1 Physical Infrastructure - Transport Briefing Document Resilient Puerto Rico Advisory Commission February

2 Contents 1 Introduction 3 2 Overview of Existing Transportation Governance and Services 3 a. Transportation Governance 3 1. Puerto Rico Metropolitan Planning Organization (MPO) 3 2. Puerto Rico Department of Transport and Public Works (DTOP) and Associated Agencies 4 3. MPO Committees and Working Groups 6 b. Relevant Transportation Policies and Plans 6 c. Current Transportation System and Users 7 3 Summary of Hurricanes Impacts on Transportation Infrastructure 9 a. Transportation Impacts from Hurricanes Irma and Maria 9 b. Pre-hurricane Transportation Funding and Financing Issues and Their Relationship to Recovery 10 c. Number of Residents without Transportation Service as a Result of the Hurricanes 11 4 Framework for Recovery: Existing Support and Preliminary Opportunity Areas 11 a. Relevant Federal/State Recovery Policies 11 b. Description of Focus Areas to Facilitate Recovery Processes 12 c. Opportunities: Relevant Studies and Recovery Frameworks 14 2

3 1 Introduction Resilience is defined as the capacity of individuals, communities, institutions, businesses, and systems to survive, adapt, and grow no matter what kinds of chronic stresses and acute shocks they experience. The focus on resiliency and disaster recovery is both broad and comprehensive, and is predicated on three factors that cause disasters in the first place: Hazards: risks, such as severe weather conditions, that are present for a given community Vulnerability: a community s capacity (or lack thereof) to deal with disasters Exposure: hazardous locations, such as coastal positions or low-lying areas, which are likely to be affected in severe weather conditions This summary report presents an overview of Puerto Rico s existing transportation governance, systems and policies. In addition, the known impacts from Hurricanes Irma and Maria are summarized, along with existing recovery plans and programs, as well as potential frameworks and relevant studies for developing timely, actionable plans for disaster recovery and resilience in Puerto Rico. Main Shocks and Stressors in Puerto Rico Aging infrastructure Coastal & tidal flooding Declining population / human capital flight Increasing elderly population groups Disease outbreaks Earthquakes Extreme weather events Infrastructure failures Fluvial & pluvial flooding 2 Overview of Existing Transportation Governance and Services a. Transportation Governance 1. Puerto Rico Metropolitan Planning Organization (MPO) The Puerto Rico MPO framework is organized into seven transportation planning regions, including two large population Transportation Management Areas (TMAs) San Juan and Aguadilla and five smaller regions containing nine other urbanized areas, which each are comprised of several municipalities (as shown in the map below)

4 MPO responsibilities include the planning and programming of federal funds through the Long Range Transportation Plan (LRTP) and State Transportation Improvement Program (TIP), respectively, and the approval of highway, transit, and non-motorized transportation-related projects across the island. Each of the areas was required to create their own individual LRTP, which aspects were adapted for the MPO-led Islandwide LRTP. The MPO organizational structure includes three components of policy decisions, technical oversight, and public involvement (see organizational chart below). This structure assures a forum for cooperative decision-making in the planning process with several structured committees (Policy, Technical and Citizen Participation), which are discussed in more detail later Puerto Rico Department of Transport and Public Works (DTOP) and Associated Agencies The Puerto Rico Department of Transport and Public Works (DTOP) is in charge of the infrastructure across the Commonwealth and was designated as the Operative Arm of the MPO for the San Juan Urbanized Area in It operates as the parent agency of the following four transportation agencies (government-owned corporations) and one commission ascribed to the DTOP: Commission on Traffic Safety (Comisión para la Seguridad en el Transito - CST): CST is responsible for preparing and implementing a general traffic safety program and determining the use of state and federal funds assigned to it

5 Highways and Transportation Authority (Autoridad de Carreteras y Transportación - ACT): ACT is in charge of construction, operation, and maintenance of roadways, bridges, highways, tunnels, public parking, tolls, and other transit facilities. 4 ACT filed for Title III bankruptcy in May 2017 despite having outstanding bond payments. 5 Metropolitan Bus Authority (Autoridad Metropolitana de Autobuses - AMA): AMA is the public transit provider of local bus service based in San Juan. 6 Maritime Transport Authority (Autoridad de Transporte Marítimo - ATM): ATM is in charge of providing maritime transportation services for cargo and passengers (including ferry service) within Puerto Rico and islands of Vieques and Culebra. 7 Ports Authority (Autoridad de Puertos - AP): AP is in charge of developing, operating, and overseeing all 9 seaports/harbors and 10 airports in Puerto Rico. 8 Puerto Rico Metropolitan Planning Organization (MPO) Puerto Rico Department of Transportation and Public Works (DTOP) Commission on Traffic Safety (CST) Highways and Transportation Authority (ACT) Metropolitan Bus Authority (AMA) Maritime Transport Authority (ATM) Ports Authority (AP) P3: Autopistas de Puerto Rico (Teodoro Moscoso Bridge) P3: Metropistas (PR-5 & PR-22) The multimodal transportation network in Puerto Rico is a system of highways, transit and ferry services, and bicycle and pedestrian facilities. In August 2014, the governor signed Act 123 to smooth out the inter-agency planning process and related inefficiencies by integrated everything under a central transit authority Puerto Rico Island Integrated Transit Authority (ATI). This included transferring Puerto Rico s Highway and Transportation Authority s (ACT) operations, rights, obligations, and related assets to ATI. The other main agency assigned to ATI was the Metropolitan Bus Authority (AMA). While ATI operates the entire mass transportation system, the Tren Urbano system is operated by Alternate Concepts, Inc. through a P3. The three primary goals established for ATI include to: (1) reduce costs by addressing service overlaps between bus lines and Tren Urbano rail; (2) maximize rider access by showing despite the overall bus service cuts, travel times by transit and walking were not significantly reduced; and (3) minimize adverse social impacts of service changes using demographic data and considering how low-income households and neighborhoods would be

6 affected. Increased ridership from the reduced headways and improved systems appeared in the first few months following the system changes. 9 The American Public Transportation Association (APTA) recognizes three large transit agencies (over 2 million boardings per year) in San Juan: DTOP, AMA, and ACT. 10 ACT has two existing private-public-partnerships (P3): Autopistas de Puerto Rico operates the Teodoro Moscoso Bridge and Metropistas operate the PR-5 and PR-22 toll roads. 3. MPO Committees and Working Groups The Puerto Rico MPO has a collection of structured committees and working groups related to public policy, technical, and citizen participation to assure a forum for cooperative decision-making in the planning process with several structured committees. 11 The Policy Committees contain three subcommittees: San Juan Urbanized Area (SJUA), Aguadilla Urbanized Area (AUA), and Urbanized Areas under 200,000 Population (UZA), for which members are involved in the planning process from inception to final approval of routine planning documents prepared by the MPO. The Technical Committees (TCs) are comprised of technical representatives of MPO agencies and municipalities (including public and private transportation providers). The Technical Group (TG) is an ad hoc subcommittee of the MPO s TC comprised of DTOP, ACT, municipal and other agency liaison representatives, private entities and consultants with the primary purpose of establishing a participatory forum during development or revision of regional transportation studies and plans. The Public Participation Committee (PPC) is an ad hoc committee of the MPO and organized by ACT with representatives from state and federal agencies, local civic, professional and community groups, and the general public to provide an early forum to the community about Transportation Plans. The Public Involvement Committee (PIC) is organized by ACT to promote and facilitate the participation of private agencies, community organizations, and the general public. It assures that the interests and social, economic, and environmental concerns of the community are being considered in the planning process. The Central Planning and Coordination Work Group (CPCWG) includes technical staff from DTOP s Office of the Assistant Secretary for Planning and ACT s Planning Area. This group provides technical support to the MPO committees and subcommittees to prepare the planning documents as well as carry out outreach efforts to the community. b. Relevant Transportation Policies and Plans The Puerto Rico 2040 Islandwide Long Range Transportation Plan was released by DTOP and ACT in September 2013 to assess trends, conditions, and changes in factors that affect the transportation system: demand for its use,

