Pre privatisation

Similar documents
Closure of GM Holden Government Response. January 2014

Committee for Melbourne Briefing Note Victorian State Budget Overview of Key Announcements

RE: SUBMISSION TO THE JOINT SELECT PARLIAMENTARY COMMITTEE INQUIRY ON NORTHERN AUSTRALIA

ERA overview. Dan Janney General Manager, Operations

ASX Announcement. Appointment of Preferred Contractor for CHPP Construction at Colton Mine

License Application Gas Trading License

Distinguished guests, parliamentary colleagues, ladies and gentlemen.

2013 IQA Young Members Network Study Tour Hong Kong / China

Communication and consultation protocol

For personal use only

Development Projects. Turner River Hub Project. centralised processing facility drawing feed from nearby satellite mines.

TO MAXIMUM CAPACITY AND BEYOND

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

Brisbane set to host G20 conference in 2014

LARGE AIR TANKER OPERATIONS IN NEW SOUTH WALES

Community engagement in the Northern Territory January 2017 update

MINISTER S MESSAGE. Dear friends:

Oakland A s Gondola Economic Impact

Civil aviation and its changing world of work

STRATEGIC PLAN

For personal use only

The Holes Creek Bridge Replacement By Bradley McClelland

2013/14 Pre-Budget Submission Accommodation Association of Australia

Australian Railroad Group DVD Script

1. CEO s message. PETER B. SCHNEIDER Chief Executive Officer EASTERN METROPOLITAN REGIONAL COUNCIL

BRIEFING PAPER APRIL 2002 MINING AREA C DEVELOPMENT PORT HEDLAND PORT & CAPACITY EXPANSION

INTERNATIONAL FIRE TRAINING CENTRE

Submission Cover Sheet Fishermans Bend Planning Review Panel

GIPPSLAND TOURISM MASTER PLAN

Paul Fletcher Minister for Urban Infrastructure and Cities Launch of Infrastructure Australia Future Cities Paper. Fri 23 February 2018

Sunshine Coast Council Locked Bag 72 Sunshine Coast Mail Centre QLD Submitted via online portal. 2 June 2017.

Site Formation Works of the Kai Tak Cruise Terminal Project

Suspected Arson-Murder of the Godmother of Boy. 17. January 2011

Greater Shepparton City Council Planning Scheme Amendment C192 and C193 VicRoads Submission to Traffic Conclave

TOTTENHAM TO ALBURY JUNE We re progressing our planning in Victoria for Inland Rail Australia s largest rail freight project

QUARTERLY ACTIVITIES REPORT. For three months ended 31 March Highlights. 2. Operating Summary

BENCHMARKING THE PERFORMANCE OF THE NATIONAL ROAD SAFETY STRATEGY

DEFENCE - MAXIMISING OPPORTUNITIES

Amended Maintenance Dredge Spoil Management Plan. Shute Harbour Marina Resort

Civil Aviation, Annual Operating and Financial Statistics, Canadian Air Carriers, Levels I to III

Manigurr-ma Palmerston partnership showcases city

For personal use only

Industry briefing NOVEMBER 2017

Double Win for Liberty Industrial at World Demolition Awards

Smart Cities Plan IMPLEMENTATION. Townsville City Deal. April 2017

The cultural heart of York Central

Answer 1. What special astronomical event did people around the world see in the sky last week?

11 January Dear Public Consultations Team of the White Paper Task Force,

WORK RELATED DEATHS NEW SOUTH WALES - JULY 2009 TO DECEMBER ALL INDUSTRIES Date First Name Surname M/F Age Details Mechanism Industry No.

