1 Dilmunia Development Fund I L.P. INVESTORS REPORT July 1st, 2016 to December 31st, 2016 Enchancing Life, Restoring Balance
2 Contents: Dilmunia Key Developments Master Plan Design Process Infrastructure Works Sales and Marketing Upcoming Activities Appendix Dear Investors, Welcome to the 23rd edition of the Dilmunia Development Fund I L.P. Investors Report, covering the period from July 2016 to December On behalf of Ithmaar-Dilmunia General Partner Company Limited ( GP / the Company ), we are happy to report continued steady progress in Dilmunia infrastructure work and its sub-developers projects. Our latest retail residential mast plan release was Jenina, a development in the southeast side of Dilmunia consisting of 39 residential plots, which was announced to the public towards the end of the previous reporting period, in June Sales expectations have been met and all villa plots are now sold. We are pleased as well to announce progress in Dilmunia s Phase 2 infrastructure works, which cover the eastern part of the master development, and our preparation for Phase 3, the last infrastructure phase. In parallel, construction continued on schedule on a number of other developments in Dilmunia, including SeaVilla, Temara, The Treasure, and Essence at Dilmunia. Other projects, including the Dilmunia shopping mall, Canal View, Residence Sharq, and Hanging Gardens have completed designs and are ready to start construction during 2017, while the South West Residential Development is in the design development stage. Coordination with public authorities continued during the reporting period on different aspects concerning the Dilmunia development. The electrical network pertaining to Phase 1 is now fully energised. Phase 1 streets are now lightening at night and the first individual electrical meters for residential units were also installed during the reporting period. In addition, the fixed telecommunication network was completed and all plots in Phase 1 are now serviced with fiber optic cables. Finally, soft landscaping and palm tree planting on the main roads in Dilmunia began in November We remain on schedule towards meeting all targets related to Dilmunia s individual projects, infrastructure and the master plan. We look forward to updating you on further developments as the project continues to progress. Best regards, Fund Manager, Ithmaar Bank B.S.C. ( Ithmaar ) 2 Fund Report
3 Dilmunia Key Developments Dar Al-Handasah Consultants (Shahir and Partners) is preparing the design for Dilmunia Gateway Bridge. Development Control Guidelines ( DCG ) for sub-developers of plots in Phase 1 and Phase 2 have been issued. The Primary Electrical Substation for Phase 1 was energised in August The electricity transmission connection to Dilmunia has been completed. Jenina, a development in the southern east part of Dilmunia consisting of a total of 39 residential plots, was announced to the public in June The response has been remarkable, with all villa plots now sold. Construction of Phase 2 infrastructure works, including, the arterial bridge, the second bridge in Dilmunia, are progressing well. Plot and street numbering details were received from authorities and first address plates were fixed during the reporting period. Cadastral survey drawings for Phase 1 are completed and transmitted to the concerned authorities. Phase 1 fiber optic network installations are completed, and a completion certificate signed in December Master Plan Further to the completion of Cadastral Survey drawings covering the western part of Dilmunia and its submission to the Survey and Land Registration Bureau, Phase 2 cadastral survey drawings are being prepared for the eastern side of Dilmunia, and are expected to be completed towards the end of Phase 2. Building permit procedures with the Muharraq Municipality have been established and building permits issued to all projects under construction on site. Plot and street numbering as per authorities requirements were received in June 2016, following a request sent to the Central Informatics Organization ( CIO ), and the first plate numbers were fixed in Dilmunia during the reporting period. Dilmunia s block number is 269. Design Process A Request for Proposal ( RFP ) for detailed design and supervision services for the Canal was launched in Q3 2016, with seven companies expressing interest. The first assessment report has been completed and clarification meetings will be held with the preferred bidders. Design of the Canal District Development ( CDD ) is progressing towards final submission. Ansari Engineering Services has been appointed to perform the design consultancy services required for civil works relating to the second 66kv primary substation. SNC Lavalin has been appointed to perform design consultancy services for the second 66kv primary substation plant. Phase 3 infrastructure drawings are being updated and the third bridge in Dilmunia, located over the marina, is being designed. Soft and hard landscaping for the canal and marina areas, roads, and other open spaces in Dilmunia are ready for implementation. Design work on the Dilmunia Gateway Bridge ( DGB ) 3 Fund Report
4 progressed during the reporting period, with the preliminary design being completed in October Water transmission designs have been issued and approved, and are awaiting final Wayleave approval from the authorities for the beginning of construction. Infrastructure Works walkway block paving on roads in Phase 1 progressing. The reporting period witnessed the first soft landscaping plantation on site. Site investigations for Dilmunia Gateway Bridge, needed for the detailed design, were completed in November Cebarco s scope of work in relation to Phase 2 infrastructure are progressing well with the completion date set for end of As Phase 2 Infrastructure works started in March 2016, works on the arterial bridge, the second bridge in Dilmunia, which is located over the canal, are progressing. Further to the Planning Permission drawings for the water transmission pipeline being circulated, Wayleave documents were issued to the concerned public authorities. Wayleave was granted by all authorities except the Roads Planning and Design Directorate ( RPDD ), whose final approval is subject to the resolution of a Letter of Undertaking between the RPDD and the Electricity and Water Authority ( EWA ) regarding any future pipeline diversions resulting from the RPDD s future plans to expand the Dry Dock Highway. With regards to Phase 1 infrastructure, Cebarco continued attending to various identified defects as per defect liability period requirements. Construction works on the foul water network is progressing, as is work on the water distribution and storm water networks. Secondary 11 KV electrical substation civil works also started. Keller, the sub-contractor for piling works, completed foundation and piles construction work relating to the Arterial Bridge during the reporting period. Arterial bridge sub-structure works, including pile and pile cap construction, have been completed and work on the superstructure is set to start soon. The temporary access road, which was completed in May 2016, now allows permanent access to the first residences. Hard landscaping works resumed in H2 2016, with Black paving bricks and installation of light poles on Wellness Road Casting of Pile Cap Foul water pipe laying at the Arterial Road Installation of rings for pumping stations Palms - Access to Temara A view of the south-west part of Dilmunia 4 Fund Report
