1 Construction News Issue 10 Spring 2011 Helpline: The East-West Link, a public covered space. In conjunction with English Heritage, it was agreed that the old scars of the assembly sheds should be left to highlight the historical background of the buildings. Fit-out works have commenced! We ve done it. For the last three years we have been working on the transformation of the Granary Complex into a new home for the University of the Arts London ready for their 4,500 staff and students to move into this September. The University buildings have achieved, what s known in the business as, practical completion - well done BAM Construct. There is still a lot more to do. The University of the Arts London and their contractor Overbury commenced fitting out the spaces and bringing in equipment from April in readiness for their use. The University s new home is made up of three different buildings a brand new purpose built set of studios, workshops and performance theatre in what was once the old railway assembly sheds, a retained façade construction in the Eastern Transit Shed, and the Granary Building. Once on the English Heritage s at risk register the Grade II listed Granary building has been fully restored and refurbished. With the estate officially open from September this year the arrival of the world-famous art college at King s Cross will bring other benefits, including public access for the first time to numerous areas of the historic Eastern Goods Yard. The following contractors are working in partnership to deliver King s Cross:
2 Contract Complete! cont. Work on King s Boulevard and Goods Way has started, connecting the campus directly to the King s Cross and St Pancras transport hub. Initially, King s Boulevard will be pedestrianised, and will be open to the public by September. Other major pieces of infrastructure have also been installed as part of the project including a utilities spine from the Energy Centre in the north, up to the new vehicle bridge across the Regent s Canal. Not only does this serve the University, but it will also provide utilities connections to many other development plots helping to create a well serviced site. All sorts of civil engineering works have also been undertaken, including the new bridge, major retaining structures, surface and foul sewers, roads and painstaking laying of historic granite cobbles as part of the landscaping and public realm works. Some interesting facts: The gross area of the University buildings is around 430,000 sq ft or almost 10 acres. More than 1.3 million oak timber blocks have been individually laid in the covered street floor Approximately 20,000 cubic metres of concrete has been used enough to fill eight Olympic sized swimming pools. Over 150 listed building consents and reserved matter conditions have been submitted and approved At full capacity the air handling units combined can shift 95,000 litres of air a second Granary Square With the Granary Building now complete we have turned our attention to finishing Granary Square. At the moment we re focusing on foundation works to create a large pump room next to the new bridge. Here we will be installing pumping equipment to serve the 1,080 water jets for the fountains which are being installed in front of the building. We are also transforming the access to the Regent s Canal by creating a wide set of south facing shallow steps and new terraces. The public realm in Granary Square has been designed by Townshend Landscape Architects, the street furniture by Paul de Monchaux and fountain design by The Fountain Workshop. Granary Square will be completed by Summer View down the University s covered street Installing the terraced steps to the Regent s Canal
3 Heating, Cooling and Powering the University The energy efficient mechanical and electrical systems for the University are in their final testing phase. They will soon be ready to contribute to our site-wide target of cutting carbon emissions by at least 50% relative to 2005 levels through energy-efficient building design, the application of the latest technologies and connection to a site-wide Combined Heat and Power (CHP) driven hot water distribution network. All our buildings will connect to the hot water distribution network which will be fed from the Energy Centre (completed some time ago). The power generated by the CHP plant will also be used to off-set electrical supplies from the National Grid. The cooling demands of the office buildings, which represent the largest energy requirement on the site, will be met by a combination of absorption chillers fed from the district heat network (trigeneration) with any extra demand met from efficient mechanical chillers. Cooling systems will use the best chilled beam technology in order to minimise energy use. Constant temperature heating circulation pumps King s Boulevard King s Boulevard works started in September The interim retaining structure to the east of King s Boulevard has been completed and this has enabled the works to proceed while Network Rail are still occupying Zone A (they are due to leave in 2012). Temporary sheet piling has been installed at the south end of King s Boulevard to protect the gas mains from disturbance during the future construction of the subway to Building B2. The lines of the future piling of King s Boulevard were excavated in autumn last year to remove obstructions prior to the earthwork operations. View looking north showing the works underway to create King s Boulevard The Boulevard levels are being built up using soils from the development site to create a sloping route from King s Cross Station to Goods Way. The large diameter attenuation drainage is nearly finished and this will be followed by the large gas mains and the district heating.