UrbanBuzz. 2 nd December Roger Madelin Joint Chief Executive, Argent Group PLC

First time sewerage scheme from

Growing Regional Victoria 2018 Victorian Election Priorities GROWING REGIONAL VICTORIA 2018 VICTORIAN ELECTION PRIORITIES

LEEDS GRENVILLE Economic Development Summit Strength Through Diversity Friday, November 20, 2015

PROJECT UPDATE BETTER TIMES AHEAD ON CLEM7 CLEM JONES TUNNEL. Fast facts AUGUST 2008

Airline Operating Costs Dr. Peter Belobaba

PERTH-ADELAIDE CORRIDOR STRATEGY

2001/02 Financial review of the Ministry of Transport. Report of the Transport and Industrial Relations Committee

TECHPORT AUSTRALIA - AUSTRALIA S PREMIER NAVAL INDUSTRY HUB

% change in reported RASK % change in underlying RASK (excl. FX) Group 1.8% 2.6% Short Haul 5.3% 5.4% Long Haul (3.8%) (2.0%)

HISTORY OF THE CENTRAL EYRE IRON PROJECT (CEIP)

REDD+ IN YUCATAN PENINSULA

LOCAL BUYING. Supporting Western Australia through local buying. PROGRAM BUILDING OUR FUTURE TOGETHER

About Us. An introduction to Network Rail

The Coalition s Policy to Build Melbourne s East West Link

MADAGASCAR: POST-FLOOD FOOD SECURITY AND CHOLERA PREVENTION

SWISS posts stable first-half result

Blackburn Road Blackburn Level Crossing Removal. Frequently Asked Questions August 2014 GENERAL

APPENDIX I: PROCESS FOR FIRST NATIONS REGIONAL DIALOGUES

Queensland Treasury s primary role is to advance the performance of Queensland s economy and to manage the State s finances.

TORONTO TRANSIT COMMISSION REPORT NO.

For personal use only

NATIONAL AIRSPACE POLICY OF NEW ZEALAND

WICET WIGGINS ISLAND COAL EXPORT TERMINAL

JAL Group Announces its FY Medium-Term Business Plan

For personal use only

Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018

World Air Transport Statistics. Special AGM Edition WORLD AIR TRANSPORT SUMMIT

ENVIRONMENTAL SCRUTINY COMMITTEE 6 DECEMBER 2016

Recorded accounts tell us that this method of fire control took place as early as the winter of 1894.

Page 1 of 7 FULL TRANSCRIPT: WESTERN SYDNEY AIRPORT ANIMATION VIDEO

About Us. An introduction to Network Rail

QANTAS DELIVERS STRONG FIRST HALF RESULT DESPITE HIGHER FUEL BILL

15-17 November 2018 Bankstown Airport

TUCSON INTERNATIONAL AIRPORT (TUS) DISABLED AIRCRAFT RECOVERY PLAN Section TABLE OF CONTENTS Page

2012 Americas School of Mines

SAM S HOTEL INTERESTS at AHAURA, GREYMOUTH & NELSON

Community engagement in the Northern Territory June 2016 update

QUARTERLY ACTIVITIES REPORT 31 JANUARY 2019

COLLINGWOOD FOOTBALL CLUB

Offshore & Specialist Ships Australia

Caroona Coal Project. Gunnedah Coal Conference 20 September 2006

REINVIGORATING GLENELG JETTY AND FORESHORE REDEVELOPMENT

Next Meeting Tony Spring District Governor s Visit Partners Night

ISSUE 36 SEPTEMBER 2015 MOVING AHEAD CROSSRAIL PROJECT SEPTEMBER UPDATE WATCH! WATCH THE LATEST MOVING AHEAD VIDEO ON YOUTUBE.

NARRABEEN LAGOON SUMMIT am Wednesday, 13 April 2005 Warringah Council Chambers, 725 Pittwater Road, Dee Why.

Outlook: FY13 EBITDA guidance $28M - $29M. Pursuing contracted 300MW in 2013 growth strategy. FY13 maiden franked dividend payment expected

Certificate for international voyage application form

OUR COMMITMENT TO ENVIRONMENTAL SUSTAINABILITY

What options were considered

ACI-NA/World Conference & Exhibition. PPPs: Will it work for your Airport?

