1 Transportation Roundtable Executive Committee July 17, 2017 Revenue Projections (Green Sheet) As of June 12, 2017 April 2018 March 2028 Total Revenue $637,746,847 75% for Project Investment $478,310,135 List 25% for Local Shares $159,436,712 1
2 Executive Committee / Roundtable Schedule Executive Committee Meetings to review projects and develop Draft Investment List 7/17; 7/24; 7/31; 8/7; 8/14 Executive Committee to hold two public hearings on Draft Investment List week of 8/14 Final Executive Committee Meeting to approve Final Recommended Investment week of 8/21 Roundtable meeting to approve Investment List and Call for Election week of 8/21 (can be immediately following Executive Committee) To meet deadlines of Secretary of State, call for the election must take place by August 25, 2017 for the November 7, 2017 election. MGRC TSPLOST Executive Committee TIA Update Kelvin Mullins, State TIA Administrator July 17,
3 TIA Office State TIA Administrator Kelvin Mullins Program Management AECOM TIA Regional Coordinator Kenneth Franks TIA Regional Coordinator Eric Wilkinson TIA Regional Coordinator (Pending New TIA Regions) TIA Regions Central Savannah River Area River Valley Heart of Georgia Altamaha 3
4 TIA Regions (with possible additions of Middle and Southern Georgia Regions) River Valley Middle Georgia Central Savannah River Area Heart of Georgia Altamaha Southern Georgia TIA- Thru May 2017 Collections Region Total Approved Investment List (75%) Local Discretionary (25%) CSRA $284,453,128* $213,339,846* $71,113,282* River Valley $200,177,098* $150,132,823* $50,044,274* Heart of Georgia $126,587,060* $94,940,295* $31,646,765* Totals (*rounded amounts) $611,217,286 $458,412,964 $152,804,321 4
5 TIA Update thru May 2017 Original Revenue Forecast Actual Revenue Collected % Behind Forecast CSRA $338,235,002* $284,453,128* 15.9% River Valley $240,178,895* $200,177,098* 16.7% Heart of Georgia $159,633,527* $126,587,060* 20.7% Totals (*rounded amounts) $738,047,424 $611,217, % Challenges/Lessons Learned SCOPE Project Delivery Signal Warrants for Traffic Signals Final Investment List Project Description Don t be too specific Allow flexibility 5
6 Project Scope Examples US 280 Widening, Crisp County Project Description: The Project, widening US 280, begins at the Crisp County Line on the East end of the Lake Blackshear Bridge and runs 7.60 miles east to the SR 300 Connector, West of Cordele. Project components include widening the existing two lanes to four lanes with a depressed grassy median (which entails environmental documentation and implementation, clearing, grading and draining the ROW), base and paving of the new lanes and shoulders, resurfacing the existing lanes, grassing, striping and marking. It will also provide numerous intersection improvements along the route. Project Descriptions Improvements to District Line Road, Sumter County Project Description: Improvements to District Line Road from U.S. 280 to SR 49. 6
7 Challenges/Lessons Learned SCHEDULE Project Schedules/Delivery Bands Delivery Timeframe Look for Early Successes Construction Impacts Augusta Downtown Area Augusta Downtown Revitalization Projects 7
8 Challenges/Lessons Learned BUDGET Program and Project Cost Estimates Fully Funded Projects Project Funds are not Transferrable Administration Inflation Blended Projects with Federal Funds Logical Termini Environmental clearance Project Delivery Time River Valley Project Overview Harris Talbot Taylor 23 Total Projects Marion Macon Schley Stewart Sumter Randolph Dooly Crisp 8 In Construction 2 Projects Completed $69,742,698 Total Expenditure to Date (as of ) 8
9 METRA Improvements, Express Bus Park-N-Ride Services (Muscogee) US 27/SR 1 Reconstruction & Widening (Randolph) 9
10 South Lumpkin Trail (Muscogee) HOGA Project Overview Laurens Johnson Emanuel Candler 764 Total Projects Wilcox Dodge Telfair Jeff Davis Evans Tattnall Appling Wayne 96 In Construction 310 Projects Completed $64,964,817 Total Expenditure to Date (as of ) 10
11 336 total miles paved to date 299 completed resurfacing projects Windmill Road (Candler) 11
12 Oconee River Bridge (Laurens) Cartee Lee Road (Emanuel) 12
