1 Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015
2 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans to meet future aviation demand. - FAA Advisory Circular 150/5070-6B, Airport Master Plans 2
3 City s Master Plan Goals Holistic approach to a vision and direction Gather community interests Economic advancement Assess environmental factors Fiscally, environmentally, operationally and socially sustainable 3
4 FAA Master Plan Objectives Address relevant issues and satisfy regulations Consider reasonable alternatives Input for future environmental evaluations Schedule of development and funding plan Graphic depiction of proposed development Framework for continuous planning 4
5 Master Plan Progress Airport Inventory (Oct. 2013) Public Meeting (Feb. 2014) Aviation Demand Forecast (April 2014) Environmental Constraints Report (April 2014) Selection of Design Aircraft (April 2014) Public Meeting (May 2014) Public Meeting (June 2015) Phase 2 Report Published (June 2015) Public Meeting (Mar. 2015) Alternative Development Concepts (Feb. 2015) Phase 1 Report Published (Feb. 2015) City Council Workshop (Aug. 2014) City Council Selects Alternative (Oct. 2015) Publish Draft Final Report CEQA Analysis ALUC Reviews ALP City Council Adopts ALP FAA Review and Approval of ALP 5
6 FINDINGS TO DATE Documents can be found on the Airport Master Plan page of the City s web site. Visit to download the reports. 6
7 Draft Aviation Demand Forecast 32,000 30, % Average year-over-year Annual Operations 28,000 26,000 24,000 22, % Average year-over-year FAA TAF Boyd Forecast 20, Calendar Year Source: FAA and The Boyd Group 7
8 Air Service - Conclusions Unlikely in forecast period Significant shift in airline industry Practical options exist (RNO, SMF) Potential with subsidy? LAS to TVL AZA to TVL Retain commercial service capabilities Dictated on economic conditions and demand 8
9 City Council Direction to Project Team Commercial Service General Aviation Lake Tahoe Airport s Future Primary Role 9
10 City Council Direction to Project Team Commercial Service General Aviation Lake Tahoe Airport s Future Primary Role 10
11 Design Aircraft Current Future Dassault Falcon 2000 B-II Gulfstream G-V C-III 11
12 Table 3-6. Minimum runway to taxiway separation approach categories A and B Visibility Minimums Aircraft Design Group I (small) I II III IV Not lower than ¾ mile Lower than ¾ mile but not lower than ½ mile Lower than ½ mile Runway to Taxiway Separation Runway to Taxiway Separation Runway to Taxiway Separation Source: FAA Advisory Circular 150/ A, Airport Design 12
13 292.5 Feet 13
14 Table 3-7. Minimum runway to taxiway separation approach categories C, D and E Visibility Minimums Aircraft Design Group I II III IV V VI Not lower than ¾ mile Runway to Taxiway Separation Lower than ¾ mile but not lower than ½ mile Runway to Taxiway Separation Lower than ½ mile Runway to Taxiway Separation Source: FAA Advisory Circular 150/ A, Airport Design 14
15 Key Environmental Considerations Air quality Compatible land use Fish, wildlife, and plants (threatened and endangered) Floodplains (100 and 500 year) Construction impacts Water quality Wetlands Stream Environmental Zone (SEZ) 15
16 Recommended Initiatives Vision/Mission/Goals Minimum Standards revision and enforcement Airport Business Plan Rates and Charges Analysis Airport Rules and Regulations revision Release of Part 139 Certificate Airport User Outreach/Communication Plan Marketing Plan Update Noise Abatement Program Outreach 16
17 Alternatives Development: FAA Priorities 1. Safety 2. Security 3. Sustainability 4. Capacity 17
18 Alternatives Approach Identify Alternatives Facility Requirements Sustainability Opportunities Establish Criteria FAA guidance South Lake Tahoe, Airport and Sustainability goals Evaluate We Are Here 18 Select Preferred Alternative