Transcription:

History of Hazelwood

Hazelwood Power Station is synonymous with the Latrobe Valley. For the last 52 years, Hazelwood has helped power Victoria, supplying 25 per cent of the state s electricity needs. Its long history, boasting some significant achievements, is a tribute to all employees.

1960s Hazelwood took shape over this decade. Preliminary firing of the Unit 1 boiler on 22 February 1964, was a milestone with briquettes used for the trials. Coal deliveries to the Hazelwood Slot Bunker started in mid-july with the first line of coal conveyors, M162, from Morwell Eastfield to the Station completed the following month. All was ready for commissioning of the first unit in October. In May 1965, parliamentary approval was 1990s given to the SEC to extend Hazelwood to a 1600 megawatt station by the adding a further two, 200 megawatt units. Dredger 10 was ordered in June and the following month, Unit 2 came into service. Dredger 11 was ordered in December. Contracts were let for Units 7 and 8 in 1966, coinciding with the operational start of Dredger 9. Unit 3 started operating in August 1966, Unit 4 in July 1967, Unit 5 August 1968 and Unit 6 in May 1969. THE BEGINNING An Act of the Victorian Parliament on 13 October 1959 signalled the beginning of a project that would change the face of the Valley for more than 50 years. Construction of the Hazelwood Power Station was approved for the eastern slope of the ridge, about three kilometres Morwell Power Station. Initially, six 200 megawatt units would come on stream progressively between 1964 and 1970 as baseload increments. An additional two units were approved by the government in 1965, extending the station to eight units, producing 1600 megawatts. A familiar face at Hazelwood retired from service in August 1994 when the Morwell Open Cut s oldest dredger, Dredger 21, was taken out of operation. The 753 tonne bucket wheel dredger, built in 1955, was relocated to the nearby PowerWorks visitor centre for display and remains there today. Arguably the biggest change to the state s power industry came the following year when the Victorian Government took the first step towards privatising the SEC on 1 February 1995, by transforming it into an entity known as Generation Victoria. power industry and the Latrobe south west of the former An estimated 80,000 cubic metres (150,000 tonnes) of earth collapsed into the mine on 11 February 1992, surrounding Dredger 10 within minutes and pushing it, together with the conveyor and hopper, some 20 metres sideways. The 1800 tonne overburden dredger was operating at the time of the slip however none of the dredger crew was injured. 1970s Hazelwood s final two units started operating in 1970 - Unit 7 in March and Unit 8 in December. On Friday, 12 March 1971, the Station was officially opened. It was planned for Victorian Premier, Sir Henry Bolte, to cut a ribbon but subsequent reports reveal this never happened. The open day attracted thousands of visitors, many arriving by train onsite and alighting under a rising conveyor. Construction continued with the M260 conveyor completing the installation of the fixed conveyors taking coal from the Mine to the Power Station. In June 1973, the SEC announced revised plans for the long-term development of the Morwell Open Cut (now called Hazelwood Mine). Valuable coal deposits under the flood plain area of the Morwell River would now be used earlier than intended. The Morwell River Diversion Project started in 1977 and saw a three kilometre long tunnel constructed to carry the base flow of the river as well as a 3.7 kilometre diversion channel for floodwaters. The tunnel comprised more than 900 individual pipes, each weighing 13 tonnes. At noon on Friday 4 November in 1977, a fire broke out in the north-west corner of the Mine, caused by a spark from a vehicle. A fire control team and support tankers were quickly on the scene but a sharp wind change spread ignited coal particles over several levels of the Mine. Tragedy struck on 9 December 1978, when three employees died in an explosion in the Unit 3 generator. The cause was an incomplete purge of hydrogen. 