MONTGOMERY COUNTY PUBLIC SCHOOLS BETHESDA-CHEVY CHASE MIDDLE SCHOOL #2 SAMAHA ASSOCIATES, PC

Size: px
Start display at page:

Download "MONTGOMERY COUNTY PUBLIC SCHOOLS BETHESDA-CHEVY CHASE MIDDLE SCHOOL #2 SAMAHA ASSOCIATES, PC"

Transcription

1

2 SITE B-CC MS #2

3 SITE ANALYSIS

4 PROGRAM

5 CONCEPT OPTIONS PRESENTED

6 DEVELOPED CONCEPT OPTIONS 4, 5, AND 6

7 FEASIBILITY STUDY PLAN OPTION 1

8 FEASIBILITY STUDY SITE SECTION OPTION 1

9 FEASIBILITY STUDY SITE SECTION OPTION 1

10 FEASIBILITY STUDY 3-D VIEW OPTION 1

11 FEASIBILITY STUDY 3-D VIEW OPTION 1

12 FEASIBILITY STUDY OPTION 1 ADVANTAGES: + Bus entry located at triangle intersection at Saul Road and Haverhill Drive, so it is not located directly in front of any houses. + Grade levels are organized by floor, one grade per floor (Grade 6, Grade 7 and Grade 8). + Activity spaces are separated from academic spaces. + The main entrance is easily identifiable. + Care taken to separate parent cars from buses and all vehicles from pedestrians on the school site. + Four Story building preserves more green space. + Administration is located at both entrances; main entrance and activity entrance. + Layout of softball and soccer fields is efficient. + Corridors surrounding core spaces enhances circulation within the building. + Staff/visitor parking is maximized as compared to the other options. + Car queuing space at the student drop-off is maximized as compared to the other options. + Playfields and courts are adjacent to each other for ease of monitoring students. DISADVANTAGES: - Staff/visitors parking less than maximum requirement (-20 spaces) may create traffic congestion in the community with on street parking. However at staffing for 836 students the initial parking requirement will be met. - Administration suite is on the lowest level, not as centralized as desired. - The main entrance is located at the beginning of the parent drop off area, possibly creating traffic congestion if cars do not pull forward. - Building parking lot on top of existing WSSC water main. - The community asserts that there is a safety concern with buses, parents, and pedestrians entering the site at Saul Road. - Retaining walls at the staff parking lot face the street. - Fourth story requires more expensive construction protected structure. - Future re-locatable classrooms would be located north of the bus area, where students have to go around the bus loop to get to the portables. - No courtyard - No natural light in the music suite.

13 FEASIBILITY STUDY PLAN OPTION 2

14 FEASIBILITY STUDY SITE SECTION OPTION 2

15 FEASIBILITY STUDY SITE SECTION OPTION 2

16 FEASIBILITY STUDY 3-D VIEW OPTION 2

17 FEASIBILITY STUDY 3-D VIEW OPTION 2

18 FEASIBILITY STUDY OPTION 2 ADVANTAGES: + Bus entry located at triangle intersection at Saul Road and Haverhill Drive, so it is not located directly in front of any houses. + Grade levels are organized by floor, one grade per floor (Grade 6, Grade 7 and Grade 8). + Activity spaces are separated from academic spaces. + The main entrance is easily identifiable. + Care taken to separate parent cars from buses and all vehicles from pedestrians on the school site. + The car and bus site access both utilize the existing curb cuts off Saul Road. + Four-story building preserves more green space. + Administration is located at both entrances; main entrance and activity entrance. + Courtyard enhances circulation within school building. + Courtyard provides natural light to all spaces including core spaces. + Smallest building footprint. DISADVANTAGES: -Staff/visitors parking less than maximum requirement (-25 spaces) may create traffic congestion in the community with on street parking. However at staffing for 836 students the initial parking requirement will be met. - Administration suite is on the lowest level, not as centralized as desired. - The main entrance is located at the beginning of the parent drop off area, possibly creating traffic congestion if cars do not pull forward. - Building parking lot on top of existing WSSC water main. - The community asserts that there is a safety concern with buses, parents, and pedestrians entering the site at Saul Road. - Retaining walls at the staff parking lot face the street. - Music suite below classrooms requires extra sound isolation. - Layout of softball and soccer fields not as efficient as option 1. - Fourth story requires more expensive construction protected structure.

