LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017

Similar documents
Hospital Link Project Project Update September 2015

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

AGENDA ITEM I-6 Public Works

November 21, 2012 Barbara Kelleher, (954)

Public Information Center August 12, 2010

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

Second Street Improvements Project Project Update Archive

Weekly construction update

October 31, 2014 Chuck McGinness, (954)

Transportation TRANSPORTATION PROJECTS

Ohio Department of Transportation Construction Update

Mason Street Bike/Pedestrian Trail Project

PRESENTED TO Town of Middlebury, VT. PRESENTED BY VTrans, VHB, Fitzgerald & Halliday, Inc., and Kubricky Construction

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

Hospital Link Project Project Update Winter 2018

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

BUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019

December 2012 Update. I-95 New Haven Harbor Crossing. Corridor Improvement Program

Atlantic Street Bridge Project CTDOT Project Nos & (Phase 2)

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018


Exposition Light Rail Transit Project

Palm Beach County Traffic Report July 13 through July 20, 2012

City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Florida Department of Transportation MIKE DEW SECRETARY

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

City of Grand Island Tuesday, December 12, 2017 Council Session

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

Route 29 Solutions Projects

MEMORANDUM VILLAGE OF NORTHBROOK

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Impact Report

Florida Department of Transportation ERIK FENNIMAN INTERIM SECRETARY

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Guide to. Road Construction Projects

THREE MILE PLAN TOWN OF SUPERIOR COLORADO

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

ADVANCED WARNING SYSTEM FOR SHARED USE CROSSING ON HOWARD STREET EAST OF NORDICA AVENUE

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

LUDWIG RD. SUBDIVISION PROJECT TRAFFIC IMPACT ANALYSIS

Site Location and Setting

Grade Crossings in High Speed Rail Corridors

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

25 th Avenue Grade Separation. September 13, 2017

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

PRIORITIES COMMITTEE MEETING

Palm Beach County Traffic Report August 24 through August 31, 2012

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop.

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Crenshaw/LAX Transit Project Construction Community Meeting July 26 th, 2017

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014

ROUTE 630 DIVERGING DIAMOND INTERCHANGE

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016

State Route 8 Corridor. Northern Summit County s Path to Success

Monday, September 18, 2017 Sunday, October 1, 2017

Welcome to the Illinois High-Speed Rail Chicago to St. Louis Construction Update Meeting. Today s meeting will provide an overview of the Program,

2 Construction Program

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

FOR IMMEDIATE RELEASE February 22, 2019 CONTACT: Jen K. Ward, SALEM 69

Construction Staging Adelaide Street West

Riverside County Transportation Department Summary of Bids

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects

Caltrans District 5. District Director s Report A quarterly publication for our transportation partners. Rosales leads Program Project Management

Project Start Date: Project Completion Date: July 1, Contractor: Mattson Construction Contact Information: Nate Lillemon

Carlisle Connectivity Projects Communication Plan and Project Status

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

FDOT Treasure Coast Traffic Impact Report

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

Florida Department of Transportation Daniels Parkway Fort Myers, FL 33913

Projected Advertisement Date

4. Safety Concerns Potential Short and Medium-Term Improvements

US 19 Sunset Point Rd to Countryside Blvd.

95 Express Lanes: Before/After Study

Northeast Corridor Transportation Update

WEEKLY HIGHWAY ALERT RICHMOND DISTRICT

ABINGDON v ELEMENTARY SCHOOL

Section 3-04 Cross Sectional Elements TABLE OF CONTENTS. INTRODUCTION...3 General...3 Exhibit 1-Cross-Sectional Elements...3

Important Lane Closures, April 3 9, 2011

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

ELECTION SIGN GUIDELINES

RESORT AREA STRATEGIC ACTION PLAN (RASAP) STEERING COMMITTEE MEETING - APRIL 3, 2019

Atlantic Street Bridge Project Update CTDOT Project Nos & (Phase 2)

MEMORANDUM. Honorable Mayor and City Councilmembers William S. Joynes, Sr., City Administrator

First rail. August 2011

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

WHO IS METROLINX?

Transcription:

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Canwood Street work was closed on April 3. Construction of retaining wall and other improvements in the area will continue until August 1.

