FAA Update. Airports Program. Western-Pacific Region. Federal Aviation Administration
|
|
- Lynne Garrett
- 6 years ago
- Views:
Transcription
1 Airports Program Western-Pacific Region Presented to: ACA By: Robin Hunt & David Cushing Date: September 14, 2012
2 FY11 Program Highlights AIP Performance Metric FAA Modernization and Reform Act of 2012 Are You Ready for FY13? Safety/Compliance Initiatives 2
3 $180 FY11 AIP Projects Funded (Western-Pacific Region) $160 $140 $120 $100 Total: $461M $80 $60 $40 $20 $0 Land Acquisition $8M Navaids / Equipment $10 Environmental / Planning $14M Other $36M Building/Terminal $41M Noise $45M Taxiway $71M Apron $74M Runway $162M 3
4 AIP Funding for FY10 & FY11 4
5 FY11 AIP Program (by State in millions) Fund Types AZ CA NV HI Pacific Total State Apportionment $7 $21 $5 $1 $2 $36 Entitlement $24 $77 $14 $23 $9 $147 Discretionary $55 $140 $36 $9 $38 $278 Total: $86 $238 $55 $33 $49 $461 5
6 AIP Performance Metric Office of Management and Budget (OMB) outlay rates: By end of year in which appropriated, disburse 18% By end of 1st year after appropriation, disburse 60% By end of 2nd year after appropriation, disburse 81% By end of 3rd year after appropriation, disburse 91% By end of 4th year after appropriation, disburse 96% After the 4th year, all funds should be fully disbursed and the grant closed. 6
7 Current Grant Performance Target 40% (FY11 Grant balance) 19% (FY10 Grant balance) 9% (FY09 Grant balance) 4% (FY08 Grant balance) Arizona 54% 15% 7% 1% California 59% 16% 7% 5% Nevada 50% 16% 6% 3% Hawaii 75% 26% 10% 12% Pacific 77% 28% 11% 1% 7
8 Financial Report SF-425 SF-272 is obsolete SF-425 replaced SF-272 Submit SF-425 to FAA within 30 days after the end of each fiscal year 8
9 FAA Modernization and Reform Act of 2012 The President signed the FAA Modernization & Reform Act of 2012 on February 14, year FAA reauthorization bill Authorizes $3.35 billion for AIP (FY12 15) $165 million less than previous years ($3.5 billion) Still subject to annual appropriation bill 9
10 New Federal Share for AIP Grants The federal share for development projects reverts back from 95% to the following rate: o Arizona 91.06% (except PHX 75%) o Nevada 93.75% (except LAS 75%) o Hawaii 90% o Pacific Islands 90% o California 90.06% (except BUR, ONT, OAK, SMF, SAN, SJC, SNA %, SFO & LAX 75%) 10
11 Essential Air Service Airports in Economically Distressed Areas US DOT determined the following airports to remain eligible at a 95% federal share: Kingman (AZ) Prescott (AZ) Show Low (AZ) Crescent City (CA) El Centro (CA) Merced (CA) Visalia (CA) 11
12 Miscellaneous Provision Construction projects with discretionary funds may begin before execution of grant agreements, due to climatic condition Changes made to residential through-the-fence (TTF) and disposal of noise land requirements TTF adds language enabling a GA airport to enter into an agreement with a person to access airport with property adjacent to or near the airport Disposal of noise land allows designation of noise land as buffer land. Airports can lease without treating land as disposal. 12
13 New Electronic Grant Payments Delphi einvoicing is in operation. Call DOT Help desk if you have any registration issues. 1 (866) , Option 4, Option 3 1 (405) , Option 4, Option 3 Delphi einvoicing manual payment will begin on November 1 st. 13
14 Are You Ready for FY13? Ready means that by 12/31/12 you have: Planning complete Project on an approved ALP FAA environmental complete (FONSI, ROD, or submission of extraordinary circumstance form) Airspace review and approval complete Design complete and project ready for bid 14
15 FY13 Environmental Deadline Environmental documents should be completed by December 31, 2012 Finding of No Significant Impact (FONSI) for Environmental Assessment (EA) Record of Decision (ROD) for Environmental Impact Statement (EIS) Submission of extraordinary circumstance form to support categorical exclusions 15
16 FY 2013 Grants Applications Get your application is early Ensure calculation adds up and are supported Administrative cost and support services need to have back-up for all numbers Force Account work must be approved by FAA Bids should not include contingency even by another name 16