7 funding available for maintenance and improvement, priorities for system management, new requirements on how the system relates to land use and the environment, among other concerns. It is an overarching 28-year blueprint to guide the collaborative efforts of DTOP, ACT, and other Puerto Rico stakeholder industries to improve and integrate roadways, transit, pedestrian and bicycle facilities, airports, seaports, and freight networks. This plan thus considers policies and strategies to meet the expectations of Puerto Ricans, help promote economic development, create more livable communities, and advance environmental sustainability by coordinating transportation and land use to the natural and built environments. The document describes the plan framework, public outreach conducted, island-wide socio-demographic characteristics, existing transportation systems, funding sources, strategic direction, and implementation and performance monitoring. 12 To address stakeholder and agency engagement, DTOP (through ACT), in coordination with the MPO, developed LRTPs for each of the seven transportation planning regions, which federally require public involvement in the development process. A Technical Working Paper: Public Involvement Plan (PIP) was released in January 2012 as a plan for execution of the regional planning operation and administration of funds through FTA programs. The PIP describes the required public participation process and strategies/tools to deploy when engaging stakeholders, including public citizens, technical advisory groups, underserved populations, media, and documentation. Also discussed is recommended MPO, client, and agency coordination during the process. The primary objectives include developing an early, proactive, and ongoing public participation process, building a marketing campaign to increase public awareness, and creating communication channels to encourage public participation. 13 The Strategic Highway Safety Plan (SHSP) was prepared in partnership with the Puerto Rico CST, the Puerto Rico Police, the Puerto Rico Health Department, and the Puerto Rico s ACT. Its approval in July 2014 represented a starting point for a collaborative process among safety stakeholders in Puerto Rico that share the same interest of reducing fatalities and serious injury crashes. Emphasis area that continuously contribute to the enhancement of SHSP include: traffic records & information systems, alcohol impaired driving, vulnerable road users, emergency medical response, aggressive driving, roadway departure, occupant protection, young drivers (15 to 20 years), and intersections. The latest SHSP Annual Report was released in c. Current Transportation System and Users The multimodal transportation network in Puerto Rico is a system of highways, transit and ferry services, and bicycle and pedestrian facilities. This network serves the general public, businesses, tourists, government, defense, ports and seaports while supporting trips related to work and school commuting, freight and goods movement, recreation, shopping, among other functions of society. DTOP released the Puerto Rico 2040 Islandwide LRTP in September Summaries of facilities by type are listed in the following subsections, as described in the LRTP SupportingPlans/PuertoRico2040IslandwideLongRangeTransportationPlan.pdf 7

8 Highway System: PR s extensive highway system has 16,691 miles of roadways with the breakdown show in the table below. There were approximately 51 million vehicle miles traveled (VMT). The primary regional corridors consist of PR-2/PR-22 Northwest Corridor, PR-2 West Corridor, PR-3/PR-66 Northeast Corridor, PR-3/53 Southeast Corridor, PR-2 National Highway System Other Federal-Aid Highways Non-Federal-Aid Highways # Miles 412 3,092 13,186 % Urban 85% 84% 81% Southwest Corridor, PR-10 Corridor, and PR-30 Corridor. All freight is moved by truck in Puerto Rico and therefore the major highways carry significant truck volumes. Bridges: Of the 2,222 bridges under Puerto Rico s jurisdiction, half were found to be deficient (structural or functional) during the 2012 data collection. Public Transportation: The public transit network in Puerto Rico consists of heavy rail (Tren Urbano), local buses, trolleys, publicos, ferries, and taxis. Local buses and trolleys are typically owned by specific municipalities and operate exclusively within them. DTOP operates the Tren Urbano rail line and the Metropolitan Bus Authority, which is a fixed route bus system in the San Juan core area. Rail ridership was approximately 34,000 in 2012 serving 16 stations, including 6 park-and-ride facilities. The Metro Urbano BRT line on PR-22 connects the Bayamon station to the reversible dynamically tolled lanes within the median of PR-22. Publicos are a form of public transportation as shared taxis or vans that can travel around the island and are centered around major destinations. Ferries: Ferries within the San Juan harbor are operated by Puerto Rico Maritime Authority to connect between Old San Juan, and Cataño, and passenger and vehicle service between Fajardo and the islands of Vieques and Culebra. Bicycle and Pedestrian (Non-Motorized) Facilities: There are 20 bicycle and pedestrian trails covering 237 kilometers described in the Long-Range Plan, but numerous expansion plans were also listed, which have likely been constructed since then. Pedestrian and bicycle planning is coordinated between the municipalities and ACT. Maintenance is relatively inconsistent, and sidewalks are often used as parking in some locations which inhibits pedestrian and bicycle travel. Recent projects and plans have been incorporating Complete Streets elements. DTOP and ACT released two draft planning documents in July 2017 for public comment. The Comprehensive Bicycle and Pedestrian Plan for Puerto Rico is a public policy document that defines the vision, goals, objectives and action strategies necessary to integrate cycling and pedestrian activity in the transportation system. Seaports: The Port of San Juan is located on the north coast and is the primary commercial port handling cargo and large cruise ships. The Port of the Americas (Port of Ponce) is controlled by the government-owned corporation called Ponce Port Authority. Other ports include the Port of Mayaguez, Guayanilla, Guayama, Yabucoa, Arecibo, and Port of Fajardo. Airports: The primary airport for air cargo and passenger traffic is San Juan s Luis Munoz Marin International Airport (SJU), with ten additional regional airports. All airports are owned and operated by the Puerto Rico Ports 8

9 Authority, but a public-private partnership to manage SJU was awarded in In 2016, over 9 million passengers utilized SJU. 18 Other Transportation Modes: Other modes of transportation have emerged over the past few years by private companies that offer alternatives to public transportation. Uber is a ride-for-hire service and is available only in the eastern and northern parts of the island, primarily serving San Juan. 19 Pinkcar is a new transportation company authorized by Puerto Rico s Public Service Commission (PSC) to offer service exclusively to women and children driven in vehicles by women. This company was enabled by the law signed by Governor Rossello to simplify the process and requirements of all ground passenger transportation operators in Puerto Rico Summary of Hurricanes Impacts on Transportation Infrastructure a. Transportation Impacts from Hurricanes Irma and Maria As the hurricanes were the strongest storms to hit the island in more than 80 years, losses to transportation infrastructure were recorded across all modes and sectors. Heavy rain and winds carpeted roadways with debris, knocked out the electrical grid and cell towers, destroyed clean water sources, and destroyed other important infrastructure. Gasoline supplies became depleted, and roughly two-thirds of the gas stations were closed as a result of the storm, which limited mobility of residents across the island due to a strong reliance on personal automobiles. The air traffic control system was also significantly damaged during the storm, and a week into Hurricane Maria, Federal Aviation Administration crews were continuing to repair radar units, navigational aids and other equipment, with seven of the eight commercial airports operating on very limited capacity. At the end of the storm, only the Luis Muñoz Marín International Airport in San Juan was able to operate a few dozen flights daily. 21 Puerto Rico s Secretary of DTOP, Carlos Contreras Aponte, shared a preliminary estimate of damage shortly following the Hurricanes of $240 million, but also acknowledged that not all damages were accounted for as information was not able to be obtained for all roadways. 800 incidents were recorded after Irma, with an additional 1,500 cases of damaged or destroyed transportation infrastructure recorded after Maria, which do not include broken traffic lights. 22 The Federal Highway Administration (FHWA) has released a total of $72.5 million in quick release Emergency Relief (ER) funds: an initial $2.5 million after Hurricane Irma, $40 million after Hurricane Maria in September to begin the repair process of critical roadways and bridges across the island, and an additional $30 million in late November to continue emergency work As on November 3, 2017, 2,932 miles of the 5,073 miles of roads pdf million-to-fix-them/?utm_term=.78890e93fd

