1 AIRSPACE CHANGE COMMUNITY ENGAGEMENT REPORT Proposed RNP AR approaches and STAR updates at Ottawa Macdonald Cartier International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 August 2016 The information and diagrams contained in this report are for illustrative purposes only and are not to be used for navigation.
2 Table of Contents Executive Summary Purpose Background Overview of Proposed Changes to Routes Runways 07 Arrivals, Proposed RNP AR Flight Path and New STAR Runways 14 Arrivals, Proposed RNP AR Flight Path and New STAR Runway 25 Arrivals, Proposed RNP AR Flight Path and New STAR Runway 32 Arrivals, Proposed RNP AR Flight Path and New STAR Overall Impact on Community Noise Reduced Emissions Community Outreach and Engagement Engagement with Airport Website Open Houses Survey Results and Other Feedback Methodology Survey Respondents Summary of input received Consideration of Main Mitigations Proposed by Residents Recommendation Communication Post Implementation Review
3 Executive Summary Airspace Change Community Engagement Report CYOW RNP AR Required Navigation Performance (RNP) and Area Navigation (RNAV) are part of a family of technologies that lever the capabilities of modern flight management systems and GNSS for safer and more efficient navigation. RNP is increasingly being used to provide safe and accurate arrival routes to busy airports; it is also a significant piece of the technology tool kit being utilized to meet commitments made by the global aviation industry to reduce greenhouse gas emissions. This study examines the proposal to implement new RNP Authorization Required (AR) procedures as well as update existing RNAV Standard Terminal Arrival Routes (STARs) to runways 07/25 and 14/32 at Ottawa Macdonald Cartier International Airport, and reports on noise modelling and the community consultation undertaken as per the Airspace Change Communications and Consultation Protocol. The consultation process, which ran from May 16, 2016 to June 30, 2016, included briefings to elected officials and the airport s noise consultative committee, hosting of community open house events in two locations and use of a survey mechanism to enable the public to provide direct comment. To support consultation, extensive noise modeling was completed. Overall, modeling shows benefits for several communities with very small increases in cumulative noise exposure at low noise levels, often below typical community noise levels, for some areas. The consultation team s recommendation is to proceed with implementation of the proposed RNP AR procedures and updated RNAV STARs with a target implementation date in September
4 1.0 Purpose This study examines the proposal to implement new RNP AR procedures and update existing RNAV STAR procedures at Ottawa Macdonald Cartier International Airport. It reports on the community consultation undertaken as per the Airspace Change Communications and Consultation Protocol (2015). The report includes an overview of the proposed changes, expected quantitative environmental impacts (including emissions reductions and noise impacts), details public engagement activities and their results, and provides recommendations. 2.0 Background Today, modern avionics are providing new opportunities to design routes that are no longer bound by ground-based navigational aids. These opportunities, enabled by Global Navigation Satellite System (GNSS), allow for the design of routes that are more precise, predictable, fuel efficient and environmentally friendly. RNP and RNAV are part of a family of technologies that lever the capabilities of modern flight management systems and GNSS for safer and more efficient navigation. RNAV provides an efficient navigation tool that is used by many aircraft today. RNP, which brings a new level of precision and design flexibility, is increasingly being used to provide safe and accurate arrival routes to busy airports; they are, together, a significant piece of the technology tool kit being utilized to meet commitments made by the global aviation industry to reduce greenhouse gas emissions. The deployment of Performance Based Navigation (PBN) technologies, of which RNP and RNAV are a part, has been encouraged by the International Civil Aviation Organization (ICAO). ICAO took steps in 2007 to require its member countries to develop formal plans for the deployment of PBN in their respective jurisdictions. NAV CANADA Performance-Based Navigation Operations Plan (2014) and the Transport Canada PBN State Plan identifies the goal of achieving a total PBN environment in Canada with RNAV and/or RNP for all operations. RNP achieves benefits in part by allowing for flight path designs that reduce the track miles that an aircraft must fly to its destination while providing for a constant descent compared to an approach that requires level segments (which in turn require more thrust and burn more fuel). RNP AR has been used in Canada since 2004, primarily by WestJet using specific company approaches. New criteria recently published by Transport Canada as part of TP308 Criteria for the Design of Instrument Procedures enable RNP AR approach procedures to be designed for use by more airlines and by more types of aircraft. Ottawa International Airport is the country s eighth 1 busiest airport. The airport has a variety of approach procedures, including RNAV STAR procedures that provide a combination of GNSS-based guidance and air traffic control instructions to a point where the pilot can intercept the glide path emanating from the ground-based Instrument Landing System (ILS). The airport is also serviced by WestJet RNP AR approach procedures for runways 25 and 32. NAV CANADA is proposing new RNP AR approaches in addition to updating RNAV STARs for runways 07/25 and 14/32. No changes are proposed for runways 04/22. 1 Annual aircraft movement statistics (2014). Statistics Canada. Retirieved from: x eng.htm 4
5 3.0 Overview of Proposed Changes to Routes The proposed RNP AR approaches have been designed to mirror the downwind and final approach of existing flight paths with the base leg arc located within the existing distribution of traffic on the base leg. The new RNP AR segments will result in a reduction of track miles flown for many aircraft and will enable a reduced power constant descent arrival at a three (3) degree descent angle. It is important to note that approximately 23% of aircraft operating to Ottawa International today are equipped to fly RNP AR routes and utilization of the routes will be considerably less than that number for a variety of operational reasons. Equipage rates are expected to grow slowly but steadily over time through fleet renewal, reaching the 30-33% range by Runways 07 Arrivals, Proposed RNP AR Flight Path and New STAR Runway 07 receives approximately 25 per cent of arrivals on an annual basis. When in use, ceiling and visibility are lower than usual and often accompanied by precipitation. It is normally in use for several hours or a few consecutive days at a time. Figure 1 shows the proposed RNP AR path (in blue) on a map of the Ottawa region with a 24-hour sample of arrival traffic as flown by aircraft on February 23, (in turquoise). The new base legs are located amongst existing traffic patterns and at comparable altitudes; the approach from the north avoids populated areas by using greenspace. While a broad distribution of traffic will continue, the new RNP AR approach will allow many equipped aircraft to turn sooner than they might have otherwise and will result Figure 1: Sample traffic and proposed RNP AR route in a smaller number of aircraft completing their turn over a wide region. 5-7 aircraft/day 2 Operations can vary from day to day. For illustrative purposes only. 3-5 aircraft/day Approximately 5-7 aircraft/day are expected to utilize the RNP AR approach from the north and 3-5 from the south when this runway is in use. The downwind component of the approach from the south is moved approximately 0.5 nautical miles south of the current standard 5
6 arrival route, though its length is much shorter. Figure 2 shows the current standard arrival. The purple shading area represents the areas that experience overflight today when this runway is in use. STARs provide guidance to the end of the downwind leg, at which point pilots follow for the controller s instructions to turn on to the base leg. Aircraft will turn on to the base leg at various points depending on sequencing needs, pilot operation and aircraft performance. Despite the existence of STARs, other areas will experience overflight, particularly when vectors are used to Figure 2: Current RNAV STAR and Airspace Usage sequence traffic or pilots conduct visual approaches. In these instances, the pilot flies a more direct route to the final approach. This means that approaches can be distributed over a wide region; the shaded areas on the maps show typical traffic distribution taking in to account all types of approaches. Figure 3: Proposed RNAV STAR and Airspace Usage Figure 3 shows the proposed standard arrival route with blue shading representing the areas that are expected to experience overflight when this runway is in use. Aircraft icons portray aircraft altitudes at respective locations. The proposed redesign of STARs would narrow the shaded operating region somewhat as a result of the intercept for the final approach (see aircraft icon at 3,000 ) being relocated approximately 3 kilometres closer to the airport. In addition, the downwind component of the approach from the south is moved approximately 0.5 nautical miles south of its current location. Aircraft would be at similar altitudes on the proposed route compared to the current route. 6