17 Important Dates for FY13 (AIP Grants) Events Due Dates Environmental (FONSI, ROD, or CAT EX) December 2012 Application December 2012 Open Bids March 31 Carryover May 1 Grant Offers (approximate) July 30 Grant Execution August 15 Grant Payments Periodically- at least every 6 months Financial Report (SF-425) With 30 days of the end of each FY Grant Closing < 4 Years (within 30 days of final inspection) 17
18 Vehicle Pedestrian Deviations In FY11, there were 44 Vehicle/Pedestrian Deviation related Runway Incursions (VPD-RIs) in AWP. This is by far the highest number of all Regions. To date in FY12, there have been 18 VPD Runway Incursions in AWP. By this time last year, AWP had experienced 22 so we are doing better, but We need your vigilance as we move into spring and summer which are our peak times for V/PD RIs. Nevada Airports are doing well. NV Airports had 4 VPD-Ris in FY11. There have been 3 VPD-RI this fiscal year to date at Nevada Airports. 2 at LAS and 1 at VGT. ASDE-X snapshot of HNL VPD Runway Incursion on 2/22/12. Aircraft overflew HNL Ops Vehicle by approximately 150 feet. 18
19 Wildlife Hazard Management To date in FY12, A total of 123 wildlife strikes have been reported at or near AWP Airports. Of those, 116 occurred at Part 139 certificated airports. The remaining occurred at General Aviation (GA) airports. We strongly recommend all Part 139 certificated airports and busy GA Airports conduct a Wildlife Hazard Assessment and develop a Wildlife Hazard Management Plan even if they have not experienced a triggering event. All wildlife strikes should be reported to FAA at 19
20 Runway Safety Area Program All practicable improvements to RSAs at Part 139 airports, including NavAids related actions, must be completed by December 30, GOOD NEWS: Based on the information we have, all Part 139 Certificated Runways in Nevada meet current RSA Standards. Not So Good News: We have 30 RSA projects to be completed by the deadline. AWP program is faced with timing & funding challenges in meeting the 2015 deadline. Our ACIP, includes over $400 million in AIP funding for RSA projects. This means that other, lower priority, projects must be deferred. 20
21 Safety Management System (SMS) Airports implementation of SMS is limited to Large Hub Airport projects only until further notice. FAA-Air Traffic Organization (ATO) implementation of SMS may include any project with potential to impact operation of the National Airspace System. AWP has identified the following large hub airport projects that require further screening under the SMS process in 2012: McCarran (LAS) Two Taxiway Rehabilitations (CSPP). Honolulu (HNL) Rehabilitate Taxiway Z (design only). San Francisco (SFO) Runway 10L-28R and 10R-28L Runway Safety Areas. Los Angeles (LAX) Construct two aprons at Bradley Terminal and Taxiway T. Phoenix (PHX) Rehab Taxiway B8. Other SRMPs may be initiated by FAA-ATO. 21
22 Design Standards Update FAA is working on update to Advisory Circular 150/ , Airport Design. FAA s goal is to publish AC 150/ A by the end of Fiscal Year 12. Principal Changes are in the areas of: Chapter 3, Runway Design Chapter 4, Taxiway and Taxilane Design Declared Distances and RSA Application Runway Protection Zone (RPZ) Taxiway Design Group (TDG) Concept for Fillet Design Runway Design Code (RDC), Runway Reference Code (RRC) and Taxiway Design Group (TDG) designation Minimum separation between non-intersecting runways Runway incursion prevention geometry for new construction Consolidation of numerous runway design tables to one design requirements matrix Table 3-5 FAA is also working on updates to the Heliport Design AC and new standards for Parachute Landing Areas on airports. 22
23 National ADO Initiatives Geographic Balancing (Geo-balancing) National redistribution of resources to better serve our customers New Phoenix ADO to serve AZ and NV Phoenix office will initially report to LAX ADO LAX and SFO ADOs will exclusively serve California National SOPs under development to create consistency among ADOs 23
24 Summary Talk to us. Talk early. Plan ahead. Stay abreast of current regulation and guidance. Please talk to us before an issue becomes a problem! 24
25 Contact Information Mark McClardy, Division Manager Western-Pacific Region (310) Debbie Roth, Deputy Manager Western-Pacific Region (310) Mia Ratcliff, Manager Planning and Programming Branch (310) Brian Armstrong, Manager Safety and Standards Branch (310) David Cushing, Manager Los Angeles Airports District Office (310) Robin Hunt, Manager San Francisco Airports District Office (650) Ron Simpson, Manager Honolulu Airports District Office (808)
