1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466) Operation Name: CO Integrated Mass Transit Systems (P082466) Project Stage: Implementation Seq.No: 16 Status: ARCHIVED Archive : 11-Nov-2012 Country: Colombia Approval FY: 2004 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Specific Investment Loan Implementing Agency(ies): Ministerio de Transporte Key s Board Approval 10-Jun-2004 Original Closing 31-Mar-2009 Planned Mid Term Review 20-Oct-2006 Last Archived ISR 29-Mar-2012 Effectiveness 20-Jan-2005 Revised Closing 31-Dec-2012 Actual Mid Term Review 20-Oct-2006 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of the Project are to: (i) develop quality and sustainable BRTSs in selected medium and large cities to improve mobility along the most strategic mass transit corridors; (ii) improve accessibility for the poor through feeder services and fare integration; (iii) build greater institutional capacity at the national level in order to formulate integrated urban transport policies, and at the local level in order to improve urban transport planning and traffic management. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) losure Authorized Public Disclosure Authorized Component Name Component Cost CAPACITY BUILDING 4.80 BRTS DEVELOPMENT Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Highly Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating High Implementation Status Overview Project is coming to its end. Civil works financed by the project are almost finished in all cities. 5 Bus Rapid transit (BRT) systems are operating: Bogota NQS, Pereira (PE), Bucaramanga (BU) Barranquilla (BA) and Medellin (ME). It is expected that Cartagena will start operations in year A second additional loan for US$ 300 Million was approved by the Bank in August 4th, This operation will finance the Government of Colombia (GOC) transfers from After the approval of this operation, the total amount of Bank support to the National Urban Transport Project (NUTP) is $757 million. A new loan ($ 350 million) has been presented for Board approval on July 21, The new loan will continue financing the GOC#s transfers for Bucaramanga, Cartagena and Valle de Aburra and will include two new Page 1 of 5
2 medium sized Sincelejo and Valledupar (Ciudades Amables Sistemas Estrategicos de Transporte Publico). This loan will finance the Government's transfers to the NUTP between 2011 and The current loan is almost fully disbursed (99%). The remaining $2.4 million will be used in the TA component. Transfers between the GOC and the municipalities have progressed according to the yearly disbursement program. The GOC has transferred about 80% of his commitments to the NUTP. This flow of transfers is expected to conclude in 2016 according to the most recent CONPES documents prepared by National Planning Department (DNP). Construction of BRT trunk lines is well advanced and completion percentages -with respect to the total contracted civil works (some of them no financing by the Bank's loan-) vary between 78% (Cartagena),, 94% Pereira, and Bucaramanga, Barranquilla, Bogota NQS and Medellin at 100%. The Project Implementation Unit (PIU) is providing key support to the cities in the implementation of the project. The loan has bee extended and will closed on December 30, Locations Country First Administrative Division Location Planned Actual Colombia Not Entered Soledad Colombia Not Entered Soacha Colombia Not Entered Piedecuesta Colombia Not Entered Medellin Colombia Not Entered Itagui Colombia Not Entered Giron Colombia Not Entered Floridablanca Colombia Not Entered Envigado Colombia Not Entered Dosquebradas Colombia Not Entered Cartagena Colombia Not Entered Cali Colombia Not Entered Bucaramanga Colombia Not Entered Bogota Colombia Not Entered Bello Colombia Not Entered Barranquilla Colombia Not Entered Barranquilla Colombia Not Entered Valle de Aburra Results Page 2 of 5