10 are open to allow passage through the outer ring of the island. Additionally, 88% of gas stations (970 of 1,100) have been reopened as of December 26, The Federal Aviation Administration (FAA) immediately supported the restoration of services to most of the commercial airports in Puerto Rico, restored full Air Traffic Control service to the primary Luis Munoz Marin International Airport, and worked to restore radars, navigational aids and other damaged equipment to increase the number of flights that could arrive and depart the island. 26 All airports are currently open or open with restrictions. 27 The Federal Transit Administration (FTA) awarded $8.4 million in critical grant funding to Puerto Rico to support the island s transit systems. 28 As of December 29, 2017, all AMA bus routes are operational. 29 The Maritime Administration provided vessels to deliver power, food, clean water and berthing to first responders to free up hotels for displaced residents. 30 All ports, including container ship ports have been reopened. 31 On September 28, 2017, the U.S. President temporarily waived the Jones Act to allow foreign ships coming from U.S. port to dock in Puerto Rico to deliver supplies, as was previously done for Florida and Texas. Under the Jones Act, only goods traveling by boat from one U.S. port to another can be a U.S. ship, which disallows foreign ships to dock in Puerto Rico if they plan to continue to the mainland and unload goods there. 32 Specific and current data by mode type and extent of needed investment is not readily available as it was unlikely collected and updated due to concentrating on specific recovery efforts, but this data will prove critical in better understanding impacts to effectively direct future recovery efforts and funding. b. Pre-hurricane Transportation Funding and Financing Issues and Their Relationship to Recovery Municipalities in Puerto Rico were already facing financial struggles prior to Hurricanes Irma and Maria and were approximately $74 billion in debt. These financial struggles affected ability to receive Federal transportation funding. Due to Puerto Rico s long standing fiscal and economic situation, they were not often able to provide the necessary 20% minimum local match funding to receive Federal dollars. Mayors across the island were requesting funds for infrastructure improvements due to crumbling roadways, collapsed bus terminals, and other deteriorating infrastructure, but did not have the matching funds available. 33 Additionally, Puerto Rico has been long crippled by debt and an essentially bankrupt financial system, making the road to recovery even longer. Compared to mainland states like Texas and Florida, which were also recently hit by major storms, Puerto Rico

11 has and is facing considerably more challenges in receiving recovery funds due to the political, financial, and logistical challenges of delivering aid to the island. 34 In May 2017, ACT filed for Title III bankruptcy. The Bank of New York Mellon Corp serves as trustee for bonds issued by the ACT but was directed by the agency to not cover any bond payments coming due as the agency claims the money belongs to them as it works through bankruptcy proceeding to reduce its debt. The authority has approximately $4 billion of debt and at least one large holder of these highway bonds is suing Puerto Rico in an attempt to stop them from redirecting toll revenue away from bondholders, but the court denied the preliminary injunction. Credit ratings across all sectors in Puerto Rico were downgraded following the Hurricane Maria and are aligned with Moody s estimates of Puerto Rico s reduced debt serving capacity due to damage from natural causes. The Highways and Transportation Authority, 1968 Resolution bonds were specifically downgraded from Ca to C. 37 In May 2017, DTOW released Amendment #1 to the Transportation Improvement Program (TIP) Fiscal Year It was prepared in accordance with the requirements of MAP-21 and presents proposed improvements to the transportation and highway system in Puerto Rico for a period of four fiscal years. This TIP Amendment covers transportation programs and projects totaling approximately $58.1 million over four years. c. Number of Residents without Transportation Service as a Result of the Hurricanes Extremely limited data on the current status of transportation services is limited, but FEMA has reported that 58% of roads are open as of November 3 to allow passage through the outer ring of the island. Additionally, all airports and federally maintained ports are open or open with restrictions. 38 More specific data will prove critical in better understanding impacts to effectively direct future recovery efforts and funding. 4 Framework for Recovery: Existing Support and Preliminary Opportunity Areas a. Relevant Federal/State Recovery Policies The Federal Emergency Management Agency (FEMA) was established in 1979 to coordinate federal disaster policy including preparation, mitigation, response, and recovery. In 2011, FEMA released the National Disaster Recovery Framework (NDRF). The NDRF is a guiding framework that enables effective recovery support to disaster-impacted areas and enables disaster recovery managers to operate in a unified and collaborative manner (see organizational chart below, left). Its focus is how to best restore, redevelop and revitalize the health, social, economic, natural and environmental fabric of the community. Within the NDRF, a framework is provided if a disaster with catastrophic impact occurs to multiple sectors (see below, right). The joint field office (JFO) has a unified group of both state and federal officers and recovery coordinators to deliver recovery support functions

12 (RSFs) for each sector as defined in the figure. Transportation is listed under the Infrastructure System s RSF. Recovery services should be available by public transit as quickly as possible and consider accessibility for those with disabilities. 39 Over the first three months of recovery, over $1 billion federal funds have been provided to Puerto Rico as a result of Hurricanes Irma and Maria, largely driven by FEMA ($500m+), FHWA Emergency Relief funds ($72.5m), and public donations. 40 FEMA recommends ways for individuals to support recovery efforts through donating time or money to trusted charitable organizations. 41 FHWA s Emergency Relief Program is a special program from the Highway Trust Fund to repair Federal-aid highways and roads which have suffered serious damage from external causes. The authorized budget is $100 million annually but could be limited to $20 million for U.S. Territories. 42 The provision of quick release funds defers on-site damage surveys to later in the recovery process. 43 The Robert T. Stafford Disaster Relief and Emergency Assistance Act (Stafford Act) is one of the most encompassing Federal funding mechanisms to provide financial assistance to local, tribal, and State governments after a Presidential declaration has been made. Assistance under the Stafford Act is provided by FEMA in the form of both individual assistance and public assistance. 44 b. Description of Focus Areas to Facilitate Recovery Processes With the goal of the Resilient Puerto Rico Commission focusing around actionable and timely recommendations for aligning funding programs and recovery frameworks, the forthcoming recommendations from these efforts will focus on evaluating and prioritizing critical transportation infrastructure needs, identifying relevant funding

13 opportunities, and leveraging existing and enhanced organizational frameworks to build resilience across both hard and soft assets of Puerto Rico. In acknowledging the hazards, vulnerability and exposure which define the level of impact of Hurricanes Irma and Maria, the focus for the Resilient Puerto Rico Commission should evaluate key considerations in building resilience for the island, which includes the following: Mitigation: mitigation measures include efforts undertaken before an event to reduce or eliminate the risks from hazards that may affect human lives and property. The Federal Emergency Management Agency or FEMA, in the US, identifies several forms of mitigation, which includes a focus on land use practices to minimize exposure to hazardous areas, and construction practices to lessen the structural damage to critical buildings and infrastructure. Moreover, upon initiation, it is important for transportation agencies to integrate resilience planning as part of their strategy as early as possible; the sooner the implementation of a protection framework, the more cost efficient and effective it becomes. Preparedness and Emergency Response: for the physical infrastructure working group, this will include a focus on a vulnerability assessment of key infrastructure assets (and in this case, transportation assets) to prioritize those assets and align associated funding sources to enable a more rapid recovery. This also includes an evaluation of communications protocols and plans for assessing, repairing and returning transportation infrastructure to sufficient operating standards as quickly as possible. Recovery: In tandem with the preparedness and emergency response initiatives, recovery efforts will include both short-term and long-term initiatives. Generally, short-term initiatives tend to focus on life sustaining, property and infrastructure protection, and other measures intended to neutralize the immediate threat to life, environment, and property and infrastructure to stabilize the community. Long-term recovery, on the other hand, provides an assessment of critical facilities and transportation infrastructure to enable redundancy or reduce risks of future disruption based on their location and design. An example of a long-term initiative would be the widening of a bridge or roadway that improves both residents access to employment areas and improves a hurricane evacuation route. As a long-term effort and important investment in Puerto Rico s resiliency, evaluating the planning framework for the island s transportation infrastructure among other physical and natural infrastructure will be critical for ensuring the sustainability of the investments identified through this commission. 13

