LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Canwood Street work was closed on April 3. Construction of retaining wall and other improvements in the area will continue until August 1.
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Reinforcement and forming of the bridge abutment on the south side
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Falsework for a bent cap, rebar and forms for both bridge bents
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Median bridge bent
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Ramp metering pull boxes at NB off-ramp
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Abutment wall on the south side with City of Calabasas embedded lettering
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Next stage of the project will start on August 4, 2017: New NB off-ramp will be opened; SB on- and off- ramps traffic will be switched to new pavement; Lost Hills Road south of FWY will be switched to new pavement; Duration of next stage is projected to be 5-6 months: SB off-ramp construction with traffic being placed on temporary section; Switch traffic and work on the other side of SB off-ramp; Sound wall and west side of Lost Hills Road north of FWY; Traffic on Lost Hills Road south of FWY will be placed in the middle; Sidewalk, curb & gutter and AT&T and LVMWD work south of FWY Traffic signal, electrical and irrigation work in each work zone
LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Anticipated project schedule: Stage 1 bridge girder and deck (west side) - June-July 2017 Completion of Canwood Street improvements - August 2017 Soundwall completion - July-August 2017 Demolition of the old bridge - August 2017 Stage 2 bridge (east side) - January-February 2018 Landscaping - March-April 2018
LAS VIRGENES ROAD SCENIC CORRIDOR PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL
MAY-JUNE 2016 ROADWAY GRADING The residents were against the road closure and detour for completion of horizontal and vertical realignment of the roadway in front of Paxton project caused approximately two months setback
SEPTEMBER 2016: THE CITY PORTIONS OF THE ROAD PROJECT WERE COMPLETED Two lanes in each direction with landscaped median islands
Winter of 2017 Preparation for a storm event; no run-offs left the Paxton side Rainy weather delayed Paxton project s on-site grading and installation of curb & gutter on the east side of Las Virgenes Road
March 2017 Previously graded east side of the roadway was contaminated with dirt from the Paxton site and needed to be re-graded
UTILITY WORK SCE schedule dependency on completion of underground conduit and appurtenances for transmission lines performed by the developer s contactor delayed the schedule for approximately 3 weeks April 3 Curb & gutter is placed on the Paxton side; SCE crew is working on sub-structures and cable installation
LAS VIRGENES ROAD PROJECT UPDATES April 4 Traffic signal foundations and Edison work
LAS VIRGENES ROAD PROJECT UPDATES April 17-18 Concrete curb & gutter for center medians
LAS VIRGENES ROAD PROJECT UPDATES April 17-26, 2017 East side of Las Virgenes Road, landscaping and sidewalk in front of Paxton
LAS VIRGENES ROAD PROJECT UPDATES April 26 Placement of asphalt south of Willow Glen Street
LAS VIRGENES ROAD PROJECT UPDATES April 26 Asphalt patching on the west side of Las Virgenes Road
LAS VIRGENES ROAD PROJECT UPDATES Current Schedule
Las Virgenes/Thousand Oaks Roundabout Updates
Layout of a Roundabout Community Workshop 3/24/2015 Las Virgenes/Thousand Oaks Roundabout City Council 2
Location of Crosswalk Vehicle length increment away from edge of the circulatory roadway to prevent back of the car encroaching on the exit roadway into the circulatory roadway. Drivers focus attention to vehicles in the circulatory roadway without concerning about any pedestrian crossing Las Virgenes/Thousand Oaks Roundabout City Council 3
Las Virgenes/Thousand Oaks Traffic Characteristics Las Virgenes/Thousand Oaks Roundabout City Council 4
Las Virgenes/Thousand Oaks Traffic Characteristics Las Virgenes/Thousand Oaks Roundabout City Council 5
East Leg Pedestrians East Leg Pedestrians Saturday 4/1/2017 6 7 PM 2 6 5 6 PM 4 6 4 5 PM 2 10 3 4 PM 5 6 2 3 PM 1 8 1 2 PM 12 1 PM 0 2 2 7 Peds Could Use Other Xings Peds Continue on East Leg 11 AM 12 PM 1 7 10 11 AM 3 7 9 10 AM 0 6 8 9 AM 6 8 7 8 AM 1 7 0 2 4 6 8 10 12 Las Virgenes/Thousand Oaks Roundabout City Council 6
Proposed Roundabout Layout Las Virgenes/Thousand Oaks Roundabout City Council 7
Infrastructure Obstacles Las Virgenes/Thousand Oaks Roundabout City Council 8
Video Showing Visibility Issue Visibility Distance of Existing Crosswalk 220 ft No Visibility of Proposed Crosswalk Las Virgenes/Thousand Oaks Roundabout City Council 9
Sample Turning Speed Survey Conducted on April 18, 2017 at 7:35 AM Sample Size 50 Average Speed 27.5 mph 85 th Percentile Speed 31 mph Las Virgenes/Thousand Oaks Roundabout City Council 10
Aerial Video of Right Turning Vehicles on April 19, 2017 at 7:46: AM Las Virgenes/Thousand Oaks Roundabout City Council 11
Locations with Fewer Than 4 Crossings Parkway Calabasas & Calabasas Rd Parkway Calabasas & Park Granada Parkway Calabasas & Paseo Primario Las Virgenes Rd & Agoura Rd Las Virgenes Rd & Lost Hills Rd Calabasas Rd & US 101 Fwy SB Ramps Las Virgenes/Thousand Oaks Roundabout City Council 12
Conclusion Staff recommends that the Council approve construction of the roundabout as shown Las Virgenes/Thousand Oaks Roundabout City Council 13