Monthly Traffic Update

Similar documents
The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

Important Lane Closures, April 3 9, 2011

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

FDOT Treasure Coast Traffic Impact Report

Day and night work: Hills M2 Motorway tunnel portals and Coral Tree Drive electrical substation

Brisbane Airport Corporation. Operating procedures

Pedestrian Safety Review Spadina Avenue

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

Neighbourhood Committee NDG - Westmount. September 12, 2016

2017 POLICY DOCUMENT. M1 Action Plan. Putting Queenslanders First

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

NDG-Westmount Neighbourhood Committee. November 16, 2015

November 21, 2012 Barbara Kelleher, (954)

Palm Beach County Traffic Report August 24 through August 31, 2012

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30

5.7 Local road upgrades

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Waverley Council Executive Manager, Creating Waverley Waverley Council Manager, Transport and Development Waverley Council Traffic Engineer

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

Brisbane Airport Overview. To City

Parking Amendments - Bay Street, between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

7.0 GROUND TRANSPORT DEVELOPMENT PLAN OVERVIEW. Sydney Airport Master Plan

Concord Road Interchange. Standard hours of work

Brisbane Airport Corporation Register of Building Applications

FDOT Treasure Coast Traffic Report through

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

Brisbane Airport Corporation Register of Building Applications

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

2017 Work and Launch of the Next Phase. Information meeting, Montréal-Ouest September 14, 2017

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release.

GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop.

Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

FDOT Treasure Coast Traffic Impact Report

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

The Point Roundabout Improvement Scheme

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

Brisbane Airport Ground Transport Operators Forum Tuesday 25 July, 2pm Brisbane Airport Meeting Room Ground Transport Operators

A. CONCLUSIONS OF THE FGEIS

Palm Beach County Traffic Report July 13 through July 20, 2012

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

Hospital Link Project Project Update Winter 2018

Bridging Brisbane Survey 2017 Supplementary Report

October 31, 2014 Chuck McGinness, (954)

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

Important Lane Closures March 1 5, 2010

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO

PROJECT UPDATE BETTER TIMES AHEAD ON CLEM7 CLEM JONES TUNNEL. Fast facts AUGUST 2008

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

Sky Temporary Car Park Transport Statement

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014

Neighbourdhood Committee NDG-Westmount. October 16, 2017

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

D L R C C T R A F F I C N E W S

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.

M2 Junction 5. improvements scheme. Preferred route announcement

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/14/ :00:05 PM

All closures this week happen at night, including full closures of Mesa and I-10

Road Closure & Traffic Mangement Information during the 2018 ASICS Windermere Marathon Race.

Gold Coast. Rapid Transit. Chapter content. Chapter four Route selection and staging

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee. PW Royal Bank of Canada Canadian Open

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

Road Signs, Markings and Their Meaning

Chapter 2 Route window W25 Maidenhead station. Transport for London

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

Guide to. Road Construction Projects

M621. Junctions 1 to 7 Improvement scheme. Share your views

Brisbane Airport Corporation Register of Building Applications

PRIORITIES COMMITTEE MEETING

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County

Road Construction Ahead January-April 2015 NORTHWEST REGION

PennDOT Interstate Work next week March 30-April 3:

OREGON DEPARTMENT OF TRANSPORTATION STATEWIDE ROAD, WEATHER AND INCIDENT CONDITIONS 9/5/2018 2:12:06 PM

Construction Staging Area Blue Jays Way (357 King Street West)

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018

TERMINAL DEVELOPMENT PLAN

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

5.1 Traffic and Transportation

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

WOKING INTEGRATED TRANSPORT PROJECT

Weekly construction update

Greater Shepparton City Council Planning Scheme Amendment C192 and C193 VicRoads Submission to Traffic Conclave

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Route 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016

Construction Staging Adelaide Street West

Transcription:

Brisbane Airport Corporation Monthly Traffic Update PAGE 1 ISSUE 26 DECEMBER 2009 Northern Access Road Project opens 3 December Brisbane Airport Corporation (BAC) is pleased to announce that after two years of construction the Northern Access Road Project (NARP) is due to open on Two major roads and a number of link roads and bridges will be opened during the night of Wednesday 2 December into the early hours of The new major roads are: Moreton Drive - linking the new Gateway Motorway to Brisbane Airport via exit 108. Nancy-Bird Way - linking Moreton Drive to the International Terminal. The opening of these new roads will create a second major access into and out of Brisbane Airport, reducing traffic on Airport Drive by around 40 percent. BAC would like to thank airport users for their patience during construction. Please see the NARP brochure attached with this traffic update or visit www.brisbaneairport.com.au for details about how the NARP works. Moreton Drive joins the Domestic Terminal precinct. NARP OPENING DETAILS Moreton Drive, Nancy-Bird Way, the associated link roads and bridges and new entries to car parks in the Domestic Terminal will be opened during the night of Wednesday 2 December into the early hours of The following are target times for the opening of various parts of the project: Moreton Drive outbound from the terminals - open from 10:30pm Wednesday 2 December. Moreton Drive inbound to the terminals - open from 2:00am Nancy-Bird Way (both directions) - open from 2:00am New entries to the Domestic Terminal s undercover, PARKLONG car park (at the northern end of the car park, accessed via Moreton Drive or Dryandra Road) - open from 8:00pm Wednesday 2 December. New entries into the Domestic Terminal s open-air PARKSHORT car park (accessed via Moreton Drive or Dryandra Road) - open from 8:00pm Wednesday 2 December. New open-air PARKSHORT car park (best for Virgin Blue and Jetstar) open from 8:00pm Wednesday 2 December - access via Chloris Street off ive. Please keep in mind that weather and other unforeseen circumstances may impact these targets. Police and traffic controllers will be in place to assist with traffic management during the transition. Until Moreton Drive opens, access to the Domestic Terminal will remain via ive only.