19 FEASIBILITY STUDY PLAN OPTION 3

20 FEASIBILITY STUDY SITE SECTION OPTION 3

21 FEASIBILITY STUDY SITE SECTION OPTION 3

22 FEASIBILITY STUDY 3-D VIEW OPTION 3

23 FEASIBILITY STUDY 3-D VIEW OPTION 3

24 FEASIBILITY STUDY OPTION 3 ADVANTAGES: + Bus entry located at triangle intersection at Saul Road and Haverhill Drive, so it is not located directly in front of any houses. + Grade levels are organized by floor, one grade per floor (Grade 6, Grade 7 and Grade 8). + Activity spaces are separated from academic spaces. + The main entrance is easily identifiable. + Care taken to separate parent cars from buses and all vehicles from pedestrians on the school site. + The car and bus site access both utilize the existing curb cuts off Saul Road. + Layout of softball and soccer fields is efficient. + Playfields and courts are adjacent to each other for ease of monitoring students. + Courtyard enhances circulation within the school building. + Courtyard provides natural light to all spaces including core spaces. + All students enter the building at one location. + Administration can monitor the single entrance. + School is only three stories and may reduce travel time for students and staff. + Future re-locatable classrooms would be located close to the building. + Less massive building facing the streets and the ball fields. DISADVANTAGES: - Staff/visitors parking less than maximum requirement (-30 spaces) may create traffic congestion in the community with on street parking. However at staffing for 836 students the initial parking requirement will be met. - Administration suite is on the lowest level, not as centralized as desired. - The main entrance is located at the beginning of the parent drop off area, possibly creating traffic congestion if cars do not pull forward. - Building parking lot on top of existing WSSC water main. - The community asserts that there is a safety concern with buses, parents, and pedestrians entering the site at Saul Road. - Retaining walls at the staff parking lot face the street. - Sharp turns and steep grades for the buses leaving the bus area. - Bus loop runs parallel to Saul Road reducing buffer space that could provide landscape screening. - Building has the largest footprint, because it is three stories.

25 OPTIONS COMPARISON CHART Existing Ed Spec Westland Middle School Option 1 Option 2 Option 3 Tennis Courts Basketball Courts Softball Fields Soccer Field Sizes (yards) 65x105 65x x x100 (multi-use fields) 55x90 55x90 55x90 55x90 75x120 (overlapping) 55x90 55x90 75x120 (overlapping) 55x90 55x90 75x120 (overlapping) Buses n/a n/a Parking Spaces Overlaid Parking on Bus Loop n/a n/a Car Queuing n/a n/a Building SQFT n/a n/a n/a 153,000 SF 151,000 SF 155,000 SF Building Footprint n/a n/a 79,500 SF (+/-) 60,800 SF 53,900 SF 69,600 SF Courtyard n/a n/a 16,000SF n/a 4,500 SF 5,000 SF Future Addition n/a n/a n/a 6,000 SF 6,000 SF 6,000 SF

26 NEXT STEPS Superintendent s Recommended FY Capital Improvements Program (CIP) released Date October 28, 2011 Board of Education Work session to discuss CIP November 2, 2011 Board of Education Facilities Public Hearings* November 10 and 14, 2011 Board of Education Action on the FY CIP November 17, 2011 *To testify at the Board of Education Facilities Public Hearings on November 10 and 14, 2011, contact the Board of Education office at

27 QUESTIONS? Feasibility Study Schedule FSC #1 Wednesday, June 8, :00 pm FSC #2 Wednesday, June 22, :00 pm FSC #3 Wednesday, July 13, :00 pm FSC #4 Thursday, July 28, :00 pm FSC #5 Wednesday, August 10, :00 pm FSC #6 Wednesday, August 17, :00 pm Community Presentation Thursday, September 22, :00 pm

Mr. Ron Mancan Mr. Paul Falkenbury Samaha Associates

Mr. Ron Mancan Mr. Paul Falkenbury Samaha Associates August 15, 2011 TO: FROM: Montgomery County Public Schools Dennis Cross, AIA, Project Manager Samaha Associates, PC PROJECT: Bethesda - Chevy Chase Middle School #2 RE: Feasibility Study Meeting #5 August

More information

Transportation TRANSPORTATION PROJECTS

Transportation TRANSPORTATION PROJECTS Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William

More information

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis ITB MAIN TERMINAL DEPARTURES LEVEL & BOARDING AREAS A & G ALTERNATIVES ANALYSIS

More information

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,

More information

Stage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge

Stage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge Stage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge Public Consultation Centre (PCC) No. 3 Please Sign-in Cambridge City Hall November 21, 2017 2:00 to 8:00pm Preston Memorial Auditorium

More information

Traffic Management Plan 2018

Traffic Management Plan 2018 Traffic Management Plan 2018 Jesuit College Preparatory School of Dallas Amendment to Planned Development No. 353 Dallas, Texas June 6, 2018 Prepared for Jesuit College Preparatory School of Dallas Prepared

More information

Fuller/Fuller Heights Road Improvements

Fuller/Fuller Heights Road Improvements Fuller/Fuller Heights Road Improvements Total Project Cost - $4.4M Project Description This project will construct a mini-roundabout at the intersection of Fuller Heights Road and Old Triangle Road to

More information

TERMINAL DEVELOPMENT PLAN

TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN Key points The development plan in the Master Plan includes the expansion of terminal infrastructure, creating integrated terminals for international,

More information

M E S T I Z O C U R T I S P A R K

M E S T I Z O C U R T I S P A R K ARAPAHOE CONNECTION TO BUS ROUTE AT ND AND LAWRENCE, FUTURE LIGHT RAIL STATION LEGEND SOCIAL TRAIL FLAGSTONE PAVING TO RESTORE/MAINTAIN CONCRETE PAVING DIAGONAL CURVILINEAR SOCIAL ROUTE IS OUT OF HISTORIC