1980s The 80s was another decade of significant engineering achievements with a number of major projects at Hazelwood. The Half Life Refit project started in May 1982. completed three years later while the oldest dredger in service in the Morwell Open Cut, Dredger 21, underwent a major overhaul in May the following year. A major refurbishment of Unit 3 was undertaken in April 1985. The Plant Life Extension started mid-1986 and was The Open Cut plan for beyond 2000 was developed in November 1988 with a new overburden system planned. The government disaggregated Generation Victoria into five separate, state-owned generating businesses including Hazelwood Power Corporation. In August 1996, the government announced the sale of Hazelwood Power Corporation to the Hazelwood Power Partnership for $2.35 billion. The business was purchased by a consortium led by British giant National Power and other partners. a new century Hazelwood was awarded the inaugural Premier s Foundation Award in July/August 2002 for partnerships at work, recognising the success in developing a partnership approach to improve workplace relations. The playground in the Morwell Town Common officially opened on 1 March, 1998. It was constructed in just six days in a project initiated by Hazelwood and many of its employees. The next few years saw a number of milestones with Hazelwood Power Corporation rebranded as International Power in January 2003 and the first coal from the new Westfield development scooped out by Dredger 11 on 4 February 2004. The following year, Hazelwood s new wetlands sites were established to provide a wide variety of habitats for plants and animals. The official opening of a 7.5 kilometre section of the Strzelecki Highway, south west of Morwell, on 13 March, 2008, marked a significant milestone 2010-2017 in the Rivers and Roads Relocation Project (RRR) as part of the Westfield development. The Mine experienced another fire on 14 September 2008. The fire was under control in three days as a result of the efforts of more than 100 personnel from Hazelwood and its alliance partners, supported by around 70 CFA personnel. The Carbon Capture Pilot Plant officially opened in May/June 2009 following a comprehensive commissioning project. The $10 million pilot project was designed to initially capture 25 tonnes of CO2 a day from just one of Hazelwood s eight generating units. February 2010 saw the most significant river relocation and improvement project ever undertaken in Victoria. The new section of the Morwell River took a previouslymoved section of the river out of an old concrete pipe and into a natural meandering riverine environment. On 4 February 2011, the merger of GDF SUEZ and International Power took place. The same day, torrential rain overwhelmed drains and inundated Hazelwood land, next to Morwell and the freeway, causing a large sink hole in the area of the Morwell Main Drain. The freeway was closed for seven months due to ground movement in an area close to the freeway and the Mine s northern batters. The fire came within 200 metres of the power station on 25 February, providing further challenges for those involved. Some 189 Hazelwood personnel, with support from contractors and Loy Yang B, were engaged in the emergency effort. More than 7000 individual full-time and volunteer firefighters - many returning several times - worked a total of approximately 20,000 shifts over the duration of the fire. The Victorian Government established the Hazelwood Mine Fire Inquiry after the fire, with public hearings held between 26 May and 18 June. On 2 September, the inquiry s report and recommendations were handed down and released to the public. In July 2011, Australian Prime Minister, Julia Gillard, visited Hazelwood followed by Federal Opposition Leader, Tony Abbott. The document outlined 6 recommendations and 17 affirmations to be addressed by GDF SUEZ. On 9 February 2014, fire entered the Hazelwood Mine. It would take 45 days of intensive firefighting to bring to an end one of the most challenging events in Hazelwood s history. On 24 November 2014, Hazelwood marked 50 years of operation. Another name change came on 18 April 2015, when GDF SUEZ became ENGIE. The new name represented the human and positive vision of energy, and a contraction of the word energy. Hazelwood s trial of alternate auxiliary fuels went international on 18 November, following the arrival on site of brown coal briquettes from Germany. The scaling down of Energy Brix led the business to explore alternatives for its auxiliary fuel needs during Power Station startups and shutdowns. closure announced On 3 November 2016, Chief Executive of ENGIE in Australia, Alex Keisser, advised Hazelwood staff of the extremely difficult decision to close all eight generating units by 31 March 2017. At the time, Hazelwood directly employed 750 people - 450 employees and 300 contractors. It supplies up to 25 per cent of Victoria s energy requirements and more than 5 per cent of Australia s total energy demand.

