2. SECTOR Energy 1. PROJECT TITLE LOWER VRBAS HYDROPOWER PLANTS

Size: px
Start display at page:

Download "2. SECTOR Energy 1. PROJECT TITLE LOWER VRBAS HYDROPOWER PLANTS"

Transcription

1 1. PROJECT TITLE LOWER VRBAS HYDROPOWER PLANTS. SECTOR Energy 3. LOCATION The lower course of the Vrbas, i.e. the stretch from the city of Banja Luka to the mouth of the Vrbas, is planned to accommodate the construction of four hydropower plants: Trn HPP, Laktasi HPP, Kosjerevo HPP and Razboj HPP. On this section, the Vrbas is about 69 m long and has the available head of 6 m. All planned hydropower plants are located in the territory of the city of Banja Luka. Satellite image of the hydropower plants: Trn HPP, Kosjerevo HPP, Laktasi HPP and Razboj HPP 1

2 4. BRIEF PROJECT DESCRIPTION The first data about the use of the hydropower potential of the lower course of the Vrbas River were made for the needs of the preparation of the Water Management Master Plan in The main feature of this section of the Vrbas River is that it can accommodate the construction of four hydropower plants of small reservoir volumes to be formed for the needs of the head. All four hydropower plants are of run-of-the-river type with derivation canals. Each solution includes a low concrete dam to direct the water into the derivation canal planned to enable navigation. The Water Management Master Plan enabled providing basic information about the potential locations for hydropower plants, which were subsequently tested for the needs of various users. An integral water and energy study of the development of the Vrbas River basin was prepared in 013, as an amendment to the Water Management Master Plan. An overview of the technical and energy features of the hydropower plants according to the Water Management Master Plan is given below. TRN HPP The dam of the Trn HPP comprises an intake structure, a supply canal in the right side and four run-of-the-river fields with low concrete thresholds used for the evacuation of the high thousand-year waters. The storage reservoir is of insignificant volume and 5.15 km long. To provide the elevation of the normal operating level of 145 masl, which is at the same also the maximum backwater elevation, it is necessary to build embankments along the reservoir in order to avoid flooding fertile areas and settlements. The embankments need to be about 4.00 km long on the left bank and about 1.00 km long on the right bank, of maximum height of 7.00 m. On the right bank, about.00 km of the existing road need to be superelevated. For water supply to the turbines, a m long supply canal is planned along the edge of the field. Normal water depth in the canal is 5.00 m. In the end of the supply canal there is an above ground engine room which accommodates two generators with Kaplan turbines and other electromechanical equipment. Trn HPP general information HPP name Trn Run-of-theriverderivation Energy features of the hydropower plant: - Mean annual flow m 3 /s - Normal backwater elevation m - Elevation of minimum operating level m

3 - Tailwater elevation m - Gross head Hb m - Net head Hn m 4.01 MW LAKTASI HPP Downstream from the town of Klasnice to the mouth, the river Vrbas runs through the Lijevce Field and the Srbacko-Nozicka Plain, with many meanders and a very mild head of The total head at those lowest m downstream is m. The project task for the preparation of the Water Management Master Plan of the Vrbas River Basin provides also for an analysis of the possibility of navigation. The proposed variant foresees a pier in Klasnice, which is why the solution for hydropower use of the water on this stretch had to be adjusted to the requirements of navigation. For that purpose, two variants were analyzed: The first variant with six toe-of-dam hydropower plants in a series, so that the tailwater of the upstream hydropower plant is at the same time also the head water of the downstream hydropower plant, The second variant with three derivation and canal hydropower plants. The second variant was adopted and elaborated, with three hydropower plants of identical gross heads (13.0 m) and identical installed power. These are Laktasi HPP, Kosjerevo HPP and Razboj HPP. The construction of the dam and side embankments would form a 4.60 km long storage reservoir of minimum volume required for the safe operation of the hydropower plant. The maximum height of the embankment is 4.50 m and its length is planned to be about 8.50 m. The embankments to form this reservoir and the two downstream hydropower plants are of the same features as for the upstream hydropower plant. The dam comprises an intake structure, a supply canal in the left bank and four run-of-theriver fields with low concrete thresholds. The dimensions of the canal are set based on navigation requirements. The supply canal is m long and of trapeze cross-section. The supply canal is planned in the embankment, of minimum height of 6.00 m, and maximum of 8.00 m. The crest of the embankment is 1.00 m above the elevation of the maximum level. The supply canal lets the waters up to the size of the installed streamflow, and any higher water streamflow is let through the run-of-the-river fields into the bed of the river Vrbas. The tailrace is m long and it is planned to be made throughout the length in the cutting. The engine room is above ground and it is planned to accommodate two generators with Kaplan turbines and other electromechanical equipment. Along with the engine room, construction of a ship lock is planned as its integral part. 3

4 Laktasi HPP general information HPP name Laktasi - Mean annual flow m 3 /s - Normal backwater elevation m - Elevation of minimum operating level m - Tailwater elevation m - Gross head Hb m - Net head Hn 1.34 m KOSJEREVO HPP Run-of-the-riverderivation MW The Kosjerevo HPP is a run-of-the-river-derivation plant. The dam comprises an intake structure, a supply canal in the left bank and four run-of-the-river fields. The run-of-the-river fields are used to evacuate high waters as well as any water higher than the installed streamflow into the bed of the river Vrbas. The storage reservoir is formed by the construction of embankments and it is of minimum volume to enable the safe operation of the hydropower plant. The length of the reservoir is 6.45 km. To form the reservoir it is necessary to build 8.00 km long embankments of maximum height of 8.00 m. The embankments need to be built because the banks of the river Vrbas are low in this most downstream, plain lower course. The other features of the embankments are the same as for the two upstream hydropower plants. The supply canal is m long and of trapeze cross-section, planned in the embankments. The minimum height of the embankment is.50 m, and it is maximum at the engine room 8.00 m. Other features of the tailrace are the same as for the upstream hydropower plant. The engine room is above ground and it is planned to accommodate three generators with Kaplan turbines and other electromechanical equipment. Along with the engine room, a ship lock is planned as its integral part. Kosjerevo HPP general information: HPP name Kosjerevo Run-of-theriverderivation Energy features of the hydropower plant: - Mean annual flow 15.9 m 3 /s - Normal backwater elevation m - Elevation of minimum operating level m 4

