan Update Public Meeting June 15, 2017 Master Plan Update Team Reid Middleton/Everett, WA Shannon Kinsella, Project Manager Melania Haagsma, Project Engineer Mead & Hunt/Tulsa,

More information

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction

More information

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Project Team Kittitas County, WA Airport Owner (Sponsor) and Operator, Land Use Century West

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together Bringing g the PUBLIC WORKSHOP Venice Municipal Airport New Opportunities Presented for Venice City Council & Citizens of Venice September 25, 2009 Slide 1 Bringing g the Welcome & Introductions May 12th

More information

MASTER PLAN CONCEPT 1 DRAFT

MASTER PLAN CONCEPT 1 DRAFT The Airport Master Plan Update for Dallas Executive Airport has included the development of aviation demand forecasts, an assessment of future facility needs, and the evaluation of airport development

More information

PLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016

PLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016 PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016 Meeting Agenda 1. Introductions and Contacts [10 Minutes] 2. Plan Overview and MPAC Role [20 Minutes] 3. MPAC Visioning

More information

Lake Tahoe Airport Master Plan

Lake Tahoe Airport Master Plan Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES

SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES 5.1 INTRODUCTION This section investigates Airfield Development Alternatives, generalized Land Use Alternatives, and more detailed General Aviation Alternatives.

More information

Raleigh Executive Jetport Master Plan Update MPAC MEETING #3 NOVEMBER 1, 2018

Raleigh Executive Jetport Master Plan Update MPAC MEETING #3 NOVEMBER 1, 2018 Raleigh Executive Jetport Master Plan Update MPAC MEETING #3 NOVEMBER 1, 2018 Agenda» Website Update» Alternatives» Discussion» Evaluation» Schedule Agenda» Website Update» Alternatives» Discussion» Evaluation»

More information

Collier County Airport Authority. Joint Automated Capital Improvement Program

Collier County Airport Authority. Joint Automated Capital Improvement Program Collier County Airport Authority Joint Automated Capital Improvement Program Joint Automated Capital Improvement Program (JACIP) What is the JACIP? Financial planning process supported by Web-based computer

More information

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4

PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) MEETING #4 AGENDA & ACTION ITEMS Date/Time: Location: Monday, March 19, 2018 from 1:30-3:30 p.m. Thun Field Airport

More information

Grants Pass Airport Master Plan & Airport Layout Plan Update

Grants Pass Airport Master Plan & Airport Layout Plan Update Attendees: Grants Pass Airport Master Plan & Airport Layout Plan Update Meeting #3 January 26, 2010 Merlin Community Center 100 Acorn Street, Merlin 5:45 7:15 p.m. Josephine County Department of Airports:

More information

Chapter 1 Introduction and Project Overview

Chapter 1 Introduction and Project Overview EPHRATA MUNICIPAL AIRPORT Chapter 1 Introduction and Project Overview The Port of Ephrata in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Ephrata Municipal

More information

Chapter 4 Airport Facility Requirements

Chapter 4 Airport Facility Requirements Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT

More information

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.

More information

ACTION TRANSMITTAL

ACTION TRANSMITTAL Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED

More information

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item.

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item. Committee Report Business Item No. 2017-191 Transportation Committee For the Metropolitan Council meeting of September 13, 2017 Subject: Final Crystal Airport 2035 Long Term Comprehensive Plan (LTCP) Proposed

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

DRAFT MASTER PLAN UPDATE

DRAFT MASTER PLAN UPDATE DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS

More information

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business Plan Steering Committee December 14, 2006 Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business

More information

MONTROSE REGIONAL AIRPORT

MONTROSE REGIONAL AIRPORT MONTROSE REGIONAL AIRPORT FEBRUARY 25, 2016 DRAFT AGENDA READY FOR TAKE OFF WHAT ARE WE GOING TO DO TODAY? Introductions Why conduct an airport master plan? Master Plan Process Deliverables Schedule Identify

More information

Master Plan Update Community Advisory Committee Kick-off Meeting

Master Plan Update Community Advisory Committee Kick-off Meeting Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

Master Plan Update Technical Advisory Committee Meeting

Master Plan Update Technical Advisory Committee Meeting Nashville International Airport Master Plan Update Technical Advisory Committee Meeting February 14, 2019 Agenda Welcome and Introductions Aviation Activity Forecast Facility Requirements Alternatives