7 Figure 4: Single Event Contour for Runway 07 RNP AR Figure 5: Single Event Contour for Proposed RNAV STAR Noise Modeling Figure 4 shows a single event noise contour for the proposed RNP AR approach to runway 07. Contours show areas likely to experience certain noise levels from overflight. In this instance the model uses a aircraft, a type of aircraft seen frequently at the airport. Figure 5 shows a single event contour for the proposed RNAV STAR. It is important to note that RNAV STARs are flown with greater variance and that this is a sample of one typical approach. The location of the noise footprint will vary based on the exact flight path flown. 7
8 3.2 Runways 14 Arrivals, Proposed RNP AR Flight Path and New STAR Runway 14 receives a very small proportion of the traffic to Ottawa Macdonald-Cartier Airport. On an annual basis, less than two per cent of the traffic arrives on this runway. When in use, weather conditions are poor. Figure 6 shows the proposed RNP AR path for runway 14 arrivals (in blue) on a map of the Ottawa region with a 4-hour sample of arrival traffic as flown by aircraft on February 3, 2016 (in turquoise). The more Figure 6: Sample traffic and proposed RNP route 7-12 aircraft/day 1-3 aircraft/day direct approach brings aircraft closer to populated areas. However, the low usage levels results in no significant change to the cumulative noise exposure in the region. The broad distribution of traffic will continue and the new RNP AR approach will reduce the amount of land overflown for those aircraft that are equipped. Figure 7 shows the current standard arrival. The purple shaded area represents the area that experience overflight today when this runway is in use. STARs provide guidance to the end of the downwind leg, at which point pilots follow the controller s instructions to turn on to the base leg. Aircraft will turn towards the Figure 7: Current RNAV STAR and Airspace Usage base leg at various points depending on sequencing needs, pilot operation and aircraft performance. Despite the existence of RNAV and RNP AR routes, pilots can still operate in other places through the use of controllerissued vectors or visual approaches. In these instances, the pilot flies a more direct route to the final approach. This means that approaches can be 8
9 Figure 8: Proposed RNAV STAR and Airspace Usage distributed over a wide region; the shaded areas on the map below show typical traffic distribution taking in to account all types of approaches. Figure 8 shows the proposed standard arrival route as well as blue shading over the areas that are expected to experience overflight when this runway is in use. Aircraft icons portray aircraft altitudes at respective locations. The change would narrow the shaded operating region somewhat as a result of the final approach course fix (see aircraft icon at 3,000 ) relocating approximately 3 kilometres closer to the airport. Figure 9: Single Event Contour for Runway 14 RNP AR Noise Modeling Figure 9 shows a single event noise contour for the proposed RNP AR approach to runway 14. Contours show areas affected by specific noise levels. In this instance the model represents a aircraft, a type of aircraft seen frequently at the airport. Figure 10 shows a single event contour for the proposed RNAV STAR. It is important to note that RNAV STARs experience greater variance of flight path and that this is a sample of one typical approach. Figure 10: Single Event Contour for Proposed RNAV STAR 9
10 3.3 Runway 25 Arrivals, Proposed RNP AR Flight Path and New STAR Runway 25 receives approximately 37 per cent of arrivals on an annual basis. When in use, weather conditions are usually good. It is normally used in conjunction with Runway 32; together these two Runways receive approximately 74 per cent of the traffic to Ottawa Macdonald-Cartier Airport. Figure 11 shows the proposed RNP AR path (in blue) on a map of the Ottawa region with a 24-hour sample of arrival traffic as flown by aircraft on February 29, (in turquoise). In white, WestJet s Figure 11: Sample traffic and proposed RNP route 1-3 aircraft/day 7-12 aircraft/day existing RNP AR route is shown. The new base legs are located amongst existing traffic patterns and at comparable altitudes; the approach from the north transits between Blackburn Hamlet and Orleans to best avoid populated areas. The downwind component of the approach from the south is moved approximately 0.5 nautical miles south of the current standard arrival route, though its length is much shorter than the latter. While the broad distribution of traffic will continue, the new RNP AR approach will allow many equipped aircraft to turn sooner and will reduce the amount of land overflown. Figure 12 shows the current standard arrival. The purple shaded area represents the area that experiences overflight today when this runway is in use. STARs provide guidance to the end of the downwind leg, at which point pilots follow the controller s instructions to turn on to the base leg. Aircraft will turn on to the base leg at various points depending on sequencing needs, pilot operation and aircraft performance. Despite the existence of STARs, pilots can still operate in other places through the use of controller-issued vectors or visual approaches. In these instances, the pilot flies a more direct route to the final approach. This means that approaches can be distributed over a wide region; the shaded areas on the map below show typical traffic distribution taking in to account all types of approaches. 3 Operations can vary from day to day. For illustrative purposes only. 10
11 Figure 12: Current RNAV STAR and Airspace Usage Figure 13 shows the proposed standard arrival route with blue shading representing the areas that are expected to experience overflight when this runway is in use. Aircraft icons portray aircraft altitudes at respective locations. The change would narrow the shaded operating region somewhat as a result of the final approach course fix (see aircraft icon at 3,000 ) relocating approximately 3 kilometres closer to the airport. In addition, the downwind component of the approach from the south is moved approximately 0.5 nautical miles south of its current location. Figure 13: Proposed RNAV STAR and Airspace Usage 11
12 Figure 15: Single Event Contour for Proposed RNAV STAR Figure 14: Single Event Contour for Runway 25 RNP AR Noise Modeling Figure 14 shows a single event noise contour for the proposed RNP AR approach to runway 25. Contours show when the maximum noise level attains a level of 60 dba or above. In this instance the model uses a aircraft, a type of aircraft seen frequently at the airport. Figure 15 shows a single event contour for the proposed RNAV STAR. It is important to note that RNAV STARs experience greater variance of flight path and that this is a sample of one typical approach. 12
13 Figure 16: Sample traffic and proposed RNP AR route 3.4 Runway 32 Arrivals, Proposed RNP AR Flight Path and New STAR aircraft/day 2-4 aircraft/day Runway 32 receives approximately 37 per cent of arrivals on an annual basis. When in use, weather conditions are usually good. It is normally used in conjunction with Runway 25; together these two Runways receive approximately 74 per cent of the traffic to Ottawa Macdonald-Cartier Airport. Figure 16 shows the proposed RNP AR path (in blue) on a map of the Ottawa region with a 24- hour sample of arrival traffic as flown by aircraft on February 29, (in turquoise). The proposed downwind from the north is located in the same location as the current route; the downwind from the south is closer to the airport than the existing non-rnp route. In white, WestJet s existing RNP AR route is shown. While the broad distribution of traffic will continue, the new RNP AR approach will allow many equipped aircraft to turn sooner and will reduce the amount of land overflown. Figure 17: Current RNAV STAR and Airspace Usage Figure 17 shows the current standard arrival. The purple shaded area represents the areas that experience overflight today when this runway is in use. STARs provide guidance to the end of the downwind leg, at which point pilots follow the controller s instructions to turn on to the base leg. Aircraft will turn on to the base leg at various points depending on sequencing needs, pilot operation and aircraft performance. Despite the existence of RNAV and RNP AR routes, pilots can still operate in other places through the use of controllerissued vectors or visual approaches. In these instances, the pilot flies a more direct route to the final 4 Operations can vary from day to day. For illustrative purposes only. 13