26 Questions? 26
Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN
Overview of the FAA s Office of Airports Prepared for: Presented by: 2016 ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Eduardo Angeles Associate Administrator for Airports Date:
More information6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)
6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement
More informationMassDOT Aeronautics Division Capital Improvements Presentation
MassDOT Aeronautics Division Capital Improvements Presentation MassDOT Board Retreat October 27, 2011 Presentation Agenda Capital Improvement Plan (CIP) Overview Airports Capital Improvement Plan (ACIP)
More informationUpdate on FAA Standard Operating Procedures (SOP)
Update on FAA Standard Operating Procedures (SOP) SOP 2.0 - Airport Layout Plan (ALP) SOP 3.0 - Exhibit A Airport Property Map Presented to: Association of California Airports (ACA); ACA Annual Conference,
More informationFAA Update. Dakota-Minnesota (DMA) Airports District Office. Federal Aviation Administration. Presented to: By: Date: South Dakota Airports Conference
FAA Update Dakota-Minnesota (DMA) Airports District Office Presented to: By: Date: South Dakota Airports Conference Chris Hugunin & Dave Anderson March 18, 2015 FY 2014 DMA ADO Total AIP Funding $107.2
More informationBOARD OF AIRPORT COMMISSIONERS
1 8/17/2018 8/21/2018 8/16/2018 i ElY MY Y I : JH MT BY...01,, III1*.ji,"1.111Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: la Approved by: e1. "ampbell, Chief Airports
More informationPresented to the: NCTCOG Air Transportation Advisory Committee. Presented to the: NCTCOG Air Transportation Advisory Committee
...while at FAA By: Kelvin L. Solco, P.E., MBA, President, The Solco Group Presented to the: NCTCOG Air Transportation Advisory Committee Presented to the: NCTCOG Air Transportation Advisory Committee
More informationChapter Seven COST ESTIMATES AND FUNDING A. GENERAL
Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction
More informationFAA Reauthorization Issues & Impacts on Airports
Issues & Impacts on Airports Presentation to Mid America Association of State Transportation Officials July 21, 2011 Presented by Greta J. Hawvermale Sr. Director of Engineering & Environmental Matters
More informationAirport. Improvement Program (AIP) Overview. Federal Aviation Administration. Texas Aviation Conference Ben Guttery, Texas ADO April 2017
Airport Improvement Program (AIP) Overview Texas Aviation Conference Ben Guttery, Texas ADO April 2017 Objectives Status of AIP Legislative Authority History and Summary of AIP AIP funding formulas 2 AIP
More informationFinance and Implementation
5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter
More informationUpdate from the FAA s Office of Airports
Update from the FAA s Office of Airports Prepared for: Presented by: Airports Council International-North America Business of Airports Conference Orlando, FL Elliott Black Director Office of Airport Planning
More informationFAA Update. Dakota-Minnesota (DMA) Airports District Office. Federal Aviation Administration. Presented to: By: Date: Minnesota Council of Airports
FAA Update Dakota-Minnesota (DMA) Airports District Office Presented to: By: Date: Minnesota Council of Airports Chris Hugunin April 15, 2015 FY 2014 DMA ADO Total AIP Funding $107.2 Million / 136 Grants
More informationWashington Update: FAA Reauthorization, ATC Reform, 1500 Hour Rule, and $1 Billion in Omnibus Funding
Session Ten: Washington Update: FAA Reauthorization, ATC Reform, 1500 Hour Rule, and $1 Billion 2018 GAA Annual Conference & Expo Jekyll Island, Ga Back to the Beach: For a Low Country Luau in Omnibus
More informationNext Generation Air Transportation System Financing Reform Act of 2007
Next Generation Air Transportation System Financing Reform Act of 2007 Funding Proposal An ACC Summary of Key Provisions in the USDOT s FAA Reauthorization Proposal Overall, the change in the aviation
More informationFor Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018
COUNTY OF INYO REQUEST FOR QUALIFICATIONS For Airport Environmental Services Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018 County of Inyo Public Works Department P.O.
