TNB Stage II Inter Connection and Transmission System Expansion Project No. 9. l&ll i Xi -it-ljtirn

Size: px
Start display at page:

Download "TNB Stage II Inter Connection and Transmission System Expansion Project No. 9. l&ll i Xi -it-ljtirn"

Transcription

1 Public Disclosure Authorized E-235 VOL. 22 D2 Public Disclosure Authorized TNB Stage II Inter Connection and Transmission System Expansion Project No. 9 Public Disclosure Authorized J2 VII Viil Uiiiii~i-UI H l&ll i Xi -it-ljtirn Construction and Maintenance of Transmission Lines EGAT - INVESTMENT PROGRAM SUPPORT PROJECT (WORLD BANK PARTIAL CREDIT GUARANTEE) Public Disclosure Authorized

2 TNB Stage II Inter Connection and Transmission System Expansion Project No. 9 Environmentai Guiueiines for irianni-ug, Construction and Maintenance of Transmission Lines

3 Contents TRANSMISSION SYSTEM EXPANSION PROJECT NO. 9 and EGAT-TNB STAGE II INTER CONNECTION ENVIRONMENTAL GUIDELINES FOR PLANNING, CONSTRUCTION AND MAINTENANCE OF TRANSMISSION LINES Executive Summary page i 1 Introduction 1 2 Project Description 3 3 Legal and Administrative 72 4 Route Selection Criteria and Mitigation Strategies 78 5 Environmental Issues 90 6 Mitigation Measures Monitoring 93

4 Executive Summary TNB Stage 11 Inter Connection and Transmission System Expansion Project No. 9 Environmental Guidelines for Planning, Construction and Maintenance of Transmission Lines Introduction 1. The Electricity Generating Authority of Thailand (EGAT) is a state enterprise under direct supervision of the Office of the Prime Minister. EGAT was established on May V to nationalize nd consolidate tha>e fulnctions and responsibili-es of three independent state enterprises: the Yanhee Electricity Authority (YEA), the Lignite Authority (LA) and the North-East Electricity Authority (NEEA). EGAT is now in the process of privatization. EGAT has the responsibility to provide electricity for the entire Kingdom of Thailand by generating, transmitting and selling bulk energy to two distributing entities, namely the Metropolitan Electricity Authority (MEA) and the Provincial Electricity Authority (PEA). 2. The current EGAT long term Power Development Plan (PDP 95-01) includes about 13,100 MW total power purchase from IPPs up to the year 2011, representing 30% of the total installed capacity at that time. To facilitate private sector investment in IPP projects, EGAT will construct Transmission System Expansion Project No. 9 and TNB Stage II Inter Connection.

5 Project Description 3. Transmission System Expansion Project No. 9 is also prepared in response to the Government's policy to continue the development of infrastructure to sustain the economic growth of the country. TS 9 is a package of 26 subprojects of transmission lines and substations expansion and reinforcement. The project involves the construction and reinforcement of transmission lines totalling 1,890.0 circuit-kilomreters, and 10 substations. The total amount of 5,900 MVA transformer capacity and 1,202.4 MVA reactive power compensation equipment installed at the existing substations are also included. 4. TNB stageil Interconnection consisits of two parts: the construction of HVDC transmission, and internal system reinforcement. Legal and Administrative 5. Environmental Impact Assessment (EIA) is not required under current Thailand law and regulation for the Transmission System Expansion Project No. 9 and TNB Stagell Inter Connection. The EIA for the transmission system will be expected only when all or a portion of the transmission line routes are located in Watershed classification class 1 B (or wildlife sanctuary area, or national park area, or mangrove area). The project routes do not traverse any of these. This report is a focused environmental analysis of environmental impacts of project components and their mitigation measures as required by the World Bank. Analysis of Alternatives 6. Power system studies were reviewd based on the latest EGAT and TNB Power Dhevelopment Planis (PDP) to firm up the 300 MW EGAT - TNB Stage II Interconnection.The studies have been carried out for three options: (1) Without EGAT - TNB Stage II Interconnection, (2) With EGAT - TNB HVAC Interconnection and (3) With EGAT -TNB Stage II Interconnection. The EGAT PDP, revised PDP ii

6 92-01, and 1991 load forecast together with the updated version of TNB' s PDP and load were adopted for the study. Route Selection Criteria and Mitigation Strateeies 7. In selection of routes for transmission lines and substation sites, EGAT uses design criteria to minimize environmental impacts on forest, wildlife, watershed areas, populations, archaeological sites and scenery. Transmission line right of ways are not to be located through: (a) restricted Class IA watershed area, according to laws and regulations; and, (b) holy places, archeological sites and government sites. Transmission line right of ways should also avoid: (a) watershed area class lb, Addiional forest conservation areas (Class C),mangrove forest, national parks and other conservation areas; (b) community and developed areas; (c) parallel with, or close to telephone and telegraph cables for a long distance to avoid 8. Detailed Route Surveys: Before construction of the transmission system, detailed route surveys will be performed by EGAT staff together with the Royal Forest Department (RFD). The number of forest trees to be cut will be documented. In addition, final route selection adjustments to avoid dwellings and circumvent other areas of potential negative impact will be made, according to EGAT's environmental design criteria. 9. Construction: EGAT's guidelines for construction activities are: (a) avoid installation of new access roads for construction purposes; try to utilize existing trails; (b) no cutting of trees over the limitations set by RFD; and, (c) clean up construction sites upon completion of construction work. 10. Maintenance of the Right of Way: Along the valleys, only trees considered to be hazardous to the stability of the transmission system would be cut down. Landowners are permitted to cultivate economic crops under EGAT's criteria along the right of way corridors. Upon completion of transmission line construction iii

7 work, ground cover around the towers will be planted and land contouring will be done as required to provide a protective covering for the earth and to prevent soil erosion. No herbicides are used in right of way maintenance. Environmental Issues: 11. Environmental Impact on Water Resources: Potential impacts of a transmission system on water quality are related to construction activities: surface run-off from construction sites; wastewater from the temporary office and construction camps; and, wastewater contaminated with oil or grease from machinery which will be mitigated. The construction sites, temporary office and construction camp will locate more than 100 meters far from water resource or stream and all of slope area is less than 45 degree. The construction will follow the EGAT'S Environmental Guidelines for Transmission System. 12. Forest resources: There are 25 sub projects, with a length of approximately kilometers, that pass through the reserve forest (non protected forest). There are no watershed area class IA and 1B, wildlife sanctuary, national park,mangrove forest area or addition forest conservation area (C) near any transmission line of subproject on Transmission System Expansion Project No. 9. TNB Stage II Inter Connection Project comprises 3 tranmission lines,a distance of approximately kilometers, that pass through the reserve forest. Many of these 'forest areas' have already been cleared for agriculture are other purposes. The attached route maps show the actual conditions found in walk-throughs. There is no watershed area class 1A and IB, wildlife sanctuary, national park,mangrove forest area or addition forest conservation area (C) near any transmission line of subprojects. 13. Wildlife: There are kilometers of Transmission System Expansion Project No. 9 and kilometers of TNB Stage ii inter Connection Project fhat pass through the reserve forest that are not significant for conservation. Many of the reserve forest areas where the transmission lines traverse have already been cleared iv

8 for agriculture and other purposes (see maps). The wildlife are mostly small in size and they can adjust well to minor change in the environment. 14. Land Use: The project construction phase will cause the loss and limitation of agricultural land use in the ROW; however, the impact is on a small total land area because most of the crops have a short growing season and they do not exceed the height restrictions for vegetation in the right of way. Transmission System Expansion Project No. 9 and TNB Stage II Inter Connection Project have tranmission lines which pass through the agricultural land totalling about 1, and km. The Maintenance of the right of way will follow the EGAT policy on post-project land use. 15. Cultural and Esthetic Resources: There were no cultural or esthetic resources that would potentially be impacted along the Transmission System Expansion Project MNr 0 nira 'T'NTf St-g YT T,,+_. T 'fl--2 No B nd Sa II +.ecucion I roject. 16. PCB Management: Transmission System Expansion Project No. 9 and TNB Stage II Inter Connection Project will not involve replacement of equipment potentially contaminated with PCB. EGAT has surveyed all potentially contaminated electrical equipment. 17. Electromagnetic Frequency (EMF): A full discussion of EMF effects and EGAT transmission lines is included in the Environmental Impact Analyses of the Greater Bangkok Area, and the Environmental Report for 500 KV Transmission Line for IPP's. Mitigation Measures: 18. Natural Resources: Foundation towers and construction activities including transportation of construction materials, material storage and worker housing would be located at least 50 meters away from surface water resources to avoid soil erosion. In case it is necessary to use areas closer to water resources, soil barriers would be v

9 built to block erosion and sedimentation. Vegetative cover would be replaced along streambanks and the surrounding project site if disturbed, to prevent soil erosion. In all areas, sanitary latrines will be constructed for workforce and temporary offices, and good housekeeping measures will minimize potential water contamination clue to construction. 19. Forest Resources: The following mitigation measures would be followed: (i) deforestation to be done only in the right of way ii) reforestation is the responsibility of EGAT, the area of reforestation would be more than the area of national forest reserve used for the ROW; iii) in case private land is used in construction, it is the responsibility of EGAT to contact the owner and pay fair compensation. Many of the 'forest areas' along the routes have already been cleared for agriculture and other purposes (see map section). 20. Wildlife: The impacts can be controlled by: i) deforestation only in the right of way area; ii) prohibition on disturbing wildlife, including nests, eggs, holes, hollows and other habitat; iii) prevention of noise pollution by limiting work hours between 8.00 am and pm., all work to be forbidden at night. 21. Land Use: EGAT would plan all the project activities including material transportation, pole mounting and others in the dry season, because most of the crops would already have been harvested. Removal of agricultural plants (particularly perennials) would be done only as necessary and compensation paid. Farmers would be allowed to grow short-lived crops with heights in the ROW under EGAT's Criteria after construction. Monitoring 22. The following monitoiirig plan will be adopted to track the effectiveness of mitigation techniques, and to address recognized problems in an appropriate and timely manner. This regular scheduled monitoring program will consist chiefly of visual inspections during construction and operation for: vi

10 o erosion along access roads, substation and transmission tower foundations; o encroachment of settlements within rights of ways, encroachment of settlements within protected areas via transmission line access roads, exploitation of forest resources in protected areas via access roads; o vegetation clearances below transmission lines, and invasion of exotic species along right of ways; o transformer fluid leakage and spills. vii

11 TNB Stage II Inter Connection and Transmission System Expansion Project No. 9 Environmental Guidelines for Planning, Construction and Maintenance of Transmission Lines 1. Introduction The Electricity Generating Authority of Thailand (EGAT) is a state enterprise under direct supervision of the Office of the Prime Minister. EGAT was established on May 1, 1969 to nationalize and consolidate the functions and responsibilities of three independent state enterprises: the Yanhee Electricity Authority (YEA), the Lignite Authority (LA) and the North-East Electricity Authority (NEEA). EGAT is now in the process of privatization. EGAT has the responsibility to provide electricity for the entire Kingdom of Thailand by generating, transmitting and selling bulk energy to two distributing entities, namely the Metropolitan Electricity Authority (MEA) and the Provincial Electricity Authority (PEA). It is certainly realized that the electric power, a source of energy, is an infrastructure in strengthening the economic and social development of a country. To provide the adequate and reliable supply of electricity is the predominant responsibility of EGAT. Following the recovery from economic recession period in 1987, the electricity consumption in Thailand has been increasing at the extremely high rate. The growth rates of peak generation requirement were recorded at two digits, and expected to further increase at high levels (10.09 % for the 7th NESDP and 7.90 % for the 8th NESDP). In line with the electricity requirement of the country, EGAT's Power Development Plan (PDP) has been prepared and periodically revised. The PDP always includes the investments for expansions of transmission system as well as the power generation facilities, since the electricity once generated must be transmitted and distributed to consumers. The transmission system expansion program involves the constructions of 1

12 transmission lines and substations for reinforcement of the electric power system to keep abreast of the load growth and to expand the electricity services to remote areas. Several Transmission System Expansion Projects (TS Projects) have been included in the PDPs and implemented in successive stages. So far, eight transmission system expansion projects, namely Transmission System Expansion Projects No.1 to Transmission System Expansion Projects No.8 have been formulated. In addition to the normal transmission system expansion projects, several accelerated transmission projects have also been formulated to increase the power transfer capability of the interconnection between regions and to supply power for large industrial loads and the unexpected fast increase in power demand. Transmission System Expansion Projects No.9 (TS.9 project) has been listed as one of the transmission system expansion projects in the Seventh National Economic and Social Development Plan (the 7th NESDP). In the 7th NESDP, the Government has set the policy guidelines to improve the power system reliability. One of the policy guidelines is to improve transmission and distribution systems for more sufficient, reliable, high quality, and safety of supply, especially for industrial and new economic development areas; and to reinforce the power system interconnection with neighbouring countries to provide more energy interchange capability for the economic and system reliability. The TS.9 Project is planned for implementation during TNB Stage II Inter Connection is the power system interconnection between EGAT and TNB (Tenaga Nasional Berhad) of Malaysia was first energized on February 1, The interconnection consists of a 24.5 km single circuit 132 KV 240 mm 2 ACSR transmission line linking Sadao substation of EGAT and chuping Substation of TNB; and two 115/132 KV transformers, rated 66.7 MVA each. The existing EGAT-TNB interconnection are initially proposed for regular peak power exchange, but operation of the systems indicated oscillatory damping and power swing problems as the size of the interconnection is too small in relation to the size of the two systems.

