1 DTW Class B Airspace Redesign Proposal Presented for Informal Public Meetings, July 20-22, 2010 Presented to: Informal Public Meetings By: John Hoelscher, Lockheed Martin Date: July 20-22, 2010
2 The current design of the Detroit Metro (DTW) Class B Airspace does not allow for aircraft containment as required by FAA directives. 2 2
3 The Detroit Class B Airspace was originally designed in the 1970s and implemented as a Terminal Control Area (TCA). Since then the Detroit TRACON (D21) airspace and the DTW Airport have both gone through extensive changes while the Class B has remained unchanged. 3 3
4 In the mid 1980s, due to demand, Detroit TRACON (D21) began utilizing simultaneous ILS procedures (SILS) as the primary instrument approach configuration The requirements for these procedures are such that the aircraft must be established on their respective final no less than 17 miles from the runway This forces the traffic pattern out of the lateral limit of the Detroit Class B to the northeast when landing 22/21 and to the southwest when landing 4/3 4 4
5 In 1993 runway 27L opened allowing for SILS approaches when on a west flow Again the traffic pattern extends well beyond the lateral limits of the current Class B design. 5 5
6 In 2001 runway 22R opened creating two more issues First, there were no modifications to the Class B allowing for the new final approach courses being as far west as they are 6 6
7 Second, Having created the third parallel ILS approach, D21/DTW will begin utilizing triple ILS approaches These procedures require that aircraft be established on the final no less than 21 miles from the runway. 7 7
8 Beginning December of 2006, D21/DTW began receiving numerous user complaints about the traffic flows and the inadequate Class B Airspace. Since that time the facility has looked at several ways in which to improve the Class B. 8 8
9 CURRENT DTW CLASS B AIRSPACE 9 9
10 PROPOSED DTW CLASS B AIRSPACE: 10 10
11 Simultaneous ILS Approaches In each of the following flows none of the arrival patterns are fully contained in the Class B These illustrations show the optimal traffic pattern At our higher demand levels and/or less than ideal wind conditions, these patterns are stretched even further 11 11
12 Triple ILS Approaches With the introduction of Precision Runway Monitor (PRM) procedures and the design of triple ILS approaches, the current Class B is even less effective The points at where aircraft are required to be established on the final are beyond what is displayed
13 The Detroit Metro Airport has two main configurations, north and south Additionally, there is a west flow which is used approximately seven to ten percent of the time in strong winds All of these configurations were analyzed for compatibility with the proposed design All existing arrival and departure routes remain the same
14 Proposed DTW Class B Airspace South Flow Traffic Patterns 14 14
15 Current DTW Class B Airspace North Flow Traffic Patterns Proposed DTW Class B Airspace North Flow Traffic Patterns 15 15
16 Current DTW Class B Airspace West Flow Traffic Patterns 16 16
17 New 10,000 MSL ceiling is due to the current traffic patterns at D21 Traffic used to enter the D21 airspace at 8,000 MSL With changes to aircraft characteristics and airspace, traffic now enters D21 airspace at 11,000 and 12,
18 Mail responses to : Mr. Roger McGrath FAA ATO Central Service Center Operations Support Group, AJO-2C Meacham Blvd. Fort Worth, Texas roger.mcgrath@faa.gov 18 18
Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update
Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update Ultimate ASV, Runway Use and Flight Tracks 4th Working Group Briefing 8/13/18 Meeting Purpose Discuss Public Workshop input
More informationMilton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.
Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet
More informationDraft Concept Alternatives Analysis for the Inaugural Airport Program September 2005
Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 1 - Introduction This report describes the development and analysis of concept alternatives that would accommodate
More information** DETERMINATION OF NO HAZARD TO AIR NAVIGATION **
Mail Processing Center Federal Aviation Administration Southwest Regional Office Obstruction Evaluation Group 2601 Meacham Boulevard Fort Worth, TX 76137 Issued Date: 05/16/2011 Aeronautical Study No.