5 Sales and marketing Current Projects Status Several third party projects are reaching visible construction milestones. Our team is keeping close coordination with sub-developers, giving them guidance and assistance. Jenina Jenina, a development located in the southern part of Dilmunia and consisting of a total of 39 residential plots (four assigned for residential buildings and 35 for residential villas), was announced to the public in June It covers a total area of approximately 36,850 square metres with a net sellable land area of approximately 26,600 sqm. Road leading to Temara Res 49 As the final designs have been approved, construction on a plot located in the centre-north of Dilmunia, with a total area of approximately 3,152 sqm, will start after the issuance of the building permit. SeaVilla Development Project The handover of the units started in H and is still ongoing. Start of construction on the third villa in Temara Private Villa A plot located in the south of Dilmunia with an area of approximately 5,606 sqm has been purchased for the construction of a private villa, with enabling and land preparation works having started in Q Superstructure works were completed during the reporting period. Construction of the luxurious Seavilla sub-development is completed Temara Temara plot purchasers continued to submit individual villa designs for approval during this period as construction continued on the first two plots, with one additional villa starting construction during the reporting period. Designs for five other villas have been approved and construction will start after receipt of building permits. Construction of Private Villa 5 Fund Report
6 The Treasure The Treasure, a project of Bahraini developer, Bin Faqeeh Real Estate Investment Company S.P.C. which is being developed on an approximately 8,100 sqm piece of land, will be a high quality residential 12 storey apartment complex comprised of around 230 living spaces. Works are progressing on site and construction of the superstructure and external works have been completed. Glass cladding was started and completed during the reporting period. The project is expected to be finished during Q Dilmunia Shopping Mall During the reporting period, the final designs were approved and the building permit received by the sub-developer. Construction is planned to commence during The full majestic height of The Treasure Essence at Dilmunia Essence at Dilmunia is a 300-apartment residential project by Bahraini real estate developer, United Tower Real Estate Development WLL, which will be built on an approximately 11,610 sqm land area. Construction is progressing on site and coordination with the subdeveloper is ongoing. Superstructure works have been completed during Q and the project is expected to be finished by end of Dilmunia Shopping Mall Design Canal View Naseej B.S.C., which purchased three mixed-use canal plots with a total area of approximately 13,068 sqm, have got approval on the architectural designs. This project, designed to develop four independent buildings linked by a podium and commercial gallery, will encompass 240 apartments. Utility and infrastructure drawings are being reviewed with the sub-developer. Geotechnical site investigations were completed in Canal View Plots Superstructure works on Essence of Dilmunia are now complete 6 Fund Report
7 Residence Sharq Residence Sharq, which has been recently offered to the market, will consist of a mix of apartments and duplexes. It will be built on a plot with an area of approximately 17,000 sqm. A project developed on the south seafront, it will encompass a mix of different types of apartments totaling 280 units. Design approvals were given to the sub-developer in December Utility and infrastructure drawings are being reviewed with the subdeveloper before submission for a building permit. Hanging Garden at Dilmunia The preliminary designs for this project, which covers three plots over a total land area of 20,375 sqm, was approved during the reporting period and the final design is under review. The project was named Best Mixed-Use Development Arabia at International Property Awards in Dubai in September 2016, and Best International Mixed Use Development at the International Property Awards for in London in December Residence Sharq South West Residential Development: The concept design for the 30,713 sqm plot, located in the southwest corner of Dilmunia, was submitted in Q Final designs are being reviewed and close cooperation is being maintained with the sub-developer. The project, being developed on the southwest seafront, will include a mix of different types of apartments and villas on the seaside, totaling 378 units. The Hanging Gardens Top View Upcoming Activities Development: Follow up with all sub-developers (continuous task) Implementing soft landscaping Starting of canal and marina detailed designs Infrastructure: Monitoring of progress of Phase 2 infrastructure works Preparing for Phase 3 infrastructure works SWRD Concept Design Mix 24 and 25: Tendering for design and supervision services was completed in Q on these two canal view plots, which cover a total area of approximately 9,830 sqm. Appointment of a consultant by the client, and therefore the design work, is planned to start during Q Fund Report