13 Walke Dairy Bridge (Laurens) CSRA Project Overview Wilkes Lincoln Columbia Warren Richmond Hancock Jefferson Burke Washington Jenkins 84 Total Projects 32 In Construction 21 Projects Completed $108,998,145 Total Expenditure to Date (as of ) 13
14 Daniel Field Hangar Door Restoration (Richmond) Hoyt Braswell Road (Jefferson) 14
15 Bridge Replacement & Rehabilitations (Richmond) Broad Street over Augusta Canal Old Waynesboro Road over Spirit Creek Scott s Way over Rae s Creek 11 th Street over Augusta Canal Riverwatch Parkway (Richmond) 15
16 Discretionary Funds Talbot & Sumter Counties Construction and maintenance equipment Appling County: Center turn lane for school entrance Harris County Mulberry Road Repaving City of Dublin School Zone Beacons City of Dublin SR 19 Sidewalk Extensions Program Contacts Kelvin Mullins TIA Administrator (404) Eric Wilkinson TIA Regional Coordinator CSRA & HOGA (478) Kenneth Franks TIA Regional Coordinator River Valley & HOGA (404) Shrujal Amin TIA Program Manager (404) tia.com 16
17 Notes for Initial Project Reviews #1 priority of each local government (if known) in red *on 2012 Final Investment List (as FYI) Goal of today, 7/24 and 7/31 is to understand all of the projects Cost estimates are less important today Today s Projects 76 from Macon Bibb, Putnam, Wilkinson counties Macon Bibb Project Types (31) Type Number Aviation 1 Transit 1 Bridge 2 Widening 3 Construction 3 Signalization 5 Resurfacing 16 17
18 Macon Bibb Projects MGRC 104 Extend Runway 5 23 at Middle Georgia Regional Airport* Current is 6,501 feet; proposed expansion to 8,001 Includes tunnel/ bridge at Avondale Mill/ Sardis Church Road, airfield lighting, signage, pavement, fill material, and drainage. * 2012 Final Investment List Macon Bibb Projects (cont) MGRC 105 Peake Road Bridge Replacement Posted for less than full capacity / low sufficiency rating School Bus route MGRC 106 Tucker Road Bridge Replacement Existing timber pile bridge (9,690 vehicles per day) Low weight limits/ low sufficiency rate MGRC th Street Truck Route* Enhancements to 7th Street and connecting streets to encourage trucks to minimize travel along Martin Luther King Jr Blvd/Broadway through downtown Macon and increase travel along the 7th Street Corridor. This project will include a new bridge over Brosnan Yard entrance, improvements to intersections along 7th St, including MLK at Walnut St, Walnut at 7th St, Edgewood Ave and 7th St, Eisenhower Parkway at Edgewood Ave, and Broadway and Eisenhower Parkway. Also includes new or improved bike and pedestrian facilities along the corridor, including those on Riverside Drive between MLK and Central City Park. * 2012 Final Investment List 18
19 Macon Bibb Projects (cont) MGRC 108 Sardis Church Road Extension to I 16* New construction to extend Sardis Church Road/ Avondale Mill Road to I 16 at Sgoda Road MGRC 109 Spring Street / Pine Street Roundabout Intersection improvement Construct a roundabout at the intersection of Spring Street and Pine Street (five legged intersection with enhance the entry to the Navicent Health Campus) * 2012 Final Investment List Macon Bibb Projects (cont) MGRC 110 Bethel Church / Redding Way from Eisenhower to Mt. Pleasant Church MGRC 111 Weslyan Drive from Rivoli Drive to Riverside Drive MGRC 112 Napier Avenue from Coleman Avenue to Forsyth Road MGRC 113 Columbus Road from SR 74 to Eisenhower Parkway MGRC 114 Barrington Hall Drive from Zebulon Road to Foster s Green MGRC 115 Rocky Creek Road from Houston Avenue to Bloomfield Road MGRC 116 Presidential Parkway from Log Cabin Drive to Eisenhower Parkway MGRC 117 Hartley Bridge Road from I 75 to Houston Road MGRC 118 Walden Road from Houston Road to Duffy Drive 19
20 Macon Bibb Projects (cont) MGRC 119 Joe Tamplin Industrial Blvd from Ocmulgee East Blvd to Riggins Mill Road MGRC 120 Riggins Mill Road from Emery Highway to Twiggs County line MGRC 121 Rivoli Drive from Old Forsyth Road to Forsyth Road MGRC 122 Zebulon Road from Forsyth Road to Peake Road MGRC 123 Tucker Road from Thomaston Road to Forsyth Road MGRC 124 Williamson Road from Pio Nono Avenue to Bloomfield Road MGRC 125 Upper River Road from Jones County line to Clinton Road Macon Bibb Projects (cont) MGRC 126 Upgrade Pio Nono Avenue Signalization Vineville to Guy Paine Road (15 intersections) MGRC 127 Install traffic signal Houston Road and Allen Road MGRC 128 Install traffic signal Hartley Bridge Road and School Road MGRC 129 Replace traffic signal Little Richard Penniman Blvd and Plant Street MGRC 130 Install traffic signal / roundabout Bowman Road and Wesleyan Drive 20
