Preferred Options Report

Size: px
Start display at page:

Download "Preferred Options Report"

Transcription

1 Preferred Options Report Preferred Options Report Executive Summary A5 Western Transport Corridor June 2009 Produced for Roads Service Western Division Prepared by Andrew Heap Deputy Project Manager Project Office: Mouchel Shorefield House 30 Kinnegar Drive Holywood County Down Northern Ireland BT18 9JQ T F E andrew.heap@mouchel.com

2 Document Control Sheet Project Title A5 Western Transport Corridor Report Title Preferred Options Report - Executive Summary Revision 1 Status Draft Control Date 23 rd June 2009 Record of Issue Issue Status Author Date Check Date Authorised Date 1 Draft A. Heap P.G. Edwards A. Campbell Distribution Organisation Contact Copies Roads Service Conor Loughrey 2 1

3 Contents 1 Introduction Introduction to the Scheme Background to the Scheme Existing Conditions Sectional Split of A5WTC Sources of Information Existing Conditions Section 1 New Buildings to South of Strabane Existing Conditions Section 2 South of Strabane to South of Omagh Existing Conditions Section 3 South of Omagh to Aughnacloy Development of Preferred Corridor to Preferred Route Development Methodology Preferred Corridor to Preferred Route Focus of Assessment Assessment Process Engineering Process Environment Process Description of Route Options Initial Route Option Assessment Route Options for Assessment Route Development Assumptions 15 2

4 3.6.2 Section Section Section Route Assessment Section 1 Engineering Assessment (Chapter 4 of the Main Report) Section 1 Environmental Assessment (Chapter 5 of the Main Report) Section 2 Engineering Assessment (Chapter 6 of the Main Report) Section 2 Environmental Assessment (Chapter 7 of the Main Report) Section 3 Engineering Assessment (Chapter 8 of the Main Report) Section 3 Environmental Assessment (Chapter 9 of the Main Report) Cost Estimates and Economics Selection of the Preferred Route Section 1 Preferred Route Section 2 Preferred Route Section 3 Preferred Route Cost Estimate and Benefit to Cost Ratio (BCR) Cost Estimate Benefit to Cost Ratio (BCR) Conclusions and Recommendations Conclusions Recommendations

5 1 Introduction 1.1 Introduction to the Scheme Proposals to upgrade the A5 between Londonderry and Aughnacloy have featured prominently in recent strategy documents produced by the Department for Regional Development. In July 2007, the Irish Government indicated its intention to make available a contribution of 400m to help fund major roads programmes in Northern Ireland, providing dual carriageway standards on routes serving the Northwest Gateway and Eastern Seaboard Corridor from Belfast to Larne. The Northern Ireland Executive has confirmed its acceptance, in principle, to taking forward these two major roads projects, which have been included in the Investment Delivery Plan (IDP) for Roads, which was published in April A number of milestones have been agreed, the first of which was the announcement of the Preferred Corridor in late A further milestone is the announcement of the Preferred Route in July The production of this Preferred Options Report is a key part of the process and includes the rationale and process behind the decisions that contribute to the defining of the Preferred Route. 1.2 Background to the Scheme In September 2001, the Department for Regional Development, of which Roads Service is part, formulated Shaping Our Future: The Regional Development Strategy for Northern Ireland 2025 (RDS). An integral feature of the RDS was the requirement to develop a Regional Transportation Strategy having a vision of a modern, integrated and sustainable transportation system which benefits society, the economy and the environment and which actively contributes to social inclusion and everyone s quality of life. In July 2002, the Assembly approved the strategic direction and underlying principles of the Regional Transportation Strategy for Northern Ireland (RTS). Delivery of the RTS is being progressed through three multi modal transport plans, one of which is the Regional Strategic Transport Network - Transport Plan (RSTN - TP), published in March A number of priority schemes to improve the RSTN were ongoing and appraisal work (based on the Government s five key criteria of environment, safety, economy, accessibility and integration) was undertaken to identify further Strategic Roads Improvement (SRI) schemes for inclusion in the RSTN - TP. Delivery of the RDS received a boost in 2005 with the announcement of the Investment Strategy for Northern Ireland (ISNI). The 16bn strategy set out a high level view of planned investment up to 2015 with proposals for up to 1.4 billion of strategic road improvement schemes. In July 2006, Roads Service published the 4

6 consultation document Expanding the Strategic Road Improvement Programme 2015 which included schemes to the value of the ISNI programme as well as a list of schemes that performed well in assessment but were not affordable within anticipated ISNI funding for the period The strategy has recently evolved further in conjunction with the Northern Ireland Executive s Programme for Government and three year budget plan. In 2008 the Northern Ireland Executive agreed it s first three year Budget and endorsed a revised ten year Investment Strategy, covering the period This strategy includes proposals to invest over 3bn, which includes a contribution of 400m from the Irish Government, in the Northern Ireland roads infrastructure. The RSTN TP has 8 primary objectives including the need to examine access to regional gateways and cross border links with an emphasis on improving connections from the 5 key transport and 4 link corridors. The A5 Western Transport Corridor (A5 WTC) is one of the five Key Transport Corridors and starts in the North West of the province at Londonderry and runs for a distance of 88km south to the border, close to the village of Aughnacloy. The A5 WTC joins the N2 in the Republic of Ireland at the Moy Bridge border crossing and together the A5 and N2 provide a strategic link between Dublin and the North West. Within the extent of the scheme itself there are strategic links between the urban centres of Londonderry, Strabane, Omagh, and Aughnacloy. The existing corridor, in addition, provides crucial links from both Dublin and Northern Ireland to urban centres in County Donegal. In October of 2007 Mouchel were appointed by Roads Service to take the scheme through to Preferred Route Announcement. The first major deliverable of this process, the Preliminary Options Report, was published in October 2008 and is available electronically from the A5WTC website, This Preferred Options Report will report on the conclusions of the Preliminary Options Report and will describe the existing engineering, traffic and environmental status of the Preferred Corridor. It will also detail the various route options available to Roads Service for the improvement of the corridor as well as detailing the results and conclusions of the assessment process that has been undertaken in accordance with Roads Service Policy and Procedure Guidelines (RSPPG) E030 Major Road Improvement Schemes - Inception to Construction and TD 37/93 Scheme Assessment Reporting of the Design Manual for Roads and Bridges (DMRB) Volume 5 Section 1. The key purpose of the report is to compare the different route options and, from those comparisons, to make a recommendation for the Preferred Route. 5

7 2 Existing Conditions 2.1 Sectional Split of A5WTC For the purposes of route option development and assessment the A5WTC has been divided into three sections:- Section 1 New Buildings to South of Strabane Section 2 South of Strabane to South of Omagh Section 3 South of Omagh to Aughnacloy 2.2 Sources of Information In order to establish the existing site conditions, data was gathered from numerous sources including, public records, statutory body records and policies, Roads Service records, desk based studies and site surveys. 2.3 Existing Conditions Section 1 New Buildings to South of Strabane The existing A5 within Section 1 is approximately 21km in length and runs south from New Buildings towards Strabane, initially travelling adjacent to the River Foyle. It passes through Magheramason before continuing in a south-westerly direction round the base of Gortmonly Hill toward the bridge over the Burn Dennet River. South of the river crossing, the A5 continues to traverse between sparsely located residential and commercial properties, while passing through the settlements of Cloghcor and Ballymagorry. The A5 then enters Strabane and continues to an at-grade roundabout junction with connections to Lifford Road (A38) and Railway Street (B73), before crossing the River Mourne. After the river crossing, the A5 enters a roundabout with Bradley Way, before heading along the Strabane Bypass which follows an alignment around the western edge of the town. The A5 then joins Melmount Road at another roundabout at the southern end of Strabane Bypass, before heading south to Sion Mills. There are many natural and man-made constraints along the existing A5 which obstruct upgrading possibilities. These include a number of settlements comprising commercial properties such as shops, filling stations, public houses and housing. The settlements in Section 1 fall within either The Derry Area Plan (2011) or the Strabane Area Plan ( ). There are various cultural, landscape and environmental features both within and surrounding the A5 corridor, such as McKeans Moss and the Rivers Finn and Foyle to the west (and associated floodplain), Strabane Glen, Knockavoe Hill and the West Sperrin Mountains to the east (including the Sperrins Area of Outstanding Natural Beauty). 6