More informationThe purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration
Chapter 4 Page 65 AIRPORT DEMAND CAPACITY The purpose of this Demand/Capacity Analysis is to examine the capability of the Albert Whitted Airport (SPG) to meet the needs of its users. In doing so, this
More informationSaint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis
Saint Petersburg-Clearwater International Airport Airspace & Instrument Approach Analysis February 23, 2005 Jeppesen Boeing Jeppesen Government / Military Services Group Airspace Services Division AIRSPACE
More informationSUMMARY: This action establishes Class E airspace at Parkston, SD. Controlled airspace
This document is scheduled to be published in the Federal Register on 07/12/2013 and available online at http://federalregister.gov/a/2013-16436, and on FDsys.gov [4910-13] DEPARTMENT OF TRANSPORTATION
More informationCHAPTER 1 INTRODUCTION AND BACKGROUND
CHAPTER 1 INTRODUCTION AND BACKGROUND An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance with the National
More informationUSA Near-Term Progress for Closely Spaced Parallel Runways
2005 The MITRE Corporation. All rights reserved. USA Near-Term Progress for Closely Spaced Parallel Runways Wakenet 2 Europe November 30, 2005 This is the copyright work of The MITRE Corporation, and was
More informationAccording to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:
4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity
More informationTown of East Hampton Airport 200 Daniel s Hole Road Wainscott, NY
Town of East Hampton Airport 200 Daniel s Hole Road Wainscott, NY 11975 631.537.1130 2014 Noise Abatement The following Helicopter Noise Abatement Procedures have been developed in collaboration with the
More information** DETERMINATION OF NO HAZARD TO AIR NAVIGATION **
Federal Aviation Administration Air Traffic Airspace Branch, ASW-520 2601 Meacham Blvd. Fort Worth, TX 76137-0520 Aeronautical Study No. 2010-WTE-13969-OE Issued Date: 09/30/2010 Morgan Johnston University
More informationFederal Aviation Administration. Air Traffic 101. By: Michael Valencia & Dianna Johnston Date: Feb. 26, 2017
Presented to: UC Davis Aviation Symposium By: Michael Valencia & Dianna Johnston Date: Overview Part 1 Air Traffic Controllers History Safety and Navigation Terminology Air Traffic Facility Types Equipment
More informationSUMMARY: This action amends Class D airspace at Wichita, McConnell AFB, KS. The
This document is scheduled to be published in the Federal Register on 09/23/2014 and available online at http://federalregister.gov/a/2014-22508, and on FDsys.gov [4910-14] DEPARTMENT OF TRANSPORTATION
More informationNavigation at the. Federal Aviation Administration Crossroads
Navigation at the Crossroads To: Stanford 2010 PNT Symposium By: Leo Eldredge GNSS Program Manager Date: Peak Aircraft Traffic Over The US 5000 aircraft 689 M passengers 36 B pounds cargo 2 If We Do Nothing
More informationPRE-LEASING KDTO. Denton Enterprise Airport ±15,500 SF CORPORATE HANGAR FACILITY. West Court Drive Denton Texas UNDER CONSTRUCTION OCT 2018
PRE-LEASING UNDER CONSTRUCTION OCT 2018 ±15,500 SF CORPORATE HANGAR FACILITY Denton Enterprise Airport UNDER CONSTRUCTION (PRE-LEASING) 12,000 SF CORPORATE HANGAR (120' WIDE x 100' DEEP) SCHWEISS HYDRAULIC
More informationDEMAND/CAPACITY ANALYSIS St. Petersburg-Clearwater International Airport
DEMAND/CAPACITY ANALYSIS St. Petersburg-Clearwater International Airport 5.1 GENERAL OVERVIEW The next step in the Master Plan process is analyzing the capacity of existing airport facilities against forecasted