More information

Engagement Summary Report. Trans-Canada Highway 1 RW Bruhn Bridge Replacement Project. Community Engagement November 15, 2016 to January 15, 2017

Engagement Summary Report. Trans-Canada Highway 1 RW Bruhn Bridge Replacement Project. Community Engagement November 15, 2016 to January 15, 2017 Trans-Canada Highway 1 RW Bruhn Bridge Replacement Project Community Engagement November 15, 2016 to January 15, 2017 Engagement Summary Report February 2017 Prepared by Kirk & Co. Consulting Ltd. Trans-Canada

More information

Memorandum / Letter of Intent

Memorandum / Letter of Intent VERONA WAUKESHA KENOSHA APPLETON WESTON Memorandum / Letter of Intent To: Adam Sayre, Director of Planning & Development, City of Verona From: Kevin Yeska, JSD Professional Services, Inc. www.jsdinc.com

More information

FUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities

FUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities FUTURE PASSENGER PROCESSING ACRP 07-01 New Concepts for Airport Terminal Landside Facilities In association with: Ricondo & Associates, TransSolutions, TranSecure RESEARCH Background Research Objective

More information

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MCPB Item No. Date: 6/23/2016 Lucy V. Barnsley Elementary School Addition, Mandatory Referral MR2016027

More information

Building Level Planning Committee March 30, 2016

Building Level Planning Committee March 30, 2016 Arlington Public Schools Wilson School Site Evaluation Traffic Analysis and Pick-up/Drop-off location Building Level Planning Committee March 30, 2016 1 SAN ANTONIO-BEXAR COUNTY PEDESTRIAN SAFETY ACTION

More information

CHAPTER 4: ALTERNATIVES

CHAPTER 4: ALTERNATIVES MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the

More information

NFTA Access Enhancement Study for Canalside and Cobblestone Alternatives Discussion. Alternative A South Park Avenue

NFTA Access Enhancement Study for Canalside and Cobblestone Alternatives Discussion. Alternative A South Park Avenue Alternative A South Park Avenue Alternative A Summary Alternative A extends Metro Rail service around the foot of Main Street east along South Park Avenue to serve a new station platform located along

More information

NEWBORO AND PORTLAND HARBOUR REDVELOPMENT PLANS

NEWBORO AND PORTLAND HARBOUR REDVELOPMENT PLANS INTRODUCTION The Municipal docks in both Newboro and Portland were transferred to the Township of Rideau Lakes by Parks Canada in 2002. Little has been done to improve the docks physical condition or role

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9

More information

AVAILABLE FOR SALE ENTITLED 53,228 SF BUILDING FOR SALE Washington Dr., Fontana. Property Features:

AVAILABLE FOR SALE ENTITLED 53,228 SF BUILDING FOR SALE Washington Dr., Fontana. Property Features: Property Features: Free - Standing; Entitled 53,8 SF;,311 SF Office (3) Dock High Loading Rare, New Planned Wholesale Warehouse Corner Location (Live Oak Ave. & Washington Dr.) 1 Block South Of Valley

More information

Engagement Summary Report. Trans-Canada Highway 1 RW Bruhn Bridge and Approaches Project Community Engagement February 1 18, 2018.

Engagement Summary Report. Trans-Canada Highway 1 RW Bruhn Bridge and Approaches Project Community Engagement February 1 18, 2018. Trans-Canada Highway 1 RW Bruhn Bridge and Approaches Project Community Engagement February 1 18, 2018 Engagement Summary Report April 2018 Prepared by Kirk & Co. Consulting Ltd. Trans-Canada Highway 1

More information

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan

Buchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business Plan Steering Committee December 14, 2006 Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business

More information

Love Field Modernization Program Update: Master Planning Recommendations

Love Field Modernization Program Update: Master Planning Recommendations Love Field Modernization Program Update: Master Planning Recommendations Briefing to the Council Transportation and Environment Committee April 28, 2008 1 1 Briefing Objective Discuss the background and

More information

PIONEER PARK. City of Des Peres Parks Master Plan. SWT Design 46 INTRODUCTION

PIONEER PARK. City of Des Peres Parks Master Plan. SWT Design 46 INTRODUCTION PIONEER PARK INTRODUCTION Pioneer Park is a 7 acre neighborhood park located east of Interstate 270 and south of Manchester Road along Tallie Road. The park is situated in a residential neighborhood with

More information

Pioneer Events Center

Pioneer Events Center Planning Workshop for the Concept Design of the Pioneer Events Center Filer, Idaho May 3, 2014 With The Twin Falls County Fair Board and Staff By: Populous Architects / Planners David Forkner ASLA Principal

More information

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item.