21 Macon Bibb Projects (cont) MGRC 131 Transit Services* Match for Fleet Recapitalization (20%) 2 electric buses per year 2 diesel buses per year 2 para transit buses per year Match for Operations per year (50%) Terminal Station improvements (100%) * 2012 Final Investment List Macon Bibb Projects (cont) MGRC 132 MGRC 133 MGRC 134 Bass Road Widening from New Forsyth to Bowman Road Bass Road Widening from Bowman Road to Westchester Dr. Forest Hill Widening from Vineville/ Forsyth to Wimbish Road (Phase 2) 21
22 Putnam Project Types (10) Type Number Construction 1 Intersection Improvements 5 Operational / Safety 2 Bike and Pedestrian 2 Eatonton Projects Intersection Improvements MGRC 52 Lower Harmony Road / US 441 Business MGRC 53 Rock Lane MGRC 54 S Jefferson / US 441 Business MGRC 55 SR 16/ SR 44 (see also MGRC 165)* Bike and Pedestrian MGRC 56 Oconee Street MGRC 57 Westside of SR 24 (completion of TE Project) New Construction MGRC 168 NE Bypass and Roundabout * 2012 Final Investment List 22
23 Putnam County Projects Intersection Improvements MGRC 165 SR 16/ SR 44 (see also MGRC 55)* Safety / Operational Improvements MGRC 166 Harmony Road MGRC 167 Twin Bridges Road New Construction MGRC 168 NE Bypass and Roundabout* * 2012 Final Investment List Wilkinson Project Types (35) Type Number Resurfacing Allentown 1 Gordon 3 Irwinton 6 (plus one intersection) Ivey 4 McIntyre 6 Toomsboro 1 Wilkinson County 13 23
24 Wilkinson County Projects Allentown MGRC 01 Allen Avenue Gordon MGRC 59 Milledgeville Road MGRC 60 Macon Road MGRC 61 Ball Park Road Irwinton MGRC 75 Wriley Road/ Old 441 / Parker Street Intersection Improvements MGRC 76 Asbell Road MGRC 77 Bacon Street MGRC 78 East Banks Street MGRC 79 Old 441 MGRC 80 Pine Street MGRC 81 Wriley Road Wilkinson County Projects (cont) Ivey MGRC 82 Industrial Blvd MGRC 83 Chickasaw Drive MGRC 84 Pinebluff Drive MGRC 85 Magnolia Avenue McIntyre MGRC 135 Vinson Road MGRC 136 Railroad Street MGRC 137 Pine Circle MGRC 138 Wriley Circle MGRC 139 Dedrick Road MGRC 140 Macon Road Toomsboro MGRC 169 Shephard Street 24
25 Wilkinson County Projects (cont) MGRC 182 Nunn Wheeler Road MGRC 183 Old Balls Ferry Road MGRC 184 Old Macon Road MGRC 185 Asbury Church Road MGRC 186 Council McCranie Road MGRC 187 Quinn Williams Road MGRC 188 Cross Justice Road MGRC 189 Mt. Carmel Road MGRC 190 Old Toomsboro Road MGRC 191 Papermill Road Wilkinson County Projects (cont) MGRC 192 JR Simms Road* MGRC 193 Kaolin Road MGRC 194 Gordon McIntyre Road* *2012 Final Investment List 25
26 Summary Next Meeting July 24, 2017 Baldwin, Crawford, Jones, Monroe County Projects (51 Projects) Process Change? 26
AREA 1 SOUTH CENTRAL DOWNTOWN, INCLUDING HERITAGE TRAIL RIVERWALK Bound by the following streets or roads BORDERS:
AREA 1 SOUTH CENTRAL DOWNTOWN, INCLUDING HERITAGE TRAIL RIVERWALK Bound by the following streets or roads NORTHEAST - Forsyth St. and Hemlock St. to past 11 th St. NORTHWEST - I-75. SOUTH - Eisenhower
More informationO.C.G.A GEORGIA CODE Copyright 2014 by The State of Georgia All rights reserved. *** Current Through the 2014 Regular Session ***
O.C.G.A. 15-6-3 GEORGIA CODE Copyright 2014 by The State of Georgia All rights reserved. *** Current Through the 2014 Regular Session *** TITLE 15. COURTS CHAPTER 6. SUPERIOR COURTS ARTICLE 1. GENERAL
More informationCONTACT INFORMATION - APPENDIX A
CONTACT INFORMATION - APPENDIX A LOCAL ISSUING AUTHORITY For a complete list of the Local Issuing Authorities throughout Georgia go to www.gaswcc.org and click on E & S Information and then Local Issuing
More information4124 Arkwright Road, Suite 1, Macon, GA (478) Fax (478)
FOR SALE: LARGEST CONTIGUOUS TRACT IN NORTH MACON Approximately 216 contiguous acres Owner will divide (ask Agent for details) Mixed use zoning (commercial, residential and multi-family) Water and sewer
More informationFORT WORTH DISTRICT. Springtown Area Projects. Loyl C. Bussell, P.E. Acting District Engineer. Thursday, February 8, 2018 Date.