More informationTechnical Report. Aircraft Noise Analysis. Portola Valley and Woodside, California. July Prepared by: Aircraft Noise Abatement Office
Technical Report Aircraft Noise Analysis Portola Valley and Woodside, California Prepared by: San Francisco International Airport P.O. Box 8097 San Francisco, California 94128 (650) 821-5100 Introduction
More informationVATUSA C90 TRACON AND O HARE ATCT LETTER OF AGREEMENT
VATUSA C90 TRACON AND O HARE ATCT LETTER OF AGREEMENT EFFECTIVE: 02/01/2019 SUBJECT: INTERFACILITY COORDINATION 1. PURPOSE: This agreement establishes coordination procedures and defines delegation of
More informationPart 150 Update Status and Recommendation
Part 150 Update Status and Recommendation Presentation to: Noise Compatibility Committee October 26, 2010 Ted Baldwin 2 Topics Part 150 background Project status Noise Exposure Map Noise Compatibility
More informationRaleigh-Durham International Airport Airport Capacity Enhancement Plan. August 1991
ii Raleigh-Durham International Airport Airport Capacity Enhancement Plan August 1991 Prepared jointly by the U.S. Department of Transportation, Federal Aviation Administration, Raleigh-Durham Airport
More informationNextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures
NextGen: New Technology for Improved Noise Mitigation Efforts: DFW RNAV Departure Procedures DFW International Airport Sandy Lancaster, Manager Noise Compatibility October 13, 2008 OUTLINE About DFW Airport
More informationAPPENDIX H 2022 BASELINE NOISE EXPOSURE CONTOUR
APPENDIX H 2022 BASELINE NOISE EXPOSURE CONTOUR This appendix sets forth the detailed input data that was used to prepare noise exposure contours for 2022 Baseline conditions. H.1 DATA SOURCES AND ASSUMPTIONS
More informationKHND MEDIUM. Henderson Executive Airport Las Vegas, Nevada, United States. Diagram #1: Airport Map All Aircraft Categories / All Runways
Diagram #1: Airport Map http://whispertrack.com/airports/ p. 1 of 5 Diagram #2: Abatement Chart http://whispertrack.com/airports/ p. 2 of 5 OVERVIEW To reduce noise over adjacent residential areas, please
More informationEast Hampton Airport (KHTO) Noise Abatement Plan 2016 Prepared by the Eastern Region Helicopter Council
East Hampton Airport (KHTO) Noise Abatement Plan 2016 Prepared by the Eastern Region Helicopter Council DRAFT Original 1 The following presentation has been prepared by the Eastern Region Helicopter Council
More informationOverview of Boston Logan Operations and Noise from Overflights. Presentation to Massport Board March 19, 2015
Overview of Boston Logan Operations and Noise from Overflights Presentation to Massport Board March 19, 2015 Contents How the Airport Operates Massport s Noise Abatement Program for Logan Recent Trends
More informationAIRPORT COMPLIANCE th Texas Aviation Conference. 3/29/2018 Date. Footer Text
AIRPORT COMPLIANCE 2018 36 th Texas Aviation Conference 3/29/2018 AWOS FCC LICENSE RENEWAL Needs renewal every 10 years (renew 90 days before expiration). Needs update if there is name change, coordinate
More informationOperational Demonstration of a Performance-Based Separation Standard at The Hartsfield-Jackson Atlanta International Airport
Operational Demonstration of a Performance-Based Separation Standard at The Hartsfield-Jackson Atlanta International Airport Implementation and Benefits of Equivalent Lateral Spacing Operation (ELSO) Departures
More informationVATUSA PHOENIX TRACON and VATUSA PHOENIX ATCT LETTER OF AGREEMENT. SUBJECT: Interfacility Coordination Procedures
VATUSA PHOENIX TRACON and VATUSA PHOENIX ATCT LETTER OF AGREEMENT EFFECTIVE: 01/08/08 SUBJECT: Interfacility Coordination Procedures 1. PURPOSE. This Letter of Agreement establishes procedures for coordinating