More informationWELCOME TO YOUR REGIONAL AIRPORT AUTHORITY MEETING OF THE CITY OF MERCED AGENDA
WELCOME TO YOUR REGIONAL AIRPORT AUTHORITY MEETING OF THE CITY OF MERCED AUTHORITY MEMBERS Larry Morelock-Chair, Alvin Osborn-Vice-Chair, John Sundgren, Rodrigo Flores, Ryan Smith, and Michael Bodine.
More informationAirports and UAS: Integrating UAS into Airport Infrastructure and Planning
ACRP Problem Statement 17-03-09 Recommended Allocation: $500,000 Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Staff Comments This is one of four UAS-themed problem statements
More informationChapter 8.0 Implementation Plan
Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.
More informationSERVING CALIFORNIA S COMMERCIAL AIRPORTS
SERVING CALIFORNIA S COMMERCIAL AIRPORTS Annual Report 2011 Top Left: Santa Barbara Municipal Airport Top Right: Sacramento International Airport Right: John Wayne Airport, Orange County Introduction The
More informationChapter 1 Introduction and Project Overview
EPHRATA MUNICIPAL AIRPORT Chapter 1 Introduction and Project Overview The Port of Ephrata in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Ephrata Municipal
More informationSession 6 Airport Finance 101 Funding Sources for Airports
Session 6 Airport Finance 101 Funding Sources for Airports 31 st Annual AAAE Basics of Airport Law Workshop and 2015 Legal Update November 1-3, 2015 Desk Reference Chapters 2, 19, 22 Frank J. San Martin
More informationAirport Funding FAA Airport Improvement Program (AIP)
Airport Funding FAA Airport Improvement Program (AIP) Presented to: Texas Aviation Conference By: Mike Nicely, Manager Texas ADO Date: May 15, 2013 Discussion Topics Enabling Legislation Authorization
More informationNotice of Passenger Facility Charge (PFC) Approvals and Disapprovals
This document is scheduled to be published in the Federal Register on 12/04/2014 and available online at http://federalregister.gov/a/2014-28535, and on FDsys.gov 1 DEPARTMENT OF TRANSPORTATION Federal
More informationFEDERAL AIRPORT IMPROVEMENT PROGRAM (AIP) PRE-APPLICATION FFY 2017 CHECKLIST
Form 291111wd (09-15) Storm Lake Municipal Airport Airport FEDERAL AIRPORT IMPROVEMENT PROGRAM (AIP) PRE-APPLICATION FFY 2017 SLB FAA Identifier CHECKLIST Please attach the following documents with your
More informationAnalysis Item 71: Department of Aviation Aurora State Airport Runway Extension
Analysis Item 71: Department of Aviation Aurora State Airport Runway Extension Analyst: Gregory Jolivette Request: Approve, retroactively, the submission of a federal grant application to the Federal Aviation
More informationRESOLUTION NO
RESOLUTION NO. 2015-15 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MARINA AUTHORIZING SUBMISSION OF A GRANT APPLICATION TO THE FEDERAL AVIATION ADMINISTRATION (FAA) FOR PARTICIPATION IN THE 2015 MILITARY
More informationChapter 1 Introduction and Project Overview
Chapter 1 Introduction and Project Overview Kittitas County in cooperation with the Federal Aviation Administration (FAA) is updating the Airport Master Plan for Bowers Field Airport (FAA airport identifier
More informationNantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012
Nantucket Memorial Airport Commission Master Plan Workshop October 26, 2012 Agenda Introductions Master Plan 101 Airport Planning Issues Noise Abatement Activities Environmental Monitoring Public Outreach
More informationInput Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot
Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot community Airport Advisory Board meetings Elected Officials
More informationLos Angeles International Airport (LAX) Airside $907M
Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking
More informationYakima Air Terminal/McAllister Field Airport Master Plan Update
Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used
More informationMONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES
MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the
More informationSafety Enhancement SE RE Airports Policies and Procedures to Mitigate Runway Excursion Consequences & Severity