14 Source: AECOM c. Opportunities: Relevant Studies and Recovery Frameworks For an initial overview, below are two relevant studies and recovery frameworks developed to evaluate recent natural disasters and imminent challenges in the U.S. due to climate change. In response to Hurricane Sandy, the FHWA released the Post-Hurricane Sandy Transportation Resilience Study of NY, NJ, and CT. 45 This report contains a framework for evaluating the exposure, vulnerability, and risk faced by transportation assets from various climate stressors including sea level rise and coastal storm surge. It also contains 10 case studies on how the framework was applied to 10 different transportation assets (such as roadway segments, railway segments, bridges, roadway drainage systems, etc.) to evaluate their vulnerability, and come up with appropriate engineering-based adaptation strategies to mitigate vulnerabilities. The framework follows a certain pattern where the asset sensitivities and adaptive capacity are first documented, followed by a risk assessment which focuses more on what the broader economic, social, or environmental consequences of those assets going out of service might be. For example, if a bridge serves as an emergency evacuation route, then damage to the bridge is more consequential than if it were a regular bridge with plenty of redundancies in the overall transportation network. The risk assessment outlined here is often used as a way of prioritizing the most important assets to focus on for disaster recovery and long-term resiliency planning. In the San Francisco Bay Area, the Metropolitan Transportation Commission (MTC) released its report: Climate Change and Extreme Weather Adaptation Options for Transportation Assets in the Bay Area Pilot Project in December This report contains a very comprehensive compendium of different types of adaptation strategies that can be applied to different transportation assets. The strategies range from physical (e.g., levees) to

15 informational (e.g., doing a drainage study to fill knowledge gaps about drainage patterns on a highway) to governance-based strategies (e.g., updating a capital improvement plan to account for sea level rise considerations). It also contains a neat prioritization exercise for adaptation strategies, because often times multiple adaptation strategies are proposed for the same asset in order to select the most suitable among the options. The exercise uses a set of social, environmental, economic or governance criteria to evaluate the strategy options, and the strategy that scores the highest across each category rises to the top. While this initial report presents only a couple of relevant studies and recovery frameworks, additional analysis of additional studies and approaches that are applicable to Puerto Rico will be conducted through the physical infrastructure working group to identify other best practices for developing the key recommendations for the commission. 15

16 APPENDIX: Puerto Rico Transportation Plans & Reports 2040 Islandwide Long Range Transportation Plan: Long Range Multimodal Transportation Plans, Technical Working Paper: Public Involvement Plan (Task 2) Comprehensive Bicycle and Pedestrian Plan for Puerto Rico: _Main_Document.pdf FEMA s National Disaster Recovery Framework FEMA s Stafford Act: a531e65a3e1e63b8b2cfb7d3da7a785c/stafford_actselecthsa2016.pdf FHWA Post-Hurricane Sandy Transportation Resilience Study of NY, NJ, and CT 2017: MTC Climate Change and Extreme Weather Adaptation Options for Transportation Assets in the Bay Area Pilot Project 2014: Strategic Highway Safety Plan (SHSP) : SHSP Annual Report 2016: Transportation Improvement Program (TIP) FY Amendment #1: 16

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

TransAction Overview. Introduction. Vision. NVTA Jurisdictions

TransAction Overview. Introduction. Vision. NVTA Jurisdictions Introduction Vision NVTA Jurisdictions In the 21 st century, Northern Virginia will develop and sustain a multimodal transportation system that enhances quality of life and supports economic growth. Investments

More information

September 29, resilience360.com

September 29, resilience360.com September 29, 2017 resilience360.com resilience360@dhl.com 2 DHL RESILIENCE360 SPECIAL BRIEF Hurricane Maria made landfall in Puerto Rico on September 20, causing severe damage to the country s infrastructure,

More information

PUERTO RICO: PATHWAY TO THE FUTURE Opportunities of an Economic Transformation

PUERTO RICO: PATHWAY TO THE FUTURE Opportunities of an Economic Transformation PUERTO RICO: PATHWAY TO THE FUTURE Opportunities of an Economic Transformation Rebuilding Puerto Rico Mr. Omar J. Marrero, Esq. Executive Director Puerto Rico Public-Private Partnerships Authority & Central

More information

Preferred Alternative Summary

Preferred Alternative Summary Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative

More information

Puerto Rico in the Aftermath of Hurricanes Irma and Maria Jason Bram, Officer Research Economist

Puerto Rico in the Aftermath of Hurricanes Irma and Maria Jason Bram, Officer Research Economist Puerto Rico in the Aftermath of Hurricanes Irma and Maria Jason Bram, Officer Research Economist March 7, 2018 The views expressed here are those of the presenter and do not necessarily represent those

More information

SPECIAL AFRICA-INDIAN OCEAN (AFI) REGIONAL AIR NAVIGATION (RAN) MEETING

SPECIAL AFRICA-INDIAN OCEAN (AFI) REGIONAL AIR NAVIGATION (RAN) MEETING International Civil Aviation Organization 18/8/08 WORKING PAPER SPECIAL AFRICA-INDIAN OCEAN (AFI) REGIONAL AIR NAVIGATION (RAN) MEETING Durban, South Africa, 24 to 29 November 2008 Agenda Item 6: Development

More information

A Master Plan is one of the most important documents that can be prepared by an Airport.

A Master Plan is one of the most important documents that can be prepared by an Airport. The Master Plan A Master Plan is one of the most important documents that can be prepared by an Airport. A Master Plan is a visionary and a strategic document detailing planning initiatives for the Airport

More information

Dogpatch Community Task Force Meetings. April 24, 2017 Meeting #6

Dogpatch Community Task Force Meetings. April 24, 2017 Meeting #6 Dogpatch Community Task Force Meetings April 24, 2017 Meeting #6 Agenda I. Welcome and Introductions II. Agenda Overview, Recap of Meeting #5 and Dogpatch Community Task Force Process III. Comments from

More information

TERMS OF REFERENCE. Drone Advisory Committee (DAC) Role Name or Title Organization. Director, UAS Integration Office. Director, UAS Integration Office

TERMS OF REFERENCE. Drone Advisory Committee (DAC) Role Name or Title Organization. Director, UAS Integration Office. Director, UAS Integration Office TERMS OF REFERENCE Drone Advisory Committee (DAC) Committee Leadership Role Name or Title Organization Chairman Lead Designated Federal Officer Subcommittee Oversight Oversight Brian Krzanich Administrator

More information

Puerto Rico and the U.S. Virgin Islands After Hurricanes Irma and Maria Jason Bram, Officer Research Economist

Puerto Rico and the U.S. Virgin Islands After Hurricanes Irma and Maria Jason Bram, Officer Research Economist Puerto Rico and the U.S. Virgin Islands After Hurricanes Irma and Maria Jason Bram, Officer Research Economist Economic Press Briefing: February 22, 2018 The views expressed here are those of the presenter

More information

PPCR/SC.4/5 October 9, Meeting of the PPCR Sub-Committee Washington, D.C. October 28, REVIEW OF ON-GOING WORK OF THE MDBs IN DJIBOUTI

PPCR/SC.4/5 October 9, Meeting of the PPCR Sub-Committee Washington, D.C. October 28, REVIEW OF ON-GOING WORK OF THE MDBs IN DJIBOUTI PPCR/SC.4/5 October 9, 2009 Meeting of the PPCR Sub-Committee Washington, D.C. October 28, 2009 REVIEW OF ON-GOING WORK OF THE MDBs IN DJIBOUTI Proposed Sub-Committee Decision The Sub-Committee reviewed

More information

Establishes a fare structure for Tacoma Link light rail, to be implemented in September 2014.