Chloris St PAGE 2 DOMESTIC TERMINAL PRECINCT WORKS In the lead up to the opening of Moreton Drive, road works will be undertaken in and around the Domestic Terminal precinct. Traffic controllers and police will be on site during these works to assist with traffic management. Expect delays in the Domestic Terminal Precinct between 8:00pm on Monday 30 November and 4:00am on Works include (see map below): Closure of Alpinia Drive between the hours of 8:00pm and 4:00am with all Domestic Terminal bound traffic diverted along Dryandra Road. Entrance to the Domestic Terminal precinct will be made under temporary police control via the new intersection of Dryandra Road and Moreton Drive. Access to the undercover PARKLONG car park will be via the new entries at the northern end of the car park. Access to the existing open-air PARKSHORT car park will be via the reversed Alpinia Drive. Please note that there will be no access to the open-air PARKSHORT car park on the following dates during the following hours: Tuesday 1 December - between the hours of 1:00am and 4:00am. Wednesday 2 December to Thursday 3 December - between the hours of 11:00pm and 2:00am. You will be directed to park in the undercover PARKLONG car park during these times. Dryandra Rd Moreton Dr No access to Alpinia Drive Terminal face roads Domestic Terminal New open-air car park - best for Virgin Blue / Jetstar (up to 4 hours) OPEN 3 DECEMBER Access arrangements for Domestic Terminal Precinct works NARP FINISHING WORKS NARP finishing works will continue for a least two weeks following the opening of Moreton Drive and Nancy-Bird Way. In addition to these works, the replacement of temporary lighting and some remediation works may continue until February 2010. Landscaping works will continue until mid 2010. Where possible, these works will be undertaken at night between 9:00pm and 5:00am, from Sunday to Friday. Temporary lane closures, reduced speed limits and advisory signage may be implemented and during these works, Bridge 1 will be converted to one lane. Traffic controllers will be in place to assist where necessary. Road users are asked to proceed with caution and be aware of changing road conditions. In addition, there will be speed reductions and temporary lane closures within the Domestic Terminal precinct between 3 December 2009 and late December 2009 to facilitate finishing works. ive / Lomandra Drive Night Works Work in this area may result in the intermittent closure of the right hand turn lane from ive into Lomandra Drive, and the right hand turn lane from Lomandra Drive into ive. For motorists wishing to turn right from ive into Lomandra Drive: travel along ive to make a U-turn at the International Terminal Roundabout, returning on the outbound lanes of ive to turn left into Lomandra Drive. For motorists wishing to turn right from Lomandra Drive into ive: turn left from Lomandra Drive into Airport Drive to make a U-turn at the East-West Arterial roundabout, returning on the inbound lanes of ive to the terminals.