13 The present power system is operated in such a way that parts of southern portion of EGAT system or parts of northern region system of TNB will have to be disconnected with the rest of its main grid and synchronized with the other system whenever the power exchange is required. As the two systems cannot be fully synchronized, thus restricts its utilization, EGAT and TNB therefore agreed to individually conduct the preliminary studies to strengthen the interconnection and the possibility of upgrading the interconnection to gain the full benefits of the interconnection. Since 1986, several meeting between EGAT's and TNB's system planning staff have been held both in Thailand and Malaysia to review results of the preliminary studies and pursued the joint study on the Stage II EGAT-TNB Interconnection Project aiming at the maximum power exchange of 300 MW. 2. Project description The land use classification are shown in the maps attacked to the project description. There are two basic land use in the transmission line project areas: agricultural land and reserve forest. The reserve forest areas have been broken down into areas for which land use permits have been obtained, and areas for which land use permits are pending. As can be seen in the map, the majority of the routes traverse agricultural area. These area are typically para rubber or rice. The reserve forest areas are usually degraded forest (or converted to rubber plantation), as oppossed to protected forest. There are no protected forest area involved in the project no. 9 or TNB. The reserved forest areas through which the TNB project passes are almost exclusively converted to rubber plantation. Only 10 % of the TNB project passes through reserve forest areas.. ~3

14 2.1 TNB Stage II Inter Connection The EGAT-TNB stage II Interconnection consisits of two parts: the construction of HVDC transmission, and the internal system reinforcement. 1. The HVDC transmission comprises: (a) Due to the limited area of Hat Yai 2 substation, a new site is proposed at Khlong Ngae for the installation of HVDC converter. The HVDC converter will be 250 KV 300 MW monopolar and upgradable at a later stage to bipolar for 600 MW. (b) Construction of a 250 KV HVDC bipolar line from Khlong Ngae converter station to the Thailand-Malaysia border, using 2x400 mm 2 conductors per pole (pole 2 conductor will be used as metallic return for the initial stage monopolar), a distance of approximately 24 km. (c) Installation of communication system. 2. The internal network reinforcement comprises: (a) Construction of HVAC 230 KV Switchyard at Khlong Ngae to link the HVDC converter station via two converter transformers with the 230 KV HVAC four lines, two lines from Hat Yai 2 substation and two lines from Thung Song Substation. (b) Construction of a double circuit 230 KV Hat Yai 2-Khlong Ngae linw, using 2 x1272 MCM ACSR conductor per phase, a distance of approximately 30 KM. (c) Construction of a double circuit 230 KV Thung Song-Khlong Ngae lin, using 2 x1272 MCM ACSR conductor per phase, a distance of approximately 210 KM. Nage converter station. Ngae converter station (d) Expansion of 230 KV Hat Yai 2 Substation for two outgoing lines to Khlong (e) Expansion of 230 KV Thung Song Substation for two outgoing lines to Khlong (f) Addition of communication system. 4

15 4 ' ' l ll:.abottloslsusl~~~~~~~~~~~~~~~~~~~~fllll;\. 'n,<.'.:,.'>''-: :'':''';'.'. :'.: '' :' ";,:.;,.;.,':--''.c :,- v~~~~~~~~~~~~~~~~~~~~~~~~7... ',,.. ;... ::.--!-...8.'>''. ',. -:,' v.-.1!.:. 4'W :-. ;.^=-i ': ^.!-! 'At;( r;si,...,... s,... j, ;...!,;+,., X, :.... T- X '.,. '.,,,.,. t AW ::'trd'sl,-ertix I ',~~~~~~~~~~~~~~~~~~~~~~~~. FffX~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ l < ' ;i '-'''} '\t;, J '+' '.'--!;1 ' EEREFRSTAES(PRI ENIG i.s::,-x wi<'jg;ll,,,.,7_ :!' ~~~~~~AGRCTR RA tt! j;i';,-; ts{.'x> TOO.D9 tl Z~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~ :,.. t.,t ', ',jlo.ovre TTDI /' * odv!jo rk' -: _~~~~~~~~~~~~... V _,~~ ~~~~~~~...._ Figure ronsmision Lne Roue For GAT-TtB Sto3_ Inte... IT... r.recton Proec' r

16 TNB Stage II Inter Connection Name of Transmission Lines Lenght Reserved Forest Passed Agriculture Land KV Klong Ngae-Thung Song KV Had Yai 2- Klong Ngae KV Klong Ngae - Borded (Thai-Malasia) KV Krabi-Thung Song KV Border (Namn Province) -Mae Moh

17 2.2 Transmission System Expansion Project No.9 TS.9 project is also prepared in response to the Government's policy to continue the development of infrastructure to sustain the economic growth of the country. The objectives of the TS.9 project are therefore: (i) (ii) (iii) to provide sufficient power for future demand; to improve reliability of power supply particular in new industrial and commercial areas; to support the distribution system expansion to various remote areas. The TS.9 project is a package of 25 subprojects of transmission lines and substations expansion and reinforcement. The project involves the construction and reinforcement of transmission lines totalling 1,890.0 circuit-kilometers, and 10 substations. The total amount of 5,900 MVA transformer capacity and 1,202.4 MVA reactive power compensation equipment installed at the. ~7

18 TRANMISSION SYSTEM EXPANSION PROJECT NO. 9 No. Name of Transmission Lines Lenght Reserved Forest Passed Private Land Passed Remarks Km. Km. Km /115 KV BAN PONG 2 - BAN PONG I - NAKHON CHAISRI old ROW - SAM PHRAN 2 LINES KV BOR WIN - BAN BUNG LINE KV THATAGO - THA WUNG LINE KV THA]LAN 3 - SARABURI I LINE old ROW KV THALAN 1 - THALAN 3 LINE KV RATCHABURI 2 - PHETCHABURI LINE KV PRACHIN BURI 2 - WATTHANA NAKHON LINE KV MUKDAHAN - THAT PHANOM LINE KV THAT PHANOM - NAKHON PHANOM LINES KV UDON THANI 2 - NONG BUA LAM PHU LINE KV ROI ET - PHAYAKKHAPHUM PHISAI LINE KV PHAYAKKHAPHUM PHISAI - SURIN LINE KV CHAIYAPHUM - BAMNET NARONG LINE KV UBON RATCHATHANI 2 - KANTHARALAK LINE KV SURIN - SANGKHA LINE KV THUNG SONG - NAKHON SI THAMMARAT LINE old ROW KV SURAT THANI - THUNG SONG LINE old ROW KV KHLONG NGAE - YALA LINE old ROW KV PHlANGNGA - PHUKET JUNCTION - PHUKET 2 LINE old ROW KV YALA - NARATHIWAT LINE KV SURAT THANI - BAN DON LINE KV LAN KRABU - KAMPHAENGPHET LINE KV MAE MOH 3 - LAMPANG 2 LINE KV CHIANG MAI 2 - MAE TAENG LINE AND SUBSTATIONS KV RATCHABURI 2 - PRACHAUB KHIRIKHUN LINE II I old ROW

19 SUBPROJECT NO.1 230/115 KV BAN PONG 2- BAN PONG 1- NAKHON CHAISRI -SAM PHRAN 2 LINE A. Objective Objective of Subproject No.1, the 230/115 kv Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi - Sam Phran 2 lines and substations, is to provide sufficient and reliable power supply for the increasing demand of industrial plants in the western area. B. Proiect Scope and Description Project Scove The scope for the 230/115 kv Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi -Sam Phran 2 lines and substations consists of the following constructions: a) Construction of 115 kv temporary detour lines on the existing rights-of-way from Ban Pong 1 to Nakhon Chaisi and from Nakhon Chaisi to Sam Phran 2, using 1272 MCM ACSR conductor, and dismantling the existing 115 kv Ban Pong 2 - Ban Pong 1 Line No.2 (200 sq.mm TACSR/AW conductor) and the existing 115 kv Ban Pong 1 - Nakhon Chaisi - Sam Phran 2 single circuit line. b) Construction of 230 kv double circuit Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi - Sam Phran 2 transmission line, double circuit steel towers, using 2x1272 MCM ACSR conductor per phase, a distance of approximately 43 km. The new 230 kv line designed with differential insulation, will be constructed on the existing right-of-way of the dismantled 115 kv single circuit Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi - Sam Phran 2 line. The new 230 kv lines will be initially energized at 115 kv and one circuit will be temporary terminated at 115 kv Ban Pong 1 Substation and both circuit will be terminated at 115 kv Nakhon Chaisi Substation. 9

20 c) Expansion of 115 kv Ban Pong 2 Substation for one additional line. d) Expansion of 115 kv Nakhon Chaisi Substation for two additional lines. e) Expansion of 115 kv Sam Phran 2 Substation for one additional line. f) Land procurement for the extension of Nakhon Chaisi Substation for future 230 kv switchyard. However, if the adjoining piece of land would not be available, the new site of 230 kv switchyard, called Nakhon Chaisi 2, would be considered, and the four-circuit transmission line for double circuit 230 kv line and double circuit 115 kv line on the same tower would be constructed to link the new 230 kv Nakhon Chaisi 2 Substation to the existing 115 kv substation. g) Addition of communication system. Project Description At present, the transmission system which supply power demand in the western area consists of a 115 kv loop among three major 230 kv substations, via 230/115 kv tie transformers at Sam Phran 1, Ban Pong 2 and Ratchaburi 2 Substations. The demand in this area has been increasing rapidly due to the industrial development. Part of 115 kv line sections have been reinforced under ATP and TS.8 projects to maintain the power supply reliability. The reconstruction of 115 kv Sam Phran 1 - Sam Phran 2 line from single circuit to double circuit, using 2x795 MCM ACSR conductor per phase, is being implemented under TS.8 project and expected to be commissioned by the end of The combined peak power demand at Ban Pong 1, Nakhon Chaisi, and Sam Phran 2 Substation was MW in 1993 which caused heavy line loading on 115 kvlines from Ban Pong 2 to Sam Phran 1 Substations and it is anticipated that the line loading will reach the transmission line capacity limit in near future. Since, most of the power demand in this area is industrial load, therefore, high reliability of power supply is very important. The

21 transmission system reinforcement to cope with the increasing demand is therefore required. Due to the difficulty to obtain a new right-of-way in these areas, the construction of a 230 kv double circuit Ban Pong 2 - Ban Pong 1 - Nakhon Chaisi - Sam Phran 2 line on the existing rights-of-way and initially energized at 115 kv is proposed in view of long-term planning consideration. The differential insulation should also be considered in the design of the double circuit structure to reduce the probability of simultaneously trip of both circuits due to lightning stroke. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is December ~ i2i.

22 s~~~ A 7 7* Ljl.20VTO 3RIflAGARINOD ~IIiK 6K!mN AEH' TOn s-3k 3.nRNOa, L 1'~~~~~~~~~' ~~~~~~~\ ~ ~ ~ ~ ~ K--Ph il.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ 1,4 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~~~~~1 11 CI..I S. - fld4uji 1 ' qy 0 Zql A KV 1~~~~~~~~~U4~~TArI0bN I SUBPROJECT NO /115KV BAN PONG 2~~~-BNPNG-NAONCASI-AMPRN2IE

23 SUBPROJECT NO KV BOR WIN - BAN BUNG LINE A. Objective Objectives of Subproject No.2, 115 kv Bo Win - Ban Bung line and substations, are to provide sufficient power supply for future demand and industrial loads and to improve reliability of power supply in the Ban Bung area. B. Project Scope and Description Proiect Scope The scope for the 115 kv Bo Win - Ban Bung line and substations consists of the following constructions: a) Construction of 115 kv double circuit Bo Win - Ban Bung line, double circuit steel towers, using 2x795 MCM ACSR conductor, a distance of approximately 27 km. b) Expansion of 115 kv Bo Win Substation for two outgoing lines. c) Expansion of 115 kv Ban Bung Substation for two incoming lines. d) Addition of communication system. Project Description The existing 115 kv Ban Bung Substation is connected with the 115 kv Si Racha Substation via a 115 kv single circuit line, 33.2 km, using 477 MCM ACSR conductor. The present peak demand at Ban Bung Substation is 49.6 MW and is expected to increase at high growth rate due to the industrial developments in this area. Ban Bung is located in the 13

24 area which is classified by The Board of Investment (BOI) as the Investment Promotion Zone 2 which has more privilege than Zone 1 where the Government has recently issued the policy to limit the industrial developments in Zone 1, and also the policy to move out some existing industries from the area of Zone 1. The area around Ban Bung is considered one of the suitable locations to accommodate the industries and industrial estates. The new transmission lines is therefore required to improve the reliability of power supply. The construction of a 115 kv double circuit Bo Win - Ban Bung line is proposed. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is September

25 110 M A ) Tr_ U-1 Y Z'J_l Z I--i Z 4-11!5 0 T' 0 31 RACtiA IQ Y- rh V /j_j Ji L.,I di _b A-jv IJ N V' LI 7 77 M,; t V-1 N _2 V--- Jr V zrl r sc - fto La L AGRICUTUREAREA N w N_Y, 1 4 slo xv lum a, I nall z3o- II15 I T: 4r `T( R SUBPROJECT NO KV BOR WIN - BAN BUNG LINE

26 SITBPROJECT NO KV THA WUNG SUBSTATION AND LINE (115 KV THATAGO - THA WUNG LINE) A. Objective Objectives of Subproject No.3, 115 kv Tha Wung substation and lines termination, are to increase power supply capability to meet the increasing demand at Sing Buri and Lop Buri 1 Substations, to improve system reliability, and also to reduce transmission system losses. B. Project Scope and Description Project Scope The scope for the 115 kv Tha Wung Substation and lines termination consists of the following constructions: a) Construction of new 115 kv Tha Wung Substation together with the termination of 115 kv double circuit Ang Thong 2 - Lop Buri 2 line and 115 kv single circuit Sing Buri - Lop Buri 1 line at Tha Wung Substation. The power supply for station service will be received from PEA distribution line or a small transformer relocated from the existing system. b) Land Procurement for the 115 kv Tha Wung Substation with provision for future 230 kv switchyard. c) Addition of communication system. 16