3 Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Reduction in generalized door- to-door travel cost (fare, time) to users Percentage of people rating the system as being better than the previous system At least three BRTS schemes operating successfully and GOC systematically monitoring program performance and impact functioning. Text Value Bog: 0.99,65.01 Per: 0.83, Med: 0.91, Buc: Info inexistent (II) Car: 1.04, 31.5 Bar: 1.09, II 20-Jan-2005 Text Generalized travel cost for low income users Text Sub Type Breakdown Average travel time for low income users Text Sub Type Breakdown Value Text Value BRTS operating successfully (Transmilenio Bogota) 20-Jan-2005 Value Bog: 1.24, Per: Jan-2005 Value Bog: minutes Per: minutes 20-Jan-2005 This indicator has not yet measure Barranquilla and Bucaramanga operating below the estimated demand 12-Nov Nov-2008 Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of km constructed Text Value Kms to finish construction of trunk lines 20-Jan Dec-2012 Number of construction contracts awarded according to procurement Text Value Through ICB and NCB 12 contracts awarded (6 in Pereira and 6 in Cartagena) 20-Jan May-2011 Page 3 of 5
4 Number of operation contracts awarded Text Value 0 5 cities. All cities except Medellin, where operation will be handled directly by Metro de Medellin 31-Aug-2012 Number of fare collection systems awarded Text Value Bogota 5. All cities except Medellin, where fare collection will be handled directly by Metro de Medellin 01-Jan May Nov-2011 Data on Financial Performance (as of 17-Oct-2012) Financial Agreement(s) Key s Project Ln/Cr/Tf Status Approval Signing Effectiveness Original Closing Revised Closing P IBRD Closed 10-Jun Sep Jan Mar Mar-2009 P IBRD Closed 12-Jun Dec Jan Mar Mar-2010 P IBRD Effective 04-Aug Sep Dec Mar Dec-2012 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IBRD Closed USD P IBRD Closed USD P IBRD Effective USD Disbursement Graph Page 4 of 5
5 Key Decisions Regarding Implementation no Restructuring History Level two Approved on 11-Mar-2011, Level two Approved on 06-Dec-2011, Level two Approved on 18-Apr-2012 Related Projects P Integrated Mass Transit System - Additional Financing, P CN-P LEN-BBCBF, P Integrated Mass Transit Systems Second Additional Financing Page 5 of 5
Implementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466) Operation Name: CO Integrated Mass Transit
More informationImplementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia CO Integrated Mass Transit Systems (P082466) Operation Name: CO Integrated Mass Transit
More informationImplementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379)
Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Operation Name: Djibouti Power Access and
More informationImplementation Status & Results Mexico MX Urban Transport Transformation Progr (P107159)
losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Mexico MX Urban Transport Transformation Progr (P107159) Operation
More informationImplementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379)
Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Djibouti Djibouti Power Access and Diversification Project (P086379) Operation Name: Djibouti Power Access and
More informationImplementation Status & Results Peru Vilcanota Valley Rehabilitation and Management Project (P082625)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Peru Vilcanota Valley Rehabilitation and Management Project (P082625) Operation Name: Vilcanota
More informationImplementation Status & Results Argentina AR Road Safety (P116989)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina AR Road Safety (P116989) Operation Name: AR Road Safety (P116989) Project Stage: Implementation
More informationImplementation Status & Results Argentina National Urban Solid Waste Management Project (P089926)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina National Urban Solid Waste Management Project (P089926) Operation Name: National Urban
More informationImplementation Status & Results Argentina AR Cordoba Road Infrastructure (P099585)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina AR Cordoba Road Infrastructure (P099585) Operation Name: AR Cordoba Road Infrastructure
More informationImplementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932) Operation Name: Colombian
More informationImplementation Status & Results Argentina Essential Public Health Functions Programs II Project (P110599)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina Essential Public Health Functions Programs II Project (P110599) Operation Name: Essential
