NDG-Westmount Neighbourhood Committee November 16, 2015
2 Feedback on previous questions Order-in-Council 890-2010 - condition 8 The ministère des Transports must : Establish a buffer zone at the foot of the Saint-Jacques escarpment of at least 9.7 hectares. The average width of this zone must be at least 30 meters; Recreate a wetland at the foot of the Saint-Jacques escarpment fed by rainwater from the escarpment, groundwater, and, if needed, by pretreated rainwater from the road network; Replant trees on the land acquired along boulevard de Sainte-Anne-de- Bellevue and certain parts of the Saint-Jacques escarpment.
3 Feedback on previous questions
4 Update on the Work Redeveloping rues Saint-Rémi/Saint-Jacques/Pullman Strengthening and diverting the collector Maintenance Work Construction of structures for Route 136 Rues Saint-Rémi/Saint-Jacques sector Avenue Greene sector Work on boulevard Angrignon Work on Montréal-Ouest interchange Closure of avenue Saint-Pierre entry Work on boulevard de Sainte-Anne-de-Bellevue sector Closure of rue De Courcelle / chemin Glen
5 Saint-Rémi / Saint-Jacques / Pullman Reopening of exit no 2 rue Saint-Jacques scheduled end of November LONG-TERM CLOSURE Exit n o 2 Rue Saint-Jacques 5
6 Strengthening and Diverting the Collector Road marking at intersection Traffic light : time for pedestrians crossing
7 Maintenance Work Weekend of November 20, 2015 from Friday at 11:00 p.m. until Monday at 5:00 a.m. CLOSURE A-15 SOUTHBOUND CLOSURE A-20 EASTBOUND TOWARD A-15 SOUTHBOUND CLOSURE A-720 WESTBOUND TOWARD A-15 SOUTHBOUND CLOSURE EXIT 62 BOUL. DE LA VÉRENDRYE/AV. DE L ÉGLISE CLOSURE BOUL. DE LA VÉRENDRYE TOWARD A-15 SOUTHBOUND
8 Structures for Route 136 Rues Saint-Rémi/Saint-Jacques sector Caisson piles will be driven for the structure that will cross rues Saint- Rémi and Saint-Jacques Approximate location of caisson piles
9 Structures for Route 136 (cont.) Rues Saint-Rémi/Saint-Jacques sector View from rue Saint-Rémi looking north
10 Structures for Route 136 (cont.) Greene Avenue sector Closure of Selby Park Clearing of part of green space Installation of a temporary sound barrier between Greene and Brooke avenues Approximate work area Temporary sound barrier
11 Structures for Route 136 (cont.) Construction of temporary detour Scheduled to come into service in the fall of 2016
12 Work on boulevard Angrignon Reopening of boulevard Angrignon with its temporary configuration on November 13, 2015 Temporary configuration of Angrignon Blvd New structure
13 Work on boulevard Angrignon (cont.) Dismantling of the north section of the overpass to create a connection between temporary configurations
14 Work on Montréal-Ouest Interchange Closure of R-138 / H-20 access ramps Dismantling of railway tunnel Relocation of rail corridor
15 Closures rue Notre-Dame Ouest 1. Closure of three out of four lanes (3/4): November 21 and 22, 2015 Alternating traffic with flagman 2. Closure of a westbound lane: November 15, 2015 Work related to temporary exit 2. 1. Temporary exit Hindrances
16 Closure of Avenue Saint-Pierre entry Construction of a temporary exit on rue Notre-Dame ouest to maintain traffic flow H-20 East Temporary exit Closure Movement towards exit Conflicting movement towards H-20 eastbound
17 Closure of Avenue Saint-Pierre entry (cont.) Overnight closure - November 23 to 24, 2015 Closure of a section of Montreal-Toronto Blvd. Detour via Notre-Dame Ouest Street and H-20 eastbound on Angrignon Blvd. Detour H-20 eastbound
18 Work on Montréal-Ouest Interchange (cont.) Entry into service of temporary exit : December 2015 Start of work around the railway tunnel in preparation for dismantling (winter 2016) Temporary exit New structure Closures Detour H-20 West towards Sainte-Anne-de-Bellevue Blvd.
19 Work on Montréal-Ouest Interchange (cont.) Closure of access ramps H-20 /R-138: December 2015 Start of work around the railway tunnel in preparation for dismantling (winter 2016) Temporary exit New structure Closures Detour H-20 West Detour H-20 East Detour R-138 West
20 Work on boul. Sainte-Anne-de-Bellevue Sector Construction of a retaining wall along rue Pullman Installation of a temporary retaining wall
21 Closure of rue De Courcelle / chemin Glen November 23 to mid-january 2016 Bike path will remain open on west side Building cutoff wall Excavation Install sheet pile cutoff wall Filling and paving Closure Rue Saint-Antoine Ouest Local traffic and access to businesses
22 Questions
23 For More Information NDG-Westmount neighbourhood committee January 18, 2016 Sud-Ouest neighbourhood committee December 8, 2015 Website dedicated to the project: www.turcot.gouv.qc.ca Twitter @MTQ_Turcot Monthly electronic bulletins (subscribe via the Turcot website) Dedicated telephone line: 514 873-1372 Turcot email: turcot.commentaires@mtq.gouv.qc.ca