27 Project Description At present, the existing 115 kv Sing Buri Substation is connected with the 115 kv system via a single circuit line with conductor size of 477 MCM ACSR, a distance of 28 km from Takhli 2 Substation; and a single circuit line with small conductor size of 4/0 ACSR, a distance of 33 km from 115 kv Ang Thong 1 Substation. The 115 kv line is also extended from Sing Buri Substation with a single circuit using small conductor size of 4/0 AWG ACSR to supply power radially to Lop Buri 1 Substation. The existing 115 kv lines will not be sufficient to provide reliable power supply to the total power demand at Sing Buri 1 and Lop Buri 1 in To cope with the increasing demand, the system reinforcement in this area is necessary. According to the present transmission network configuration, there is a line crossing between the double circuit 115 kv Ang Thong 2 -Lop Buri 2 line and the 115 kv Sing Buri - Lop Buri 1 line at Tha Wung district, therefore the construction of a new substation at Tha Wung with the termination of 115 kv Ang Thong 2 - Lop Buri 2 line and 115 kv Sing Buri -Lop Buri 1 line at Tha Wung Substation is proposed. This substation will improve the system reliability of power supply at Sing Buri and Lop Buri 1 Substations. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is December

28 a 4-11!SKV TO TAKtiLl 2 K. V, TOCHAIBADAH t,, OAXHON S Ji-j1ymA-j'?-3qM-MTU_1% 0.qI O,A;,o A -4 J A il 7 n pkjo (1- W 0 lu e gang Tj M 'Al Mu' iu Do. f Nu- 4.n 00,, D Pk. f-*,,, va, L bc J., A n-i j Kqai ira'p LVI ab. I, CO A p B wj) -,;v t t, PIIR W Ampltc,IL S6warn ACRICUTURE % IT', wl A I 7--- Amph6e Phc A "A 1131(v SU63TATMM 130.V 2USITAT143N A PI)i o 1&69 D6n S- 0 C, bon.1-thang Y., 4n an 0,1 5;se 500KVT0fjotj,3CHOK 4j I I TRA"3.1331om Lifft :11 2, Kv I a -ti 1- B IK IANG OfW 1 SUBPROJECT NO. 3, 115 KV THATAGO - TIJA WUNG LINE

29 SUIBPROJECT NO KV TIHA LAN - SARA BURI LINE A. Objective Objective of Subproject No.4, 5, 115 kv Thalan - Saraburi line and substations, is to improve reliability of power supply for Saraburi Province. B. Proiect Scope and Description Project Scope The scope for the 115 kv Thalan 3 - Saraburi 1 line and substations consists of the following constructions: a) Construction of 115 kv temporary detour single circuit line from Thalan Junction (near Thalan 3 Substation) on the existing right-of-way to Saraburi 1 Substation, using 477 MCM ACSR conductor stringing on concrete pole for a distance of approximately 13 km. b) Dismantling the existing 115 kv line section from Saraburi 1 Substation to Thalan Junction and reconnecting this temporary detour line with the remaining 115 kv line section from Thalan Junction to Thalan 1 Substation. c) Construction of 115 kv double circuit Thalan 3 - Saraburi 1 line, double circuit steel towers, using 795 MCM ACSR conductor for a distance of approximately 15 km. The new transmission line section from Thalan Junction to Saraburi 1 will be constructed on the existing right-of-way. The Thalan Junction to Thalan 3 will require a new right-of-way. d) Construction of 115 kv Thalan 3 - Thalan Junction - Thalan 1 line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, for a distance of 5 km. The new line section between Thalan Junction and Thalan 1 Substation will be constructed on the right-of-way of the existing 115 kv line to Thalan 1 which will be dismantled. This line section will form a new 115 kv Thalan 1 - Thalan 3 line.. <- 49

30 e) Expansion of 115 kv Thalan 3 Substation for three outgoing lines. f) Expansion of kv Saraburi i Substation for one additional incoming line. g) Addition of communication system. Project Description The power demand in Saraburi Province is mainly supplied from Saraburi 1 Substation which is connected with Thalan 1 Substation via a 115 kv single circuit line. The present peak demand is 44.4 MW and expected to increase at 10 % annually. Since there is only one circuit that supplies power to Saraburi 1 Substation, additional transmission circuit is required to improve reliability of supply. The construction of a new 115 kv double circuit Thalan 3 - Saraburi 1 is therefore proposed. To avoid the problems on right-of-way acquisition, the right-of-way of the existing 115 kv line from Thalan 3 Junction, about 2 km south of Thalan 3 Substation (See Figure 4.4), to Saraburi 1 substation will be used for the construction of the new transmission line. To maintain power supply to Saraburi 1 Substation during the deenergization of the existing line, construction of a temporary 115 kv detour line from Thalan 3 Junction to Saraburi 1 Substation is required. To utilize the existing ritght-of-way of 115 kv line section from Thalan 3 Junction to Thalan 1, the construction of 115 kv Thalan 1 - Thalan Junction - Thalan 3 line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, is also recommended. This line will increase power transfer capability between Thalan 1 and Thalan 3 Substation. Figure of the proposed line route ofthe Subproject is shown in appendix C. Project Implementation The proposed commissioning dates is July

31 -,4-230KV TO TliA ifi!. 4_'3'OKVTO 4A, a u... %V., p IL Z7 1,14. U7 k (SULisi R_ L t STAT,;" TIIALAN -4, % UNCTION XIII) vi, IW4 r 7 b4b,", -r7, A& V NJ J1 qf... : J1461J., ia L2 Vvf, Pt,/ it, x:. 7' tls-j C, SU....14t' vu Nl UV:- 7t. z l(v AGRICUTUREAREAS SUBPROJECT NO KV TIIALAN 3 - SARABURI I LINE

32 SlJBPROJECT NO KV RATCHABURI - PHETCHABURI LINE A. Objective Objectives of Subproject No.6, 115 kv Ratchaburi 2 - Phetchaburi line and substations, are to maintain reliability of power supply at Phetchaburi Substation, and also to reduce system losses. B. Project Scope and Description Project Scone l-he scope for the 115 kv Ratchaburi 2 - Phetchaburi line and substations consists of the following constructions: a) Construction of 115 kv double circuit Ratchaburi 2 - Phetchaburi transmission line, using 2x795 MCM ACSR conductor/per phase, a distance of 53.1 km, on the right-of-wayof the existing 115 kv single circuit line which will be dismantled. b) Expansion of 115 kv Ratchaburi 2 Substation for one additional outgoing line. c) Expansion of 115 kv Phetchaburi Substation for one additional incoming line. d) Addition of communication system. C' ' )

33 Project Description 1Tne transmission network which supplies power in the areas of Ratchaburi 2, Phetchaburi, Cha-Am and Hua Hin Substations is a loop tied between the two 230/115 kv Ratchaburi 2 and Hua Hin (under construction) terminal substations via a double circuit 230 kv line and a single circuit 115 kv line from Hua Hin to Ratchaburi 2 via Cha-Am and Phetchaburi Substations. Since the only one circuit of the 230 kv line from Ratchaburi 2 was planned to be terminated at Hua Hin Substation; therefore, with the new projected increasing demand, there will be overloaded problem in the 115 kv line when the 230 kv Ratchaburi 2 - Hua Hin line tripping out. The reinforcement of the 115 kv line sections between Ratchaburi 2 and Hua Hin Substations is necessary, and the construction of a new double circuit 115 kv Ratchaburi 2- Phetchaburi line is proposed. Due to the difficulty of obtaining a new right-of-way in this area, the existing right-of-way will be used for the construction of the new transmission line. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is February

34 . _ I,: - j, 2oKV To BAN PONtG 2M 4-I5KVtO BAN PONO I 3'-..:7- -r I.- -\V ~~~~~~~~-.-.~ SUBPROJECT 6.~ 115 NO. RATCHABURI ' ' - AHTCH ABURI 11. ~~~~~~~~N ''S, ' _ rk.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~m, 07-4~. -!- -. RATC-ABURI# cc ' A '-.~~~ 4, J 'ia7i 51.a SUBPROJECT 115 K~~~' NO. RATCHABURI PHPETTHABURIRLINE

35 SUJBPROJECT NO KV PRACHIN BURI 2 - WATTHANA NAKHON LINE A. Objective Objectives of Subproject No.7, 115 kv Prachin Buri 2- Watthana Nakhon line and substations, are to provide sufficient and reliable power supply for future demand at Watthana Nakhon Substation, and to reduce system losses. B. Project Scope and Description Project Scope The scope for the 115 kv Prachin Buri 2 - Watthana Nakhon line and substations consists of the following constructions: a) Construction of 115 kv Prachin Buri 2 - Watthana Nakhon line, single circuit on double circuit steel towers, using 2x795 MCM ACSR conductor per phase, a distance of approximately 67 km. b) Expansion of 115 kv Prachin Buri 2 Substation for one additional outgoing line to Watthana Nakhon Substation. c) Expansion of 115 kv Watthana Nakhon Substation for one additional incoming line from Prachin Buri 2 Substation. d) Addition of communication system.

36 Project Description Tne existing 115 k-v Watthana Nakhon Substation is radiaiiy connected with the 115 kv Prachin Buri 1 Substation via a single circuit line. Under TS.8 Project, the termination of 115 kv Prachin Buri 1 - Watthana Nakhon line at the new 230/115 kv Prachin Buri 2 terminal substation will be completed in Voltage regulation at Watthana Nakhon Substation will be improved by receiving power from Prachin Buri 2 Substation. However, the improvement of reliability of power supply is still needed, since Prachin Buri and Sra Kaew provinces is also considered the suitable sites for the industrial estates to accommodate the new industries and the industries which would be moved out from BOI's Investment Promotion Zone 1. The construction of a new 115 kv line, single circuit on double circuit, is therefore proposed. Figure of the proposed line route of the Subproject is shown in appendix C. Proiect Implementation The proposed commissioning date is July S 2S

37 -'*~~~~~~~~~~~~~~~~~~~~~~~~A I ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~1 SU iorj MNA 11.. ". s I*-p1 L~ ~~ ~~ I of.~ctu C ~ ~ i ~ - s ~ ~ j ~ ~. V -k --.~, " IST UTIT TIO J ~ ~~RSRE OETAREAS (PERMIT PENDING) A SUBPROJECT NO KV PRACHIN BURI 2 - WATTHANA NAKHION LINE

38 SUBPROJECT NO.8, 9 230/115 KV MUKDAHAN 2 SUBSTATION AND 115 KV MUKDAHAN 2 - THAT PHANOM - NAKHON PHANOM LINES A. Objective Objectives of Subproject No.8, 9, 230/115 kv Mukdahan 2 Substation and 115 kv Mukdahan 2 - That Phanom - Nakhon Phanom lines and substations are to improve reliability and quality of power supply, to increase the power supply capability to Mukdahan and Nakhon Phanom Provinces and to reduce system losses. B. Project Scope and Description Project Scope The scope for the 230/115 kv Mukdahan 2 Substation and 115 kv Mukdahan 2 - That Phanom - Nakhon Phanom lines and substations consists of the following constructions: a) Construction of new 230/115 kv Mukdahan 2 Substation to accommodate two 3- phase 230/ kv tie transformers, rated OA/FA/FOA 120/160/200 MVA, together with 230 kv bays for the termination of one circuuit of 230 kv Savannakhet -Roi Et line (constructed under Nam Theun 2 hydroelectric project in Lao PDR), including 115 kv bays for connection to the existing 115 kv Mukdahan 1 Savannakhet and That Phanom Substations. b) Construction of 115 kv Mukdahan 2 - That Phanom line, double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 36 km. c) Construction of 115 kv That Phanom - Nakhon Phanom line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 59 km.

39 d) Upgrading the existing 69 kv That Phanom Substation from 69 kv to 115 kv substation. Two 3-phase, power transformers, each rated OA/FA/FOA, 15/20/25 iviva (using spare transformer from the system) will be instailed with three ii5 KV iine bays provided for 115 kv lines from Mukdahan 2 and one 115 kv line to Nakhon Phanom Substation. e) Upgrading the existing Nakhon Phanom Substation from 69 kv to 115 kv Substation. Two 3-phase, power transformers, each rated OA/FA/FOA, 15/20/25 MVA (using spare transformers from the system) will be installed with one 115 kv bay provided for the line from That Phanom Substation. f) Expansion of the 115 kv Mukdahan 1 Substation for one line from the Mukdahan 2 Substation. g) Addition of communication system. h) Land Procurement for the 230 kv Mukdahan 2 Substation and for the expansion of 115 kv That Phanom Substation. Proiect Description At present, the power demand in Mukdahan Province is supplied from 115 kv Mukdahan Substation which connected with Amnat Charoen Substation by a single circuit line. Due to the long transmission line and the small conductor size, the unacceptable low voltage is encountered at Mukdahan Substation. Therefore, the transmission system reinforcement is required. The present demand at Nakhon Phanom and That Phanom Substations was and MW respectively. Both are the end-substations; for which Nakhon Phanom Substation is connected with the 115/69 kv Sakon Nakhon Substation by the 69 kv Sa-kon Nalchon - Nakhon Phanom single circuit line with small conductor size of 95 sq.mm., for a distance of 89 km; and That Phanom Substation is connected with the 115/69 kv Sakon Nakhon

40 Substation by the 69 kv Sakon Nakhon - That Phanom line with small conductor size of 58 sq.mm., for a distance of 70 km. Due to the increasing demand, the poor voltage regulation has been facing at both substations, therefore to improve the voltage regulation and to increase the reliable power supply capability to Mukdahan and Nakhon Phanom Provinces, the construction of a new 230/115 kv Mukdahan 2 Substation and construction of the 115 kv Mukdahan 2 - That Phanom - Nakhon Phanom lines are proposed. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is August

41 X.,- ;--- '-Snh%L. -=_c. SUBS-TATION --- I- V O ~ ~ '.;.--<-..'A.. -- '----'c--a < _ \, \,, ;;, ~~HAIGW~44< w x ; > 1 S - - -I', " s _' esv s- CD -ON ZM~~~~~~ 7.~. Cto 'Xt,O ze "! sue Id KDHA A - *O. IIL -i -- AGRIC-, sttussstresrefet AREAS (EMTPNIG SUBPROJECT NO hv MUhDAHAN - THAT PHANOMI LINE SUBPROJECT NO KY- THAT PHANOMl - NAKHION PHANOMl LINES

42 SUBPROJECT NO KV UDON THANI 2 - NONG BUA LAM PH11U LINE A. Objective Objective of Subproject No.10, 115 kv Udon Thani 2 - Nong Bua Lam Phu line and substations, is to improve reliability of power supply for Nong Bua Lam Phu and Loei Provinces. B. Project Scope and Description Project Scope The scope for the 115 kv Udon Thani 2 - Nong Bua Lam Phu line and substations consists of the following constructions: a) Construction of 115 kv Udon Thani 2 - Nong Bua Lam Phu line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 61 km. b) Expansion of 115 kv Udon Thani 2 Substation for one outgoing line. c) Expansion of 115 kv Nong Bua Lam Phu Substation for one incoming line. d) Addition of communication system. Project Description At present, the power demand in Nong Bua Lam Phu Province is supplied from Udon Thani 1, Udon Thani 2 and Loei substations via PEA 22 kv distribution lines. The Nong Bua Lam Phu Substation is being constructed under TS.8 Project by terminating the existing 115 kv single circuit Udon Thani 1 - Loei line. The new 115 kv Nong Bua Lam Phu Substation, which will be completed by the end of 1995, will increase the power supply v.c) P..l'_

43 capability with better quality at an acceptable reliable services to the Nong Bua LTam Phu Province and its vicinity. However, the power supply for Nong Bua Lam Phu and Loei provinces is still supplied by a 115 kiv singie circuit line from Udon Thani 1 Substation. Therefore, to cope with the future high peak demand, the improvement of reliability of power supply is required to prevent the possibility of total blackout in these two provinces. The construction of a new 115 kv Udon Thani 2 - Nong Bua Lam Phu line is proposed. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning dates is August 1998.