More informationNOISE COMPLAINT HOTLINE
206 ANNUAL NOISE COMPLAINT HOTLINE REPORT Introduction The Columbus Regional Airport Authority (CRAA) owns and operates John Glenn Columbus International (CMH), Rickenbacker International (LCK) and Bolton
More informationChapter 4 Airport Facility Requirements
Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT
More informationCharlotte - Douglas International
Charlotte - Douglas International Standard Operating Procedures CLT TRACON 7110.65D Effective: May 1, 2011. 1 CHAPTER 1. Departure/Satellite Radar SECTION 1. EQUIPMENT 1-1-1. Callsign Usage and Frequency
More informationAnalysis of ATM Performance during Equipment Outages
Analysis of ATM Performance during Equipment Outages Jasenka Rakas and Paul Schonfeld November 14, 2000 National Center of Excellence for Aviation Operations Research Table of Contents Introduction Objectives
More informationKSFO RNAV TO GLS DEMONSTRATION
Delta Air Lines - Noah Flood GLS GLS DTT 1.9 DTT 1.9 GLS1 GLS1 KSFO RNAV TO GLS DEMONSTRATION Key Components Three Key Components 1. Global Navigation Satellite System A. GPS/Galileo/GLONASS 2. Ground
More informationBurlington ATCT Standard Operating Procedures
This air traffic control procedural document is provided for virtual air traffic control in the ZBW ARTCC of the VATSIM network only. It is not for real-world ATC use. These procedures are approved for
More informationReliever Airports: NOISE ABATEMENT PLAN Flying Cloud Airport (FCM)
Reliever Airports: NOISE ABATEMENT PLAN Flying Cloud Airport (FCM) INTRODUCTION The Noise Abatement Plan (FCM Plan) for the Flying Cloud Airport has been prepared in recognition of the need to make the
More informationPreliminary Findings of Proposed Alternative
Preliminary Findings of Proposed Alternative The attached drawing provides a schematic layout of the proposed alternative that will be discussed on July 27, 2010. A full report will follow and should be
More informationNOTAM AIRCRAFT OWNERS AND PILOTS ASSOCIATION (AOPA) FLY-IN CHINO AIRPORT (CNO) CHINO, CALIFORNIA
NOTAM AIRCRAFT OWNERS AND PILOTS ASSOCIATION (AOPA) FLY-IN CHINO AIRPORT (CNO) CHINO, CALIFORNIA EFFECTIVE 12:00 NOON LOCAL FRIDAY, SEPTEMBER 19, 2014 UNTIL 6:00 PM LOCAL SATURDAY, SEPTEMBER 20, 2014 TEMPORARY
More informationZTL ARTCC. Asheville Regional. Air Traffic Control Tower. Standard Operating Procedures AVL B. Effective: May 1, 2011
ZTL ARTCC Asheville Regional Air Traffic Control Tower Standard Operating Procedures AVL 7110.65B Effective: May 1, 2011 CHAPTER 1. GENERAL CONTROL SECTION 1. EQUIPMENT 1 1-1-1. Callsign Usage and Frequency
More informationContinuous Descent? And RNAV Arrivals
Continuous Descent? And RNAV Arrivals From an ATC Perspective Presentation to: CDA Workshop GA Tech Name: Don Porter RNP Project Lead FAA, RNAV RNP Group Date: 18 April 2006 My Background 22 years Terminal
More informationTable of Contents. Overview Objectives Key Issues Process...1-3
Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5
More information1) Rescind the MOD (must meet the standard); 2) Issue a new MOD which reaffirms the intent of the previous MOD; 3) Issue a new MOD with revisions.
ALBUQUERQUE INTERNATIONAL SUNPORT AIRCRAFT HOLD LINE LOCATION ANALYSIS WHITE PAPER JUNE 24, 2016 HOLD LINE LOCATION ISSUE The location of many of the taxiway hold lines at the Sunport do not meet current
More information** DETERMINATION OF NO HAZARD TO AIR NAVIGATION **
Mail Processing Center Federal Aviation Administration Southwest Regional Office Obstruction Evaluation Group 2601 Meacham Boulevard Fort Worth, TX 76137 Issued Date: 01/04/2012 Aeronautical Study No.