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item. Committee Report Business Item No. 2017-191 Transportation Committee For the Metropolitan Council meeting of September 13, 2017 Subject: Final Crystal Airport 2035 Long Term Comprehensive Plan (LTCP) Proposed

More information

MARTA & City of Atlanta Sales Tax Referendums. Public Hearings May 25 & 26, 2016 June 1 & 2, 2016

MARTA & City of Atlanta Sales Tax Referendums. Public Hearings May 25 & 26, 2016 June 1 & 2, 2016 MARTA & City of Atlanta Sales Tax Referendums 1 MARTA & City of Atlanta Sales Tax Referendums Public Hearings May 25 & 26, 2016 June 1 & 2, 2016 MARTA & City of Atlanta Sales Tax Referendums 2 Guiding

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

Chapter 6. Action Program. Heart of the Lakes Area Recreation Plan

Chapter 6. Action Program. Heart of the Lakes Area Recreation Plan Heart of the Lakes Area Recreation Plan 1. Design and construct the following trails (please see the following map): a. the Speedway Trail 1) primary pathway the main trail 2) secondary pathway the proposed

More information

BNA Master Plan Update Community Advisory Committee Meeting No. 5

BNA Master Plan Update Community Advisory Committee Meeting No. 5 A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,

More information

BASSETTS CREEK SECTION CONTENTS: BASSETTS CREEK BRYN MAWR LUCE LINE

BASSETTS CREEK SECTION CONTENTS: BASSETTS CREEK BRYN MAWR LUCE LINE BASSETTS CREEK SECTION CONTENTS: BASSETTS CREEK BRYN MAWR LUCE LINE GLENWOOD AVE MULTI-USE DIAMONDS VINCENT AVE N MORGAN AVE N PENN AVE N DOG PARK MULTI-USE FIELDS PLAYGROUND AK E RD S CHESTNUT AVE DA

More information

Northwest Corridor LRT Line to Irving/DFW

Northwest Corridor LRT Line to Irving/DFW Northwest Corridor LRT Line to Irving/DFW AGENCY SCOPING May 25, 2005 NW to Irving/DFW Agenda: Introductions Project Development Process Project Update Federal Involvement Scoping Project Schedule Decisions

More information

To apprise Council of the process and timeline for the preparation of the Final Concept Plan and report; and

To apprise Council of the process and timeline for the preparation of the Final Concept Plan and report; and Corporate NO: R243 Report COUNCIL DATE: November 20, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: November 15, 2006 FROM: Acting General Manager, Planning and Development FILE: 0850-20 (CF) SUBJECT:

More information

SRTA Year End Fixed Route Ridership Analysis: FY 2018

SRTA Year End Fixed Route Ridership Analysis: FY 2018 SRTA Year End Fixed Route Ridership Analysis: FY 2018 2018 Contents Introduction... 1 A. Key Terms Used in this Report... 1 Key Findings... 2 A. Ridership... 2 B. Fare Payment... 4 Performance Analysis

More information

Update on Monarch Bay Shoreline Development Project. City Council Work Session October 9, 2017

Update on Monarch Bay Shoreline Development Project. City Council Work Session October 9, 2017 Update on Monarch Bay Shoreline Development Project { City Council Work Session October 9, 2017 Overview Monarch Bay Development Project 220 Room Hotel Public Amenities Monarch Bay Park, Pescador Park,

More information

Northwest Corridor LRT Line to Irving/DFW

Northwest Corridor LRT Line to Irving/DFW Northwest Corridor LRT Line to Irving/DFW SCOPING March 10, 2005 NW to Irving/DFW Agenda: Introductions Project Development Process Project Update Federal Involvement Scoping Project Schedule Decisions

More information

Frederickson LUAC. Community Plan Update. Parks & Recreation. September 25, 2017

Frederickson LUAC. Community Plan Update. Parks & Recreation. September 25, 2017 Frederickson LUAC Community Plan Update Parks & Recreation September 25, 2017 Kimberly Freeman Resource Stewardship Superintendent kimberly.freeman@co.pierce.wa.us 253-798-4261 Joseph Coppo Senior Parks

More information

Arlington County Board Meeting Project Briefing. October 20, 2015

Arlington County Board Meeting Project Briefing. October 20, 2015 Arlington County Board Meeting Project Briefing October 20, 2015 Project Map 2 Project Context Only Interstate in the Country limited to HOV only traffic during rush hours Stoplight at the end of I-66

More information

NORTH OF BROADWAY SECTION CONTENTS: COTTAGE PARK FARVIEW PARK GLEN GALE PARK IRVING TRIANGLE JORDAN PARK NEWTON PARK PERKINS HILL PARK

NORTH OF BROADWAY SECTION CONTENTS: COTTAGE PARK FARVIEW PARK GLEN GALE PARK IRVING TRIANGLE JORDAN PARK NEWTON PARK PERKINS HILL PARK NORTH OF BROADWAY SECTION CONTENTS: COTTAGE PARK FARVIEW PARK GLEN GALE PARK IRVING TRIANGLE JORDAN PARK NEWTON PARK PERKINS HILL PARK N ILIO NA VE N JAM ES AV E PLAYGROUND PAR K PRO PER TY B OUN DAR Y

