P3 & Design-Build. 101 st Annual THE Conference February 25 th, Speaker: Andrew Gensch, P.E.

Similar documents
Projected Advertisement Date

IRONTON-RUSSELL BRIDGE REPLACEMENT

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

PRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction

November 21, 2012 Barbara Kelleher, (954)

5.7 Local road upgrades

DALLAS HORSESHOE PROJECT. Project Update including the Margaret McDermott Bridge Transportation and Trinity River Project Committee February 22, 2016

ROUTE 630 DIVERGING DIAMOND INTERCHANGE

State Route 8 Corridor. Northern Summit County s Path to Success

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

Pattullo Bridge Replacement Project

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

Northeast Anthony Henday Drive. Bill van der Meer Urban Construction Manager - Edmonton Alberta Transportation

PRIORITIES COMMITTEE MEETING

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

Ohio Department of Transportation Construction Update

I-75 in Hamilton County Project Termini

Rudy McLellan, P.E. GEC, Inc., Baton Rouge, LA For Vicksburg Bridge Commission, VBC

District Construction Progr am. John R. Kasich, Ohio Governor Jerry Wray, ODOT Director Steve Mary, P.E., District Deputy Director

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017

Add-A-Lane Contract V. along a Section of I-95 includes 6 Bridges

Concord Road Interchange. Standard hours of work

Whittier Bridge Project

FDOT Treasure Coast Traffic Report through

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

Public Information Center August 12, 2010

APPENDIX F List of Commitments

Section 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps

Welcome to Webinar on Accelerated Bridge Construction Colorado Flyover Ramp Showcases Precast Pier Caps and Curved Spliced Precast U-Girders

Northern Virginia District State of the District. Helen L. Cuervo, P.E. District Engineer October 18, 2017

Community Advisory Panel Meeting #

25 th Avenue Grade Separation. September 13, 2017

Route 29 Solutions Projects

PennDOT Interstate Work next week March 30-April 3:

FDOT Treasure Coast Traffic Impact Report

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

Fairfax County Parkway Widening Fairfax County

Constructor: Joseph B. Fay

I-35 Reconstruction Project

Long water shutdown scheduled for Tuesday, September 18

Section 3-04 Cross Sectional Elements TABLE OF CONTENTS. INTRODUCTION...3 General...3 Exhibit 1-Cross-Sectional Elements...3

APPENDIX F. Structural Design Report

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

25 th Avenue Grade Separation. December 13, 2017

BUSH INTERCONTINENTAL AIRPORT

Viaduct Demolition at Girard Interchange

Crystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.

BUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019

Frequently Asked Questions on the Route 29 Solutions Improvements Projects

Appendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited

Ossington Station Easier Access Project - Construction & Public Art Concept Update

San Mateo County Transportation Authority Board Meeting November 2, 2017 Item #10 1

Appendix 4.8 A. Agency Correspondence and Final APE Statement

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2)

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)

Yonge Street / Highway 401 Improvements Update. Public Works and Infrastructure Committee. General Manager, Transportation Services

A. CONCLUSIONS OF THE FGEIS

RESIDENT ENGINEERING, CONSTRUCTION MANAGEMENT & QA/QC SERVICES (CONTINUOUS CONTRACTS FROM

THREE MILE PLAN TOWN OF SUPERIOR COLORADO

2 Construction Program

ADDENDUM 2 APPENDIX D STANDARD DRAWINGS

Public Informational Meeting

City of Fort Lauderdale. Frequently Asked Questions. Proposed Sea Wall Ordinance

Metro ExpressLanes April 5, 2011 Community Meeting re: Adams Blvd Improvements

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

FY TRANSPORTATION IMPROVEMENT PROGRAM. Authority Projects FY

Pardon Our Dust Public Information Meeting

ONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1

Project Overview. Hunter Mill Road Over Colvin Run Bridge Replacement Fairfax County. Get Involved. Public Information Meeting. Contact Information

Northeast Corridor Transportation Update

Legal Notice. Columbus and Franklin County Metro Parks Request for Statement of Qualifications (RFQ): Professional Design and Engineering Services

Welcome to Webinar on Accelerated Bridge Construction Milton-Madison Bridge Replacement: the Mega-Lateral Slide

Score. Category. Access Aesthetics Community Resources

The Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP).