4 Aerial View looking West - May 2011 Camley Street Natural Park St Pancras International Pancras Road Gasholder No. 8 1 Granary Square King s Boulevard King s Cross Station Shared Service Yard entrance Goods Way Kings Place
5 Goods Way carriageway works 1 Public realm works around the University Energy Centre 2 Public East-West Link 3 4 University of the Arts London 2 5 Building R4 3 University s covered street York Way 4 University s Performance Theatre 5 Simon Hazelgrove
6 Plot R4 Building R4 started on site in December and was the first residential building on the development to be brought forward. It will contain 117 high quality affordable homes as well as commercial units on the ground floor. The thoughtfully planned building, designed by PRP Architects, will be handed over to our Affordable Housing Partner, One Housing Group. Almost a third of the units will be for families and all have been designed to meet Lifetime Homes standards. The Contractor delivering R4 is Carillion Construction Limited. As the photo below shows, the concrete frame of the building is rapidly taking shape and the first six storeys are in place. We will also be delivering significant public realm improvements alongside this building, both within the site and along York Way including a new Zebra Crossing. Construction is due to complete in July Interim Service Road (ISR), March 2011 Access Reconfiguration The Interim Service Road was opened in January 2011 and this enabled the closure of Battle Bridge Road to Network Rail traffic and secure the site for the construction of King s Boulevard. Work to the south side of Goods Way has been completed and now switches to the northern side of the carriageway enabling the diversion of the existing utilities and the provision of new utilities (district heating, electricity and communications) linked to the canal bridge. In January 2011 a section of Pancras Road was closed to southbound traffic from Goods Way to allow the contractor to start trial pits and excavation for the new Thames Water main and the relocated gas mains. From June to October this same section of Pancras Road will be closed to all traffic. Access to Coach Road and St Pancras Station car park will be retained. Plot R5 (North) Works to Building R4, May 2011 Simon Hazelgrove Progress is also being made on Plot R5 (North), after detailed plans for 143 homes were given reserved matters approval by Camden Council in April. Construction is now underway on the scheme which consists of a collection of three buildings, varying in height from two to 15 storeys, with commercial uses on the ground floor. The new homes, designed by architects Maccreanor Lavington, meet a priority need in the Borough with more than a quarter specifically designed for the elderly. 40 apartments with communal areas, in one of the buildings, will allow older people to live independently while also having access to the care and support services which they may need over time. The remaining homes in the other two blocks comprise 63 social rented apartments and 40 shared ownership apartments. As with R4, Plot R5 (North) will be owned and managed by the development s affordable housing partner, One Housing Group. Carillion Construction Plc, the main contractor, has commenced construction of the substructure including installation of over 180 piles, various pile caps and drainage works. The project is due to be completed in December New bridge Goods Way Interim Service Road Works to Goods Way, May 2011 Simon Hazelgrove
7 Station deliveries After 157 years, vehicular servicing to King s Cross station moved from the surface to below ground, into the Shared Service Yard a project which has been jointly funded by King s Cross Central and Network Rail. This has significant operational benefits for the station, allowing retail and on-board services to be accessed from subterranean levels, minimising disruption to passengers during delivery. View from St Pancras International across King s Cross Station Additionally, it clears the way for the delivery of Station Square, the gateway to the development, making all the difference to the opening of King s Boulevard for visitors wishing to explore the site from September. Apprentices Our Construction Skills Centre continues to go from strength to strength with everyone who uses the facility currently on an apprenticeship placement in the local area. This includes working on King s Cross itself with 5% of BAM Nuttall and Carillion s workforce made up of apprentices. The centre on York Way offers local people training, professional qualifications and employment opportunities in the construction industry and also provides apprenticeship placements for people aged who are out of work or carrying out unskilled work. This continues to be incredibly popular and we are currently recruiting for the summer intake. For more information call: Construction Hoarding On your travels you may have noticed our new hoarding around the site creating a more unified and identifiable development site. We have two designs in place: a red Girder effect around the key entrances which represents the reuse of heritage within the site and on longer stretches a leaf motif to reflect the significant amount of public realm being created - some eleven acres. Dotted around the hoarding key statistics and facts are displayed as oversized elements such as the example seen above which highlights the number of historic buildings and structures being restored across the 67 acre site. Oliver Knight, Property Awards 2011 Property Awards 2011 King s Cross Central won the Regeneration Award in the Property Awards 2011, hosted by Property Week. The awards, which were based on nominations made through the magazine s website, were announced at a ceremony in April. King s Cross Central was described as showing true regeneration, completely transforming a rundown part of the country and now succeeding with a succession of leasing deals. To see more details about the awards and all the other winners visit:
8 Junction Proposals 1. Canal Street / York Way Works commence in late Public opening mid Initially this will be a priority junction. Traffic lights to be installed when Zone W is developed. 2. Plot R4 / Plot R5 / York Way Not a signalled junction. 3. Plot R2 / York Way Road junction omitted. 4. York Way / Copenhagen Street Traffic signals installed - to be switched on in July Wharf Road / York Way Existing traffic signals switched off in July 2011 and removed. 6. Goods Way / York Way Amend traffic lights when junction is re-configured as part of the development of the petrol station site (includes a right hand turn south down York Way from Goods Way). Approximate implementation in King s Boulevard / Goods Way / Regent s Canal Bridge Install zebra crossing by September 2011 in-line with opening of King s Boulevard. Upgrade to full signal junction when King s Boulevard opens to buses and taxis (earliest 2014). 8. Camley Street / Goods Way / Pancras Road Re-configure the existing traffic signals by December Pancras Road / King s Boulevard Traffic signals installed. Full signal junction when King s Boulevard opens to buses and taxis (earliest 2014) A1 A2 9 E1 B2 B4 A3 A4 F 6 B1 B6 A5 5 B3 B5 7 J 8 4 Q1 Q2 R2 N1 N2 N1 N1 P1 P2 S2 R1 R3 R5(S) R4 3 2 T1 T2 S1 S4 R5 W2 W3 S5 T3 S3 T4 T5 1 W1 T6 Aerial View looking west with potential build-out Miller Hare All images John Sturrock unless noted otherwise Contacting Us There is a dedicated website and freephone helpline staffed during normal working hours, Monday to Friday. If somebody cannot answer immediately, there is an answer-phone facility. Freephone Helpline: Training and Jobs As part of our commitment to deliver local benefits, the Construction Skills Centre on York Way, run by contractor Carillion, offers advice and information on finding work in the construction industry local to King s Cross. It also provides apprenticeships for people aged who are out of work or carrying out unskilled work. For more information call: Who is backing the scheme? King s Cross Central is being developed by the King s Cross Central Limited Partnership (KCCLP), which brings together: Argent King s Cross Limited Partnership London & Continental Railways DHL Supply Chain For information on the future of King s Cross, please visit our marketing suite, which is open to the public Tuesdays to Fridays, during office hours: King s Cross Marketing Suite German Gymnasium Pancras Road London N1C 4TB Scope of Works The development at King s Cross will bring enormous and continuing benefits to the area. Safety and cleanliness are two of the local residents main objectives, but this development will offer a lot more. It will provide some 2,000 homes and serviced apartments, employment for thousands, schools, shops, food and drink outlets, cultural and community uses, health centres and many other facilities. Over 40% of this development will be public realm. Much of the area s heritage will be maintained by refurbishing 20 historic buildings and structures, including the listed Gasholder triplet.