5 - Tailwater elevation m - Gross head Hb m - Net head Hn 1.34 m 13.3 MW RAZBOJ HPP The most downstream planned hydropower plant on the river Vrbas is the Razboj HPP, with the elevation of the normal and maximum operating level of masl and the tailwater of masl. The dam of this hydropower plant, like those of the three upstream hydropower plants, comprises an intake structure, a supply canal and four spillway fields dimensioned to evacuate the high thousand-year waters of m 3 /s. The storage reservoir is 4.70 km long and due to the low banks it is necessary to make the embankments 6.50 km long, of maximum height of 7.0 m, and of other features as those of the embankments around the upstream reservoirs. For the supply canal and the tailrace, everything is the same as for the two upstream hydropower plants; they only differ in lengths and heights of embankments and cuttings. The supply canal is m long, with maximum embankment height of 6.50 m. The tailrace is m long with maximum height of the cutting at the engine room of m. The engine room is also above ground, with two generators and Kaplan turbines, whose power depends on the considered variant of the hydropower use of waters, and it is the same as for the two upstream hydropower plants. The engine room is planned to accommodate also other turbine and generator equipment. Construction of a ship lock is planned as an integral part of the engine room. Razboj HPP general information HPP name Razboj Run-of-theriverderivation Energy features of the hydropower plant: - Mean annual flow m 3 /s - Normal backwater elevation m - Elevation of minimum operating level m - Tailwater elevation m - Gross head Hb m - Net head Hn 1.6 m MW 5

6 5. PROJECT DETAILS PROJECT STATUS The hydropower use of the Vrbas river basin was considered in various studies of integral use of water resources in the Vrbas basin. The highest importance for the lower course of the Vrbas lies with the Water Management Master Plan of the Vrbas River Basin of The main problem regarding the use of the data given in this document lies in the fact that a lot of time has elapsed since its preparation and that the changes (social, environmental, legislative, etc.) that have happened in the meantime must be taken into account, since they can affect the planned solutions. Therefore, the Water Management Master Plan of the Vrbas River Basin was updated in 013 (Cowi AS Norway) in order to evaluate various development options of water resources and hydropower development in the Vrbas basin. In order to plan specific investments, this study recommends preparing a full feasibility study for each hydropower plant, as well as a social and an environmental impact assessment. REASONS TO INVEST IN THE PROJECT Electricity is an asset just like any other merchandise, and therefore it has its market price. Demand for electricity in the world, including also this region, is rapidly growing. Under the conditions of a deregulated market, the meeting of own needs is certainly not the only criterion for construction of new plants. In the overall valorization of the project of the Lower Vrbas HPPS, it should be borne in mind that in addition to electricity generation, this hydropower system with its technical solutions would enable also navigation in the derivation canals. 6. PROJECT FINANCING ESTIMATED TOTAL INVESTMENT According to the data from the study Concession Model of Construction of Energy Facilities in the Republic of Srpska (Energo Nor, August 000), the estimated investments for hydropower plants on the Lower Vrbas are as follows: Trn HPP million US$ Laktasi HPP million US$ Kosjerevo HPP million US$ Razboj HPP million US$ That is, the estimated total investment for the Lower Vrbas HPPS amounts to million US$ (data of 000) PLANNED SOURCES OF FINANCING The RS Energy Development Strategy provides for various models of financing in the energy sector: 6

7 - Public financing - this implies a dominant role of the public sector, i.e. financing based on the existing capital accumulation of the Mixed Holding and its subsidiaries, combined with loan funds, - Mixed financing - partnership between the public and the private sector and - Private financing investing by private companies due to limited financing opportunities of the public sector, aimed at market liberalization. The final decision concerning the manner of the Lower Vrbas project implementation and financing will be made by the RS Government. 7. LOCATION FOR PROJECT IMPLEMENTATION The run-of-the-river-derivation plant Trn HPP is foreseen on the stretch of the Vrbas River from the Delibasino Selo HPP to the town of Klasnice, about 1.40 km long. The dam of the Trn HPP is near the town of Trn, at chainage km. The construction of the Laktasi HPP is foreseen downstream from the town of Klasnice, in Lijevce Field, at chainage km of the river Vrbas. The Kosjerevo HPP stretches from chainage 40.5 to 4.40 m of the Vrbas River, i.e. at the length of km. The dam of the Kosjerevo HPP is foreseen immediately downstream from the town of Kosjerevo at chainage km of the Vrbas River, in the area of the vast plain of the Lijevce Field and the Srbacko-Nozicka Plain. The area of the Razboj HPP plant covers the length of km, from chainage 5.00 to chainage 1.10 km, and the downstream section of the river Vrbas which needs to be developed for those needs is under the backwater of the Sava River. The dam of the Razboj HPP is foreseen at chainage km, within the lowest river alluvial plain through which the Vrbas meanders. 8. APPLICANT AND CONTACT INFORMATION Ministry of Industry, Energy and Mining Trg Republike Srpske 1, Banja Luka Telephone: Fax: mier@mier.vladars.net 7

1. PROJECT TITLE LOWER DRINA HYDROPOWER PLANTS

1. PROJECT TITLE LOWER DRINA HYDROPOWER PLANTS 1. PROJECT TITLE LOWER DRINA HYDROPOWER PLANTS The lower course of the Drina River covers the area downstream from the Zvornik HPP, up to the mouth of the Drina into the Sava. This section of the Drina

More information

1. TITLE OF THE PROJECT HYDROPOWER SYSTEM UPPER HORIZONS. 2. SECTOR Energy

1. TITLE OF THE PROJECT HYDROPOWER SYSTEM UPPER HORIZONS. 2. SECTOR Energy 1. TITLE OF THE PROJECT HYDROPOWER SYSTEM UPPER HORIZONS 2. SECTOR Energy 3. LOCATION The term Upper Horizons means the undeveloped part of the hydropower system Trebišnjica, which is located above the

More information

Concessions and PPPs in. Bosnia and Herzegovina

Concessions and PPPs in. Bosnia and Herzegovina Bosnia and Herzegovina Concessions and PPPs in Bosnia and Herzegovina Milomir Amovic Commission for Concessions of BiH Bosnia and Herzegovina is a small Balkan country with 4.5 million people and it composed

More information

Lessons Learned from the Floods this May

Lessons Learned from the Floods this May Building Resiliance to Disasters in Western Balkans and Turkey Design a Regional Multi-Hazard EWS Composed of harmonized National EWS econd Meeting of the Design Team 9 11 September 2014, Durrës, Albania

More information

Catchment and Lake Research

Catchment and Lake Research LARS 2007 Catchment and Lake Research Multilateral versus bilateral agreements for the establishment of river based organizations: comparison of legal, economic and social benefits in the Zambian experience.