19 Airfield Alternative 1 TAXIWAY A (8541 X ) RUNWAY (8541 X 100 ) 19
20 Airfield Alternative 2 REMOVE EXCESS PAVEMENT REMOVE HIGH SPEED EXITS TAXIWAY A (8541 X ) RUNWAY (8541 X 100 ) REMOVE BYPASS TAXIWAY CONSTRUCT 90 DEGREE TAXIWAY EXITS Alternative Highlights: 1. Meet ARC B-II standards 2. Maintain 100 runway width 3. Reconfigure taxiway system to meet updated design standards 20
21 Airfield Alternative 3 REMOVE EXCESS PAVEMENT REMOVE HIGH SPEED EXITS TAXIWAY A (8541 X 50 ) RUNWAY (8541 X 75 ) REMOVE BYPASS TAXIWAY CONSTRUCT 90 DEGREE TAXIWAY EXIT Alternative Highlights: 1. Meet ARC B-II standards 2. Narrow runway width to Narrow Taxiway A width to Reconfigure taxiway system to meet updated design standards 21
22 Airfield Alternative 4 REMOVE EXCESS PAVEMENT REMOVE HIGH SPEED EXITS TAXIWAY A (8541 X 50 ) RUNWAY (8541 X 75 ) Runway centerline to taxiway centerline = 240 REMOVE BYPASS TAXIWAY CONSTRUCT 90 DEGREE TAXIWAY EXITS Alternative Highlights: 1. Meet ARC B-II standards 2. Narrow runway width to Relocate runway centerline to meet minimum required separation distance 4. Narrow Taxiway A width to Reconfigure taxiway system to meet updated design standards 22
23 Airfield Alternative 5 RELOCATE RUNWAY CENTERLINE REMOVE HIGH SPEED EXIT (TAXIWAY E) WIDEN TAXIWAY TO 50 TAXIWAY A (8541 X ) RUNWAY (8541 X 100 ) Runway centerline to taxiway centerline = 400 REMOVE BYPASS TAXIWAY CONSTRUCT 90 DEGREE TAXIWAY EXITS Alternative Highlights: 1. Meet ARC C-III standards 2. Shift runway centerline east from taxiway to meet minimum required separation distance 3. Extend taxiway throats to serve relocated runway 4. Reconfigure taxiway system to meet updated design standards 23
24 Airfield Alternative 6 RELOCATE TAXIWAY CENTERLINE REMOVE HIGH SPEED EXIT (TAXIWAY E) WIDEN TAXIWAY TO 50 TAXIWAY A (8541 X 50 ) RUNWAY (8541 X 100 ) Runway centerline to taxiway centerline = 400 REMOVE BYPASS TAXIWAY CONSTRUCT 90 DEGREE TAXIWAY EXITS Alternative Highlights: 1. Meet ARC C-III standards 2. Shift taxiway centerline west to meet minimum required separation distance 3. Extend taxiway throats 4. Reconfigure taxiway system to meet updated design standards 24
25 Airfield Alternative 7 RELOCATE TAXIWAY CENTERLINE REMOVE HIGH SPEED EXIT (TAXIWAY E) WIDEN TAXIWAY TO 50 TAXIWAY A (8541 X 50 ) RUNWAY (8541 X 100 ) Runway centerline to taxiway centerline = 400 REMOVE BYPASS TAXIWAY CONSTRUCT 90 DEGREE TAXIWAY EXITS RELOCATE RUNWAY CENTERLINE Alternative Highlights: 1. Meet ARC C-III standards 2. Shift taxiway centerline and runway centerline to meet minimum required separation distance 3. Extend taxiway throats 4. Reconfigure taxiway system to meet updated design standards 25
26 Public Comments Evaluation Process Sustainability Screening Process Results 26
27 Dot Polling Station 27
28 Dot Polling Results Preferred Airfield Alternative Alternative Votes 1 - No Action Meet ARC B-II and Maintain Flexibility Meet ARC C-III and Shift Runway/Taxiway Meet ARC C-III and Shift Runway East Meet ARC C-III and Shift Taxiway West Meet ARC B-II and Reduce Airport Footprint Meet ARC B-II and Reduce Airport Footprint (runway centerline shift) 1 28
29 Alternative Evaluation Criteria Economic Viability Operational Efficiency Natural Resource Conservation Social Responsibility 29
30 Alternative Evaluation / Scoring Rating Evaluation of Impact Score Positive 2 Neutral 1 Negative 0 30
31 Technical Analysis / Scoring Airfield Alternative Summary Score Ranking 1: No Action 19 First (tie) 2: Meet ARC B-II and Maintain Flexibility 19 First (tie) 4: Meet ARC B-II and Reduce Airport Footprint (runway centerline shift) 18 Second 3: Meet ARC B-II and Reduce Airport Footprint 17 Third 5: Meet ARC C-III and Shift Runway East 13 Fourth (tie) 6: Meet ARC C-III and Shift Taxiway West 13 Fourth (tie) 7: Meet ARC C-III and Shift Runway/Taxiway 13 Fourth (tie) 31