Construction News. Granary Complex scoops Mayor of London s top prize
Construction News Issue 13 Spring 2012 Helpline: 0800 328 8840 www.constructionatkingscross.com The CSM reception area and central atrium of the Granary Granary Complex scoops Mayor of London s top prize
More informationKing s Cross Construction Impact Group Quarterly Monitoring Report 8 th June 2009
King s Cross Construction Impact Group Quarterly Monitoring Report 8 th June 2009 Contents: Introduction Progress Update Newsletters and Flyers Press Update Noise monitoring summary report Air Quality
More informationUrbanBuzz. 2 nd December Roger Madelin Joint Chief Executive, Argent Group PLC
UrbanBuzz King s Cross Development Meeting the requirements of sustainability and creating neighbourhoods where commerce, residencies and infrastructure can all thrive. 2 nd December 2008 Roger Madelin
More informationLISTED BUILDING AND FIRE STATION CENTRAL SITE WHITGIFT STREET OLD PARADISE GARDENS
WELCOME The London Fire Brigade (LFB) and partners U+I are working together to develop proposals for 8 Albert Embankment. Thank you to everyone who visited our previous public exhibition and provided feedback
More informationDEVELOPMENT MAP 2017/18
INVEST IN DEVELOPMENT MAP 2017/18 WELCOME TO Situated in the very centre of the country and on the edge of the Peak District National Park, Chesterfield is highly ambitious. Over 1 billion of development
More informationBartlett Square Welcome. Investment Framework. London Airport Ltd
1 Welcome Welcome to Luton s public exhibition on proposals for the (formerly known as Stirling Place) project which will comprise 2.5 acres of commercial development, providing up to 2,000 jobs for local
More informationHISTORY IN THE MAKING. The UK s most important city centre development outside London. Being delivered by:
UPDATE JANUARY 2016 HISTORY IN THE MAKING The UK s most important city centre development outside London. Being delivered by: THE HEART OF THE CITY St Philip s Square Birmingham Museum & Art Gallery A
More informationLONGBRIDGE WEST COMMERCIAL COFTON PARK PARK VIEW RESIDENTIAL 66 MILLION BOURNVILLE COLLEGE. teaching 3,500 students in a range of industries
LONGBRIDGE BIRMINGHAM Mixed use LONGBRIDGE EAST RESIDENTIAL LONGBRIDGE WEST COMMERCIAL COFTON PARK PARK VIEW RESIDENTIAL LONGBRIDGE WEST RESIDENTIAL LONGBRIDGE NORTH RESIDENTIAL LOWHILL LANE RESIDENTIAL
More informationForeword. Sir Robin Wales Mayor of Newham
Foreword Nowhere else in the UK is undergoing transformation on the scale of Newham. With an abundance of development land, excellent transport links and a young, energetic and increasingly skilled workforce,
More informationEnterprise Way. The new Airport City link road. June 2017 Progress Update
Enterprise Way The new Airport City link road June 2017 Progress Update Airport City Manchester is one of the most exciting business destinations in development today. The total planning area of Airport
More informationWHAT MAKES A SUCCESSFUL BUSINESS COMMUNITY?