More information

3. COLTA / HUGA CONNECTIONS - PRELIMINARY

3. COLTA / HUGA CONNECTIONS - PRELIMINARY 9 3. COLTA / HUGA CONNECTIONS - PRELIMINARY 3.1 COLTA The Chain of Lakes Trail Association (COLTA) trail, formerly identified as the Chester Spur Line, was completed and opened for use in June 2011. The

More information

NORTHWEST SECTION CONTENTS: CLEVELAND PARK FOLWELL PARK RYAN LAKE PARK VICTORY PRAIRIE DOG PARK VICTORY PARK

NORTHWEST SECTION CONTENTS: CLEVELAND PARK FOLWELL PARK RYAN LAKE PARK VICTORY PRAIRIE DOG PARK VICTORY PARK NORTHWEST SECTION CONTENTS: CLEVELAND PARK FOLWELL PARK RYAN LAKE PARK VICTORY PRAIRIE DOG PARK VICTORY PARK LUCY LANEY COMMUNITY SCHOOL N 33RD AVE N 33RD AVE SINGLE-FAMILY RESIDENTIAL MULTI-USE DIAMOND

More information

Trails Technical Committee

Trails Technical Committee Trails Technical Committee Winter 2017 Draft Report Alignment Proposals for the Inyo National Forest and the Town of Mammoth Lakes Map ID #S18 February 08, 2017 Map ID #S18 Key Agreements As of February

More information

STARA PLANINA REVISION OF APPLE PLATEAU BASE AREA DEVELOPMENT

STARA PLANINA REVISION OF APPLE PLATEAU BASE AREA DEVELOPMENT STARA PLANINA REVISION OF APPLE PLATEAU BASE AREA DEVELOPMENT 1.0 Assumptions Successful mountain resort design is derived from analysing the flow and circulation of guests to and within the resort. Determining

More information

Score. Category. Access Aesthetics Community Resources

Score. Category. Access Aesthetics Community Resources NO BUILD ALTERNATIVE The No Build Alternative is the do nothing option that is used for comparison to the build alternatives. The screening assumes no new facilities are constructed as part of the I-93

More information

STUDY WORK GROUP MEETING No. 4. July 12, 2017

STUDY WORK GROUP MEETING No. 4. July 12, 2017 STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,

More information

Chapter 4 Terminal Facility Requirements and Alternatives

Chapter 4 Terminal Facility Requirements and Alternatives Chapter 4 Terminal Facility Requirements and Alternatives I. Terminal Facility Requirements Introduction This chapter of the master plan converts the forecasted passenger demand levels that were identified

More information

Welcome to the Cross County Trail Public Input Session!

Welcome to the Cross County Trail Public Input Session! Welcome to the Cross County Trail Public Input Session! Please sign in on the table below! What are we doing here? Camden County has proposed a bicycle and pedestrian trail spanning across the entire county.

More information

Fuller Road/Fuller Heights Road Improvements

Fuller Road/Fuller Heights Road Improvements Transportation Fuller Road/Fuller Heights Road Improvements Total Project Cost - $4.4M This project will widen Fuller Road, which is the entrance road serving the Quantico Marine Corps Base, the Town of

More information

Dogpatch Project Descriptions Summary DRAFT UNDER REVIEW January 11, 2017

Dogpatch Project Descriptions Summary DRAFT UNDER REVIEW January 11, 2017 1. OPEN SPACE A. Esprit Park Why : Esprit Park, Dogpatch s only City Park, is already struggling under current use. It was not designed for intensive use and is not sustainable in its current state. What

More information

Tampa International Airport Master Plan Update. December 12, 2012

Tampa International Airport Master Plan Update. December 12, 2012 Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking

More information

Community Park Capital Project. February 6, 2017

Community Park Capital Project. February 6, 2017 Community Park Capital Project February 6, 2017 Construction Budget Estimate Bid Recommended $10,318,690 $7,725,000 Staff Recommended +$1.1M $8,850,000 +$2.6M -$1.47M Pre-Bid Estimate 11/22/2016

More information

Aircraft Arrival Sequencing: Creating order from disorder

Aircraft Arrival Sequencing: Creating order from disorder Aircraft Arrival Sequencing: Creating order from disorder Sponsor Dr. John Shortle Assistant Professor SEOR Dept, GMU Mentor Dr. Lance Sherry Executive Director CATSR, GMU Group members Vivek Kumar David

More information

2 SITE ANALYSIS AND DESIGN CRITERIA

2 SITE ANALYSIS AND DESIGN CRITERIA 2 SITE ANALYSIS AND DESIGN CRITERIA PRELIMINARY DEVELOPMENT CRITERIA 12 URBAN CONTEXT 13 VIEW 14 SITE GRADING 16 EXISTING STRUCTURES 16 STRUCTURAL AND SEISMIC CONSTRAINTS 18 CRUISE INDUSTRY AND ACTIVITY

More information

Director, Community Planning, Toronto and East York District

Director, Community Planning, Toronto and East York District STAFF REPORT October 25, 2005 To: From: : Subject: Toronto and East York Community Council Director, Community Planning, Toronto and East York District Status Report OPA & Rezoning Application 05 117524