FORT WORTH DISTRICT Springtown Area Projects Loyl C. Bussell, P.E. Acting District Engineer Photo by Liam Frederick Footer Text Thursday, February 8, 2018 Date Maintaining a Safe System TxDOT is responsible
More informationTHE IMPACT OF THE TRANSPORTATION INVESTMENT ACT ON COLUMBUS & THE STATE OF GEORGIA GEORGIA PLANNING ASSOCIATION SEPTEMBER 27, 2017
THE IMPACT OF THE TRANSPORTATION INVESTMENT ACT ON COLUMBUS & THE STATE OF GEORGIA GEORGIA PLANNING ASSOCIATION SEPTEMBER 27, 2017 RICK JONES, AICP DIRECTOR OF PLANNING COLUMBUS CONSOLIDATED GOVERNMENT
More informationNovember 21, 2012 Barbara Kelleher, (954)
November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related
More informationDistrict Construction Progr am. John R. Kasich, Ohio Governor Jerry Wray, ODOT Director Steve Mary, P.E., District Deputy Director
District 8 2014 Construction Progr am Preble Greene Butler Warren Clinton Lebanon Hamilton Clermont Serving Butler, Clermont, Clinton, Greene, Hamilton, Preble and Warren Counties. John R. Kasich, Ohio
More informationCurrent Amendment or Modification. Prior Amendment or Modification. All other Amendments and Modifications
Individual HIGHWAYS Bridge - On State System SR46598 P-4 Region 4 Bridge - On System Pool CDOT Region 4 Bridge Federal National Highway Performance Program - - 956 483 719 719 2,877 State State Highway
More informationOctober 16, 2015 NEWS REPORT NO. 5137
NEWS REPORT NO. 5137 October 16, 2015 News Report Contents: GDOT Awards September 18, 2015 Letting GDOT Apparent Low Bidders October 16, 2015 Letting 2160 Satellite Blvd., NW Suite 100 Duluth, GA 30097
More information2009 Regional Solicitation Selected Projects*
2009 Regional Solicitation Selected Projects* Special Federal Allocation from the MPO Mn/DOT I-494/TH169 Interchange Reconstruction $34,000,000 Surface Transportation Program - Urban Guarantee AR-09-10
More informationFDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015
From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction
More informationWeekly East Tennessee Construction Report for May 31-June 6, 2018
Weekly East Tennessee Construction Report for May 31-June 6, 2018 Thursday, May 31, 2018 01:30pm ANDERSON COUNTY, SR 62 between Union Valley Road and SR 162: Motorists should be alert for possible lane
More informationFDOT Treasure Coast Traffic Report through
FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;
More information(Jo Daviess, Stephenson, Winnebago, Boone, Carroll, Ogle, Whiteside, Lee, Rock Island, Henry counties)
District 1 (Cook, DuPage, Will, McHenry, Kane and Lake Counties) District 2 -Jane Byrne Interchange reconstruction in Chicago o $76.6 million; $31.8 million spent o Spread over four separate contracts
More informationIt!:! December 7, Citizen's Review Panel (CRP) Members Mr. C.M. "Buddy" Leger, Chairman River Valley Special District
Russell McMurry,P.E., Commissioner GEORGIA DEPARTMENT OF TRANSPORTATION One Georgia Center, 600 West Peachtree Street, NW Atlanta, Georgia 30308 Telephone: (404} 631-1000 December 7, 2016 Citizen's Review
More informationUniversity Region Non-Motorized Plan 2015
Non-Motorized Transportation Non-motorized facilities are important components to the transportation system. They provide an environmentally-friendly, low-cost mode of travel. Some of the facilities can
More informationSummer Camp Transportation Details
Summer Camp Transportation Details Drivers Drop off at Will-A-Way is Sunday, June 12 th between 3:00-4:30PM. We are busy preparing for your campers so please do not arrive before 3PM as the gates will
More informationNon-Motorized Transportation
Non-Motorized Transportation Non-motorized facilities are important components to the transportation system. They provide an environmentally-friendly, low-cost mode of travel. Some of the facilities can
More informationCurrent Amendment or Modification. Prior Amendment or Modification. All other Amendments and Modifications. FY TIP Project Title/Location Number
Individual STIP ID Improvement Type Source of Funds Type/ Program TOTAL HIGHWAYS Bridge - On State System SR46598 P-4 Region 4 Bridge - On System Pool CDOT Region 4 Bridge Federal National Highway Performance
More informationTENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS
Florida Department of TRANSPORTATION - DISTRICT ONE TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS 2017-2021 DISTRICT ONE HEADQUARTERS (BARTOW) SOUTHWEST AREA OFFICE (FORT MYERS) MISSION STATEMENT The Department
More informationFDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015
June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane
More informationTENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. No Projects Under Development in Blount County
SR-33 No Projects Under Development in Blount County PIN: 118351.00 FROM OLD KNOXVILLE PIKE TO EAST LINCOLN ROAD Length - 0.6 (Intersection Improvements and Signals) SR-33 US-411 PIN: 118422.00 INTERSECTION