More information

General Aviation Master Plan Update

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System

More information

HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1

HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1 HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1 Feb. 27, 2017 HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Welcome Curtis Robinhold, Port of Portland 1 HILLSBORO

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

Chapter 1 Introduction and Project Overview

Chapter 1 Introduction and Project Overview Chapter 1 Introduction and Project Overview Kittitas County in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Bowers Field Airport (FAA airport identifier

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016 Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand

More information

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D STAFF REPORT SUBJECT: Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan MEETING DATE: AGENDA ITEM: 7D STAFF CONTACT: Peter Imhof, Andrew Orfila RECOMMENDATION: Adopt findings

More information

Chapter 4.0 Alternatives Analysis

Chapter 4.0 Alternatives Analysis Chapter 4.0 Alternatives Analysis Chapter 1 accumulated the baseline of existing airport data, Chapter 2 presented the outlook for the future in terms of operational activity, Chapter 3 defined the facilities

More information

TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017

TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017 TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017 Please find attached for your review prior to the PAC Meeting #4,

More information

Regular Board Meeting August 4, 2015

Regular Board Meeting August 4, 2015 Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956 PUBLIC COMMENT FY 16 Rates & Charges FY 16 Budget Approval Rates & Charges will provide the Board the ability to operate

More information

Pierre Regional Airport Airport Master Plan. Kickoff Meeting April 7, 2017

Pierre Regional Airport Airport Master Plan. Kickoff Meeting April 7, 2017 Pierre Regional Airport Airport Master Plan Kickoff Meeting April 7, 2017 Agenda Introductions Airport Master Planning Planning Considerations Master Plan Elements Schedule Public Involvement Basics about

More information

Planning Advisory Committee Meeting #4 September 12, 2017

Planning Advisory Committee Meeting #4 September 12, 2017 Planning Advisory Committee Meeting #4 September 12, 2017 1 HILLSBORO AIRPORT MASTER PLAN UPDATE Welcome and Meeting Introduction Jerry Willey, Committee Chair Anne Pressentin, EnviroIssues 2 Agenda Welcome

More information

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4 MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis

More information

Chapter 8.0 Implementation Plan

Chapter 8.0 Implementation Plan Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.

More information

MESA COUNTY DEPARTMENT OF PUBLIC WORKS Administration - Building - Engineering Road and Bridge Traffic - Planning - Solid Waste Management

MESA COUNTY DEPARTMENT OF PUBLIC WORKS Administration - Building - Engineering Road and Bridge Traffic - Planning - Solid Waste Management MESA COUNTY DEPARTMENT OF PUBLIC WORKS Administration - Building - Engineering Road and Bridge Traffic - Planning - Solid Waste Management 200 S. Spruce St. P.O. Box 20,000 Grand Junction, Colorado 81502-5022

More information

8.0 AIRPORT LAYOUT PLANS

8.0 AIRPORT LAYOUT PLANS 8.0 AIRPORT LAYOUT PLANS This chapter presents a detailed graphic and narrative description of the selected development concept for General Mitchell International Airport (MKE). The plans package presented

More information

CHAPTER 3 AIRPORT FACILITY REQUIREMENTS

CHAPTER 3 AIRPORT FACILITY REQUIREMENTS CHAPTER 3 AIRPORT FACILITY REQUIREMENTS 3.1 Introduction The existing runway and taxiway system at Skyhaven Airport provides more than adequate operational capacity to accommodate future peak hour and

More information

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3 This is the presentation for the third Master Plan Update Working Group Meeting being conducted for the Ted Stevens Anchorage International Airport Master Plan Update. It was given on Thursday March 7

More information

Chapter 1: Introduction Draft

Chapter 1: Introduction Draft Chapter 1: Draft TABLE OF CONTENTS 1... 4 1.6.1 Stakeholder Engagement Plan... 10 Chapter 1 Page 2 TABLE OF EXHIBITS Exhibit 1.1-1 ABIA Annual Growth Since 1993... 5 Exhibit 1.4-1: ABIA Location Map...

