1 Kit Carson-Challenger Ridge Trail Project Project Accomplishments Report-USFS December 15, 2015 Photo courtesy of Justin Peterson 815 South 25 th Street, Suite 101 Colorado Springs, CO Dedicated to the conservation and stewardship of public lands in Southern Colorado

2 2 Background The Rocky Mountain Field Institute completed year 2 of the 3-year Kit Carson-Challenger Ridge Trail Project in the summer months of The project is designed to manage the high-use impacts of Willow Lake Basin in the Sangre de Cristo Mountain Range in Southern Colorado. The fourth highest mountain in the Sangres, Kit Carson Peak (elevation 14,165 ) towers over 6,000 feet above the San Luis Valley floor. Kit Carson generally refers to the three main summits that make up the massif: Kit Carson Peak, Challenger Point, and Columbia Point (informally known as Kat Carson). These peaks and Willow Lake Basin situated below the glacial-formed cirque are a popular recreation spot for hikers, climbers, anglers, and other backcountry enthusiasts. The Basin is particularly popular with residents of the town of Crestone and nearby Baca Grande subdivision, both of which sit at the foot of the mountain. The trail project is designed to reduce visitor impacts to the area and enhance the quality of the climbing and hiking recreational experience. Upon completion of the three-phase project, a sustainable trail will provide access from the Willow Creek Trailhead to the ridge of Challenger Point, approximately 7.25 miles in total. From that point, the existing summit trail to Kit Carson generally follows natural contours or crosses talus fields, causing little damage to the sensitive alpine environment. The current user-created social trail is in very poor condition from the east side of Willow Lake to the talus field below the notch of the ridge. The trail is gullied, unsafe, and unpleasant for hikers. The current trail also crosses environmentally fragile areas including populations of sensitive alpine plants and an alpine wetland east of Willow Lake. The focus of Phase 1 of the project is to re-route the current social trail to a more durable and sustainable location, and to reconstruct and stabilize usable sections of the existing alignment with proper structures including rock steps and retaining walls, thus protecting the surrounding environment by defining a single trail corridor. All phases of the project also include substantial social trail closure and restoration including erosion control and revegetation work. In Phase 1 of the project (spanning the field seasons), RMFI will construct approximately 2,795 feet of new trail and improve approximately 2,760 feet of existing trail. Beginning in 2017, RMFI will build off the success of Phase 1 of the project and continue to improve the summit trail in Phase 2. This report details the accomplishments of the project during the 2015 field season. Summary of Work 2015 Field Season Utilizing financial support from various funders, the Rocky Mountain Field Institute (RMFI) leveraged the use of a paid youth corps crew and a volunteer collegiate class to make significant progress on Phase 1-Year 2 of the Kit Carson Peak- Challenger Ridge Trail Project. RMFI utilized a new partnership with the Southwest Conservation Corps (SCC) as well as the efforts of 10 college students who participated in the 13 th edition of the RMFI Earth Corps field studies program to accomplish 2015 project objectives. Phase 1-Year 2 project accomplishments can be broken down into three primary tasks: trail reconstruction, new trail construction, and trail maintenance. A late spring snowmelt at the project site as well as unanticipated challenges with project logistics and implementation resulted in original project accomplishments not being fully met. However, the amount of work contributed toward overall project goals was not affected and the project is still on track to accomplish Phase 1 in the initial timeline. The following is a breakdown of project objectives.

3 3 1. Trail Reconstruction: 1,874 linear feet Construct rock steps, rock risers, drainage structures, cairns, and rock retaining walls; clear loose rock; rearrange rock to create tread in talus field Trail reconstruction goals were met during Phase 1-Year 2. Approximately 1,844 linear feet of existing social trail was improved to meet U.S. Forest Service standards for backcountry hiking trails (Photo #1). Starting at an elevation of approximately 11,500 feet, work crews brushed willow and Krummholtz from the trail corridor (12+82 to 24+90), cleared boulders that were causing trail braiding, reinforced the water crossing with installation of stepping stones (24+90), and improved the existing trail through the talus by adding an aggregate layer of rock that provided a more stable and accommodating tread surface (12+56 to 16+17, Photo #1). This work was started in the talus to the north of Willow Lake at (where the 2014 work left off) and ended at the start of the new trail alignment at Over the past two field seasons, the summit trail has been re-constructed from 0+00 to This section is now complete, aside from some willow brushing that may need to occur on a seasonal basis. This section was of particular concern because it contains habitat of the Smith s draba (Draba smithii), a species of concern as identified by the U.S. Fish and Wildlife Service. 2. New Trail Construction: 1,050 linear feet Cut 24 full bench tread into hillslope, clear branches and logs from trail corridor. Construct rock steps, drainage structures, cairns, and rock retaining walls. Approximately 1,050 linear feet of new trail was constructed during Phase 1-Year 2 of the project (Photos #2, 4-6). New trail construction at an elevation of approximately 12,000 feet is extremely taxing and equally rewarding. Work crews cut a 24 bench into the alpine tundra and rearranged rocks from talus fields in order to establish a sustainable trail tread. For areas where the trail crossed talus, rubble retaining walls were constructed on both the inslope and outslope in order to prevent additional rock from sliding into the trail. In places where the trail gained elevation through a steep gradient, rock steps and risers were built to provide stabilization (Photo #2). 3. Trail Maintenance: 15,800 linear feet of trail maintenance As is the norm for large-scale trail projects, unplanned trail maintenance projects arose at the onset of the field season. Tree snags were cleared, logs were cut from the trail corridor, overgrown vegetation was brushed back, and rockslides were removed from the Willow Lake Trail. Crews maintained more than 3 miles (15,800 linear feet) of the Willow Lake Trail below Willow Lake. While not originally included in the proposal for Phase 1 of the project, this work was necessary for the mule string to pack in project supplies. The work was also very important for the overall sustainability of the access trail to Willow Lake. Other Work The 2015 spring season saw record rain and snowfall in many areas of Colorado, which affected snowpack, stream crossings, and the ability to use mule pack strings to establish a basecamp in the Willow Lake Basin. Therefore, in order to be in compliance with organizational safety policies and procedures and to allow for early season access into the Basin, the two 9-day hitches with SCC were delayed from an original start date of June 8 th to June 22 nd. In place of restoring campsites around Willow Lake, work crews improved a hazardous stream crossing with the construction of a log bridge. This accomplishment was a very high priority as it ensured safe