8 North of Strabane, in geotechnical terms, the existing road marks a distinct east west division. To the west of the A5 is the broad flat flood plain of the River Foyle, with extensive sand and gravel but potentially some soft surface soils and localised peat. East of the A5 the ground rises steeply in the foothills of the Sperrins Mountains, formed by ancient metamorphosed sandstones, limestones and mudstones. These mountains are dissected by east-west trending side valleys, some of which are broad with extensive gravel deposits (Burn Dennet Valley) and some of which are very steep sided (Pattens Glen). There are 8 structures (cumulative span greater than 40m) on the existing A5 in Section 1. Existing (24 hour) traffic flows for Section 1 are shown in Figure 2.1 below. 7

9 2.4 Existing Conditions Section 2 South of Strabane to South of Omagh In Section 2, the existing A5 carriageway is approximately 31km in length. It runs through Sion Mills along the west of the Mourne River outside the Preferred Corridor. South of Sion Mills the A5 re-enters the Preferred Corridor for a length of 1km. The road then follows the meander of the Mourne River where it passes through the village of Victoria Bridge and intersects with the B165 (Clady to Douglas Bridge Road) before exiting the corridor again. Between Victoria Bridge and Newtownstewart the existing A5 runs in close proximity to the western banks of the Mourne and Strule Rivers before bypassing the local town of Newtownstewart. North of Newtownstewart the B164 (Deerpark Road) joins the A5 at Lower Deerpark. Newtownstewart Bypass, which opened in 2002, follows a route to the north and east of the town where it is intersected by the B46 (Plumbridge Road). The bypass crosses the Strule River twice before tying back into the original A5 to the south-east of the town. South of Newtownstewart, the road continues to run in close proximity to the western banks of the River Strule steadily rising to the site of the Ulster American Folk Park. From here the level of the existing A5 generally falls continuing south past Poe Bridge before entering the outskirts of Omagh. The A5 then passes through the urban areas within Omagh and, as such, is outside the Preferred Corridor. There are many natural and man-made constraints along the existing A5 which obstruct upgrading possibilities. These include a number of settlements comprising commercial properties such as shops, filling stations, public houses and housing. The settlements in Section 2 fall within either The Strabane Area Plan ( ) or the Omagh Area Plan ( ). There are various cultural, landscape and environmental features both within and surrounding the A5 corridor, such as the Strule River, the Owenkillew River, Harry Avery s Castle, Grange Wood, Bessy Bell, the Sperrins AONB, Fairy Water and Tully Bog SAC. In geotechnical terms, north of Newtownstewart, the valley system is broad with widespread deposits of sand and gravel (that have been extensively worked), though south of Newtownstewart the valley is narrow and steep sided, with existing roads benched onto the slopes. At the edges of the valley, the ground (formed of the same ancient sandstone/mudstone/limestone strata) rises steeply into the Sperrins and Bessy Bell. There are extensive sands, gravels and alluvial clay associated with the river floodplains which have been proved to be up to 25m deep at Strabane and Newtownstewart. Elsewhere, the bedrock is covered by a variable thickness (generally thinnest or absent on the high ground) of stony glacial clays. 8

10 South of Mountjoy the terrain changes from the steep sided mountains & valleys with ancient bedrocks to a more open, lower-lying character. Around Omagh, the glacial clays are largely much thicker and there are a series of drumlins present (mounds of stony clay) and the hollows between them are likely to be affected by soft clays and peats. There are 14 significant structures (cumulative span greater than 40m) on the existing A5 in Section 2. Existing (24 hour) traffic flows in Section 2 are shown in Figure 2.2 below. 9

11 2.5 Existing Conditions Section 3 South of Omagh to Aughnacloy In Section 3, the existing A5 carriageway is approximately 32km in length. It runs from Doogary (south-west of Omagh) to the border south of Aughnacloy, joining the proposed N2 in the Republic of Ireland. From Doogary it travels south east and passes to the north east of Gortaclare. It continues through Garvaghy to the east of Garvaghy Big Hill until it joins the A4 (Annaghilla Road) at the Ballygawley Roundabout. The existing road then continues in a south-easterly direction to Aughnacloy before joining the existing N2 at Moy Bridge. There are natural and man-made constraints along the existing A5 which obstruct upgrading possibilities, including a number of settlements comprising commercial properties such as shops, filling stations, pubs and housing. The settlements in Section 3 fall within either Omagh Area Plan ( ) or the Dungannon & South Tyrone Area Plan (2010). There are various cultural, landscape and environmental features both within and surrounding the A5 corridor, such as a broad rounded ridge that forms part of the Brougher Mountains, Clogher Park, Errigal Kerrogue, The Thistle and Favour Royal. In geotechnical terms, between Omagh and Ballygawley, the ground rises gently up the north slope of a ridge of Carboniferous age purple sandstone/conglomerate. These rocks are likely to be very close to surface, though there are local pockets of gravel and clay with (especially south of Omagh) peat covering them. The crest of the ridge at Slievemore is also covered by blanket peat. The south facing slopes of the ridge are very steep but are dissected by several narrow valleys, which have been utilised as the existing north-south road corridors. South of the Slievemore Ridge, the Clogher Valley and the area round Aughnacloy is a second well developed drumlin field, with steep sided clay drumlins up to 20m high, though the hollows in between are infilled with soft clays and peat. This area is crossed by the 100m wide floodplains of the Ballygawley Water and the River Blackwater, which are expected to consist of soft clays with some gravel. There are 9 significant structures (cumulative span greater than 40m) on the existing A5 in Section 3. 10

12 Existing (24 hour) traffic flows in Section 3 are shown in Figure 2.3 below. 11

13 3 Development of Preferred Corridor to Preferred Route 3.1 Development Methodology Preferred Corridor to Preferred Route Following announcement of the Preferred Corridor, the development of the Preferred Route was carried out in accordance with the flow chart in Fig 3.1 below. Preferred Corridor identified Review aerial photographs and update constraints information Review constraints to eliminate areas where route options cannot be developed Identify and develop route options Public Consultation February 2009 Undertake initial route option assessments and consider public/stakeholder comments Develop routes within retained sections Determine full length sectional routes, and undertake further assessments Recommend a Preferred Route Ministerial Announcement Preferred Route Exhibitions 12

14 3.2 Focus of Assessment The primary focus of this assessment is to recommend a Preferred Route that can be developed and progressed through the next stage of assessment. The key objectives of the proposed A5 WTC scheme are: To improve road safety, To improve the road network in the west of the Province and North/South links, To reduce journey travel times along the A5 Western Transport Corridor, To provide increased overtaking opportunities for motorists along the A5 Western Transport Corridor, To develop the final proposals in the light of environmental, engineering, economic and traffic considerations. The purpose of this Stage 2 assessment procedure is to critically evaluate the various routes culminating in the selection of a Preferred Route. 3.3 Assessment Process Engineering Process The Engineering assessment has been undertaken in accordance with the guidance detailed in Roads Service Policy and Procedure Guide (RSPPG) _E030 Major Road Improvement Schemes - Inception to Construction and TD 37/93 Scheme Assessment Reporting of the Design Manual for Roads and Bridges (DMRB) Volume 5 Section Environment Process The Environmental assessment has been undertaken in accordance with the guidance detailed in Volume 11 of the Design Manual for Roads and Bridges (DMRB) (as updated August 2008), and reported in this document in accordance with TD 37/93. Volume 11 provides a framework for taking into account environmental interests and assessing and reporting on environmental impacts and their resultant effects. 13

15 3.4 Description of Route Options Four Route Options were developed and displayed at the Public Consultation Events, held in February 2009, namely:- Brown Route Option Pink Route Option Green Route Option Blue Route Option Plans of these route options are contained on drawing numbers D to D in Appendix A of this Executive Summary. 3.5 Initial Route Option Assessment As part of the assessment process, the route options presented at the February 2009 Public Consultation Events were appraised in consideration of comments received from the public and key stakeholders and against the four criteria of engineering, environment, economics and traffic to assist in the development of routes to be taken forward for Stage 2 Assessment. As a result of this appraisal it was considered that: Routes should not be developed south of the Glenmornan River, within the Brown Route Option in Section 1, on the grounds of impact on the River Foyle and Tributaries SAC, River Foyle floodplain and for reasons of poor traffic transfer. With the exception of the area around Newtownstewart, routes should not be developed within the Brown Route Option in Section 2 on the grounds of poor transfer of traffic from the existing A5, poor connectivity to Omagh and south Strabane, and the significant landscape and visual impacts associated with a new road corridor on the eastern slopes of Bessy Bell. Routes should not be developed south of Newtownstewart to north of Mountjoy, within the Green Route in Section 2, on engineering grounds or around Omagh due to poor connectivity. Routes should not be developed within the Brown Route Option in Section 3 on the grounds of poor transfer of traffic from the existing A5 and poor connectivity to Omagh and the A4 dual carriageway. 14

