PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony Henday Drive (NEAHD) Project. Council History June 12, 2012 - Council was given a verbal presentation by Bill Van der Meer, Alberta Transportation. June 11, 2013 - Council was given a verbal presentation by Bill Van der Meer, Alberta Transportation. Strategic Plan Priority Areas Economy: n/a Governance: n/a Social: Increased vehicular mobility Culture: Users of regional transportation system Environment: n/a Other Impacts Policy: n/a Legislative/Legal: n/a Interdepartmental: Transportation and Agriculture Services, Capital Planning and Construction, Utilities, Planning and Development Services Summary Alberta Transportation has initiated construction of the northeast leg of the Anthony Henday Drive project. Transportation and Agriculture Services is the County s first point of contact and liaison with Alberta Transportation. The role of Transportation and Agriculture Services is to assist Alberta Transportation in minimizing the impact to County residents and County infrastructure during the construction project. Construction commenced in June 2012, and will impact the County road users at most major connection points with Anthony Henday (Highway 216) and Highway 16 until completion in 2016. Enclosure I Northeast Anthony Henday Drive Powerpoint (Document: 5950089) Document : 5974560 Page 1 of 1
Enclosure I Northeast Anthony Henday Drive Northeast Anthony Henday Drive Updatete Priorities Committee Meeting May 13, 2014 Transportation and Agriculture Services Ryan Wilson Manager, Transportation Infrastructure Alberta Transportation Bill Van der Meer Urban Construction Manager Edmonton Document: 5950089
Project Background 2
Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest opened 2006 Southeast opened 2007 Completion of the Northeast section will make Anthony Henday Drive the first complete ring road around a Canadian city. 3
Project Scope And Progress 4
Project Scope 27 kilometres of freeway: Anthony Henday Drive, from Whitemud Drive to Yellowhead Trail 9km of reconstructed freeway Anthony Henday Drive, from Yellowhead Trail to Manning Drive 9km of new freeway Yellowhead Trail, east of the river to east of Sherwood Drive 6km of reconstructed freeway Sherwood Park Freeway, west of 17 St to Ordze Crescent 3km of reconstructed freeway 9 interchanges 2 flyovers 47 bridges (includes NSR crossing) 24 stormwater ponds 103 overhead signs 5
Manning Drive 3 new bridge structures Paving of already graded east leg to be completed as part of NEAHD N Progress to date Girders installed on two bridges Third bridge underway Granular basecourse placed on mainline 6
CN Crossings Six flyovers at Coronado and Vegreville CN crossings Progress to date Girders installed on the six rail flyovers Mainline grading complete 7
18 Street/Victoria Trail Twin underpasses Future alignment of Victoria Trail Future alignment of LRT Progress to date 18 Street temporarily closed Bridge construction underway Mainline grading complete Manning Drive Interchange CN Coronado flyovers N 8
153 Avenue New grade-separated interchange in greenfield 1 new bridge structure N Progress to date Girders installed Mainline grading completed 9
North Saskatchewan River Crossing New four-span twin bridge structures across the North Saskatchewan River N 10
North Saskatchewan River Crossing Progress to date Girders installed on south half of both bridges Berm removed from south side and constructed on north side 11
EWMC 130 Avenue/Aurum Road Meridian Street New grade-separated interchange 1 new bridge structure Access to EWMC and gravel operations to be maintained Meridian Street Progress to date Girders installed on bridge Granular basecourse placed on mainline Temporary detour along service road and 130 Avenue Temporary detour N 12
CN Railway/Hayter Road Two new flyovers Progress to date Temporary detour along service road Bridge construction underway N 13
Yellowhead Trail Systems Interchange 11 new bridge structures on 3 elevations New major, multi-level, freeflow interchange replacing existing service interchange Progress to date Construction of various bridges underway Grading underway 14
Yellowhead Trail/Broadmoor Boulevard Existing parclo interchange to be replaced. 1 new bridge structure Progress to date Minor grading and utility works N 15
Yellowhead Trail/Sherwood Drive Existing right-in-right-out intersection to be replaced with new grade-separated interchange 1 new bridge structure Progress to date Girders installed Grading underway N 16
Petroleum Way Underpass Evacuation route for Petro Canada refinery Road to be widened with grading for 4 lanes; 2 lanes paved in Stage 1 Existing bridge culvert structure to be removed and replaced with new ultimate stage bridges Progress to date Northbound Henday traffic detoured to southbound side 17
Baseline Road/101 Avenue N Reconstruction of existing interchange Signalized ramp intersection 3 new bridge structures Progress to date Signalization of ramps Eastbound traffic detoured to westbound side Demolition of one bridge Northbound traffic detoured to southbound side Girders installed on two new bridges 18
Sherwood Park Freeway/17 Street Existing half diamond New full diamond interchange 2 new bridge structures Progress to date Demolition of 76 Avenue bridge Minor grading work N Piling 19