More informationImplementation Status & Results Indonesia Strategic Roads Infrastructure Project (P079906)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Strategic Roads Infrastructure Project (P079906) Operation Name: Strategic Roads Infrastructure
More informationImplementation Status & Results Argentina National Urban Solid Waste Management Project (P089926)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina National Urban Solid Waste Management Project (P089926) Operation Name: National Urban
More informationImplementation Status & Results Serbia SERBIA ROAD REHABILITATION AND SAFETY PROJECT (P127876)
Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Serbia SERBIA ROAD REHABILITATION AND SAFETY PROJECT (P127876) Operation Name: SERBIA ROAD REHABILITATION AND SAFETY
More informationImplementation Status & Results Argentina AR Basic Municipal Services Project (P060484)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina AR Basic Municipal Services Project (P060484) Operation Name: AR Basic Municipal Services
More informationImplementation Status & Results Mozambique Roads and Bridges Management and Maintenance Program - Phase II (P083325)
losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Mozambique Roads and Bridges Management and Maintenance Program
More informationImplementation Status & Results Argentina Norte Grande Road Infrastructure (P120198)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina Norte Grande Road Infrastructure (P120198) Operation Name: Norte Grande Road Infrastructure
More informationImplementation Status & Results Peru Sierra Irrigation Subsector (P104760)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Peru Sierra Irrigation Subsector (P104760) Operation Name: Sierra Irrigation Subsector (P104760)
More informationImplementation Status & Results Peru PE Sierra Irrigation Subsector (P104760)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Peru PE Sierra Irrigation Subsector (P104760) Operation Name: PE Sierra Irrigation Subsector (P104760)
More informationImplementation Status & Results Serbia Transport Rehabilitation Project (Serbia) (P075207)
Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Serbia Transport Rehabilitation Project (Serbia) (P075207) Operation Name: Transport Rehabilitation Project (Serbia)
More informationImplementation Status & Results Argentina Urban Transport in Metropolitan Areas (P095485)
losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Argentina Urban Transport in Metropolitan Areas (P095485)
More informationImplementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932) Operation Name: Colombian
More informationImplementation Status & Results Peru Sierra Irrigation Subsector (P104760)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Peru Sierra Irrigation Subsector (P104760) Operation Name: Sierra Irrigation Subsector (P104760)
More informationImplementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932) Operation Name: Colombian
More informationImplementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932) Operation Name: Colombian
More informationImplementation Status & Results Egypt, Arab Republic of Railways Restructuring (P101103)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Egypt, Arab Republic of Railways Restructuring (P101103) Operation Name: Railways Restructuring
More informationImplementation Status & Results Moldova NATIONAL WATER SUPPLY & SANITATION PROGRAM (P107612)
Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Moldova NATIONAL WATER SUPPLY & SANITATION PROGRAM (P107612) Operation Name: NATIONAL WATER SUPPLY & SANITATION
More informationImplementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Colombia Colombian National Protected Areas Conservation Trust Fund (P091932) Operation Name: Colombian
More informationUrban Transport in Metropolitan Areas (P095485)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2010 Seq No: 12 ARCHIVED on 09-May-2016 ISR22958 Implementing Agencies:
More informationUrban Transport in Metropolitan Areas (P095485)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2010 Seq No: 14 ARCHIVED on 30-Jun-2017 ISR28825 Implementing Agencies:
More informationNorte Grande Road Infrastructure (P120198)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2011 Seq No: 15 ARCHIVED on 02-Apr-2018 ISR31768