More information

2014 floods in Serbia

2014 floods in Serbia 16 th Meeting of WGF, Rim, 9-10 October 2014 2014 floods in Serbia Radovanka Pavlović Ministry of Agriculture and Environmental Protection Republic Water Direcrorate, Belgrade, Serbia Specific cyclone

More information

The Potential of Renewable Energy Sources in Bosnia and Herzegovina

The Potential of Renewable Energy Sources in Bosnia and Herzegovina The Potential of Renewable Energy Sources in Bosnia and Herzegovina Petar M.Gvero, Ph.D.,M.Sc. Assistant Professor Climate Change in South-Eastern European Countries: Causes, Impacts, Solutions Graz, Austria

More information

"Transboundary coordination according to the FD Directive in the shared river basins of Greece

Transboundary coordination according to the FD Directive in the shared river basins of Greece Workshop on Transboundary Issues Budapest March 31st April 1st "Transboundary coordination according to the FD Directive in the shared river basins of Greece Katerina Triantafyllou, ECOS Consulting S.A.

More information

1. PROJECT TITLE HOTEL WITH SUPPORTING FACILITIES WITHIN KASTEL FORTRESS. 2. SECTOR Tourism and hospitality industry. 3. LOCATION Banja Luka

1. PROJECT TITLE HOTEL WITH SUPPORTING FACILITIES WITHIN KASTEL FORTRESS. 2. SECTOR Tourism and hospitality industry. 3. LOCATION Banja Luka 1. PROJECT TITLE HOTEL WITH SUPPORTING FACILITIES WITHIN KASTEL FORTRESS 2. SECTOR Tourism and hospitality industry 3. LOCATION Banja Luka 4. BRIEF PROJECT DESCRIPTION Banja Luka s Kastel Fortress, as

More information

2.1 Physical and Biological Description Matabitchuan River Watershed

2.1 Physical and Biological Description Matabitchuan River Watershed 2.1 Physical and Biological Description Watershed 2.1.1 Physical Description The system watershed has a total area of about 933 km 2 and is a tributary system to Lake Temiskaming and the Ottawa River Drainage

More information

Slobomir Company Inc. Slobomir, Bijeljina,Bosnia and Hercegovina. OPPORTUNITY TO INVEST IN AQUA CITY - Aqua Park in Slobomir, Bijeljina

Slobomir Company Inc. Slobomir, Bijeljina,Bosnia and Hercegovina. OPPORTUNITY TO INVEST IN AQUA CITY - Aqua Park in Slobomir, Bijeljina Slobomir Company Inc. Slobomir, Bijeljina,Bosnia and Hercegovina OPPORTUNITY TO INVEST IN AQUA CITY - Aqua Park in Slobomir, Bijeljina Basic information about the company Slobomir Company Inc. Slobomir,

More information

Project Data Sheet BASIC PROJECT DATA. Rehabilitation and Development of Transport and Navigation on the Sava River Waterway. Full project title:

Project Data Sheet BASIC PROJECT DATA. Rehabilitation and Development of Transport and Navigation on the Sava River Waterway. Full project title: BASIC PROJECT DATA Full project title: Short project title: (acronym) Rehabilitation and Development of Transport and Navigation on the Sava River Waterway Project logo: Project website: www.savacommission.org

More information

EPCG is seated at the address no 2 Vuka Karadžića St. in Nikšić

EPCG is seated at the address no 2 Vuka Karadžića St. in Nikšić hpp Piva CONTENTS: About us 1 hpp "Piva" 3 Construction 5 Technical features 7 Generation 9 Reconstruction and modernization 11 Environment 13 Society 15 Contact 17 About us Elektroprivreda Crne Gore A.D.

More information

ACTIVITIES RELATED TO THE WFD IMPLEMENTATION IN SERBIA AND MONTENEGRO WB, HMWB AND AWB - PRELIMINARY IDENTIFICATION

ACTIVITIES RELATED TO THE WFD IMPLEMENTATION IN SERBIA AND MONTENEGRO WB, HMWB AND AWB - PRELIMINARY IDENTIFICATION ACTIVITIES RELATED TO THE WFD IMPLEMENTATION IN SERBIA AND MONTENEGRO WB, HMWB AND AWB - PRELIMINARY IDENTIFICATION Slobodan Petković, Marina Babic Mladenovic,, Bruno Jurak and Dragana Ninkovic Institute

More information

AMENDMENTS TO THE DECISION 14/12 ON ADOPTION OF CLASSIFICATION OF THE SAVA RIVER WATERWAY

AMENDMENTS TO THE DECISION 14/12 ON ADOPTION OF CLASSIFICATION OF THE SAVA RIVER WATERWAY Conscious of the importance of the Sava River for the economic, social and cultural development of the region, Desirous of development of the inland navigation on the Sava River, Having regard to the European

More information

Paper 87 - INTERNATIONAL COLLABORATION CONCERNING THE USE OF THE DANUBE RIVER IN ROMANIA

Paper 87 - INTERNATIONAL COLLABORATION CONCERNING THE USE OF THE DANUBE RIVER IN ROMANIA Paper 87 - INTERNATIONAL COLLABORATION CONCERNING THE USE OF THE DANUBE RIVER IN ROMANIA CIORTAN R.; DUMITRU M.; SUCIU I.; KRKLJUS D. Ph.D, Corresponding Member of the Romanian Academy of Technical Sciences,

More information

ACTION PLAN FOR THE PERIOD concerning the STRATEGY ON IMPLEMENTATION OF THE FRAMEWORK AGREEMENT ON THE SAVA RIVER BASIN

ACTION PLAN FOR THE PERIOD concerning the STRATEGY ON IMPLEMENTATION OF THE FRAMEWORK AGREEMENT ON THE SAVA RIVER BASIN Doc. 1S-26-O-11-5/1-2 ACTION PLAN FOR THE PERIOD 2011-2015 concerning the STRATEGY ON IMPLEMENTATION OF THE FRAMEWORK AGREEMENT ON THE SAVA RIVER BASIN April 2011 Table of Contents INTRODUCTION... 5 1.