4 4 access to the project site by the mule string and work crews (Photo #3). Campsite restoration will occur during the 2016 field season. Work Statistics 1,874 linear feet of trail improved 1,050 linear feet of trail constructed 15,800 linear feet of trail maintained 2,200 linear feet of rubble wall linear feet of retaining wall 83 rock steps 12 cairns 1, 2-log bridge crossing Labor Statistics 36 workdays 2,730 volunteer hours $62, volunteer value 1,090 paid crew hours 1,201 RMFI staff hours Contact Information Joe Lavorini RMFI Program Director joe@rmfi.org (719) ext. 3#

5 5 Map of Willow Lake Basin and project objectives.

6 6 Photo Documentation Photo #1: Tread through talus at Photo #2: Rock staircase at Photo #3: New bridge at major crossing of Willow Creek, below headwall.

7 7 Photo #4 (above): Before and after rock steps at to Photo #5 (below): Before and after of trail corridor clearing through Krummholz at

8 8 Photo #6 (above): Before and after of rock staircase at Photo #7 (below): 2015 SCC crew (left) & 2015 Earth Corps crew (right).

Kit Carson-Challenger Ridge Trail Project Annual Performance Report-2014 October 22, 2014

Kit Carson-Challenger Ridge Trail Project Annual Performance Report-2014 October 22, 2014 1 Kit Carson-Challenger Ridge Trail Project Annual Performance Report-2014 October 22, 2014 Willow Lake and Kit Carson Peak 2 SUMMARY The Rocky Mountain Field Institute began Phase 1 of a multi-phase,

More information

Dixon Trail Construction - From the Top of the Mountain 2016 Interim Report Friends of Cheyenne Mountain State Park September 2 nd, 2016

Dixon Trail Construction - From the Top of the Mountain 2016 Interim Report Friends of Cheyenne Mountain State Park September 2 nd, 2016 - Dixon Trail Construction - From the Top of the Mountain 2016 Interim Report Friends of Cheyenne Mountain State Park September 2 nd, 2016 Prepared by: Andy Riter, Program Coordinator, and Joe Lavorini,

More information

Bear Creek Habitat Improvement Project

Bear Creek Habitat Improvement Project 06/10/10 Bear Creek Habitat Improvement Project El Paso County, Colorado Pike National Forest and Colorado Springs Utilities Owned Land Report prepared by: Eric Billmeyer Executive Director Rocky Mountain

More information

Shelf Road Recreation Area 2015 BLM Annual Report of Rocky Mountain Field Institute Stewardship Under BLM Agreement L12AC20483 November 19, 2015

Shelf Road Recreation Area 2015 BLM Annual Report of Rocky Mountain Field Institute Stewardship Under BLM Agreement L12AC20483 November 19, 2015 Summary Shelf Road Recreation Area 2015 BLM Annual Report of Rocky Mountain Field Institute Stewardship Under BLM Agreement L12AC20483 November 19, 2015 Managed by the BLM Royal Gorge Field Office, Shelf

More information

Bear Creek Watershed Restoration Project Final Project Report December 21, 2016

Bear Creek Watershed Restoration Project Final Project Report December 21, 2016 Bear Creek Watershed Restoration Project Final Project Report December 21, 2016 Dedicated to the conservation and stewardship of public lands in Southern Colorado Rocky Mountain Field Institute 815 South

More information

South Colony Basin Recreation Fee Proposal

South Colony Basin Recreation Fee Proposal South Colony Basin Recreation Fee Proposal Purpose and Need for Collecting Fees in South Colony Basin: Forest Service appropriated funds have not been sufficient to maintain current recreational services

More information

Volunteer Project Trip Report Yosemite National Park May 16-20, 2012

Volunteer Project Trip Report Yosemite National Park May 16-20, 2012 Conservation Volunteers International Program 120 Village Square #9 Orinda, California 94563 USA www.conservationvip.org A Non-Profit 501c3 Tax Exempt Organization CST 2089890-40 Volunteer Project Trip

More information

Appendix C. Tenderfoot Mountain Trail System. Road and Trail Rehabilitation Plan

Appendix C. Tenderfoot Mountain Trail System. Road and Trail Rehabilitation Plan Appendix C Tenderfoot Mountain Trail System Road and Trail Rehabilitation Plan All rehabilitation work would be under the direction of the District Fisheries Biologist, the Forest Hydrologist, and/or the

More information

Non-motorized Trail Plan & Proposal. August 8, 2014

Non-motorized Trail Plan & Proposal. August 8, 2014 Town of Star Valley Ranch, Wyoming and the Star Valley Ranch Association in partnership with the USDA Forest Service, Bridger-Teton National Forest, Greys River Ranger District Non-motorized Trail Plan

More information

American Conservation Experience

American Conservation Experience ACE Project Report For Tonto National Forest, Arizona Trail Association and Arizona State Parks Title of Project: 4 Peaks Trail Maintenance Award Contract Number: ASP NM11021 Project Partner: Paul Burghard

More information

DECISION MEMO North Zone (Legacy Trails) Trail Stabilization Project

DECISION MEMO North Zone (Legacy Trails) Trail Stabilization Project DECISION MEMO North Zone (Legacy Trails) Trail Stabilization Project USDA FOREST SERVICE Rocky Mountain Region (R2) Shoshone National Forest Wapiti and Greybull Ranger District Park County, Wyoming Background