8 Appendix Central Bank of Bahrain Disclosure Requirements: The Fund has been extended until 2018, however, the investors were given the opportunity to exit the fund by exercising their in-kind redemption rights. Bankers: Ithmaar Bank B.S.C. Management Fees: The Fund Manager has suspended its Management Fees since October Placement Fees: The Placement Fee was 3% of the respective Commitment. Original Development Plan: According to the PPM, the development plan is to invest in the Development Land measuring approximately 650,000 sqm intended to be developed as a state-of-the-art Health Island exclusively for promoting health and wellness away from the hustle and bustle of the city. The Health Island with a total area of 1,250,000 sqm will be located in the north east of Muharraq Island of the Kingdom of Bahrain. Commercial Component; Residential Component (including: first-class condominiums; low-rise canal view condominiums; pier-side condominiums; canal residences; river apartments; and exclusive villas); and Landscape Component (including landscape; waterscape; and landforms). The original development plan remains unchanged. Utilisation of Proceeds: Amount Spent from 1 July 2016 to 31 December 2016 and on Cumulative Basis: From 1 Jul 2016 Till 31 Dec 2016 On Cumulative Basis Category Amount (USD) Percentage (%) Amount (USD) Percentage (%) Infrastructure Costs 6,350, % 55,217, % Fund Expenses 146, % 15,982, % Total 6,497, % 71,200, % Recipients of Material Amounts (above 10%): The Fund will have the opportunity to invest in the Infrastructure of the Development Land and realize its investment and returns through the sale of Parcels including Infrastructure up to the boundaries of the Parcels. The Development Land will be a mixed-use waterfront real estate project centered around health and well-being facilities and to be known as Dilmunia Island. It is contemplated that the Dilmunia Island project will include the following: Medical Component (including: Children s and Women Hospital; Research Centre; Wellness Hospital; Medical Aesthetic Centre; Diagnostic Centre; Nutrition Centre; Diabetic Centre; and Sports Medicine); Hotel Component (including: 5-Star Hotel offering Traditional Chinese Medicine; 5-Star Hotel offering French Holistic Treatment; 5-Star Hotel offering Thai Holistic Treatment; and 4-Star Hotel with Commercial); Supplier Amount (USD) % of Total Spent during the period Cebarco Bahrain 5,006,125 79% Mott MacDonald 922,096 15% Utilisation of Proceeds comparison with PPM: Costs Budgeted as per the PPM ( ) Cash and Cash Equivalent Funds utilised during H Development Land Infrastructure Costs Fund Expenses* Total *The cost overruns are attributed to the extension of the Fund. All amounts in USD million Bank Accounts held by Dilmunia Bank Amount (USD) Current Account as at 31 Dec 2016 Ithmaar Bank B.S.C. 4,852,389 Modaraba Accounts as at 31 Dec 2016 Ithmaar Bank B.S.C. 19,548,662 The company does not have senior management and it is managed by the Fund Manager 8 Fund Report
9 Current Board Members of the General Partner of the Fund: Name Date Elected Date Resigned Mohammed Khalil Al Sayed 5 Nov Abdulhakeem Al Mutawa 18 Sep Ayoob Yusuf Alawadhi 7 Dec There was no Board remuneration paid during the reporting period. Summary of Board resolutions from 1 July 2016 to 31 December 2016: a): Approving the Company s audited financials for the year ended 31 December b): Approving the Company s reviewed interim financials for the period ended 30 June c): Approving the appointment of Ansari Engineering Services to perform the design and supervision consultancy services required for the construction of the second 66kv primary substation at Dilmunia. d): Approving the sponsorship of the Bahrain Authority for Culture and Antiquities to support the Authority in organizing the Spring of Culture event in Bahrain for e): Approving prices of Plots No to known as South Residential Development. In relation to the Dilmunia project, The Fund Manager confirms that there are no active legal proceedings that have been filed against the Company, the Fund or its parent company, or any complaints brought by investors or any investigations by regulatory bodies (of which the Fund Manager is aware) during the reporting period. The Fund Manager confirms that the assets of the Company are free from any charges or pledges. The Fund Manager confirms that the Company has not undertaken any debt facility. 9 Fund Report
10 Condensed Statement of Financial Position as of 30 June 2016 Assets Cash and Balances with financial institution Development Properties Furniture and Equipment Amount Due from a Related Party Total Assets All amounts in USD 30 June December 2015 (Reviewed) (Audited) 24,401,201 19,075, ,048, ,021, ,515 2,192,621 2,192, ,642, ,294,544 Equity Partnership Capital Accumulated Losses Total Equity 185,000,000 (14,460,008) 170,539, ,000,000 (13,959,616) 171,040,384 Liabilities Advances from Customers Other Liabilities Total Liabilities 39,879,740 1,223,266 41,103, , ,565 29,254,160 Total Equity and Liabilities Net Asset Value per Unit based on 18,500 units outstanding 211,642, ,294,544 9,218 9,245 Condensed Statement of Profit or Loss and Other Comprehensive Income as of 30 June 2016 Income from Placement with a financial institution 30 June 2016 (Reviewed) 56,404 All amounts in USD 31 December 2015 (Audited) 2,101 Marketing and Advertising Expenses General and Administrative Cost Total Expenses (357,832) (198,964) (556,796) (86,388) (87,466) (173,755) Loss for the Period Other Comprehensive Income Total Comprehensive Income (500,392) - (500,392) (171,755) - (171,755) 10 Fund Report
11 Enchancing Life, Restoring Balance
Dilmunia Development Fund I L.P. Enhancing Life, Restoring Balance. January 1st 2014 to June 30th 2014
Dilmunia Development Fund I L.P. Enhancing Life, Restoring Balance January 1st 2014 to June 30th 2014 Contents Dilmunia Key Developments Project Development Key Targets Appendix The Fund Manager, Ithmaar
More informationInvestor Briefings First-Half FY2016 Financial Results
Cedar Woods Properties Limited Investor Briefings First-Half FY2016 Financial Results 26 February 2016 Cedar Woods Presentation 2 Snapshot of Achievements in FY2016 Extensive portfolio of residential estates
More informationExecutive Directors Review
Financial Summary Turnover for the year ended 31 December 2011 amounted to HK$571.4 million ( 47.6 million) (2010: HK$706.8 million ( 58.7 million)). The turnover was principally attributable to the recognition
More informationThe beauty of Seavilla goes beyond seaside living
The beauty of Seavilla goes beyond seaside living An alluring seaside retreat All information, specifications, plans and visual representations are subject to change and shall not form part of the offer
More informationTotal Uses 250,000 2,124,049 1,850, ,499 2,003, , , , , , , , , ,398 -
Homburg Invest Inc. Cash Flow Statement Number of weeks 13 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Start Date: Friday, September 09, 2011 TRUE TRUE TRUE TRUE TRUE TRUE TRUE TRUE TRUE TRUE TRUE TRUE TRUE TRUE FALSE