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Reinforcement and forming of the bridge abutment on the south side

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Falsework for a bent cap, rebar and forms for both bridge bents

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Median bridge bent

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Ramp metering pull boxes at NB off-ramp

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Abutment wall on the south side with City of Calabasas embedded lettering

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Next stage of the project will start on August 4, 2017: New NB off-ramp will be opened; SB on- and off- ramps traffic will be switched to new pavement; Lost Hills Road south of FWY will be switched to new pavement; Duration of next stage is projected to be 5-6 months: SB off-ramp construction with traffic being placed on temporary section; Switch traffic and work on the other side of SB off-ramp; Sound wall and west side of Lost Hills Road north of FWY; Traffic on Lost Hills Road south of FWY will be placed in the middle; Sidewalk, curb & gutter and AT&T and LVMWD work south of FWY Traffic signal, electrical and irrigation work in each work zone

LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Anticipated project schedule: Stage 1 bridge girder and deck (west side) - June-July 2017 Completion of Canwood Street improvements - August 2017 Soundwall completion - July-August 2017 Demolition of the old bridge - August 2017 Stage 2 bridge (east side) - January-February 2018 Landscaping - March-April 2018

LAS VIRGENES ROAD SCENIC CORRIDOR PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL

MAY-JUNE 2016 ROADWAY GRADING The residents were against the road closure and detour for completion of horizontal and vertical realignment of the roadway in front of Paxton project caused approximately two months setback

SEPTEMBER 2016: THE CITY PORTIONS OF THE ROAD PROJECT WERE COMPLETED Two lanes in each direction with landscaped median islands

Winter of 2017 Preparation for a storm event; no run-offs left the Paxton side Rainy weather delayed Paxton project s on-site grading and installation of curb & gutter on the east side of Las Virgenes Road

March 2017 Previously graded east side of the roadway was contaminated with dirt from the Paxton site and needed to be re-graded

UTILITY WORK SCE schedule dependency on completion of underground conduit and appurtenances for transmission lines performed by the developer s contactor delayed the schedule for approximately 3 weeks April 3 Curb & gutter is placed on the Paxton side; SCE crew is working on sub-structures and cable installation

LAS VIRGENES ROAD PROJECT UPDATES April 4 Traffic signal foundations and Edison work

LAS VIRGENES ROAD PROJECT UPDATES April 17-18 Concrete curb & gutter for center medians

LAS VIRGENES ROAD PROJECT UPDATES April 17-26, 2017 East side of Las Virgenes Road, landscaping and sidewalk in front of Paxton

LAS VIRGENES ROAD PROJECT UPDATES April 26 Placement of asphalt south of Willow Glen Street

LAS VIRGENES ROAD PROJECT UPDATES April 26 Asphalt patching on the west side of Las Virgenes Road

LAS VIRGENES ROAD PROJECT UPDATES Current Schedule

Las Virgenes/Thousand Oaks Roundabout Updates

Layout of a Roundabout Community Workshop 3/24/2015 Las Virgenes/Thousand Oaks Roundabout City Council 2

Location of Crosswalk Vehicle length increment away from edge of the circulatory roadway to prevent back of the car encroaching on the exit roadway into the circulatory roadway. Drivers focus attention to vehicles in the circulatory roadway without concerning about any pedestrian crossing Las Virgenes/Thousand Oaks Roundabout City Council 3

Las Virgenes/Thousand Oaks Traffic Characteristics Las Virgenes/Thousand Oaks Roundabout City Council 4

Las Virgenes/Thousand Oaks Traffic Characteristics Las Virgenes/Thousand Oaks Roundabout City Council 5

East Leg Pedestrians East Leg Pedestrians Saturday 4/1/2017 6 7 PM 2 6 5 6 PM 4 6 4 5 PM 2 10 3 4 PM 5 6 2 3 PM 1 8 1 2 PM 12 1 PM 0 2 2 7 Peds Could Use Other Xings Peds Continue on East Leg 11 AM 12 PM 1 7 10 11 AM 3 7 9 10 AM 0 6 8 9 AM 6 8 7 8 AM 1 7 0 2 4 6 8 10 12 Las Virgenes/Thousand Oaks Roundabout City Council 6

Proposed Roundabout Layout Las Virgenes/Thousand Oaks Roundabout City Council 7

Infrastructure Obstacles Las Virgenes/Thousand Oaks Roundabout City Council 8

Video Showing Visibility Issue Visibility Distance of Existing Crosswalk 220 ft No Visibility of Proposed Crosswalk Las Virgenes/Thousand Oaks Roundabout City Council 9

Sample Turning Speed Survey Conducted on April 18, 2017 at 7:35 AM Sample Size 50 Average Speed 27.5 mph 85 th Percentile Speed 31 mph Las Virgenes/Thousand Oaks Roundabout City Council 10

Aerial Video of Right Turning Vehicles on April 19, 2017 at 7:46: AM Las Virgenes/Thousand Oaks Roundabout City Council 11

Locations with Fewer Than 4 Crossings Parkway Calabasas & Calabasas Rd Parkway Calabasas & Park Granada Parkway Calabasas & Paseo Primario Las Virgenes Rd & Agoura Rd Las Virgenes Rd & Lost Hills Rd Calabasas Rd & US 101 Fwy SB Ramps Las Virgenes/Thousand Oaks Roundabout City Council 12

Conclusion Staff recommends that the Council approve construction of the roundabout as shown Las Virgenes/Thousand Oaks Roundabout City Council 13