16 Routes should not be developed north of the A4, within the Blue Route Option, as large sections are coincident with other route options. However, discrete sections could be considered to provide links between the Pink and Green Route Options. 3.6 Route Options for Assessment Route Development Assumptions The following approach to road design was taken when developing routes, for comparison purposes, with reference to Chapter 6 of the Design Manual for Roads and Bridges: Design speed 120kph Dual 2 All-Purpose cross-section Departures from Standard only permitted in exceptional circumstances eg. when incorporating the existing A5 into a route option Minimal use of relaxations permitted by standards eg. gradients up to 8% Grade separation of junctions Side roads generally bridged over or passed under Developing the routes to the above criteria presented a worst case scenario when assessing the engineering and environmental impacts and enabled comparable assessment. Further development of the Preferred Route, to be made after its announcement, will reduce impacts along the road. Other specific aims and considerations when developing routes include: Connectivity to future A5/A6 Link; Connectivity to the main towns and communities including Strabane, Sion Mills, Newtownstewart, Omagh, Fintona, Ballygawley and Aughnacloy; Consideration of links to the N14 and N15 in County Donegal; Consideration of links to the N2 in County Monaghan; Consideration of the local road network required as roads are crossed by the route options; 15

17 Minimization of loss of residential and commercial properties and community facilities; and Avoidance, where possible of significant statutory undertakers apparatus Section 1 As a result of the above the following routes were developed in Section 1 for assessment:- Purple Route; Black Route; Pink Route; Green Route It should be noted that new colours for routes were used when combinations of sections of route options were utilised. A plan of these routes is contained on drawing numbers D and D in Appendix A of this Executive Summary Section 2 As a result of the above the following routes were developed in Section 2 for assessment:- Yellow Route; Black Route; Red Route; Purple Route. It should be noted that new colours for routes were used when combinations of sections of route options were utilised. A plan of these routes is contained on drawing numbers D and D in Appendix A of this Executive Summary. 16

18 3.6.4 Section 3 As a result of the above the following routes were developed in Section 3 for assessment:- Green Route Pink Route Purple Route; Red Route. It should be noted that new colours for routes were used when combinations of sections of route options were utilised. A plan of these routes is contained on drawing numbers D and D in Appendix A of this Executive Summary. 17

19 4 Route Assessment 4.1 Section 1 Engineering Assessment (Chapter 4 of the Main Report) In Section 1 the key issues differentiating the routes in terms of Engineering Assessment are:- Buildability difficulties associated with the Purple and Green Routes; Departures from Standard and Relaxations required on the Purple and Green Routes; The Pink and Black Routes provide greater connectivity to Strabane due to the link to the A38 and the proximity of potential junctions to the border. They also cater for a larger number of local movements in addition to enhancing strategic traffic movements; The Black Route has the shortest additional carriageway requirements to serve the new link to the ROI at Strabane. The Purple and Green Routes require significant additional lengths of carriageway to facilitate the crossing; The Pink and Black Routes may have very large impacts on flooding and the flood plains of the River Finn and River Mourne and require significant lengths of multi-span viaduct; The Green Route requires earthworks of a massive scale (deep rock cuttings); The Pink Route utilises a length of the existing A5 via the Strabane throughpass, which would restrict standards (50mph speed limit) and compromise the scheme objectives in terms of providing a high quality dual carriageway throughout; A junction provided on the Pink and Purple Routes to the south-west of Strabane provides greater connectivity to the south west of the town but requires further development land to do so. The Green Route offers the greatest benefits in terms of journey time savings for strategic traffic but attracts the least volume of traffic; 18

20 4.2 Section 1 Environmental Assessment (Chapter 5 of the Main Report) In Section 1 the key issues differentiating the routes in terms of Environmental Assessment include:- The Purple Route, Black and Pink Routes would have similar impacts on the low lying valley floor west of the existing A5, whilst the Green Route and southern part of the Purple Route would have a severe and significant impact on the landscape character associated with the foothills and tributary valleys that constitute the eastern margin of the Preferred Corridor and that frame the Foyle Valley to the east; Landtake from the Bready Cricket Club at Magheramason under the Green Route; Potential impacts of the Black, Pink and Purple Routes on populations of wildfowl that use the part of the Foyle flood plain known as Grangefoyle; Landtake from McKeans Moss ASSI under the Black, Purple and Pink Routes; The loss of the Grade B1 listed Castletown House under the Black Route; The impact of the Black and Pink Routes on Strabane Canal Scheduled Monument; The Green Route and southern part of the Purple Route would have severe and significant impact on landscape character, particularly east of Strabane; Potential impacts of the Black Route on the internationally designated Special Area of Conservation (SAC) associated with the River Finn, south of Strabane; Potential impacts of the Purple and Green Routes on the landscape, ecology, surface and ground water regimes of the nationally designated Strabane Glen ASSI. 4.3 Section 2 Engineering Assessment (Chapter 6 of the Main Report) In Section 2 the key issues differentiating the routes in terms of Engineering Assessment are:- The Red and Purple Routes have potentially large/very large impacts on flooding and flood plains. 19

21 Buildability difficulties of the Purple and Red Routes around Newtownstewart in terms of required closures of the existing road; Departures from Standard and Relaxations required on the Purple, Red and Yellow Routes; Significant structures will be required, on poor ground, to cross the Strule River at Newtownstewart on both the Purple and Red Routes; Poor ground conditions on significant sections of the Purple Route; The Yellow and Black Routes include earthworks of a large scale; Potential large number of watercourse diversions and culverts associated with the Yellow Route. The Black, Red and Purple Routes offer the better connectivity to Omagh via the existing A5 and A Section 2 Environmental Assessment (Chapter 7 of the Main Report) In Section 2 the key issues differentiating the routes in terms of Environmental Assessment include:- The Yellow and Black Routes would have significant impacts on the setting and amenity value of Harry Avery s Castle; The Red and Purple Routes would have significant impacts on the Pubble Friary and graveyard; The Black and Yellow Route Options are prominently located on the high ground west of Newtownstewart and on the slopes of Bessy Bell whilst the Red and Purple Routes would increase the influence of the existing road corridor in the attractive composition of town and valley below; The Red and Purple Routes would involve the loss of high value woodland at Grange Wood ASSI; The Red and Purple Routes have the potential to impact the aquatic and marginal habitats along a 5km reach of the Owenkillew and Strule Rivers (part of the River Foyle and Tributaries SAC); 20

22 The Black, Red and Purple Routes would have significant impact on an area of well-wooded landscape near Mountjoy, these woodland areas also provide important habitats for protected species; The Black, Red and Purple Routes would result in severance at Mountjoy. 4.5 Section 3 Engineering Assessment (Chapter 8 of the Main Report) In Section 3 the key issues differentiating the routes in terms of Engineering Assessment are:- Buildability difficulties of the Purple and Pink Routes in areas close to the existing A5; Departures from Standard and numerous Relaxations, due to topography and alignment, would be required on the Purple and Pink Routes; Remoteness of Green Route affects accessibility for construction purposes; Large cuttings (up to 21m deep) associated with the Green and Red Routes; The Green Route has the most potentially large/very large impacts on flooding and flood plains; The Red and Green Routes provide the better connectivity to Fintona via the B46; Poor connectivity of the Green Route to the existing A4 and A Section 3 Environmental Assessment (Chapter 9 of the Main Report) In Section 3 the key issues differentiating the routes in terms of Environmental Assessment include:- The Green and Red Routes would have large adverse impacts on landscape and visual context between Gortaclare/Moylagh and Ballygawley; The Green, Red and Pink Routes encroach on the settlement limits of the hamlets of Gortaclare and Moylagh; The Green and Red Routes both result in a major adverse impact on Errigal Keerogue ecclesiastical site; The Green and Red Routes have the potential to cause significant impacts to bats (European protected species); 21