More informationIndiabulls Real Estate Limited (CIN : L45101DL2006PLC148314)
Indiabulls Real Estate Limited (CIN : L45101DL2006PLC148314) Earnings Update Audited Financial Results FY 2013-14 April 23, 2014 Safe Harbor Statement This document contains certain forward looking statements
More informationCathay Pacific Airways Limited Abridged Financial Statements
To provide shareholders with information on the results and financial position of the Group s significant listed associated company, Cathay Pacific Airways Limited, the following is a summary of its audited
More informationTalaat Moustafa Group Holding 1Q08 Results Earnings Release
Talaat Moustafa Group Holding Results Earnings Release Cairo, April 13 th 08 Talaat Moustafa Group Holding ( TMG Holding ) the leading Egyptian community real estate developer with over years of experience,
More informationCairo, May 21, TMG Holding reports EGP BN consolidated revenue, EGP 161 MN consolidated net profit
First Quarter ending Earning Release Cairo, May 21, - reports EGP 1.139 BN consolidated revenue, EGP 161 MN consolidated net profit after minority and EGP 2.2 BN of new sales value for the first quarter
More informationCairo, November 15, 2016 TMG holding reports EGP 3.9 BN consolidated revenues, EGP 616 MN consolidated net profit
Nine Months and Third Quarter ending September 30, Earning Release Cairo, November 15, TMG holding reports EGP 3.9 BN consolidated revenues, EGP 616 MN consolidated net profit after minority and EGP 5.5
More informationCathay Pacific Airways Limited Abridged Financial Statements
To provide shareholders with information on the results and financial position of the Group s significant listed associated company, Cathay Pacific Airways Limited, the following is a summary of its audited
More information12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization
REPORT FOR ACTION 12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization Date: April 27, 2018 To: Toronto and East York Community Council From: Senior Strategic Director,
More informationPre-launch information
Pre-launch information DUBAI MARINA Occupying one of the last remaining plots in Dubai Marina, No.9 represents an exclusive, final opportunity to purchase luxury frontline property in the most sought-after
More informationCAPITAL MARKETS DAY 14 NOVEMBER 2016
CAPITAL MARKETS DAY 14 NOVEMBER 2016 DISCLAIMER This disclaimer governs the use of this presentation. You must not rely on the information in the presentations and alternatively we recommend you to seek
More informationINVITATION TO PRE-QUALIFICATION FOR PARALLEL PROJECTS. +One
INVITATION TO PRE-QUALIFICATION FOR PARALLEL PROJECTS +One A HUB IN TOMORROW S GOTHENBURG By 2030, there will be no borders between the Swedish Exhibition & Congress Centre, Gothenburg and the wider world.
More informationThe St. Joe Company. Raymond James Institutional Investors Conference March 10, 2009
The St. Joe Company Raymond James Institutional Investors Conference March 10, 2009 Forward Looking Statements This presentation contains forward-looking statements about future events that are subject
More informationManagement Presentation. March 2016
Management Presentation March 2016 Forward looking statements This presentation as well as oral statements made by officers or directors of Allegiant Travel Company, its advisors and affiliates (collectively
More informationPresentation on Results for the 2nd Quarter FY Idemitsu Kosan Co.,Ltd. November 14, 2018
Presentation on Results for the 2nd Quarter FY 2018 Idemitsu Kosan Co.,Ltd. November 14, 2018 Table of Contents 1. FY 2018 2nd Quarter Financials (1) Overview (2) Segment Information 2. Reference Materials
More informationRevenue Gross Profit Profit Before Tax Profit After Tax
TA CORPORATION LTD (Incorporated in the Republic of Singapore on 7 March 2011) (Company Registration No. 201105512R) NEWS RELEASE TA CORPORATION 1Q2012 PROFIT AFTER TAX SOARS 113.5% to S$16.4 MILLION -
More informationThe St Joe Compan November 2009
The St. Joe Company November 2009 Forward Looking Statements e ts This presentation contains forward-looking statements about future events that are subject to numerous assumptions, risks and uncertainties.
More informationYWCA Townsville Townsville
Queensland Projects Projects I wholly recommend Cadence Australia as a property development and project management company I have found their attention to detail, rigorous documentation and process management,
More information26 October 2017 Icelandair Group Interim Report NET PROFIT USD 101 MILLION IN THIRD QUARTER
NET PROFIT USD 101 MILLION IN THIRD QUARTER Total income in Q3 up by 10% between years, to USD 536.0 million Passenger revenue higher than expected EBITDA unchanged year on year, at USD 161.1 million Passenger
More informationClarkston Playgroup and Nursery. Scottish Charity No. SC Annual Report & Financial Statements. For the Year Ended 31 March 2016
Clarkston Playgroup and Nursery Scottish Charity No. SC010635 Annual Report & Financial Statements For the Year Ended 31 March 2016 Page 1 of 9 Trustees Annual Report For the Year Ended 31 March 2016 The
More informationMEXICO CITY S NEW INTERNATIONAL AIRPORT 2017 ACI-LAC Conference. November 2017
MEXICO CITY S NEW INTERNATIONAL AIRPORT 2017 ACI-LAC Conference November 2017 Millions of Passengers The need for a new airport» New Airport opening in 2020 Passenger Projections Growth: 140 120 100 80
More information4 th -7 th December 2017 Palais des Expositions, SAFEX Algiers, Algeria
4 th -7 th December 2017 Palais des Expositions, SAFEX Algiers, Algeria NORTH AFRICA S PREMIER BUILDING & CONSTRUCTION EVENT www.algeriabuild.com Organised by WELCOME TO ALGERIA BUILD 2017 Dear Industry
More informationANGLIAN WATER GREEN BOND
ANGLIAN WATER GREEN BOND DNV GL ELIGIBILITY ASSESSMENT Scope and Objectives Anglian Water Services Financing Plc is the financing subsidiary of Anglian Water Services Limited. References in this eligibility
More informationAppendix. Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Gatwick Airport Limited
Gatwick Airport Limited Response to Airports Commission Consultation Appendix 37 Gatwick Airport Ltd - Further information on Gatwick s revised phasing strategy (including Programme) Further information
More informationHighlights from the Annual Results December 2007
Highlights from the Annual Results December 2007 Disclaimer The information in this document is taken from the BAA 2007 Annual Results ( the Results ) which were published on 11 March 2008 and other public
More information1 The Cadastral Mapping Fee Order (AR 94/2000) is amended by this Regulation.