More information

Volunteer Project Report for May 14-20, 2017 Yosemite National Park Volunteer Trip. Executive Summary

Volunteer Project Report for May 14-20, 2017 Yosemite National Park Volunteer Trip. Executive Summary 120 Village Square #9, Orinda, California 94563 www.conservationvip.org info@conservationvip.org Tel: (925) 228-5946 A Non-Profit 501c3 Tax Exempt Organization Volunteer Project Report for May 14-20, 2017

More information

Colorado Mountain Club 2015 Stewardship Team Program Accomplishments

Colorado Mountain Club 2015 Stewardship Team Program Accomplishments Summary In 2015, CMC launched a new Stewardship Team program and hired a crew of young (25 and under), natural resource professionals to increase capacity of public land management agencies and coordinate

More information

COLORADO FOURTEENERS INITIATIVE 2009 ANNUAL REPORT

COLORADO FOURTEENERS INITIATIVE 2009 ANNUAL REPORT COLORADO FOURTEENERS INITIATIVE 2009 ANNUAL REPORT reconstruction maintenance education outreach finan COVER: Sunrise at South Sunlight Lake. Photo by Glenn Randall, www.glennrandall.com. THIS PAGE: Lone

More information

2019 Work Week Crew. Schedule and Descriptions

2019 Work Week Crew. Schedule and Descriptions 2019 Work Week Crew WAWONA WW1 Mariposa Grove Restoration and Invasive Plant Removal June 2 June 8 YOSEMITE VALLEY YV1 Washington Column Climber s Trail Rehabilitation June 9 June 15 YV2 Weed Warriors/

More information

Route #1) Mt. of the Holy Cross - North Ridge

Route #1) Mt. of the Holy Cross - North Ridge Climbing 14ers can be very dangerous, please read the Mountaineering Safety Page and make sure you have a map+compass and can use them effectively, without the help of electronic devices. Route #1) Mt.

More information

Trail Assessment Report

Trail Assessment Report Trail Assessment Report Trail Options for the Bear Creek Canyon located in Pikes Peak Ranger District, Pike National Forest and on Colorado Springs Utility Lands Due to the presence of a unique species

More information

Youth Corps Project Report BUREAU OF LAND MANAGEMENT COLORADO STATE OFFICE

Youth Corps Project Report BUREAU OF LAND MANAGEMENT COLORADO STATE OFFICE Youth Corps Project Report BUREAU OF LAND MANAGEMENT COLORADO STATE OFFICE FISCAL YEAR 2013 Colorado Youth Corps Association www.cyca.org 1 Table of Contents Program Summary 3 Individual Project Summaries

More information

APPENDIX D: SUSTAINABLE TRAIL DESIGN. APPENDICES Town of Chili Parks and Recreation Master Plan Update

APPENDIX D: SUSTAINABLE TRAIL DESIGN. APPENDICES Town of Chili Parks and Recreation Master Plan Update APPENDIX D: SUSTAINABLE TRAIL DESIGN APPENDICES Town of Chili Parks and Recreation Master Plan Update Sustainable Trail Construction Sustainable trails are defined by the US Forest Service as trails having

More information

HIKING IN THE CANADIAN ROCKIES

HIKING IN THE CANADIAN ROCKIES HIKING IN THE CANADIAN ROCKIES Distance Time Elevation y MORAINE LAKE TRAILS THE ROCKPILE 0.8 km (0.5 mi) 20 min 30 m (98 ft) Located adjacent to the Lodge, the short interpretive trail up the Rock Pile

More information

Understanding user expectations And planning for long term sustainability 1

Understanding user expectations And planning for long term sustainability 1 Understanding user expectations And planning for long term sustainability 1 What is a natural surface trail? It can be as simple has a mineral soil, mulched or graveled pathway, or as developed as elevated

More information

ROAD AND TRAIL PROJECT APPROVAL

ROAD AND TRAIL PROJECT APPROVAL ROAD AND TRAIL PROJECT APPROVAL www.marincountyparks.org Marin County Parks, 3501 Civic Center Dr, Suite 260, San Rafael, CA 94903 DATE: July 12, 2017 PRESERVE: Gary Giacomini Open Space Preserve PROJECT:

More information

Bear Creek Watershed Restoration Project Final Project Report December 21, 2017

Bear Creek Watershed Restoration Project Final Project Report December 21, 2017 Bear Creek Watershed Restoration Project 2017 Report 1 Bear Creek Watershed Restoration Project Final Project Report December 21, 2017 Dedicated to the conservation and stewardship of public lands in Southern

More information

Sierra National Forest 2015 Wilderness Program Accomplishment Report

Sierra National Forest 2015 Wilderness Program Accomplishment Report Sierra National Forest 2015 Wilderness Program Accomplishment Report The Sierra National Forest wilderness program provided stewardship and trail maintenance in the Ansel Adams, Dinkey Lakes, John Muir,

More information

Trail Phasing Plan. Note: Trails in the Clear Creek Canyon area (Segments will be finalized in the future to minimize wildlife impacts

Trail Phasing Plan. Note: Trails in the Clear Creek Canyon area (Segments will be finalized in the future to minimize wildlife impacts Note: Trails in the Clear Creek Canyon area (Segments 2 5 and a future JCOS connection) will be finalized in the future to minimize wildlife impacts Trail Phasing Plan P Parking 3 Easy Trail Intermediate

More information

Preferred Recreation Recommendations Stemilt-Squilchuck Recreation Plan March 2018

Preferred Recreation Recommendations Stemilt-Squilchuck Recreation Plan March 2018 Preferred Recreation Recommendations Stemilt-Squilchuck Recreation Plan March 2018 Below are the recommended recreation ideas and strategies that package together the various recreation concepts compiled