14 approach. This means that approaches can be distributed over a wide region; the shaded areas on the map show typical traffic distribution taking in to account all types of approaches. Figure 18 shows the proposed standard arrival route as well as blue shading over the areas that are expected to experience overflight when this runway is in use. Aircraft icons portray aircraft altitudes at respective locations. Figure 18: Proposed RNAV STAR and Airspace Usage The change would narrow the shaded operating region somewhat as a result of the final approach course fix (see aircraft icon at 3,000 ) relocating approximately 3 kilometres closer to the airport. 14
15 Noise Modeling Figure 19 shows a single event noise contour for the proposed RNP AR approach to runway 32. Contours show areas expected to experience specific noise levels. In this instance the model uses a aircraft, a type of aircraft seen frequently at the airport. Figure 20 shows a single event contour for the proposed RNAV STAR. It is important to note that RNAV STARs experience greater variance of flight path and that this is a sample of one typical approach. Figure 19: Single Event Contour for Runway 32 RNP AR Figure 20: Single Event Contour for Proposed RNAV STAR 15
16 4.0 Environment 4.1 Overall Impact on Community Noise The overall community noise impact of the proposed changes are expected to be positive or low impact based on the following: Much of the new portion of the RNP AR flight paths have been designed to overfly nonresidential land use. Key examples include the RNP AR approaches from the north to runways 07 and 25 respectively. These flight paths represent a significant reduction in population overflown from the typical arrival routing that would either fly further west to land on runway 07 or further east over runway 25. RNP AR provides aircraft with guidance for constant descent operations The 3 degree descent gradient that RNP AR provides should result in reduced noise as compared to equivalent flights that require aircraft to fly a level segment before intercepting the final approach glide path. Constant descent has been shown to reduce single event noise by 1-5 db in portions of the flight path. 5 The relocation of STAR routes which are used more frequently than RNP AR, include some changes, however, proposed routes are in places that experience overflight today. To better compare current and proposed impacts, cumulative noise exposure maps were developed. The contours show the cumulative sound impact of operations using the Day-Night Level (DNL) metric. The DNL metric is widely used as a measure to communicate a cumulative exposure to aircraft noise, using a 24-hour average. The metric assists with the comparison of different aircraft operations, such as those expected before and after an airspace change. The DNL metric takes all the aircraft noise events at a location and averages them to provide a single numerical value. This allows for comparison between one location that experiences a handful of very loud events in a day against another that may receive more events that are not as loud. The metric also applies a noise penalty to operations between 10 p.m. and 7 a.m. to recognize lower community ambient noise levels at those times. Due to the volume of traffic and runway variance at Ottawa Macdonald-Cartier International Airport, all of the cumulative exposure above 50 DNL occurs at locations where aircraft are on final approach. As a result, the changes appear very subtle on maps comparing current and propose cumulative exposure. 5 CAA ERCD, BAA, CDA Briefing Paper, Noise benefits associated with Continuous Descent Approach Procedures at London Heathrow. 32 DTLR (1999). And Noise from arriving aircraft: Final Report of the ANMAC Technical Working Group, Departments for Transport Local Government and the Regions, December
17 The following map provides the contours for current operations: The following map shows what the cumulative impact would be if the proposed changes were implemented in 2016: 17
18 However the biggest benefits will be in instances of reduced track miles and reduced population overflown as a direct result when aircraft use the RNP AR rather than the traditional RNAV to ILS procedure. For communities that are overflown by the proposed RNP AR flight path, some increase in the amount of daily traffic experienced can be expected. However the overall utilization of RNP AR is expected to continue to be a relatively small proportion of overall traffic due to both equipage levels and the sequencing requirements of traffic. 4.2 Reduced Emissions The implementation of PBN in Canada is an objective of Canada s Action Plan to Reduce Greenhouse Gas Emissions from Aviation (2012), due to its potential to reduce fuel burn and associated emissions from aircraft operations. The Action Plan was the Government of Canada s response to the International Civil Aviation Organization s (ICAO) Assembly Resolution A37-19, which encourages Member States to submit national plans detailing the measures they are taking to address aviation emissions. In addition to safety benefits for pilots and controllers resulting from improved predictability of operations during one of the busiest phases of flight, it is estimated that the earlier turns off of the downwind leg at Ottawa Macdonald Cartier International Airport will reduce flying time by up to two minutes per flight. Over the course of a year, this is equivalent to approximately 300,000 million litres of fuel savings and a reduction of 750 metric tonnes of greenhouse gas emissions 6. 6 Estimate based on 2015 equipage rates and is expected to grow overtime. Does not include some added efficiencies related to RNAV STAR approach improvements. 18
19 5.0 Community Outreach and Engagement 5.2 Engagement with Airport NAV CANADA s design team worked with the airport s environmental services staff at the early stages of design to ensure their knowledge of the local community was taken into consideration. This was followed up with meetings and workshops to discuss the results of noise modeling and develop a consultation strategy as per the industry s Airspace Change Communication and Consultation Protocol. In addition, the airport s noise consultative committee was briefed during the consultation period. 5.3 Website All meeting materials were made available online at on May 16, Consultation materials available on the website were as follows: A description of the changes, including maps of existing air traffic, the proposed flight paths and cumulative noise contours, a video explaining RNP AR technology in plain language, a schedule of Open House events, and, access to the feedback mechanism, consisting of a survey with open and close ended questions. Webpage analytics shows that this section of the website received more than 3,500 unique visitors. 5.4 Open Houses Two Open House events were held in the Ottawa area. This provided the public with opportunities to learn about proposed changes in person, to ask questions directly to personnel of NAV CANADA and provide input for consideration in the final flight path design. To ensure community awareness of the consultation effort, notices (sample in Appendix A) were placed in community weeklies and popular daily newspapers with a combined distribution of over 650,000 readers per insertion. Notices included information on dates and locations of community Open Houses and encouraged residents to visit the website. In addition, the effort garnered earned media in several mainstream media outlets in the region, including the CBC Ottawa television, radio and web, Unique FM (94.5), Manotick News and Blackburn Hamlet News. Some elected officials helped promote the consultation effort through their own newsletters and social media channels. Notices of the Open Houses were published in the following media on the dates indicated. Publication Estimated circulation per Insertion Dates edition Ottawa Citizen 243,000 May 17 and 28; June 15 Le Droit 35,800 May 18 and 28; June 15 All EMC papers in Ottawa 474,000 Kanata Courier-Standard Manotick News Nepean/Barrhaven News Orleans News Ottawa East, South, West EMS Stittsville News Aylmer Bulletin Not available May 27; June 1 and 15 19