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015

A DIALOGUE WITH THE NORTHERN VIRGINIA DISTRICT. Nicholas J. Roper, P.E. Northern Virginia District Project Development Engineer

Major Projects Overview

Technical Design Manual

2016 Regional Transportation Alternatives Program (TAP) Grant Application

Project Location MP A44.5 MP A38 PRELIMINARY. A A57 (Future Project) A42 - A44.5 (Fall Fall 2019) A38 - A42. A31 - A38 - In Design

Dufferin Jog Elimination Project

395 Express Lanes Project Update

K SIGNAGE & TRAFFIC CONTROL. Table of Contents

Public-Private Partnerships (P3) for Social Infrastructure. Alberta Schools Alternative Procurement (ASAP Team) Alberta Infrastructure

PROGRESS PARK CONNECTOR

1.2 Corridor History and Current Characteristics

US 19 Sunset Point Rd to Countryside Blvd.

Guide to. Road Construction Projects

WATERFRONT PROGRAM PROGRESS REPORT

2015 PURDUE ROAD SCHOOL March 11, 2015

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

SAN RAFAEL City Council January 20, 2015

Transcription:

P3 & Design-Build 101 st Annual THE Conference February 25 th, 2015 Speaker: Andrew Gensch, P.E.

Presentation Outline Ohio River Bridges Project Overall Discussion Downtown Crossing and East End Locations Program Goals Cost Schedule Downtown Crossing Project Overview/Facts, Teams, Delivery Method Sections 1, 2, and 3 Overview, Technical Highlights, Challenges/Solutions East End Crossing Project Overview/Facts, Teams, Delivery Method Sections 4, 5, and 6 Overview, Technical Highlights, Challenges/Solutions 2

Project Location Louisville, Kentucky East End Crossing Downtown Crossing 3

Project Goals Provide regional redundancy for Ohio River Crossings (Both Projects) Add additional crossing over the river east of Louisville (East End) Provide by-pass around downtown Louisville for traffic to I-65 north and east (East End) Upgrade the outdated spaghetti junction intersection downtown Louisville (Downtown Crossing) Rehabilitate existing JFK bridge (Downtown Crossing) Construct C-D system north of river in Indiana (Downtown Crossing) 4

Project Delivery Methods Downtown Crossing Design Build Design and construction services are contracted by a single entity - DBT Teaming Agreement RFQ Submission Shortlist Prelim Design and Estimate Contract Award Based on Price and Technical Score Project Execution East End Public Private Partnership (P3, or PPP) Operation and Maintenance Warranty Period Flow Down provisions from agreements between Design Builder and Concessionaire Interaction with the project owner limitations The review cycle Concessionaire has a say! 5

Project Cost 6 Source: kyinbridges.com

Project Schedule 7 Source: kyinbridges.com

8 Downtown Crossing Design Build

9 Downtown Crossing Location Louisville, Kentucky

Downtown Crossing Project Facts/Overview Section 1 - Reconfigure Spaghetti Junction (I-64, I-65 and I-71) (Blue) Section 2 - Build a new I-65 bridge with six northbound lanes (Yellow) Section 2 - Rehab Kennedy Bridge (I-65) with six southbound lanes (Yellow) Section 3 - Reconfigure Indiana roadway and bridge approaches (Red) 10 Project Cost $1.27B

Downtown Crossing Project Team Design Build Team: Owner: 11 Design Team - Management, Structures, Geotechnical, MOT, River Hydraulics Applied Research Associates Bridge Security Buckland and Taylor Cable Stay Designer Earth Exploration - Geotechnical GRW Lighting, Electrical, Utilities International Bridge Technologies Independent Bridge Check Linebach Funkhouser Contaminated Materials MacDonald Architects Bridge Lighting Aesthetics Clough, Harbour & Associates (formerly RW Armstrong) Section 3 Road, Drainage, Structures Rowan, Williams, Davies, and Irwin (RWDI) Wind Engineering Stantec Section 1 Bridges, Drainage, Roadway Project Wide Aesthetics