32 Landside Alternative A DESIGNATED NON- AERONAUTICAL USE (17.8 acres) 32
33 Landside Alternative B ELECTRIC CHARGING STATIONS RESTRIPE 6 BIKE LANE ATCT REMOVAL HANGAR RELOCATION DESIGNATED HELICOPTER PARKING ROOFTOP SOLAR RELOCATE PERIMETER FENCE SELF-SERVE FUEL STN. APRON PAVEMENT REDUCTION FUEL FARM CLOSURE Alternative Highlights: 1. Consolidate facilities 2. Look to maximize non-aeronautical land uses DESIGNATED NON- AERONAUTICAL USE (30 acres) DESIGNATED NON- AERONAUTICAL USE (17.8 acres) TRANSIENT AIRCRAFT PARKING BASED AIRCRAFT PARKING 33
34 Landside Alternative C ELECTRIC CHARGING STATIONS ATCT REMOVAL DESIGNATED HELICOPTER PARKING ROOFTOP SOLAR SELF-SERVE FUEL STATION RESERVE FOR FBO EXPANSION LARGE AIRCRAFT STORAGE HANGAR (120 x 120 ) AIRCRAFT WASH RACK Alternative Highlights: 1. Maintains flexibility 2. Enhance pilot services 3. Mix of non-aeronautical and aeronautical use 34
35 Landside Alternative D ELECTRIC CHARGING STATIONS ATCT REMOVAL RESERVE FOR FUTURE TERMINAL EXPANSION RESERVE FOR ARFF EXPANSION ROOFTOP SOLAR DESIGNATED HELICOPTER PARKING SELF-SERVE FUEL STATION RESERVE FOR FBO EXPANSION LARGE AIRCRAFT STORAGE HANGAR (120 x 240 ) AIRCRAFT WASH RACK APRON EXPANSION EMERGENCY SERVICES EXPAND TAXIWAY TO 50 FUEL FARM CLOSURE Alternative Highlights: 1. Focus on revenue generation/corporate aviation 2. Enhance pilot services 3. Preserve property for aeronautical use and facility expansion 35
36 Dot Polling Results Preferred Landside Alternative Alternative Votes D - Focus on growth potential that seeks to maximize airport revenues and optimize 27 available land assets A - No Action 18 C - Maintain flexibility to accommodate future growth potential 11 B - Maintain and consolidate facilities to minimize the airport s footprint 8 36
37 Technical Analysis / Ranking Landside Alternative C: Maintain flexibility to accommodate future growth potential B: Maintain and consolidate facilities to minimize the airport s footprint Summary Score Ranking 20 First 18 Second D: Focus on growth potential that seeks to maximize airport revenues and optimize available land assets 16 Third A: No Action 14 Fourth 37
38 Alternative 2C ELECTRIC CHARGING STATIONS DESIGNATED HELICOPTER PARKING RESERVE FOR FUTURE NON-AERO. USE (15 ACRES) RESERVE FOR FUTURE AERONAUTICAL USE (2.8 ACRES) RETENTION POND ROOFTOP SOLAR RESERVE FOR FUTURE NON-AERO. USE (4.3 ACRES) ARFF SELF-SERVE FUEL STATION TERMINAL TRANSIENT AIRCRAFT PKNG. RESERVE FOR FBO EXPANSION ATCT REMOVAL HANGARS BASED AIRCRAFT PARKING TAXIWAY A (8541 X ) AIRCRAFT WASH RACK RUNWAY (8541 X 100 ) RESERVE FOR FUTURE NON-AERO. USE (11.2 ACRES) LARGE AIRCRAFT STORAGE HANGAR (120 x 120 ) RESERVE FOR FUTURE AERONAUTICAL USE (18.8 ACRES) FUEL FARM REMOVE HIGH SPEED EXITS REMOVE EXCESS PAVEMENT CONSTRUCT 90 DEGREE TAXIWAY EXITS CONSTRUCT 90 DEGREE TAXIWAY EXITS REMOVE BYPASS TAXIWAY Airside Highlights: 1. Meet ARC B-II standards 2. Maintain 100 runway width 3. Reconfigure taxiway system to meet updated design standards Landside Highlights: 1. Maintains flexibility 2. Enhance pilot services 3. Mix of non-aeronautical and aeronautical use 38
39 Next Steps City Council selection of preferred alternative Finalize ALP drawing set Publish Draft Final Report CEQA analysis ALUC review of ALP City Council adopt ALP Submit to FAA for approval 39
Lake Tahoe Airport Master Plan Public Meeting March 16, 2015
Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans
More informationDRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014
DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation
More informationExecutive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport
Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche
More informationAirport Master Plan. Brookings Regional Airport. Runway Runway 17-35
Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements
More informationBNA Master Plan Update Public Meeting No. 2
A Six Sigma Organization BNA Master Plan Update Public Meeting No. 2 September 18, 2012 Agenda BNA Master Plan Update Consultants Status of the BNA Master Plan Update Workstation Boards Forecasts of Aviation
More informationGeneral Aviation Master Plan Update
Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System
More informationMONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES
MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the
More informationAirport Master Plan for. Brown Field Municipal Airport PAC Meeting #3
Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus
More informationAirport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3
Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline
More informationCHAPTER 1 EXECUTIVE SUMMARY
CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport
More informationTable of Contents. Master Plan March 2014 TOC i Spokane International Airport
Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land
More informationMASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4
MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis
More informationAirport Master Plan Open House Front Range Airport February 23, 2017
Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future
More informationBNA Master Plan Update Community Advisory Committee Meeting No. 5
A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,
More informationNantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012
Nantucket Memorial Airport Commission Master Plan Workshop October 26, 2012 Agenda Introductions Master Plan 101 Airport Planning Issues Noise Abatement Activities Environmental Monitoring Public Outreach
More informationMeeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012
Meeting Presentation Master Plan Update October 30, 2012 Agenda We encourage open discussion during today s meeting Team Goals Background (Airport Master Plans) Areas of Emphasis Schedule Special Concerns
More informationAddendum - Airport Development Alternatives (Chapter 6)
Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary
More informationKittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016
Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Project Team Kittitas County, WA Airport Owner (Sponsor) and Operator, Land Use Century West
More informationMerritt Island Airport
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory
More informationChapter 8.0 Implementation Plan
Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.
More informationPreferred Alternative Summary
Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative
More informationDallas Executive Airport Town Hall Meeting April 3, 2014
Dallas Executive Airport Town Hall Meeting April 3, 2014 Background 1,040 acre general aviation facility owned and operated by the City of Dallas 150 based aircraft including business jets and helicopters,
More informationTABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i
TABLE OF CONTENTS Chapter 1 Overview... 1-1 1.1 Background... 1-1 1.2 Overview of 2015 WASP... 1-1 1.2.1 Aviation System Performance... 1-2 1.3 Prior WSDOT Aviation Planning Studies... 1-3 1.3.1 2009 Long-Term
More informationGerald R. Ford International Airport Authority Master Plan Update A World Class Gateway
Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Master Plan Advisory Committee (MPAC) Alternatives September 28, 2017 AGENDA Review of Previous Work Ultimate Land
More informationOctober 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION
October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.