23 The total number of potential visual receptors is similar for the Green, Pink and Purple Routes, whilst the Red Route would have an impact on a markedly lower number of receptors; The Green Route causes the greatest level of impact on landscape and visual context around Aughnacloy; The Red Route would result in the loss of part of the Lissenderry Golf Course and part of a graveyard to the north of Aughnacloy; The Green Route results in a significant adverse impact on The Thistle Registered Park, Garden and Demesne. 4.7 Cost Estimates and Economics Cost estimates for each route were calculated sectionally, based on a level of design detail suitable for a Stage 2 Assessment, to provide a range of scheme cost estimates that were used for the economic comparison of the various full length routes. These are detailed in the main report. Economic evaluations, based on the aforementioned costs and the calculated benefits for the various full length routes were also carried out and used in to inform the decision on the Preferred Route. Again, these are detailed in the main report. 22

24 5 Selection of the Preferred Route 5.1 Section 1 Preferred Route Following due consideration of the assessments undertaken and reported in Section 4 of this Executive Summary, it is recommended that the following route is selected as the Preferred Route for Section 1. The Purple Route is preferred from the commencement of the scheme south of New Buildings. It continues south before adopting the Black Route, at approximately Chainage 8000, for the remainder of Section 1. The Preferred Route in Section 1 is summarised below: Single carriageway bypass to the west of New Buildings; The dual carriageway starts south of New Buildings; Passes west of Magheramason; Passes east of Bready; Passes between Drumgauty and Magherareagh; Passes west of Cloghcor and Ballymagorry; Skirts the western edge of Strabane town, before heading south-east towards Glebe and Sion Mills. There are proposed junctions at the following locations: J1.1 - Towards the centre of the single carriageway New Buildings Bypass; J1.2 - South end of the single carriageway New Buildings Bypass; J1.3 - North of Strabane on the existing A5; J1.4 - West of Strabane on the A38 (Lifford Road)/existing A5; J1.5 - West of Strabane on B85 (Urney Road). This junction will also accommodate the new Lifford (N14/N15) Link; J1.6 - North-west of Sion Mills on the existing A5. 23

25 A plan of the Section 1 Preferred Route is contained on drawing numbers D and D in Appendix A of this Executive Summary. 5.2 Section 2 Preferred Route Following due consideration of the assessments undertaken and reported in Chapter 4 above, it is recommended that the Black Route should be taken forward as the Preferred Route for Section 2. The Preferred Route in Section 2 is summarised below: Starts between Sion Mills and Glebe; Passes to the west of Seein; Passes to the west of both Newtownstewart and Harry Avery s Castle; Traverses the lower slopes of Bessy Bell before passing to the west of Mountjoy, roughly following the path of the disused railway line; Follows a line close to the western outskirts of Omagh There are proposed junctions at the following locations: J2.1 - Adjacent to Victoria Bridge on the B72 (Fyfin Road); J2.2 - West of Newtownstewart on the B84 (Baronscourt Road); J2.3 - North-west of Omagh with the existing A5; J2.4 - South-west of Omagh on the A32 (Clanabogan Road); For the location of the junction south of Omagh, see section 5.3 below. A plan of the Section 2 Preferred Route is contained on drawing numbers D and D in Appendix A of this Executive Summary. 5.3 Section 3 Preferred Route Following due consideration of the assessments undertaken and reported in Chapter 4 above, it is recommended that the Preferred Route for Section 3 initially follows the alignment of the Red Route as far as the A4 before adopting the Pink Route for the remainder of Section 3. 24

26 The Preferred Route in Section 3 is summarised below: Starts south-east of Omagh at Doogary; Passes west of Moylagh; Passes east of Newtownsaville; Passes west of Garvaghy Big Hill; Passes west of Ballygawley; Passes west of Tullyvar; Passes north of Aughnacloy before bypassing the town to the east; Ties in to the existing A5 north of the border at Moy Bridge with a single carriageway link between the A28 and the existing A5; There are proposed junctions at the following locations: J3.1 - South of Omagh on the existing A5; J3.2 - South-west of Moylagh on the B46 (Moylagh Road); J3.3 - South-west of Ballygawley on the A4 (Annaghilla Road); J3.4 - South east of Aughnacloy on A28 (Caledon Road) A plan of the Section 3 Preferred Route is contained on drawing numbers D and D in Appendix A of this Executive Summary. 25

27 6 Cost Estimate and Benefit to Cost Ratio (BCR) 6.1 Cost Estimate The purpose of the Stage 2 cost estimates is to differentiate between the alternative route options in terms of affordability and scheme economics, and not to set the scheme budget. The rates used for pricing are consistent to each section and no consideration has been given to potential value engineering savings. The Stage 2 cost estimates are based on Q prices and are based on a combination of unit rates and measured quantities. The majority of the pricing information was obtained from analysis of costs for previous and current roads projects in Ireland including A1/N1 Newry Dundalk Link Road, M8/N8 Cullahill to Cashel and A4/A5 Dungannon to Ballygawley. Current market prices were obtained for the surfacing works. The following are included in the Stage 2 cost estimates:- Stage 2 design information; Construction costs; Land costs; Other costs including contractor s overhead and preparation and supervision costs; Risk based on a Monte Carlo type analysis; Optimism Bias applied in accordance with Director of Engineering Memorandum for Major Works Estimates. As described in Section 4 of this Executive Summary, cost estimates for each route were calculated sectionally, based on a level of design detail suitable for a Stage 2 Assessment, to provide a variety of overall scheme cost estimates. Further, more detailed, work was then carried out on the design and cost estimate of the Preferred Route in order to provide a more robust figure for affordability and use in the economic assessment of the Preferred Route. This is work that is normally carried out as the design is developed through Stage 3. The cost estimate for the Preferred Route, based on this work is 844,303, Benefit to Cost Ratio (BCR) An economic evaluation of the Preferred Route based on the above cost, and the calculated benefits arising from the scheme was carried out and provided a Benefit to Cost Ratio (BCR) of

28 7 Conclusions and Recommendations 7.1 Conclusions A plan of the Preferred Route is contained on drawing numbers D to D in Appendix A of this Executive Summary. The cost estimate for the Preferred Route is 844,303,296, which results in a BCR of Recommendations On the basis of the Stage 2 Assessment described in this report, it is recommended that the Preferred Route, shown on drawing numbers D and D in Appendix A of this Executive Summary, be taken forward and progressed through a Stage 3 Assessment (TD 37/93) culminating in the preparation and publication of the Statutory Procedures, including Notice of Intention to Make Vesting Order (NIMVO), Notice of Intention to Make Direction Order (NIMDO) and the Environmental Statement It is also recommended that, in accordance with the Habitats Regulations Assessment, the Appropriate Assessment procedure is completed for all locations where the Preferred Route crosses the River Foyle and Tributaries SAC. Continued liaison with Irish Government officials has ensured that adequate provision has been made for connectivity with the road network in the Republic of Ireland. It is recommended that the cooperative working with Irish Government officials continues with a view to maximising the benefits of the A5 project through delivery of cross border linkages. 27

29 See Separate Folder for Appendix A - Drawings 28

Western Division Interim Report To Derry City and Strabane District Council. 24 th February Berryhill Road, Donemana.

Western Division Interim Report To Derry City and Strabane District Council. 24 th February Berryhill Road, Donemana. Western Division Interim Report To Derry City and Strabane District Council 24 th February 2016 Berryhill Road, Donemana. CONTENTS PAGE Foreword by Divisional Manager 1 Western Division 3 Senior Management

More information

EXPLANATORY STATEMENT

EXPLANATORY STATEMENT THE LONDON TO FISHGUARD TRUNK ROAD (A40) (PENBLEWIN TO SLEBECH PARK IMPROVEMENT) ORDER 200- AND THE LONDON TO FISHGUARD TRUNK ROAD (A40) (PENBLEWIN TO SLEBECH PARK IMPROVEMENT SIDE ROADS) ORDER 200-1.