Alberta Regulation 21/2005 Surveys Act CADASTRAL MAPPING FEE AMENDMENT ORDER Filed: March 2, 2005 For information only: Made by the Minister of Sustainable Resource Development (M.O. 03/2005) on February
More informationCrown Resorts Limited
Crown Resorts Limited 2015 Full Year Results Presentation 13 August 2015 1 Crown Resorts Limited Results Overview Crown Resorts Limited (Crown) performance: Overall, the results for Crown s portfolio of
More informationINTERNATIONAL CIVIL AVIATION ORGANIZATION
INTERNATIONAL CIVIL AVIATION ORGANIZATION Implementation of ICAO Universal Safety Oversight Audit Programme (USOAP) Corrective Action Plan Revised Plan of Action for Malawi JULY 2013 - 2 - REVISED ICAO
More informationDevine Limited Annual General Meeting. The Marriott Hotel 515 Queen Street, Brisbane 31 October, am
Devine Limited Annual General Meeting The Marriott Hotel 515 Queen Street, Brisbane 31 October, 2008 11.00am Agenda 1. Welcome 2. Chairman s Address 3. Managing Director s Address 4. Formal Business CHAIRMAN
More informationMASSACHUSETTS PORT AUTHORITY REQUEST FOR LETTERS OF INTEREST DEVELOPMENT OF THE MASSPORT MARINE TERMINAL
MASSACHUSETTS PORT AUTHORITY REQUEST FOR LETTERS OF INTEREST DEVELOPMENT OF THE MASSPORT MARINE TERMINAL The Massachusetts Port Authority ( Massport ) is seeking Letters of Interest for available development
More informationLITTLE WALDINGFIELD PARISH COUNCIL Minutes of Meeting held on Tuesday 20 th September 2016 at 7.30pm in the Parish Room
Present: Attending: Councillors Andy Sheppard (Chairman), Stewart Braybrook, Jeremy Coomber, Tim Sheppard and Chris White. Colin Spence (Suffolk County Councillor), Dave Crimmin (Clerk) and 1 resident.
More informationSunway berhad. Q Results Briefing Pack. 26 February 2016
Sunway berhad Q4 2015 Results Briefing Pack 26 February 2016 1 Full Year Profitability Maintained Despite SunCon Dilution 1) Full Year Performance PATMI is maintained at RM732.4 million in 2015 (2014:
More informationCROWN ANNOUNCES 2019 HALF YEAR RESULTS
ASX / MEDIA RELEASE FOR IMMEDIATE RELEASE 20 February 2019 CROWN ANNOUNCES 2019 HALF YEAR RESULTS MELBOURNE: Crown Resorts Limited (ASX: CWN) ( Crown ) today announced its results for the half year ended
More informationGreat Portland Estates Trading Update Strong Operational Performance
Press Release 6 July 2017 Great Portland Estates Trading Update Strong Operational Performance Great Portland Estates plc ( GPE ) today publishes its trading update for the quarter to 30 June 2017. Continued
More informationMain Points in the Results for FY2015
0 1 2 Main Points in the Results for FY2015 Operating profit increased to 75.4 billion yen, exceeding the goal of 75.0 billion yen for the final year of the medium-term management plan in the first year
More information4 VIVA PHASE 2 YONGE STREET - Y2, AND HIGHWAY 7 - H3 CORRIDORS PRELIMINARY ENGINEERING UPDATE
4 VIVA PHASE 2 YONGE STREET - Y2, AND HIGHWAY 7 - H3 CORRIDORS PRELIMINARY ENGINEERING UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the following: 1. The presentation
More informationInvestor Meeting Presentation. 4 June 2014
Investor Meeting Presentation 4 June 2014 COMPANY OVERVIEW 1Q2014 RESULTS OVERVIEW OPERATION HIGHLIGHTS Q&A 2 Founded in 1963, listed on the Singapore Exchange in 1964 Three core businesses: - Property
More informationScottish Pilgrim Routes Forum Scottish Charitable Incorporated Organisation - SC045212
Scottish Pilgrim Routes Forum Scottish Charitable Incorporated Organisation - SC045212 Report and Accounts for the period 1 st August 2015 to 31 July 2016 (1) Reference and administrative information Scottish
More informationPARTNERING FOR SUCCESS
PARTNERING FOR SUCCESS PARTNERING FOR SUCCESS WE HELP SHAPE THE WORLD AROUND US TO BECOME A BETTER PLACE. W e are the leading design and consultancy firm for natural and built assets. With a global network
More informationSubject: Information Memorandum on the Disposition of Assets of Laguna Resorts & Hotels Public Company Limited
No. L028/2010 10 August 2010 Subject: Information Memorandum on the Disposition of Assets of Laguna Resorts & Hotels Public Company Limited To: President The Stock Exchange of Thailand The meeting of the
More informationMEMORANDUM OF UNDERSTANDING WITH BUSINESS IMPROVEMENT DISTRICTS WITHIN BIRMINGHAM
MEMORANDUM OF UNDERSTANDING WITH BUSINESS IMPROVEMENT DISTRICTS WITHIN BIRMINGHAM For services in respect of: Highway Maintenance and Management Car Parking Traffic Management Signatories: For Birmingham
More informationPresentation to the British Irish Airport s EXPO John Heffernan Chief Development Officer, Dublin Airport
Presentation to the British Irish Airport s EXPO John Heffernan Chief Development Officer, Dublin Airport 1 DUBLIN-LONDON 28.4 No.1 +2,200 MILLION PASSENGERS BUSIEST ROUTE IN EUROPE &No. 2 IN THE WORLD
More informationMinistry seeking to overcome slow growth in real estate sector in past years: Mostafa Madbouly
Ministry seeking to overcome slow growth in real estate sector in past years: Mostafa Madbouly September 26, 2016 Source: dailynewsegypt.com As the Ministry of Housing works to put together a strategy
More informationBritish Columbia. property society. Annual report unclaimedpropertybc.ca
British Columbia Unclaimed property society Annual report 2014 unclaimedpropertybc.ca Reuniting Forgotten Dollars with their Rightful Owners Message from the Chair and Executive Director At the BC Unclaimed