44 lj~~~. ~ ~ ~~~i ' ~ * sub~~~statioij. - ~~~~~ ~ ~ h YIr in liiflth~~~1?~l, / )/ 1 A 3 - K.t 1b1 q g 3ufl ~ ~ I og~i~/ dl. SUOSTATICt (\I IuKP ij mb C.J ~1 T. -- ONGBPRUJLAT NOPII 1KVUO HN 2 OGBALAIPULN

45 SUBPROJECT NO.11, KV ROI ET - PHAYAKKHAPHUM PHI SAI - SURIN LINE A. Objective Objective of Subproject No.12, 115 kv Roi Et - Phayakkhaphum Phisai -Surin lines and substations, is to improve reliability of power supply at Phayakkhaphum Phisai and Surin Substations. B. Project Scope and Description Project Scope The scope for the 115 kv Roi Et - Phayakkhaphum Phisai - Surin lines and substations consists of the following constructions: a) Stringing the second circuit on the double circuit towers of the 115 kv Roi Et - Phayakkhaphum Phisai line (under construction in TS.8 Project for commissioning by the end of 1996), using 795 MCM ACSR conductor, a distance of approximately 84 km. b) Construction of 115 kv Phayakkhaphum Phisai - Surin line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 80 km. c) Expansion of 115 kv Roi Et Substation for one outgoing line. d) Expansion of 115 kv Phayakkhaphum Phisai Substation for two lines. e) Expansion of 115 kv Surin Substation for one line. f) Addition of communication system. k 4 nr~ f~

46 Project Description Atpresent, thle powef deinwd in P-hrayaukkaphum Pnisai district and its vicinities is supplied from several nearby 115 kv EGAT's substations via 22 kv PEA's distribution lines. A new 115 kv substation at Phayakkhaphum Phisai is being constructed, under TS.8 Project for commissioning in 1996, to increase the capability of power supply to those areas at an acceptable reliability level and better power quality. However, since the new 115 kv Phayakkhaphum Phisai is still supplied by a single circuit line, therefore second circuit is required to further increase the reliability level. For the same reason as mentioned above, the power at 115 kv to Surin Substation is still supplied from Buriram Substation via a 115 kv single circuit line, therefore, a new 115 kv line is required. Stringing of the second 115 kv circuit on the underconstructed 115 kv double circuit line Roi Et - Phayakkhaphum Phisai line and the construction of a new 115 kv Phayakkhaphum Phisai - Surin line is proposed. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is August 1998.

47 --A, 115KVTOKHOC KAEN I..- -U'ISVTOPHON THON -I'KVT KA2L SI.w, -_*' z -...,.' II 4-_ ~~~~~~~.. /\ * - ' a S O N *' E HI ST.. BPROJEC NO N PHYKHPU HS1SURIN LN SUBPROJECTNO RA PBYAAP U,--HIS.,- SUI LIE

48 SUBPROJECT NO KV CHAIYAPHLUM - BAMNET NARONG LINE A. Objective Objectives of Subproject No.13, 115 kv Chaiyaphum - Bamnet Narong line and substations, are to provide sufficient power supply to Bamnet Narong and nearby districts with satisfactory voltage regulation and acceptable reliability of services and also to reduce system losses. B. Project Scope and Description Proiect Scope The scope for the 115 kv Chaiyaphum - Bamnet Narong line and substations consists of the following constructions: a) Construction of 115 kv Chaiyaphum - Bamnet Narong transmission line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 58 km. b) Expansion of 115 kv Chaiyaphum Substation for one outgoing line. c) Construction of new 115 kv Bamnet Narong Substation with two 3-phase, kv power transformers, each rated OA/FA/FOA 30/40/50 MVA (land for the substation has been purchased in TS.8 project). d) Addition of communication system.

49 Proi ect Description The PEA 22 kv distribution lines which supply power to Bamnet Narong and nearby districts are connected with EGAT's 115 kv Nakhon Ratchasima 1, Chaiyaphum and Sikhiu substations at the distance of approximately 85, 70 and 90 km respectively. The high growth of power demand is expected due to the establishment of the ASEAN Potash Mine Project. Due to long distribution line, PEA has been facing with voltage drop problem and high distribution losses. Automatic voltage regulators (AVR) have been installed on the 22 kv distribution lines, however the excessive power losses still remain and the supply reliability is not at the acceptable level. The construction of a new 115 kv substation at Bamnet Narong will greatly increase capability of power supply to cope with the increasing demand in this area at an acceptable reliability level and satisfactory voltage regulation. Figure of the proposed line route of the Subproject is shown in appendix C. Proiect Implementation The proposed commissioning date is November 1997.

50 ~~:r~~~ lj :;~~~~~~~~LQ, ~'E ~~~~~~~~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ IAI 0~¾ZOVT KHON KAEN 3 I ~~~~~~~~'-~~~~~~~~*: ~ 1 ' ~ ~ ~ ~ ~ ~ - I N ~~~~~~~~~~ Thy,.~~~~~~~~~~~~~ WKA G;,),''~ ; ~5, T. 1 ¼ ', I I NAHNRTCISIA t, I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~4 C ~~ ~-~sss -~~.i* ~ ~ AGRICUTUREAREAS,,.,,..,,~~~~~~ u.. SUBPOJET NO KV HATAPHU - AMNT NAONGLIN

51 SUBPROJECT NO KV UBON RATCHATHANI 2 - KANTHARALAK LINE A. Objective Objectives of Subproject No.14, 115 kv Ubon Ratchathani 2 - Kantharalak line and substations, are to increase power supply capability to Kantharalak and nearby districts, to improve reliability of services and voltage regulation, and to reduce system losses. B. Project Scope and Description Proiect Scope The scope for the 115 kv Ubon Ratchathani 2 - Kantharalak line and substations consists of the following constructions: a) Construction of 115 kv Ubon Ratchathani 2 -Kantharalak transmission line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 55 km. b) Expansion of 1 15 kv Ubon Ratchathani 2 Substation for one outgoing line. c) Construction of new 115 kv Kantharalak Substation with two 3-phase, kv power transformers, each rated OA/FA/FOA 30/40/50 MVA (land for the substation has been purchased in TS.8 project). d) Addition of communication system.

52 Project Description The power supply for Kantharalak and nearby districts is available from the 115 kv Si Sa Ket Substation via PEA 22 kv distribution lines at a distance of 65 km. Due to long distribution line, PEA has therefore installed automatic voltage regulators (AVR) to boost the voltage at the receiving end. However high power losses is still encountered and reliability of power supply is not at the acceptable level. The power demand in Kantharalak and nearby districts is expected to increase at high growth rate, because PEA has planned to expand the distribution lines to serve more remote villages. The construction of 115 kv Ubon Ratchathani 2 - Kantharalak line will support the PEA's distribution project and increase reliability of the electric services in this area. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is August 1998.

53 . \... K 1'YS T 1153Y S _ C v O ONU N i.-iis / 1: KDAHA H AN N N ~~ Z\,-' / L Th~~~~~. ~~ L' ~~~~~~~~UBON X t o,]-.~ * \,,, -- RATCHATHANI 11 N ~~~~~ ~ ~ ~ ~ ~ ~ - -'~~~~~~~~~~-K > '' i I i;:; 2 WE~~~~~~~~~~~~~~~~~~~~N T~~~~~~~~\, / A I, ~ ~ ~ SUUST T[ TIO -llvt0s KET.,,. A / GRREA fe~~~~~~~4 -w W 01U ' J t TwH~JIRiOs--e.'.... "-(? ^ i~~~~~-,..,'r-. _. M EsltoirN CII SUBPROJECT NO KV UBON RATCHATHANI 2- KANTHARALAK LINE 4;3

54 SUBPROJECT NO KV SURIN - SAGKHA LINE A. Objective Objectives of Subproject No.15, 115 kv Surin - Sangkha line and substations, are to cope with the increasing demand in Sangkha and nearby districts with satisfactory voltage regulation and reliability, and also to reduce system losses. B. Project Scope and Description Project Scope The scone for the 115 kv Surin - Sanackha line and zihztntions constructions: consits nf the fn1in.xana a) Construction of 115 kv Surin - Sangkha line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 49 km. b) Construction of new 115 kv Sangkha Substation, equipped with two 3-phase, kv power transformers, each rated OA/FA/FOA 30/40/50 MVA. c) Expansion of 1 15 kv Surin Substation for one outgoing line. d) Land procurement for Sangkha Substation. e) Addition of communication system. A 4

55 Project Description At present, power demand in Sangkha and nearby districts is supplied from Surin and Si Sa Ket Substations via PEA 22 kv distribution lines at distance of 50 and 60 km respectively. However, large voltage drop and excessive distribution line losses have been encountered due to long distribution line. To meet the increasing power demand, further reinforcement of the distribution system will not be economical in long-term. The construction of a new substation at Sangkha district is proposed to increase the power supply capability to the areas of Sangkha and its vicinity. The better quality and reliability of services will be provided. The distribution system operation will have more flexibility and also the distribution line losses will be substantially reduced. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is August itr

56 fl Irl >Y\!-,,ftSkv?, -A d%- t4 0 7; t 'S CH seuds'l AY1,W4 vitpon v C- (L A- Am6hus Pran usun- -4- K.6py, N1, Vr u L t3 7) 7 3 t i. LIWLIIII I " 7 "g, 74 0 tow v f K..Q v 0 -/1 L;OP-K" TK;;m C ph)- 'Zan T Wes-10. RESERVE FOREST AREAS (PERMIT PENDING) 21.- AGRICUTURE AREAS N. -V ly T. SUBPROJECT NO KV SURIN - SANGKHA LINE

57 SUBPROJECT NO.16, KV SURAT TRANI - THUNG SONG - NAKHON SI THAMMARAT LINE A. Objective Objective of Subproject No.16, kv Surat Thani - Thung Song - Nakhon Si Thammarat lines and substations, is to prevent line overloading on the 230 kv Khanom - Nakhon Si Thammarat and the 115 kv Thung Song - Nakhon Si Thammarat lines. B. Project Scope and Description Proiect Scope The scope for the 230 kv Surat Thani - Thung Song - Nakhon Si Thammarat lines and substations consists of the following constructions: a) Construction of 230 kv double circuit Surat Thani - Thung Song - Nakhon Si Thammarat transmission line, double circuit steel towers, using 2x1272 MCM ACSR conductor per phase for Surat Thani - Thung Song line section (122 km) and lx1272 MCM ACSR conductor per phase for Thung Song - Nakhon Si Thammarat line section (54 km) for a total distance of approximately 176 km, on the right-of-way of the existing 115 kv Surat Thani - Thung Song - Nakhon Si Thammarat line which will be dismantled. The new 230 kv line will be terminated at a new 230 kv switchyard at Thung Song, and the line section between Thung Song and Nakhon Si Thammarat will be initially energized at 115 kv. b) Expansion of Thung Song Substation for a new 230 kv switchyard. The new 230 kv switchyard will be constructed with the installation of two 3-phase 230/ kv tie transformers, each rated OA/FA/FOA 120/160/200 MVA, to integrate with the existing 115 kv system; and two 230 kv bays for lines to Surat Thani. The two additional 115 kv bays are provided for lines to Nakhon Si Thammarat. a 7

58 c) Expansion of 230 kv Surat Thani Substation for two outgoing lines to Thung Song Substation. d) Expansion of 115 kv Nakhon Si Thammarat Substation for one additional line to Thung Song Substation. e) Temporary installation of 3x20 MVAr 115 kv Shunt Capacitor banks at Thung Song Substation. f) Land procurement for the extension of the existing Thung Song Substation. g) Addition of communication system. Project Description The major transmission line which supply power to the lower part of Southern Thailand is the 230 kv Surat Thani - Khanom - Nakhon Si Thammarat - Phatthalung -Hat Yai 2 double circuit line. The power flow on these 230 kv lines is being increased due to the rapid growth power demand at the lower Southern area and the cement factory expansion at Thung Song. To maintain the reliability of power supply, the transmission system reinforcement to cope with the increasing demand is therefore required. Due to the difficulty to obtain a new right-of-way in these areas, the construction of 230 kv double circuit Surat Thani - Thung Song - Nakhon Si Thammarat line on the existing right-of-way is proposed based on the least cost solution. To maintain the continuous power supply for Thung Song Substation, two line section of this subproject should be constructed at two different schedules. Construction of the double circuit 230 kv Nakhon Si Thammarat - Thung Song line section should be completed before dismantling the 115 kv Surat Thani - Thung Song line section. Figure of the proposed line route of the Subproject is shown in appendix C. Proiect Implementation The proposed commissioning dates are June 1997 for 230/115 kv Thung Song - Nakhon Si Thammarat line and August 1998 for 230 kv Surat Thani - Thung Song line. E.9