More information

Capital & Counties. October 2007

Capital & Counties. October 2007 Capital & Counties October 2007 Contents!" # $ % % $ & ' "&( # Appendix 1 Appendix 2 1 Introduction 1.1.1 Wincheap regeneration scheme proposes a 600 space Park and Ride facility to replace the existing

More information

NEW MEADOWS PARK PROPOSED MASTER PLAN

NEW MEADOWS PARK PROPOSED MASTER PLAN NEW MEADOWS PARK PROPOSED MASTER PLAN A vision for your neighborhood park, the draft master plan is ready for your review. Tuesday September 12 th, 2017 5:30-7:00 PM Hellgate School District #4 middle

More information

MINUTES OF THE ST. MARY S COUNTY PLANNING COMMISSION MEETING ROOM 14 * GOVERNMENTAL CENTER * LEONARDTOWN, MARYLAND Monday, April 26, 2004

MINUTES OF THE ST. MARY S COUNTY PLANNING COMMISSION MEETING ROOM 14 * GOVERNMENTAL CENTER * LEONARDTOWN, MARYLAND Monday, April 26, 2004 MINUTES OF THE ST. MARY S COUNTY PLANNING COMMISSION MEETING ROOM 14 * GOVERNMENTAL CENTER * LEONARDTOWN, MARYLAND Monday, April 26, 2004 Members present were John Taylor, Sr., Chairman; Lawrence Chase,

More information

395 Express Lanes Project Update

395 Express Lanes Project Update 395 Express Lanes Project Update Key Dates Milestone Date Limited Notice to Proceed February 2017 Early Works March-June 2017 Full Notice to Proceed July 2017 Preparatory Work Summer 2017 Draft Noise Abatement

More information

Premier 550-acre business park in Central Austin

Premier 550-acre business park in Central Austin Premier 550-acre business park in Central Austin Built For Business OFFICE CAMPUS Easily accessible central location, a variety of building designs and sizes, reliable power and connectivity, generous

More information

AGENCY NAME TRANSPORTATION

AGENCY NAME TRANSPORTATION TRANSPORTATION TRANSPORTATION AGENCY NAME Prince William County FY 2015 BUDGET CIP-TRANSPORTATION 561 Fuller Road/Fuller Heights Road Improvements Total Project Cost - $4.4 M This project will widen Fuller

More information

Fort Ward District Park Maintenance Operations

Fort Ward District Park Maintenance Operations Fort Ward District Park Maintenance Operations 2008 Fiscal Year Cost Center Report July 2008 Fort Ward District - Park Maintenance Operations Fort Ward Cost Center 2008 Published and Printed by The City

More information

Westbrook Station. Transit Oriented Development Opportunity

Westbrook Station. Transit Oriented Development Opportunity DEVELOPM Westbrook Station Transit Oriented Development Opportunity OPPOR Table of Contents Prime Real Estate Development Opportunity page 1 Calgary City of Opportunity page 3 What is Transit Oriented

More information

City of Grand Island Tuesday, December 12, 2017 Council Session

City of Grand Island Tuesday, December 12, 2017 Council Session City of Grand Island Tuesday, December 12, 2017 Council Session Item E-3 Public Hearing on One & Six Year Street Improvement Plan Council action will take place under Resolution item I-1. Staff Contact:

More information

McLean Citizens Association Transportation Committee Project Briefing

McLean Citizens Association Transportation Committee Project Briefing McLean Citizens Association Transportation Committee Project Briefing November 10, 2015 Project Map 2 Project Context Only Interstate in the Country limited to HOV only traffic during rush hours Stoplight

More information

Project Deliverable 4.1.3d Individual City Report - City of La Verne

Project Deliverable 4.1.3d Individual City Report - City of La Verne Pomona Valley ITS Project Project Deliverable 4.1.3d Individual City Report - City of La Verne Prepared by: April 19, 2002 099017000.1 Copyright 2002, Kimley-Horn and Associates, Inc TABLE OF CONTENTS

More information

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 LAWTON-FORT SILL REGIONAL AIRPORT LAWTON, OKLAHOMA PASSENGER FACILITY CHARGE PROPOSED

More information

Landside Safety Programs

Landside Safety Programs Landside Safety Programs Ali Ousmane Mahamane AVN 1160- Aviation Safety Spring 2013 The paper is about the landside safety programs. Landside facilities are facilities related to ground access, vehicle

More information

PARKSIDE COMMUNITY ASSOCIATION 2018 Summer Arts Camp Parent Packet

PARKSIDE COMMUNITY ASSOCIATION 2018 Summer Arts Camp Parent Packet PARKSIDE COMMUNITY ASSOCIATION 2018 Summer Arts Camp Parent Packet Session Dates & Times Session I: July 10 27 Session II: July 30 August 17 Monday - Friday: 9:00AM 3:00PM Location Delaware Park Tot Lot