More informationAir Traffic Control & Management
Air Traffic Control & Management To fully understand the varying performance characteristics of aircraft, it is necessary to understand certain elements of the environment in which they operate. The performance
More informationExecutive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport
Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche
More informationHOBART AIRSPACE DESIGN
HOBART AIRSPACE DESIGN RICHMOND COMMUNITY Airservices has undertaken a review of the Hobart Airport Standard Instrument Departures (SIDs) and Standard Instrument Arrivals (STARs) for Runway 12 and Runway
More informationAviation Safety Information Analysis and Sharing ASIAS Overview PA-RAST Meeting March 2016 ASIAS Proprietary Do Not Distribute
Aviation Safety Information Analysis and Sharing ASIAS Overview PA-RAST Meeting March 2016 ASIAS Proprietary Do Not Distribute Updated: March 2016 2 12 How can safety be improved in an environment of near-zero
More informationHOBART AIRSPACE DESIGN
HOBART AIRSPACE DESIGN SORELL COMMUNITY Airservices has undertaken a review of the Hobart Airport Standard Instrument Departures (SIDs) and Standard Instrument Arrivals (STARs) for Runway 12 and Runway
More informationAppendix C AIRPORT LAYOUT PLANS
Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development
More informationAmendment of Restricted Areas R-3004A and R-3004B and Establishment of R-3004C;
This document is scheduled to be published in the Federal Register on 09/25/2017 and available online at https://federalregister.gov/d/2017-20435, and on FDsys.gov 4910-13 DEPARTMENT OF TRANSPORTATION
More informationLAX Community Noise Roundtable Work Program A1 Review of SoCal Metroplex Proposed Procedures and Suggestions for Comment Letter.
LAX Community Noise Roundtable Work Program A1 Review of SoCal Metroplex Proposed Procedures and Suggestions for Comment Letter July 8, 2015 Southern California Metroplex Environmental Assessment Presentation
More informationKey Purpose & Need Issues
Key Purpose & Need Issues Efficiently meet demand through the 2025 planning horizon 864,000+ annual operations 180-200 operations during peak daytime hours Balance peak hour arrival/departure capability
More informationSTAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D
STAFF REPORT SUBJECT: Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan MEETING DATE: AGENDA ITEM: 7D STAFF CONTACT: Peter Imhof, Andrew Orfila RECOMMENDATION: Adopt findings
More informationSECTION 4 DEMAND/CAPACITY ANALYSIS AND FACILITY REQUIREMENTS
SECTION 4 DEMAND/CAPACITY ANALYSIS AND FACILITY REQUIREMENTS This Section compares the projected demand and the existing capacity for the major elements of the Airport and establishes the facility requirements
More informationStandard Operating Procedures Atlanta Intl Airport (ATL) Air Traffic Control
SUBJ: Air Traffic Control This order prescribes air traffic control procedures and phraseology for use by personnel providing air traffic control services. Controllers are required to be familiar with
More informationOperational Authorization Process for ILS Precision Runway Monitor (PRM) and Simultaneous Offset Instrument Approach (SOIA)
GOVERNMENT OF INDIA CIVIL AVIATION DEPARTMENT DIRECTOR GENERAL OF CIVIL AVIATION OC NO 4 OF 2016 Date: 29 th February 2016 OPERATIONS CIRCULAR File No AV 22024/20/2015-FSD Subject: Operational Authorization
More informationSafety Enhancement 186R3.2 TCAS-Sensitivity Level Command
Safety Enhancement Action: Statement of Work: Total Relation to Current Aviation Community Initiatives: Performance Goal Indicators: Key Milestones: Safety Enhancement 186R3.2 TCAS-Sensitivity Level Command
More informationRedesign Traffic Routes Review the Present Route Structure and Procedures for Inefficiencies
AIRSPACE DESIGN 7 AIRSPACE DESIGN 7 7 AIRSPACE DESIGN This chapter describes the FAA s initiatives to increase airspace capacity by restructuring airspace. Airspace issues may be identified from within
More informationChapter 3. Demand/Capacity & Facility Requirements
Chapter 3. Demand/Capacity & Facility Requirements Chapter 3. DEMAND/CAPACITY & FACILITY REQUIREMENTS This chapter provides an assessment of future airport development requirements based upon the forecasts
More informationACTION TRANSMITTAL
Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL 2018-16 DATE: February 9, 2018 TO: Transportation Advisory Board FROM: Technical Advisory Committee PREPARED
More informationForecast of Aviation Activity
DETROIT METROPOLITAN WAYNE COUNTY AIRPORT FAR PART 150 NOISE COMPATIBILITY STUDY UPDATE CHAPTER B FORECAST OF AVIATION ACTIVITY Forecast of Aviation Activity Introduction This chapter summarizes past aviation
More informationOperators may need to retrofit their airplanes to ensure existing fleets are properly equipped for RNP operations. aero quarterly qtr_04 11
Operators may need to retrofit their airplanes to ensure existing fleets are properly equipped for RNP operations. 24 equipping a Fleet for required Navigation Performance required navigation performance
More information[Docket No. FAA ; Airspace Docket No. 13-ASW-2] Proposed Amendment of Class E Airspace; Fort Polk, LA
This document is scheduled to be published in the Federal Register on 04/30/2013 and available online at http://federalregister.gov/a/2013-10169, and on FDsys.gov [4901-13] DEPARTMENT OF TRANSPORTATION
More information9/23/2010 RDU B. Raleigh-Durham Air Traffic Control Tower. Standard Operating Procedures
Raleigh-Durham Air Traffic Control Tower Standard Operating Procedures 1) Purpose This order defines duties and responsibilities, depicts areas of airspace, runways, and taxiways allocated to each position
More informationAirlake Airport 2035 Long Term Comprehensive Plan (LTCP)
Airlake Airport 2035 Long Term Comprehensive Plan (LTCP) Public Informational Meetings August 9 & 10, 2017 Draft LTCP Overview Briefing Agenda Airport Role & Context Existing Conditions & Previous Plan
More informationDenver ARTCC Colorado Springs ATCT & TRACON STANDARD OPERATING PROCEDURES
Denver ARTCC Colorado Springs ATCT & TRACON STANDARD OPERATING PROCEDURES OCTOBER 7, 2018 Definition of Airspace Colorado Springs Class C airspace is defined as show in Appendix 1. Definition of Positions
More informationEUROCOPTER FRANCE
Page 1 2009-22-04 EUROCOPTER FRANCE Amendment 39-16055 Docket No. FAA-2009-0952; Directorate Identifier 2009-SW-04-AD PREAMBLE Effective Date (a) This airworthiness directive (AD) becomes effective on
More information1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION
1.1.3 Taxiways EWN has an extensive network of taxiways and taxilanes connecting the terminal, air cargo, and general aviation areas with the runways as listed in Figure 1-15. A 50-foot wide parallel taxiway
More informationLas Vegas McCarran International Airport. Capacity Enhancement Plan
Las Vegas McCarran International Airport Capacity Enhancement Plan Las Vegas McCarran International Airport Capacity Enhancement Plan September 1994 Prepared jointly by the U.S. Department of Transportation,
More informationAirport Safety Management Systems: Integrating Planning Into the Process
Airport Safety Management Systems: Integrating Planning Into the Process Kenneth Jacobs Senior Airport Planner FAA Airport Planning and Environmental Division ken.jacobs@faa.gov SMS Defined A process for
More informationThe following criteria shall be applied within the boundaries of the AO District:
Sec. 419 (a) Purpose AIRPORT OVERLAY DISTRICT (AO) The purpose of the Airport Overlay District is to regulate and restrict the height of structures, objects, or natural growth, regulate the locations of
More informationNextGen Priorities: Multiple Runway Operations & RECAT
NextGen Priorities: Multiple Runway Operations & RECAT May 2018 Presented by Paul Strande & Jeffrey Tittsworth Federal Aviation Administration National Airspace System Today Air traffic services for the
More informationPLAN Anoka County - Blaine Airport
Reliever Airports: NOISE ABATEMENT PLAN Anoka County - Blaine Airport INTRODUCTION The noise abatement plan for the Anoka County-Blaine Airport was prepared in recognition of the need to make the airport
More informationRecommended Performance Measures
Recommended Performance Measures January 2009 1 RECOMMENDED PERFORMANCE MEASURES Performance measures are utilized by the North Central Texas Council of Governments (NCTCOG) to monitor the performance
More informationThis section sets forth all Los Angeles World Airports (LAWA) noise abatement procedures, restrictions, and regulations involving aircraft operations.