59 -,3PAC HUAP 14NDI KH, A I.i -' -.':- 5 ^ - ^ ~ ;. 1 U ~ ~ ~ ~ ~ ~ C r.t 3RC!- q O R z ', t H * rdw H A L W,,; a, t, Y _t, Z 44 M, ABR JC N.1S- O'-.'L S E U CT B P R O N J O l v A r T H U N G S O N G - N AhwH O N S l T H A.\ l i! N PHU PtBAN N DO U~~~~~~~~~~~~~~~-~ T.CAMAL~ei ~ _ oi ns n os Tln ror rr".=,l SUBPROJECTNO K',' SURA THANI THU G SONG LIN SUBROJCT 230KY O.16. HU G SNG 4K O'~SI BA~MA~T INE~A

60 SUBPROJECT NO KV KHLONG NGAE - YALA 2 LINE A. Objective Objectives of Subproject No.18, 230 kv Khlong Ngae - Yala line and substations, are to improve reliability of supply and to provide sufficient power supply for future demand, at Yala, Pattani, Narathiwat and Sungai Kolok substations. B. Project Scope and Description Proiect Scope Thp -cnnp fnr thp 9Ifl kv T(hlnno Nop _ Yala line nnai q11hgttinnq rnnqktq nf tht- fnllnwino constructions: a) Construction of 230 kv Khlong Ngae - Yala line, double circuit steel towers, using 1272 MCM ACSR conductor, a distance of approximately 120 km. Part of the right-of-way of the existing 115 kv Hat Yai 2 - Yala single circuit line, which will be dismantled, will be used for the construction of the new 230 kv lines. b) Construction of 230 kv Yala Switchyard with the installation of two 3-phase 230/ kv tie transformers, rated OA/FA/FOA 120/160/200 MVA, to integrate with the existing 115 kv system. Two 230 kv line bays are also provided to receive power from 230 kv Khlong Ngae Substation. c) Expansion of 230 kv Khlong Ngae Substation for two outgoing lines. d) Land procurement for the extension of Yala Substation. e) Addition of communication system.

61 Project Description The power demand at Pattani, Yala, Narathiwat and Sungai Kolok Substations are supplied from Bang Lang Dam and 230/115 kv Hat Yai 2 Substation via 115 kv Hat Yai 2 - Yala single circuit line and 115 kv Hat Yai 2 - Pattani double circuit line. The peak demand of Yala, Narathiwat and Sungai Kolok Substation is increased at 7.3 % annually. The generation from Bang Lang Dam has been occasionally derated in case of low head of water level or shutdown for maintenance, and the power supply for those areas rely on the long transmission lines from Hat Yai 2 Substation. For such the cases the reliabily of supply is not meet the criteria and the system reinforcement is therefore required. The Khlong Ngae switching station, a new substation being implemented under the EGAT-TNB Stage II Interconnection Project, is considered as a firm power source. The construction of the Khlong Ngae - Yala line and substations is proposed to effectively improve the reliability of power supply and provide sufficient power for the increasing demand in the areas of Pattani, Yala and Narathiwat provinces. Part of the existing right-of-way of the 115 kv Hat Yai 2 - Yala line (Hat Yai 2 Junction, approximately 27 km. southeast of Hat Yai 2 Substation, to Yala line section, see Figure 4.14), which will be dismantled, will be used for the new proposed 230 kv line. The remaining section of the 115 kv line from Hat Yai 2 Substation to Hat Yai 2 Junction will be energized to maintain the right-of-way for the future use. During dismantling the 115 kv line and constructing the new 230 kv line on this line section, the Bang Lang power plant has to generate at least 40 MW all the time. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is April ~~~~~~Ir ~ ~ ~ ~ ~ r

62 I-. ~~~~~~~~~~~~~~~~~~~ ;7.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~r 7~~~~~~~~~~~Vi /~~~~~~~~~~~~~~ A >~~~~~~~~~~~~.w. U0A Vy.\ ;ML EAL SBPOEC N V HONGME LN

63 SUBPROJECT NO /115 KV PHANG NGA - PHUKET JUNCTION - PHUKET 2 LINE A. Objective Objectives of Subproject No.19, the 230/115 kv Phangnga - Phuket Junction - Phuket 2 lines and substations, are to increase the power supply capability and to maintain the reliability and quality of power supply to Phuket Province. B. Project Scope and Description Project Scope The scope for 230/115 kv Phangnga - Phuket Junction - Phuket 2 lines and substations consists of the following constructions: a) Construction of 230 kv double circuit Phangnga - Phuket Junction (about 6 km north of Phuket 1 Substation) transmission line, double circuit steel towers, using 1272 MCM ACSR conductor, initially energized at 115 kv, a distance of approximately 76 km. This transmission line will be constructed on the right-of-way of the existing 115 kv single circuit Phangnga - Phuket 2 line of which the line section from Phangnga to the Phuket Junction will be dismantled. One circuit of this new double circuit line will be connected with the remaining 115 kv line section to 115 kv Phuket 2 Substation and the other circuit will be connected with the new 115 kv compact line to Phuket 2 Substation as described in (b) below. b) Construction of the 115 kv Phuket 2 - Phuket Junction compact line on one side of the existing right-of-way of 115 kv Phuket 2 - Phuket Junction line section, which is 25 meters width from the centre to the edge of the right-of-way, single circuit using 2x795 MCM ACSR conductor, a distance of approximately 12 km. This transmission line will be connected with one circuit of double circuit 230 kv Phangnga - Phuket Junction line as described in (a) above. 53

64 c) Expansion of 115 kv Phuket 2 Substation for one incoming line from Phan-guiga. d) Expansion of 115 kv Phangnga Substation for one additional line. e) Land procurement for the future 230 kv substation in Phuket Province (near the Phuket Junction). f) Addition of communication system. Project Description The power demand in Phuket Province is supplied from Phuket 1 and Phuket 2 Substations which receive power from Phangnga Substation via one 115 kv double circuit line strung with 477 MCM ACSR conductor and one 115 kv single circuit line strung with 150 sq.mm AAC conductor. The existing transmission system will not sufficient to serve the power demand in the future which is expected to increase at high growth rate, since Phuket Island is the very famous tourist spot known as Pearl of Andaman. In order to secure reliability and quality of power supply in Phuket Province, the reinforcement of transmission system is required. The difficulties of obtaining a new right-of-way in the Phuket island is foreseen, therefore, the use of existing right-of-way for the new transmission line has been planned. Consequently, to maintain the power supply reliability during dismantling the existing transmission line, early construction of the new transmission line is recommended, and the construction of a double circuit 230 kv Phangnga - Phuket Junction - Phuket 2 line (initially energized at 115 kv) on the right-of-way of the existing 115 kv single circuit line Phangnga - Phuket 2 (Phuket Junction) is proposed. Figure of the proposed line route of the Subprojeet is shown in appendix C. Project Implementation The proposed commissioning date is November 1997.

65 N.~~~~ 2 't ' l 9 t '; 9 '' %<- t a VU. 't*~a v5 ;J 7-.r- n r-!^;.ixy zrmu s; Inl: ^1v: ~~~~~~~~~~~~~~- L ao Y,2/r SUBPROJECT NO ~ - nn1~~~~~~~~~~~~~~~~~~~~~~~~~*. n. L-~W 4S!e 11EV ft ~ ~ ~ ~ J UKET JUNCKVPAGGA-PUETJNTON-PUT'LN (6 r 4 - ~~~~~~~~~~~136-q l~~~~~~~~~~~ LX6', o! -~*. =~XI- PNUKVT 2 r.v-.,- S - no., P H 1 U KEY J USN C I' ON,_ tn~~~~~~~~~~~~~~~~~~~~~~~~~~~

66 SUBPROJECT NO KV YALA - NARATHIWAT LINE A. Obiective Objective of Subproject No.20, 115 kv Yala - Narathiwat line and substations, is to improve reliability of power supply for Narathiwat Province. B. Project Scope and Description Project Scope The scope for the 115 kv Yala - Narathiwat line and substations consists of the following constructions: a) Construction of 115 kv Yala - Narathiwat line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 61 km. b) Expansion of 115 kv Yala Substation for one tutgoing line. c) Expansion of 115 kv Narathiwat Substation for one incoming line. d) Addition of communication system. Proiect Description At present, the power demand in Narathiwat including Sungai Kolok district is supplied from Yala substation via 115 kv single circuit line. The present peak demand is 31.8 MW and expected to increase at 8.2 % annually. New additional transmission circuit is therefore required to cope with the future high peak demand and to improve the reliability of power supply. The construction of a new 115 kv Yala - Narathiwat line is proposed. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning dates is April

67 4-115 KV T10 P Wr 1'A NI / ;1?.2I7lrlbt Y' ' 17 onl YAL1~~~~~ P-Po q h 228~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~2 S;jA ~ ~ 4/JInM! 9~A KV DAM TO 11ANG L~~~~~~~N0 9 l*ft SUBPOJEC 15 NO.20. V YAA - ARATIWATLIN

68 SU'BPROJECT NO KV SURAT THANI - BAN DON LINE A. Objective Objectives of Subproject No.21, 115 kv Surat Thani - Ban Don line and substations, are to improve reliability of power supply, to provide sufficient power supply for future demand, and to reduce system losses. B. Project Scope and Description Project Scope The scope for the 115 kv Surat Thani - Ban Don line and substations consists of the following constructions: a) Stringing second circuit on the existing double circuit towers of the 115 kv Surat Thani - Ban Don line, using 477 MCM ACSR conductor, a distance of 13.4 km. b) Expansion of 115 kv Surat Thani Substation for one outgoing line. c) Expansion of 115 kv Ban Don Substation for one incoming line. Project Description The existing 115 kv Ban Don Substation is connected with 230/115 kv Surat Thani Substation by a single circuit on double circuit steel towers 115 kv line, 13.4 km, using 477 MCM ACSR conductor. The present peak demand at Ban Don Substation is 52.4 MW and expected to increase at the average growth rate of 6.5 % per year for the next 10 years period... 53

69 The reason for stringing only one circuit at the beginning is due to the fact that the power demand in Ban Don was not too high that PEA could maintain the continuous power supply by 33 kv distribution lines from Phunphin Substation in an emergency case when the 115 kv line trips out. With the high increasing demand, it is beyond the capability of the 33 kv line to serve the demand in such an emergency case, therefore the stringing of second circuit on the existing double circuit steel tower of the 115 kv Surat Thani - Ban Don line is proposed to ensure the reliable power supply in Surat Thani area. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is March

70 f-23op(vtoprachtuapkhifilklian' I~I.iŽ.[~I~ I.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~N Z., 7.7 A 3~~~~~~~~~~~~~~~~~~~~~ 2 3 /. k ~~~~~~ - ~ ~~~~~~~~~~~~~.I~~~~~~~~~~~~~~~~~~~~~=5 4: ~ t5v~3tto z~~~~~~~~~~~~~~~~~ -V..~~~~~~~~~. TPAPSMI DON UM SUBPROJECT NO KV SURAT TiSUNSTANTDON LINE

71 en SUBPROJECT NO KV LAN KRABU - KHAM PHAENG PHET LINE A. Obiective Objective of Subproject No.22, 115 kv Lan Krabu - Kamphaengphet line and substations is to improve the reliability and quality of power supply at Tak 1 and Kamphaengphet Substations. B. Project Scope and Description Proiect Scope T.bs scope fior thek. 1 1 IrxL V T vaoli 1a-.n., l ;ht "A slubtaofns- minea -cr.sts of t.ea following constructions: a) Construction of 115 kv Lan Krabu - Kamphaengphet line, double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 47 km. b) Expansion of 115 kv Lan Krabu Switchyard for two outgoing lines. c) Expansion of 1 15 kv Kamphaengphet Substation for two incoming lines. d) Addition of communication system. Project Description At present, the power demand at 115 kv Tak 1 and Kamphaengphet Substations is supplied from the two single circuit 115 kv lines linking Tak 1 Substation with the 230 kv Bhumibol switchyard and 115 kv Sukhothai Substation which further connecting with 230 kv Phitsanulok 2 Substation. In case that the 115 kv Bhumibol -Tak 1 line trips out, the power demand for these two substations will be supplied from the 230 kv Phitsanulok 2 61

72 Substation via the 115 kv Phitsanulok 2 - Sukhothai - Tak 1 single circuit line for a total distances of 120 km. This case will lead to overload on the 115 kv Phitsanulok 2 - Sukhothal line section and the unacceptable low voltage at Tak 1 and Kamphaengphet Substations. Furthermore, Kamphaengphet Substation is an end substation which connects with Tak 1 Substation by a single circuit 115 kv line. Therefore, there is the possibility of total blackout in Kamphaengphet area if this line section trips out. Therefore, the construction of 115 kv Lan Krabu - Kamphaengphet is recommended. Figure of the proposed line route of the Subproject is shown in appendix C. Project ImDlementation The proposed commissioning date is November

73 0~~~~~~~~~~~~~~~1 im,~~~~~~~~~~~~~~~~~~~~~~~- W*' I4aMa.n - /~~~~a -ortf ~~~~~~~~~~~~~ K~~~~~~~~~~~~~~iVIMLI ~~~1 ha~~ w.~~ ~ ~ rn.n *" f~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~f S~~~,a ~ Tba.arag ~ Sa,.n ~ ~ ~ ~ ~ ~ ~~D W.gph L'IIJI~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ tfllatt,a'~~~a /~~~~IMDV0 < N naajahk V~T.~~su'on~o h,~~~~~~~.g~~~~~~ah~~~~~k~~~~4 1 ~~~~~~ - "B..W m ' '1/- ~~~~~~AWAN4~~~~ A2OIVTNAbIN5WA r, Inaawn SUPRJCTNO 2.11 V ANKKA -KMPAPGHE LN

74 SUBPROJECT NO KV MAE MOH 3 - LAMPANG 2 LINE A. Objective Objective of Subproject No.23, 115 kv Mae Moh 3 - Lampang 2 line and substations is to increase power supply capability to cope with the increasing demand at Lampang 2 and Lamphun 2 Substations. B. Project Scope and Description Project Scope The scope for the 115 kv Mae Moh 3 - Lampang 2 line and substations consists of the following constructions: a) Construction of 115 kv Mae Moh 3 - Lampang 2 line, double circuit steel towers, using 2x795 MCM ACSR conductor per phase, a distance of approximately 27 km. b) Modification of 115 kv Mae Moh 3 Switchyard from Main & Transfer bus arrangement to Breaker and a Half scheme and expansion for two outgoing line. c) Modification of 115 kv Lampang 2 Substation from tapped substation to fully equipped circuit breaker substation for terminating both circuits of the 115 kv double circuit Mae Moh 2 - Lamphun 2 line and the expansion of 115 kv bays for two incoming lines from Mae Moh 3 switchyard. d) Addition of communication system. 64.