More information

Acadia National Park. Waterman Fund Grant Report 2016 Cadillac Mountain South Ridge Trail Rehabilitation. Acadia National Park

Acadia National Park. Waterman Fund Grant Report 2016 Cadillac Mountain South Ridge Trail Rehabilitation. Acadia National Park Acadia National Park National Park Service U.S. Department of the Interior Natio n alpar kser vic e U. S. Depar tm en t o f the In ter io r Waterman Fund Grant Report 2016 Cadillac Mountain South Ridge

More information

SEGMENT ASSESSMENT REPORT

SEGMENT ASSESSMENT REPORT 2017 SEGMENT ASSESSMENT REPORT SEGMENT 3: MT ROSE / TAHOE MEADOWS TO SPOONER SUMMIT REPORT SUMMARY This report is a compilation of information collected on the Tahoe Rim Trail during assessments performed

More information

USDA Trails Strategy WRI: ENGLISH PEAK SURVEY. Theodore Mendoza San Diego State University June 6 th 2016 August 18 th Advisor: Sam Commarto

USDA Trails Strategy WRI: ENGLISH PEAK SURVEY. Theodore Mendoza San Diego State University June 6 th 2016 August 18 th Advisor: Sam Commarto WRI: ENGLISH PEAK SURVEY Theodore Mendoza San Diego State University June 6 th 2016 August 18 th 2016 Advisor: Sam Commarto Klamath National Forest Submitted: March 21, 2017 Table of Contents Acknowledgements

More information

Mission. Purpose. Idaho Trails Association promotes the continued enjoyment of Idaho s hiking trails.

Mission. Purpose. Idaho Trails Association promotes the continued enjoyment of Idaho s hiking trails. The Idaho Trails Association (ITA) is a non-profit 501(c)3. Mission Idaho Trails Association promotes the continued enjoyment of Idaho s hiking trails. Purpose To facilitate the active enjoyment of Idaho

More information

STONE MOUNTAIN PROVINCIAL PARK Purpose Statement and Zoning Plan

STONE MOUNTAIN PROVINCIAL PARK Purpose Statement and Zoning Plan 1 STONE MOUNTAIN PROVINCIAL PARK Purpose Statement and Zoning Plan Stone Mountain Provincial Park is situated 140 km west of Fort Nelson at Kilometre 595 of the Alaska Highway. The 25 690 ha park is located

More information

Exhibit A Section 2 Large Application Selection Criteria

Exhibit A Section 2 Large Application Selection Criteria Exhibit A Section 2 Large Application Selection Criteria LARGE APPLICANT INFORMATION Applicant or Organization Name: Colorado Fourteeners Initiative Mailing Address: 1600 Jackson St, Suite 352, Golden

More information

Trail Beginning Elevation: 7553 ft The Poison Creek Trailhead is located at the end of National Forest Road 646E (NF-646E).

Trail Beginning Elevation: 7553 ft The Poison Creek Trailhead is located at the end of National Forest Road 646E (NF-646E). West Mountain Trails Poison Creek Trail #134 Length: 2.9 miles (4.7 km) Difficulty Horseback: A good trail for the first time west mountain rider, some steep sections Hiking: Most Difficult USGS Maps:

More information

April 19-21, See below for Course Descriptions. Columbia Cascades Trail Skills College Cascades Locks, Oregon.

April 19-21, See below for Course Descriptions. Columbia Cascades Trail Skills College Cascades Locks, Oregon. Columbia Cascades Trail Skills College Cascades Locks, Oregon April 19-21, 2013 Friday, April 19 198, 199 First Aid and CPR 300 Basic Rock Work 302 Water Crossings and Seeps 398 Working with Pack Stock

More information

Stein Valley Nlaka pamux Heritage Park

Stein Valley Nlaka pamux Heritage Park Stein Valley Nlaka pamux Heritage Park - Trail Information Update and Winter Advisory November 2017 March 2018 Welcome to Stein Valley Nlaka pamux Heritage Park! **This trail update is to inform park users

More information

USDA TRAILS STRATEGY PROGRAM

USDA TRAILS STRATEGY PROGRAM USDA TRAILS STRATEGY PROGRAM WRPI Program: English Peak Survey Jorge D. Briceño Southwestern Community College Internship Time Period: June 6, 2016 August 8, 2016 Advisor: Sam Commarto Recreation Officer

More information

Restore and implement protected status that is equivalent, or better than what was lost during the mid-1990 s

Restore and implement protected status that is equivalent, or better than what was lost during the mid-1990 s THE ROSSLAND RANGE, OLD GLORY AREA. Executive summary. The Friends of the Rossland Range Society, on behalf of the local outdoor community, seeks to accomplish the following with respect to the Old Glory

More information

Itinerary Overview. Sangre de Cristo Alpine Backpacking 22 days Ages Course Description

Itinerary Overview. Sangre de Cristo Alpine Backpacking 22 days Ages Course Description Itinerary Overview Sangre de Cristo Alpine Backpacking 22 days Ages 16-18 Course Description Welcome, you re in for an experience of a lifetime! Imagine hiking through rolling forests, sharing alpine meadows

More information

US Forest Service Bears Ears Trail - NFST 1144 California Park to Hole in Wall Creek. Good (1) 2 3

US Forest Service Bears Ears Trail - NFST 1144 California Park to Hole in Wall Creek. Good (1) 2 3 Trail Maintenance Endowment Fund Trail Criteria Form The Trail Maintenance Endowment Fund (TMEF) grant criteria form is used in determining the use of funds available on an annual basis. Decisions on how

More information

The Chu property is a 6.57 acre parcel located in the Town of Superior on the west side of McCaslin Boulevard. In 2014, the Town of Superior acquired

The Chu property is a 6.57 acre parcel located in the Town of Superior on the west side of McCaslin Boulevard. In 2014, the Town of Superior acquired 1 The Chu property is a 6.57 acre parcel located in the Town of Superior on the west side of McCaslin Boulevard. In 2014, the Town of Superior acquired the Chu property for open space with a contribution