WHAT MAKES A SUCCESSFUL BUSINESS COMMUNITY? The traditional business park format is no longer sustainable. Occupiers want more; more amenities, more convenience and a better working environment [work-life
More informationGreenwich Peninsula Investor and Analyst Day 12 March 2013 Quintain Estates and Development PLC
Greenwich Peninsula Investor and Analyst Day 12 March 2013 Agenda Maxwell James Chief Executive Anthony Gill Development Director, Greenwich Overview Greenwich Peninsula 2 Quintain Strategy Delivering
More informationPre-application submission for Committee: Phase 4 development at West Hendon
Pre-application submission for Committee: Phase 4 development at West Hendon 1. Development Details Phase 4 of the West Hendon Estate Regeneration. 2. Background The redevelopment of the West Hendon Estate
More informationJobcentre Plus advisers giving guidance to a job seeker at the Crossrail Visitor Information centre
Crossrail Bulletin www.crossrail.co.uk 0345 602 3813 FREEPOST CROSSRAIL ISSUE 20 Mar 2010 Crossing the Capital Connecting the UK Jobcentre Plus - at the Visitor Information Centre Crossrail is committed
More informationCreating a High Quality Business District
Date Month Date Month Friday 7 November 2014 Nine Elms on the South Bank A Bilfinger Real Estate company Creating a High Quality Business District New London Architecture Introduction Nine Elms Vauxhall
More informationMaking Cities Examples of Urban Development in London. David Partridge, Managing Partner, Argent
Making Cities Examples of Urban Development in London David Partridge, Managing Partner, Argent NEW YORK PARIS La Defense LONDON King s Cross Canary Wharf ARGENT PROJECTS THE KING S CROSS AREA THE TRANSPORT
More informationEnergy from Waste and Recycling Facility Trident Park, Cardiff. Planning History. January 2010 SLR Ref: B
Energy from Waste and Recycling Facility Trident Park, Cardiff Planning History January 2010 Ref: 402-0036-0306B Viridor Ltd. i 402/0036/00306B CONTENTS 1.0 INTRODUCTION... 1 2.0 GENERAL HISTORY... 3
More informationSustainable Brisbane Walking Tour
Sustainable Brisbane Walking Tour 150 Charlotte Street 4 Star Green Star Office As Built v3 The refurbishment of this commercial office building focused on upgrading mechanical, electrical and hydraulic
More informationMuse Developments helps Morgan Sindall Group's results
News 9.08.18 Muse Developments helps Morgan Sindall Group's results Urban regeneration and property development company Muse Developments, which has offices in London, Manchester, Glasgow and Leeds, has
More informationThe Edinburgh 12. Monthly Bulletin March City of Edinburgh Council. Steve McGavin Head of Business Partnerships
The Edinburgh 12 Monthly Bulletin March 2015 City of Edinburgh Council Steve McGavin Head of Business Partnerships steve.mcgavin@edinburgh.gov.uk Also available to view online: http://www.investinedinburgh.com/the-edinburgh-12/.
More informationKEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM THE ELEPHANT ISSUE 08 SUMMER 2015
Building for future generations KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM THE ELEPHANT ISSUE 08 SUMMER 2015 See p.10 for latest events 24/7 HELPLINE: 020 3600 0001 LENDLEASE.COM/ELEPHANTANDCASTLE
More informationHAVELOCK NEWSLETTER HAVELOCK NEWSLETTER. ISSUE 15 Spring ISSUE 15. Spring
Your new Neighbourhood Coordinator Nicola Wheeler is your new Havelock Neighbourhood Coordinator. Her job is to work with people who live on Havelock and those who provide services to the local community
More information317a & 400 Hoe Street, Walthamstow, E17 9AA
North East London Residential Led Development Opportunity 317a & 400 Hoe Street, Walthamstow, E17 9AA Red line boundary for indicative purposes only Summary Residential-led two-site development opportunity
More informationPARK CRESCENT LUTON LONDON. The best of both worlds.
PARK CRESCENT LUTON LONDON The best of both worlds. Contents About Luton... 3 Five reasons why Luton is flying high... 4 Accessibility and travel times... 5 Luton to London in 23 minutes... 6 Luton airport...
More informationThe Brief The Brief APS
The Brief APS Public transport accessibility The site benefits from a high level of public transport accessibility with a PTAL rating of 6b ( Excellent ). Goodge Street Tottenham Court Road, Oxford Street
More informationChapter 2 Route window W25 Maidenhead station. Transport for London
Chapter 2 Route window W25 Maidenhead station MAIDENHEAD STATION 2 Route window W25 Maidenhead station 2.6 The drawings provided at the end of this chapter present the main features of the route window,
More informationTRANSFORMING EAST LONDON...
TRANSFORMING EAST LONDON... OUR VISION FOR EAST PLUS An opportunity to create one of the most sought after business destinations in London. A catalyst for the wider economic regeneration of London Riverside.
More informationNotes form the North of Horsham development Parish Liaison Meeting. at Roffey Millennium Hall Crawley Road, Horsham.
Notes form the North of Horsham development Parish Liaison Meeting held on Friday 28 th September 2018 at 10am at Roffey Millennium Hall Crawley Road, Horsham. Planning application:- DC/16/1677 Development
More informationWelcome. Welcome to our public exhibition which explains our proposed changes to the Brentford Community Stadium development, at Lionel Road South.