75 Proiect Description At present, the power demand at the 115 kv Lampang 2 Substation is supplied from one circuit of the 115 kv double circuit Mae Moh 2 - Lamphun 2 line. The power demand at Lampang 2 Substation is increasing highly due to the requirement of the cement factory which is being constructed in this area. The existing 115 kv line also transmits generated power from Mae Moh Power Plant to Lamphun and Chiang Mai areas; therefore, with the large power demand at Lampang 2 Substation, heavy line loading on the 115 kv Mae Moh 2 - Lampang 2 line section is observed, and overloading on this line section will occur if one circuit of the double circuit trips out. Therefore, construction of a new 115 kv Mae Moh 3 - Lampang 2 line is proposed together with the modification and expansion of Mae Moh 3 and Lampang 2 substations. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is December

76 0~~~~~~~~~~~~~~~~~~~~' -- / F2 I~~~~~~~~~ "L ~~~~~~~~ 1KV (' 5 MY 6.11 ~ oiti ~ ~ ~ ~ ~ ~ ~ Og~~ ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~z SUBPROJECT 23. NO. 115 KV MAE M LANIPANG 2 LINFY W M~~~

77 SUBPROJECT NO KV CHIANG MAI 2 - MAE TAENG LINE A. Objective Objectives of Subproject No.24, 115 kv Chiang Mai 2 - Mae Taeng line and substations, are to provide more reliable power supply to Mae Taeng and nearby areas, to improve quality of power supply and also to reduce system losses. B. Project Scope and Description Proiect Scope The scope for the 115 kv Chiang Mai 2 - Mae Taeng line and substations consists of the following constructions: a) Construction of 115 kv Chiang Mai 2 - Mae Taeng transmission line, single circuit on double circuit steel towers, using 795 MCM ACSR conductor, a distance of approximately 42 km. b) Expansion of 1 15 kv Chiang Mai 2 Substation for one outgoing line. c) Construction of a new 1 1 kv Mae Taeng Substation, equipped with two 3-phase, kv power transformers, each rated OA/FA/FOA 30/40/50 MVA. d) Land Procurement for Mae Taeng Substation. e) Addition of communication system. 67,

78 Project Description Tne power demand in Mae Taeng and its vicinity is presently supplied from 115 kv Chiang Mai 2 Substation and Mae Ngat small hydro power plant through PEA 22 kv distribution system. According to the demand forecast in this area, the existing PEA system will not meet the expected increasing demand, and will not be able to support the PEA's rural electrification program to expand its distribution system to several remote villages in this area. To meet the increase of power demand at Mae Taeng and its vicinity with more reliable power supply, the construction of 115 kv Chiang Mai 2 - Mae Taeng line and new substation at Mae Taeng is proposed. Figure of the proposed line route of the Subproject is shown in appendix C. Project Implementation The proposed commissioning date is June

79 d_wwnn RESERVE FOREST AREAS (PERMIT PENDING)?., u ivws^.. l _ ~~AGRICUTURE AREAS ; " 0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ 12 s ns,: Hda t1 t~~~~~~~~~~~~~~~~, ;ISTUTINCrwrt X:TY ura. \.^x : = \r 2 *\ a- 2 1gl*,/* ; SUBPOJEC NO hv CHANG TAI A TEGLNEADSBSAIN -A-~h

Procurement Plan. Estimated Price (Million Baht) Tentitive Plan. Remark. No. Bid No. Description

Procurement Plan. Estimated Price (Million Baht) Tentitive Plan. Remark. No. Bid No. Description No. Bid No. Description 1 TS12-L-04 Supply and Construction of Transmission Lines 230 kv Chanthaburi - Trat Procurement Plan Estimated Price (Million Baht) Tentitive Plan Bid Issue Bid Opening Letter of

More information

The System Angle Instability Reduction in Transmission System of Northeastern Region of Thailand

The System Angle Instability Reduction in Transmission System of Northeastern Region of Thailand The System Angle Instability Reduction in Transmission System of Northeastern Region of Thailand Poom Phogun, Short-Term Transmission System Study Section, Transmission Operation Planning Department, Power

More information

Note : Rainfall, temperatures and natural disasters were updated up to November 14, 2015

Note : Rainfall, temperatures and natural disasters were updated up to November 14, 2015 Monthly Weather Summary in Thailand The monsoon trough lay across lower northern, central and northeastern parts during early month. After that it moved southward to lie across lower central, eastern and

More information

Monthly Weather Summary in Thailand September 2016

Monthly Weather Summary in Thailand September 2016 Monthly Weather Summary in Thailand September 2016 September 2016 was dominated by the monsoon trough which lay across upper Thailand almost the whole month coupled with the prevailing of moderate to rather

More information

Monthly Weather Summary in Thailand October 2016 The monsoon trough mostly lay across upper Thailand coupled with southwest monsoon prevailed over

Monthly Weather Summary in Thailand October 2016 The monsoon trough mostly lay across upper Thailand coupled with southwest monsoon prevailed over Monthly Weather Summary in Thailand October 2016 The monsoon trough mostly lay across upper Thailand coupled with southwest monsoon prevailed over the Andaman Sea, southern part and the Gulf of Thailand

More information

Monthly Weather Summary in Thailand September 2015

Monthly Weather Summary in Thailand September 2015 Monthly Weather Summary in Thailand September 2015 September 2015 was dominated by the monsoon trough which occasionally lay across the northern, upper central and upper northeastern parts coupled with

More information

Monthly Weather Summary in Thailand November 2016 The moderate to rather active high pressure area from China periodically extended its ridge to

Monthly Weather Summary in Thailand November 2016 The moderate to rather active high pressure area from China periodically extended its ridge to Monthly Weather Summary in Thailand November 2016 The moderate to rather active high pressure area from China periodically extended its ridge to cover upper Thailand, successive cool weather was occasionally

More information

Monthly Weather Summary in Thailand January 2019

Monthly Weather Summary in Thailand January 2019 Monthly Weather Summary in Thailand January 2019 In January 2019, the high pressure area from China occasionally extended its ridge to cover upper Thailand and the South China Sea caused cool weather in

More information

CASE STUDY YUWADEE SUWANMANEE THAI METEOROLOGICAL DEPARTMENT (TMD) THAILAND INTERNATIONAL WORKSHOP ON THE ASSESSMENT OF SOCIO-ECONOMIC BENEFITS OF

CASE STUDY YUWADEE SUWANMANEE THAI METEOROLOGICAL DEPARTMENT (TMD) THAILAND INTERNATIONAL WORKSHOP ON THE ASSESSMENT OF SOCIO-ECONOMIC BENEFITS OF CASE STUDY YUWADEE SUWANMANEE THAI METEOROLOGICAL DEPARTMENT (TMD) THAILAND INTERNATIONAL WORKSHOP ON THE ASSESSMENT OF SOCIO-ECONOMIC BENEFITS OF METEOROLOGICAL AND HYDROLOGICAL SERVICES (NANJING, CHINA,

More information

Monthly Weather Summary in Thailand August 2018

Monthly Weather Summary in Thailand August 2018 Monthly Weather Summary in Thailand August 2018 Thailand s weather in August 2018 was dominated by the southwest monsoon which prevailed over the Andaman Sea, Thailand and the Gulf of Thailand throughout

More information

MRC SEA of Hydropower on the Mekong Mainstream. Thailand baseline assessment

MRC SEA of Hydropower on the Mekong Mainstream. Thailand baseline assessment MRC SEA of Hydropower on the Mekong Mainstream Thailand baseline assessment Presentation overview 1. Socio-economic Population & GDP Poverty incidence income & expenditure 2. Power Mekong province energy

More information

Monthly Weather Summary in Thailand May 2016

Monthly Weather Summary in Thailand May 2016 Monthly Weather Summary in Thailand May 2016 In May 2016, hot weather still persisted in Thailand nearly the whole month especially in the northern and upper central parts where successive of very hot

More information

STRENGTHENING SAFETY MANAGEMENT SYSTEM OF AGRICULTURAL PRODUCTS

STRENGTHENING SAFETY MANAGEMENT SYSTEM OF AGRICULTURAL PRODUCTS STRENGTHENING SAFETY MANAGEMENT SYSTEM OF AGRICULTURAL PRODUCTS By Supannikar Pakkethati Division of Rice research and Development Rice Department, thailand Rice Department Leading rice research and development

More information

Pick & Mix: Thailand VISA: TAKE THE WORRY OUT OF TRAVEL ADVERTISING FEATURE. Table of Contents

Pick & Mix: Thailand VISA: TAKE THE WORRY OUT OF TRAVEL ADVERTISING FEATURE. Table of Contents Pick & Mix: Table of Contents ADVERTISING FEATURE VISA: TAKE THE WORRY OUT OF TRAVEL Everyone who travels overseas worries about money. But Visa has a range of safe and widely-accepted card options that

More information

GEN 3.4 COMMUNICATION SERVICES

GEN 3.4 COMMUNICATION SERVICES GEN.- GEN. COMMUNICATION SERVICES.. Responsible services The responsible service for the provision of telecommunication and navigation facility services in Thailand is Aeronautical Radio of Thailand Limited.

More information

RUNWAY SAFETY ISSUES and MITIGATION OPTIONS

RUNWAY SAFETY ISSUES and MITIGATION OPTIONS RUNWAY SAFETY ISSUES and MITIGATION OPTIONS By Wing Commander Nutt Homasavin Airports of Thailand Plc. 1 CONTENT AOT s Airports Safety Policy, Structure and Committee Runway Safety Program Background of

More information

New Evidences on the Effects of the 300 Baht Minimum Wage on Employment, Hours Worked, and Wage Inequality in Thailand

New Evidences on the Effects of the 300 Baht Minimum Wage on Employment, Hours Worked, and Wage Inequality in Thailand New Evidences on the Effects of the 3 Baht Minimum Wage on Employment, Hours Worked, and Wage Inequality in Thailand Dilaka Lathapipat, World Bank July 21, 215 1 Objective of the Study To inform the debate

More information

Thailand Annual Weather Summary, 2012

Thailand Annual Weather Summary, 2012 Thailand Annual Weather Summary, 2012 The year 2012 was warmer than usual. Mean air temperature was above normal for all months, while monthly mean values for late year were 2-3 o C above normal. Annual

More information

2011 Thailand Flood Execute Summary

2011 Thailand Flood Execute Summary 2011 Thailand Flood Execute Summary In 2011, Thailand witnessed its worst flooding in half a century, leaving severe impairments to the country s economy, industrial sector, and society. Factors that contributed

More information

Comparison of the Water Footprint of Cassava and Sugarcane in Northeast, Thailand

Comparison of the Water Footprint of Cassava and Sugarcane in Northeast, Thailand erd Research article Comparison of the Water Footprint of Cassava and Sugarcane in Northeast, Thailand NARUEMOL KAEWJAMPA* Faculty of Forestry, Kasetsart University, Bangkok, Thailand Email: narue77@gmail.com

More information

h // id d / bli i / g papers/2012/en_gb/wp /

h // id d / bli i /   g papers/2012/en_gb/wp / The effects of rural land right security on labour structural transformation and urbanisation: Evidence from Thailand Thanyaporn yp Chankrajang May 2012 WIDER Working Paper No. 2012/41, ISBN No. 978 92

More information

Airports of Thailand Public Company Limited

Airports of Thailand Public Company Limited Airports of Thailand Public Company Limited (AOT) 2 nd nd Quarter 2006 (January - March 2006) Agenda AOT Business Highlights Air Traffic Statistics Airport Capacity Suvarnabhumi Airport Recent Development

More information

BRIEF ENVIRONMENT REPORT

BRIEF ENVIRONMENT REPORT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PEOPLE COMMITTEE OF HOCHI MINH CITY WORLD BANK HO CHI MINH CITY DEVELOPMENT PROJECT HDP

More information

Annual Weather Summary of Thailand in 2011

Annual Weather Summary of Thailand in 2011 1 Annual Weather Summary of Thailand in 2011 2011 was the wettest year for Thailand in the 61- years (1951-2011) record. This resulted mainly from widespread rain in Thailand especially during summer and

More information

Study on the Urban Development Plan in the Station Areas (Nakhon Sawan & Phitsanulok)

