HUME CORRIDOR INTEGRATED GROWTH AREA PLAN (HIGAP) INFRASTRUCTURE AND DELIVERY STRATEGY

Size: px
Start display at page:

Download "HUME CORRIDOR INTEGRATED GROWTH AREA PLAN (HIGAP) INFRASTRUCTURE AND DELIVERY STRATEGY"

Transcription

1

2

3

4 HUME CITY COUNCIL HUME CORRIDOR INTEGRATED GROWTH AREA PLAN (HIGAP) INFRASTRUCTURE AND DELIVERY STRATEGY DECEMBER

5 PREAMBLE This Infrastructure and Delivery Strategy aims to provide direction of what an appropriate order and timing to the delivery of new development and new infrastructure would be to guide the growth of the Hume Corridor. It does not guarantee that development and infrastructure will occur as outlined and for this reason the Strategy will be updated frequently (at least every 5 years) with the costs, staging and funding of development and infrastructure updated accordingly. 1

6 CONTENTS 1. INTRODUCTION NEW INFRASTRUCTURE DEVELOPMENT SEQUENCING & INFRASTRUCTURE TIMING ACHIEVING POPULATION & JOBS GROWTH BALANCE FUNDING INFRASTRUCTURE FURTHER WORK MONITORING AND REVIEW

7 1. INTRODUCTION The Hume Corridor will see significant sustained growth and change in the coming 30 years and more. This growth and change brings significant opportunity for improvements in access to jobs, housing and the multitude of services communities and businesses require. However, it also presents a very serious and important challenge to local, state and federal government, and the private and voluntary sectors to deliver new infrastructure and services in step with this change. There is growing evidence that infrastructure in growth area locations like the Hume Corridor is not keeping up with the rate of development. This includes a report by the Auditor General (see Box 1.1) that concluded that State Governments have continually failed to find sufficient funding to support growth with a backlog of $10 billion for transport infrastructure alone. Box 1.1 Victorian Auditor General s 2013 report Developing Transport Infrastructure and Services for Population Growth Areas (page viii) Over many years, the state has failed to deliver the transport infrastructure and services needed to support rapidly growing communities. This is adversely impacting accessibility, and risks the future liveability of metropolitan Melbourne. Urgent action is required to address this serious problem. Inadequate public transport and growing gaps in the road network in these communities are creating barriers to mobility, including access to critical services, education and employment opportunities. In turn, these deficiencies are increasing car dependence, pollution and exacerbating traffic congestion at significant community cost. This both limits state productivity and the time that people can spend with their families. Despite these growing problems, funding to address the transport needs of growth areas can take more than a generation to materialise. This longstanding disconnect between planning and funding gives credence to the perception that past statewide planning initiatives have been disingenuous. Growing pressure on state finances heightens the need to effectively prioritise limited funds, and to develop alternative funding sources and implementation strategies to meet the growing challenge. Hume City Council has developed a Spatial Strategy to guide the future development of Hume Corridor as enabled by the State Government s Growth Corridor Plan, Plan Melbourne and Precinct Structure Plans. The Spatial Strategy outlines the future vision for the area and details where new development and change will occur and what infrastructure is required. 3

8 1.1. Purpose of this Document This Infrastructure & Delivery Strategy outlines in more detail when and how this development, change and infrastructure will be delivered. In doing so, this document serves a number of purposes: A document outlining what new infrastructure will be required to meet demand from new development, how much it will cost, and who is responsible to fund it including investment from Council, State Agencies and State Government. Evidence to demonstrate the need for investment in infrastructure to unlock development and achieve the sustainable growth of the area as set out in the Spatial Strategy. A tool to prioritise and co-ordinate State and local infrastructure funding priorities to ensure it is delivered in step with development. A tool to direct the sequencing and opening up of new development fronts so that they align with the location and enable timely provision of planned infrastructure and services. Evidence to support new detailed precinct specific Development Contributions Plans, future development tariffs, and Section 173 Agreements for the delivery of infrastructure. A clear document identifying what further work is required, when and by whom to facilitate and enable development and change to deliver the Spatial Strategy. In so doing, this Infrastructure and Delivery Strategy aims to: Enable appropriately staged development that is coordinated with appropriately funded and timely infrastructure delivery Status of this Document The content of this document has been informed by meetings and discussions with a range of service providers and private sector agencies. It draws from the Northern Horizons work prepared for NorthLink by ARUP that identifies the infrastructure needs of the whole Northern Sub Region over the coming 50 years. Many of the actions and investment strategies required to realise this Infrastructure and Delivery Strategy are outside the control of Hume City Council. It is intended that this work will inform the forward planning and investment plans of those responsible for their delivery, notably State Government agencies. This Strategy provides a preferred and appropriate order and timing to the delivery of new development and new infrastructure needed. It does not guarantee that development and infrastructure will occur as outlined and for this reason the Strategy will be updated frequently (at least every 5 years) with the costs, timing and funding of development and infrastructure updated accordingly. 4