More information

Adopt a Trail Blue Ridge Parkway

Adopt a Trail Blue Ridge Parkway Adopt a Trail Blue Ridge Parkway THANK YOU Thank You for volunteering to maintain a trail with the Adopt-A-Trail program! You are helping to keep these trails open for public use and enjoyment. We couldn

More information

GOLDEN EARS PROVINCIAL PARK

GOLDEN EARS PROVINCIAL PARK GOLDEN EARS PROVINCIAL PARK Trail Information as of October 10 th 2015 Do not underestimate the mountainous wilderness of Golden Ears Provincial Park. The combination of rugged terrain and rapidly changing

More information

Appendix A Appendix A (Project Specifications) Auk Auk / Black Diamond (Trail 44) Reroute

Appendix A Appendix A (Project Specifications) Auk Auk / Black Diamond (Trail 44) Reroute Appendix A (Project Specifications) Auk Auk / Black Diamond (Trail 44) Reroute I. Proposed Action: This project proposes to reroute approximately 1,800 feet of a 50 inch wide trail, off of private property

More information

DECISION MEMO. Rawhide Trail #7073 Maintenance and Reconstruction

DECISION MEMO. Rawhide Trail #7073 Maintenance and Reconstruction Page 1 of 6 Background DECISION MEMO USDA Forest Service Jefferson Ranger District Jefferson County, Montana Rawhide Trail #7073 is located in the Elkhorn Mountain Range approximately 10 miles east of

More information

CIEC 9 PEAKS AWARD SUPPLEMENT POSSIBLE ROUTES FOR THE 9 PEAKS AWARD TRIP

CIEC 9 PEAKS AWARD SUPPLEMENT POSSIBLE ROUTES FOR THE 9 PEAKS AWARD TRIP CIEC 9 PEAKS AWARD SUPPLEMENT POSSIBLE ROUTES FOR THE 9 PEAKS AWARD TRIP As you plan your trip, be aware of 3 regulations in this wilderness: 1. Camp only in designated campsites. 2. No campfires allowed.

More information

Finn Creek Park. Management Direction Statement Amendment

Finn Creek Park. Management Direction Statement Amendment Finn Creek Park Management Direction Statement Amendment November 2013 Management Direction Statement Amendment Approved by: Jeff Leahy Regional Director, Thompson Cariboo BC Parks November 12, 2013 Date

More information

Rocky Mountain Field Institute City of Colorado Springs Open Space Stewardship Services (TOPS) Contract #C Annual Project Report

Rocky Mountain Field Institute City of Colorado Springs Open Space Stewardship Services (TOPS) Contract #C Annual Project Report City of Colorado Springs Open Space Stewardship Services (TOPS) Contract #C008169 2017 Annual Project Report January 4, 2018 Report prepared by: Hannah Millsap, Field Instructor 815 South 25th Street,

More information

Rocky Mountain Field Institute

Rocky Mountain Field Institute Rocky Mountain Field Institute Palmer Park Stewardship Project 2016 Annual Project Report December 20, 2016 Report prepared by: Andy Riter, Program Coordinator and Alex Hladkyj, Field Instructor 815 South

More information

Cultural Resource Management Report Deer Valley 4wd Restoration and Blue Lakes Road Maintenance Project R

Cultural Resource Management Report Deer Valley 4wd Restoration and Blue Lakes Road Maintenance Project R Cultural Resource Management Report R2015-05-03-10005 Undertaking Description: The proposes to perform road maintenance and meadow restoration on the Deer Valley 4wd trail and road maintenance on the Blue

More information

INTRODUCTION. Mailing address: Burke County Community Development Attn: Tim Johnson P. O. Box 219 Morganton, NC

INTRODUCTION. Mailing address: Burke County Community Development Attn: Tim Johnson P. O. Box 219 Morganton, NC REQUEST FOR QUALIFICATIONS: PROFESSIONAL, EXPERIENCED TRAIL BUILDERS FOR THE CONSTRUCTION OF THE FONTA FLORA STATE TRAIL LAKE JAMES SECTION BURKE COUNTY COMMUNITY DEVELOPMENT INTRODUCTION Burke County

More information

Coast to Crest Trail Corridor Hike

Coast to Crest Trail Corridor Hike Coast to Crest Trail Corridor Hike Jim Cunningham, Poway City Council member and Board Chair of the San Dieguito River Park in 2013 has embarked on a project to hike the entire 70-mile San Dieguito River

More information

Table of Contents. page 3 Long term Goals Project Scope Project History. 4 User Groups Defined Trail Representative Committee. 5 Trail Users Breakdown

Table of Contents. page 3 Long term Goals Project Scope Project History. 4 User Groups Defined Trail Representative Committee. 5 Trail Users Breakdown Launched April 27th, 2010 1 Table of Contents page 3 Long term Goals Project Scope Project History 4 User Groups Defined Trail Representative Committee 5 Trail Users Breakdown 13 Trail Users Desires 16

More information

Port Gamble Shoreline Area Conceptual Trail Proposal

Port Gamble Shoreline Area Conceptual Trail Proposal The North Kitsap Trails Association is pleased to be a partner to the Kitsap Forest and Bay Project and assist Kitsap County, Forterra, Olympic Property Group, Great Peninsula Conservancy and the Port

More information

Rocky Mountain Field Institute Garden of the Gods Community Restoration Program 2015 Annual Project Report

Rocky Mountain Field Institute Garden of the Gods Community Restoration Program 2015 Annual Project Report Garden of the Gods Community Restoration Program 2015 Annual Project Report December 18 th, 2015 Report prepared by: Mark Tatro, Field Instructor 815 South 25 th Street, Suite 101 Colorado Springs, CO