More informationUrban Transport in Metropolitan Areas (P095485)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2010 Seq No: 15 ARCHIVED on 26-Jan-2018 ISR31117
More informationUrban Transport in Metropolitan Areas (P095485)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Argentina Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2010 Seq No: 11 ARCHIVED on 15-Sep-2015 ISR20616 Implementing Agencies:
More informationImplementation Status & Results Paraguay Road Maintenance (P082026)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Paraguay Road Maintenance (P082026) Operation Name: Road Maintenance (P082026) Project Stage: Implementation
More informationImplementation Status & Results Paraguay Road Maintenance (P082026)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Paraguay Road Maintenance (P082026) Operation Name: Road Maintenance (P082026) Project Stage: Implementation
More informationImplementation Status & Results Paraguay Road Maintenance (P082026)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Paraguay Road Maintenance (P082026) Operation Name: Road Maintenance (P082026) Project Stage: Implementation
More informationImplementation Status & Results Report Mozambique Conservation Areas for Biodiversity and Development Project (P131965)
Public Disclosure Authorized AFRICA Mozambique Environment & Natural Resources Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 8 ARCHIVED on 27-Dec-2017 ISR30661 Implementing Agencies:
More informationImplementation Status & Results Bosnia and Herzegovina REAL ESTATE REGISTRATION PROJECT (P128950)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Bosnia and Herzegovina REAL ESTATE REGISTRATION PROJECT (P128950) Operation Name: REAL ESTATE REGISTRATION
More informationThe World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized
Public Disclosure Authorized AFRICA Mozambique Water Global Practice IBRD/IDA Specific Investment Loan FY 2008 Seq No: 16 ARCHIVED on 30-Oct-2015 ISR21080 Implementing Agencies: Public Disclosure Authorized
More informationImplementation Status & Results Bolivia BO Rural Alliances (P083051)
losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Bolivia BO Rural Alliances (P083051) Operation Name:
More informationImplementation Status & Results Africa GEF-Western Indian Ocean Marine Highway Development and Coastal and Marine Contamination Prevention (P078643)
losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa GEF-Western Indian Ocean Marine Highway Development
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Ethiopia Trade & Competitiveness Global Practice IBRD/IDA Specific Investment Loan FY 2009 Seq No: 14 ARCHIVED on 21-Dec-2015 ISR20896 Implementing Agencies: Public
More informationImplementation Status & Results Andean Countries Adaptation to the Impact of Rapid Glacier Retreat in the Tropical Andes (P098248)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Andean Countries Adaptation to the Impact of Rapid Glacier Retreat in the Tropical Andes (P098248)
More informationJanuary 2018 Air Traffic Activity Summary
January 2018 Air Traffic Activity Summary Jan-2018 Jan-2017 CY-2018 CY-2017 Passengers 528,947 505,421 4.7% 528,947 505,421 4.7% Passengers 537,332 515,787 4.2% 537,332 515,787 4.2% Passengers 1,066,279
More informationNATIONAL SUPPORT PROGRAMS FOR SUSTAINABLE URBAN TRANSPORT IN COLOMBIA
NATIONAL SUPPORT PROGRAMS FOR SUSTAINABLE URBAN TRANSPORT IN COLOMBIA Adriana Paola Sarmiento Hernández National Planning Department Infrastructure and Energy Department September, 2017 www.dnp.gov.co
More informationImplementation Status & Results Africa GEF-Western Indian Ocean Marine Highway Development and Coastal and Marine Contamination Prevention (P078643)
Public Disclosure Authorized Public Disclosure Authorized losure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa GEF-Western Indian Ocean Marine Highway Development
More informationNATIONAL PROGRAM OF URBAN TRANSPORT IN COLOMBIA. Opportunities for Engineering and Planning Services
NATIONAL PROGRAM OF URBAN TRANSPORT IN COLOMBIA Opportunities for Engineering and Planning Services Luis Felipe Lota Coordinator of Urban Transport and Mobility April of 2011 Contents - National Framework