20 The following table provides specific locations and dates of the Open Houses, as well as the number of attendees at each event: Location Date and Time Number of attendees Good Shepherd School Gymnasium 101 Bearbrook Road Gloucester, ON K1B 3H5 Maurice-Lapointe School Gymnasium 17 Bridgestone Drive, Kanata, ON K2M 0E9 June 2, :30 p.m. 8:30 p.m. June 22, p.m. 8:30 p.m Community Open House events were hosted in gymnasiums with large, open spaces. NAV CANADA representatives were available throughout to explain proposed changes, discuss current and expected flight patterns and answer resident questions. Attendees were invited to provide their name on a sign-in sheet for tracking purposes. To better explain the proposed changes, large boards were printed containing information on NAV CANADA, RNP AR technology as well as maps showing current tracks and the proposed RNP AR flight paths. Other resources available during the open houses included: a computer that allowed residents to locate their own residence on a Google Earth map with current flight tracks and proposed RNP AR and RNAV approaches overlaid in 3D; another computer station had noise modelling information to analyze noise impacts based on resident s postal code or street. Most residents in attendance had previewed information on current and proposed flight paths online, and arrived seeking information specific to their residence. Overall, residents seemed appreciative of NAV CANADA s effort to communicate changes and the quality/detail of information available. The Open Houses provided residents with a good understanding of the changes. Residents asked wellinformed questions and seemed satisfied with the answers. A small number of residents indicated sensitivity to small increases in aircraft overflight, but seemed somewhat reassured by noise modeling information. Many took the opportunity to fill in paper copies of the survey while others indicated they would do so online. Based on the number of completed surveys, it is clear that others opted not to provide any formal comments through the feedback mechanism. Based on the number of Open House participants against the number of survey responses, combined with the tone of conversations held with several residents, supportive or neutral feedback is potentially underrepresented. 6.0 Survey Results and Other Feedback 6.1 Methodology To garner consistent feedback, a survey containing a mix of 12 closed- and open-ended questions was made available on the website and publicized at community events. For those that wished it, copies of the online survey were available at all Open Houses. Surveys filled out by residents at the Open Houses and left behind with staff were entered into the survey tool and considered along with those entered online. 6.2 Survey Respondents 20
21 A total of 56 individuals completed the survey. Figure 21 shows the approximate location* of respondents based on postal code information provided. The yellow icons, identify the location of the two consultation events. Figure 21: Approximate Location of Survey Respondents The location of respondents shows a good mix from communities in the East, West, North and South. There are some clusters of respondents in areas currently affected by noise which are not located near proposed flight path changes, such as Barrhaven and Country Place (the former which is under the final approach to runway 07, the latter which is exposed to flight school operations). Overall, the number of survey respondents is quite low when one considers the significant visibility effort and the overall population of Ottawa and surrounding communities as well as the significant web traffic the relevant web pages received. 6.3 Summary of input received The engagement effort related to new RNP AR procedures revealed some concerns by residents regarding flight paths, but the distribution of respondents made it difficult to identify any clear locationbased trends except in those areas which are currently exposed to significant aircraft noise. Some were concerned that RNP AR would further exacerbate the current concentration of flights over their areas. A total of 54 per cent of survey respondents indicated that they expected noise to increase if the proposal were implemented, while the remaining 46 per cent expected it to either stay the same or decrease. 21
22 Overall, feedback received indicated that residents preferred that flight paths be designed so as to avoid overflying populated areas where possible. Comments from the public are important inputs in considering airspace proposals; however, the volume of responses against the number of website and event visitors is considered to be quite low. The full results of the survey are available in APPENDIX Consideration of Main Mitigations Proposed by Residents Avoid Overflying Communities NAV CANADA is sensitive to the fact that overflight of residential areas can be perceived as a nuisance for communities. As such, it makes efforts to balance the requirements for safe navigation, the interests of surrounding communities and the need to reduce the environmental impact of the industry. Unfortunately, due to the location of airports in relation to communities, flight path design criteria and safety requirements, it is not always possible to avoid overflying residential areas. Where possible, the company endeavors to design flight paths that overfly commercial or non-residential areas in a manner that respects Transport Canada-approved design criteria. Some of the suggestions to move existing flight paths were unrelated to RNP AR and beyond the scope of this consultation. With respect to the RNP AR design, the proposed RNP AR represents an improvement over the existing RNP AR utilized at Ottawa MacDonald Cartier International Airport. Fewer residential areas are directly overflown by the proposed design. Design Multiple Flight Paths to Each Runway Design criteria, noise abatement procedures and other factors constrain flight path locations in many points along the route. While respite routes have been used in some locations internationally with mixed success, the use of multiple flight paths does not usually occur within the same time period. The figures above that show current traffic distribution as well as flight tracks over a 24 hour period demonstrate some variation in flight paths. Varied, or alternating flight paths significantly increases airspace complexity and, in turn, air traffic controller and pilot workload as well as the risk of errors. It is not being considered at this time. Despite this, sequencing needs and pilot requests will mean that dispersion of traffic will still occur for aircraft that are not equipped or not granted a clearance for an RNP AR approach. Increase the altitude of aircraft The altitude of an aircraft on approach is directly related to its distance from the airport. The closer to the airport, the lower the aircraft must be. Flight paths are generally designed to provide constant descent to the runway at a 3 degree angle. This is the most optimal angle to enable aircraft to operate efficiently with low power settings and in a clean configuration through reduced use of flaps and other drag devices. In some cases, a steeper rate of descent would require the use of aerodynamic drag devices, such as wing flaps which can increase noise output, and depending on the rate chosen, can limit the types of aircraft that can operate at the airport. 22
23 7.0 Recommendation Airspace Change Community Engagement Report CYOW RNP AR RNP AR procedures have been flown at Ottawa Macdonald Cartier International Airport since Its use by WestJet at the airport has been successful in providing a shorter flight path and reducing emissions. The proposed RNP AR design ensures approaches to all runways, has some design benefits over the current procedure including strategic use of non-residential areas, and will be able to be utilized by other suitably equipped and certified operators. It is recommended that the proposed RNP AR procedures for Ottawa Macdonald Cartier International Airport be implemented. A target implementation date in September 2016 should be identified. Implementation will be subject to review as per section Communication As per the Airspace Change Communications and Consultation Protocol, NAV CANADA will communicate the decision by posting this study on both the NAV CANADA website at least three weeks prior to implementation. 9.0 Post Implementation Review An assessment of the change will be made by NAV CANADA and the Airport operator within 180 days following implementation of the new RNP AR arrival routes. This assessment will include noise monitoring to determine actual decibel levels in the affected area. The 180 day review will be shared with the Airport Community Consultative Committee and published on NAV CANADA s website. 23
24 APPENDIX 1 Below is a sample notice that was published in the Ottawa Citizen. 24
25 APPENDIX 2 Survey Results The following section provides a summary of the responses received to the online survey. 1. What should be the considerations when designing air routes? Please rank in order of importance, with 1 being most important and 8 being least important. (56 responses) Top three rankings: Most popular #1 rankings: Safety (66%) Community Noise Exposure (27%) Reducing delays (7%) Most popular #2 rankings Community Noise Exposure (42%) Safety (18%) Air quality/pollution (13%) Most popular #3 rankings Air quality/pollution (36%) Reducing fuel burn/ghgs (21%) Shortening flight times (9%) Average Rankings Safety 1.72 Community noise exposure 2.58 Air quality/pollution 3.65 Reducing fuel burn/greenhouse gas emissions 3.94 Reducing delays 4.6 Shortening flight times 5 Increasing airspace capacity How often do you travel by air? (56 responses) Never 9% 1 to 5 times per year 80% 5 to 10 times per year 7% More than 10 times per year 4% 3. How would you describe your current exposure to aircraft noise? With 1 being low and 5 being high. (56 responses) 1 low high 14% 17% 23% 23% 23% 4. Is the current level of aircraft noise a concern to you? (56 responses) Yes 70% No 30% 25