More information

Rocky Mountain Youth Corps Garfield County Conservation Corps Crews Final Report 2013

Rocky Mountain Youth Corps Garfield County Conservation Corps Crews Final Report 2013 Rocky Mountain Youth Corps Garfield County Conservation Corps Crews Final Report 2013 Rock wall construction with gabion baskets, East Elk 2013 RMYC Garfield County Crews - End of Session Rocky Mountain

More information

Recreation News. Welcome. Chris Jackson. In this Issue: O S U C o l l e ge F o r e s t s

Recreation News. Welcome. Chris Jackson. In this Issue: O S U C o l l e ge F o r e s t s Recreation News O S U C o l l e ge F o r e s t s In this Issue: Welcome New tree identification posts... New Arboretum Trails New Interpretive Signs Ridge Trail Seasonal Closures Leave No Trace reminder

More information

Itinerary Overview. Colorado San Juan Mountaineering 15-days

Itinerary Overview. Colorado San Juan Mountaineering 15-days Itinerary Overview Colorado San Juan Mountaineering 15-days Course Description Welcome, you re in for an experience of a lifetime! Imagine hiking through rolling forests, sharing alpine meadows with mountain

More information

FINAL TESTIMONY 1 COMMITTEE ON RESOURCES UNITED STATES HOUSE OF REPRESENTATIVES. July 13, 2005 CONCERNING. Motorized Recreational Use of Federal Lands

FINAL TESTIMONY 1 COMMITTEE ON RESOURCES UNITED STATES HOUSE OF REPRESENTATIVES. July 13, 2005 CONCERNING. Motorized Recreational Use of Federal Lands FINAL TESTIMONY 1 STATEMENT OF DALE BOSWORTH CHIEF Of the FOREST SERVICE UNITED STATES DEPARTMENT OF AGRICULTURE Before the SUBCOMMITTEE ON FORESTS AND FOREST HEALTH And the SUBCOMMITTEE ON NATIONAL PARKS,

More information

Four Fourteeners in One Day

Four Fourteeners in One Day Mt. Democrat: Summit: 14, 148 Mt. Cameron: Summit: 14,050 Mt. Lincoln: Summit: 14,286 Mt. Bross: Summit: 14,172 Four Fourteeners in One Day Trailhead: Trailhead Elev.: Total Elevation Gain: Roundtrip:

More information

Itinerary Overview: What you will be doing Maroon Bells Alpine Backpacking 22 days

Itinerary Overview: What you will be doing Maroon Bells Alpine Backpacking 22 days Itinerary Overview: What you will be doing Maroon Bells Alpine Backpacking 22 days 0BCourse Description Welcome, you re in for an experience of a lifetime! Imagine hiking through rolling forests, sharing

More information

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM Backcountry Trail Flood Rehabilitation A June 2013 Flood Recovery Program Summary In June 2013, parts of Southern Alberta were devastated from significant

More information

Bob Marshall Wilderness Foundation

Bob Marshall Wilderness Foundation About the Bob Marshall Wilderness Complex Considered by many to be the crown jewel of the wilderness preservation system, the Bob Marshall Wilderness Complex located in Northwestern Montana, is the third

More information

Great Pond Mountain Conservation Trust Request for Bids Wildlands Hillside Trail Relocation and Restoration Project

Great Pond Mountain Conservation Trust Request for Bids Wildlands Hillside Trail Relocation and Restoration Project Great Pond Mountain Conservation Trust Request for Bids Wildlands Hillside Trail Relocation and Restoration Project Project Description: Great Pond Mountain Conservation Trust (GPMCT), a nonprofit land

More information

PROPOSED PARK ALTERNATIVES

PROPOSED PARK ALTERNATIVES 8 Chimne y Rock State Park M a ster Pl an 2011 PROPOSED PARK ALTERNATIVES Introduction Three different park development concepts were prepared and presented to the citizens of North Carolina through a

More information

PRESS RELEASE VIOLET CROWN TRAIL OPENS, RALLYING COMMUNITY TO TAKE ACTION

PRESS RELEASE VIOLET CROWN TRAIL OPENS, RALLYING COMMUNITY TO TAKE ACTION PRESS RELEASE CONTACT: Nico D Auterive O: 512-328-2481, Ext. 202 M: 347-282-8425 E: nico@hillcountryconservancy.org Ashley Kegley-Whitehead O: 512-482-8693 M: 512-660-2898 E: ashley@buieco.com For Immediate

More information

2.0 PARK VISION AND ROLES

2.0 PARK VISION AND ROLES 2.0 PARK VISION AND ROLES 2.1 Significance in the Protected Area System Marble Range and Edge Hills provincial parks protect 6.8% of the Pavillion Ranges Ecosection, which is located in the Southern Interior

More information

GREENWOOD VEGETATION MANAGEMENT

GREENWOOD VEGETATION MANAGEMENT APPENDIX G GREENWOOD VEGETATION MANAGEMENT PROJECT RECREATION RESOURCE REPORT Prepared by: Laurie A. Smith Supervisory Forester Stearns Ranger District Daniel Boone National Forest August 4, 2016 The

More information

Fixed Anchors. Non-Wilderness Management Areas

Fixed Anchors. Non-Wilderness Management Areas Access Fund-Carolina Climbers Coalition Proposals Submitted for Consideration and Support to the National Forest Forum and Nantahala- Pisgah Forest Partnership July 25, 2017, Updated July 28, 2017 Fixed

More information

Willow Creek Horse Camp Reconstruction

Willow Creek Horse Camp Reconstruction Performance Period: 04/15/2017-12/31/2017 The following is a summary of hours and work completed on the Black Hills National Forest and other public lands during the reporting period for 2017 by the Black

More information

Stephens State Park Trails

Stephens State Park Trails TRAILS OF ALLAMUCHY MOUNTAIN & STEPHENS STATE PARKS Allamuchy Mountain and Stephens State Parks contain 28 marked trails providing access to diverse landscapes for walking, hiking, biking, bird-watching,