More informationBUSINESS OPPORTUNITIES FOR THE PUBLIC TRANSPORT IN LATIN AMERICA
BUSINESS OPPORTUNITIES FOR THE PUBLIC TRANSPORT IN LATIN AMERICA CONTENTS 1. COLOMBIA AND BOGOTÁ: Investment and exporting opportunities 2. TRANSMILENIO: The bus rapid transit system that serves Bogotá
More informationPublic Transport Planning and Regulation: An Introduction
VI. Measures and Standards Public Transport Planning and Regulation: An Introduction VI-1 Planning and Analysis Building Blocks Schedule Building Cost Analysis and Financial Planning Performance Analysis
More informationTraffic Results YTD Mar 2017
Traffic Results YTD Mar 2017 Departing Pax 348,583-14% Departing Pax - US/CAN 225,066 5% Total Seat Capacity - Outbound 447,620-17% Seat Capacity USA 253,332 5% LF USA 82% LF CANADA 88% Traffic Results
More informationGEOGRAPHICAL LOCATION OF colombia
GEOGRAPHICAL LOCATION OF colombia Population: 48 Million inhabitants Urban: 37 million inhabitants rural: 11 million inhabitants GDP PER CAPITA: USD 7.930 Unemployment: 8,8% poverty: 28.5% Santa Marta
More informationPerformance monitoring report 2017/18
Performance monitoring report /18 Gatwick Airport Limited 1. Introduction Date of issue: 20 July 2018 This report provides an update on performance at Gatwick in the financial year /18, ending 31 March
More informationJ.P. Morgan 9 th Annual Global Emerging Markets Corporate Conference. Miami, February 2018
J.P. Morgan 9 th Annual Global Emerging Markets Corporate Conference Miami, February 2018 This presentation may include forward-looking comments regarding the Company s business outlook and anticipated
More informationMETRO OPERATIONS COMMITTEE
Los Angeles County Metropolitan Transportation Authority Item 1 CHIEF OPERATIONS OFFICER S S REPORT METRO OPERATIONS COMMITTEE Lonnie Mitchell Chief Operations Officer May 19, 20 1 Employee Recognition
More informationSound Transit Operations December 2014 Service Performance Report. Ridership
Ridership Total Boardings by Mode Mode Dec-13 Dec-14 % YTD-13 YTD-14 % ST Express 1,266,130 1,396,787 10.3% 16,605,299 17,661,976 6.4% Sounder 248,710 285,016 14.6% 3,035,735 3,361,317 10.7% Tacoma Link
More informationResults of Tourism Activity
Reporting Date: January 18, 2016 Results of Tourism Activity Mexico, November 2015 Reserva de la Biósfera El Cielo, Tamaulipas. San Juan de Ulúa, Veracruz. Museo de la Muerte, Aguascalientes. Xilitla,
More informationManagement Presentation. November 2018
Management Presentation November 2018 Forward looking statements This presentation as well as oral statements made by officers or directors of Allegiant Travel Company, its advisors and affiliates (collectively
More informationManual vs. Automatic Operation and Operational Restrictions
Customer Services, Operations, and Safety Committee Board Information Item IV-B March 11, 2010 Manual vs. Automatic Operation and Operational Restrictions Page 81 of 91 Washington Metropolitan Area Transit
More informationWith the completion of this project, we would like to follow-up on the projections as well as highlight a few other items:
TO: FROM: Mayor and Council Interim City Manager Rebecca Underhill, Director of Finance DATE: February 28, 2014 SUBJECT: Water Meter Project Analysis On March 28, 2012, Acting City Manager Mike Loftin
More informationLOVE FIELD ENVIRONMENTAL ADVISORY COMMITTEE QUARTERLY REPORT. October December 2016
LOVE FIELD ENVIRONMENTAL ADVISORY COMMITTEE QUARTERLY REPORT October December 2016 VOLUNTARY NOISE CONTROL PROGRAM COMPLIANCE DURING PREFERENTIAL HOURS 2100 0600 (JAN SEP 2016) 2 PERCENTAGE OF COMPLIANCE
More informationDTTAS Quarterly Aviation Statistics Snapshot Quarter Report
Contents DTTAS Quarterly Aviation Statistics Snapshot Quarter 4 2015 Report 1.1 Dublin Airport Key Statistics... 1 1.2 Cork Airport Key Statistics... 3 1.3 Shannon Airport Key Statistics... 5 1.4 Total
More informationDTTAS Quarterly Aviation Statistics Snapshot Quarter Report
Contents DTTAS Quarterly Aviation Statistics Snapshot Quarter 3 2018 Report 1.1 Dublin Airport Key Statistics... 1 1.2 Cork Airport Key Statistics... 3 1.3 Shannon Airport Key Statistics... 5 1.4 Total
More informationBoard Box. October Item # Item Staff Page 1. Key Performance Indicators Sep 2018 M. Mungia Financial Report Aug 2018 H.