Safety Enhancement SE 221.1 RE Airports Policies and Procedures to Mitigate Runway Excursion Consequences & Severity Safety Enhancement Action: Implementers: Statement of Work: Airport operators and the
More informationCollier County Airport Authority. Joint Automated Capital Improvement Program
Collier County Airport Authority Joint Automated Capital Improvement Program Joint Automated Capital Improvement Program (JACIP) What is the JACIP? Financial planning process supported by Web-based computer
More informationGDOT AND FAA ADO UPDATES
GDOT AND FAA ADO UPDATES Building on the Past Soaring Into the Future Aviation Program Update 2015 GDOT PowerPoint October 27, 2016 Title Page Georgia Airports Association Presented By Steven V. Brian,
More informationTable 14: Transportation Page 1
Table 14: Transportation Page 1 Major 2 and 4 Lane Highways Linking the Area Metro Area Miles Interstate 40 to Las Angeles, California 318 US Highway 93 to Las Vegas, Nevada 103 US Highway 95 to Yuma,
More informationDALLAS LOVE FIELD MAY 2015 DRAFT
8. Funding Plan This section presents a potential funding plan for implementing the CIP projects recommended in the Master Plan Update, along with an assessment of the ability of the Airport sponsor (i.e.,
More informationNational Association of State Aviation Officials. John Shea Government Relations Manager (703)
National Association of State Aviation Officials John Shea Government Relations Manager (703) 610-0272 jshea@nasao.org Fiscal 2018 Omnibus: DOT Highlights Department of Transportation (DOT) The bill provides
More information2015 PURDUE ROAD SCHOOL March 11, 2015
2015 PURDUE ROAD SCHOOL March 11, 2015 Runway Protection Zone (RPZ) Definition It is a trapezoidal shape formed off the end of a runway and its geometry it a function of the airport s aircraft approach
More informationDepartment of Transportation, Federal Aviation Administration (FAA). SUMMARY: Under this notice, the FAA announces the submission deadline of
This document is scheduled to be published in the Federal Register on 05/09/2018 and available online at https://federalregister.gov/d/2018-09894, and on FDsys.gov [4910-13] DEPARTMENT OF TRANSPORTATION
More informationCatExes vs. EAs When and How to Prepare
CatExes vs. EAs When and How to Prepare Panel: Steve Culberson, Ricondo & Associates Frank Smigelski, FAA Mary Vigilante, Synergy Tuesday December 10, 2013 Washington, DC 1 So you have a project Do I have
More informationAirport Master Plan Open House Front Range Airport February 23, 2017
Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future
More informationSTUDY WORK GROUP MEETING No. 3. November 29, 2016
STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity
More informationCHAPTER 1: INTRODUCTION
CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the
More informationChapter 9 Airport Financial Plan
Chapter 9 Airport Financial Plan Introduction The purpose of this chapter is to present the projects identified in the twenty-year Airport Capital Improvement Program (ACIP) that have been developed and
More informationAppendix 6.1: Hazard Worksheet
Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp
More informationPUBLIC NOTICE. Table 1 Projects Proposed by Amendment
PUBLIC NOTICE The Dallas Department of Aviation (the Department) intends to file an amendment application to increase the PFC amount of one previously approved project at Dallas Love Field Airport (the
More informationTHE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY FIRST QUARTER 2015
THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY FIRST QUARTER 2015 Pursuant to the California Department of Transportation
More informationBOARD OF AIRPORT COMMISSIONERS -
0 OF1 Los Angeks World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS - Meeting Date: O'IAA.A.)1.Alk-Tort/uQA212J`s-- Approved by: Samantha Bricker - Deputy Executive Director 11/16/2017 11-Pleviewed
More informationAirportInfo. Airport Improvement Program
AirportInfo Airport Improvement Program April 2014 Airport Improvement Program (AIP) AIP provides grants to airport sponsors for the planning and development of public-use airports. To be eligible for