More information

LEAVE NO TRACE CENTER FOR OUTDOOR ETHICS CONSULTING SERVICES

LEAVE NO TRACE CENTER FOR OUTDOOR ETHICS CONSULTING SERVICES LEAVE NO TRACE CENTER FOR OUTDOOR ETHICS CONSULTING SERVICES LEAVE NO TRACE PURPOSE Americans love the outdoors. Today, more than 300 million people visit America s national parks and another 150 million

More information

National Forests and Grasslands in Texas

National Forests and Grasslands in Texas United States Department of Agriculture Forest Service National Forests and Grasslands in Texas Sam Houston NF 394 FM 1375 West New Waverly, Texas 77358 Phone 936-344-6205 Dear Friends, File Code: 1950

More information

Route Combo) Mt. Bierstadt - Bierstadt, Sawtooth, Evans

Route Combo) Mt. Bierstadt - Bierstadt, Sawtooth, Evans Climbing 14ers can be very dangerous, please read the Mountaineering Safety Page and make sure you have a map+compass and can use them effectively, without the help of electronic devices. Route Combo)

More information

City of Durango 5.8 FUNDING TRAILS DEVELOPMENT

City of Durango 5.8 FUNDING TRAILS DEVELOPMENT 5.8 FUNDING TRAILS DEVELOPMENT The City has been successful in establishing dedicated local funding sources as well as applying for grants to develop the City s trail system, having received nearly $2.4

More information

Photopoint Monitoring in the Adirondack Alpine Zone

Photopoint Monitoring in the Adirondack Alpine Zone Photopoint Monitoring in the Adirondack Alpine Zone Julia Goren (PI) and Seth Jones Adirondack High Peaks Summit Steward Program Adirondack Mountain Club summit@adk.org PO Box 867, Lake Placid, NY 12946

More information

playwinterpark.com Off The Beaten Path Hikes Hiking Recommendations for the Adventurous Hiker

playwinterpark.com Off The Beaten Path Hikes Hiking Recommendations for the Adventurous Hiker playwinterpark.com Off The Beaten Path Hikes Hiking Recommendations for the Adventurous Hiker Hike: Devil s Thumb (difficult) Length: 3.93 miles one-way Elevation: Trailhead 9609 Destination 12,236 Trailhead

More information

Itinerary Overview. Maroon Bells Mountaineering 22-days. Course Description

Itinerary Overview. Maroon Bells Mountaineering 22-days. Course Description Itinerary Overview Maroon Bells Mountaineering 22-days Course Description Welcome, you re in for an experience of a lifetime! Imagine hiking through rolling forests, sharing alpine meadows with mountain

More information

Route #2) Mt. Massive - Southwest Slopes

Route #2) Mt. Massive - Southwest Slopes Route #2) Mt. Massive - Southwest Slopes Difficulty: Class 2 Ski: Advanced, D6 / R2 / III Exposure: Summit Elevation: Trailhead Elevation: Elevation Gain: Round-trip Length: Trailhead: County Sheriff:

More information

Course 102. Tread and Drainage

Course 102. Tread and Drainage PCTA Trail Skills College Curriculum Instructor Planning Guide Water and gravity constantly threaten our trails and thus we must learn how best to deflect them. This course begins with basics of hillside

More information

Understanding the caring capacity of the visitor experience Provide facilities to support a high level user experience Address visual quality through

Understanding the caring capacity of the visitor experience Provide facilities to support a high level user experience Address visual quality through Understanding the caring capacity of the visitor experience Provide facilities to support a high level user experience Address visual quality through recreation ecological restoration opportunities Collaboration

More information

Assessing Your Trails, Keeping Them Safe and Enjoyable

Assessing Your Trails, Keeping Them Safe and Enjoyable Jon Wood, PLA, ASLA Associate Vice President Stewart Bert Lynn, PLA, ASLA, LEED AP Project Manager Mecklenburg County Asset and Facility Management Assessing Your Trails, Keeping Them Safe and Enjoyable

More information

RE: Access Fund Comments on Yosemite National Park Wilderness Stewardship Plan, Preliminary Ideas and Concepts

RE: Access Fund Comments on Yosemite National Park Wilderness Stewardship Plan, Preliminary Ideas and Concepts September 30, 2016 Superintendent Yosemite National Park Attn: Wilderness Stewardship Plan P.O. Box 577 Yosemite, CA 95389 RE: Access Fund Comments on Yosemite National Park Wilderness Stewardship Plan,

More information

Kennesaw Mountain Trail Club. Trail Skills Workshop ~ Dips and Drains. Presented by: Jay M Dement

Kennesaw Mountain Trail Club. Trail Skills Workshop ~ Dips and Drains. Presented by: Jay M Dement Kennesaw Mountain Trail Club Trail Skills Workshop ~ Dips and Drains Presented by: Jay M Dement KEY CONCEPTS: Control Erosion and Users Where Do Trails Come From, and How Do They Work: Concept of trail

More information

Outdoor Recreation Opportunities Management

Outdoor Recreation Opportunities Management Outdoor Recreation Opportunities Management Introduction The natural features of Height of the Rockies and Elk Lakes provincial parks provide a wide variety of outdoor recreational activities. However,

More information

Bibbulmun Track. Cape to Cape Track. Two of the world s great long distance walking tracks. 973 km. 135 km km Off-road cycle touring

Bibbulmun Track. Cape to Cape Track. Two of the world s great long distance walking tracks. 973 km. 135 km km Off-road cycle touring Trail revitalising Western Australia Bibbulmun Track 973 km Cape to Cape Track 135 km Two of the world s great long distance walking tracks 1062 km Off-road cycle touring Trail revitalising 1. Framework