This section sets forth all Los Angeles World Airports (LAWA) noise abatement procedures, restrictions, and regulations involving aircraft operations. 13.1. Aircraft Noise Abatement 13.1.1. All aircraft
More informationPTK AIR TRAFFIC CONTROL TOWER OPERATION GOOD CHEER PROCEDURES 2018 (rev A, 12/05/18)
PTK AIR TRAFFIC CONTROL TOWER OPERATION GOOD CHEER PROCEDURES 2018 (rev A, 12/05/18) TABLE OF CONTENTS GENERAL INFORMATION.. 1 o Phone Numbers o Frequencies PREFLIGHT PLANNING o IFR Aircraft 2 o VFR Aircraft.3
More informationProposed Establishment of and Modification to Restricted Areas; Fort Sill, OK
This document is scheduled to be published in the Federal Register on 10/19/2015 and available online at http://federalregister.gov/a/2015-26499, and on FDsys.gov 4910-13 DEPARTMENT OF TRANSPORTATION Federal
More informationMASTER PLAN UPDATE GRANT NUMBER
T MASTER PLAN UPDATE D R AF GRANT NUMBER 3-48-0062-42 MAY 2015 1. Introduction... 1-1 1.1 History of Dallas Love Field... 1-1 1.2 Airport Setting... 1-2 1.2.1 DALLAS-FORT WORTH-ARLINGTON METROPOLITAN STATISTICAL
More informationAtlanta NextGen PBN Activities
Atlanta NextGen PBN Activities Presentation to: Name: Date: EWG Ops SC Meeting Jim Arrighi RNAV/RNP Group Jim Allerdice A80 May 18, 2010 0 0 Atlanta Performance Based Navigation Project Planning Seven
More informationMinneapolis-St. Paul International Airport (MSP)
2 nd Quarter 2016 Minneapolis-St. Paul International Airport (MSP) Public Input Meeting Metropolitan Airports Commission Noise Program Office April 27, 2016 PUBLIC INPUT MEETING Meeting Goals To hear the
More informationKBLI MEDIUM. Bellingham Intl Airport Bellingham, Washington, United States. Diagram #1: All Runways. NOISE ABATEMENT PROCEDURES by Whispertrack
Diagram #1: p. 1 of 5 Diagram #2: p. 2 of 5 OVERVIEW Bellingham International Airport (BLI) is a full service commercial airport located in Whatcom County, approximately 3 miles N.W. of the city limits
More informationFACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW
FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW This summary is intended to provide a brief overview of the key issues associated with conformance to FAA standards at Methow Valley State Airport.
More informationChapter 6. Nonradar. Section 1. General DISTANCE
12/10/15 JO 7110.65W Chapter 6. Nonradar Section 1. General 6 1 1. DISTANCE Use mileage based (DME and/or ATD) procedures and minima only when direct pilot/controller communications are maintained. FIG
More informationDallas Love Field Community Weekly Update
DALLAS LOVE FIELD COMMUNITY WEEKLY UPDATE October 18-October 24, 2014 Dallas Love Field Community Weekly Update FOR OUR LITTLE PASSENGERS-THE LIL LOVE LOUNGE IS LOCATED IN THE STEM OF THE TERMINAL IN THIS
More informationUpdates to Procedures at St. John s International Airport
October 10, 2017 Updates to Procedures at St. John s International Airport This document provides notice of upcoming changes to instrument procedures being implemented by NAV CANADA at the St. John s International
More informationFrom: Commanding Officer, Naval Air Station Pensacola. Subj: NAVAL AIR STATION PENSACOLA CLOSED CONTROL TOWER AIRFIELD OPERATIONS
DEPARTMENT OF THE NAVY COMMANDING OFFICER NAS PENSACOLA 150 HASE ROAD STE-A PENSACOLA, FLORIDA 32508-1051 NAVAL AIR STATION PENSACOLA INSTRUCTION 3710.1 NASPCOLAINST 3710.1 N32 From: Commanding Officer,
More informationIndianapolis International Airport Capacity Enhancement Plan
Indianapolis International Airport Capacity Enhancement Plan 2 Indianapolis International Airport Capacity Enhancement Plan Indianapolis International Airport Capacity Enhancement Plan May 1993 Prepared
More informationSUMMARY: This action amends Class B airspace at the Louis Armstrong New Orleans