More information

DaHar Danube Inland Harbour Development

DaHar Danube Inland Harbour Development The European Union's Southeast Europe programme supporting DaHar Danube Inland Harbour Development DaHar WP 4 A4: Local Action Plan of the Port of Novi Sad Final version: 30 th of December 2013 This project

More information

Kurobegawa No.4 Power Plant Toyama Prefecture, Japan (Asia)

Kurobegawa No.4 Power Plant Toyama Prefecture, Japan (Asia) IEA Hydropower Implementing Agreement Annex VIII - Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 14-02: Development of Regional Industries Kurobegawa No.4 Power Plant,

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE March 2009 Report No.: AB4607 Project Name

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE March 2009 Report No.: AB4607 Project Name PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE March 2009 Report No.: AB4607 Project Name Rio Bogota Environmental Infrastructure Region LATIN AMERICA AND CARIBBEAN Sector Sewerage (70%); Flood protection

More information

NETWORK OF DANUBE WATERWAY ADMINISTRATIONS data & user orientation SOUTH EAST EUROPE TRANSNATIONAL COOPERATION PROGRAMME ATLAS OF BERTH

NETWORK OF DANUBE WATERWAY ADMINISTRATIONS data & user orientation SOUTH EAST EUROPE TRANSNATIONAL COOPERATION PROGRAMME ATLAS OF BERTH NETWORK OF DANUBE WATERWAY ADMINISTRATIONS data & user orientation SOUTH EAST EUROPE TRANSNATIONAL COOPERATION PROGRAMME ATLAS OF BERTH Republic of Croatia Document ID O 4.2.6 Activity Act. 4.2 Author/organisation

More information

Water Management in Serbia

Water Management in Serbia Water Management in Serbia Stevan Ilincic, M.Sc.C.E. Public Water Management Company "VODE VOJVODINE" Novi Sad, Bulevar Mihajla Pupina 25, Serbia office@vodevojvodine.com, www.vodevojvodine.com Content.

More information

International Bank for Reconstruction and Development International Development Association

International Bank for Reconstruction and Development International Development Association International Bank for Reconstruction and Development International Development Association PROGRESS REPORT TO THE BOARD OF EXECUTIVE DIRECTORS ON THE IMPLEMENTATION OF THE MANAGEMENT ACTIONS IN RESPONSE

More information

Mapping of the theoretical potential for wind energy and small hydropower plants in the region of Peloponnesus

Mapping of the theoretical potential for wind energy and small hydropower plants in the region of Peloponnesus Mapping of the theoretical potential for wind energy and small hydropower plants in the region of Peloponnesus Peloponnesus covers an area of some 21,550 km² (8,320 square miles) and constitutes the southernmost

More information

International Sava River Basin Commission

International Sava River Basin Commission International Sava River Basin Commission Pilot project on climate change: Building the link between the Flood Risk Management planning and climate change assessment in the Sava River Basin climate change

More information

Presentation from 2015 World Water Week in Stockholm. The authors, all rights reserved. SIWI siwi.org

Presentation from 2015 World Water Week in Stockholm.   The authors, all rights reserved. SIWI siwi.org Presentation from 2015 World Water Week in Stockholm www.worldwaterweek.org The authors, all rights reserved SIWI siwi.org WORLD WATER WEEK Stockholm, 23 th August 2015 Co-operative water governance: catalyst

More information

Workshop on WATER-FOOD-ENERGY-ECOSYSTEMS NEXUS ASSESSMENT IN THE SAVA RIVER BASIN. Sectoral goals in the Sava River Basin

Workshop on WATER-FOOD-ENERGY-ECOSYSTEMS NEXUS ASSESSMENT IN THE SAVA RIVER BASIN. Sectoral goals in the Sava River Basin Workshop on WATER-FOOD-ENERGY-ECOSYSTEMS NEXUS ASSESSMENT IN THE SAVA RIVER BASIN Sectoral goals in the Sava River Basin B&H : Strategic orientation in energy sector Zagreb, 4.3. 14. Prof. Tarik Kupusović

More information

ASSET MANAGEMENT AND AUTOMATION: ANDRITZ DIGITAL SOLUTIONS AND CASE STUDIES

ASSET MANAGEMENT AND AUTOMATION: ANDRITZ DIGITAL SOLUTIONS AND CASE STUDIES HYDRO ASSET MANAGEMENT AND AUTOMATION: ANDRITZ DIGITAL SOLUTIONS AND CASE STUDIES DIEGO ALIPRANDI SALTO GRANDE HPP AUGUST 27 TH 2018 COMPREHENSIVE EXPERTISE OF ANDRITZ HYDRO We are a global supplier of

More information

Cofferdam Performance Hurricanes Harvey & Irma

Cofferdam Performance Hurricanes Harvey & Irma Cofferdam Performance Hurricanes Harvey & Irma - 2017 Greg Hammer Senior Geotechnical Engineer CELRH-DSPC-GS DSMMCX Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making 2018 USSD

More information

WP4.4 Cordevole MCA alternatives description

WP4.4 Cordevole MCA alternatives description WP4.4 24/11/2010 version 2.0 Authors Member number and name Sara PAVAN, Matteo Cesca, Alessandro Vianello, Italo Saccardo PP2-ARPAV SHARE - Sustainable Hydropower in Alpine Rivers Ecosystems http://www.sharealpinerivers.eu

More information

REPUBLIC OF SERBIA IRRIGATION AND DRAINAGE REHABILITATION PROJECT (P087964) (Credit No 4105YF and Loan No 7467YF)

REPUBLIC OF SERBIA IRRIGATION AND DRAINAGE REHABILITATION PROJECT (P087964) (Credit No 4105YF and Loan No 7467YF) REPUBLIC OF SERBIA IRRIGATION AND DRAINAGE REHABILITATION PROJECT (P087964) (Credit No 4105YF and Loan No 7467YF) Component 1 Progress of Rehabilitation Summary Report Table 1 Completed s (Status as of

More information

Natural Factors Affecting the Level of Osoyoos Lake

Natural Factors Affecting the Level of Osoyoos Lake Natural Factors Affecting the Level of Osoyoos Lake Background Osoyoos Lake is operated under conditions prescribed by the International Joint Commission (IJC) and Figure 1 shows the ranges within which

More information

Project Data Sheet BASIC PROJECT DATA

Project Data Sheet BASIC PROJECT DATA BASIC PROJECT DATA Full project title: Short project title: (acronym) Improvement of navigation in the joint Bulgarian-Romanian section of the Danube river from km 530 to km 520 Batin and from km 576 and

More information

The Danube-Tisa-Danube Canal System in a Community Setting

The Danube-Tisa-Danube Canal System in a Community Setting The Danube-Tisa-Danube Canal System in a Community Setting Prof. Atila Salvai, Ph. D Stevan Ilincic, M.Sc.C.E. Public Water Management Company "VODE VOJVODINE" Novi Sad, Bulevar Mihajla Pupina 25, Serbia

More information

OICE (Roma) & ANCE (Salerno) delegation in visit to Bucharest Camber of Commerce

OICE (Roma) & ANCE (Salerno) delegation in visit to Bucharest Camber of Commerce BUCHAREST CHAMBER OF COMMERCE AND INDUSTRY 140 years at the service of the business community Business Opportunities OICE (Roma) & ANCE (Salerno) delegation in visit to Bucharest Camber of Commerce 2008,