Board Box October 2018 Item # Item Staff Page 1. Key Performance Indicators Sep 2018 M. Mungia 2-10 2. Financial Report Aug 2018 H. Rodriguez 11-15 ITEM 1 October 31, 2018 TO: FROM: RE: BOARD OF DIRECTORS
More informationDTTAS Quarterly Aviation Statistics Snapshot Quarter Report
Contents DTTAS Quarterly Aviation Statistics Snapshot Quarter 1 2018 Report 1.1 Dublin Airport Key Statistics... 1 1.2 Cork Airport Key Statistics... 3 1.3 Shannon Airport Key Statistics... 5 1.4 Total
More informationResults of Tourist Activity
Results of Tourist Activity México, January, 2014 Ministry of Tourism Tourist Planning and Policy Undersecretariat Index Relevant Results, January, 2014.. Analysis of Main Results in the Sector..... 1
More informationSound Transit Operations August 2015 Service Performance Report. Ridership
Ridership Total Boardings by Mode Mode Aug-14 Aug-15 % YTD-14 YTD-15 % ST Express 1,534,241 1,553,492 1.3% 11,742,839 12,354,957 5.2% Sounder 275,403 326,015 18.4% 2,139,086 2,463,422 15.2% Tacoma Link
More informationBank of America Merrill Lynch 2018 Emerging Markets Corporate Credit Conference. Miami, May 2018
Bank of America Merrill Lynch 2018 Emerging Markets Corporate Credit Conference Miami, May 2018 This presentation may include forward-looking comments regarding the Company s business outlook and anticipated
More informationInformation meeting. 1 st September 2011
Information meeting 1 st September 2011 Full Year 2010-11 key data April 2010-March 2011 Revenues in billions Operating result in millions 77% Passenger 18.10 +11.3% -44 +874 13% Cargo 3.16 +29.5% +69
More informationMonthly SunPass Transponder Sales Inception to June 2012
Monthly SunPass Transponder Sales Inception to June 2012 This graph shows the monthly SunPass transponder sales since inception. The significant increase in transponder sales during March 2004 is attributed
More informationManagement Presentation. March 2016
Management Presentation March 2016 Forward looking statements This presentation as well as oral statements made by officers or directors of Allegiant Travel Company, its advisors and affiliates (collectively
More informationExchange Sunshine Coast 2014
Exchange Sunshine Coast 2014 A refresher on CSQ... What does CSQ do? We: promote careers in the building and construction industry invest in skills and training grow the number of skilled workers build
More informationInterim Management Report First Half Results 2010/11. October 29, 2010
Interim Management Report First Half Results 2010/11 October 29, 2010 Disclaimer Certain information included in these statements is forward-looking and involves risks and uncertainties that could cause
More informationJumpstart 2017 Lukas Johnson SVP, Commercial. June 2017
Jumpstart 2017 Lukas Johnson SVP, Commercial June 2017 Forward looking statements This presentation as well as oral statements made by officers or directors of Allegiant Travel Company, its advisors and
More informationResults of Tourism Activity
Results of Tourism Activity Mexico, July 2016 Lago de San Miguel Regla, Hidalgo. Jardín en Hacienda San Gabriel, Morelos. Parras, Coahuila. Paseo Santa Lucía, Monterrey. Undersecretariat of Planning and
More informationPrices are Starting From MARINER OF THE SEAS VOYAGER CLASS TONNAGE :
MARINER OF THE SEAS SAILING ON MARCH 2018 1-Mar-18 5-Mar-18 9-Mar-18 12-Mar-18 16-Mar-18 19-Mar-18 29-Mar-18 2-Apr-18 6-Apr-18 4 NIGHTS 4 NIGHTS 3 NIGHTS 4 NIGHTS 3 NIGHTS 3 NIGHTS 4 NIGHTS 4 NIGHTS 3
More informationFull Year 2009 Results
Full Year 2009 Results 1 Antonio Vázquez Chairman & Chief Executive Officer 2 Highlights 2009 Strong decrease in revenues: weak demand and yield deterioration. High competition and drop of business traffic.