Establishes a fare structure for Tacoma Link light rail, to be implemented in September 2014. RESOLUTION NO. R2013-24 Establish a Fare Structure and Fare Level for Tacoma Link MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE: Board 09/26/2013 Final Action Ric Ilgenfritz, Executive Director,

More information

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM

BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM BACKCOUNTRY TRAIL FLOOD REHABILITATION PROGRAM Backcountry Trail Flood Rehabilitation A June 2013 Flood Recovery Program Summary In June 2013, parts of Southern Alberta were devastated from significant

More information

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. Connecting People Building Opportunities 198 Brisbane Airport Corporation CHAPTER 10

More information

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012 1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley

More information

Agenda: SASP SAC Meeting 3

Agenda: SASP SAC Meeting 3 Agenda: SASP SAC Meeting 3 Date: 04/12/18 Public Involvement Plan Update Defining the System Recommended Classifications Discussion Break Review current system Outreach what we heard Proposed changes Classification

More information

NATIONAL AIRSPACE POLICY OF NEW ZEALAND

NATIONAL AIRSPACE POLICY OF NEW ZEALAND NATIONAL AIRSPACE POLICY OF NEW ZEALAND APRIL 2012 FOREWORD TO NATIONAL AIRSPACE POLICY STATEMENT When the government issued Connecting New Zealand, its policy direction for transport in August 2011, one

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

The role of Emergency Management Australia with Natural Hazards. Kerryn Vine-Camp

The role of Emergency Management Australia with Natural Hazards. Kerryn Vine-Camp The role of Emergency Management Australia with Natural Hazards NSW Geography Teachers Association Annual Forum Sydney 26 August 2011 Kerryn Vine-Camp Assistant Secretary, Crisis Coordination Branch Emergency

More information

Draft Executive Summary

Draft Executive Summary Draft Executive Summary The Juneau Tourism Plan development process was undertaken by Egret Communications and ARA Consulting in April 2001, under contract with the City and Borough of Juneau, Alaska.

More information

SASP Advisory Committee Meeting #2

SASP Advisory Committee Meeting #2 SASP Advisory Committee Meeting #2 MnDOT Office of Aeronautics #FlyMN www.minnesotago.org 1 Agenda Introductions Progress since last meeting Assessment of Prior Efforts Objectives and Strategies Trends

More information

Formulation of econometric solutions of immediate resources for a disaster area in Mayagüez, Puerto Rico

Formulation of econometric solutions of immediate resources for a disaster area in Mayagüez, Puerto Rico Department of Civil Engineering and Surveying University of Puerto Rico Mayagüez Campus Formulation of econometric solutions of immediate resources for a disaster area in Mayagüez, Puerto Rico Coral A.

More information

Why we re here: For educational purposes only

Why we re here: For educational purposes only Transportation 2050 Why we re here: For educational purposes only Transportation 2050 Bus Elements PUBLIC TRANSIT DEPARTMENT City of Phoenix Citizens Committee on the Future of Phoenix Transportation (CCFPT)

More information

A CASE FOR COMPLETING THE JORDAN RIVER PARKWAY: A

A CASE FOR COMPLETING THE JORDAN RIVER PARKWAY: A A CASE FOR COMPLETING THE JORDAN RIVER PARKWAY: A safe crossing at 9000 South and 850 West Proposed 9000 South Underpass Parkway Timeline Parkway, Trail, and Tourism Facts Blueprint Jordan River 1971 1973

More information

Puerto Rico Department of Transportation and Public Works Highway and Transportation Authority

Puerto Rico Department of Transportation and Public Works Highway and Transportation Authority Puerto Rico Department of Transportation and Public Works Highway and Transportation Authority San Juan Urbanized Area (SJUA) Urbanized Areas Under 200,000 in Population (UZA) Aguadilla Urbanized Area

More information

Potomac River Commuter Ferry Feasibility Study & RPE Results

Potomac River Commuter Ferry Feasibility Study & RPE Results 1.1 Introduction The Prince William County Department of Transportation conducted a route proving exercise (RPE) and feasibility study of a proposed commuter ferry service on the Potomac River between

More information

Airport Planning Area

Airport Planning Area PLANNING AREA POLICIES l AIRPORT Airport Planning Area LOCATION AND CONTEXT The Airport Planning Area ( Airport area ) is a key part of Boise s economy and transportation network; it features a multi-purpose

More information

Puerto Rico & the US Virgin Islands in the Aftermath of Hurricanes Irma and Maria Jason Bram, Officer Research Economist

Puerto Rico & the US Virgin Islands in the Aftermath of Hurricanes Irma and Maria Jason Bram, Officer Research Economist Puerto Rico & the US Virgin Islands in the Aftermath of Hurricanes Irma and Maria Jason Bram, Officer Research Economist Presentation to Community Advisory Group June 21, 2018 The views expressed here

More information

Eastern Caribbean Humanitarian Situation Report No. 12

Eastern Caribbean Humanitarian Situation Report No. 12 @UNICEF/Romaro Richardon/Anguilla2017 Eastern Caribbean Humanitarian Situation Report No. 12 14 November 2017 Highlights As of mid-november, the majority of schools in Anguilla, Antigua, British Virgin

More information

Opportunities in Non-Container Trade and the Expanding Cruise Industry

Opportunities in Non-Container Trade and the Expanding Cruise Industry Opportunities in Non-Container Trade and the Expanding Cruise Industry AAPA Commissioners Seminar Steven Cernak, Port Director Port of Galveston San Francisco, CA May 18, 2005 The Port Industry Is a highly

More information

FERRY SYSTEM FOR METRO AND ISLAND SERVICES April 20, 2017

FERRY SYSTEM FOR METRO AND ISLAND SERVICES April 20, 2017 FERRY SYSTEM FOR METRO AND ISLAND SERVICES April 20, 2017 DISCLOSURE The materials contained in this presentation are for informational purposes only. This document does not constitute an offer to sell

More information

Waterfront Plan Working Group Meeting Maritime & Water-Dependent Uses Meeting Agenda

Waterfront Plan Working Group Meeting Maritime & Water-Dependent Uses Meeting Agenda Waterfront Plan Working Group Meeting Maritime & Water-Dependent Uses Meeting Agenda Overview of Port Maritime & Water-Dependent Uses Summary of Maritime Planning and Policies Q&A and Discussion of Operational

More information

FLIGHT PATH FOR THE FUTURE OF MOBILITY

FLIGHT PATH FOR THE FUTURE OF MOBILITY FLIGHT PATH FOR THE FUTURE OF MOBILITY Building the flight path for the future of mobility takes more than imagination. Success relies on the proven ability to transform vision into reality for the betterment

More information

WESTERN EL DORADO COUNTY SHORT AND LONG-RANGE TRANSIT PLAN Executive Summary

WESTERN EL DORADO COUNTY SHORT AND LONG-RANGE TRANSIT PLAN Executive Summary WESTERN EL DORADO COUNTY SHORT AND LONG-RANGE TRANSIT PLAN Executive Summary Prepared for the El Dorado County Transportation Commission Prepared by The El Dorado County Transportation Commission (EDCTC)

More information

Traditional and Alternative Financing of Cruise Terminals

Traditional and Alternative Financing of Cruise Terminals Traditional and Alternative Financing of Cruise Terminals Steven Cernak, Port Director Port of Galveston AAPA Cruise Seminar Grand Cayman, Cayman Islands January 11, 2007 How

More information

Terms of Reference: Introduction

Terms of Reference: Introduction Terms of Reference: Assessment of airport-airline engagement on the appropriate scope, design and cost of new runway capacity; and Support in analysing technical responses to the Government s draft NPS

More information

REPORT 2014/065 INTERNAL AUDIT DIVISION. Audit of air operations in the United. Nations Assistance Mission in Afghanistan

REPORT 2014/065 INTERNAL AUDIT DIVISION. Audit of air operations in the United. Nations Assistance Mission in Afghanistan INTERNAL AUDIT DIVISION REPORT 2014/065 Audit of air operations in the United Nations Assistance Mission in Afghanistan Overall results relating to the effective management of air operations in the United

More information

Blueways: Rivers, lakes, or streams with public access for recreation that includes fishing, nature observation, and opportunities for boating.