Welcome Recent aerial view of the site with Griffin Park, the existing stadium, in the background. Welcome to our public exhibition which explains our proposed changes to the Brentford Community Stadium
More informationCreating Connections in Niagara Region
Creating Connections in Niagara Region GERRY CHAPUT, CHIEF CAPITAL OFFICER - METROLINX ERIN MOROZ, DIRECTOR OF COMMUNICATIONS AND COMMUNITY RELATIONS - METROLINX METROLINX PRESENTATION TO NIAGARA REGION
More informationInside Government Conference Case Study: Norwich Northern Distributor Road
Inside Government Conference Case Study: Norwich Northern Distributor Road 29 March 2017 Martin Wilby Chair of Environment, Development and Transport Committee Norfolk County Council Introduction What
More informationWest of England. Priority Places Requiring Public Investment
West of England Priority Places Requiring Public Investment Development Urban Regeneration & Suburban Intensification Bristol Central Area Bristol Central Area; Stokes Croft, Temple Meads & St Philips
More informationHotel and Hospitality Services. Capita Real Estate
Hotel and Hospitality Services Capita Real Estate About Us At GL Hearn we are seeing continuous growth in the hotel investment and development markets. We act for investors, developers and occupiers across
More informationOpen Report on behalf of Richard Wills, Executive Director for Environment and Economy
Agenda Item 7 Executive Open Report on behalf of Richard Wills, Executive Director for Environment and Economy Report to: Executive Date: 02 September 2014 Subject: Lincoln East West Link Road Phase 1
More informationGreat Portland Estates Trading Update Strong Operational Performance
Press Release 6 July 2017 Great Portland Estates Trading Update Strong Operational Performance Great Portland Estates plc ( GPE ) today publishes its trading update for the quarter to 30 June 2017. Continued
More informationPublic Realm & Landscape
Town Centre Context Public Realm & Landscape 1. Public realm in the Town Centre varies significantly in quality. Areas of particularly good quality public realm are located around the Minster and outside
More informationBloor Street West Rezoning Application for a Temporary Use By-law Final Report
STAFF REPORT ACTION REQUIRED 3741 3751 Bloor Street West Rezoning Application for a Temporary Use By-law Final Report Date: June 12, 2007 To: From: Wards: Reference Number: Etobicoke York Community Council
More informationCORPORATION STREET, COVENTRY. Another prestigious development by Award Winning Developer 1/7
CORPORATION STREET, COVENTRY Another prestigious development by Award Winning Developer 1/7 NEW PRIME OFFICE SPACE Award winning developer EDG Property is delighted to present Hawkins; newly refurbished
More informationPRINCEGATE HOUSE DONCASTER, DN1 3EN. Well Located Strategic Investment/Development Opportunity with Short Term Government Income
INVESTMENT SUMMARY Prominent location in the heart of Doncaster town centre situated on Princegate. Freehold. Ideally located close to the Waterdale Shopping Centre and the recently regenerated new 300
More informationImproving our roads to drive our future
Improving our roads to drive our future Improving our roads to drive our future From April 2013, Island Roads will begin upgrading, enhancing and maintaining the Isle of Wight s 804 kms of rural and urban
More informationPART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT
PART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT NOVEMBER 2012 1.0 INTRODUCTION This report has been prepared in support
More informationBusiness Case Approved. Under Construction. Business Case Approved. Under Construction
Item 6 Appendix A: LGF Project Summary for South Essex Update September Project and A127 Network Resilience (Essex) Basildon Integrated Transport Package (Essex) Range of improvements at key locations
More informationThamesmead newsletter April 2018
Thamesmead newsletter April 2018 Waterfront update Transport for London (TfL) has been asked by the Mayor of London to investigate how the Docklands Light Railway (DLR) can be extended from Gallions Reach
More informationRichard Starkey CFO Crosby Lend Lease Investor Roadshow UK / US May 2006
Case Study Clarence Dock, Leeds Richard Starkey CFO Crosby Lend Lease Investor Roadshow UK / US May 2006 Case Study Clarence Dock Case study Clarence Dock, Leeds Leeds demographics History Site acquisition
More informationBolton Council Invest in Bolton. Welcome INVEST IN
Welcome INVEST IN Partnerships for Growth Building a brighter future through partnership Vision Invest in Logistics North Bolton When it comes to the economic regeneration of Greater Manchester, Bolton
More informationROCHESTER RIVERSIDE. City of learning, culture, tourism and enterprise.