More informationLPA Location Federal Funds Awarded to LPA. Fairfield Avenue, SR 101 and Oxford Pike
LPA Location Federal Funds Awarded to LPA Allen County Allen County Bridge #271: South County Line Road over St Marys River $1,091,200.00 Boone County On CR 500W, approximately 750' South of Middle Jamestown
More informationFDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016
March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related
More informationuser s guide to Transportation Improvements in Astoria Planning Efforts outside Astoria for more information, contact:
The Miles Crossing/ Jeffers Garden transportation plan (underway), will identify needed improvements to the Warrenton Astoria Highway and local street improvements to serve expected growth in the Miles
More informationAmerican Job Center Finder
American Job Finder Job Finder Name Address Phone Hours Gainesville, Rockdale Resource Gwinnett WIA Resource Waycross, City of Atlanta Development Agency Newnan, Athens, Cartersville, Carrollton, Thomasville,
More information* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties
New York State Department of Transportation 2008 Highway/Bridge Construction Projects * Short term resurfacing projects are not included in this listing. Genesee 4T39.07 Project: Annual Rural County Sign
More informationAviation Summit Design and Construction Services
Aviation Summit 2017 Design and Construction Services Agenda: Terminal 3 Modernization PHX Sky Train Stage 2 Terminal 4 S1 Concourse & Apron Other Capital Program Projects Terminal 3 Modernization Processor
More informationPalm Beach County Traffic Report July 13 through July 20, 2012
For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be
More informationNortheast Corridor Transportation Update
Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer
More informationApril 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014
April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures
More informationCurrent Amendment or Modification. Prior Amendment or Modification. All other Amendments and Modifications. FY TIP Project Title/Location
STIP ID HIGHWAYS Bridge - On State System SR46598 P-4 Region 4 Bridge - On System Pool CDOT Region 4 Bridge Federal National Highway Performance Program - - 956 483 719 719 2,877 State State Highway Fund
More informationOctober 31, 2014 Chuck McGinness, (954)
From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October
More informationGulf Coast MPO Obligated Projects
Gulf Projects */ 104866/801000 STPD-9370-00(004) Dedeaux Rd. From Three Rivers Rd. to SR 605. MS $3,259,353 106448/701000 STP-8971-00(005) City of City of - widen to include three lanes on Hospital Road
More informationCONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND
BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK
More informationNEWS REPORT NO July 19, 2013
NEWS REPORT NO. 5110 July 19, 2013 News Report Contents: GDOT Awards June 21, 2013 Letting GDOT Apparent Low Bidders July 19, 2013 Letting 2160 Satellite Blvd., NW Suite 100 Duluth, GA 30097 Telephone
More information2 Construction Program
2018 C P 2018 Districtonstruction 2 Construction Program rogram district 2 Governor John Kasich ODOT Director Jerry Wray District Deputy Director Pat McColley, PE, SI 2018 Construction Program Thank you
More informationFY FY 2022 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) North Front Range Transportation & Air Quality Planning Council
Bridge - On State System PREVIOUS ENTRY P-4 Region 4 Bridge - On System Pool CDOT Region 4 Bridge Federal National Highway Performance Program - - 956 483 719 719 2,877 SR46598 State State Highway Fund
More informationAdditional Economic Development Strategy submissions- Klickitat County
Klickitat County Transportation Improvement Projects 1 White Salmon to Hood River Bridge Final EIS, design, bridge replacement 2 Klickitat County Rural Arterials Reconstruct to all-weather roads Part of
More informationTHE RICHMOND REGION Transportation Priority Projects
Priority Order Project Description Estimated Need (in millions) 1* Main Street Station Phase III - Station facility improvements Route 360 East of I-295 Widen to 6 & 8 lanes (I-295 to Walnut Grove Rd)
More informationCrenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018
Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)
More informationMontgomery Citizens Advisory Committee Meeting Minutes
Voting Members Mr. James Brown Ms. Ruth Ott Mr. Crews Reaves Mr. Blair Rehnberg Mr. Charles Rowe Mr. Rich Beauchamp Ms. Gracie Stroud Mr. Theodore White Montgomery Citizens Advisory Committee Meeting Minutes
More informationCounty - School Appling County - 4th District Elem Appling County - Altamaha Elem Appling County - Appling High_Elem Appling County - Appling Mid