Blueways: Rivers, lakes, or streams with public access for recreation that includes fishing, nature observation, and opportunities for boating. Parks, Open Space and Trails PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN TRAILS PLAN CONTENTS The components of the trails plan are: Intent Definitions Goals, Policies, and Action Strategies Trails Map

More information

Department of Legislative Services Maryland General Assembly 2009 Session

Department of Legislative Services Maryland General Assembly 2009 Session Department of Legislative Services Maryland General Assembly 2009 Session SB 650 FISCAL AND POLICY NOTE Senate Bill 650 (Senators Pipkin and Astle) Finance and Budget and Taxation Medevac Helicopter Improvement

More information

IOW Ramblers Submission Paper to the Sept 2016 ROW Improvement Plan Consultation.

IOW Ramblers Submission Paper to the Sept 2016 ROW Improvement Plan Consultation. IOW Ramblers Submission Paper to the Sept 2016 ROW Improvement Plan Consultation. The current Island Rights of Way Improvement Plan is a comprehensive document and much of its content is still relevant

More information

FY Transit Needs Assessment. Ventura County Transportation Commission

FY Transit Needs Assessment. Ventura County Transportation Commission FY 18-19 Transit Needs Assessment Ventura County Transportation Commission Contents List of Figures and Appendices.. 2 Appendices... 1 Chapter 1: Introduction What is the Ventura County Transportation

More information

Attachment 1 PARK & RIDE GUIDELINES

Attachment 1 PARK & RIDE GUIDELINES Attachment 1 PARK & RIDE GUIDELINES The City of Edmonton August 2018 Executive Summary Edmonton will soon be a city of a million people - not within 25 years but within the next five years. This growth

More information

DRAFT GENERAL IMPLEMENTATION PLAN AND SPECIFIC IMPLEMENTATION PLAN MIDDLETON MUNICIPAL AIRPORT MOREY FIELD. Revised 12/12/03

DRAFT GENERAL IMPLEMENTATION PLAN AND SPECIFIC IMPLEMENTATION PLAN MIDDLETON MUNICIPAL AIRPORT MOREY FIELD. Revised 12/12/03 DRAFT GENERAL IMPLEMENTATION PLAN AND SPECIFIC IMPLEMENTATION PLAN MIDDLETON MUNICIPAL AIRPORT MOREY FIELD Revised 12/12/03 As recommended for approval by the Plan Commission General Project Description

More information

Regional Planning for Tri-Rail Coastal Link

Regional Planning for Tri-Rail Coastal Link 2013 APTA Rail Conference Regional Planning for Tri-Rail Coastal Link William L. Cross, P.E. South Florida Regional Transportation Authority Director of Planning and Capital Development Pompano Beach,

More information

Implementation Strategy for the Lethbridge Destination Management Organization (LDMO)

Implementation Strategy for the Lethbridge Destination Management Organization (LDMO) Implementation Strategy for the Lethbridge Destination Management Organization (LDMO) IMPLEMENTATION AND TRANSITION STRATEGY LDMO MANDATE: To establish a destination management organization that provides

More information

Federal Aviation Administration Flight Plan Presented at the Canadian Aviation Safety Seminar April 20, 2004

Federal Aviation Administration Flight Plan Presented at the Canadian Aviation Safety Seminar April 20, 2004 Federal Aviation Administration Flight Plan 2004-2008 Presented at the Canadian Aviation Safety Seminar April 20, 2004 Challenges Reducing an Already Low Commercial Accident Rate Building an Air Traffic

More information

WELLINGTON $422 MILLION $614 MILLION $83 MILLION 22% SPEND $1.9 BILLION

WELLINGTON $422 MILLION $614 MILLION $83 MILLION 22% SPEND $1.9 BILLION WELLINGTON WELLINGTON $1.9 BILLION FORECAST TOTAL WELLINGTON INVESTMENT The Wellington region s transport challenges are dominated by the region s concentration of population in the metropolitan cities,

More information

Chapter 1: Introduction Draft

Chapter 1: Introduction Draft Chapter 1: Draft TABLE OF CONTENTS 1... 4 1.6.1 Stakeholder Engagement Plan... 10 Chapter 1 Page 2 TABLE OF EXHIBITS Exhibit 1.1-1 ABIA Annual Growth Since 1993... 5 Exhibit 1.4-1: ABIA Location Map...

More information

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the

More information

Tolling in Washington State. Craig J. Stone, P.E. Assistant Secretary, Toll Division

Tolling in Washington State. Craig J. Stone, P.E. Assistant Secretary, Toll Division Tolling in Washington State Craig J. Stone, P.E. Assistant Secretary, Toll Division Connecticut Department of Transportation Bridgeport, CT June 4, 2014 Tolling in Washington State Tolling is part of Washington

More information

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT

Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT December 2018 Project Summary Boulder County, Colorado, in partnership with the City of Boulder, is evaluating options for multi-use

More information

Overview of Highway 37 Project. Novato Rotary November 4, 2016

Overview of Highway 37 Project. Novato Rotary November 4, 2016 Overview of Highway 37 Project Novato Rotary November 4, 2016 Project Location-Caltrans District 4 SR 37 Corridor Features Two to Four lane 21 mile corridor traversing Solano, Sonoma, and Marin Counties.

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JANUARY 25, 2011

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JANUARY 25, 2011 Item 1, Report No. 1, of the Priorities and Key Initiatives Committee, which was adopted without amendment by the Council of the City of Vaughan on January 25,. 1 RAPID TRANSIT UPDATE TORONTO-YORK SPADINA

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT

8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT 8 CROSS-BOUNDARY AGREEMENT WITH BRAMPTON TRANSIT The Transportation Services Committee recommends the adoption of the recommendations contained in the following report dated May 27, 2010, from the Commissioner

More information

EMBARGOED FOR 5AM ET JUNE 5, 2017 PRESIDENT DONALD J. TRUMP S PRINCIPLES FOR REFORMING THE U.S. AIR TRAFFIC CONTROL SYSTEM.

EMBARGOED FOR 5AM ET JUNE 5, 2017 PRESIDENT DONALD J. TRUMP S PRINCIPLES FOR REFORMING THE U.S. AIR TRAFFIC CONTROL SYSTEM. EMBARGOED FOR 5AM ET JUNE 5, 2017 PRESIDENT DONALD J. TRUMP S PRINCIPLES FOR REFORMING THE U.S. AIR TRAFFIC CONTROL SYSTEM Overview The U.S. Air Traffic Control (ATC) system is one of the most important

More information

WORKING TOGETHER TO ENHANCE AIRPORT OPERATIONAL SAFETY. Ermenando Silva APEX, in Safety Manager ACI, World

WORKING TOGETHER TO ENHANCE AIRPORT OPERATIONAL SAFETY. Ermenando Silva APEX, in Safety Manager ACI, World WORKING TOGETHER TO ENHANCE AIRPORT OPERATIONAL SAFETY Ermenando Silva APEX, in Safety Manager ACI, World Aerodrome Manual The aim and objectives of the aerodrome manual and how it is to be used by operating

More information

Rebuilding Puerto Rico:

Rebuilding Puerto Rico: KEEPING YOU IN THE KNOW Rebuilding Puerto Rico: The Aftermath of Hurricanes Irma and María By Lynnette Alicea León, E.I.T. This image shows a collapsed bridge in Road PR-634 km 11.7, Morovis, Puerto Rico.