More information

BRIEF HISTORY OF WATER MANAGEMENT CONDITIONS FROM 16 th TO 21 st CENTURY IN SERBIAN PROVINCE OF VOJVODINA

BRIEF HISTORY OF WATER MANAGEMENT CONDITIONS FROM 16 th TO 21 st CENTURY IN SERBIAN PROVINCE OF VOJVODINA Marko Vuksanović BRIEF HISTORY OF WATER MANAGEMENT CONDITIONS FROM 16 th TO 21 st CENTURY IN SERBIAN PROVINCE OF VOJVODINA FIRST WATER WORKS AT THE BEGINNING OF 18 th CENTURY CONSTRUCTION OF THE GRAND

More information

Lake Chelan Operations

Lake Chelan Operations Lake Chelan Operations IPMA Executive Seminar September 17, 2013 Presented by: Janet Jaspers Chelan County PUD Lake Chelan Hydroelectric Project Today s Discussion Chelan PUD Overview Interesting Facts

More information

Outline of the Shinryu Head Works

Outline of the Shinryu Head Works Outline of the Shinryu Head Works Midori Network Water and farmland protection Midori Network Shinryu 1. History Land reclamation began in 1890 under the initiative of the Uryu Aristocratic Farm, headed

More information

International Sava River Basin Commission - An example of EU/non EU country cooperation in water management

International Sava River Basin Commission - An example of EU/non EU country cooperation in water management International Sava River Basin Commission - An example of EU/non EU country cooperation in water management Improvement and co-operation possibilities in the water sector with non-eu countries Ulm, 29

More information

Project Fiche MASTER PLAN FOR DEVELOPMENT OF THE NAUTICAL TOURISM IN THE SAVA RIVER BASIN

Project Fiche MASTER PLAN FOR DEVELOPMENT OF THE NAUTICAL TOURISM IN THE SAVA RIVER BASIN Project Fiche MASTER PLAN FOR DEVELOPMENT OF THE NAUTICAL TOURISM IN THE SAVA RIVER BASIN 1. Basic information 1.1 Title: Master plan 1.2 Location: Sava River Basin which covers Bosnia and Herzegovina,

More information

Updated on November 28, 2016

Updated on November 28, 2016 Investment Opportunities in Public infrastructure and Public Service Infrastructure ProInversion (State Initiatives and Unsolicited proposals projects) 2016-2018 Updated on November 28, 2016 LONGITUDINAL

More information

Bosnia and Herzegovina

Bosnia and Herzegovina Bosnia and Herzegovina Country Report by Damir Mrđen PC for Water Management for Adriatic Sea RBD in FBIH, by Damir Mrđen 1 Geographic, Social and Economic Context - Total surface area 51,197 km 2, - Population

More information

Project of E-763 Motorway Construction, Section: Belgrade Ostružnica - Požega Boljare/ Border of Montenegro

Project of E-763 Motorway Construction, Section: Belgrade Ostružnica - Požega Boljare/ Border of Montenegro Project of E-763 Motorway Construction, Section: Belgrade Ostružnica - Požega Boljare/ Border of Montenegro I Legal Framework: Preparation of design for construction of E-763 motorway, section: Belgrade

More information

REPUBLIC OF CROATIA MINISTRY OF MARITIME AFFAIRS, TRANSPORT AND INFRASTRUCTURE AGENCY FOR INLAND WATERWAYS

REPUBLIC OF CROATIA MINISTRY OF MARITIME AFFAIRS, TRANSPORT AND INFRASTRUCTURE AGENCY FOR INLAND WATERWAYS REPUBLIC OF CROATIA MINISTRY OF MARITIME AFFAIRS, TRANSPORT AND INFRASTRUCTURE AGENCY FOR INLAND WATERWAYS BRATISLAVA, MAY 3rd, 2012 Inland Waterways in Republic of Croatia Significant waterways in the

More information

HYDROELECTRIC POWER PLANTS ON THE LOWER SAVA RIVER

HYDROELECTRIC POWER PLANTS ON THE LOWER SAVA RIVER HYDROELECTRIC POWER PLANTS ON THE LOWER SAVA RIVER The construction of a chain of hydroelectric power plants on the lower course of the Sava River is a multi-purpose project that makes a significant contribution

More information

ANNEX IV. Heavily Modified Surface Water Bodies in Serbia and Montenegro

ANNEX IV. Heavily Modified Surface Water Bodies in Serbia and Montenegro ANNEX IV Heavily Modified Surface Water Bodies in Serbia and Montenegro Annex IV Heavily Modified Surface Water Bodies in Serbia and Montenegro 1 (1) HMWB Danube Location location Code/abbreviation of

More information

ENLOE HYDROELECTRIC PROJECT FERC PROJECT NO PUBLIC SAFETY PLAN. Final

ENLOE HYDROELECTRIC PROJECT FERC PROJECT NO PUBLIC SAFETY PLAN. Final ENLOE HYDROELECTRIC PROJECT FERC PROJECT NO. 12569 PUBLIC SAFETY PLAN Final November 18, 2013 Okanogan Public Utility District 1331 2nd Ave N PO Box 912 Okanogan, WA 98840 ENLOE HYDROELECTRIC PROJECT FERC

More information

Outlook: FY13 EBITDA guidance $28M - $29M. Pursuing contracted 300MW in 2013 growth strategy. FY13 maiden franked dividend payment expected

Outlook: FY13 EBITDA guidance $28M - $29M. Pursuing contracted 300MW in 2013 growth strategy. FY13 maiden franked dividend payment expected ASX CODE PEA ISSUED CAPITAL Ordinary Shares 360.8M Options 10.7M KPS CONTRACTED CAPACITY 240MW HYDRO CONTRACTED CAPACITY 6MW 14 February 2013 STRONG ORGANIC GROWTH UNDERPINS RECORD PACIFIC ENERGY RESULT

More information

SECTION 3 GENERAL DESCRIPTION OF THE RIVER BASIN

SECTION 3 GENERAL DESCRIPTION OF THE RIVER BASIN SECTION 3 GENERAL DESCRIPTION OF THE RIVER BASIN SECTION 3 GENERAL DESCRIPTION OF THE RIVER BASIN River basin description. A general description of the river basin or subbasin, as appropriate, in which

More information

Discontiguous Features Southern Adirondack Feeder Reservoirs

Discontiguous Features Southern Adirondack Feeder Reservoirs Section number 7 Page 191 Mile 17.32 Buoy R134 marking head of Cayuga-Seneca Canal at outlet of Seneca Lake limit of historic district boundary Discontiguous Features Southern Adirondack Feeder Reservoirs