More information

CHRISTCHURCH MOTORWAYS. Project Summary Statement February 2010

CHRISTCHURCH MOTORWAYS. Project Summary Statement February 2010 CHRISTCHURCH MOTORWAYS Project Summary Statement February 2010 Table of Contents 1. Purpose of Document 2. Strategic Context 3. Benefits 4. Project Scope and Economics 5. Implementation Plan 1 ROADS OF

More information

an engineering, safety, environmental, traffic and economic assessment of each option to inform a preferred route option choice; 3) Development and as

an engineering, safety, environmental, traffic and economic assessment of each option to inform a preferred route option choice; 3) Development and as Page: 42 Infrastructure Services REPORT TO ABERDEENSHIRE COUNCIL COMMITTEE 26 APRIL 2018 A96 ABERDEEN TO INVERNESS DUALLING POSITION STATEMENT 1 Recommendations Aberdeenshire Council is recommended to:

More information

N5 Westport to Bohola Road Project Route Selection Report Volume 1 Main Text

N5 Westport to Bohola Road Project Route Selection Report Volume 1 Main Text Roughan & O Donovan - Faber Maunsell Alliance Volume 1 Main Text Document No:... 07522/RSR Made:... Barry Corrigan Checked:... Morgan Hart Approved:... Jim Thorpe Revision Description Made Checked Approved

More information

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018 Lead officer: Chris Tunstall GCP Director of Transport A10 Foxton level crossing bypass and travel hub 1. Purpose 1.1 The list of

More information

Major Scheme Business Case Summary Report for Programme Entry

Major Scheme Business Case Summary Report for Programme Entry Paper A Heart of South West Local Transport Board Major Scheme Business Case Summary Report for Programme Entry M5 Junction 25, Taunton July 2016 1 SCHEME SUMMARY Scheme Name M5 Junction 25, Taunton Date

More information

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited Gatwick Airport Limited Response to Airports Commission Consultation Appendix 37 Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Further information

More information

N4 Carrick-on-Shannon to Dromod Road Project. 2.1 Introduction

N4 Carrick-on-Shannon to Dromod Road Project. 2.1 Introduction Chapter 2 Need for the Scheme 2.1 Introduction The National Primary Route N4, Dublin to Sligo is a strategic corridor from Dublin to the northwest and border counties (See RCSR 101 in Volume 2). The National

More information

Economic Development Sub- Committee

Economic Development Sub- Committee Report title: Economic Development Sub- Committee Item No. Date of meeting: 24 November 2016 A47 Road Investment Strategy - update Responsible Chief Tom McCabe Executive Director, Community Officer: and

More information

Local Development Scheme

Local Development Scheme Local Development Scheme August 2014 Local Development Scheme (August 2014) / Page 2 Contents Section 1: Introduction Great Yarmouth s Development Plan 4 Section 2: Plan Making Process Public participation

More information

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library

EAST DON TRAIL ENVIRONMENTAL ASSESSMENT. Community Liaison Committee Meeting #3 July 15, :30 to 8:30 pm Flemingdon Park Library EAST DON TRAIL ENVIRONMENTAL ASSESSMENT Community Liaison Committee Meeting #3 July 15, 2013 6:30 to 8:30 pm Flemingdon Park Library Agenda 1. Welcome 2. Housekeeping and Updates a) Housekeeping b) CLC

More information

PSP 75 Lancefield Road. Northern Jacksons Creek Crossing Supplementary Information

PSP 75 Lancefield Road. Northern Jacksons Creek Crossing Supplementary Information PSP 75 Lancefield Road Northern Jacksons Creek Crossing Supplementary Information September 2017 The northern crossing of Jacksons Creek proposed within the Lancefield Road PSP is a key part of the ultimate

More information

PART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT

PART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT PART VIII APPLICATION FOR REVISED SOUTH SIDE TRAFFIC MANAGEMENT WORKS TO FACILITATE LUAS BXD PLANNING REPORT ROADS & TRAFFIC DEPARTMENT NOVEMBER 2012 1.0 INTRODUCTION This report has been prepared in support

More information

Project No Brent Cross, Cricklewood London, UK Phase 1A North RMA

Project No Brent Cross, Cricklewood London, UK Phase 1A North RMA Project No. 431679 Brent Cross, Cricklewood London, UK Phase 1A North RMA River Overshadowing Impact Study For Waterman Energy, Environment & Design 18 th November 2014 431679 Report 2 Rel.3 1 of 23 431679rep2v3.docx

More information

TOWN PLANNING SUBMISSION TO THE GREATER SYDNEY COMMISSION LANDS AT ARTARMON

TOWN PLANNING SUBMISSION TO THE GREATER SYDNEY COMMISSION LANDS AT ARTARMON TOWN PLANNING SUBMISSION TO THE GREATER SYDNEY COMMISSION LANDS AT ARTARMON March 2017 TABLE OF CONTENTS 1.0 INTRODUCTION 3 2.0 THE SUBJECT SITE 4 3.0 STRATEGIC PLANNING CONTEXT 6 4.0 SUMMARY AND CONCLUSIONS

More information

Non-technical summary

Non-technical summary Introduction NTS1 NTS2 NTS3 Troika Developments Ltd (Troika) has submitted a planning application to Bournemouth Borough Council (BBC) for an extension of time to implement planning permission 7/2004/16450/G,

More information

North Herts District Council Local Plan Timeline for Response to Council s Request for Strategic Housing Land Land to the North of the Grange,

North Herts District Council Local Plan Timeline for Response to Council s Request for Strategic Housing Land Land to the North of the Grange, North Herts District Council Local Plan Timeline for Response to Council s Request for Strategic Housing Land Land to the North of the Grange, Letchworth Garden City Introduction As part of central government

More information

The Strategic Commercial and Procurement Manager

The Strategic Commercial and Procurement Manager Item 3 To: Procurement Sub Committee On: 8 June 2016 Report by: The Strategic Commercial and Procurement Manager Heading: Renfrewshire Council s Community Benefit Strategy 2016 1. Summary 1.1. The purpose

More information

Open Report on behalf of Richard Wills, Executive Director for Environment and Economy

Open Report on behalf of Richard Wills, Executive Director for Environment and Economy Agenda Item 7 Executive Open Report on behalf of Richard Wills, Executive Director for Environment and Economy Report to: Executive Date: 02 September 2014 Subject: Lincoln East West Link Road Phase 1

More information

Today we are showing you the early designs to improve the A27 at Arundel and we would like to hear your views on our options.

Today we are showing you the early designs to improve the A27 at Arundel and we would like to hear your views on our options. Welcome Welcome to the Highways England A27 Arundel Bypass public consultation. Thank you for coming. Today we are showing you the early designs to improve the A27 at Arundel and we would like to hear

More information

PLANNING THE SUNBURY GROWTH CORRIDOR

PLANNING THE SUNBURY GROWTH CORRIDOR SUNBURY GROWTH CORRIDOR NOVEMBER 2016 PLANNING THE SUNBURY GROWTH CORRIDOR Sunbury Planning Background The Victorian Planning Authority, in consultation with Hume City Council, is undertaking a number

More information

Perth and Kinross Council Development Control Committee 27 August 2008 Recommendation by Development Quality Manager

Perth and Kinross Council Development Control Committee 27 August 2008 Recommendation by Development Quality Manager Perth and Kinross Council Development Control Committee 27 August 2008 Recommendation by Development Quality Manager 5(7) 08/414 Erection of kennels and cattery at Baltree Farm, Hatchbank, Kinross, KY13

More information

SUMMER VILLAGE OF SILVER SANDS. Municipal Development Plan

SUMMER VILLAGE OF SILVER SANDS. Municipal Development Plan SUMMER VILLAGE OF SILVER SANDS Municipal Development Plan Bylaw 253-2014 Adopted August 22, 2014 Summer Village of Silver Sands Municipal Development Plan Bylaw No. 253-2014 Page 2 1 INTRODUCTION 1.1 SETTING

More information

JOINT CORE STRATEGY FOR BROADLAND, NORWICH AND SOUTH NORFOLK EXAMINATION MATTER 3C EASTON/COSTESSEY

JOINT CORE STRATEGY FOR BROADLAND, NORWICH AND SOUTH NORFOLK EXAMINATION MATTER 3C EASTON/COSTESSEY Matter 3C Easton/Costessey Representor No. 8826 JOINT CORE STRATEGY FOR BROADLAND, NORWICH AND SOUTH NORFOLK EXAMINATION MATTER 3C EASTON/COSTESSEY SUBMISSION ON BEHALF OF TAYLOR WIMPEY DEVELOPMENTS AND