More informationOxley Delivers Stellar Growth of 58% in PATMI to. S$130.9 million for HY2017
For immediate release Oxley Delivers Stellar Growth of 58% in PATMI to S$130.9 million for HY2017 - Half-year revenue increased by 19% year-on-year to S$732.2 million - Gross profit margin increased from
More informationCorporate Presentation. July 2018
Corporate Presentation July 2018 Introduction AMBER Consulting is an independent firm established in 2006 that offers a comprehensive range of hospitality, business strategy and mixed-use consulting services
More informationPARTNERING FOR SUCCESS
PARTNERING FOR SUCCESS PARTNERING FOR SUCCESS WE HELP SHAPE THE WORLD AROUND US TO BECOME A BETTER PLACE. W e are the leading design and consultancy firm for natural and built assets. With a global network
More informationimall Sharjah, UAE Leasing Information Pack
imall Sharjah, UAE Leasing Information Pack Introduction PROJECT ESSENTIALS imall is a value shopping mall with a focus on value fashion and electronics. The property was developed by Nice Home Real Estate
More informationCrown Resorts Limited
Crown Resorts Limited 2016 Half Year Results Presentation 25 February 2016 1 Crown Resorts Limited Results Overview Crown Resorts Limited (Crown) performance: The 2016 First Half results across Crown s
More informationMainland China Property Development
Management Discussion and Analysis Mainland China Property Development With our advanced project management capabilities and a high level of collaboration among teams, every future Hang Lung project will
More informationRef. PE004/ May Subject: Management Discussion and Analysis for the First Quarter of 2018
Ref. PE004/2561 10 May 2018 Subject: Management Discussion and Analysis for the First Quarter of 2018 Attention: President The Stock Exchange of Thailand According to the financial reports of Nok Airlines
More informationPersianas Group, Anticipating the Future
Persianas Group, 2010 Anticipating the Future Introduction & Background The Persianas Group consists of various businesses, of which Persianas Properties Limited ( PPL ) incorporated in 1990, is the largest
More informationSTRONGER CHRISTCHURCH INFRASTRUCTURE REBUILD TEAM (SCIRT) REAAA
STRONGER CHRISTCHURCH INFRASTRUCTURE REBUILD TEAM (SCIRT) REAAA 21 st August 2012 Context Legend Areas of observed liquefaction! Port Hills area Approx Scale 1:50,000 0 500 1000 1500 2000 2500 (m) Notes:
More informationInvestor update presentation. November 2016
Investor update presentation November 2016 Content Update on Q3 2016 financial performance 3-8 Recap on ATG Evolution 9-10 Update on hospitality strategic business unit 11-14 Update on online travel and
More informationWorld Design Capital Taipei 2016 International Design House Exhibition Exhibition Participation Procedures
World Design Capital Taipei 2016 International Design House Exhibition Exhibition Participation Procedures I. Foreword Introduction World Design Capital (abbreviated to WDC) is a global event initiated
More informationPART 4 SUMMARY OF CHANGES TO POLICIES
PART 4 SUMMARY OF CHANGES TO POLICIES 1. SUMMARY OF CHANGES TO POLICIES The complete detailed policies are available on the municipal website www.stevetshwetelm.gov.za for public scrutiny. 1.1 Asset management
More informationARTWEI ARTWEI ARTWEI
Protection / Management Plans for Natura 2000 areas and Maritime Spatial Plan for internal sea waters - including the Szczecin Lagoon Szczecin, 7th May 2011 Andrzej Zych Inspectorate of Coast Protection
More informationPowerade Centre Overview. Budget Committee October 2015
Powerade Centre Overview Budget Committee October 2015 Powerade Centre Background City established the Brampton Sports Park in late 1980s on lands acquired from the province The park was developed for
More information317a & 400 Hoe Street, Walthamstow, E17 9AA
North East London Residential Led Development Opportunity 317a & 400 Hoe Street, Walthamstow, E17 9AA Red line boundary for indicative purposes only Summary Residential-led two-site development opportunity
More informationand Immigration U.S. Citizenship Services * This page is intentionally left blank. *
U.S. Department of Homeland Security U.S. Citizenship and Immigration Services Immigrant Investor Program Mailstop 2235 Washington, DC 20529 U.S. Citizenship and Immigration Services Mr. James Lavigne
More informationBẢN TIN THÁNG 04/2015 1Q 2018 EARNINGS CALL
1Q 2018 EARNINGS CALL May 8, 2018 Key Highlights 1 Business performance of 1Q2018 1 1. Vingroup (ticker: VIC) reported that consolidated net revenue reached VND 29.1tn (+84% YoY), in which revenue from
More informationInvestor update presentation. August 2016
Investor update presentation August 2016 Content Update on Q2 2016 financial performance 4-8 Update on hospitality projects 10-11 Update on E-commerce businesses 13-16 2 Section 1 Update on Q2 2016 financial
More informationCapitaLand Analysts/Media Trip 2017
CapitaLand Analysts/Media Trip 2017 Mr. Lucas Loh CEO, CapitaLand China; Co-ordinating CEO China 2 July 2017 Contents 1 2 3 Key Highlights Business Overview Concluding Remarks 2 3 1 Key Highlights Successful
More informationEB-5 Financing as an Alternative Source of Capital for Housing
EB-5 Financing as an Alternative Source of Capital for Housing U.S. Department of Housing and Urban Development Presentation Debbie A. Klis, Esq. klisd@ballardspahr.com February 1, 2017 The EB-5 Investment