More information

Wilderness Areas Designated by the White Pine County bill

Wilderness Areas Designated by the White Pine County bill Wilderness Areas Designated by the White Pine County bill SEC. 321. SHORT TITLE. This subtitle may be cited as the `Pam White Wilderness Act of 2006'. SEC. 322. FINDINGS. Congress finds that-- The White

More information

CURRENT CONDITIONS OF LARGE DAMS IN BOSNIA AND HERZEGOVINA

CURRENT CONDITIONS OF LARGE DAMS IN BOSNIA AND HERZEGOVINA CURRENT CONDITIONS OF LARGE DAMS IN BOSNIA AND HERZEGOVINA Slobodan Kovačina, B.Sc.Civ.Eng. 1, Dženan Malović, Dipl.Ing.El.Eng. 2 1ENCOS d.o.o. Sarajevo, 2 IFC, World Bank Group, Sarajevo Office ABSTRACT

More information

Climate Change Impact on Water Resources of Pakistan

Climate Change Impact on Water Resources of Pakistan Pakistan Water and Power Development Authority (WAPDA) Climate Change Impact on Water Resources of Pakistan Glacier Monitoring & Research Centre Muhammad Arshad Pervez Project Director (GMRC) Outline of

More information

The results of the National Tourism Development Strategy Assessments

The results of the National Tourism Development Strategy Assessments The results of the National Tourism Development Strategy Assessments - 2012 (I) The assessment tool In 2012 the Sustainable Tourism Working Group of the CEEweb for Biodiversity prepared a guidance for

More information

WORKSHOP ON THE TRANSPOSAL AND IMPLEMENTATION OF THE EU URBAN WASTE WATER TREATMENT DIRECTIVE (UWWTD 91/271/EEC) IN SERBIA

WORKSHOP ON THE TRANSPOSAL AND IMPLEMENTATION OF THE EU URBAN WASTE WATER TREATMENT DIRECTIVE (UWWTD 91/271/EEC) IN SERBIA WORKSHOP ON THE TRANSPOSAL AND IMPLEMENTATION OF THE EU URBAN WASTE WATER TREATMENT DIRECTIVE (UWWTD 91/271/EEC) IN SERBIA TRANSPOSITION AND IMPLEMENTATION OF THE UWWTD IN SERBIA CURRENT STATUS AND MAIN

More information

STRABAG SE Successful in Eastern Europe

STRABAG SE Successful in Eastern Europe STRABAG SE Successful in Eastern Europe STRABAG at a glance Building Construction & Civil Engineering Commercial and industrial Facilities Public Buildings Civil Engineering Power Plants Housing Environmental

More information

UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF RECLAMATION REGION 4 SALT LAKE CITY, UTAH. May 29, 1958

UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF RECLAMATION REGION 4 SALT LAKE CITY, UTAH. May 29, 1958 UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF RECLAMATION REGION 4 SALT LAKE CITY, UTAH May 29, 1958 FACT SHEET ON PRIME CONTRACT FOR CONSTRUCTION OF FLAMING GORGE DAM GENERAL INFORMATION Bids will

More information

Lepu Medical Technology (Beijing) Co., Ltd. (300003) - Medical Equipment - Deals and Alliances Profile

Lepu Medical Technology (Beijing) Co., Ltd. (300003) - Medical Equipment - Deals and Alliances Profile Lepu Medical Technology (Beijing) Co., Ltd. (300003) - Medical Equipment - Deals and Alliances Profile Lepu Medical Technology (Beijing) Co., Ltd. (300003) - Medical Equipment - Deals and Alliances Profile

More information

Budi Hadi Narendra Harris Herman Siringoringo Chairil Anwar Siregar. Research and Development Center for Forest

Budi Hadi Narendra Harris Herman Siringoringo Chairil Anwar Siregar. Research and Development Center for Forest Budi Hadi Narendra Harris Herman Siringoringo Chairil Anwar Siregar Research and Development Center for Forest Background Coastal management should be wisely done as a part of watershed management. Typologically,

More information

Management of a Large The Danube. Mr. Mitja Bricelj ICPDR President Perth,13 October 2010

Management of a Large The Danube. Mr. Mitja Bricelj ICPDR President Perth,13 October 2010 Management of a Large International ti River Basin: The Danube Mr. Mitja Bricelj ICPDR President Perth,13 October 2010 From the Black Forest From the Black Forest to the Black Sea Human activities damaged

More information

Prof. Dr Željko Vaško Doc. Dr Tihomir Predić MSc Boris Marković

Prof. Dr Željko Vaško Doc. Dr Tihomir Predić MSc Boris Marković First Interim Meeting of the Regional Expert Advisory Working Group on Areas with Natural Constrains Prof. Dr Željko Vaško Doc. Dr Tihomir Predić MSc Boris Marković 29 th June 01 th July, 2016 Andrevlje,

More information

Business Plan INTRODUCTION AIRPORT ENTERPRISE FUND OVERVIEW. Master Plan Guiding Principles

Business Plan INTRODUCTION AIRPORT ENTERPRISE FUND OVERVIEW. Master Plan Guiding Principles 5 Business Plan INTRODUCTION Just as previous chapters have outlined plans for the airport s physical development, this chapter outlines a plan for the airport s financial development. More specifically,

More information

Albania Energy Country Profile. Presented By: Mr. Koli Bele General Secretary of Ministry of Energy and Industry August 25, 2014

Albania Energy Country Profile. Presented By: Mr. Koli Bele General Secretary of Ministry of Energy and Industry August 25, 2014 Albania Energy Country Profile Presented By: Mr. Koli Bele General Secretary of Ministry of Energy and Industry August 25, 2014 Albania Energy Country Profile Albania Energy Country Profile Energy and

More information

Public Seminar 30 October 2018, Lisbon. Water sector in B&H

Public Seminar 30 October 2018, Lisbon. Water sector in B&H Public Seminar 30 October 2018, Lisbon Water sector in B&H Ministry of Foreign Trade and Economic Relations www.mvteo.gov.ba Boško Kenjić, Head of Department Tel: +387 33 262 155 E-mail: bosko.kenjic@mvteo.gov.ba

More information

4180 acre-feet minimum conservation pool

4180 acre-feet minimum conservation pool MEMORANDUM Subject: Bear River Basin Plan SULPHUR CREEK RESERVOIR Date: July 20, 2000 Location: Section 34, Township 14N, Range 119W. Located on Sulphur Creek, tributary to the Bear River. Located approximately