More information

HEAD OF ECONOMIC PROMOTION AND PLANNING Nathan Spilsted, Senior Planning Officer Tel:

HEAD OF ECONOMIC PROMOTION AND PLANNING Nathan Spilsted, Senior Planning Officer   Tel: 7. TRAVELLER SITES ALLOCATIONS DOCUMENT REPORT OF: Contact Officer: Wards Affected: Key Decision: Report to: HEAD OF ECONOMIC PROMOTION AND PLANNING Nathan Spilsted, Senior Planning Officer Email: nathan.spilsted@midsussex.gov.uk

More information

Report Author: Jo Turton, Executive Director for the Environment, Lancashire County Council

Report Author: Jo Turton, Executive Director for the Environment, Lancashire County Council Transport for Lancashire Committee 1 st July 2013 Local Major Transport Scheme Investment Programme Report Author: Jo Turton, Executive Director for the Environment, Lancashire County Council Executive

More information

Level Crossing Risk Assessment Polegate MCB

Level Crossing Risk Assessment Polegate MCB Level Crossing Risk Assessment Polegate MCB Polegate MCB Level Crossing Risk Assessment 1 CONTENTS 1 INTRODUCTION 3 1.1 Background 3 1.2 Reason for the risk assessment 3 2 DESCRIPTION OF THE SITE 4 2.1

More information

1 INFORMATION REQUIREMENTS

1 INFORMATION REQUIREMENTS 1 INFORMATION REQUIREMENTS 1.1 BACKGROUND 2 1.2 WHAT IS THE DISTRICT PLAN 3 1.3 DISTRICT PLAN STRUCTURE 4 1.4 HOW TO USE THE DISTRICT PLAN 5 1.5 STRATEGIC FRAMEWORK 6 Whanganui District Plan (15 January

More information

Committee. Presentation Outline

Committee. Presentation Outline CW-33-15 11/9/2015 Community and Corporate Services Committee November 10, 2015 1 Presentation Outline Background Vision and Objectives Study Process and Timeline Public and Stakeholder Engagement Organization

More information

A21 TONBRIDGE TO PEMBURY DUALLING. Statement of Case

A21 TONBRIDGE TO PEMBURY DUALLING. Statement of Case A21 TONBRIDGE TO PEMBURY DUALLING Statement of Case In Respect of Applications for the Demolition of Listed Buildings Under the Provisions of the Planning (Listed Buildings and Conservation Areas) Act

More information

John Betts School Crossing Review

John Betts School Crossing Review John Betts School Crossing Review Paddenswick Road London Borough of Hammersmith & Fulham August 2015 DOCUMENT CONTROL Project Centre has prepared this report in accordance with the instructions from the

More information

7. CONSULTATION ON THE TRAVELLER SITES ALLOCATIONS DOCUMENT

7. CONSULTATION ON THE TRAVELLER SITES ALLOCATIONS DOCUMENT 7. CONSULTATION ON THE TRAVELLER SITES ALLOCATIONS DOCUMENT REPORT OF: HEAD OF ECONOMIC PROMOTION AND PLANNING Contact Officer: Nathan Spilsted, Senior Planning Officer Email: nathan.splistead@midsussex.gov.uk

More information

PERTH-ADELAIDE CORRIDOR STRATEGY

PERTH-ADELAIDE CORRIDOR STRATEGY INTRODUCTION The Royal Automobile Association of SA Inc (RAA), the State s principal advocate for motorists on a broad range of motoring-related issues, represents the views of more than 560,000 South

More information

SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1

SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1 Air Transport Connectivity Enhancement Project (RRP BHU 44239-013) SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1 Sector Road Map 1. Sector Performance,

More information

Part four. In this part you will find: The next steps to deliver the master plan

Part four. In this part you will find: The next steps to deliver the master plan Part four NEXT STEPS In this part you will find: The next steps to deliver the master plan 6. How COULD the Master Plan be delivered? There are a number of steps required to take the proposals in the master

More information

Seek the Board s approval for the Donald Place kerb and channel renewal to progress to final design, tender and construction; and

Seek the Board s approval for the Donald Place kerb and channel renewal to progress to final design, tender and construction; and 3. DONALD PLACE - KERB AND CHANNEL RENEWAL General Manager responsible: General Manager City Environment Officer responsible: Transport and City Streets Manager Author: Michelle Flanagan, Streets Capital

More information

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan New Plan Acheson Industrial Area Structure Plan Amendment Parkland County Municipal Development Plan Board Reference

More information

London Borough of Barnet Traffic & Development Design Team

London Borough of Barnet Traffic & Development Design Team London Borough of Barnet Traffic & Development Design Team AERODROME ROAD PEDESTRIAN FACILITY AND BUS STOP INTRODUCTION FEASIBILITY REPORT Job Number: 60668 Doc Ref: S106/12-13/60668 Author: Manoj Kalair

More information

Welcome and introduction

Welcome and introduction Welcome and introduction Welcome to this public exhibition. The purpose of the exhibition is to present the preferred option for the Maybole Bypass and explain the need for the scheme, its objectives and

More information

Submission to NSW Koala Strategy Consultation Process. March 2017

Submission to NSW Koala Strategy Consultation Process. March 2017 Submission to NSW Koala Strategy Consultation Process March 2017 Table of contents Opening 3 Response 3 Whole-of-government NSW koala strategy 3 State Environment Planning Policy (SEPP) 44 3 The draft

More information

1.0 Introduction. The paper provides:-

1.0 Introduction. The paper provides:- Local Development Plan Tourism October 2018 1.0 Introduction 1.1 This background paper has been prepared to draw together the evidence base that has been used to inform the preparation of the Fermanagh

More information

Consideration will be given to other methods of compliance which may be presented to the Authority.

Consideration will be given to other methods of compliance which may be presented to the Authority. Advisory Circular AC 139-10 Revision 1 Control of Obstacles 27 April 2007 General Civil Aviation Authority advisory circulars (AC) contain information about standards, practices and procedures that the

More information

ENVIRONMENTAL SCRUTINY COMMITTEE 6 DECEMBER 2016

ENVIRONMENTAL SCRUTINY COMMITTEE 6 DECEMBER 2016 CITY & COUNTY OF CARDIFF DINAS A SIR CAERDYDD ENVIRONMENTAL SCRUTINY COMMITTEE 6 DECEMBER 2016 EASTERN BAY LINK JOINT STUDY PROPOSAL Reason for the Report 1. To provide Members with the opportunity to

More information

PUBLIC CONSULTATION - THE PURPOSE

PUBLIC CONSULTATION - THE PURPOSE PUBLIC CONSULTATION - THE PURPOSE ² To review the sites identified for housing development; ² To introduce new sites that have come forward since the last Public Consultation with potential for housing

More information

1. Summary of key points 2

1. Summary of key points 2 Petitions Committee NEVAR petition: Cardiff Airport access road This brief sets out the history and policy background to the development of proposals for improved surface access to Cardiff Airport (CA).