County - School Appling County - 4th District Elem Appling County - Altamaha Elem Appling County - Appling High_Elem Appling County - Appling Mid Atkinson County - Pearson Elem Atkinson County - Willacoochee
More informationFY Regional Transportation Improvement Program Basic Project List (All Values in Thousands of Dollars) All costs in current dollars
FY2016-2020 Regional Transportation Improvement Program Basic Project List () All costs in current dollars Project Name Key # Year Project Cost 10th Avenue Bridge, Caldwell 13055 2018 $1,367 10th Avenue
More informationGuide to. Road Construction Projects
Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or
More informationFiscal Year
Fiscal Year 2017-2018 Workshop May 2, 2017 CIP Overview Based on Board Priorities Based on Board Priorities Balanced, Generally on a Pay-as-You-Go Basis FY17-18 Closely Mirrors this Year s Approved Plan
More informationDULLES AREA HIGHLIGHTS. Gary Garczynski Commonwealth Transportation Board Northern Virginia District. Committee for Dulles August 4, 2016
DULLES AREA HIGHLIGHTS Gary Garczynski Commonwealth Transportation Board Northern Virginia District Committee for Dulles August 4, 2016 Smart Scale (formerly HB2) Overview Round 1 completed with the adoption
More informationLee County Board of County Commissioners January 24, 2017 Workshop Meeting
Lee County Board of County Commissioners January 4, 017 Workshop Meeting 1 Review Current Transportation Priorities (Tiers 1,, 3) Discuss Status of Projects 3 Discuss Ranking Recommendations 1 State of
More informationSPLOST ADVISORY COMMITTEE. October 30, 2012 MINUTES
SPLOST ADVISORY COMMITTEE October 30, 2012 MINUTES Committee Members: Chairman Dan Slagle Monica Smith Theron Ussery Bruce Freeman Lindsay Holliday David Lucas Dr. John Swint Staff Attending Steve Layson,
More informationFDOT Treasure Coast Traffic Impact Report
July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane
More informationCurrent Amendment or Modification. Prior Amendment or Modification. All other Amendments and Modifications. FY TIP Project Title/Location
North Front Range Transportation & Air Quality Planning Council (NFRT & AQPC) Current Amendment or Modification STIP ID Project Title/Location Project Sponsor Improvement Type Source of Funds HIGHWAYS
More information45102 Super-Public Use Microdata Area (Super-PUMA) State ADAMS County
SOUTH CAROLINA - Census 2000 Super-Public Use Microdata Areas (Super-PUMAs) CHEROKEE 35 CHESTERFIELD DILLON KERSHAW DARLINGTON LEE MARION 34 FLORENCE HORRY SUMTER CLARENDON WILLIAMSBURG BERKELEY 33 CHARLESTON
More informationBecky A. Bradley, AICP. Executive Director, LVPC Secretary, LVTS
Becky A. Bradley, AICP Executive Director, LVPC Secretary, LVTS 2017 Final Plans Total Plans (427) Lehigh County Municipality Plan Count ALLENTOWN CITY 32 LOWER MACUNGIE TOWNSHIP 26 UPPER MACUNGIE TOWNSHIP
More informationWelcome to the Downtown Fort Lauderdale Neighborhood Working Group Meeting. First meeting june 17, 2010
Welcome to the Downtown Fort Lauderdale Neighborhood Working Group Meeting First meeting june 17, 2010 State of the Project Draft Environmental Impact Statement Study Phase This study is NOT the final
More informationHighways: Interstate. Highways: State Highways
FLORIDA DEPARTMENT OF TRANSPORTATION 5 - YEAR TRANSPORTATION PLAN ($ IN THOUSANDS) TENTATIVE FY 2019-2023 (10/01/2017 20:15:01) ALACHUA COUNTY Highways: Interstate 4230716 I-75(SR121)WILLISTON RD SR222(NW
More informationGDOT Local Bridge Replacement Program
GDOT Local Bridge Replacement Program August 29, 2018 Local Bridge Replacement Program GDOT Partners with Local Governments to Replace Off-System Deficient, Posted Bridges The replacement of a deficient,
More informationFDOT Treasure Coast Traffic Impact Report
July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane
More information2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016
2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016 Project numbers do not signify ranking they are for mapping identification purposes only. 1. 15th Street East The
More informationMajor Projects Overview
Major Projects Overview Miami-Dade Expressway Authority February 2018 About MDX MDX operates 5 roads in Miami Dade County SR 924, SR 112, SR 836, SR 874 and SR 878 MDX Primary Source of Revenue: User Fees-Tolls
More informationUpdate on the I-680 Transit Corridor Improvement Project HOV on/off Ramps Environmental Impact Report Community Engagement Plan
Update on the I-680 Transit Corridor Improvement Project HOV on/off Ramps Environmental Impact Report Community Engagement Plan Presentation Overview Introductions Susan Miller, Director of Projects, Contra
More informationPUBLIC NOTICE. Table 1 Projects Proposed by Amendment