Study on the Urban Development Plan in the Station Areas (Nakhon Sawan & Phitsanulok) [ August, 2018 ] PREPARATORY SURVEY BANGKOK-CHIANGMAI HIGH SPEED RAIL DEVELOPMENT PROJECT PHASE 1 STAGE 2 Study on the Urban Development Plan in the Station Areas (Nakhon Sawan & Phitsanulok) JIC OCG NK

More information

Thailand s Transport Infrastructure Development plans

Thailand s Transport Infrastructure Development plans Thailand s Transport Infrastructure Development plans Mr. Chaiwat Thongkamkoon Director General, Office of Transport and Traffic Policy and Planning Thailand s Transport Infrastructure Development Strategies

More information

Tour H, Isaan Tour. page 1 of 6. Siam Bike Tours Co. Ltd. Boat Avenue 49/4 Bandon-Choengthale Road Thalang, Choeng Thale Phuket 83110, Thailand

Tour H, Isaan Tour. page 1 of 6. Siam Bike Tours Co. Ltd. Boat Avenue 49/4 Bandon-Choengthale Road Thalang, Choeng Thale Phuket 83110, Thailand Siam Bike Tours Co. Ltd. Boat Avenue 49/4 Bandon-Choengthale Road Thalang, Choeng Thale Phuket 83110, Thailand phone: +66 (0) 89 7307 441 mail@siambiketours.com www.siambiketours.com Tour H, Isaan Tour

More information

Environmental Management System for Tourist Accommodations in Amphawa, Samut Songkram,Thailand

Environmental Management System for Tourist Accommodations in Amphawa, Samut Songkram,Thailand Abstract Amphawa is the most popular weekend destination for both domestic and international tourists in Thailand. More than 112 homestays and resorts have been developed along the water resources. This

More information

Project Purpose: Project History and Status:

Project Purpose: Project History and Status: Plant Unit Substation Improvements Project Purpose: The purpose of this project is to ensure that the portions of the Nine Springs Wastewater Treatment Plant powered by Unit Substations U11, U12, and U13

More information

National Forests and Grasslands in Texas

National Forests and Grasslands in Texas United States Department of Agriculture Forest Service National Forests and Grasslands in Texas Sam Houston NF 394 FM 1375 West New Waverly, Texas 77358 Phone 936-344-6205 Dear Friends, File Code: 1950

More information

VAR-501-WECC-3 Power System Stabilizer. A. Introduction

VAR-501-WECC-3 Power System Stabilizer. A. Introduction A. Introduction 1. Title: Power System Stabilizer (PSS) 2. Number: VAR-501-WECC-3 3. Purpose: To ensure the Western Interconnection is operated in a coordinated manner under normal and abnormal conditions

More information

This document is downloaded from DR-NTU, Nanyang Technological University Library, Singapore.

This document is downloaded from DR-NTU, Nanyang Technological University Library, Singapore. This document is downloaded from DR-NTU, Nanyang Technological University Library, Singapore. Title Country paper from Thailand Author(s) Amporn Samosorn Citation Amporn S. (1998). Country paper from Thailand.

More information

Financing Railway: PPP s Lesson form Mass Transit in Bangkok Sumet Ongkittikul August 2017

Financing Railway: PPP s Lesson form Mass Transit in Bangkok Sumet Ongkittikul August 2017 Thailand Development Research Institute Financing Railway: PPP s Lesson form Mass Transit in Bangkok Sumet Ongkittikul August 2017 Content Infrastructure Investment in Thailand Mass Transit Investment

More information

CHAPTER 8 INDUSTRY. 8.1 Current Situation of Thai Industry Industrial Development. (1) 1950 s Industrial Situation

CHAPTER 8 INDUSTRY. 8.1 Current Situation of Thai Industry Industrial Development. (1) 1950 s Industrial Situation The Study on the Integrated Regional Development Plan for the Northeastern Border Region in the Kingdom of Thailand Sector Plan: Chapter 8 Industry CHAPTER 8 INDUSTRY 8.1 Current Situation of Thai Industry

More information

28 August 2017 INVESTOR RELATIONSHIP PRESENTATION

28 August 2017 INVESTOR RELATIONSHIP PRESENTATION 28 August 2017 200 Jasmine lnternational Tower 15th Floor, Moo 4, Changwattana Rd., T.Pakkret, A.Pakkret, Nonthaburi, 11120 INVESTOR RELATIONSHIP PRESENTATION www.unique.co.th ir@unique.co.th Table of

More information

Performance of Wind Farms in Thailand

Performance of Wind Farms in Thailand Performance of Wind Farms in Thailand Based on Mott MacDonald s in country experience Sasaraj Laoharatchapruek Bangkok, 06 June 2018 Sasaraj Laoharatchapruek Renewable Energy Consultant Bangkok Based Experience

More information

COUNTRY SECTION. Thailand Meat products. Validity date from 04/12/2017 Date of publication 21/11/2017. List in force

COUNTRY SECTION. Thailand Meat products. Validity date from 04/12/2017 Date of publication 21/11/2017. List in force COUNTRY SECTION Thailand Meat products Validity date from 04/12/2017 Date of publication 21/11/2017 00215 List in force 02 Thai Q.P. Co., Ltd Ban Pong Ratchaburi 03 CPF (Thailand) Public Co., Ltd. Min

More information

Thailand Country Report

Thailand Country Report The 4 th meeting of the Working Group on the Asian Highway and Expert Group Meeting on Progress on Road safety Improvement in Asia and the Pacific Bangkok, Thailand, 27 29 September 2011 Thailand Country

More information

Rule Governing the Designation and Establishment of All-Terrain Vehicle Use Trails on State Land

Rule Governing the Designation and Establishment of All-Terrain Vehicle Use Trails on State Land Rule Governing the Designation and Establishment of All-Terrain Vehicle Use Trails on State Land 1.0 Authority 1.1 This rule is promulgated pursuant to 23 V.S.A. 3506. Section 3506 (b)(4) states that an

More information

C. APPROACH FOR IDENTIFYING THE BEST ROUTES FOR THE NEEDED TRANSMISSION SYSTEM IMPROVEMENTS

C. APPROACH FOR IDENTIFYING THE BEST ROUTES FOR THE NEEDED TRANSMISSION SYSTEM IMPROVEMENTS C. APPROACH FOR IDENTIFYING THE BEST ROUTES FOR THE NEEDED TRANSMISSION SYSTEM IMPROVEMENTS CL&P s approach for identifying the best routes for the needed transmission system improvements included a determination

More information

Chapter 1: Introduction Draft

Chapter 1: Introduction Draft Chapter 1: Draft TABLE OF CONTENTS 1... 4 1.6.1 Stakeholder Engagement Plan... 10 Chapter 1 Page 2 TABLE OF EXHIBITS Exhibit 1.1-1 ABIA Annual Growth Since 1993... 5 Exhibit 1.4-1: ABIA Location Map...

More information

Table 1 : Malaysian Investment Projects Submitted to BOI

Table 1 : Malaysian Investment Projects Submitted to BOI Table 1 : Malaysian Investment Projects Submitted to BOI No. of projects 40 38 40 37 38 39 Total Investment 13,467.7 5,542.0 8,578.1 10,342.7 3,610.8 7,058.7 Total Registered Capital 3,539.4 1,073.4 633.8

More information

Electric System Serving Pierce County Current system and future investments. Janet Olsen Steve Botts

Electric System Serving Pierce County Current system and future investments. Janet Olsen Steve Botts Electric System Serving Pierce County Current system and future investments Janet Olsen Steve Botts Project Manager Real Estate t / Rights-of-Way April 13, 2011 Presentation overview Information requested

More information

SUMMER VILLAGE OF SILVER SANDS. Municipal Development Plan

SUMMER VILLAGE OF SILVER SANDS. Municipal Development Plan SUMMER VILLAGE OF SILVER SANDS Municipal Development Plan Bylaw 253-2014 Adopted August 22, 2014 Summer Village of Silver Sands Municipal Development Plan Bylaw No. 253-2014 Page 2 1 INTRODUCTION 1.1 SETTING

More information

Electric System Serving Pierce County Current system and future investments

Electric System Serving Pierce County Current system and future investments Electric System Serving Pierce County Current system and future investments Janet Olsen Project Manager Steve Botts Real Estate / Rights-of-Way April 13, 2011 Presentation overview Information requested

More information

Large Disturbances During 2014 in Power System of Serbia

Large Disturbances During 2014 in Power System of Serbia Large Disturbances During 2014 in Power System of Serbia (32 nd Conference of CIGRE Serbia, Zlatibor, 17.-21. May 2015) by Gojko Dotlić SO3 SU3 SR NS3 SANDORFALVA ZR2 Power Transmission System of Serbia

More information

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited Gatwick Airport Limited Response to Airports Commission Consultation Appendix 37 Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Further information

More information

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February

More information

Parcel Post Compendium Online Thailand Post Co., Ltd. TH - Thailand THA

Parcel Post Compendium Online Thailand Post Co., Ltd. TH - Thailand THA Basic Services 1 Maximum weight limit admitted 1.1 Surface parcels (kg) 30 1.2 Air (or priority) parcels (kg) 30 2 Maximum size admitted 2.1 Surface parcels 2.1.1 2m x 2m x 2m (or 3m length & greatest

More information

Global Sustainable Tourism Destinations Criteria

Global Sustainable Tourism Destinations Criteria Global Sustainable Tourism Destinations Criteria Draft destination level Global Sustainable Tourism Criteria as proposed after Destinations and International Standards joint working group meeting and follow-up

More information

MEMBER REPORT. ESCAP/WMO Typhoon Committee 8 th Integrated Workshop/2 nd TRCG Forum THAILAND

MEMBER REPORT. ESCAP/WMO Typhoon Committee 8 th Integrated Workshop/2 nd TRCG Forum THAILAND MEMBER REPORT ESCAP/WMO Typhoon Committee 8 th Integrated Workshop/2 nd TRCG Forum THAILAND Macao, China 2-6 December 2013 CONTENTS CONTENTS Page I. Overview of tropical cyclones which have affected/impacted

More information

A. Introduction Title: Power System Stabilizer (PSS) 2. Number: VAR 501 WECC

A. Introduction Title: Power System Stabilizer (PSS) 2. Number: VAR 501 WECC A. Introduction 1. 1. Title: Power System Stabilizer (PSS) 2. 3. 2. Number: VAR 501 WECC 2 3. Purpose: To ensure the Western Interconnection is operated in a coordinated manner under normal and abnormal

More information

APPENDIX F List of Commitments

APPENDIX F List of Commitments APPENDIX F List of Commitments s Table F.1 Standard Mitigation Measures Mitigation Measure MnDOT Specification Number Status Update Description Status Update Utilities Provide early notice to utility operators

More information

D1 January 8, 2014 Public Hearing APPLICANT: HUNT CLUB FARM

D1 January 8, 2014 Public Hearing APPLICANT: HUNT CLUB FARM D1 January 8, 2014 Public Hearing APPLICANT: HUNT CLUB FARM PROPERTY OWNER: HUNT CLUB A-1- A, LLC. STAFF PLANNER: Kevin Kemp REQUEST: Modification of a Conditional Use Permit approved by the City Council

More information

ENR 1.6 RADAR SERVICES AND PROCEDURES

ENR 1.6 RADAR SERVICES AND PROCEDURES AIP ENR 1.6-1 10 NOV 16 ENR 1.6 RADAR SERVICES AND PROCEDURES 1. Operation 1.1 Air traffic control radar is the predominant means of control at Bangkok Area Control Centre and Approach Control Units at

More information

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan New Plan Acheson Industrial Area Structure Plan Amendment Parkland County Municipal Development Plan Board Reference

More information

TOWARDS SUSTAINABLE MANAGEMENT OF MARINE AND COASTAL HABITATS ASIA- PACIFIC DAY FOR THE OCEAN

TOWARDS SUSTAINABLE MANAGEMENT OF MARINE AND COASTAL HABITATS ASIA- PACIFIC DAY FOR THE OCEAN TOWARDS SUSTAINABLE MANAGEMENT OF MARINE AND COASTAL HABITATS WANNAKIAT THUBTHIMSANG PHUKET MARINE BIOLOGICAL CENTER, DMCR, THAILAND ASIA- PACIFIC DAY FOR THE OCEAN 20 NOVEMBER 2018, CONFERENCE ROOM 4,

More information

Chapter 1: Introduction

Chapter 1: Introduction Chapter 1: TABLE OF CONTENTS 1... 4 1.1 Master Plan Study Content... 4 1.2 Purpose and Scope of Master Plan Study... 4 1.3 Airport History and Role... 6 1.4 Airport Location and Service Area... 6 1.5 ABIA

More information

Criteria for a Successful Shore Power Project

Criteria for a Successful Shore Power Project Criteria for a Successful Shore Power Project Availability of an adequate supply of electricity at a reasonable cost. Frequency of calls by cruise vessels equipped to connect to Shore Power. Availability

More information

LAND ABSCHNITT. Thailand Fleischerzeugnisse. In Kraft seit 18/12/2018 Datum der Veröffentlichung 05/12/2018. Liste in Kraft

LAND ABSCHNITT. Thailand Fleischerzeugnisse. In Kraft seit 18/12/2018 Datum der Veröffentlichung 05/12/2018. Liste in Kraft LAND ABSCHNITT Thailand Fleischerzeugnisse In Kraft seit 18/12/2018 Datum der Veröffentlichung 05/12/2018 00223 Liste in Kraft 02 Thai Q.P. Co., Ltd Ban Pong Ratchaburi 03 CPF (Thailand) Public Co., Ltd.