More information

US 380 FEASIBILITY STUDY

US 380 FEASIBILITY STUDY US 380 FEASIBILITY STUDY Denton County CSJ(s): 0135-10-061, 0135-10-062 Public Meeting(s): January 15 & 22, 2019 WELCOME US 380 Denton County Feasibility Study DALLAS DISTRICT PUBLIC MEETING January 15

More information

China Creek North Park Upgrades and Glen Pump Station. Park Board Committee Meeting Monday, July 10, 2017

China Creek North Park Upgrades and Glen Pump Station. Park Board Committee Meeting Monday, July 10, 2017 China Creek North Park Upgrades and Glen Pump Station Park Board Committee Meeting Monday, July 10, 2017 Purpose The purpose of this presentation is to: Share the results of the public engagement processes;

More information

FOLWELL PARK LOCATION AND HISTORY LOCATION

FOLWELL PARK LOCATION AND HISTORY LOCATION FOLWELL PARK LOCATION LOCATION AND HISTORY Folwell Park is a large (by neighborhood park standards) tract of land located south of Dowling Avenue between Humboldt and Knox Avenues. The land for the park

More information

State of Hawaii Dept. of Transportation Airports Division Capital Improvement Program Update

State of Hawaii Dept. of Transportation Airports Division Capital Improvement Program Update State of Hawaii Dept. of Transportation Airports Division Capital Improvement Program Update Enabling Inter-Island Improvements for Mauka CC Honolulu International Airport Before After Mauka Concourse

More information

2. Goals and Policies. The following are the adopted Parks and Trails Goals for Stillwater Township:

2. Goals and Policies. The following are the adopted Parks and Trails Goals for Stillwater Township: D. PARKS AND TRAILS 1. Introduction Stillwater Township s population is relatively low, with most residents living on rural residences on large lots. The need for active park space has been minimal in

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

Elevating the Upstate

Elevating the Upstate Greenville-Spartanburg Int l Airport Elevating the Upstate SC Economic Developers Association October 12, 2012 Introduction/Presentation Outline Introductions Airport Overview Air Service Terminal Improvement

More information

Buchanan Field. Airport Planning Program. FAR Part 150 Meeting. September 28, Master Plan FAR Part 150 Noise Study Strategic Business Plan

Buchanan Field. Airport Planning Program. FAR Part 150 Meeting. September 28, Master Plan FAR Part 150 Noise Study Strategic Business Plan Airport Planning Program Master Plan FAR Part 150 ise Study Strategic Business Plan FAR Part 150 Meeting September 28, 2006 Agenda Introduction Part 150 Study Working Paper Two Operational Alternatives

More information

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT December 2018 Project Summary Boulder County, Colorado, in partnership with the City of Boulder, is evaluating options for multi-use

More information

Technical Advisory Committee Briefing #3

Technical Advisory Committee Briefing #3 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY Technical Advisory Committee Briefing #3 June 22, 2018 Master Plan Schedule Overview Coordination Review Recommended Remote 5-Gate Facility

More information

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Form PDES 8 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Summary of Duties: A Senior Airport Engineer performs the more difficult and

More information

WOODROW WILSON BUILDING COMMITTEE MEETING MINUTES REGULAR MEETING MARCH 30, 2017

WOODROW WILSON BUILDING COMMITTEE MEETING MINUTES REGULAR MEETING MARCH 30, 2017 WOODROW WILSON BUILDING COMMITTEE MEETING MINUTES REGULAR MEETING MARCH 30, 2017 Present: Chair Mary Bartolotta, Christopher Drake, Richard Pelletier, John Philips, John Giuliano, Gene Nocera, Christopher

More information

PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40

PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40 PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40 Project Description The primary purpose of this project is to improve the major

More information

A. CONCLUSIONS OF THE FGEIS

A. CONCLUSIONS OF THE FGEIS Chapter 11: Traffic and Parking A. CONCLUSIONS OF THE FGEIS The FGEIS found that the Approved Plan will generate a substantial volume of vehicular and pedestrian activity, including an estimated 1,300

More information

British Museum World Conservation and Exhibitions Centre

British Museum World Conservation and Exhibitions Centre British Museum World Conservation and Exhibitions Centre Montague Place elevation of proposed World Conservation and Exhibitions Centre The British Museum is consulting widely about revised proposals for

More information

4. Proposed Transit Improvements

4. Proposed Transit Improvements 4. Proposed Transit Improvements The following proposed transit improvements have been assembled based on input received from the community meetings and from review and coordination with the TAC as well

More information

FEASIBILITY CRITERIA

FEASIBILITY CRITERIA This chapter describes the methodology and criteria used to evaluate the feasibility of developing trails throughout the study areas. Land availability, habitat sensitivity, roadway crossings and on-street

More information

ATTACHMENT B. Reference No.