Sherwood Park Freeway Completely new Parclo interchange Elevated Directional EB-NB ramp 4 new bridge structures N Progress to date Westbound traffic detoured to eastbound side Demolition of one bridge Girders installed on two new bridges 20
Whitemud Drive Resurfacing of existing cloverleaf interchange Addition of one lane on SB-WB ramp Progress to date Minor maintenance work N 21
2014 Program 22
2014 Program Completion of Anthony Henday from Manning Drive to 153 Ave Re-opening of 18 Street Permanent closure of Fort Road/167 Ave intersection Completion of girders on the river bridges 23
2014 Program Completion of new Baseline Road bridge and demolition of existing bridge Completion of new Sherwood Park Freeway bridge and demolition of existing bridge Pavement rehabilitation of Whitemud interchange 24
2014 Program Detour to Waste Management Centre using 130 Ave bridge ramps Completion of Sherwood Drive interchange Temporary detour of Yellowhead along CD roads Temporary closure of Broadmoor Boulevard bridge 25
2014 Program Yellowhead Detour Key features Broadmoor Yellowhead EB closed between detoured onto existing NB-EB new CD roads and SB-WB ramps Anthony Henday Broadmoor Boulevard Yellowhead WB detoured onto Yellowhead EB and new CD roads Sherwood Drive 26
2014 Program Yellowhead Detour Key features Free-flow Right Temporary link Sherwood Drive in/right out at from Service interchange is Broadmoor/ Road to fully operational Yellowhead EB Yellowhead WB Anthony Henday Broadmoor Boulevard Sherwood Drive 27
2014 Program Yellowhead Detour Eastbound Yellowhead to southbound Broadmoor East along CD road detour Right at Broadmoor Anthony Henday Broadmoor Boulevard Sherwood Drive 28
2014 Program Yellowhead Detour Eastbound Yellowhead to northbound 17 Street Anthony Henday East along CD road detour Left at Sherwood Drive Across bridge over Yellowhead North along RR232 West along 121 Ave Broadmoor Boulevard Sherwood Drive 29
2014 Program Yellowhead Detour Westbound Yellowhead to southbound Broadmoor No direct route Alternative routes south are Clover Bar Road, Sherwood Drive or Anthony Henday Drive Anthony Henday Broadmoor Boulevard Sherwood Drive 30
2014 Program Yellowhead Detour Westbound Yellowhead to northbound 17 Street Exit ramp at Sherwood Drive North along RR232 West along 121 Ave Anthony Henday Broadmoor Boulevard Sherwood Drive 31
2014 Program Yellowhead Detour Northbound Broadmoor to northbound 17 Street Anthony Henday East along CD road Left at Sherwood Drive Across bridge over Yellowhead North along RR232 West along 121 Ave Broadmoor Boulevard Sherwood Drive 32
2014 Program Yellowhead Detour Northbound Broadmoor to eastbound Yellowhead East along CD road Ramp onto Yellowhead Anthony Henday Broadmoor Boulevard Sherwood Drive 33
2014 Program Yellowhead Detour Northbound Broadmoor to westbound Yellowhead Anthony Henday East along CD road Left at Sherwood Drive Across bridge over Yellowhead Left down ramp onto Yellowhead West along CD road detour Broadmoor Boulevard Sherwood Drive 34
2014 Program Yellowhead Detour Southbound 17 Street to southbound Broadmoor No direct route Alternative routes south are Sherwood Drive or Anthony Henday Drive Anthony Henday Broadmoor Boulevard Sherwood Drive 35
2014 Program Yellowhead Detour Southbound 17 Street to eastbound Yellowhead Anthony Henday East along 121 Ave Right at RR232 Across Yellowhead Bridge Left down ramp onto Yellowhead Broadmoor Boulevard Sherwood Drive 36
2014 Program Yellowhead Detour Southbound 17 Street to westbound Yellowhead East along north service road Right down temporary ramp onto Yellowhead Anthony Henday Broadmoor Boulevard Sherwood Drive 37
2014 Program Yellowhead Detour Conditions for closure of Broadmoor Bridge There must be a minimum of 2 lanes on southbound Broadmoor Boulevard and dedicated left and right turn bays at Pembina Road and Strathmoor Drive Anthony Henday Broadmoor Boulevard Sherwood Drive interchange must be complete Sherwood Drive 38
2014 Program Yellowhead Detour Conditions for closure of Broadmoor Bridge Two lanes of traffic The Westcan Temporary in each direction on signals at access must be Yellowhead detour realigned with RR232/121 Ave with a speed limit of must be 121 Ave 80kph installed Anthony Henday Broadmoor Boulevard Sherwood Drive 39
Project information 40
Project Costs Net present value $1.81B Largest provincial road contract ever Previous Alberta Projects Northwest Ring Road $1,420M net present value Southeast Ring Road $497M net present value Northeast Stony Trail $651M net present value 41
Challenges Construction on existing roads 15 rail crossings North Saskatchewan River crossing 500+ identified potential utility conflicts including major pipelines 42
Detour Standards Yellowhead Trail, Anthony Henday Drive - 2 lanes each direction at all times Baseline Road, Sherwood Park Freeway, Broadmoor Boulevard, Sherwood Drive, Whitemud Drive 2 lanes each direction at all times All other roadways 1 lane each direction at all times 43
The Team Client Owner - Alberta Transportation Owner's Engineer - ISL Engineering Concessionaire Capital City Link Group Partnership (CCLGP) Design/Build Contractor Team Flatiron Dragados Aecon Lafarge (FDAL) AECOM, Stantec and MMM Operations/Maintenance Volker Stevin 44
Any Questions? 45