26 5. If yes, what do your current concerns relate to? (39 responses) Aircraft on approach to landing (arrivals) 64% Aircraft taking off (departures) 59% Night flights 36% I'm not certain 10% Other 18% For those that selected other, the comments provided generally indicated concern with the time of flight (mornings and evenings) or the type of aircraft (commercial jet or single propeller). 6. Do your current concerns relate to operations from (select all that apply): (39 responses) Commercial jets 90% Turbo props 51% Small/recreational aircraft 21% Helicopters 41% I'm not sure <1% 7. Do you expect aircraft noise to increase, decrease or stay the same based on what you understand regarding the upcoming proposed RNP? (56 responses) Increase 54% Decrease 14% Stay the same 32% 8. If you selected "Increase" for question 7, please explain why: (open ended question with 30 responses) Explanations provided included the following: The new flight paths are above/closer to my neighbourhood (15 mentions) I m not certain (6 mentions) I m concerned with the growth of traffic levels (6 mentions) I currently experience a significant amount of aircraft noise (5 mentions) RNP will concentrate aircraft overflight (3 mentions) RNP will result in aircraft being lower than they were before (2 mentions) 9. If you selected "Decrease" for question 7, please explain why: (open ended question with 7 responses) Explanations provided included the following that continuous descents are smoother/quieter (6 mentions), shorter flight paths (3 mentions), aircraft engines are becoming quitter (2 mentions) and better population avoidance (1 mention). 11. Please provide any further feedback, comments or concerns related to the proposed changes. (Open ended question with 43 responses) Comments include: The designs should better avoid densely populated areas/go over industrial/rural areas or prioritize community noise impacts (10 comments). 26
27 Some respondents indicated that consultation should be more extensive or that existing consultation include clearer information materials 7 (14 comments) while a few mentioned that they thought the information materials were well done (4 comments) Several comments mentioned displeasure with current flight patterns (9 comments) Positioning the initiative as beneficial to the environment or to communities is disliked (4 comments) Some respondents further indicated that they were neutral to the changes (3 comments) Other comments include that air traffic should be dispersed, that there were benefits to RNP, that they expect more noise, that altitudes should be higher and that RNP should be adopted by airlines sooner. 7 An effort was made to reach out to respondents that had questions in their survey entries. Eight individuals were contacted independently during the consultation to help clarify impacts. 27
AIRSPACE CHANGE COMMUNITY ENGAGEMENT REPORT
AIRSPACE CHANGE COMMUNITY ENGAGEMENT REPORT Proposed RNP AR approaches and STAR updates at Halifax Stanfield International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 October 2016 The
More informationPOST-IMPLEMENTATION COMMUNITY IMPACT REVIEW
POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Winnipeg James Armstrong Richardson International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 November
More informationPOST-IMPLEMENTATION COMMUNITY IMPACT REVIEW
POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Halifax Stanfield International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 November 2017 The information
More informationPOST-IMPLEMENTATION COMMUNITY IMPACT REVIEW
POST-IMPLEMENTATION COMMUNITY IMPACT REVIEW RNAV STAR updates and RNP AR approaches at Edmonton International Airport NAV CANADA 77 Metcalfe Street Ottawa, Ontario K1P 5L6 January 2018 The information
More informationUpdates to Procedures at St. John s International Airport
October 10, 2017 Updates to Procedures at St. John s International Airport This document provides notice of upcoming changes to instrument procedures being implemented by NAV CANADA at the St. John s International
More informationCOMMUNITY NOISE MITIGATION SUGGESTIONS
COMMUNITY NOISE MITIGATION SUGGESTIONS Toronto Pearson is one of North America's fastest growing global hub airports, handling nearly 40 million passengers today, and well on its way to reaching greater
More informationAir Navigation Bureau ICAO Headquarters, Montreal
Performance Based Navigation Introduction to PBN Air Navigation Bureau ICAO Headquarters, Montreal 1 Performance Based Navigation Aviation Challenges Navigation in Context Transition to PBN Implementation
More informationUPDATE ON THE 6 IDEAS (1-4) NAV CANADA
UPDATE ON THE 6 IDEAS (1-4) THE 6 INITIATIVES 1. New approaches for night-time operations - Implemented 2. New departure procedures for night-time operations - Implemented 3. Increased downwind arrival
More informationTWELFTH AIR NAVIGATION CONFERENCE
International Civil Aviation Organization AN-Conf/12-WP/6 7/5/12 WORKING PAPER TWELFTH AIR NAVIGATION CONFERENCE Agenda Item 2: Aerodrome operations improving airport performance 2.2: Performance-based
More informationQUIETER OPERATIONS A GUIDE FOR PILOTS AND CONTROLLERS
QUIETER OPERATIONS A GUIDE FOR PILOTS AND CONTROLLERS FOREWORD It takes a cross-industry effort to ensure that every flight happens safely and efficiently airlines, air navigation services, airport authorities,
More informationAppendix A. Meeting Coordination. Appendix A
Appendix A Meeting Coordination Appendix A Philadelphia International Airport Noise Compatibility Program Update FAR Part 150 Noise Compatibility Program Update Report Prepared by: DMJM Aviation AECOM
More informationTWELFTH WORKING PAPER. AN-Conf/12-WP/137. International ICAO. developing RNAV 1.1. efficiency. and terminal In line.
International Civil Aviation Organization WORKING PAPER 31/10/12 English only TWELFTH AIR NAVIGATION CONFERENCE Montréal, 19 to 30 November 2012 Agenda Item 5: Efficient flight paths through trajectory-based
More informationFUTURE AIRSPACE CHANGE
HEATHROW EXPANSION FUTURE AIRSPACE CHANGE UPDATE SEPTEMBER 2018 On 25 June 2018, Parliament formally backed Heathrow expansion, with MPs voting in support of the Government s Airports National Policy Statement
More informationPBN AIRSPACE CONCEPT WORKSHOP. SIDs/STARs/HOLDS. Continuous Descent Operations (CDO) ICAO Doc 9931
International Civil Aviation Organization PBN AIRSPACE CONCEPT WORKSHOP SIDs/STARs/HOLDS Continuous Descent Operations (CDO) ICAO Doc 9931 Design in context Methodology STEPS TFC Where does the traffic
More informationAERONAUTICAL INFORMATION CIRCULAR 18/18
NAV CANADA 19 JUL 18 AERONAUTICAL INFORMATION CIRCULAR 18/18 GUIDANCE FOR STANDARD TERMINAL ARRIVAL (STAR) PROCEDURES The guidance currently published in the Transport Canada Aeronautical Information Manual
More informationMassport and FAA RNAV Pilot Study Overview Public Briefing. February 22, 2017 State Transportation Bld. Boston, MA
Massport and FAA RNAV Pilot Study Overview Public Briefing February 22, 2017 State Transportation Bld. Boston, MA As of 02/10/2017 Agenda Welcoming Remarks Tom Glynn (Massport CEO) David Carlon (Massport
More informationRESPONSE TO THE INDEPENDENT TORONTO AIRSPACE NOISE REVIEW
RESPONSE TO THE INDEPENDENT TORONTO AIRSPACE NOISE REVIEW Independent Airspace Noise Review NAV CANADA Response 1 TABLE OF CONTENTS FOREWORD... 4 SUMMARY OF RECOMMENDATIONS... 5 RECOMMENDATION 1A...8 Sunset
More informationBuchanan Field. Airport Planning Program. FAR Part 150 Meeting. September 28, Master Plan FAR Part 150 Noise Study Strategic Business Plan
Airport Planning Program Master Plan FAR Part 150 ise Study Strategic Business Plan FAR Part 150 Meeting September 28, 2006 Agenda Introduction Part 150 Study Working Paper Two Operational Alternatives
More informationNoise Action Plan Summary
2013-2018 Noise Action Plan Summary Introduction The EU Noise Directive 2002/49/EU and Environmental Noise (Scotland) Regulations 2006 requires airports with over 50,000 movements a year to produce a noise
More informationMassport and FAA RNAV Pilot Study Overview Briefing to Massport CAC. December 8, 2016
Massport and FAA RNAV Pilot Study Overview Briefing to Massport CAC December 8, 2016 Contents FAA/Massport RNAV MOU Context Boston Logan Context FAA RNAV MOU, Overview Q&A 12/8/2016 2 FAA/Massport RNAV
More informationOperators may need to retrofit their airplanes to ensure existing fleets are properly equipped for RNP operations. aero quarterly qtr_04 11
Operators may need to retrofit their airplanes to ensure existing fleets are properly equipped for RNP operations. 24 equipping a Fleet for required Navigation Performance required navigation performance
More informationEnvironmental Assessment. Runway 14 Smart Tracking Approach Gold Coast Airport
Environmental Assessment Runway 14 Smart Tracking Approach Gold Coast Airport Table of Contents Introduction ` 3 Runway 14 Smart Tracking approach 3 Assessment 3 Assumptions 3 Nominated aircraft 3 How
More informationTRAFFIC MANAGEMENT PLAN FINAL STAGE. Implementation of Standard Instrument Departure and Standard Instrument Arrival Flight Paths.