ROCHESTER RIVERSIDE City of learning, culture, tourism and enterprise www.medway.gov.uk/medwayrenaissance www.medwayrenaissance.com CAT RIVER MEDWAY 15 11 21 16 13 17 14 18 20 19 CASTLE 12 Y 1 6 4 3 2
More informationConstruction Open Evening
Construction Open Evening 16 February 2017 www.gov.uk/hs2 Forward Look www.gov.uk/hs2 Euston Station and Approach four week look ahead Week 1 Commencing 13 February 42 Water Main trial trenches Albany
More informationRoundhouse Way Transport Interchange (Part of NATS City Centre Package)
Roundhouse Way Transport Interchange (Part of NATS City Centre Package) 15/16 16/17 17/18 18/19 19/20 Total TOTAL COST Roundhouse Way Transport Interchange 0.5m 0.5m FUNDING CIL 0.05m 0.05m Growth Deal
More informationEdinburgh Waverley capacity upgrade
Edinburgh Waverley capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains and to prepare for projected future growth in demand for both track and
More informationChapter 13 Route Window NE12 Harold Wood station. Transport for London
Chapter 13 Route Window NE12 Harold Wood station HAROLD WOOD STATION 13 Route Window NE12 Harold Wood station 13.8 Harold Wood station is on Gubbins Lane close to the junction of A12 Colchester Road and
More informationProposals for the Harrogate Road / New Line Junction Improvement Scheme. August / September Supported by:
Proposals for the Harrogate / New Line Junction Improvement Scheme August / September 2016 Supported by: Introduction Key Benefits Proposals are currently being developed for changes to the junction of
More informationEXHIBIT LIST. No Exhibit Name Page. 1 R391 HS2 Residents Charter.pdf (R391) R392 Response to Select Committee
Reference No: HOC/10002 Petitioner: Reference Material Published to Collaboration Area: Monday 25-Mar-2019 EXHIBIT LIST Page 1 of 9 No Exhibit Name Page 1 R391 HS2 Residents Charter.pdf (R391) 2-3 2 R392
More informationLEEDS. INNOVATIVE INFRASTRUCTURE DELIVERY Creating a catalyst for regeneration and unlocking investment opportunities. Leeds Railway Station
LEEDS INNOVATIVE INFRASTRUCTURE DELIVERY Creating a catalyst for regeneration and unlocking investment opportunities Leeds Railway Station INTRODUCTION Leeds is at the centre of the Northern Powerhouse
More informationEnterprise and Business Scrutiny Panel
Enterprise and Business Scrutiny Panel Keren Jones, Service Director, City Economy Marie Bintley, Head of City Development 03 February 2015 Citywide Economic Context Business and enterprise: 8,065 Businesses
More informationGRAND CENTRAL BIRMINGHAM
FACT FILE JANUARY 2014 GRAND CENTRAL BIRMINGHAM Anchored by a full line John Lewis Store, Grand Central Birmingham will bring over 40 new premium and high quality stores and more than 20 new concept cafes
More informationFERRY TERMINAL ST LUCIA
Consideration: FERRY TERMINAL ST LUCIA The floods in January 2011 severely damaged the CityCat and City Ferry terminals along the Brisbane River. Directly after the event a huge effort was made to provide
More informationAVAILABLE MARCH 19 EXCHANGED
AVAILABLE MARCH 19 EXCHANGED UNITS FROM 1,420 SQ.FT TO 16,076 SQ.FT R E S T A U R A N T B A R G Y M I T Y O P P O R T U N CHESTERFIELD S40 1UN EAT DRINK SLEEP CHESTERFIELD A large thriving market town
More informationChapter 8 Route Window NE7 Chadwell Heath station. Transport for London
Chapter 8 Route Window NE7 Chadwell Heath station Transport CHADWELL HEATH STATION 8 Route Window NE7 Chadwell Heath station Baseline conditions 8.6 This route window lies within the London Boroughs of
More informationChanging Estates Strategy
Changing Estates Strategy Andrew Grainger Director UCL Estates 10 October 2014 Changing Estate Strategy Challenges and Opportunities UCL Strategy Estate Strategy and Capital Programme Funding Engagement
More informationTRANSFORMING EAST LONDON...
TRANSFORMING EAST LONDON... OUR VISION FOR EAST PLUS 2 3 An opportunity to create one of the most sought after business destinations in London. A NEW BUSINESS DESTINATION IN EAST LONDON 5 sites across
More informationA place for everyone. Brand new office, retail and leisure opportunities; welcome to the most exciting mixed-use development in the north east.
A place for everyone Brand new office, retail and leisure opportunities; welcome to the most exciting mixed-use development in the north east. 01 / DurhamGate / Home Just south of Durham s thriving city
More information@ENERGETICA_UK ENERGETICA.UK.COM BUSINESS PARKS
@ENERGETICA_UK ENERGETICA.UK.COM BUSINESS PARKS LIVE VISIT WORK INVEST CONTENTS ENERGETICA SCOTLAND S ENERGY CORRIDOR 5 ABERDEEN INTERNATIONAL BUSINESS PARK 6 ABZ BUSINESS PARK 7 D2 BUSINESS PARK 8 ABERDEEN
More informationNSW PRE-BUDGET STATEMENT FUTURE ECONOMY FUTURE JOBS
2017-18 NSW PRE-BUDGET STATEMENT FUTURE ECONOMY FUTURE JOBS Executive Summary The 2017-18 NSW State Budget presents an opportunity for the NSW Government to future-proof the tourism and transport sectors.
More informationFOOD & BEVERAGE / RETAIL OPPORTUNITY
FOOD & BEVERAGE / RETAIL OPPORTUNITY Context:- Belfast Harbour Commissioner s (BHC) have freehold title to an area of City Centre land which has been designated as the City Quays Urban Regeneration Area.