More informationInterim Results for the Six Months ended 28 February 2017
Interim Results for the Six Months ended 28 February 2017 The Group is pleased to announce its interim results for the six months ended 28 February 2017. Formation Group is focused solely on property development
More informationInvestor Update April 23, 2009
JetBlue Airways Investor Relations (718) 709-2202 ir@jetblue.com Investor Update April 23, 2009 This investor update provides our investor guidance for the second quarter ending June 30, 2009 and full
More informationFOR SALE. On behalf of. Surplus Land and Buildings at the MURRAY ROYAL HOSPITAL PERTH Available as a whole or in two lots
FOR SALE On behalf of Surplus Land and Buildings at the MURRAY ROYAL HOSPITAL PERTH Available as a whole or in two lots Location The surplus land and buildings at the Murray Royal Hospital, Perth are located
More informationMIXED-USE DEVELOPMENT RESPUBLIKA
MIXED-USE DEVELOPMENT RESPUBLIKA Country Ukraine N 1 The biggest in Europe 603,628 sq.km N 5 The population 45 mln inhabitants 114.7% increase of retail turnover in 2011 76.5% shopping expenditures of
More informationChiwayland announces 2Q2016 results, with sights set on international markets and other growth engines
Chiwayland announces 2Q2016 results, with sights set on international markets and other growth engines On track for the delivery of two major property developments by 4Q2016 Barring unforeseen circumstances,
More informationFENIX OUTDOOR INTERNATIONAL AG Interim condensed consolidated financial statement for the period ended 30 September 2017
FENIX OUTDOOR INTERNATIONAL AG Interim condensed consolidated financial statement for the period ended 30 September 2017 Third quarter 2017-07-01 2017-09-30 Period 2017-01-01 2017-09-30 Events after period
More informationEnergy from Waste and Recycling Facility Trident Park, Cardiff. Planning History. January 2010 SLR Ref: B
Energy from Waste and Recycling Facility Trident Park, Cardiff Planning History January 2010 Ref: 402-0036-0306B Viridor Ltd. i 402/0036/00306B CONTENTS 1.0 INTRODUCTION... 1 2.0 GENERAL HISTORY... 3
More informationForm I-924, Application for Regional Center under the Immigrant Investor Pilot Program. EB5 Capital California Regional Center
U.S. Citizenship and Immigration Services Immigrant Investor Program Washington, DC 20529 April 7, 2014 Angelique Brunner One Bush Street Suite 1150 San Francisco CA 94104 Application: Applicant(s): Re:
More informationS$ million 2Q2012 2Q2011 Change 1H2012 1H2011 Change Revenue % % Gross Profit % % Gross Profit Margin
Roxy-Pacific Holdings Limited NEWS RELEASE ROXY-PACIFIC ACHIEVES 8% INCREASE IN NET PROFIT TO S$17.7 MILLION IN 2Q2012 - Revenue rises 13% to S$52.7 million - 18% surge in revenue from Property Development
More informationForm I-924, Application for Regional Center under the Immigrant Investor Pilot Program
U.S. Citizenship and Immigration Services Immigrant Investor Program Washington, DC 20529 February 26, 2014 Sean Runnels 74040 Hwy 111, #210 Palm Desert, CA 92260 Application: Applicant(s): Form I-924,
More informationPolicies for Certification, operation and maintenance of UAS Andres Eduardo Parra Catama Air Safety Inspector Civil Aviation Authority of Colombia
Policies for Certification, operation and maintenance of UAS Andres Eduardo Parra Catama Air Safety Inspector Civil Aviation Authority of Colombia Abstract: Civil Aviation Authority of Colombia currently
More informationSPECTACULAR CONTEMPORARY HOME IN STUNNING BEACHSIDE LOCATION THE BEACH HOUSE 18 HYNDMAN ROAD, SEAMILL, WEST KILBRIDE, AYRSHIRE, KA23 9NL
SPECTACULAR CONTEMPORARY HOME IN STUNNING BEACHSIDE LOCATION THE BEACH HOUSE 18 HYNDMAN ROAD, SEAMILL, WEST KILBRIDE, AYRSHIRE, KA23 9NL SPECTACULAR CONTEMPORARY HOME IN STUNNING BEACHSIDE LOCATION THE
More information1Q 2017 Earnings Call. April 18, 2017
1Q 2017 Earnings Call April 18, 2017 Safe Harbor Statement Certain statements included in this presentation are forward-looking and thus reflect our current expectations and beliefs with respect to certain
More informationAspen Achieves Record Net Profit of RM85.4 Million in FY2017
PRESS RELEASE - FOR IMMEDIATE RELEASE Aspen Achieves Record Net Profit of RM85.4 Million in FY2017 4Q FY2017 Net Profit of RM42.0 Million Almost Matches 9M FY2017 Net Profit of RM43.4 Million Strong revenue
More informationAnalysts and Investors conference call. Q results. 15 May 2013
Analysts and Investors conference call Q1 2013 results 15 May 2013 Management summary Key messages of Q1 2013 +6% +9% +3.3%p. Q1 2013 operational KPIs are in line with 109.7 116.2 6.5 7.1 82.3 85.6 expectations,
More informationCROWN ANNOUNCES 2018 HALF YEAR RESULTS
ASX / MEDIA RELEASE FOR IMMEDIATE RELEASE 22 February 2018 CROWN ANNOUNCES 2018 HALF YEAR RESULTS MELBOURNE: Crown Resorts Limited (ASX: CWN) ( Crown ) today announced its results for the half year ended
More informationOFFICE FOR SALE. GINO VINCENT Vice President TURNKEY PROFESSIONAL OFFICE BUILDING
OFFICE FOR SALE GINO VINCENT Vice President 702.954.4113 gvincent@logiccre.com TURNKEY PROFESSIONAL OFFICE BUILDING PROPERTY OVERVIEW PROPERTY DETAILS Address: 1424 S. Jones Blvd., Las Vegas, NV 89146
More informationLOCATED AT THE GATEWAY OF THE TROPICAL PROVINCE, RIDING ON THE GROWTH MOMENTUM OF THE COUNTRY, WE ARE ON THE RIGHT TRACK OF TAKING OFF.