More informationFederal Aviation Administration NOTAM MANAGER. Presented to: ACA 2016 Annual Conference. Jennifer Dady NISC Contract Support. By:
NOTAM MANAGER Presented to: By: ACA 2016 Annual Conference Jennifer Dady NISC Contract Support Background and Purpose Lockheed Martin operates the FAA s current ENII Notice to Airmen (NOTAM) system and
More informationFederal Aviation Administration Flight Plan Presented at the Canadian Aviation Safety Seminar April 20, 2004
Federal Aviation Administration Flight Plan 2004-2008 Presented at the Canadian Aviation Safety Seminar April 20, 2004 Challenges Reducing an Already Low Commercial Accident Rate Building an Air Traffic
More informationTRB and ACRP Research Updates: Practical Application
TRB and ACRP Research Updates: Practical Application 2014 ACI Environmental Affairs Conference Danielle J. Rinsler, AICP FAA Office Airports, Airport Planning and Environmental Division Baltimore, MD Advisory
More informationFederal Aviation Administration. Airport Land Use Compatibility Advisory Circular ACI-NA / FAA. FAA HQ Washington, DC March 27, 2013
Airport Land Use Compatibility Advisory Circular ACI-NA / FAA FAA HQ Washington, DC March 27, 2013 The purpose of this meeting is to discuss FAA s update of the Airport Compatible Land Use Advisory Circular.
More informationAirport Master Plan. Brookings Regional Airport. Runway Runway 17-35
Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements
More informationChapter 4 Airport Facility Requirements
Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT
More informationFAA Airport. Safety and Standards Update. Federal Aviation Administration. ACI-NA Operations and Technical Affairs Committee
FAA Airport Safety and Standards Update ACI-NA Operations and Technical Affairs Committee Michael J. O Donnell, A.A.E. Director, Office of Airport Safety & Standards April 2014 Agenda 20 to one Approach
More informationAIRPORT WITH NO RUNWAYS IS A MALL
RUNWAY EXTENSION INITIATIVE AT FT. LAUDERDALE HOLLYWOOD INTERNATIONAL AIRPORT ISMAEL IZZY BONILLA DEPUTY DIRECTOR BROWARD COUNTY AVIATION AUTHORITY AIRPORT WITH NO RUNWAYS IS A MALL Runway Business Case
More informationFinancial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority
Financial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority September 12, 2017 Contents 1. Funding Sources for Airport Projects 2. Financial Metrics 3. CIP Summary and Funding
More informationChapter 10 FAA Compliance Review
Chapter 10 FAA Compliance Review Introduction This chapter discusses the elements associated with the operation and management of Albany Municipal Airport, as a federally-obligated airport. The Federal
More informationThe Law of Noise Regulation Daniel S. Reimer
The Law of Noise Regulation Daniel S. Reimer Today s Presentation Division of responsibility 2 Federal responsibility Noise source control Local responsibility Land use compatibility Aircraft restrictions
More informationMerritt Island Airport
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory
More informationPassenger Facility Charge Application #1
Passenger Facility Charge Application #1 February 2017 APPLICATION PUNTA GORDA AIRPORT PFC ASSURANCES CERTIFICATION STATEMENT The undersigned Chair of the Charlotte County Airport Authority assures
More informationGeospatial Data Collection for the FAA Airports GIS Program
Geospatial Data Collection for the FAA Airports GIS Program A Change in Direction Dr. Michael T. McNerney, P.E. FAA Office of Airports Office of Airport Safety and Standards Assistant Manager, Airport
More informationTHE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015
THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2015 Pursuant to the California Department of Transportation
More informationSOUTH CAROLINA AERONAUTICS COMMISSION
SOUTH CAROLINA AERONAUTICS COMMISSION STATEWIDE AIRFIELD PAVEMENT MANAGEMENT SYSTEM UPDATE AIRPORT: LEXINGTON COUNTY AT PELION 106 AIRPORT ROAD PELION, SC 29123 SOUTH CAROLINA AERONAUTICS COMMISSION 2553
More informationChapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update
Chapter Six ALP Drawings Master Plan Update The master planning process for the (Airport) has evolved through efforts in the previous chapters to analyze future aviation demand, establish airside and landside