More information

Arlington County Board Meeting Project Briefing. October 20, 2015

Arlington County Board Meeting Project Briefing. October 20, 2015 Arlington County Board Meeting Project Briefing October 20, 2015 Project Map 2 Project Context Only Interstate in the Country limited to HOV only traffic during rush hours Stoplight at the end of I-66

More information

AN-Conf/12-WP/162 TWELFTH THE CONFERENCE. The attached report

AN-Conf/12-WP/162 TWELFTH THE CONFERENCE. The attached report 29/11/12 TWELFTH AIR NAVIGATION CONFERENCE Montréal, 19 to 30 November 2012 REPORT OF THE COMMITTEE TO THE CONFERENCE ON AGENDA ITEM 2 The attached report has been approved by thee Committee for submission

More information

City of Durango 5.8 FUNDING TRAILS DEVELOPMENT

City of Durango 5.8 FUNDING TRAILS DEVELOPMENT 5.8 FUNDING TRAILS DEVELOPMENT The City has been successful in establishing dedicated local funding sources as well as applying for grants to develop the City s trail system, having received nearly $2.4

More information

The Corporation of the City of Kawartha Lakes Council Report

The Corporation of the City of Kawartha Lakes Council Report The Corporation of the City of Kawartha Lakes Council Report Report Number ENG2017-008 Date: September 12, 2017 Time: 2:00 p.m. Place: Council Chambers Ward Community Identifier: All Subject: Author Name

More information

Aviation, Rail, & Trucking 6-1

Aviation, Rail, & Trucking 6-1 6-1 This chapter describes the services, facilities, and condition of air, rail, and trucking as components of the transportation system. These three intermodal areas have an impact on the factors to be

More information

1.0 BACKGROUND NEW VETERANS CHARTER EVALUATION OBJECTIVES STUDY APPROACH EVALUATION LIMITATIONS... 7

1.0 BACKGROUND NEW VETERANS CHARTER EVALUATION OBJECTIVES STUDY APPROACH EVALUATION LIMITATIONS... 7 New Veterans Charter Evaluation Plan TABLE CONTENTS Page 1.0 BACKGROUND... 1 2.0 NEW VETERANS CHARTER EVALUATION OBJECTIVES... 2 3.0 STUDY APPROACH... 3 4.0 EVALUATION LIMITATIONS... 7 5.0 FUTURE PROJECTS...

More information

Draft for approval by TCC on 2/3, TAQC on 2/9 and ARC Board on 2/22. Regional Trail Plan. Mike Alexander, Director, Center for Livable Communities

Draft for approval by TCC on 2/3, TAQC on 2/9 and ARC Board on 2/22. Regional Trail Plan. Mike Alexander, Director, Center for Livable Communities DATE: February 3, 2017 ISSUE SUMMARY: Regional Trail Plan FROM: Mike Alexander, Director, Center for Livable Communities IMPORTANCE: In May 2016, ARC adopted the active transportation component of the

More information

STAFF REPORT TO COUNCIL

STAFF REPORT TO COUNCIL i CITYOF PRINCE GEORGE STAFF REPORT TO COUNCIL 1100 Patricia Blvd. I Prince George, BC, Canada V2L 3V9 I www.pri ncegeorge.ca DATE: January 24, 2017 TO: NAME AND TITLE: SUBJECT: MAYOR AND COUNCIL Dave

More information

APPENDIX B COMMUTER BUS FAREBOX POLICY PEER REVIEW

APPENDIX B COMMUTER BUS FAREBOX POLICY PEER REVIEW APPENDIX B COMMUTER BUS FAREBOX POLICY PEER REVIEW APPENDIX B COMMUTER BUS FAREBOX POLICY PEER REVIEW The following pages are excerpts from a DRAFT-version Fare Analysis report conducted by Nelson\Nygaard

More information

McLean Citizens Association Transportation Committee Project Briefing

McLean Citizens Association Transportation Committee Project Briefing McLean Citizens Association Transportation Committee Project Briefing November 10, 2015 Project Map 2 Project Context Only Interstate in the Country limited to HOV only traffic during rush hours Stoplight

More information

Wellington $312 $49 $456 OVERVIEW WELLINGTON REGIONAL SUMMARY

Wellington $312 $49 $456 OVERVIEW WELLINGTON REGIONAL SUMMARY National Land Transport Programme 2015 18 Wellington WELLINGTON REGIONAL SUMMARY OVERVIEW The Wellington region is made up of a number of cities, urban areas and supporting rural hinterland. The city is

More information

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization REPORT FOR ACTION 12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization Date: April 27, 2018 To: Toronto and East York Community Council From: Senior Strategic Director,

More information

Mass Rescue Operations

Mass Rescue Operations Mass Rescue Operations Partnership + Planning + Practice = Preparedness SARSCENE 2007 Victoria, British Columbia Rick Button Coordination Division Office of Search and Rescue, United States Coast Guard

More information

Chapter 1: Introduction

Chapter 1: Introduction Chapter 1: TABLE OF CONTENTS 1... 4 1.1 Master Plan Study Content... 4 1.2 Purpose and Scope of Master Plan Study... 4 1.3 Airport History and Role... 6 1.4 Airport Location and Service Area... 6 1.5 ABIA

More information

SR 934 Project Development And Environment (PD&E) Study

SR 934 Project Development And Environment (PD&E) Study SR 934 Project Development And Environment (PD&E) Study Project Advisory Group Meeting March 1, 2018 State Road 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive PD&E STUDY SR 934/NE/NW

More information

2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016

2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016 2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016 Project numbers do not signify ranking they are for mapping identification purposes only. 1. 15th Street East The

More information

Ridership Growth Strategy (RGS) Status Update

Ridership Growth Strategy (RGS) Status Update For Information Ridership Growth Strategy (RGS) Status Update Date: July 10, 2018 To: TTC Board From: Deputy Chief Executive Officer Summary The TTC s Ridership Growth Strategy (RGS), with all its components,

More information

Crown Corporation BUSINESS PLANS FOR THE FISCAL YEAR Trade Centre Limited. Table of Contents. Business Plan

Crown Corporation BUSINESS PLANS FOR THE FISCAL YEAR Trade Centre Limited. Table of Contents. Business Plan Crown Corporation BUSINESS PLANS FOR THE FISCAL YEAR 2014 2015 Trade Centre Limited Business Plan 2014 2015 Table of Contents Message from the CEO and the Chair... Mission... Planning Context... Strategic

More information

Preparatory Course in Business (RMIT) SIM Global Education. Bachelor of Applied Science (Aviation) (Top-Up) RMIT University, Australia

Preparatory Course in Business (RMIT) SIM Global Education. Bachelor of Applied Science (Aviation) (Top-Up) RMIT University, Australia Preparatory Course in Business (RMIT) SIM Global Education Bachelor of Applied Science (Aviation) (Top-Up) RMIT University, Australia Brief Outline of Modules (Updated 18 September 2018) BUS005 MANAGING

More information

3 Pilbara ports provide gateways

3 Pilbara ports provide gateways COMMUNITY AND STAKEHOLDERS Community Consultation Committees 8 meetings each year across our 3 port locations Dampier, Port Hedland and Ashburton Community Support Initiative >$295,000 a year in financial

More information

Fare Policy Discussion Background and History

Fare Policy Discussion Background and History Fare Policy Discussion Background and History Transportation Committee Nick Eull Senior Manager of Revenue Operations February 27 th, 2017 2013 Fare Policy Analysis Report Cross-functional group comprised