More informationSIA GROUP FINANCIAL RESULTS
FINANCIAL RESULTS For Ended 30 June 2018 197200078R Operating Result Q1 Q1 Better/ FY18/19 FY17/18 R1 (Worse) ($M) ($M) (%) Total Revenue 3,844 3,864 (0.5) Q1 Better/ FY17/18 R2 (Worse) ($M) (%) 3,689
More informationSCHEDULE OF REVENUES BY SOURCE September 1, 2015 - May 31, 2016 CV Transit District State Administered Program Transit Transit Aging Local Toll Total Total Excess Revenue Grant No Grant Name Federal Federal
More information1 2 23 24 15 16 7 8 9 Ancillary Revenue target per pax RM55 10 Online 365 11 212 13 14 14 Quarter Ended: 31 March RM'000 Revenue 2,068,227 Operating expenses: - Staff costs (286,663) - Depreciation
More informationAnnual Performance Report. easier, faster, safer
Annual Performance Report 2017 Content Introduction Choosing performance indicators Update on Corridor Traffic KPI 01: Traffic Volume (Total) KPI 02: Corridor Punctuality OM 01: Traffic Volume (Per Corridor
More informationPassenger Traffic Achieves Strong Growth of 4.8% for the Month of August
Passenger Traffic Achieves Strong Growth of 4.8% for the Month of August Montréal, 7 October Passenger traffic experienced a slight surge in growth to almost +5% for August compared to previous months
More informationResults 2Q17. August 9, 2017
Results 2Q17 August 9, 2017 2Q17 Highlights Indicators 2Q17 Var. x 2Q16 ASK (BN) 10.4-3.0% Traffic (000) 7,261-1.3% RPK (BN) 8.1 +0.5% Load Factor 77.9% +2.7 p.p. Yield (R$ cents) 23.2 +4.8% Pax Revenue
More informationDELHI TRANSCO LIMITED STATE LOAD DESPATCH CENTER (REGD. OFFICE : SHAKTI SADAN BUILDING, KOTLA ROAD, NEW DELHI
Computation of Transmiossion Losses of STU Delhi i.e. Delhi Transco Limited system for FY 2007-08 Sl. No. 6=(1 to 5) 8= (6+7) 14=(9 to 13) 15= (8-14) 16=15*100/8 Total Injection to Delhi System Apr-07
More informationThe Effect of an Efficient Public Transport System on Poverty: Lessons for Johannesburg from Bogotá Eugenia Mpofu
The Effect of an Efficient Public Transport System on Poverty: Lessons for Johannesburg from Bogotá Eugenia Mpofu A research report submitted to the Faculty of Engineering and the Built Environment: University
More informationPresentation on Results for the 3rd Quarter FY Idemitsu Kosan Co.,Ltd. February 2, 2016
Presentation on Results for the 3rd Quarter FY 2015 Idemitsu Kosan Co.,Ltd. February 2, 2016 Table of Contents 1. 3 rd Quarter FY 2015 Financials (1) Overview (2) Segment Information 2. Forecast for FY
More informationEARNINGS 2Q2016 RELEASE. August 30, 2016
EARNINGS RELEASE 2Q2016 August 30, 2016 RELEVANT CORPORATE EVENTS 2Q2016 MULTIPLAZA LA FELICIDAD BOGOTÁ - CUNDINAMARCA RELEVANT CORPORATE EVENTS New market maker with Credicorp: a value adding tool for
More informationSound Transit Operations March 2018 Service Performance Report. Ridership
March 218 Service Performance Report Ridership Total Boardings by Mode Mar-17 Mar-18 % YTD-17 YTD-18 % ST Express 1,622,116 1,47,79-4.6% 4,499,798 4,428,14-1.6% Sounder 393,33 39,6.% 1,74,96 1,163,76 8.3%
More informationResults of Tourism Activity Mexico, February 2017
Results of Tourism Activity Mexico, February Undersecretariat of Planning and Tourism Policy Available in http://www.datatur.sectur.gob.mx/sitepages/versionesrat.aspx DIRECTORy ENRIQUE DE LA MADRID CORDERO
More informationINVESTOR PRESENTATION