More information

DNEVNIK JVC Novi Sad

DNEVNIK JVC Novi Sad DNEVNIK JVC Novi Sad General Information Full legal name DNEVNIK HOLDING JSC Novi Sad Address Bulevar Oslobodjenja 81, Novi Sad Identification Number 08049815 Core activity 5814 - Publishing of journals

More information

Regulation of ownership steering and basis of other steering

Regulation of ownership steering and basis of other steering 1 (5) Administration Department/Corporate Policy 10 March 2011 Finavia Corporation's ownership strategy policies The Ministry of Transport and Communications has laid down the following enumerated ownership

More information

Suzhou Cultural & Tourism Development, China

Suzhou Cultural & Tourism Development, China AT A GLANCE VALUATION & ADVISORY SERVICES I ASIA FEATURE STORIES Retail Consultancy in Busan, South Korea We completed a retail consultancy study for a landmark shopping mall in Busan, South Korea. The

More information

Study Tour C: Swaziland and Kruger National Park (Pre-tour) 11 to 15 May 2016

Study Tour C: Swaziland and Kruger National Park (Pre-tour) 11 to 15 May 2016 Study Tour C: Swaziland and Kruger National Park (Pre-tour) 11 to 15 May 2016 Introduction This tour combines scenic routes in neighbouring country Swaziland with game watching in the Kruger National Park.

More information

PUBLIC ACCOUNTABILITY PRINCIPLES FOR CANADIAN AIRPORT AUTHORITIES

PUBLIC ACCOUNTABILITY PRINCIPLES FOR CANADIAN AIRPORT AUTHORITIES PUBLIC ACCOUNTABILITY PRINCIPLES FOR CANADIAN AIRPORT AUTHORITIES The Canadian Airport Authority ( CAA ) shall be incorporated in a manner consistent with the following principles: 1. Not-for-profit Corporation

More information

Joan Stemler. Water Control. St. Louis District. November US Army Corps of Engineers BUILDING STRONG

Joan Stemler. Water Control. St. Louis District. November US Army Corps of Engineers BUILDING STRONG St. Louis District Low Water Operations Joan Stemler Water Control St. Louis District November 2012 US Army Corps of Engineers BUILDING STRONG Overview St. Louis District Overview St. Louis District L&D

More information

Lake Manitou Dam and Spillway Upgrade

Lake Manitou Dam and Spillway Upgrade South Bend Lake Manitou Dam and Spillway Upgrade Fort Wayne Rochester Indiana 1828 to 2017 Lafayette Sky Medors, P.E., LFA David Nance, P.G., IDNR Project Background Location: Rochester Indiana, Central

More information

Georgia: Flash floods

Georgia: Flash floods Georgia: Flash floods DREF operation n MDRGE003 FF-2011-000071-GEO 25 June 2011 The International Federation of Red Cross and Red Crescent (IFRC) Disaster Relief Emergency Fund (DREF) is a source of unearmarked

More information

Amended Application for New License Major Project Existing Dam

Amended Application for New License Major Project Existing Dam Amended Application for New License Major Project Existing Dam Exhibit A Project Description Security Level: Public Prepared by: Yuba County Water Agency 1220 F Street Marysville, CA 95901 www.ycwa.com

More information

BHP Billiton Limited - Strategy, SWOT and Corporate Finance Report

BHP Billiton Limited - Strategy, SWOT and Corporate Finance Report BHP Billiton Limited - Strategy, SWOT and Corporate Finance Report BHP Billiton Limited - Strategy, SWOT and Corporate Finance Report The Business Research Store is run by Sector Publishing Intelligence

More information

Datum Issues in the Red River of the North Basin ----

Datum Issues in the Red River of the North Basin ---- Datum Issues in the Red River of the North Basin ---- Scoping Document May 1999 Russell E. Harkness, Hydrologist United States Geological Survey Water Resources Division 2 EXECUTIVE SUMMARY Two datum issues

More information

REVIEW OF HPP ZHUR FEASIBILITY STUDY INCLUDING PREPARATION OF PRELIMINARY EIA AND PRELIMINARY SA

REVIEW OF HPP ZHUR FEASIBILITY STUDY INCLUDING PREPARATION OF PRELIMINARY EIA AND PRELIMINARY SA REVIEW OF HPP ZHUR FEASIBILITY STUDY INCLUDING PREPARATION OF PRELIMINARY EIA AND PRELIMINARY SA REPUBLIKA E KOSOVËS REPUBLIKA KOSOVA REPUBLIC OF KOSOVO Ministria e Energjisë dhe Minierave Ministarstvo

More information

MARITIME DIRECTORATE OF RAVENNA. DECREE no. 21/2016

MARITIME DIRECTORATE OF RAVENNA. DECREE no. 21/2016 MARITIME DIRECTORATE OF RAVENNA DECREE no. 21/2016 The Maritime Director of Emilia Romagna, HAVING REGARD TO his Decree no. 13/2014 dated 30 December 2014, regarding pilotage rates in the Port of Ravenna

More information

Millennium and Copthorne Hotels plc - Strategy, SWOT and Corporate Finance Report

Millennium and Copthorne Hotels plc - Strategy, SWOT and Corporate Finance Report Millennium and Copthorne Hotels plc - Strategy, SWOT and Corporate Finance Report Millennium and Copthorne Hotels plc - Strategy, SWOT and Corporate Finance Report The Business Research Store is run by

More information

UNVEILING AND OPENING TO TRAFFIC OF THE THIRD GUADARRAMA TUNNEL ON THE AP-6 MOTORWAY

UNVEILING AND OPENING TO TRAFFIC OF THE THIRD GUADARRAMA TUNNEL ON THE AP-6 MOTORWAY Iberpistas, S.A. Concesionaria del Estado Sociedad Unipersonal Tel. +34 91 574 81 00 a6informacion@iberpistas.es THIRD GUADARRAMA TUNNEL UNVEILING AND OPENING TO TRAFFIC OF THE THIRD GUADARRAMA TUNNEL

More information

UNWTO Regional Workshop for Africa Addis Ababa, Ethiopia, September, 2016

UNWTO Regional Workshop for Africa Addis Ababa, Ethiopia, September, 2016 UNWTO Regional Workshop for Africa Addis Ababa, Ethiopia, 15-17 September, 2016 Presentation by Mr. Solomon Tadesse CEO, Ethiopian Tourism Organization INSTITUTIONAL ARRANGEMENTS TO TRANSFORM THE ETHIOPIAN