PUBLIC NOTICE The Dallas Department of Aviation (the Department) intends to file an amendment application to increase the PFC amount of one previously approved project at Dallas Love Field Airport (the
More informationState Route 8 Corridor. Northern Summit County s Path to Success
State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity
More informationONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1
ONONDAGA CREEKWALK PHASE II Public Information Meeting Series 1 Andrew Maxwell Director, Syracuse-Onondaga County Planning Agency Owen Kerney Assistant Director for City Planning Russell Houck, PE City
More informationCurrent Amendment or Modification. Prior Amendment or Modification. All other Amendments and Modifications
North Front Range Transportation & Air Quality Planning Council (NFRT & AQPC) Current Amendment or Modification STIP ID Title/Location HIGHWAYS Bridge - On State System SR46598 P-4 Region 4 Bridge - On
More informationProjected Advertisement Date
2013 Planned s CY 2013 and CY 2014 Richmond District Schedule Preliminary Engineering Task Order Contracts SR 288/SR 145 Survey, 288 90349 Chesterfield Ramp and Signal Design 2/27/2013 $ 0.19 I-64 Over
More informationStreets, the south side of West Cleveland Street between Broadway and Olive
Published in The Morning Sun on September 25th, 2015) ORDINANCE NO. G- 1230 AN ORDINANCE amending Section 78-116 of the Pittsburg City Code to prohibit parking on both sides of East 10th Street between
More informationFort Wayne/Allen County Trails Program
Status Report Name Contractor WO # DES # Manager Description & Status Summary Ardmore Avenue: Airport Expressway to Second Street (entrance to airport) & Extend the trail from Airport Expressway to the
More informationProgress Report for Projects of Regional Significance
Rosedale Highway facing west January 2017 What s Inside? Kern Council of Governments Progress Report for Projects of Regional Significance EDITION Status Information on: Safety & Maintenance...this section
More informationPennDOT Interstate Work next week March 30-April 3:
PennDOT Interstate Work next week March 30-April 3: Interstate 80 Interstate 81 DELAYS THIS WEEK: Exit 256 to the Schuylkill County line. Eastbound & Westbound. Bridge cleaning Monday (3/30), Tuesday (3/31)
More informationThe Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP).
The Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP). A 7-day public comment period regarding the amendment begins January
More informationGetting to The Juilliard School
Getting to The Juilliard School TRANSPORTATION FROM AREA AIRPORTS Airport Shuttles Super Shuttle (800) BLUE-VAN (800-258-3826) https://www.supershuttle.com/ NYC Airporter (718) 777-5111 http://www.nycairporter.com/
More informationLANCASTER CORRIDOR REDEVELOPMENT ROSEDALE STREET REDESIGN PEACH STREET RAILROAD CROSSINGS
LANCASTER CORRIDOR REDEVELOPMENT ROSEDALE STREET REDESIGN PEACH STREET RAILROAD CROSSINGS Presented at the SEE Development Excellence Workshop By Councilmember Wendy Davis, City of Fort Worth March 24,
More informationHighways: State Highways
FLORIDA DEPARTMENT OF TRANSPORTATION 5 - YEAR TRANSPORTATION PLAN ($ IN THOUSANDS) TENTATIVE FY 2019-2023 (10/01/2017 20:15:01) CLAY COUNTY Highways: State Highways 4135301 D2 CLAY COUNTY TRAFFIC SIGNAL
More informationNovember 9, Society of American Military Engineers
November 9, 2016 Society of American Military Engineers Transit Operator Transportation Planner Transportation Infrastructure Builder Transportation Funding Overseer 2 1,433 square-mile service area (nearly
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016
RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov
More informationVDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016
RELEASE: IMMEDIATE June 10, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov
More informationPalm Beach County Traffic Report August 24 through August 31, 2012
For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will
More informationProgress Report for Projects of Regional Significance
SR 58 BELTWAY IMPROVEMENTS MARCH 2018 What s Inside? Kern Council of Governments Progress Report for Projects of Regional Significance OCTOBER 2018 EDITION This report is updated quarterly and posted on
More informationMost people notice when ODOT builds something
ODOT District 8 2016 Construction Program Taking Care of What We Have Most people notice when ODOT builds something new. However, we actually spend 93 percent of our time and resources taking care of what
More informationChapter Seven COST ESTIMATES AND FUNDING A. GENERAL
Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction
More informationState Route 189 Project and Draft Resolution of Support. November 2014
State Route 189 Project and Draft Resolution of Support November 2014 Corridor Location Image sources: ADOT Statewide and National Importance: CANAMEX Corridor Image source: FHWA Statewide and National