1960s Hazelwood took shape over this decade. Preliminary firing of the Unit 1 boiler on 22 February 1964, was a milestone with briquettes used for the trials. Coal deliveries to the Hazelwood Slot Bunker started in mid-july with the first line of coal conveyors, M162, from Morwell Eastfield to the Station completed the following month. All was ready for commissioning of the first unit in October. In May 1965, parliamentary approval was 1990s given to the SEC to extend Hazelwood to a 1600 megawatt station by the adding a further two, 200 megawatt units. Dredger 10 was ordered in June and the following month, Unit 2 came into service. Dredger 11 was ordered in December. Contracts were let for Units 7 and 8 in 1966, coinciding with the operational start of Dredger 9. Unit 3 started operating in August 1966, Unit 4 in July 1967, Unit 5 August 1968 and Unit 6 in May 1969. THE BEGINNING An Act of the Victorian Parliament on 13 October 1959 signalled the beginning of a project that would change the face of the Valley for more than 50 years. Construction of the Hazelwood Power Station was approved for the eastern slope of the ridge, about three kilometres Morwell Power Station. Initially, six 200 megawatt units would come on stream progressively between 1964 and 1970 as baseload increments. An additional two units were approved by the government in 1965, extending the station to eight units, producing 1600 megawatts. A familiar face at Hazelwood retired from service in August 1994 when the Morwell Open Cut s oldest dredger, Dredger 21, was taken out of operation. The 753 tonne bucket wheel dredger, built in 1955, was relocated to the nearby PowerWorks visitor centre for display and remains there today. Arguably the biggest change to the state s power industry came the following year when the Victorian Government took the first step towards privatising the SEC on 1 February 1995, by transforming it into an entity known as Generation Victoria. power industry and the Latrobe south west of the former An estimated 80,000 cubic metres (150,000 tonnes) of earth collapsed into the mine on 11 February 1992, surrounding Dredger 10 within minutes and pushing it, together with the conveyor and hopper, some 20 metres sideways. The 1800 tonne overburden dredger was operating at the time of the slip however none of the dredger crew was injured. 1970s Hazelwood s final two units started operating in 1970 - Unit 7 in March and Unit 8 in December. On Friday, 12 March 1971, the Station was officially opened. It was planned for Victorian Premier, Sir Henry Bolte, to cut a ribbon but subsequent reports reveal this never happened. The open day attracted thousands of visitors, many arriving by train onsite and alighting under a rising conveyor. Construction continued with the M260 conveyor completing the installation of the fixed conveyors taking coal from the Mine to the Power Station. In June 1973, the SEC announced revised plans for the long-term development of the Morwell Open Cut (now called Hazelwood Mine). Valuable coal deposits under the flood plain area of the Morwell River would now be used earlier than intended. The Morwell River Diversion Project started in 1977 and saw a three kilometre long tunnel constructed to carry the base flow of the river as well as a 3.7 kilometre diversion channel for floodwaters. The tunnel comprised more than 900 individual pipes, each weighing 13 tonnes. At noon on Friday 4 November in 1977, a fire broke out in the north-west corner of the Mine, caused by a spark from a vehicle. A fire control team and support tankers were quickly on the scene but a sharp wind change spread ignited coal particles over several levels of the Mine. Tragedy struck on 9 December 1978, when three employees died in an explosion in the Unit 3 generator. The cause was an incomplete purge of hydrogen. 