More informationTable of Contents. Overview Objectives Key Issues Process...1-3
Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5
More informationDraft Concept Alternatives Analysis for the Inaugural Airport Program September 2005
Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined
More informationAIRPORT MASTER PLAN. Newport State Airport. Draft. (Colonel Robert F. Wood Airpark) THE Louis Berger Group, INC. Prepared for: Prepared by:
Draft AIRPORT MASTER PLAN Newport State Airport () Prepared for: 2000 Post Road Warwick, Rhode Island 02886-1533 THE Louis Berger Group, INC. 20 Corporate Woods Boulevard Albany, New York 12211-2370 Prepared
More information1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201
More informationDraft Concept Alternatives Analysis for the Inaugural Airport Program September 2005
Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9
More informationHILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1
HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1 Feb. 27, 2017 HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Welcome Curtis Robinhold, Port of Portland 1 HILLSBORO
More informationFORECASTING FUTURE ACTIVITY
EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver
More informationCHAPTER 1: INTRODUCTION
CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the
More informationSTUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES
INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes
More informationPunta Gorda Airport Master Plan Update
Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,
More informationSTUDY WORK GROUP MEETING No. 3. November 29, 2016
STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity
More informationMaster Plan Update Community Advisory Committee Kick-off Meeting
Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision
More informationNew Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together
Bringing g the PUBLIC WORKSHOP Venice Municipal Airport New Opportunities Presented for Venice City Council & Citizens of Venice September 25, 2009 Slide 1 Bringing g the Welcome & Introductions May 12th
More informationSTUDY WORK GROUP MEETING No. 4. July 12, 2017
STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,
More informationChapter 2 FINDINGS & CONCLUSIONS
Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued
More informationRaleigh Executive Jetport Master Plan Update MPAC MEETING #3 NOVEMBER 1, 2018
Raleigh Executive Jetport Master Plan Update MPAC MEETING #3 NOVEMBER 1, 2018 Agenda» Website Update» Alternatives» Discussion» Evaluation» Schedule Agenda» Website Update» Alternatives» Discussion» Evaluation»
More informationPLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016
PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016 Meeting Agenda 1. Introductions and Contacts [10 Minutes] 2. Plan Overview and MPAC Role [20 Minutes] 3. MPAC Visioning
More informationWestover Metropolitan Airport Master Plan Update
Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The
More informationTed Stevens Anchorage International Airport
Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the
More informationAIRPORT MASTER PLAN UPDATE
AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo
More informationSECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES
SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES 5.1 INTRODUCTION This section investigates Airfield Development Alternatives, generalized Land Use Alternatives, and more detailed General Aviation Alternatives.
More informationTABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved
TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING
More informationChapter 4.0 Alternatives Analysis
Chapter 4.0 Alternatives Analysis Chapter 1 accumulated the baseline of existing airport data, Chapter 2 presented the outlook for the future in terms of operational activity, Chapter 3 defined the facilities
More informationIntroduction DRAFT March 9, 2017
Chapter Overview The City of Redmond (City) initiated an update to the Airport Master Plan ( Plan ) to assess the facility and service needs of the Redmond Municipal Airport ( the Airport ) throughout
More informationCHAPTER 3 ALTERNATIVES CONSIDERED
CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from
More informationUpdate on the Aspen/Pitkin County Airport Improvements
Update on the Aspen/Pitkin County Airport Improvements and EA Process Public Information Meeting September 10, 2015 Meeting Objectives Explain what has changed since we had our last meeting and how it
More informationMASTER PLAN CONCEPT 1 DRAFT
The Airport Master Plan Update for Dallas Executive Airport has included the development of aviation demand forecasts, an assessment of future facility needs, and the evaluation of airport development
More informationLopez Island Airport Master Plan Update. Public Meeting June 15, 2017
Lopez Island Airport Master Plan Update Public Meeting June 15, 2017 Master Plan Update Team Reid Middleton/Everett, WA Shannon Kinsella, Project Manager Melania Haagsma, Project Engineer Mead & Hunt/Tulsa,
More informationERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS
EXECUTIVE SUMMARY ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS PAGE NO. CHAPTER 1-INTRODUCTION... 1-1 1.01 General...1-1 1.02 Purpose and Scope of Study...1-1 1.03 The Planning Process...1-2
More informationInput Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot
Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot community Airport Advisory Board meetings Elected Officials
More informationTed Stevens Anchorage International Airport
Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the
More informationMONTROSE REGIONAL AIRPORT
MONTROSE REGIONAL AIRPORT FEBRUARY 25, 2016 DRAFT AGENDA READY FOR TAKE OFF WHAT ARE WE GOING TO DO TODAY? Introductions Why conduct an airport master plan? Master Plan Process Deliverables Schedule Identify
More informationAirport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal
Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred
More informationChapter 5 Airport Development Alternatives
Chapter 5 Airport Development Alternatives Introduction CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-1 Evaluation Process No-Action Alternative CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-2
More informationMeeting Notes Public Open House
Meeting Notes Public Open House, 5:30-8:00 pm Fairbanks Pipeline Training Center, 3605 Cartwright Court, Fairbanks, Alaska= Agenda: Open House: 30 minutes Presentation: 45 minutes Question and Answers:
More informationCollier County Airport Authority. Joint Automated Capital Improvement Program
Collier County Airport Authority Joint Automated Capital Improvement Program Joint Automated Capital Improvement Program (JACIP) What is the JACIP? Financial planning process supported by Web-based computer
More informationPULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project
PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February
More information2015 PURDUE ROAD SCHOOL March 11, 2015
2015 PURDUE ROAD SCHOOL March 11, 2015 Runway Protection Zone (RPZ) Definition It is a trapezoidal shape formed off the end of a runway and its geometry it a function of the airport s aircraft approach
More informationBurke Lakefront Airport (BKL) Master Plan Update
Burke Lakefront Airport () Master Plan Update Public Workshop August 2, 2007 City of Cleveland Department of Port Control (DPC) City of Cleveland DPC Studies Currently In Progress Market Assessment & Feasibility
More informationSTAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D
STAFF REPORT SUBJECT: Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan MEETING DATE: AGENDA ITEM: 7D STAFF CONTACT: Peter Imhof, Andrew Orfila RECOMMENDATION: Adopt findings
More informationPrepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906
Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement
More informationNorfolk International Airport
Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport
More informationWhat is an Airport Master Plan?
What is an Airport Master Plan? The goal of a master plan is to provide the framework needed to guide future airport development that will cost-effectively satisfy aviation demand, while considering potential
More informationAgenda: SASP SAC Meeting 3
Agenda: SASP SAC Meeting 3 Date: 04/12/18 Public Involvement Plan Update Defining the System Recommended Classifications Discussion Break Review current system Outreach what we heard Proposed changes Classification
More informationStudy Committee Meeting. September 2015
W ki P T / Working Paper Two/ Study Committee Meeting September 2015 Agenda Introductions and Opening Comments Project Overview, Process, and Schedule Review Materials from Working Paper Two Comments,
More informationPublic Information Meeting. September 2015
W ki P O & T / Working Papers One & Two/ Public Information Meeting September 2015 Agenda Introductions and Opening Comments Project Overview, Process, and Schedule Review Materials from Working Papers
More informationChapter 1 Introduction and Project Overview
Chapter 1 Introduction and Project Overview Kittitas County in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Bowers Field Airport (FAA airport identifier
More informationDRAFT MASTER PLAN UPDATE
DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS
More informationExecutive Summary This document contains the Master Plan for T. F. Green Airport. The goal of a master plan is to provide a framework of potential future airport development in a financially feasible manner,
More informationJOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012
1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley
More informationTallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016
Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand
More informationExecutive Summary. Lake Tahoe Airport Master Plan Draft Phase I Report. Introduction
Introduction Executive Summary Lake Tahoe Airport, owned and operated by the City of South Lake Tahoe, is a public-use airport that currently holds a Part 139 Airport Certification Status that allows for
More informationAppendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update
Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on
More informationSouthwestFloridaInternational Airport
SouthwestFloridaInternational Airport SouthwestFloridaInternationalAirportislocatedinLee CountyalongtheGulfCoastofSouthFlorida,tenmiles southeastofthefortmyerscentralbusinessdistrict. Theprimaryhighwayaccesstotheairportfrom
More information6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)
6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement
More informationSummary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item.