More informationDepartment of Transportation, Federal Aviation Administration (FAA). SUMMARY: Under this notice, the FAA announces the submission deadline of
This document is scheduled to be published in the Federal Register on 10/02/2017 and available online at https://federalregister.gov/d/2017-21045, and on FDsys.gov [4910-13] DEPARTMENT OF TRANSPORTATION
More informationPORT OF PORTLAND. Chapter Seven CAPITAL IMPROVEMENT PROGRAM
PORT OF PORTLAND Chapter Seven CAPITAL IMPROVEMENT PROGRAM CHAPTER SEVEN PORT OF PORTLAND CAPITAL IMPROVEMENT PROGRAM The analyses conducted in the previous chapters evaluated airport development needs
More informationAirport Finance 101 Session 3 - Capital Funding
Airport Finance 101 Session 3 - Capital Funding Capital Development Funding Improvement Projects usually require substantial funding to be implemented In business world capital is associated with funds
More informationA Decade of Consolidation in Retrospect
A Decade of Consolidation in Retrospect MARCH 7, 2017 CONSOLIDATION TIMELINE Airlines Announced Closed SOC US Airways- America West Delta- Northwest Frontier- Midwest United- Continental Southwest- AirTran
More informationInterrelationship Between the Federal Aviation Administration and the City of Santa Monica Regarding the Operation of the Santa Monica Airport
To: Airport Commission ITEM 7(b) From: Subject: Airport Staff Interrelationship Between the Federal Aviation Administration and the City of Santa Monica Regarding the Operation of the Santa Monica Airport
More informationTHE CASE OF A SUCCESSFUL PFC APPLICATION
THE CASE OF A SUCCESSFUL PFC APPLICATION 1 Chapter One: Scene of the case study 2 Chapter One: The Scene Spokane, WA Home of the RED TURF at Eastern WA University (and Gonzaga) 3 Chapter One: The Scene
More informationCHAPTER 3 ALTERNATIVES CONSIDERED
CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from
More informationTHE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2017
THE BURBANK-GLENDALE-PASADENA AIRPORT AUTHORITY S UPDATE REGARDING ITS NOISE IMPACT AREA REDUCTION PLAN AND ITS PART 161 STUDY SECOND QUARTER 2017 Pursuant to the California Department of Transportation
More informationHonolulu International Airport (HNL) Transit Rail Alignment Options Review
Honolulu International Airport (HNL) Transit Rail Alignment Options Review Presented to: Federal Transit, Region IX By: Debbie Roth, Acting Manager, Western-Pacific Region, Airports Division Steve Wong,
More informationAirport Master Plan for. Brown Field Municipal Airport PAC Meeting #3
Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus
More informationHot Topics in Land Use at GA Airports. Peter J. Kirsch
2006 AAAE General Aviation Issues Conference September 19, 2006 Hot Topics in Land Use at GA Airports Peter J. Kirsch Today s Presentation 2 Focus on two hot topics : Management of lands purchased for
More informationTHE FAA MODERNIZATION AND REFORM ACT OF 2012
THE FAA MODERNIZATION AND REFORM ACT OF 2012 A. Introduction... 1 A.1 Structure of the 2012 Reform Act... 1 B. AIP Funding... 2 B.1 Level and Duration of Funding Authority... 2 B.2 Apportionment Formulas
More informationAirport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3
Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline
More informationTXDOT AVIATION DIVISION
TXDOT AVIATION DIVISION Airport Project Development & Selection Process Today s Topics Project Development Process Working with TxDOT Aviation Division Funding Sources National Plan of Integrated Airports
More informationBrian Ryks Executive Director and CEO
Brian Ryks Executive Director and CEO MAC Commissioners MAC Finances 2016 Budgeted Operating Revenues Utilities and Other 5% Airline Rates and Charges 34% Rents and Fees 14% Concessions 47% 2016 Budgeted
More informationDevelopment Program and Implementation Plan
CHAPTER 8 Development Program and Implementation Plan 8.1 INTRODUCTION The FAA identifies airports that are significant to national air transportation through the development of the National Plan of Integrated
More informationWinona Runway Shift Project