PAGE 3 GATEWAY UPGRADE PROJECT (GUP) Changed traffic conditions north of the Gateway Bridge On Thursday 3 December, the new Gateway Motorway airport interchange (Exit 108) will open to link with the NARP s Moreton Drive. To accommodate the changes to traffic between the airport and the old and new Gateway Motorway and to optimise traffic flow, the following southbound traffic configurations will be in place: New Gateway Motorway three lanes merge to two lanes near Kingsford Smith Drive overbridge and continue through to the existing Gateway Bridge. New Gateway Motorway a new Kingsford Smith Drive on-ramp southbound to the Gateway Bridge. Local traffic can continue to use Links Avenue. Old Gateway Motorway the current southbound carriageway near Links Avenue will be reduced to a single lane. For a map of these changes, see page 4 of this traffic update. For further information, visit www.gup.com.au AIRPORT ROUNDABOUT UPGRADE (ARU) Thiess John Holland is undertaking this project on behalf of the Queensland Government. We include information about the work in the BAC Traffic Update because parts of the work on the project occur on airport land. If you have any queries about the project please call the team s freecall information line on 1800 721 783 or visit the website at www.brisconnections.com.au New Gateway Motorway overpass The night time installation of Super T bridge girders for the new Gateway Motorway overpass is nearly complete with the remaining 10 to be installed in mid to late December. The Super Ts are approximately 36 metres long, which means they must be delivered and installed at night when the volume of traffic is minimal. During installation, motorists can expect shortterm lane closures and detours of the roundabout and Gateway Motorway between 10:00pm and 4:00am. Detailed notification of these changes will be via electronic message boards, 131940.com and SMS traffic alerts. You can register for SMS traffic alerts at brisconnections.com.au New East-West Arterial flyover The East-West Arterial Road has been realigned to the south to allow construction activities for the flyover to commence on the northern side of the road. Piling work continues along the northern side of East-West Arterial Road for the new flyover. Night work for the piling will include crane operations and pre-drilling so that the piles can be driven during the day. Ground improvement work will be ongoing along the northern side of East-West Arterial Road in preparation for construction of the western bridge abutment. Earthwork and pavement installation will commence shortly on ive in preparation for the realignment of the eastbound traffic to the north. This realignment will enable construction of the flyover to commence in the middle of the road between the eastbound and westbound lanes. Bicycle Route Changes With barriers now installed along East-West Arterial Road, bicycle access to the East-West Arterial Road and Nudgee Road intersection is via the existing on-road cycle facility along Widdop Street, Gellibrand Street, Zillman Road and Gerler Road. A 0.5 metre shoulder has been maintained following barrier installation on the outer shoulder of the Airport Roundabout. Service Relocations The relocation of essential services including electricity, sewerage, water main and telecommunications is ongoing within the roundabout and on East-West Arterial Road, Gateway Motorway, ive, Qantas Drive, Lomandra Drive, Nudgee Road and Serpentine Road. As a result of this work there may be intermittent short-term lane closures on Nudgee Road and East-West Arterial Road. BRISBANE CITY COUNCIL Kingsford Smith Drive Upgrade Harvey St to Theodore St Brisbane City Council is upgrading Kingsford Smith Drive between Theodore Street and Harvey Street, at Eagle Farm, as part of the Road Action Program. Construction is due to start in early 2010, and should be complete in early 2011, weather permitting. Construction will mostly occur between 7:00am and 5:00pm from Monday to Saturday. However, night works between 9:00pm and 5:00am and works on Sunday will be necessary for some of the work. The speed limit through the work area will be reduced to 40km/h and traffic control will be in place throughout construction. Motorists should expect some minor delays when travelling through the area. Safe pedestrian and cyclist access through the worksites will be maintained at all times. To register for fortnightly email updates or for further information: Phone: Email: Visit: Write to: 1800 727 923 or (07) 3403 8888 (after hours) roadactionprogram@brisbane.qld.gov.au www.brisbane.qld.gov.au (go to Traffic & Transport / Transport Plans & Projects and Kingsford Smith Drive Harvey Street to Theodore Street upgrade project). Kingsford Smith Drive Harvey Street to Theodore Street upgrade project GPO Box 1434 Brisbane QLD 4001

PAGE 4 Changed traffic conditions north of the Gateway Bridge - maps GATEWAY BRIDGE PRECINCT, EAGLE FARM New Gateway Motorway with improved connections via a northbound off-ramp to Kingsford Smith Drive and a new southbound on-ramp from Kingsford Smith Drive recommended route. AIRPORT INTERCHANGE, BRISBANE AIRPORT PRECINCT New Gateway Motorway connects with Brisbane Airport access road, via Exit 108, Moreton Drive. SOUTH OF NUDGEE ROAD, BANYO New Gateway Motorway connects with Old Gateway Motorway and also provides access to Brisbane Airport. City and Northern suburbs should use the Old Gateway Motorway

New interchange opening 3 December Lakeside Dr PAGE 5 Signalised intersection Dryandra Road Moreton Drive Bridge 4 No access to CPA until mid-2010 Bridge 3 Bridge 2 EXIT 108 International Terminal Bridge 1 NORTHGATE Domestic Terminal Bridge 4 connects ive to the Northern Access Road Chloris Street Gateway Motorway Banksia Place Hakea Street Nancy-Bird Way Airtrain Qantas Dr Boronia Rd Boronia Rd Lomandra Dr Viola Pl Old Gateway Motorway Airtrain Airport Roundabout Upgrade 40 3 1 2 Hibiscus Street (access from ive closed, entry via Chloris Street) 50 Northern Access Road Project Moreton Drive Gateway Upgrade Project (GUP) and Gateway Bridge Duplication (7 km section between Nudgee and Eagle Farm opened July 2009) Airport Roundabout Upgrade Inbound cycle route Outbound cycle route Airport Land Boundary 1. Existing multi-level PARKLONG car park (includes PARKVALET, best parking 4+hrs all airlines) New entries to this car park via Moreton Drive or Dryandra Road. 2. Existing open-air PARKSHORT car park (best for parking up to 4hr all airlines) Access via Moreton Drive or Dryandra Road. 3. New PARKSHORT car park (best for parking up to 4hrs Virgin Blue and Jetstar) Open from 3 December, Access from Chloris Street via ive. Sugarmill Road BAC Offices The Circuit DFO The Boulevard Cycling on Airport PLEASE NOTE: Cycling is not permitted on the new Moreton Drive. The designated cycle route (as shown on the map above) via Charlie Earp Bridge, Lakeside Drive and Qantas Drive will remain operational once the new road system has opened. In the interests of safety, it is vital that cyclists adhere to the designated route. A map showing the designated route can be found at www.brisbaneairport.com.au by clicking on the Major Projects link.