More information

LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN. Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS

LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN. Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS APPENDIX 15.1-3 LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN Purpose of the Structure Plan Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS LSP-P1 The District

More information

Terms of Reference: Introduction

Terms of Reference: Introduction Terms of Reference: Assessment of airport-airline engagement on the appropriate scope, design and cost of new runway capacity; and Support in analysing technical responses to the Government s draft NPS

More information

Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018

Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018 Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018 Subject: M Arrangements for the establishment of a West Yorkshire Urban Traffic Management Control

More information

CHAPTER 13 Tourism and Recreation. Kildare County Development Plan , Volume 1

CHAPTER 13 Tourism and Recreation. Kildare County Development Plan , Volume 1 Chapter 6 Rural Housing Strategy CHAPTER 13 Tourism and Recreation 197 13 TOURISM AND RECREATION 13.1 Background 13.2 Goal Tourism is one of the growth sectors in our economy. Kildare is rich in natural

More information

20mph Speed Limit Zones

20mph Speed Limit Zones Traffic Advisory Leaflet 7/91 May 1991 20mph Speed Limit Zones Summary This leaflet illustrates the main steps in the procedures for the implementation of 20mph zones. It provides brief details on: the

More information

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content Gold Coast Rapid Transit Chapter twelve Social impact Chapter content Social impact assessment process...235 Existing community profile...237 Consultation...238 Social impacts and mitigation strategies...239

More information

Your guide to. North/South and cross-border TOURISM co-operation

Your guide to. North/South and cross-border TOURISM co-operation Your guide to North/South and cross-border TOURISM co-operation March 2007 About Border Ireland Border Ireland is the first online information system to focus upon improving the understanding of North/South

More information

Establishing a National Urban Park in the Rouge Valley

Establishing a National Urban Park in the Rouge Valley STAFF REPORT ACTION REQUIRED Establishing a National Urban Park in the Rouge Valley Date: March 29, 2012 To: From: Wards: Reference Number: Executive Committee Deputy City Manager, Cluster B All p:\2012\cluster

More information

Calderdale MBC. Wards Affected: Town. Economy and Investment Panel: 20 October Halifax Station Gateway Masterplan

Calderdale MBC. Wards Affected: Town. Economy and Investment Panel: 20 October Halifax Station Gateway Masterplan Calderdale MBC Wards Affected: Town Economy and Investment Panel: 20 October 2016 Halifax Station Gateway Masterplan Report of the Acting Director, Economy and Environment 1. Purpose of the Report 1.1

More information

YORK STREET INTERCHANGE. Public Inquiry. Proof of Evidence:

YORK STREET INTERCHANGE. Public Inquiry. Proof of Evidence: Department for Regional Development - TransportNI YORK STREET INTERCHANGE Public Inquiry Proof of Evidence: (Summary) by Michael Megarry URS Beechill House 40 Beechill Road Belfast BT8 7RP THIS PAGE INTENTIONALLY

More information

Tourism Development Framework for Scotland. Executive Summary- Development Framework to 2020 for the Visitor Economy (Refresh 2016)

Tourism Development Framework for Scotland. Executive Summary- Development Framework to 2020 for the Visitor Economy (Refresh 2016) Tourism Development Framework for Scotland Executive Summary- Development Framework to 2020 for the Visitor Economy (Refresh 2016) Introduction The Tourism Development Framework for Scotland refresh 2016:

More information

Lower Thames Crossing

Lower Thames Crossing Lower Thames Crossing Post-Consultation Scheme Assessment Report Volume 7 Volume 7: Appraisal Summary and Recommendations Lower Thames Crossing 2017 - APPRAISAL SUMMARY AND RECOMMENDATIONS Contents Section

More information

Visual and Sensory Aspect

Visual and Sensory Aspect Updated All Wales LANDMAP Statistics 2017 Visual and Sensory Aspect Final Report for Natural Resources Wales February 2018 Tel: 029 2043 7841 Email: sw@whiteconsultants.co.uk Web: www.whiteconsultants.co.uk

More information

PERTH AND KINROSS COUNCIL. 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS

PERTH AND KINROSS COUNCIL. 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS PERTH AND KINROSS COUNCIL 8 16/278 22 June 2016 DEVELOPING THE CULTURAL OFFER IN PERTH AND KINROSS UPDATE AND NEXT STEPS Report by Senior Depute Chief Executive (Equality, Community Planning & Public Service

More information

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization REPORT FOR ACTION 12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization Date: April 27, 2018 To: Toronto and East York Community Council From: Senior Strategic Director,

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

Airdrie - Bathgate Railway and Linked Improvements Bill. Environmental Statement Page 1

Airdrie - Bathgate Railway and Linked Improvements Bill. Environmental Statement Page 1 Environmental Statement Page 1 1.0 INTRODUCTION 1.1 The Scheme Proposal The scheme proposals are to re-open the Airdrie to Bathgate section of the former Bathgate and Coatbridge Railway (Monklands Railway)

More information

Living & Working Tourism

Living & Working Tourism Living & Working Tourism 5.10Tourism Background 5.10.1 Tourism is a major rural industry in Dorset, contributing over 600 million in visitor expenditure and supporting over 21,000 jobs directly and indirectly

More information

Kirkcaldy Sea Wall Improvements. Non-technical Summary. For illustration purposes only to give an indicative representation of the scheme.

Kirkcaldy Sea Wall Improvements. Non-technical Summary. For illustration purposes only to give an indicative representation of the scheme. ENVIRONMENTAL STATEMENT Non-technical Summary For illustration purposes only to give an indicative representation of the scheme. Kirkcaldy Sea Wall Improvements Introduction A concrete sea wall fronts

More information

East West Rail Consortium

East West Rail Consortium East West Rail Consortium EWR Wider Economic Case: Refresh 18 th November 2015 Rupert Dyer Rail Expertise Ltd Rail Expertise Ltd. Tel: 01543 493533 Email: info@railexpertise.co.uk 1 Introduction 1.1 The

More information

A303. Sparkford to Ilchester Dualling Scheme Preferred Route Announcement

A303. Sparkford to Ilchester Dualling Scheme Preferred Route Announcement A303 Sparkford to Ilchester Dualling Scheme Preferred Route Announcement About this booklet This booklet presents the preferred route for the A303 Sparkford to Ilchester dualling scheme and a summary of

More information

East Lancashire Highways and Transport Masterplan East Lancashire Rail Connectivity Study Conditional Output Statement (Appendix 'A' refers)

East Lancashire Highways and Transport Masterplan East Lancashire Rail Connectivity Study Conditional Output Statement (Appendix 'A' refers) Report to the Cabinet Member for Highways and Transport Report submitted by: Director of Corporate Commissioning Date: 1 June 2015 Part I Electoral Divisions affected: All East Lancashire Highways and

More information

A140 study and Major Road Network

A140 study and Major Road Network A140 study and Major Road Network Executive Summary The Government s new Transport Investment Strategy sets out a new long-term approach for government infrastructure spending. Funding will be targeted

More information

St. Patrick s Street Development Brief

St. Patrick s Street Development Brief St. Patrick s Street Development Brief Bardas Chorcai Cork Corporation August 2001 Contents Introduction and background The Development Brief Area Protected and valuable buildings Urban context Objectives

More information

Scheme Evidence Update Planning & Sustainable Development. Adran yr Economi a r Seilwaith Department for Economy and Infrastructure

Scheme Evidence Update Planning & Sustainable Development. Adran yr Economi a r Seilwaith Department for Economy and Infrastructure Adran yr Economi a r Seilwaith Department for Economy and Infrastructure This document is an update to the Proof of Evidence Planning & Sustainable document. It contains an update following the addition

More information

ASSEMBLY 39TH SESSION

ASSEMBLY 39TH SESSION International Civil Aviation Organization WORKING PAPER 22/6/16 ASSEMBLY 39TH SESSION EXECUTIVE COMMITTEE Agenda Item 31: Other high-level policy issues to be considered by the Executive Committee THE

More information

Roundhouse Way Transport Interchange (Part of NATS City Centre Package)

Roundhouse Way Transport Interchange (Part of NATS City Centre Package) Roundhouse Way Transport Interchange (Part of NATS City Centre Package) 15/16 16/17 17/18 18/19 19/20 Total TOTAL COST Roundhouse Way Transport Interchange 0.5m 0.5m FUNDING CIL 0.05m 0.05m Growth Deal

More information

Gold Coast. Rapid Transit. Chapter content. Chapter four Route selection and staging

Gold Coast. Rapid Transit. Chapter content. Chapter four Route selection and staging Chapter four Route selection and staging Gold Coast Rapid Transit Chapter four Route selection and staging Chapter content Route selection...73 Section one: Helensvale to Griffith University...74 Section

More information

International Civil Aviation Organization REVIEW OF STATE CONTINGENCY PLANNING REQUIREMENTS. (Presented by the Secretariat) SUMMARY

International Civil Aviation Organization REVIEW OF STATE CONTINGENCY PLANNING REQUIREMENTS. (Presented by the Secretariat) SUMMARY BBACG/16 WP/4 31/01/05 International Civil Aviation Organization The Special Coordination Meeting for the Bay of Bengal area (SCM/BOB) and The Sixteenth Meeting of the Bay of Bengal ATS Coordination Group

More information

Response to the London Heathrow Airport Expansion Public Consultation

Response to the London Heathrow Airport Expansion Public Consultation Response to the London Heathrow Airport Expansion Public Consultation Summary This report sets out the response to the Heathrow Airport s consultation on airport expansion and airspace change. The consultation

More information

TWELFTH AIR NAVIGATION CONFERENCE

TWELFTH AIR NAVIGATION CONFERENCE International Civil Aviation Organization 17/5/12 WORKING PAPER TWELFTH AIR NAVIGATION CONFERENCE Montréal, 19 to 30 November 2012 Agenda Item 4: Optimum Capacity and Efficiency through global collaborative

More information

Guildford Borough Transport Strategy 2017, Topic Paper: Transport, June 2017 (accompanying Local Plan 2017) Local Plan Transport Strategy 2017

Guildford Borough Transport Strategy 2017, Topic Paper: Transport, June 2017 (accompanying Local Plan 2017) Local Plan Transport Strategy 2017 Guildford Society Transport Group Position Paper August 2017 Based on submissions in response to the June/July 2017 Local Plan consultation including material presented to Drop-in Session 15 July 2017.