Winona Runway Shift Project Sandy DePottey Dakota-Minnesota ADO Fall MnDOT FAAWorkshop St Cloud, Minnesota November 5, 2014 Update on 0 0 Challenges we faced The main runway 12/30 at Winona Municipal Airport
More informationOffice of Airport Safety and Standards
Office of Airport Safety and Standards Airport Lighting Program To: By: Illuminating Engineering Society Aviation Lighting Committee Government Contacts Subcommittee Michael O Donnell, Director Office
More informationand Forecast Review and Approval Process
LONG BEACH, CALIFORNIA FAA Terminal Area Forecast (TAF) Overview and Forecast Review and Approval Process Paul Devoti Airport Planner Federal Aviation Administration paul.devoti@faa.gov 1 TAF Overview
More informationJACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007
JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 27 11242 1 of 14 Sponsor: City of Naples Airport Authority NPIAS No.: 12-53 Sponsor ID: 122 Airport ID: APF Site No.: 3379.*A 11242 Airport Project ID: 1
More informationMeeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies
Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, 2017 Prepared by: File: Attendees: Shannon Eibert, C&S Companies N93.012.001 See Sign-In List A third meeting was held
More informationAviation Gridlock: Airport Capacity Infrastructure How Do We Expand Airfields?
Aviation Gridlock: Airport Capacity Infrastructure How Do We Expand Airfields? By John Boatright Vice President - Delta Air Lines Properties and Facilities Issue What can be done to expand airfield capacity?
More informationLake Tahoe Airport Master Plan
Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development
More informationAIRPORT PLANNING, DEVELOPMENT AND LAND ACQUISITION
30 th Annual AAAE Basics of Airport Law Workshop and 2014 Legal Update October 19-21, 2014 AIRPORT PLANNING, DEVELOPMENT AND LAND ACQUISITION Desk Reference Chapters 4, 13, 14 & 25 Catherine M. van Heuven,
More informationChapter 5 Airport Development Alternatives
Chapter 5 Airport Development Alternatives Introduction CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-1 Evaluation Process No-Action Alternative CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-2
More informationJUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017
JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017 1 Agenda Program Description Runway Incursions Design and Geometry Deficiencies Runway 8/26 Operations Potential Mitigation Next Steps
More informationFAA Office of Airport Safety and Standards
FAA Office of Airport Safety and Standards Airport and Runway Safety and Technology Presented to: Pan American Regional Aviation Safety Team (PA-RAST) By: Michael Meyers, Deputy Manager Airport Engineering
More informationDallas Love Field Update. Dallas City Council Briefing February 18, 2015
Dallas Love Field Update Dallas City Council Briefing February 18, 2015 Purpose Construction Update Impacts of Wright Amendment Repeal Increase in operations/passengers/ projections Concessions performance
More informationSENATE PASSES FAA REAUTHORIZATION BILL
SENATE PASSES FAA REAUTHORIZATION BILL February 17, 2011 What s at Issue The U.S. Senate has passed S.223, the FAA Air Transportation Modernization and Safety Improvement Act. Why It s Important The legislation
More informationAIR TRANSPORTATION ELEMENT
AIR TRANSPORTATION ELEMENT Sonoma County Permit and Resource Management Department 2550 Ventura Avenue Santa Rosa, CA 95403 Adopted by Resolution No. 08-0808 of the Sonoma County Board of Supervisors September
More informationChapter VI Implementation Planning
Chapter VI Implementation Planning This chapter presents a general financial plan for the capital improvements recommended in the Master Plan. The purpose of the financial plan is to demonstrate that the
More informationSpecific Plan Amendment Study (SPAS) EIR Airfield Alternatives Westside Navigational Aids/Lighting Overview
Appendix E1-9 LAX SPECIFIC PLAN AMENDMENT STUDY REPORT Specific Plan Amendment Study (SPAS) EIR Airfield Alternatives Westside Navigational Aids/Lighting Overview October 2011 Prepared for: Los Angeles
More information