Committee Report Business Item No. 2017-191 Transportation Committee For the Metropolitan Council meeting of September 13, 2017 Subject: Final Crystal Airport 2035 Long Term Comprehensive Plan (LTCP) Proposed
More informationPublic Review Draft South County Airport Master Plan Report. County of Santa Clara San Martin, California
Public Review Draft South County Airport Master Plan Report County of Santa Clara San Martin, California July 2005 County of Santa Clara Board of Supervisors Donald F. Gage Blanca Alvarado Peter A. McHugh
More informationVista Field Airport. Master Plan Update. February, Prepared for: Port of Kennewick One Clover Island Kennewick, Washington
Vista Field Airport February, 2006 Prepared for: Port of Kennewick One Clover Island Kennewick, Washington 99336 Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington
More informationChapter Seven COST ESTIMATES AND FUNDING A. GENERAL
Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction
More informationMilton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.
Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet
More informationTable of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update
Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East
More information2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)
2018 Airport Master Plan Overview of Development Concepts Greg Ballentine (WSP) Thank You Stakeholder and community consultation has included discussions with over 40 stakeholder groups including airport
More informationAlternatives Development and Evaluation Report
Airport Master Plan Alternatives Development and Evaluation Report Prepared by: AECOM Prepared for: Illinois Department of Transportation December 16, 2011 Table of Contents Topic Page Number Cover Sheet...
More informationRegular Board Meeting August 4, 2015
Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956 PUBLIC COMMENT FY 16 Rates & Charges FY 16 Budget Approval Rates & Charges will provide the Board the ability to operate
More informationB GEORGIA INFRASTRUCTURE REPORT CARD AVIATION RECOMMENDATIONS DEFINITION OF THE ISSUE. Plan and Fund for the Future:
2014 GEORGIA INFRASTRUCTURE REPORT CARD B + RECOMMENDATIONS Plan and Fund for the Future: While the system continues to enjoy excess capacity and increased accessibility it still needs continued focus
More informationAirport Master Plan Update
Duttchessss Countty Airrporrtt Masstterr Plan Updatte Airport Master Plan Update Final Report Dutchess County Airport Town of Wappingers, New York C&S Engineers, Inc. 499 Col. Eileen Collins Blvd. Syracuse,
More informationACTION TRANSMITTAL
Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED
More informationINDEPENDENCE STATE AIRPORT (7S5)
INDEPENDENCE STATE AIRPORT (7S5) Airport Master Plan Update 2018 Planning Advisory Committee PAC Meeting #3 April 11, 2018 1994-2016 AGENDA The second PAC workshop will cover the following topics: Recap
More informationPREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update
PREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update AIRPORTS DIVISION DEPARTMENT OF TRANSPORTATION March 13, 2012 AGENDA Introduction Purpose and Meeting Objectives Kahului
More informationChapter 1 Introduction and Project Overview
EPHRATA MUNICIPAL AIRPORT Chapter 1 Introduction and Project Overview The Port of Ephrata in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Ephrata Municipal
More informationMaster Plan Update Technical Advisory Committee Meeting
Nashville International Airport Master Plan Update Technical Advisory Committee Meeting February 14, 2019 Agenda Welcome and Introductions Aviation Activity Forecast Facility Requirements Alternatives
More informationYakima Air Terminal/McAllister Field Airport Master Plan Update
Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used
More informationFort Wayne International Airport Master Plan Study. Executive Summary
Fort Wayne International Airport Master Plan Study Executive Summary March 2012 Introduction Airport Background Forecast of Aviation Activity Development Plans Recommended Airfield & Access Development
More informationChapter 4 Airport Facility Requirements
Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT
More informationBirmingham Airport 2033
Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted
More information