More information

PERTH AND KINROSS COUNCIL. Housing and Health Committee. 25 May Perth and Kinross Local Housing Strategy

PERTH AND KINROSS COUNCIL. Housing and Health Committee. 25 May Perth and Kinross Local Housing Strategy PERTH AND KINROSS COUNCIL 7 16/234 Housing and Health Committee 25 May 2016 Perth and Kinross Local Housing Strategy 2016-2021 Report by Director (Housing and Social Work) PURPOSE OF REPORT This report

More information

THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES

THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES BRITISH COLUMBIA MINISTRY OF TRANSPORTATION & INFRASTRUCTURE AVALANCHE & WEATHER PROGRAMS THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES British Columbia Ministry of Transportation & Infrastructure

More information

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM Backcountry Trail Flood Rehabilitation A June 2013 Flood Recovery Program Summary In June 2013, parts of Southern Alberta were devastated from significant

More information

Decision Strategic Plan Commission Paper 5/ th May 2017

Decision Strategic Plan Commission Paper 5/ th May 2017 Decision Strategic Plan 2017-2019 Commission Paper 5/2017 5 th May 2017 Commission for Aviation Regulation 3 rd Floor, Alexandra House Earlsfort Terrace Dublin 2 Ireland Tel: +353 1 6611700 Fax: +353 1

More information

Wolverhampton City Council

Wolverhampton City Council Agenda Item: 7G Wolverhampton City Council OPEN EXECUTIVE DECISION ITEM Cabinet / Cabinet Team CABINET Date 24 MARCH 2010 Portfolio(s) Originating Service Group(s) COUNCILLOR MRS BRADLEY (REGENERATION

More information

FASI(N) IoM/Antrim Systemisation Airspace Change Decision

FASI(N) IoM/Antrim Systemisation Airspace Change Decision Safety and Airspace Regulation Group FASI(N) IoM/Antrim Systemisation Airspace Change Decision CAP 1584 Contents Published by the Civil Aviation Authority, August 2017 Civil Aviation Authority, Aviation

More information

A465 Heads of the Valleys Dualling Sections 5&6: Dowlais Top to Hirwaun. Statement of Case / Proof of Evidence

A465 Heads of the Valleys Dualling Sections 5&6: Dowlais Top to Hirwaun. Statement of Case / Proof of Evidence A465 Heads of the Valleys Dualling Sections 5&6: Dowlais Top to Hirwaun Statement of Case / Proof of Evidence The Welsh Government s Reasons for Proposing that the Published Draft Orders should be made

More information

Spadina Avenue Built Form Study Preliminary Report

Spadina Avenue Built Form Study Preliminary Report STAFF REPORT ACTION REQUIRED Spadina Avenue Built Form Study Preliminary Report Date: July 9, 2014 To: From: Wards: Reference Number: Toronto and East York Community Council Director, Community Planning,

More information

APPENDIX A. Traveller Sites Allocations Development Plan Document. DRAFT Preferred Options Report July 2014

APPENDIX A. Traveller Sites Allocations Development Plan Document. DRAFT Preferred Options Report July 2014 Traveller Sites Allocations Development Plan Document DRAFT Preferred Options Report July 2014 Contents Introduction and background... 1 Consultation... 3 How to make comments and submit site information...

More information

Strategic Transport Forum 7 th December 2018

Strategic Transport Forum 7 th December 2018 Strategic Transport Forum 7 th December 2018 Agenda Item 7: East West Rail Recommendation: It is recommended that the Forum: a) Endorse the East West Rail Consortium s position in relation to the draft

More information

Chapter 14 Route Window C12 Mile End Park and Eleanor Street shafts. Transport for London

Chapter 14 Route Window C12 Mile End Park and Eleanor Street shafts. Transport for London Chapter 14 Route Window C12 Mile End Park and Eleanor Street shafts MILE END PARK AND ELEANOR STREET SHAFTS 14 Route Window C12 Mile End Park and Eleanor Street shafts Introduction 14.1 Crossrail s twin

More information

1.2 Corridor History and Current Characteristics

1.2 Corridor History and Current Characteristics SECTION 1 Description and Background of Study Area 1.1 Introduction This preliminary engineering report was prepared for the Alaska Department of Transportation and Public Facilities (ADOT&PF). It is part

More information

Proposals for the Harrogate Road / New Line Junction Improvement Scheme. August / September Supported by:

Proposals for the Harrogate Road / New Line Junction Improvement Scheme. August / September Supported by: Proposals for the Harrogate / New Line Junction Improvement Scheme August / September 2016 Supported by: Introduction Key Benefits Proposals are currently being developed for changes to the junction of

More information

FEASIBILITY CRITERIA

FEASIBILITY CRITERIA This chapter describes the methodology and criteria used to evaluate the feasibility of developing trails throughout the study areas. Land availability, habitat sensitivity, roadway crossings and on-street

More information

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the

More information

Newcastle Transport Program Newcastle Light Rail Determination Report

Newcastle Transport Program Newcastle Light Rail Determination Report Newcastle Transport Program Newcastle Light Rail Determination Report Date Author 25 July 2016 TfNSW Ref 5276649 Status Final TfNSW 2014 UNCONTROLLED WHEN PRINTED Page 1 of 19 Table of contents 1 Introduction

More information

The Government s Aviation Strategy Transport for the North (TfN) response

The Government s Aviation Strategy Transport for the North (TfN) response The Government s Aviation Strategy Transport for the North (TfN) response Transport for the North Background Good transport links are a crucial part of a strong economy supporting labour markets and delivering

More information

Consultation on Draft Airports National Policy Statement: new runway capacity and infrastructure at airports in the South East of England

Consultation on Draft Airports National Policy Statement: new runway capacity and infrastructure at airports in the South East of England Tony Kershaw Honorary Secretary County Hall Chichester West Sussex PO19 1RQ Telephone 033022 22543 Website: www.gatcom.org.uk If calling ask for Mrs. Paula Street e-mail: secretary@gatcom.org.uk 22 May

More information

Co-ordinated and Orderly Growth A Suite of Infrastructure and Public Assets for the Future... 1

Co-ordinated and Orderly Growth A Suite of Infrastructure and Public Assets for the Future... 1 Co-ordinated and Orderly Growth... 1 A Suite of Infrastructure and Public Assets for the Future... 1 Funding Sources, Revenues and Prioritising Expenditure... 2 Stage 1 Short Term Growth Sunbury to 50,000...

More information

Report of the Strategic Director, Regeneration to the meeting of Bradford South Area Committee to be held on 28 January U

Report of the Strategic Director, Regeneration to the meeting of Bradford South Area Committee to be held on 28 January U Report of the Strategic Director, Regeneration to the meeting of Bradford South Area Committee to be held on 28 January 2016. U Subject: WINDERMERE ROAD & SURROUNDING STREETS - PETITION Summary statement:

More information

2.0 Physical Characteristics

2.0 Physical Characteristics _ 2.0 Physical Characteristics 2.1 Existing Land Use for the Project The site is comprised of approximately 114 acres bounded by Highway 101 to the north, the existing town of Los Alamos to the east, State

More information

CHAPTER 6 NOISE EXPOSURE

CHAPTER 6 NOISE EXPOSURE CHAPTER 6 NOISE EXPOSURE FAA requires that the NEM submitted for review represent the aircraft noise exposure for the year of submittal (in this case 2008) and for a future year (2013 for OSUA). However,

More information