LOCATED AT THE GATEWAY OF THE TROPICAL PROVINCE, RIDING ON THE GROWTH MOMENTUM OF THE COUNTRY, WE ARE ON THE RIGHT TRACK OF TAKING OFF. MANAGEMENT DISCUSSION INDUSTRY REVIEW Civil Aviation Industry in
More informationCLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257
Form PDES 8 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Summary of Duties: A Senior Airport Engineer performs the more difficult and
More informationGrace In Place Makkah Smart FoodCity Work, Live andleisure
Grace In Place Makkah Smart FoodCity Work, Live andleisure Under the patronage of: And the auspices of: H.R.H. Prince Khaled Al Faisal Governor of Makkah Province H.E. Engineer Abdullatif Al-Alshaikh Minister
More informationVolaris Reports Strong First Quarter 2015: 32% Adjusted EBITDAR Margin, 9% Operating Margin
Volaris Reports Strong First Quarter 2015: 32% Adjusted EBITDAR Margin, 9% Operating Margin Mexico City, Mexico, April 22, 2015 Volaris* (NYSE: VLRS and BMV: VOLAR), the ultra-low-cost airline serving
More informationDEVELOPMENT MANAGEMENT
Operational Review DEVELOPMENT MANAGEMENT The principal activities of the development business are property development and development management. 2017 HIGHLIGHTS Two major off-plan development launches;
More informationFor personal use only
Sydney Airport Holdings Limited ABN 85 075 295 760 AFSL 236875 Central Terrace Building 10 Arrivals Court Sydney International Airport New South Wales 2020 T 1800 181 895 or +61 2 9667 9871 F +61 2 9667
More informationAMATA VN Public Company Limited
AMATA VN Public Company Limited Welcome to Opportunity Day Financial Results for the period ended December 31, 2017 1 Disclaimer This document was prepared by Amata VN Public Company Limited in good faith
More informationWORKSHOP 1 ICAO RPAS Panel Working Group 1 Airworthiness
REMOTELY PILOTED AIRCRAFT SYSTEMS SYMPOSIUM 23-25 March 2015 WORKSHOP 1 ICAO RPAS Panel Working Group 1 Airworthiness Stephen George Bruno Moitre Rapporteurs WG1 Remotely Piloted Aircraft Systems (RPAS)
More informationSummary o f Results for the First Half of FY2018
Summary o f Results for the First Half of FY2018 November 9, 2018 (9005) https://www.tokyu.co.jp/ Contents Ⅰ.Executive Summary 2 Ⅱ.Conditions in Each Business 6 Ⅲ.Details of Financial Results for the 13
More informationMIRAMAR, Fla., April 29, 2015 (GLOBE NEWSWIRE) -- Spirit Airlines, Inc. (Nasdaq:SAVE) today reported first quarter 2015 financial results.
April 29, 2015 Spirit Airlines Announces First Quarter 2015 Results; Adjusted Net Income Increases 87.1 Percent to $70.7 Million and Pre-Tax Margin Increases 900 Basis Points to 22.7 Percent MIRAMAR, Fla.,
More informationRECORD REVENUE AND EFFICIENCY DRIVE SOFTEN IMPACT OF HIGH FUEL COST, ENABLE HALF YEAR PROFIT OF $578 MILLION
RECORD REVENUE AND EFFICIENCY DRIVE SOFTEN IMPACT OF HIGH FUEL COST, ENABLE HALF YEAR PROFIT OF $578 MILLION HIGHLIGHTS OF THE GROUP S PERFORMANCE First Half 2005-06 2nd Quarter 2005-06 Apr-Sep 2005 Year-on-Year
More informationALC Project # 68 Liberty Park Cape Coral, Florida
Project Proposal ALC Project # 68 Liberty Park Cape Coral, Florida PACE Loan & EB-5 1321 NE 24th Avenue Cape Coral, FL 33909 Prepared by: American Lending Center A USCIS-Designated EB-5 Regional Center
More informationRequest for Proposals
E CONOMIC DEVELOPMENT AUTHORITY of the City of Norfolk Board of Directors Officers Robert E. Garris, Jr., Chairman Executive Director Michael W. Lee, Vice Chairman Peter Chapman Jeffrey F. Brooke Kim Brown
More informationWith the completion of this project, we would like to follow-up on the projections as well as highlight a few other items:
TO: FROM: Mayor and Council Interim City Manager Rebecca Underhill, Director of Finance DATE: February 28, 2014 SUBJECT: Water Meter Project Analysis On March 28, 2012, Acting City Manager Mike Loftin
More informationInvestment Opportunity
Investment Opportunity Quest Apartment Hotel Pakenham Street, Fremantle Investment Highlights 120 key Quest serviced apartment development Fremantle s CBD is undergoing renewal and Sirona Capital is a
More information26 APPLICATION FOR APPROVAL TO EXPROPRIATE WIDENING AND RECONSTRUCTION OF ST. JOHN'S SIDEROAD PROJECT 97100, TOWN OF AURORA
Clause No. 26 in Report No. 12 of the was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 26, 2014. 26 APPLICATION FOR APPROVAL TO EXPROPRIATE
More information