1980s The 80s was another decade of significant engineering achievements with a number of major projects at Hazelwood. The Half Life Refit project started in May 1982. completed three years later while the oldest dredger in service in the Morwell Open Cut, Dredger 21, underwent a major overhaul in May the following year. A major refurbishment of Unit 3 was undertaken in April 1985. The Plant Life Extension started mid-1986 and was The Open Cut plan for beyond 2000 was developed in November 1988 with a new overburden system planned. The government disaggregated Generation Victoria into five separate, state-owned generating businesses including Hazelwood Power Corporation. In August 1996, the government announced the sale of Hazelwood Power Corporation to the Hazelwood Power Partnership for $2.35 billion. The business was purchased by a consortium led by British giant National Power and other partners. a new century Hazelwood was awarded the inaugural Premier s Foundation Award in July/August 2002 for partnerships at work, recognising the success in developing a partnership approach to improve workplace relations. The playground in the Morwell Town Common officially opened on 1 March, 1998. It was constructed in just six days in a project initiated by Hazelwood and many of its employees. The next few years saw a number of milestones with Hazelwood Power Corporation rebranded as International Power in January 2003 and the first coal from the new Westfield development scooped out by Dredger 11 on 4 February 2004. The following year, Hazelwood s new wetlands sites were established to provide a wide variety of habitats for plants and animals. The official opening of a 7.5 kilometre section of the Strzelecki Highway, south west of Morwell, on 13 March, 2008, marked a significant milestone 2010-2017 in the Rivers and Roads Relocation Project (RRR) as part of the Westfield development. The Mine experienced another fire on 14 September 2008. The fire was under control in three days as a result of the efforts of more than 100 personnel from Hazelwood and its alliance partners, supported by around 70 CFA personnel. The Carbon Capture Pilot Plant officially opened in May/June 2009 following a comprehensive commissioning project. The $10 million pilot project was designed to initially capture 25 tonnes of CO2 a day from just one of Hazelwood s eight generating units. February 2010 saw the most significant river relocation and improvement project ever undertaken in Victoria. The new section of the Morwell River took a previouslymoved section of the river out of an old concrete pipe and into a natural meandering riverine environment. On 4 February 2011, the merger of GDF SUEZ and International Power took place. The same day, torrential rain overwhelmed drains and inundated Hazelwood land, next to Morwell and the freeway, causing a large sink hole in the area of the Morwell Main Drain. The freeway was closed for seven months due to ground movement in an area close to the freeway and the Mine s northern batters. The fire came within 200 metres of the power station on 25 February, providing further challenges for those involved. Some 189 Hazelwood personnel, with support from contractors and Loy Yang B, were engaged in the emergency effort. More than 7000 individual full-time and volunteer firefighters - many returning several times - worked a total of approximately 20,000 shifts over the duration of the fire. The Victorian Government established the Hazelwood Mine Fire Inquiry after the fire, with public hearings held between 26 May and 18 June. On 2 September, the inquiry s report and recommendations were handed down and released to the public. In July 2011, Australian Prime Minister, Julia Gillard, visited Hazelwood followed by Federal Opposition Leader, Tony Abbott. The document outlined 6 recommendations and 17 affirmations to be addressed by GDF SUEZ. On 9 February 2014, fire entered the Hazelwood Mine. It would take 45 days of intensive firefighting to bring to an end one of the most challenging events in Hazelwood s history. On 24 November 2014, Hazelwood marked 50 years of operation. Another name change came on 18 April 2015, when GDF SUEZ became ENGIE. The new name represented the human and positive vision of energy, and a contraction of the word energy. Hazelwood s trial of alternate auxiliary fuels went international on 18 November, following the arrival on site of brown coal briquettes from Germany. The scaling down of Energy Brix led the business to explore alternatives for its auxiliary fuel needs during Power Station startups and shutdowns. closure announced On 3 November 2016, Chief Executive of ENGIE in Australia, Alex Keisser, advised Hazelwood staff of the extremely difficult decision to close all eight generating units by 31 March 2017. At the time, Hazelwood directly employed 750 people - 450 employees and 300 contractors. It supplies up to 25 per cent of Victoria s energy requirements and more than 5 per cent of Australia s total energy demand.