ATTACHMENT B. Reference No. ATTACHMENT B Projects in the Five-Year Capital Improvement Program for Fiscal Years Ending 2014-2018 GOVERNMENT CODE SECTION 65402 GENERAL PLAN CONFORMITY ANALYSIS 1 4 Orcutt GS Station 21 (Orcutt) Rebuild

More information

Citrus Heights Creek Corridor Trail Project. Trail Advisory Group Meeting #3 July 8, 2013

Citrus Heights Creek Corridor Trail Project. Trail Advisory Group Meeting #3 July 8, 2013 Citrus Heights Creek Corridor Trail Project Trail Advisory Group Meeting #3 July 8, 2013 Agenda Introductions Recap: Community Workshop, Survey Findings, and TAG Field Trip Community Concern Discussion:

More information

ACTION TRANSMITTAL

ACTION TRANSMITTAL Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED

More information

Construction Staging Adelaide Street West

Construction Staging Adelaide Street West REPORT FOR ACTION Construction Staging Adelaide Street West Date: October 6, 2016 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

Blueways: Rivers, lakes, or streams with public access for recreation that includes fishing, nature observation, and opportunities for boating.

Blueways: Rivers, lakes, or streams with public access for recreation that includes fishing, nature observation, and opportunities for boating. Parks, Open Space and Trails PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN TRAILS PLAN CONTENTS The components of the trails plan are: Intent Definitions Goals, Policies, and Action Strategies Trails Map

More information

URBAN DESIGN REPORT. Proposed Residential Development, Old Church Road, Caledon East

URBAN DESIGN REPORT. Proposed Residential Development, Old Church Road, Caledon East Proposed Residential Development, Old Church Road, Caledon East TABLE CONTENTS: 1.0 DEVELOPMENT 1.1 Introduction-Analysis of Guiding Principles and Documents 1.2 Community Design and Architectural Design

More information

Maryland Transit Administration. Master Plan Alignment Trail

Maryland Transit Administration. Master Plan Alignment Trail Maryland Transit Administration Master Plan Alignment Trail Master Plan Alignment Byrne Kelly Concept Trail Analysis - North vs. South Trail Access & Crossings Aesthetics Master Plan Alignment Description

More information

Town of Hamburg Planning Board Meeting July 26, 2017

Town of Hamburg Planning Board Meeting July 26, 2017 Town of Hamburg Planning Board Meeting July 26, 2017 Minutes The Town of Hamburg Planning Board met for a Work Session at 6:30 P.M., followed by a Regular Meeting at 7:00 P.M. on Wednesday, July 26, 2017

More information

Birmingham Airport 2033

Birmingham Airport 2033 Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted

More information

PAVILION RESERVATIONS

PAVILION RESERVATIONS Reservations may be requested beginning: PAVILION RESERVATIONS The first Monday the PRCS Office is open following January 1st - Residents of the City of Racine The third Monday in March - Non-City of Racine

More information

METRO Orange Line Update Metro Transit, BRT/Small Starts Projects Christina Morrison & Natalie Westberg Transportation Committee July 10, 2017

METRO Orange Line Update Metro Transit, BRT/Small Starts Projects Christina Morrison & Natalie Westberg Transportation Committee July 10, 2017 METRO Orange Line Update Metro Transit, BRT/Small Starts Projects Christina Morrison & Natalie Westberg Transportation Committee July 10, 2017 Orange Line BRT Project What is the Orange Line project? 17-mile

More information

Boston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA

Boston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA Boston Redevelopment Authority 2/26/2014 Cassidy Playground Waterworks Design revisions made since the DPIR submission March 2013 Massing - Reduced project 16,030 SF, for a total project area of 218,520

More information

LCFC ACCESS STATEMENT

LCFC ACCESS STATEMENT LCFC ACCESS STATEMENT Updated: June 2017 CONTENTS HOW TO GET TO KING POWER STADIUM... WHILE YOU RE AT KING POWER STADIUM... VIEWING AREAS... ACCESSIBLE TOILETS... FACILITIES AT KING POWER STADIUM... 3

More information

ANCLOTE COASTAL TRAIL ALTERNATIVES ANALYSIS STUDY

ANCLOTE COASTAL TRAIL ALTERNATIVES ANALYSIS STUDY ANCLOTE COASTAL TRAIL ALTERNATIVES ANALYSIS STUDY PASCO COUNTY MPO JULY 2015 PROJECT OVERVIEW... INTRODUCTION EXECUTIVE SUMMARY CONTEXT... TAMPA BAY AREA, PINELLAS, & PASCO COUNTY S MULTI-USE TRAIL PLANS

More information

North Forty Area ( area bounded by Lark Avenue, Los Gatos Boulevard, Highway 85 and

North Forty Area ( area bounded by Lark Avenue, Los Gatos Boulevard, Highway 85 and RESOLUTION 2015-056 RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF LOS GATOS ADOPTING GENERAL PLAN AMENDMENTS NECESSARY FOR THE NORTH FORTY SPECIFIC PLAN. THE PLAN AREA COMPRISES APPROXIMATELY 44 ACRES

More information

Concord Road Interchange. Standard hours of work

Concord Road Interchange. Standard hours of work Artist impression of the Concord Road interchange, Concord - concept only WestConnex s M4 East will extend the M4 Motorway with two new 5.5 kilometre tunnels from Homebush to Haberfield, providing a bypass

More information