More information

Aerodrome Emergency Plan and Public Health Emergencies

Aerodrome Emergency Plan and Public Health Emergencies Aerodrome Emergency Plan and Public Health Emergencies Nancy Onyedim ICAO TCB Field Operations Officer 5 th AFRICA REGIONAL MEETING OF THE COLLABORATIVE ARRANGEMENT FOR THE PREVENTION AND MANAGEMENT OF

More information

Consultation on Draft Airports National Policy Statement: new runway capacity and infrastructure at airports in the South East of England

Consultation on Draft Airports National Policy Statement: new runway capacity and infrastructure at airports in the South East of England Tony Kershaw Honorary Secretary County Hall Chichester West Sussex PO19 1RQ Telephone 033022 22543 Website: www.gatcom.org.uk If calling ask for Mrs. Paula Street e-mail: secretary@gatcom.org.uk 22 May

More information

WINTER SHELTER IN EAST KING COUNTY

WINTER SHELTER IN EAST KING COUNTY WINTER SHELTER IN EAST KING COUNTY Vision Statement Every person in East King County has the opportunity to live in a safe, affordable, healthy home. Value Statement Homelessness is an experience that

More information

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan

Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan Parkland County Municipal Development Plan Amendment Acheson Industrial Area Structure Plan New Plan Acheson Industrial Area Structure Plan Amendment Parkland County Municipal Development Plan Board Reference

More information

TORONTO TRANSIT COMMISSION REPORT NO. SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION STATION NAMES IN THE CITY OF VAUGHAN

TORONTO TRANSIT COMMISSION REPORT NO. SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION STATION NAMES IN THE CITY OF VAUGHAN TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: February 29, 2011 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION STATION NAMES IN THE CITY OF VAUGHAN ACTION ITEM RECOMMENDATIONS It is recommended that

More information

Introduction DRAFT March 9, 2017

Introduction DRAFT March 9, 2017 Chapter Overview The City of Redmond (City) initiated an update to the Airport Master Plan ( Plan ) to assess the facility and service needs of the Redmond Municipal Airport ( the Airport ) throughout

More information

SAMTRANS TITLE VI STANDARDS AND POLICIES

SAMTRANS TITLE VI STANDARDS AND POLICIES SAMTRANS TITLE VI STANDARDS AND POLICIES Adopted March 13, 2013 Federal Title VI requirements of the Civil Rights Act of 1964 were recently updated by the Federal Transit Administration (FTA) and now require

More information

FNORTHWEST ARKANSAS WESTERN BELTWAY FEASIBILITY STUDY

FNORTHWEST ARKANSAS WESTERN BELTWAY FEASIBILITY STUDY FNORTHWEST ARKANSAS WESTERN BELTWAY FEASIBILITY STUDY EXECUTIVE SUMMARY The 2030 Northwest Arkansas Regional Transportation Plan developed by the Northwest Arkansas Regional Planning Commission (NWARPC)

More information

Strategic Objectives, Initiatives and Actions

Strategic Objectives, Initiatives and Actions Strategic Objectives, Initiatives and Actions The following Strategic Objectives and the associated Initiatives and Actions for each have been developed to meet the challenges associated with trail development

More information

Climate Change Impacts and Adaptation for Coastal Transport Infrastructure in the Caribbean

Climate Change Impacts and Adaptation for Coastal Transport Infrastructure in the Caribbean UNCTAD Regional Workshop 5 7 December 2017, Bridgetown, Barbados Climate Change Impacts and Adaptation for Coastal Transport Infrastructure in the Caribbean Addressing the challenge of climate change adaptation

More information

UNMANNED AIRCRAFT PROVISIONS IN FAA REAUTHORIZATION BILL

UNMANNED AIRCRAFT PROVISIONS IN FAA REAUTHORIZATION BILL UNMANNED AIRCRAFT PROVISIONS IN FAA REAUTHORIZATION BILL Section 341 Comprehensive Plan -Codifies in title 49 the requirement in the 2012 FAA reauthorization Act that a comprehensive plan to safely accelerate

More information

2016 Regional Transportation Alternatives Program (TAP) Grant Application

2016 Regional Transportation Alternatives Program (TAP) Grant Application 2016 Regional Transportation Alternatives Program (TAP) Grant Application PROJECT TITLE: Yelm-Tenino Trail Extension Feasibility Study TRPC use only GENERAL PROJECT INFORMATION Agency or Organization City

More information

4.2 Regional Air Navigation/Safety Developments and Achievements. Group (NAM/CAR ANI/WG) INTEGRATION OF UNMANNED AIRCRAFT SYSTEMS (UAS)

4.2 Regional Air Navigation/Safety Developments and Achievements. Group (NAM/CAR ANI/WG) INTEGRATION OF UNMANNED AIRCRAFT SYSTEMS (UAS) 03/05/16 Sixth Meeting of the North American, Central American and Caribbean Directors of Civil Aviation (NACC/DCA/06) Nassau, Bahamas, 10 12 May 2016 Agenda Item 4: Accountability Report of the ICAO NACC

More information

EX28.6 REPORT FOR ACTION. Advancing Fare Integration SUMMARY. Date: October 16, 2017 To: Executive Committee From: City Manager Wards: All

EX28.6 REPORT FOR ACTION. Advancing Fare Integration SUMMARY. Date: October 16, 2017 To: Executive Committee From: City Manager Wards: All EX28.6 REPORT FOR ACTION Advancing Fare Integration Date: October 16, 2017 To: Executive Committee From: City Manager Wards: All SUMMARY In July 2016, City Council considered a current state assessment

More information

Update on Palm Beach MPO Funded Projects

Update on Palm Beach MPO Funded Projects Update on Palm Beach MPO Funded Projects Presented February 3, 2016: Palm Beach Technical Advisory Committee (TAC) Citizens Advisory Committees (CAC) Tri-Rail Milestones Service began Jan 9, 1989 Double-tracking

More information

Chapter 6: POLICY AND PROCEDURE RECOMMENDATIONS

Chapter 6: POLICY AND PROCEDURE RECOMMENDATIONS Chapter 6 POLICY AND PROCEDURE RECOMMENDATIONS FOR SRRA Below are seven policy elements that should be considered for adoption by the Southwest Regional Recreation Authority of Virginia: 1. Develop strategies

More information

Strengthening the Ontario Trails Strategy. Report on Consultations and the Environmental Bill of Rights Registry

Strengthening the Ontario Trails Strategy. Report on Consultations and the Environmental Bill of Rights Registry Strengthening the Ontario Trails Strategy Report on Consultations and the Environmental Bill of Rights Registry Purpose To report on the feedback and information received through the regional consultations,

More information

The Strategic Commercial and Procurement Manager

The Strategic Commercial and Procurement Manager Item 3 To: Procurement Sub Committee On: 8 June 2016 Report by: The Strategic Commercial and Procurement Manager Heading: Renfrewshire Council s Community Benefit Strategy 2016 1. Summary 1.1. The purpose

More information

Overview of Highway 37 Project. Napa County Board of Supervisors December 20, 2016

Overview of Highway 37 Project. Napa County Board of Supervisors December 20, 2016 Overview of Highway 37 Project Napa County Board of Supervisors December 20, 2016 1 Project Location-Caltrans District 4 2 SR 37 Corridor Features 2 to 4 lane 21 mile corridor traversing Solano, Sonoma,

More information

REPORT 2014/111 INTERNAL AUDIT DIVISION. Audit of air operations in the United Nations Operation in Côte d Ivoire

REPORT 2014/111 INTERNAL AUDIT DIVISION. Audit of air operations in the United Nations Operation in Côte d Ivoire INTERNAL AUDIT DIVISION REPORT 2014/111 Audit of air operations in the United Nations Operation in Côte d Ivoire Overall results relating to the effective management of air operations in the United Nations

More information