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

Chapter 1: Introduction

Chapter 1: Introduction Chapter 1: TABLE OF CONTENTS 1... 4 1.1 Master Plan Study Content... 4 1.2 Purpose and Scope of Master Plan Study... 4 1.3 Airport History and Role... 6 1.4 Airport Location and Service Area... 6 1.5 ABIA

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

Preliminary Findings of Proposed Alternative

Preliminary Findings of Proposed Alternative Preliminary Findings of Proposed Alternative The attached drawing provides a schematic layout of the proposed alternative that will be discussed on July 27, 2010. A full report will follow and should be

More information

PLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #4 March 19, 2018

PLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #4 March 19, 2018 PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 March 19, 2018 Meeting Agenda 1. Master Plan Status [5 Minutes] 2. Preferred Forecasts [15 Minutes] 3. Runway Length Options [45

More information

Norfolk International Airport

Norfolk International Airport Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport

More information

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four Airport Development Alternatives Prior to formulating a development program for Ryan Airfield, it is important to consider development potential

More information

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on

More information

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP) 6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement

More information

Chapter 4. Development Alternatives

Chapter 4. Development Alternatives Chapter 4. Development Alternatives Chapter 4. DEVELOPMENT ALTERNATIVES This chapter identifies and evaluates airport development alternatives to fulfill the facility requirements for the airport as defined

More information

Airport Master Plan 1

Airport Master Plan 1 1 Aviation Demand AIRPORT PLANNING PROCESS FAA Design Standards Financial Resources Community Goals Environmental Requirements Serve Business Community This Advisory Circular (AC) provides guidance for

More information

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update Chapter Six ALP Drawings Master Plan Update The master planning process for the (Airport) has evolved through efforts in the previous chapters to analyze future aviation demand, establish airside and landside

More information

15 Precision Approach Path Indicator 33 None RSA 150 feet wide by 300 feet long 150 feet wide by 300 feet long

15 Precision Approach Path Indicator 33 None RSA 150 feet wide by 300 feet long 150 feet wide by 300 feet long The first (AMP) was completed in 1984 and updated in 2000. The current FAA approved Airport Layout Plan (ALP) is dated November 9, 2001. The FAA suggests updating the AMP every five year in accordance

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN LAST UPDATE JULY 2013 Acknowledgements The preparation of this document was financed in part by a grant from the Federal Aviation Administration (Project No: 3-27-0000-07-10), with the financial support

More information

Executive Summary This document contains the Master Plan for T. F. Green Airport. The goal of a master plan is to provide a framework of potential future airport development in a financially feasible manner,

More information

I-3 DFW Extension Public Hearing. June 2, 2011

I-3 DFW Extension Public Hearing. June 2, 2011 1 I-3 DFW Extension Public Hearing June 2, 2011 2 DFW LRT Extension Agenda: Introductions Service Plan Amendment Alignment, Grade Separations, Station, Yard Environmental Assessment Environmental Impacts/Mitigation

More information

PIERCE COUNTY-THUN FIELD AIRPORT MASTER PLAN MASTER PLAN ADVISORY COMMITTEE (MPAC) AIRPORT TOUR RD AVE. E., PUYALLUP, WA WEDNESDAY,

PIERCE COUNTY-THUN FIELD AIRPORT MASTER PLAN MASTER PLAN ADVISORY COMMITTEE (MPAC) AIRPORT TOUR RD AVE. E., PUYALLUP, WA WEDNESDAY, PIERCE COUNTY-THUN FIELD AIRPORT MASTER PLAN MASTER PLAN ADVISORY COMMITTEE (MPAC) AIRPORT TOUR 16915-103RD AVE. E., PUYALLUP, WA 98374 WEDNESDAY, SEPTEMBER 27, 2017 (2:00 to 4:00 PM) PLU AIRPORT LOCATION

More information

Yakima Air Terminal/McAllister Field Airport Master Plan Update

Yakima Air Terminal/McAllister Field Airport Master Plan Update Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used

More information

PREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update

PREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update PREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update AIRPORTS DIVISION DEPARTMENT OF TRANSPORTATION March 13, 2012 AGENDA Introduction Purpose and Meeting Objectives Kahului

More information

Wyoming Valley Airport Proposed Improvements. Presented June 26, 2012 By The WBW Airport Advisory Board & FBO

Wyoming Valley Airport Proposed Improvements. Presented June 26, 2012 By The WBW Airport Advisory Board & FBO Wyoming Valley Airport Proposed Improvements Presented June 26, 2012 By The WBW Airport Advisory Board & FBO Contents Purpose of meeting Airport overview Background of proposed improvements SWOT analysis

More information

2015 PURDUE ROAD SCHOOL March 11, 2015

2015 PURDUE ROAD SCHOOL March 11, 2015 2015 PURDUE ROAD SCHOOL March 11, 2015 Runway Protection Zone (RPZ) Definition It is a trapezoidal shape formed off the end of a runway and its geometry it a function of the airport s aircraft approach