More information

Terms of Reference (ToR) for a Short-Term assignment

Terms of Reference (ToR) for a Short-Term assignment Terms of Reference (ToR) for a Short-Term assignment Technical assistance requested Expert for climate change mitigation and adaptation Project Title Outline of the Climate Adaptation Strategy and basin-wide

More information

OBČINA BOVEC. A3-NET project team. Colleges from Ministry of Economy of the Herzegbosnian Canton

OBČINA BOVEC. A3-NET project team. Colleges from Ministry of Economy of the Herzegbosnian Canton Newsletter Nr. 2; A3-NET Strengthening and NETworking of small Airport facilities in Adriatic Areas A3-NET, 24.4.2012, Prot.Nr. 3512-07/2009-238 http://www.a3-net.info Here is second edition of the newsletter,

More information

Appendix C AIRPORT LAYOUT PLANS

Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development

More information

INVITATION FOR EXPRESSION OF INTEREST

INVITATION FOR EXPRESSION OF INTEREST 1. Introduction INVITATION FOR EXPRESSION OF INTEREST Indah Water Konsortium Sdn Bhd (Company No. 211763-P) ( IWK ) is seeking for Expression of Interest (EOI) from consultants registered with the Ministry

More information

SATELLITE CAPACITY DIMENSIONING FOR IN-FLIGHT INTERNET SERVICES IN THE NORTH ATLANTIC REGION

SATELLITE CAPACITY DIMENSIONING FOR IN-FLIGHT INTERNET SERVICES IN THE NORTH ATLANTIC REGION SATELLITE CAPACITY DIMENSIONING FOR IN-FLIGHT INTERNET SERVICES IN THE NORTH ATLANTIC REGION Lorenzo Battaglia, EADS Astrium Navigation & Constellations, Munich, Germany Lorenzo.Battaglia@Astrium.EADS.net

More information

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET Report No. 3 of the Regional Council Meeting of March 28, 2013 1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET The recommends: 1. Receipt

More information

Investigation of River Stage Simulation Before and After Bengoh Dam Construction: Case Study of Sarawak River Basin Malaysia

Investigation of River Stage Simulation Before and After Bengoh Dam Construction: Case Study of Sarawak River Basin Malaysia International Journal of Science and Engineering Investigations vol. 4, issue 42, July 2015 ISSN: 2251-8843 Investigation of River Stage Simulation Before and After Bengoh Dam Construction: Case Study

More information

Climate Change Impacts on Glacial Lakes and Glacierized Basins in Nepal and Implications for Water Resources

Climate Change Impacts on Glacial Lakes and Glacierized Basins in Nepal and Implications for Water Resources Climate Change Impacts on Glacial Lakes and Glacierized Basins in Nepal and Implications for Water Resources Suresh R. Chalise 1, Madan Lall Shrestha 2, Om Ratna Bajracharya 2 & Arun Bhakta Shrestha 2

More information

ACCOMMODATION from the supply side

ACCOMMODATION from the supply side UNWTO Statistics Capacity Building Program WORKSHOP IV 18-20 November 2009 Vienna, Austria Reporting on the observation of collective ACCOMMODATION from the supply side DijanaMili, MinistryofTourism of

More information

Network of International Business Schools

Network of International Business Schools Network of International Business Schools WORLDWIDE CASE COMPETITION Sample Case Analysis #1 Qualification Round submission from the 2015 NIBS Worldwide Case Competition, Ottawa, Canada Case: Ethiopian

More information

PUBLIC COMPANY VODE VOJVODINE NOVI SAD WATER MANAGEMENT

PUBLIC COMPANY VODE VOJVODINE NOVI SAD WATER MANAGEMENT PUBLIC WATER MANAGEMENT COMPANY VODE VOJVODINE NOVI SAD Water management in Vojvodina stands for one of the most complex systems, which affects its inhabitants in both direct and indirect manner. The nexus

More information

Investor Relations Update October 25, 2018

Investor Relations Update October 25, 2018 General Overview Investor Relations Update Revenue The company expects its fourth quarter total revenue per available seat mile (TRASM) to be up approximately 1.5 to 3.5 percent year-over-year. Fuel Based

More information

Survey of Rodman Reservoir and middle-ocklawaha River springs during spring 2008 draw-down conditions: FWC and FWS

Survey of Rodman Reservoir and middle-ocklawaha River springs during spring 2008 draw-down conditions: FWC and FWS Survey of Rodman Reservoir and middle-ocklawaha River springs during spring 2008 draw-down conditions: FWC and FWS Date of Survey: February 26, 2008 Survey conducted by: Dawn Jennings, USFWS Nicole Adimey,

More information

BHP Billiton Limited (BHP) - Financial and Strategic SWOT Analysis Review

BHP Billiton Limited (BHP) - Financial and Strategic SWOT Analysis Review BHP Billiton Limited (BHP) - Financial and Strategic SWOT Analysis Review BHP Billiton Limited (BHP) - Financial and Strategic SWOT Analysis Review Sector Publishing Intelligence Limited (SPi) has been

More information

Danube River Basin District

Danube River Basin District Danube River Basin District Part B National Report BULGARIA Information required according to Art. 3 (8) and Annex I of the EU Water Framework Directive prepared by Ministry of Environment and Water 2

More information

Susitna-Watana Hydroelectric Project (FERC No ) Recreation Resources Study Study Plan Section Study Implementation Report

Susitna-Watana Hydroelectric Project (FERC No ) Recreation Resources Study Study Plan Section Study Implementation Report (FERC No. 14241) Recreation Resources Study Study Plan Section 12.5 2014 Study Implementation Report Prepared for Prepared by AECOM November 2015 TABLE OF CONTENTS 1. Introduction... 4 2. Study Objectives...

More information

(STOCK CODE: 3633.HK)

(STOCK CODE: 3633.HK) To: Business Editor For Immediate Release (STOCK CODE: 3633.HK) Announces Its Annual Results for the Year Ended 31 December 2013 Turnover Increased by 13.7% to HK$3,130,885,000 Profit Attributable to Owners

More information

Georgian Co-Investment Fund. April 2016

Georgian Co-Investment Fund. April 2016 Georgian Co-Investment Fund April 2016 Georgian Co-Investment Fund (GCF) Overview Established in September 2013 Georgia-dedicated private equity fund Limited Partnership set up according to international

More information

Cathay Pacific Airways Limited (293) - Financial and Strategic SWOT Analysis Review

Cathay Pacific Airways Limited (293) - Financial and Strategic SWOT Analysis Review Cathay Pacific Airways Limited (293) - Financial and Strategic SWOT Analysis Review Cathay Pacific Airways Limited (293) - Financial and Strategic SWOT Analysis Review Sector Publishing Intelligence Limited

More information