TOWNSVILLE AIRPORT TRAFFIC MANAGEMENT PLAN FINAL STAGE Implementation of Standard Instrument Departure and Standard Instrument Arrival Flight Paths. Airservices and the Department of Defence are implementing
More informationOverview of Boston Logan Operations and Noise from Overflights. Presentation to Massport Board March 19, 2015
Overview of Boston Logan Operations and Noise from Overflights Presentation to Massport Board March 19, 2015 Contents How the Airport Operates Massport s Noise Abatement Program for Logan Recent Trends
More informationFRENCH VALLEY AIRPORT (F70) Sky Canyon Dr. Murrieta, CA. Phone: Riverside FAA FSDO Complaint Line: (951)
FRENCH VALLEY AIRPORT (F70) 37600 Sky Canyon Dr. Murrieta, CA Phone: 951-600-7297 Riverside FAA FSDO Complaint Line: (951) 276-6701 Visit the F70 website for additional information regarding the airport
More informationHeathrow s Blueprint for noise reduction. Ten practical steps to cut noise in 2016/17
Heathrow s Blueprint for noise reduction Ten practical steps to cut noise in 2016/17 Working together with our communities As part of our commitment to engage openly and constructively with our local communities
More informationLAX Community Noise Roundtable Work Program A1 Review of SoCal Metroplex Proposed Procedures and Suggestions for Comment Letter.
LAX Community Noise Roundtable Work Program A1 Review of SoCal Metroplex Proposed Procedures and Suggestions for Comment Letter July 8, 2015 Southern California Metroplex Environmental Assessment Presentation
More informationContinuous Descent? And RNAV Arrivals
Continuous Descent? And RNAV Arrivals From an ATC Perspective Presentation to: CDA Workshop GA Tech Name: Don Porter RNP Project Lead FAA, RNAV RNP Group Date: 18 April 2006 My Background 22 years Terminal
More informationDesign Airspace (Routes, Approaches and Holds) Module 11 Activity 7. European Airspace Concept Workshops for PBN Implementation
Design Airspace (Routes, Approaches and Holds) Module 11 Activity 7 European Airspace Concept Workshops for PBN Implementation Design in Context TFC Where does the traffic come from? And when? RWY Which
More informationFederal Aviation Administration DCA. By: Terry Biggio, Vice President Air Traffic Services Date: June 18, Federal Aviation Administration
DCA Presented to: Arlington County By: Terry Biggio, Vice President Air Traffic Services Date: June 18, 2015 Air Traffic Roles and Responsibilities As aviation technology advances, the FAA is putting in
More informationHoneywell.com PBN Concepts Krakow, Poland
PBN Concepts Krakow, Poland EPKK (KRK) Current Operational Environment Current Operational Environment : Runways: 07/25 8,366 ft (2550m) Approaches: ILS or LOC 25 RNAV (GNSS) 07, 25 VOR 07, 25 NDB 25 Departure
More informationRNP Solutions in Australia Australia s PBN Transition brings Opportunities for Active Noise Abatement.
RNP Solutions in Australia Australia s PBN Transition brings Opportunities for Active Noise Abatement. Simon Young Strategy, Innovation and Service Performance Manager Australian Environment and PBN Drivers
More informationICAO PBN CONCEPTS, BENEFITS, AND OBJECTIVES
AFCAC/ICAO Joint Workshop Walter White ICAO PBN CONCEPTS, BENEFITS, AND OBJECTIVES 24 JUNE 2014 Airbus ProSky Corporate Presentation 29/06/2014 PERFORMANCE-BASED NAVIGATION The implementation of Performance-Based
More informationSaint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis
Saint Petersburg-Clearwater International Airport Airspace & Instrument Approach Analysis February 23, 2005 Jeppesen Boeing Jeppesen Government / Military Services Group Airspace Services Division AIRSPACE
More informationArriving and departing aircraft at Edinburgh Airport
Arriving and departing aircraft at Edinburgh Airport Contents Introduction... 3 Arriving aircraft... 3 The Instrument Landing System (ILS)... 6 Visual Approach... 6 Non Directional Beacon Approach... 6
More informationProposed Changes to Inverness Airport s Airspace The Introduction of Controlled Airspace and Optimisation of Instrument Flight Procedures
Proposed Changes to Inverness Airport s Airspace The Introduction of Controlled Airspace and Optimisation of Instrument Flight Procedures What is an Airspace Change Proposal? It is a formal UK Civil Aviation
More informationKSFO RNAV TO GLS DEMONSTRATION
Delta Air Lines - Noah Flood GLS GLS DTT 1.9 DTT 1.9 GLS1 GLS1 KSFO RNAV TO GLS DEMONSTRATION Key Components Three Key Components 1. Global Navigation Satellite System A. GPS/Galileo/GLONASS 2. Ground
More informationNoise Programs & NextGen Briefing. Stan Shepherd, Manager Airport Noise Programs
Noise Programs & NextGen Briefing Stan Shepherd, Manager Airport Noise Programs 1 Presentation Overview Noise Information Hotline Increased Operations Economic Impacts Noise Contours Noise Mitigation Programs
More informationMinneapolis-St. Paul International Airport (MSP)
2 nd Quarter 2016 Minneapolis-St. Paul International Airport (MSP) Public Input Meeting Metropolitan Airports Commission Noise Program Office April 27, 2016 PUBLIC INPUT MEETING Meeting Goals To hear the
More informationRNP AR APCH Approvals: An Operator s Perspective
RNP AR APCH Approvals: An Operator s Perspective Presented to: ICAO Introduction to Performance Based Navigation Seminar The statements contained herein are based on good faith assumptions and provided
More informationFramework Brief. Edinburgh SIDs
Framework Brief 11-Nov-2015 CAA House Edinburgh SIDs 2 Security Statement Unclassified This presentation has been approved for public distribution and publication on the CAA website. Copyright 2015 NATS/
More informationNOISE ABATEMENT PROCEDURES
1. Introduction NOISE ABATEMENT PROCEDURES Many airports today impose restrictions on aircraft movements. These include: Curfew time Maximum permitted noise levels Noise surcharges Engine run up restrictions
More informationCanberra Airport Aircraft Noise Information Report
Canberra Airport Aircraft Noise Information Report Quarter 4 2015 (October to December) 1 Version Control Version Number Detail Prepared by Date 1 - Environment March 2016 Airservices Australia. All rights
More informationSafety and Airspace Regulation Group
Page 1 of 11 Airspace Change Proposal - Environmental Assessment Version: 1.0/ 2016 Title of Airspace Change Proposal Change Sponsor Isle of Man/Antrim Systemisation (Revised ATS route structure over the
More informationARRIVALS REVIEW GATWICK
ARRIVALS REVIEW GATWICK BO REDEBORN GRAHAM LAKE bo@redeborn.com gc_lake@yahoo.co.uk 16-12-2015 2 THE TASK Has everything been done that is reasonably possible to alleviate the noise problems from arriving
More informationCAA DECISION LETTER MANSTON KENT INTERNATIONAL AIRPORT (KIA) RNAV (GNSS) HOLD AIRSPACE CHANGE PROPOSAL
Directorate of Airspace Policy NATMAC Representatives 13 July 2012 CAA DECISION LETTER MANSTON KENT INTERNATIONAL AIRPORT (KIA) RNAV (GNSS) HOLD AIRSPACE CHANGE PROPOSAL 1. INTRODUCTION 1.1 During late
More informationIRISH AVIATION AUTHORITY DUBLIN POINT MERGE. Presented by James O Sullivan PANS-OPS & AIRSPACE INSPECTOR Irish Aviation Authority
IRISH AVIATION AUTHORITY DUBLIN POINT MERGE Presented by James O Sullivan PANS-OPS & AIRSPACE INSPECTOR Irish Aviation Authority 2012 Holding Holding Before Point Merge No Pilot anticipation of distance
More informationEdinburgh Airport Airspace Change Proposal. What we have proposed and why
Edinburgh Airport Airspace Change Proposal What we have proposed and why Contents Page 01 Executive Summary 02 02 Welcome 10 03 Why do we need to change? 12 04 Current airspace 16 05 Proposed flight paths
More informationCanberra Airport Aircraft Noise Information Report
Canberra Airport Aircraft Noise Information Report Quarter 1 2016 (January to March) 1 Version Control Version Number Detail Prepared by Date 1 - Environment June 2016 Airservices Australia. All rights
More informationAtlantic Interoperability Initiative to Reduce Emissions AIRE
ICAO Colloquium on Aviation and Climate Change ICAO ICAO Colloquium Colloquium on Aviation Aviation and and Climate Climate Change Change Atlantic Interoperability Initiative to Reduce Emissions AIRE Célia
More informationPerformance Based Navigation Literature Review
Performance Based Navigation Literature Review HCNF March 2018 Glen Smith Overview Introduction and Objective of the study Overview of documents that formed the study Summary of key themes and areas derived
More informationNextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures
NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures DFW International Airport Sandy Lancaster, Manager Noise Compatibility October 13, 2008 OUTLINE About DFW Airport
More informationPerth Noise Abatement Procedures - Change to Preferred Runways
Environmental Analysis Summary Preferred Runways Perth Perth Airport Perth Noise Abatement Procedures - Change to Preferred Runways Environmental Analysis Summary April 2016 1 of 10 Environment Analysis
More informationCommunity Impact: Focus on Barston
Community Impact: Focus on Barston With flights to more than 140 destinations worldwide and a workforce of more than 6,000 people, Birmingham is the UK s 7th largest airport and an economic powerhouse,
More informationREVIEW OF PERTH AIRPORT Noise Abatement Procedures
REVIEW OF PERTH AIRPORT Noise Abatement Procedures Contents SUMMARY... 3 Summary of Review Findings... 3 BACKGROUND... 4 Noise Abatement Procedures... 4 Perth Airport Noise Abatement Procedures... 4 Noise
More informationChristchurch PBN Flight Paths Trial. Interim Report
Christchurch PBN Flight Paths Trial Interim Report Christchurch PBN Flight Paths Trial Interim Report PBN trial partners have prepared the following summary outlining progress of the PBN flight paths trial.