More information- AGENDA - October 25, 2017
CLARKSVILLE-MONTGOMERY COUNTY REGIONAL PLANNING COMMISSION - AGENDA - October 25, 2017 2:00 P.M. 329 Main Street (Meeting Room - Basement) I. CALL TO ORDER/QUORUM CHECK/PLEDGE TO FLAG II. APPROVAL OF MINUTES
More informationCulpeper District. Albemarle County Monthly Report. September 2012
Culpeper District Albemarle County Monthly Report September 2012 Special Issues Bridges on Route 745, Arrowhead Valley Road The road will be closed at the Rail Road Bridge on the southern end of the road
More informationFY Transportation Improvement Program Basic Project List (in Thousands)
FY2010-2014 Transportation Improvement Program Basic Project List (in Thousands) Project Name Key # Year Project Cost 16th Avenue North, 7th Street North to Garrity Boulevard GU09308 2011 $592 21st Avenue
More informationTransportation TRANSPORTATION PROJECTS
Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William
More informationPark System Development Charge Update Investment Plan
System Development Charge Update Investment Plan I. Summary II. SDC Investments, 1998-2007 III. IV. Population Growth Projections SDC Acquisition Target s V. SDC Development Target s VI. SDC Acquisition
More informationPenny for Pasco Renewal. FY2014/15 thru FY2024/25
Penny for Pasco Renewal FY2014/15 thru FY2024/25 1 Background Pasco Citizens Committee (PAC) Citizens Survey Results Coordination Activities Project Schedule Category Allocations Revenue Estimates Distribution
More informationCity of Madera Engineering Division. Citizen s Oversight Committee February 13, 2019
City of Madera Engineering Division Citizen s Oversight Committee February 13, 2019 INTRODUCTION The City of Madera uses Measure T funds to support various programs as outlined in the Annual Expenditure
More informationRoad Construction Ahead January-April 2015 NORTHWEST REGION
NORTHWEST REGION 1 Interstate 64 Augusta, Nelson, Albemarle counties: Installing communications conduit in median for active traffic management system on Afton Mountain. Periodic left-shoulder closures,
More informationHonorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee
Memorandum DATE August 10, 2018 CITY OF DALLAS TO Honorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee SUBJECT Dallas Love Field Master Plan Update On Monday, August
More informationBuilding the transportation network we need for the future in Niagara Region
Building the transportation network we need for the future in Niagara Region Niagara@metrolinx.com Metrolinx.com/Niagara Metrolinxengage.com INSERT FOOTER 1 WHO IS METROLINX? Metrolinx was created in 2006
More informationNEW JERSEY DEPARTMENT OF TRANSPORTATION
Burlington Burlington County Roadway Safety Improvements (DB #D0302) STPSTU CON $0.000 $0.856 $0.856 $0.000 Burlington County Roadway Safety Improvements C00S(524) $0.856 09/04/2013 County Route 528 Roundabout
More informationUS 19 Sunset Point Rd to Countryside Blvd.
Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started
More informationISSUE SUMMARY: FUNCTIONAL CLASSIFICATION NETWORK UPDATE FOR PRINCIPAL ARTERIALS
Draft for approval by TCC on 8/8; TAQC on 8/14 and ARC on 8/27/14 DATE: August 27, 2014 ISSUE SUMMARY: FUNCTIONAL CLASSIFICATION NETWORK UPDATE FOR PRINCIPAL ARTERIALS FROM: Tom Worthan, TAQC Chairman
More informationThursday, November 1, :30 P.M. Bear Creek Senior/Recreation Center, 54 McDonough Street, Hampton, Georgia. Meeting Agenda (See Attached Agenda)
Minutes SPLOST V Committee Thursday, November 1, 2018 6:30 P.M. Bear Creek Senior/Recreation Center, 54 McDonough Street, Hampton, Georgia The Henry Herald was notified of the meeting via email. I. Call
More informationConstruction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County
Construction Update Contact: The District Two Public Information Office at (419) 373-4428 or email D02.PIO@dot.ohio.gov For Immediate Release Thursday, October 18, 2018 ODOT District Two Construction Update
More informationGeorgia Skywarn Spotter linked repeater System
Location Frequency Notes Tyrone Fayetteville Peachtree City Fayetteville Madris Griffin Atlanta Dalton Jasper Sawnee Mtn 444.675+ (77.0 Hz) 444.600+ 442.500+ 145.210 (131.8hz) 147.165+ (131.8 Hz) 145.390
More informationAPPENDIX G MULTI-USE TRAILS DOWNTOWN LAKELAND
MULTI-USE TRAILS DOWNTOWN LAKELAND POINCIANA PARKWAY Multi-Use Trails Trail Name From To Status Regional Network Surface Length Present Day Cost Chain-of-Lakes Trail Bridge South of US 17/92 North of US
More informationNorthern Virginia District State of the District. Helen L. Cuervo, P.E. District Engineer October 18, 2017
Northern Virginia District State of the District Helen L. Cuervo, P.E. District Engineer October 18, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation American Society