Downtown Crossing Design Offices Project Office Section 1 St. Louis Lexington Louisville Section 2 Seattle/Vancouver Section 3 Indianapolis St. Louis

Downtown Crossing Section 1 Overview Downtown Louisville at the intersection of I-64, I-65, and I-71 48 permanent bridges, 3 temporary, 30 walls, 25 ramps 13

Downtown Crossing Section 1 Technical Highlights Multiple stages of MOT Complex geometry with 3 intersecting interstates, multiple fly over bridges Limited ROW to the south on I-65, staged bridge construction 14

Downtown Crossing Section 1 Challenges/Solutions Challenge Initial Design Friction Piles Unanticipated subsurface conditions discovered after most substructure design was complete First Pile drives made several feet of progress first blows Solution Substructure was redesigned Fewer, Smaller Piles Driven to Rock Resulted in Material / Schedule Savings 15

Downtown Crossing Section 1 Challenges/Solutions Challenge Complex MOT and Utility Coordination Multiple Stages Solution MOT Task Force meetings with designer, contractor, owner, interested parties Utilized multiple traffic calming methods Involved local police for traffic enforcement On going revision process to accommodate dynamic construction environment 16

Downtown Crossing Section 2 Overview NB I-65 Cable Stay Bridge and Indiana Approach Bridge SB I-65 Existing Steel Truss JFK Bridge and Indiana Approach Bridge Existing JFK Bridge Indiana Approaches Kentucky N Cable Stay Bridge Indiana 17

Downtown Crossing Section 2 Overview Cable Stayed 2,106' NB Approach 1,060' N Existing JFK Bridge 2,497' SB Approach 659' 18

Downtown Crossing Section 2 Technical Highlights 19 NB I-65 Cable Stay Bridge Design 3 Towers (Center Tower 254 Tall, North and South Towers 198 Tall) 4 Spans (Center Spans 750 Long, Outer Spans 303 )

Downtown Crossing Section 2 Technical Highlights 20 Cable Stay Bridge Design

Downtown Crossing Section 2 Challenges/Solutions Challenge Design Structure for durability Different Exposure Zones Solution Delineate Exposure Zones Develop Zone Specific Durability Criteria Design Modifications Concrete Mix Flyash and Slag Rebar Coating requested from KYTC Corrosion Inhibitor at Road Level 21 Durability Design of Structure

Downtown Crossing Section 2 Challenges/Solutions Challenge Determine the effects of Wind on Structure during construction and when completed. Solution Scale Model of Existing JFK and new Bridge Built in Wind Tunnel Modeled Completed Cable Stay Bridge Modeled Various Critical points During Construction for Stability 22

23 Downtown Crossing Section 2 Photos

24 Downtown Crossing Section 2 Photos

25 Downtown Crossing Section 2 Photos

26 Downtown Crossing Section 2 Photos

27 Downtown Crossing Section 2 Photos

Downtown Crossing Section 3 Overview Ties in to Existing JFK and new Cable Stay Bridge (Red) I-65 roadway reconstruction Clark Memorial Bridge direct access to NB I-65 (Yellow) 20 Bridges, all but 1 concrete. CD system overhaul Existing Clark Memorial Bridge Bridge B11 Flyover Bridge I-65 JFK and Cable Stay Footprint 28

Downtown Crossing Section 3 Technical Highlights Bridge B11 Fly over Bridge 29

Downtown Crossing Section 3 Challenges/Solutions Challenge Reconstruct the structural elements to the approach of the Clark Memorial bridge while maintaining historic block features. Solution Bridge was surveyed with Lidar and each block was individually numbered for reassembly. A specific plan package was put together for block removal and reassembly. 30

31 East End Crossing P3

32 East End Crossing Project Location Prospect, KY

East End Crossing Project Facts/Overview Completes I-265 loop New Cable Stay Bridge over the Ohio River New Tunnel under the historic Drumanard Estate Greenfield Roadway Section in Indiana Project Cost = $1.08B 33