More information

BACKGROUND DECISION. Decision Memo Page 1 of 6

BACKGROUND DECISION. Decision Memo Page 1 of 6 DECISION MEMO DEVIL S ELBOW BY-PASS, BOUNDARY TRAIL NO.1 U.S. FOREST SERVICE T9N, R7E, SECTION 9 RANGE 5E COWLITZ COUNTY WA MOUNT ST. HELENS NATIONAL VOLCANIC MONUMENT, GIFFORD PINCHOT NATIONAL FOREST

More information

Project Report Yosemite National Park Volunteer Trip September 9-15, 2018

Project Report Yosemite National Park Volunteer Trip September 9-15, 2018 Project Report Yosemite National Park Volunteer Trip September 9-15, 2018 Executive Summary Fourteen volunteers including two trip leaders from Conservation Volunteers International Program (ConservationVIP

More information

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library EAST DON TRAIL ENVIRONMENTAL ASSESSMENT Community Liaison Committee Meeting #3 July 15, 2013 6:30 to 8:30 pm Flemingdon Park Library Agenda 1. Welcome 2. Housekeeping and Updates a) Housekeeping b) CLC

More information

Opportunities for Solitude in Salt Lake Ranger District Wilderness Areas; Uinta-Wasatch-Cache National Forest

Opportunities for Solitude in Salt Lake Ranger District Wilderness Areas; Uinta-Wasatch-Cache National Forest Opportunities for Solitude in Salt Lake Ranger District Wilderness Areas; Uinta-Wasatch-Cache National Forest Prepared by: Henry Lilly (graduate research assistant) Jeff Rose (co-investigator) Matthew

More information

Appendix A. Tenderfoot Mountain Motorcycle Trail System. Maintenance and Construction Plan (6/13/13)

Appendix A. Tenderfoot Mountain Motorcycle Trail System. Maintenance and Construction Plan (6/13/13) Appendix A Tenderfoot Mountain Motorcycle Trail System Maintenance and Construction Plan (6/13/13) If the decision to implement the project as approved, grant funding would be pursued to fund construction

More information

2016 Trails Maintenance and Operating Costs

2016 Trails Maintenance and Operating Costs 2016 Trails Maintenance and Operating Costs Motorized Trails Maintenance for motorized trails comes from vehicle registration fees and a portion of the federal Recreation Trails Program (RTP) funds. The

More information

Franklin Falls. NFCT Waterway Work Trip July Introduction: Driving directions and meeting location: Camping and lodging: Food:

Franklin Falls. NFCT Waterway Work Trip July Introduction: Driving directions and meeting location: Camping and lodging: Food: Franklin Falls NFCT Waterway Work Trip July 16-18 Introduction: Last year the NFCT Stewardship Interns and Volunteers installed approximately 20 stone steps on the Permanent Rapids Carry. We also planted

More information

L U N C H C R E E K T R A I L GLACIER NATIONAL PARK

L U N C H C R E E K T R A I L GLACIER NATIONAL PARK D I R T I N M Y S H O E S L U N C H C R E E K T R A I L GLACIER NATIONAL PARK Lunch Creek "Secret" Hike This short hike on the Lunch Creek Trail will knock your socks off! It's the perfect mix of length,

More information

Rocky Mountain Field Institute Garden of the Gods Community Restoration Program 2017 Annual Project Report

Rocky Mountain Field Institute Garden of the Gods Community Restoration Program 2017 Annual Project Report 1 Garden of the Gods Community Restoration Program 2017 Annual Project Report December 21, 2017 Report prepared by: Kelly Kaufmann, Senior Field Coordinator 815 South 25 th Street, Suite 101 Colorado Springs,

More information

colorado fourteeners initiative annual report 2012

colorado fourteeners initiative annual report 2012 colorado fourteeners initiative annual report 2012 Letter from the executive director Last year Colorado Fourteeners Initiative completed another year of record accomplishment in the field coupled with

More information

Itinerary Overview. Continental Divide Alpine Backpacking 22 days Ages Course Description

Itinerary Overview. Continental Divide Alpine Backpacking 22 days Ages Course Description Itinerary Overview Continental Divide Alpine Backpacking 22 days Ages 16-18 Course Description Welcome, you re in for an experience of a lifetime! Imagine hiking through rolling forests, sharing alpine

More information

Map 1.1 Wenatchee Watershed Land Ownership

Map 1.1 Wenatchee Watershed Land Ownership Map 1.1 Wenatchee Watershed Land Ownership Map 1.1 Wenatchee Watershed Land Ownership The Wenatchee watershed lies in the heart of Washington state in Chelan County. Just larger than the state of Rhode

More information

Margaret N. Rees University of Nevada, Las Vegas,

Margaret N. Rees University of Nevada, Las Vegas, Get Outdoors Nevada Public Lands Institute 6-30-2011 Nevada Interagency Volunteer Program: Helping Hands Across Public Lands Phase II: Quarterly Progress Report, Period Covering April 1, 2011-June 30,

More information

COASTAL CONSERVANCY. Staff Recommendation December 2, 2004 COYOTE HELLYER COUNTY PARK BAY AREA RIDGE TRAIL

COASTAL CONSERVANCY. Staff Recommendation December 2, 2004 COYOTE HELLYER COUNTY PARK BAY AREA RIDGE TRAIL COASTAL CONSERVANCY Staff Recommendation December 2, 2004 COYOTE HELLYER COUNTY PARK BAY AREA RIDGE TRAIL File No. 04-057 Project Manager: Amy Hutzel RECOMMENDED ACTION: Authorization to disburse up to

More information

Recreational Trails Program funded 32 projects equaling $1,282,737 in 2016

Recreational Trails Program funded 32 projects equaling $1,282,737 in 2016 Recreational Trails Program funded 32 projects equaling $1,282,737 in 2016 The following Recreational Trails Program projects have been approved by the Outdoor Recreational Trails Advisory Board, the Division

More information