More informationWhere the future works
Building S5 Where the future works The idea of the workplace has changed dramatically in recent years. No longer just a physical setting, done right, the workplace can contribute to enhanced employee health
More informationTeam London Bridge Response to the Department for Transport Consultation on the combined Thameslink, Southern and Great Northern franchise
Team London Bridge Response to the Department for Transport Consultation on the combined Thameslink, Southern and Great Northern franchise 23 August 2012 Table of Contents 1. Executive Summary 2. Introduction
More informationA63 Castle Street, Hull HullBID Network Lunch 24 August 2017
A63 Castle Street, Hull HullBID Network Lunch 24 August 2017 James D Leeming Senior Project Manager What we will cover today? Introduction to Highways England and the Road Investment Strategy A63 Scheme
More informationPEEL WIRRAL COMMERCIAL PORTFOLIO. Over 300,000 sq ft of industrial & office space
PEEL WIRRAL COMMERCIAL PORTFOLIO Over 300,000 sq ft of industrial & office space IRRAL OMMERCIAL ORTFOLIO Click on the images to take you to the relevant developments page. Birkenhead Land and Yards Britannia
More informationLIVE. WORK. PLAY. STATUS OF DEVELOPMENT SPRING Produced for information by the City of Markham
LIVE. WORK. PLAY. STATUS OF DEVELOPMENT SPRING 2013 Produced for information by the City of Markham Community CITY OF MARKHAM CIVIC CENTRE 101 TOWN CENTRE BOULEVARD East side of Town Centre Boulevard,
More informationHarrogate Road, Eccleshill, BD2 3NS
Harrogate Road, Eccleshill, BD2 3NS SHIPLEY BRADFORD A658 MOORSIDE RD A658 HARROGATE RD ECCLESHILL A658 Major development opportunity for 600 houses Planning Consent granted April 2015 Available as a whole
More informationWarehouse case study. Cargo Facility, Stansted. 35 million, transit warehouse cargo facility pre-let to Federal Express at Stansted Airport
Warehouse case study Cargo Facility, Stansted 35 million, transit warehouse cargo facility pre-let to Federal Express at Stansted Airport This new facility shows how BAA Lynton can deliver large complex
More informationLlandudno Junction. Regeneration Proposals for the Future. December 2009
Llandudno Junction Regeneration Proposals for the Future December 2009 Llandudno Junction - Vision Statement 1 Purpose 1.1 The purpose of this document is to describe key priorities to support the regeneration
More informationKEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM THE ELEPHANT ISSUE 07 SPRING 2015
Building for future generations KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM THE ELEPHANT ISSUE 07 SPRING 2015 See p.10 for events taking place this May 24/7 HELPLINE: 020 3600 0001 LENDLEASE.COM/ELEPHANTANDCASTLE
More informationLUMIERE LONDON KING S CROSS INFORMATION and FAQs
LUMIERE LONDON KING S CROSS INFORMATION and FAQs ABOUT THE FESTIVAL When is Lumiere? Lumiere London takes place over four evenings on Thursday 18 to Sunday 21 January. The festival is open from 17.30-22.30
More informationTVP2. Thames Valley Park, Reading RG6 1PT
Thames Valley Park, Reading RG6 1PT Thames Valley Park, Reading RG6 1PT is a headquarters office building originally developed by Argent. The building has undergone a major refurbishment to bring the accommodation
More informationNEWLY REFURBISHED OFFICE SPACE
NEWLY REFURBISHED OFFICE SPACE Stephensons House_210x270_7March_Repro.indd 1 07/03/2017 15:13 CGI of Westfield, Croydon CROYDON WILL BE HOME TO A NEW WESTFIELD SHOPPING CENTRE FROM 2020, PROVIDING 1.5M
More informationHARBOUR EDGE STITCH. Uniting the Waterfront with the City Centre
78 AC_BEU_CCMP_2_TM1_4 _FD.indd 78 20/07/12 12:04 PM 01 HARBOUR EDGE STITCH Uniting the Waterfront with the City Centre 01 VISION OUR 2032 VISION IS: Quay Street as a high-quality Harbour Edge space that
More informationDOVER WESTERN DOCKS REVIVAL (DWDR) NEWSLETTER. Spring 2016
DOVER WESTERN DOCKS REVIVAL (DWDR) NEWSLETTER Spring 2016 WELCOME The Port handles 13 million passengers, 2.5 million freight vehicles and up to 119 billion of UK/European trade. It supports 22,000 jobs,
More informationWharf Estates China Limited
32 The Wharf (Holdings) Limited Annual Report 2004 BUSINESS REVIEW CHINA WHARF CHINA LIMITED Wharf Estates China Limited Balance Sheet (Extract) as at December 31, 2004 HK$M Investment properties 4,605
More informationQueenstown residents aged 18-24, contact the Quest project at wandsworth.gov.uk or call / message
NEW JOBS & TRAINING The regeneration process is creating 22,000 construction jobs, including apprenticeships, traineeships, starter roles and graduate roles - Wandsworth residents get priority for many
More informationNEWLY REFURBISHED OFFICE SPACE
NEWLY REFURBISHED OFFICE SPACE CROYDON WILL BE HOME TO A NEW WESTFIELD SHOPPING CENTRE FROM 2020, PROVIDING 1.5M SQ FT OF NEW RETAIL AND LEISURE SPACE. CGI of Westfield, Croydon WELCOME KNOLLYS HOUSE HAS
More informationColindale Gardens Site Visit
Colindale Gardens Site Visit 04 April 2017 Agenda Introduction John Tutte Group Chief Executive Colindale Gardens Overview Mark Parker Managing Director Tour of marketing suite Site visit 2 Introduction
More informationLocate in Falkirk. A guide for retail businesses
Locate in Falkirk A guide for retail businesses Contents Introduction to Falkirk and the surrounding area Introduction to Falkirk and the surrounding area...3 Key Economic Growth Priorities...4 Transport
More informationBRENT CROSS THAMESLINK
INTRODUCTION The 4.5 billion Brent Cross Cricklewood development is Barnet Council s most significant growth and regeneration programme. It will create a new sustainable mixed use town centre for Barnet
More informationBUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018
BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO
More informationAberdeen Exhibition and Conference Centre
Aberdeen Exhibition and Conference Centre Aberdeen Exhibition and Conference Centre 2 Progress to date and future projects David Anderson Managing Director Aberdeen Exhibition and Conference Centre 3 Our
More informationISSUE 36 SEPTEMBER 2015 MOVING AHEAD CROSSRAIL PROJECT SEPTEMBER UPDATE WATCH! WATCH THE LATEST MOVING AHEAD VIDEO ON YOUTUBE.