More informationReview of brisbane Airport Noise Abatement Procedures
Review of brisbane Airport Noise Abatement Procedures 1. Summary This document presents an overview of the findings of the review of the Noise Abatement Procedures in place for Brisbane Airport. The technical
More informationRNP AR and Air Traffic Management
RNP AR and Air Traffic Management BOEING is a trademark of Boeing Management Company. Copyright 2009 Boeing. All rights reserved. Expanding the Utility of RNP AR Sheila Conway RNP AR User s Forum Wellington,
More informationUNDERSTANDING NOISE COMPLAINTS
UNDERSTANDING NOISE COMPLAINTS Agenda Objective of Meeting Toronto Pearson We are Growing Mitigating our Impacts Where Complaints Fit Toronto Pearson s Noise Complaint Process What s next Objective of
More informationAirports Commission s Senior Delivery Group - Technical Report Number 01
Airports Commission s Senior Delivery Group - Technical Report Number 01 Implementation of Performance-Based Navigation in the UK Summary The UK Future Airspace Strategy (FAS) is a programme designed to
More informationAppendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis
Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway
More informationPBN Performance. Based Navigation. Days 1, 2 & 3. ICAO PBN Seminar Seminar Case Studies Days 1,2,3. Seminar Case Studies
PBN Performance Based Navigation Seminar Case Studies Days 1, 2 & 3 1 Overview 2 Case Study - Day 1 Case Study - Day 2 Case Study - Day 3 3 Case Study - Day 1 Learning Objectives Identify navigation performance
More informationOptimized Profile Descents A.K.A. CDA A New Concept RTCA Airspace Working Group
Optimized Profile Descents A.K.A. CDA A New Concept RTCA Presented to Environmental Working Group December 05, 2007 Outline RTCA Charter and Terms of Reference Objectives Membership and Organization Activities
More informationMr. Chairman, Members of the Committee, I am Chet Fuller, President GE Aviation
Mr. Chairman, Members of the Committee, I am Chet Fuller, President GE Aviation Systems, Civil. Thank you for the opportunity to testify before the Subcommittee today on the issue of Area Navigation (RNAV)
More informationCommunity Impact: Focus on Knowle
Community Impact: Focus on Knowle With flights to more than 140 destinations worldwide and a workforce of more than 6,000 people, Birmingham is the UK s 7 th largest airport and an economic powerhouse,
More informationName of Customer Representative: Bruce DeCleene, AFS-400 Division Manager Phone Number:
Phase I Submission Name of Program: Equivalent Lateral Spacing Operation (ELSO) Name of Program Leader: Dr. Ralf Mayer Phone Number: 703-983-2755 Email: rmayer@mitre.org Postage Address: The MITRE Corporation,
More informationGOLD COAST AIRPORT - Runway 14 southern departures trial
Post Implementation Review GOLD COAST AIRPORT - Runway 14 southern departures trial Version 1 Effective January 2016 Airservices Australia 2016 1 of 13 Introduction At the request of the community, Airservices
More informationICAO Big Data Project ADS-B Data as a source for analytical solutions for traffic behaviour in airspace
ICAO Big Data Project ADS-B Data as a source for analytical solutions for traffic behaviour in airspace ICAO/IATA/CANSO PBN/2 San Jose December 8, 2016 Big Data process Quantitative Quantitative / Qualitative
More informationClassification: Public AIRSPACE AND FUTURE OPERATIONS CONSULTATION (JANUARY-MARCH 2019)
AIRSPACE AND FUTURE OPERATIONS CONSULTATION (JANUARY-MARCH 2019) LOCAL AUTHORITY BRIEFING 8 FEBRUARY 2019 Westerly operations Easterly operations PRESENTATION OVERVIEW Intro Airspace and Future Operations
More informationChapter 4 Noise. 1. Airport noise
Chapter 4 Noise 1. Airport noise Airport noise includes the following: 1) Flight noise (engine noise during takeoff and landing) 2) Ground noise (i) Aircraft engine operation noise on the ground (ii) APU
More informationNaples Airport Authority Board of Commissioners and Noise Compatibility Committee Special Meeting on Central/South Florida Metroplex
Naples Airport Authority Board of Commissioners and Noise Compatibility Committee Special Meeting on Central/South Florida Metroplex March 16, 2017 Ted Baldwin and Robert Mentzer Metroplex Overview: From
More informationPerformance Based Navigation (PBN) Implementation Plan. The Gambia
Performance Based Navigation (PBN) Implementation Plan The Gambia Version 1.0 Table of contents 1. Executive summary.. 2 2. Introduction. 2 3. The need for PBN implementation 2 4. Benifit of PBN implementation
More informationLAX Community Noise Roundtable. Aircraft Noise 101. November 12, 2014
LAX Community Noise Roundtable Aircraft Noise 101 November 12, 2014 Overview Roles and Responsibilities for Aircraft Noise Relevant Federal Regulations Relevant California Regulations Aircraft Noise Metrics
More informationENABLING GREENER FLIGHT TRAJECTORIES. David Bowen Chief of ATM SESAR JU
ENABLING GREENER FLIGHT TRAJECTORIES David Bowen Chief of ATM SESAR JU 24 November 2016 SESAR vision SESAR life cycle To define, develop and deploy the technology that is needed to increase ATM performance
More informationFLIGHT OPERATIONS PANEL (FLTOPSP)
International Civil Aviation Organization FLTOPSP/1-WP/3 7/10/14 WORKING PAPER FLIGHT OPERATIONS PANEL (FLTOPSP) FIRST MEETING Montréal, 27 to 31 October 2014 Agenda Item 4: Active work programme items
More informationDeveloping an Aircraft Weight Database for AEDT
17-02-01 Recommended Allocation: $250,000 ACRP Staff Comments This problem statement was also submitted last year. TRB AV030 supported the research; however, it was not recommended by the review panel,
More informationPBN Syllabus Helicopter. Learning Objective. phase Theoretical PBN concept. in ICAO Doc 9613)
PBN Syllabus Helicopter Training Topic phase Theoretical PBN concept training (as described in ICAO Doc 9613) PBN principles PBN components PBN scope Navigation specifications RNAV and RNP Navigation functional
More informationCairns Noise Information Pack. December 2011
Cairns Noise Information Pack December 2011 Table of Contents Purpose 2 Overview 2 Cairns Airport 3 Hours of Operation 3 Runway Configuration 3 Air Traffic 3 Track Density Plot for all aircraft operations
More informationWashington Dulles International Airport (IAD) Aircraft Noise Contour Map Update
Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update Ultimate ASV, Runway Use and Flight Tracks 4th Working Group Briefing 8/13/18 Meeting Purpose Discuss Public Workshop input