More information

Nantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012

Nantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012 Nantucket Memorial Airport Commission Master Plan Workshop October 26, 2012 Agenda Introductions Master Plan 101 Airport Planning Issues Noise Abatement Activities Environmental Monitoring Public Outreach

More information

Preferred Alternative Summary

Preferred Alternative Summary Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative

More information

Financial Plan/Capital Improvements - DRAFT 6-1

Financial Plan/Capital Improvements - DRAFT 6-1 The analyses completed in previous chapters evaluated development needs at McKinney National Airport (TKI or Airport) over the next 20 years, based on forecast activity, facility requirements, safety standards,

More information

Airport Master Plan Open House Front Range Airport February 23, 2017

Airport Master Plan Open House Front Range Airport February 23, 2017 Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future

More information

Chapter 5 Airport Development Alternatives

Chapter 5 Airport Development Alternatives Chapter 5 Airport Development Alternatives Introduction CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-1 Evaluation Process No-Action Alternative CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-2

More information

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by:

AIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by: Draft AIRPORT MASTER PLAN Newport State Airport () Prepared for: 2000 Post Road Warwick, Rhode Island 02886-1533 THE Louis Berger Group, INC. 20 Corporate Woods Boulevard Albany, New York 12211-2370 Prepared

More information

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet

More information

chapter 5 Recommended Master Plan Concept airport master plan MASTER PLAN CONCEPT

chapter 5 Recommended Master Plan Concept airport master plan MASTER PLAN CONCEPT chapter 5 Recommended Master Plan Concept airport master plan The planning process for Coolidge Municipal Airport has included several analytical efforts in the previous chapters intended to project potential

More information

Friedman Memorial Airport Authority. Regular Meeting September 4, 2012

Friedman Memorial Airport Authority. Regular Meeting September 4, 2012 Friedman Memorial Airport Authority Regular Meeting September 4, 2012 UNFINISHED BUSINESS Airport Solutions Blaine County Report Airport Solutions City of Hailey Report Airport Solutions Airport Manager

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport

More information

Dallas Executive Airport Town Hall Meeting April 3, 2014

Dallas Executive Airport Town Hall Meeting April 3, 2014 Dallas Executive Airport Town Hall Meeting April 3, 2014 Background 1,040 acre general aviation facility owned and operated by the City of Dallas 150 based aircraft including business jets and helicopters,

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East

More information

5.0 ALTERNATIVES ANALYSIS

5.0 ALTERNATIVES ANALYSIS 5.0 ALTERNATIVES ANALYSIS The Alternative Analysis chapter describes and evaluates the various development alternatives considered for. In addition, it presents a preferred development plan that accommodates

More information

Chapter 4 Development Alternatives

Chapter 4 Development Alternatives LAKE COUNTY AIRPORT MASTER PLAN UPDATE The preceding chapter identified deficiencies of the Lake County Airport (Airport) with respect to existing and anticipated aeronautical demand, which are consistent

More information

What is an Airport Master Plan?

What is an Airport Master Plan? What is an Airport Master Plan? The goal of a master plan is to provide the framework needed to guide future airport development that will cost-effectively satisfy aviation demand, while considering potential

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

Nantucket Memorial Airport Master Plan Update

Nantucket Memorial Airport Master Plan Update Nantucket Memorial Airport Master Plan Update CHAPTER 1 - INTRODUCTION & PUBLIC OUTREACH PROGRAM REVIEW DRAFT SUBJECT TO CHANGE Prepared for: Nantucket Memorial Airport Commission 14 Airport Road Nantucket,

More information

STUDY WORK GROUP MEETING No. 4. July 12, 2017

STUDY WORK GROUP MEETING No. 4. July 12, 2017 STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,

More information

The Ohio State University Airport Master Plan Update Public Meeting 2

The Ohio State University Airport Master Plan Update Public Meeting 2 The Ohio State University Airport Master Plan Update Public Meeting 2 Date: Tuesday, March 12, 2019 Time: 6:00-8:00 p.m. Location: Ohio State Airport, 2160 West Case Road, Columbus, OH 43235 Meeting Summary

More information

Punta Gorda Airport Master Plan Update

Punta Gorda Airport Master Plan Update Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,

More information

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan Technical Report #7 Palm Beach International Airport Layout Plan Palm Beach International Airport Prepared for Palm Beach County

More information