ISSUE 36 SEPTEMBER 2015 MOVING AHEAD CROSSRAIL PROJECT SEPTEMBER UPDATE Andrew Wolstenholme CEO Crossrail Ltd CROSSRAIL PROGRAMME 67% 60% The programme to build the new railway for London and the South
More informationSky Temporary Car Park Transport Statement
001 Issue 26 August 2016 This report takes into account the particular instructions and requirements of our client. It is not intended for and should not be relied upon by any third party and no responsibility
More informationInvest NorthTyneside. Guide to Commercial Property
Invest NorthTyneside Guide to Commercial Property Cobalt Park Cobalt offers over 2 million sq ft of office space already built with potential for a further 250,000 sq ft which could be designed to meet
More informationA CENTRAL LONDON LANDMARK MIXED USE TOWER DEVELOPMENT SITE VAUXHALL LONDON SW8
A CENTRAL LONDON LANDMARK MIXED USE TOWER DEVELOPMENT SITE VAUXHALL LONDON SW8 EXECUTIVE SUMMARY Landmark consented (subject to execution of the S106 Agreement) residentially led mixed use tower development
More information4countries. We understand the fundamentals. A trusted partner. We have delivered million sqm. 1.8 million car spaces.
A trusted partner Multiplex is a trusted partner for all types of retail projects from Greenfield developments to refurbishments and vibrant mixed-use precincts, in both cities and regional locations.
More informationI Pinehurst & I I Pinehurst. Farnborough Business Park
I Pinehurst & I I Pinehurst Farnborough Business Park Pre-eminent Business Location / Farnborough Business Park THE PARK Farnborough Business Park Farnborough Business Park is an established mixed use
More informationThe Edinburgh 12. Monthly Bulletin May City of Edinburgh Council. Steve McGavin Head of Business Partnerships
The Edinburgh 12 Monthly Bulletin May 2015 City of Edinburgh Council Steve McGavin Head of Business Partnerships steve.mcgavin@edinburgh.gov.uk Also available to view online: http://www.investinedinburgh.com/the-edinburgh-12/.
More information2433 Dufferin Street Zoning By-law Amendment Application - Preliminary Report
STAFF REPORT ACTION REQUIRED 2433 Dufferin Street Zoning By-law Amendment Application - Preliminary Report Date: July 22, 2014 To: From: Wards: Reference Number: North York Community Council Director,
More informationClarington. Proud Home of Darlington Nuclear. Multi-Sector Based Community. Building our life Science Sector. Great Commercial Opportunity ttumi ilhf
Proud Home of Darlington Nuclear Multi-Sector Based Community Building our life Science Sector Great Commercial Opportunity ttumi ilhf Board of Trade and NUCLEAR SUPPLY CHAIN - OPPORTUNITIES IN CLARINGTON
More informationResponse to the London Heathrow Airport Expansion Public Consultation
Response to the London Heathrow Airport Expansion Public Consultation Summary This report sets out the response to the Heathrow Airport s consultation on airport expansion and airspace change. The consultation
More informationWELCOME. Members of the development team are on hand to answer questions and feedback forms are available for your comments.
WELCOME Thank you for attending our public consultation in respect of TJX Europe s proposed new landmark office building opposite Watford Junction Station. The purpose of the consultation is to present
More informationLISBON STREET, LEEDS LISBON STREET, LEEDS DEVELOPMENT OPPORTUNITY
LISBON STREET, LEEDS DEVELOPMENT OPPORTUNITY 01 A CLEARED SITE OFFERING A DEVELOPMENT OPPORTUNITY EXTENDING TO A TOTAL OF 1.12 HA (2.77 A). THE SITE HAS POTENTIAL TO ACCOMMODATE UPTO FIVE BUILDINGS ON
More informationBus Priority Package. Presentation to Leigh Business Forum. 11 December 2015
Bus Priority Package Presentation to Leigh Business Forum 11 December 2015 Over 25 miles of bus routes improved What is the bus priority package? Key Strategic Benefits Shorter journey times, more punctual
More informationSteve Winterflood. i54 - Manufacturing, Export Led, Major Investment outside of London
Steve Winterflood i54 - Manufacturing, Export Led, Major Investment outside of London Key topics for today; i54 Overview and Aims i54 History i54 Joint Venture i54 Contracts and works Overview and aims
More information