INVESTOR PRESENTATION MARCH 214 1 DISCLAIMER THIS DOCUMENT HAS BEEN PREPARED BY PARQUE ARAUCO FOR THE PURPOSE OF PROVIDING GENERAL INFORMATION ABOUT THE COMPANY. The Company assumes no responsibility for,
More informationPerformance monitoring report for 2014/15
Performance monitoring report for 20/15 Date of issue: August 2015 Gatwick Airport Limited Summary Gatwick Airport is performing well for passengers and airlines, and in many aspects is ahead of the performance
More informationMexico Hotel & Tourism Investment Conference Global Hotel Industry Overview
Mexico Hotel & Tourism Investment Conference Global Hotel Industry Overview Jeff Higley VP, digital media & communications Thursday, 7 February 2013 www.hotelnewsnow.com Click on Hotel Data Presentations
More informationFeb 6 th, 2007 Japan Airlines Corporation
Feb 6 th, 2007 Japan Airlines Corporation 0 Table of Contents JAL Group Q3 AccountSettlement For FY2006. Q3 Account Settlement For FY2006 Outline of the Consolidated Financial StatemeP3 Revision of Revenue
More informationMarch Domestic Exports Imports. Volume Tonnes SW. MAT Mar-17 5, ,880 36, , % Change 3.6% 4.9% 15.6% 10.0% -5.8% 2.
March 2018 Overview Table 1.1 Overview trends for Domestic, Export and Import trade Domestic Exports Imports Month Slaughter Pigmeat (Tonnes) Volume Tonnes SW Value $AUD (Million) Volume Tonnes SW Value
More informationSAS Group Q2 2012/13. Q2 Restructuring programme moving KPIs in the right direction
SAS Group Q2 2012/13 1 Q2 Restructuring programme moving KPIs in the right direction Operating revenues +1.6%* Yield improvement of +2.7%* Forceful implementation of 4XNG plan: Unit cost down by 10.7%
More informationOPERATING AND FINANCIAL HIGHLIGHTS
Copa Holdings Reports Net Income of US$18.6 Million and EPS of US$0.42 for the Second Quarter of 2010 Excluding special items, adjusted net income came in at $26.3 million, or $0.60 per share Panama City,
More informationAir China Limited Annual Results. March Under IFRS
Air China Limited 21 Annual Results Under IFRS March 211 Agenda Part 1 Highlights Part 2 Business Overview Part 3 Financial Overview Part 4 Outlook 2 Part 1 Highlights Steady Economic Growth; Asia Pacific
More informationRIDERSHIP TRENDS. October 2017
RIDERSHIP TRENDS October 2017 Prepared by the Division of Strategic Capital Planning December 2017 Table of Contents Executive Summary...1 Ridership...3 Estimated Passenger Trips by Line...3 Estimated
More informationImplementation of SESAR Pilot Common Project. - expected effects
Implementation of SESAR Pilot Common Project - expected effects (2014-2024) European Commission May 20, 2014 - Oslo 1 SESAR SESAR - Technological Pillar of the Single Technological pillar of the SES European
More informationPerformance Measures Year End Updated-
Performance Measures Year End 2017 -Updated- Priorities and Objectives 1. Earn and Retain the Community s Trust 2. Provide Excellent Customer Service 3. Enable Organizational Success 4. Exemplify Financial
More informationCapital Metropolitan Transportation Authority. Monthly Performance Report
Capital Metropolitan Transportation Authority Monthly Performance Report AUGUST 2010 Ridership Report August 23, 2010 Budget to Actual Ridership Budget Target: 2,290,590 Actual: 2,300,796 Ridership Comparison
More information