This document is scheduled to be published in the Federal Register on 07/20/2015 and available online at http://federalregister.gov/a/2015-17709, and on FDsys.gov 4910-13 DEPARTMENT OF TRANSPORTATION Federal
More informationPierre Regional Airport Airport Master Plan. Kickoff Meeting April 7, 2017
Pierre Regional Airport Airport Master Plan Kickoff Meeting April 7, 2017 Agenda Introductions Airport Master Planning Planning Considerations Master Plan Elements Schedule Public Involvement Basics about
More informationAgenda: SASP SAC Meeting 3
Agenda: SASP SAC Meeting 3 Date: 04/12/18 Public Involvement Plan Update Defining the System Recommended Classifications Discussion Break Review current system Outreach what we heard Proposed changes Classification
More informationCHAPTER FOUR RECOMMENDED NOISE COMPATIBILITY PROGRAM MEASURES
CHAPTER FOUR RECOMMENDED NOISE COMPATIBILITY PROGRAM MEASURES This chapter provides the detailed descriptions of the recommended Part 150 noise abatement, land use management, and program management measures
More informationNoise Programs & NextGen Briefing. Stan Shepherd, Manager Airport Noise Programs
Noise Programs & NextGen Briefing Stan Shepherd, Manager Airport Noise Programs 1 Presentation Overview Noise Information Hotline Increased Operations Economic Impacts Noise Contours Noise Mitigation Programs
More information2 Purpose and Need. 2.1 The Need for the CLT OAPM Project Description of the Problem
2 Purpose and Need Under NEPA, an Environmental Assessment (EA) must describe the purpose and need for the Proposed Action. The following sections discuss the need for the Proposed Action and provide specific
More informationFEDERAL AVIATION ADMINISTRATION CENTRAL EN ROUTE AND OCEANIC AREA OPERATIONS FORT WORTH ARTC CENTER, MAJORS ATCT, AND SKYDIVE TANDEM GREENVILLE, LLC
FEDERAL AVIATION ADMINISTRATION CENTRAL EN ROUTE AND OCEANIC AREA OPERATIONS FORT WORTH ARTC CENTER, MAJORS ATCT, AND SKYDIVE TANDEM GREENVILLE, LLC LETTER OF AGREEMENT Effective: April 10,2012 SUBJECT:
More informationGreenville Spartanburg International
ZTL ARTCC Greenville Spartanburg International Airport Traffic Control Tower Standard Operating Procedures GSP 7110.65B Effective: May 1, 2011 1 CHAPTER 1. GENERAL CONTROL SECTION 1. EQUIPMENT 2-1-1. Callsign
More informationAppendix A. Meeting Coordination. Appendix A
Appendix A Meeting Coordination Appendix A Philadelphia International Airport Noise Compatibility Program Update FAR Part 150 Noise Compatibility Program Update Report Prepared by: DMJM Aviation AECOM
More informationPaul Clayton Air New Zealand
Paul Clayton Air New Zealand External Threats Expected Events and Risks Unexpected Events and Risks External Error Internal Threats Crew-Based Errors CRM Behaviors Threat Recognition and Error Avoidance
More informationEstimating the Effects of the Terminal Area Productivity Program
NASA Contractor Report 0168 Estimating the Effects of the Terminal Area Productivity Program David A. Lee, Peter F. Kostiuk, Robert V. Hemm, Earl R. Wingrove III, and Gerald Shapiro Logistics Management
More informationProject Consultant (PC) Alternative 5 Runway 22R/L RNAV Departures
VIA E-MAIL Date: To: From: Subject: Boston Technical Advisory Committee (BOS/TAC) Project Consultant (PC) Alternative 5 Runway 22R/L RNAV Departures At the February 17, 2006 BOS/TAC meeting several issues
More informationProposed Amendment of Class D and E Airspace; Kansas City, MO; and Revocation of
This document is scheduled to be published in the Federal Register on 02/01/2018 and available online at https://federalregister.gov/d/2018-01795, and on FDsys.gov [4910-13] DEPARTMENT OF TRANSPORTATION
More information