More informationREVIEW OF GOLD COAST AIRPORT Noise Abatement Procedures
REVIEW OF GOLD COAST AIRPORT Noise Abatement Procedures Introduction The purpose of this document is to present an overview of the findings of the review of the Noise Abatement Procedures (NAPs) in place
More informationPBN Airspace Design Workshop. Area Navigation. Asia and Pacific Regional Sub-Office Beijing, China. 5 May 2016 Page 1 APAC RSO BEIJING
PBN Airspace Design Workshop Area Navigation Asia and Pacific Regional Sub-Office Beijing, China 5 May 2016 Page 1 APAC RSO BEIJING Learning Objectives By the end of this presentation, you will be: Aware
More informationSafety / Performance Criteria Agreeing Assumptions Module 10 - Activities 5 & 6
Safety / Performance Criteria Agreeing Assumptions Module 10 - Activities 5 & 6 European Airspace Concept Workshops for PBN Implementation Why have safety and performance criteria? Measure performance
More informationCanberra Noise Information Pack December 2011
Canberra Noise Information Pack December 2011 Table of Contents Purpose 2 Overview 2 Canberra Airport 3 Hours of Operation/Noise Abatement Areas 3 Runway Configuration 3 Air Traffic 3 Track density plot
More informationOpportunities to improve noise management and communications at Heathrow
Opportunities to improve noise management and communications at Heathrow Summary of a dialogue between Aviation Environment Federation, British Airways, HACAN, Heathrow Airport and NATS 1. Introduction
More informationMINNEAPOLIS-ST. PAUL PUBLIC INPUT MEETING 3 RD QUARTER 2016 INTERNATIONAL AIRPORT (MSP)
3 RD QUARTER 2016 MINNEAPOLIS-ST. PAUL INTERNATIONAL AIRPORT (MSP) PUBLIC INPUT MEETING Metropolitan Airports Commission Noise Program Office July 27, 2016 PUBLIC INPUT MEETING Meeting Goals To hear the
More informationNoise Abatement Arrival Procedures at Louisville International Airport. Prof. John-Paul Clarke Georgia Institute of Technology
Noise Abatement Arrival Procedures at Louisville International Airport Prof. John-Paul Clarke Georgia Institute of Technology The Team Noise Abatement Procedures Working Group (NAPWG) has the following
More informationUSE AND APPLICATION OF GNSS IN THE IMPLEMENTATION OF NAVIGATION BASED ON PERFORMANCE IN ECUADOR
BACKGROUND OF GNSS USE The guidelines for the transition to the use of the Global Navigation Satellite System GNSS in the CAR / SAM Regions were issued by ICAO at the Eleventh World Air Navigation Conference
More informationConsiderations for. RNP to xls. Operations. Juergen Ruppert. Regional Director Air Traffic Optimisation Services GE Aviation
Considerations for RNP to xls Operations Juergen Ruppert Regional Director Air Traffic Optimisation Services GE Aviation RNP to ILS 2 Content Why RNP to XLS What is the technology How does it work now?
More informationRNP OPERATIONS. We will now explain the key concepts that should not be mixed up and that are commonly not precisely understood.
RNP OPERATIONS 1. Introduction Planes were made as a means of transport. To successfully fly from a location A to a location B, pilots were first and foremost navigators. Originally relying on visual landmarks
More informationTANZANIA CIVIL AVIATION AUTHORITY AIR NAVIGATION SERVICES INSPECTORATE. Title: CONSTRUCTION OF VISUAL AND INSTRUMENT FLIGHT PROCEDURES
Page 1 of 8 1. PURPOSE 1.1. This Advisory Circular provides guidance to personnel involved in construction of instrument and visual flight procedures for publication in the Aeronautical Information Publication.
More informationInternational Civil Aviation Organization. PBN Airspace Concept. Victor Hernandez
International Civil Aviation Organization PBN Airspace Concept Victor Hernandez Overview Learning Objective: at the end of this presentation you should Understand principles of PBN Airspace Concept 2 Gate
More informationToronto Aviation Noise Group (T.A.N.G.) Response to NAV CANADA S response to the HELIOS report for Toronto Airspace Review
Toronto Aviation Noise Group (T.A.N.G.) Response to NAV CANADA S response to the HELIOS report for Toronto Airspace Review Sandra Best, Co-Chair, T.A.N.G. sandrabest62@me.com December 13, 2017 Contents
More informationAIRSPACE PRINCIPLES CONSULTATION DOCUMENT JANUARY 2018
AIRSPACE PRINCIPLES CONSULTATION DOCUMENT JANUARY 2018 Page 2 Contents Contents 1. Introduction 2. Airspace change process 3. Redesigning our airspace 4. Airspace design principles 5. Have your say Page
More informationFLIGHT OPERATIONS PANEL
International Civil Aviation Organization FLTOPSP/WG/2-WP/11 24/04/2015 WORKING PAPER FLIGHT OPERATIONS PANEL WORKING GROUP SECOND MEETING (FLTOPSP/WG2) Rome, Italy 4 to 8 May 2015 Agenda Item 6: Any Other
More informationGold Coast Noise Information pack June 2012
Gold Coast Noise Information pack June 2012 Table of Contents Purpose 2 Overview 2 Hours of Operation/Curfews 3 Runway Configuration 3 Air Traffic 4 Track Density Plot 4 Typical tracks for Wind Conditions
More informationNav Specs and Procedure Design Module 12 Activities 8 and 10. European Airspace Concept Workshops for PBN Implementation
Nav Specs and Procedure Design Module 12 Activities 8 and 10 European Airspace Concept Workshops for PBN Implementation Learning Objectives By the end of this presentation you should understand: The different
More informationRNP AR RWY 16 in Vienna Schwechat (LOWW) PBN based Noise Abatement
RNP AR RWY 16 in Vienna Schwechat (LOWW) PBN based Noise Abatement Dr. Philipp Daniel Schaad Head of Instrument Flight Procedures (ATM/IFP) ICANA, Frankfurt, November 2016 DIESER TEXT DIENT DER NAVIGATION
More informationNew York Aviation Management Association Conference
New York Aviation Management Association Conference Presented by: Carmine W. Gallo Federal Aviation Administration Eastern Region Regional Administrator September 14, 2016 1 The What is and Benefits of
More informationSTUDY OF RUNWAY 12L AND 12R ARRIVAL OPERATIONS. September 2016
STUDY OF RUNWAY 12L AND 12R ARRIVAL OPERATIONS September 2016 Environment Department, Noise Program Office Metropolitan Airports Commission 6040 28th Avenue South, Minneapolis, MN 55450 MetroAirports.org
More informationCairns Airport Aircraft Noise Information Report
Cairns Airport Aircraft Noise Information Report Quarter 4 2015 (October to December) 1 Version Control Version Number Detail Prepared by Date 1 - Environment February 2016 Airservices Australia. All rights