More information

Mountain Valley Pipeline, LLC Mountain Valley Pipeline Project Docket No. CP

Mountain Valley Pipeline, LLC Mountain Valley Pipeline Project Docket No. CP 16. Prior to construction, Mountain Valley shall file with the Secretary, for review and approval by the Director of OEP, a segment-specific construction and operation access plan for the area between

More information

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS

P U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS P U B L I C N O T I C E MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application 10-07-C-00-MBS INTRODUCTION: This Public Notice is issued as part of a Federal Aviation

More information

ASEAN-India Cross Border Connectivity via Thailand-Myanmar. Myanmar-India Trilateral Highways (Progress, Challenges, and Opportunities)

ASEAN-India Cross Border Connectivity via Thailand-Myanmar. Myanmar-India Trilateral Highways (Progress, Challenges, and Opportunities) International Conference on Cross-Border Connectivity The Claridges, New Delhi 12 May 2014 Session I: Emerging scenario of cross-border connectivity projects ASEAN-India Cross Border Connectivity via -

More information

THAILAND. Volunteer Program

THAILAND. Volunteer Program CONTENTS 1. INTRODUCTION 2. ACCOMMODATION 3. PROJECT: BRIEF DESCRIPTION 4. PROGRAM SERVICES 5. SAMPLE PROGRAMME ITINERARY 6. EXPERIENCE & SIDE TRIPS 7. FLIGHTS & INSURANCE 8. MAP OF INTRODUCTION Well known

More information

ДРЖАВА ОДДЕЛ. Тајланд. [mk] Validity date from 28/03/2018 Дата на објавување 15/03/2018. Листа на сила

ДРЖАВА ОДДЕЛ. Тајланд. [mk] Validity date from 28/03/2018 Дата на објавување 15/03/2018. Листа на сила ДРЖАВА ОДДЕЛ Тајланд [mk] Validity date from 28/03/2018 Дата на објавување 15/03/2018 00221 Листа на сила 02 Thai Q.P. Co., Ltd Ban Pong Ratchaburi 03 CPF (Thailand) Public Co., Ltd. Min Buri Bangkok 05

More information

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library EAST DON TRAIL ENVIRONMENTAL ASSESSMENT Community Liaison Committee Meeting #3 July 15, 2013 6:30 to 8:30 pm Flemingdon Park Library Agenda 1. Welcome 2. Housekeeping and Updates a) Housekeeping b) CLC

More information

communication tower means a tower or structure built to support equipment used to transmit communication signals;

communication tower means a tower or structure built to support equipment used to transmit communication signals; Ontario Ministry of Natural Resources Subject Communication Tower Sites on Crown Land Compiled by - Branch Lands & Waters Section Land Management Policy PL 4.10.02 Replaces Directive Title Communication

More information

ACTION TRANSMITTAL

ACTION TRANSMITTAL Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED

More information

White Mountain National Forest Saco Ranger District

White Mountain National Forest Saco Ranger District United States Department of Agriculture Forest Service White Mountain National Forest 33 Kancamagus Highway Conway, NH 03818 Comm: (603) 447-5448 TTY: (603) 447-3121 File Code: 1950 Date: February 26,

More information

Summary of Group Discussions 1 st Local Community Meeting

Summary of Group Discussions 1 st Local Community Meeting Summary of Group Discussions 1 st Local Community Meeting The Study on Implementation of the BMA Subcenters Program In the Kingdom of Thailand (Case of Lat Krabang) July 9, 2005 at Conference Room, KMIT

More information

INDUSTRIAL PROPERTY GUIDE

INDUSTRIAL PROPERTY GUIDE INDUSTRIAL PROPERTY GUIDE CONTENTS Strategic choice Investment incentives Choice of locations Industrial Estates Industrial Parks/Zones Green Field Sites Industrial Promotion Zone BOI Incentives and Privileges

More information

Corporate Presentation Financial Results Ended December 31, March 13, 2013

Corporate Presentation Financial Results Ended December 31, March 13, 2013 Corporate Presentation Financial Results Ended December 31, 2012 March 13, 2013 1 Highlights 2012 Financial Results EGCO Group s Overview 2012 Highlights 2012 Financial Results EGCO Group s Overview 2

More information

Daily Report on Water Situation in rainy season 2014 On Wednesday 18 June Weather Situation

Daily Report on Water Situation in rainy season 2014 On Wednesday 18 June Weather Situation Current Situation : Office Hours : 8.3 16.3 Water Watch and Monitoring System for Warning Center Royal Irrigation Department, Ministry of Agriculture and Cooperatives Tel: 2669 256 Fax 2243 6965, 2241

More information

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. Connecting People Building Opportunities 198 Brisbane Airport Corporation CHAPTER 10

More information

By Mr natthaphong wongjai. NetwortofCiviitSociety-MaeHongson

By Mr natthaphong wongjai. NetwortofCiviitSociety-MaeHongson By Mr natthaphong wongjai. NetwortofCiviitSociety-MaeHongson Mae Hong Son Province. Located in the north west to the north of Thailand. Most of Bangkok, which is in the north. A distance of approximately

More information

Policy PL Date Issued February 10, 2014

Policy PL Date Issued February 10, 2014 Subject RENEWABLE ENERGY ON CROWN LAND Compiled by Renewable Energy Program, Biodiversity Branch Replaces Policy Directives Waterpower Site Release Crown Land Onshore Windpower Development - Crown Land

More information

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651)

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) TDD (651) DATE: March 27, 2012 METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN 55101 Phone (651) 602-1000 TDD (651) 291-0904 TO: Metropolitan Parks and Open Space Commission FROM: Arne Stefferud, Planning

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: KENNEDY INTERCHANGE STATION: METROLINX EGLINTON CROSSTOWN LIGHT RAIL TRANSIT PROJECT - PRELIMINARY CONCEPT

More information

Mukdahan is one of the north-eastern provinces of Thailand. Neighboring provinces

Mukdahan is one of the north-eastern provinces of Thailand. Neighboring provinces Mukdaharn Province (Thailand) Geography Mukdahan is one of the north-eastern provinces of Thailand. Neighboring provinces are (from south clockwise) Amnat Charoen, Yasothon, Roi Et, Kalasin, Sakon Nakhon

More information

MATL Reference. MATL Path 83 Transfer Capability with Seasonal SOL Effects. Document. 1. Purpose

MATL Reference. MATL Path 83 Transfer Capability with Seasonal SOL Effects. Document. 1. Purpose 1. Purpose This document outlines the transfer capability on MATL Path 83 for both long-term capability and for current seasonal capabilities adjusted for known System Operating Limits (SOLs), such as

More information

Bloor Street West Rezoning Application for a Temporary Use By-law Final Report

Bloor Street West Rezoning Application for a Temporary Use By-law Final Report STAFF REPORT ACTION REQUIRED 3741 3751 Bloor Street West Rezoning Application for a Temporary Use By-law Final Report Date: June 12, 2007 To: From: Wards: Reference Number: Etobicoke York Community Council

More information

Insurance: Accident Third Party covering up a maximum of: 10,000,000 baht per accident.

Insurance: Accident Third Party covering up a maximum of: 10,000,000 baht per accident. Introducing our Non inclusive Northern Thailand Motorcycle tour. This is our three corners of Thailand tour. This is a 23 day 22 night adventure. This ride will take us from the north heading south and

More information

Part 9 MAINTENANCE MANUAL. Distribution Construction Standards Handbook

Part 9 MAINTENANCE MANUAL. Distribution Construction Standards Handbook Part 9 MAINTENANCE MANUAL Distribution Construction Standards Handbook General Notes: The Maintenance Manual (MM series) is a collection of drawings for superseded construction standards. These can be

More information

Hugo Klingenberg Senior Manager Network Development ElectraNet Adelaide, South Australia Lodged via

Hugo Klingenberg Senior Manager Network Development ElectraNet Adelaide, South Australia Lodged via Hugo Klingenberg Senior Manager Network Development ElectraNet Adelaide, South Australia 5000 Lodged via email consultation@electranet.com.au. Friday, 21 July 2017 Dear Mr Klingenberg, RE: Eyre Peninsula

More information

M A T L Reference. MATL Path 83 Transfer Capability with Seasonal SOL Affects. Document. 1. Purpose

M A T L Reference. MATL Path 83 Transfer Capability with Seasonal SOL Affects. Document. 1. Purpose 1. Purpose This document outlines the Transfer Capability on MATL Path 83 for both long-term capability and for current seasonal capabilities adjusted for known System Operating Limits (SOLs), such as

More information

[BA] COUNTRY [BA] SECTION. [ba] Thailand. [ba] Validity date from 23/10/2013 [ba] Date of publication 18/10/2013. [ba] List in force

[BA] COUNTRY [BA] SECTION. [ba] Thailand. [ba] Validity date from 23/10/2013 [ba] Date of publication 18/10/2013. [ba] List in force [BA] COUNTRY [BA] SECTION [ba] Thailand [ba] Validity date from 23/10/2013 [ba] Date of publication 18/10/2013 00121 05 CPF (Thailand) Public Co., Ltd. Nong Jok Bangkok 06 Laemthong Food Products Co.,

More information

WELCOME TO NATIONWIDE AIRPORT MEDIA

WELCOME TO NATIONWIDE AIRPORT MEDIA WELCOME TO NATIONWIDE AIRPORT MEDIA Airport Insight AVIATION GAME CHANGER FAST GROWING LOW-COST AIRLINE OPERATOR EASY FOR TRAVELING 2002 2003 2004 2006 2010 2012 2013 2014 PRESENT THAILAND is the biggest

More information

AMENDMENT NO. 03 TO THE OFFICIAL PLAN FOR THE TOWNSHIP OF ADJALA-TOSORONTIO OAK RIDGES MORAINE CONSERVATION PLAN

AMENDMENT NO. 03 TO THE OFFICIAL PLAN FOR THE TOWNSHIP OF ADJALA-TOSORONTIO OAK RIDGES MORAINE CONSERVATION PLAN AMENDMENT NO. 03 TO THE OFFICIAL PLAN FOR THE TOWNSHIP OF ADJALA-TOSORONTIO OAK RIDGES MORAINE CONSERVATION PLAN Adopted by Council July 19 th, 2004 Approved with modifications by the Province of Ontario

More information

Finn Creek Park. Management Direction Statement Amendment

Finn Creek Park. Management Direction Statement Amendment Finn Creek Park Management Direction Statement Amendment November 2013 Management Direction Statement Amendment Approved by: Jeff Leahy Regional Director, Thompson Cariboo BC Parks November 12, 2013 Date

More information

CIVIL AVIATION AUTHORITY

CIVIL AVIATION AUTHORITY CIVIL AVIATION AUTHORITY INFRASTUCTRE DEVELOPMENT: BOTTLENECKS AND SOLUTIONS IN AVIATION SECTOR by the Presentation to the ICPAU 5 th Economic Director Finance, Civil Aviation Authority, U 20 July Overview

More information

Current Activities of BRI in Lao PDR

Current Activities of BRI in Lao PDR Current Activities of BRI in Lao PDR Vanxay Sayavong, National Consultant, DESA National Workshop at National Institute for Economic Research (NIER) 6 th November 2018, Vientiane Content Background Current

More information

SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1

SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1 Air Transport Connectivity Enhancement Project (RRP BHU 44239-013) SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1 Sector Road Map 1. Sector Performance,

More information

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the

More information

Northfield to Ingle Farm #2 66 kv Sub transmission line

Northfield to Ingle Farm #2 66 kv Sub transmission line Header Reasonableness Test RT 011/11 Northfield to Ingle Farm #2 66 kv Sub transmission line RT011-11 Northfield to Inglefarm Page 1 of 8 Reasonableness Test: Northfield to Ingle Farm 66 kv line DISCLAIMER

More information

THAI AIRWAYS INTERNATIONAL PCL

THAI AIRWAYS INTERNATIONAL PCL THAI AIRWAYS INTERNATIONAL PCL PHATRA SECURITIES PCL Thai Tourism Day July 4, 2013 1 http://www.thaiairways.com/about-thai/investor-relations/en/investor.html DISCLAIMER The information contained herein

More information

Grounding Clamp. Pins and Ball-Socket Clamps for Temporary Grounding

Grounding Clamp. Pins and Ball-Socket Clamps for Temporary Grounding Grounding Clamp Pins and Ball-Socket Clamps for Temporary Grounding Pins and Ball-Socket Clamps have been designed to solve several temporary grounding situations, where the physical space or the contact

More information

TWENTY-SECOND MEETING OF THE ASIA/PACIFIC AIR NAVIGATION PLANNING AND IMPLEMENTATION REGIONAL GROUP (APANPIRG/22)

TWENTY-SECOND MEETING OF THE ASIA/PACIFIC AIR NAVIGATION PLANNING AND IMPLEMENTATION REGIONAL GROUP (APANPIRG/22) INTERNATIONAL CIVIL AVIATION ORGANIZATION TWENTY-SECOND MEETING OF THE ASIA/PACIFIC AIR NAVIGATION PLANNING AND IMPLEMENTATION REGIONAL GROUP (APANPIRG/22) Bangkok, Thailand, 5-9 September 2011 Agenda

More information

1. Thailand has four biosphere reserves which located in different parts of the country. They are as follows;

1. Thailand has four biosphere reserves which located in different parts of the country. They are as follows; Country Report on MAB programme : Kingdom of Thailand The MAB National Committee of Thailand In occasion of 26th Session of the International Co-ordinating Council of the Man and the Biosphere Programme

More information

The Boeing Company forecasts a market for the Asia-Pacific region of about 8,960 new airplanes worth US$1,130 billion for the 2009 to 2028 period.

The Boeing Company forecasts a market for the Asia-Pacific region of about 8,960 new airplanes worth US$1,130 billion for the 2009 to 2028 period. Aircraft Maintenance 2010 Update Situated in the heart of Asia, Thailand is gearing up to become a full-service hub and major player in the region s multi-billion dollar aircraft maintenance industry.

More information

Baan Dada Children's Home Cycling for Education. Read article about this charity event here.

Baan Dada Children's Home Cycling for Education. Read article about this charity event here. April 2012 1-6 Sunday thru Friday : Northern Thailand Princess Maha Chakri Sirindhorn's Cup Tour of Thailand 2012. International multi-stage road race in the Thailand provinces of Chiang Rai, Lampang,

More information