East End Crossing Project Team Owner / Developer / Builder Design Team American Structurepoint Inc. Section 6 Design Stantec Geotechnical for Section 4 and 5 Earth Exploration Inc. Geotechnical for Section 6 Buckland and Taylor Section 5 Independent Design International Bridge Technology Section 5 Superstructure Design Wiss Janney Elstner East End Bridge Corrosion Protection Plan Carman Landscaping Macdonald Architects East End Bridge Aesthetics Global Solutions Civil Engineering and General Support Rowan Williams Davies and Irwin Wind Study PCS Engineers Section 4 Noise and Safety Walls Applied Research Associates East End Bridge and Tunnel ATVA 34

East End Crossing Design Offices Project Office Section 4 Dallas (Non-Tunnel) New York (Tunnel) Section 5 Morristown San Diego Section 6 Indianapolis

East End Crossing Section 4 Overview Begins at KY 841 / I-71 Interchange Passes thru a depressed section A Tunnel extending 1700 feet under US 42 and the historic Drumanard Estate Crosses over a creek - 5-span twin Steel structures Max span 350 High fill area fill > 60 Connects to East End Bridge 36

East End Crossing Section 4 Technical Highlights Tunnel Fire protection Reduced Design Fire Harrods Creek Bridge up to 350 Span Approach Structure to Main Span Bridge 37

East End Crossing Section 4 Challenges/Solutions Challenge Impact of pile driving on LWC s water filtration tunnel Impact of pile driving on LWC s Sludge Pond Challenging rock conditions during construction of rock and soil anchored walls Harrods Creek Bridge Foundation differing rock elevation Solutions Engaged original tunnel designers to evaluate Sheet piling as cut off wall Existing soil characterization study Provide different option for different conditions Geo-tech Engineer on site Changed foundation type to Drilled shaft 38

39 East End Crossing Section 4 Photos

40 East End Crossing Section 4 Photos

41 East End Crossing Section 5 Overview

East End Crossing Section 5 Overview 3 span, Two tower, cable stay structure over the Ohio River; 2500 feet long; Towers are ~300 ft tall; 71 feet minimum vertical clearance from river normal pool; Four lane section, scalable to six lane; 13 foot pedestrian and emergency access path 42

43 East End Crossing Section 5 Overview

East End Crossing Section 5 Technical Highlights Stringent Corrosion Protection Requirements Avoidance of Fracture Critical Steel members Independently checked design Bridge construction method 44

45 East End Crossing Section 5 Technical Highlights

46 East End Crossing Section 5 Technical Highlights

47 East End Crossing Section 5 Technical Highlights

48 East End Crossing Section 5 Technical Highlights

East End Crossing Section 5 Challenges/Solutions Challenges Access to construct Indiana side pier and abutment Rebar and Miscellaneous items conflict Expansion Joint System Longitudinal and Vertical Movements Additional Vibration from Wind Analysis Solutions Grading plan Integrated Drawings Used Modular Joints by Mageba Added cable stay braces, open barrier 49

50 East End Crossing Section 5 Photos

East End Crossing Section 6 Overview Mostly Green Field Construction Reconstruction of I-265 and SR 62 Interchange Addition of new full interchange at Old Salem Road 51

52 East End Crossing Section 6 Technical Highlights

53 East End Crossing Section 6 Technical Highlights

54 East End Crossing Section 6 Technical Highlights

55 Questions?

56

57 Downtown Crossing Section 3 Challenges/Solutions Tolling Challenges 1- Tolling Requirements for Design / Toll Integrator Selection 2- Due to RFP requirements, both the East End and Downtown must by turned on as soon as either bridge is open to traffic. Solutions 1- Design barriers, medians, and foundation locations to meet the most likely number of scenarios for tolling infrastructure. 2- A temporary tolling system was designed and installed to capture tolls in the interim condition, and was designed not to conflict with the permanent condition.

58 Downtown Crossing Section 2 Photos

59 Downtown Crossing Section 2 Photos

East End Crossing Section 6 Challenges/Solutions Challenges Deck Replacement of Existing Bridges MOT of a busy interchange (with heavy railroad passing thru it) Solutions Challenge in protecting beams Fixes to damages Collaboration with Builder during construction and traffic phasing 60