1960s Hazelwood took shape over this decade. Preliminary firing of the Unit 1 boiler on 22 February 1964, was a milestone with briquettes used for the trials. Coal deliveries to the Hazelwood Slot Bunker started in mid-july with the first line of coal conveyors, M162, from Morwell Eastfield to the Station completed the following month. All was ready for commissioning of the first unit in October. In May 1965, parliamentary approval was 1990s given to the SEC to extend Hazelwood to a 1600 megawatt station by the adding a further two, 200 megawatt units. Dredger 10 was ordered in June and the following month, Unit 2 came into service. Dredger 11 was ordered in December. Contracts were let for Units 7 and 8 in 1966, coinciding with the operational start of Dredger 9. Unit 3 started operating in August 1966, Unit 4 in July 1967, Unit 5 August 1968 and Unit 6 in May 1969. THE BEGINNING An Act of the Victorian Parliament on 13 October 1959 signalled the beginning of a project that would change the face of the Valley for more than 50 years. Construction of the Hazelwood Power Station was approved for the eastern slope of the ridge, about three kilometres Morwell Power Station. Initially, six 200 megawatt units would come on stream progressively between 1964 and 1970 as baseload increments. An additional two units were approved by the government in 1965, extending the station to eight units, producing 1600 megawatts. A familiar face at Hazelwood retired from service in August 1994 when the Morwell Open Cut s oldest dredger, Dredger 21, was taken out of operation. The 753 tonne bucket wheel dredger, built in 1955, was relocated to the nearby PowerWorks visitor centre for display and remains there today. Arguably the biggest change to the state s power industry came the following year when the Victorian Government took the first step towards privatising the SEC on 1 February 1995, by transforming it into an entity known as Generation Victoria. power industry and the Latrobe south west of the former An estimated 80,000 cubic metres (150,000 tonnes) of earth collapsed into the mine on 11 February 1992, surrounding Dredger 10 within minutes and pushing it, together with the conveyor and hopper, some 20 metres sideways. The 1800 tonne overburden dredger was operating at the time of the slip however none of the dredger crew was injured. 1970s Hazelwood s final two units started operating in 1970 - Unit 7 in March and Unit 8 in December. On Friday, 12 March 1971, the Station was officially opened. It was planned for Victorian Premier, Sir Henry Bolte, to cut a ribbon but subsequent reports reveal this never happened. The open day attracted thousands of visitors, many arriving by train onsite and alighting under a rising conveyor. Construction continued with the M260 conveyor completing the installation of the fixed conveyors taking coal from the Mine to the Power Station. In June 1973, the SEC announced revised plans for the long-term development of the Morwell Open Cut (now called Hazelwood Mine). Valuable coal deposits under the flood plain area of the Morwell River would now be used earlier than intended. The Morwell River Diversion Project started in 1977 and saw a three kilometre long tunnel constructed to carry the base flow of the river as well as a 3.7 kilometre diversion channel for floodwaters. The tunnel comprised more than 900 individual pipes, each weighing 13 tonnes. At noon on Friday 4 November in 1977, a fire broke out in the north-west corner of the Mine, caused by a spark from a vehicle. A fire control team and support tankers were quickly on the scene but a sharp wind change spread ignited coal particles over several levels of the Mine. Tragedy struck on 9 December 1978, when three employees died in an explosion in the Unit 3 generator. The cause was an incomplete purge of hydrogen. 1980s The 80s was another decade of significant engineering achievements with a number of major projects at Hazelwood. The Half Life Refit project started in May 1982. completed three years later while the oldest dredger in service in the Morwell Open Cut, Dredger 21, underwent a major overhaul in May the following year. A major refurbishment of Unit 3 was undertaken in April 1985. The Plant Life Extension started mid-1986 and was The Open Cut plan for beyond 2000 was developed in November 1988 with a new overburden system planned. The government disaggregated Generation Victoria into five separate, state-owned generating businesses including Hazelwood Power Corporation. In August 1996, the government announced the sale of Hazelwood Power Corporation to the Hazelwood Power Partnership for $2.35 billion. The business was purchased by a consortium led by British giant National Power and other partners. a new century Hazelwood was awarded the inaugural Premier s Foundation Award in July/August 2002 for partnerships at work, recognising the success in developing a partnership approach to improve workplace relations. The playground in the Morwell Town Common officially opened on 1 March, 1998. It was constructed in just six days in a project initiated by Hazelwood and many of its employees. The next few years saw a number of milestones with Hazelwood Power Corporation rebranded as International Power in January 2003 and the first coal from the new Westfield development scooped out by Dredger 11 on 4 February 2004. The following year, Hazelwood s new wetlands sites were established to provide a wide variety of habitats for plants and animals. The official opening of a 7.5 kilometre section of the Strzelecki Highway, south west of Morwell, on 13 March, 2008, marked a significant milestone 2010-2017 in the Rivers and Roads Relocation Project (RRR) as part of the Westfield development. The Mine experienced another fire on 14 September 2008. The fire was under control in three days as a result of the efforts of more than 100 personnel from Hazelwood and its alliance partners, supported by around 70 CFA personnel. The Carbon Capture Pilot Plant officially opened in May/June 2009 following a comprehensive commissioning project. The $10 million pilot project was designed to initially capture 25 tonnes of CO2 a day from just one of Hazelwood s eight generating units. February 2010 saw the most significant river relocation and improvement project ever undertaken in Victoria. The new section of the Morwell River took a previouslymoved section of the river out of an old concrete pipe and into a natural meandering riverine environment. On 4 February 2011, the merger of GDF SUEZ and International Power took place. The same day, torrential rain overwhelmed drains and inundated Hazelwood land, next to Morwell and the freeway, causing a large sink hole in the area of the Morwell Main Drain. The freeway was closed for seven months due to ground movement in an area close to the freeway and the Mine s northern batters. The fire came within 200 metres of the power station on 25 February, providing further challenges for those involved. Some 189 Hazelwood personnel, with support from contractors and Loy Yang B, were engaged in the emergency effort. More than 7000 individual full-time and volunteer firefighters - many returning several times - worked a total of approximately 20,000 shifts over the duration of the fire. The Victorian Government established the Hazelwood Mine Fire Inquiry after the fire, with public hearings held between 26 May and 18 June. On 2 September, the inquiry s report and recommendations were handed down and released to the public. In July 2011, Australian Prime Minister, Julia Gillard, visited Hazelwood followed by Federal Opposition Leader, Tony Abbott. The document outlined 6 recommendations and 17 affirmations to be addressed by GDF SUEZ. On 9 February 2014, fire entered the Hazelwood Mine. It would take 45 days of intensive firefighting to bring to an end one of the most challenging events in Hazelwood s history. On 24 November 2014, Hazelwood marked 50 years of operation. Another name change came on 18 April 2015, when GDF SUEZ became ENGIE. The new name represented the human and positive vision of energy, and a contraction of the word energy. Hazelwood s trial of alternate auxiliary fuels went international on 18 November, following the arrival on site of brown coal briquettes from Germany. The scaling down of Energy Brix led the business to explore alternatives for its auxiliary fuel needs during Power Station startups and shutdowns. closure announced On 3 November 2016, Chief Executive of ENGIE in Australia, Alex Keisser, advised Hazelwood staff of the extremely difficult decision to close all eight generating units by 31 March 2017. At the time, Hazelwood directly employed 750 people - 450 employees and 300 contractors. It supplies up to 25 per cent of Victoria s energy requirements and more than 5 per cent of Australia s total energy demand.

ownership Pre privatisation 1995 2003 2011 2012 2015 engie.com.au