9 2. NEW INFRASTRUCTURE This section outlines what infrastructure projects are required and who is responsible for their delivery. It prioritises the infrastructure projects with the highest priority given to the infrastructure projects that are directly related to unlocking the potential growth of the Hume Corridor, supporting businesses or enabling it to function appropriately Responsibilities State Government is responsible for the funding and delivery of the most critical, the largest and the most expensive infrastructure projects identified in the Spatial Strategy. These include new train stations, major road upgrades, new schools and a higher education facility and a new hospital. Hume City Council is responsible for the funding and delivery of more local infrastructure, including local roads, new active sports reserves, community meeting spaces, and early years facilities such as maternal child health and pre schools. Mainstream State funding and rates funding will be the principal source of funding for much of this new infrastructure with developers also making a significant contribution through Growth Area Infrastructure Charge (GAIC) and local Development Contributions Plans (DCPs) Priorities In many cases, this mainstream funding is only set for a short period (often less than 5 years). This makes investment in large scale State and local infrastructure subject to changing budget and political decisions. To address this, genuine and justified priorities need to be made that ensure that the most important and most significant infrastructure items are not affected by changing political commitments or funding strategies, and are delivered. Hume City Council has identified a priority for each of the infrastructure projects identified in the Spatial Strategy for the Hume Corridor area based on the following three levels: Priority 1: Fundamental Infrastructure this is infrastructure that is fundamental to the management of growth and change such that it must happen to enable growth and change to occur. Failure to deliver should result in new development within the Hume Corridor being capped and planning permits being refused until it is delivered. Priority 2: Required Infrastructure this is infrastructure that is required and must happen if new development is to occur without impacting on the sustainability of the Hume Corridor. Failure to deliver should result in new development in the area associated with the infrastructure being refused a planning permit until changes to the planning of the affected areas can be made. 5

10 Priority 3: Desirable Infrastructure this is infrastructure that is desirable to deliver the overall vision in the Spatial Strategy as it would enhance the overall quality of life of residents in the Hume Corridor. Failure to deliver this infrastructure should not result in any changes to the timing of development occurring but alternative funding or planning should be pursued to achieve comparable benefits. The new large scale infrastructure items identified in the Spatial Strategy are listed below with associated priority and timing. The Lead Agency refers to the primary agency responsible for progressing the planning and delivery of that specific piece of infrastructure. The Funding Agency refers to the primary agency responsible for funding that piece of infrastructure. In some cases other agencies will be involved in either progressing or funding the infrastructure. The sequencing of development with this infrastructure is outlined in Section 3 including potential caps to development should fundamental infrastructure be delayed Large Scale New Infrastructure Transport Infrastructure The most important and costly infrastructure for the Hume Corridor is transport infrastructure. Without its delivery, new development will place a significant and unacceptable strain upon the existing road and public transport infrastructure and significantly impact upon the liveability, the economy and the sustainability of the Hume Corridor. Timings are based on projected development rates and will be updated regularly. Road Infrastructure Aitken Boulevard Aitken Boulevard is a new arterial road and future Bus Rapid Transit route that will connect development throughout the Hume Corridor and parts of Mitchell Shire to the new and expanded activity centres of Broadmeadows, Craigieburn and Mickleham (Merrifield) and their many job opportunities and services. It will be complete from Somerton Road to Mount Ridley Road by North of Mount Ridley Road should be a priority in the short term for developer and State Government funding to enable construction to Donnybrook Road by Funding should also be provided to duplicate it and extend it north to Wallan and south to the Western Ring Road by 2031 with bus priority measures. Priority: Fundamental Infrastructure Cost: $240mil (estimate) Required Timeframe: Constructed from Somerton Road to Donnybrook Road by 2021 and in full by 2031 Lead Agency: State Govt (Vic Roads/PTV) Funding Agency: State Govt and developers 6

11 Map 2.1 Major Infrastructure Requirements Hume Corridor 7

12 Attwood Connector Attwood Connector is an important new road and public transport connection to Aitken Boulevard and Barry Road that will provide high quality access for residents and businesses throughout the Hume Corridor to Melbourne Airport. It should be a high priority for State Government investment to improve access to Melbourne Airport, relieve pressure on Mickleham Road and the Tullamarine Freeway. It should be constructed by Priority: Required Infrastructure Cost: $135 million (estimate) Required Timeframe: by 2031 Lead Agency: State Govt (Vic Roads/PTV) Funding Agency: State Govt Hume Freeway and Hume Highway The Hume Freeway and Hume Highway are critical freight and commuter routes that service the many businesses of Hume. Both are anticipated to see significant increases in traffic and congestion in the coming years. New interchanges and flyovers are required in the north of the Hume Corridor along the Hume Freeway, notably a half diamond south of Donnybrook Road that will assist in unlocking employment areas. Upgrades to parallel arterial roads or the construction of the OMR should be prioritised but both roads will need an additional lane to support growth with the stretch north of Mount Ridley Road needed from Priority: Fundamental Infrastructure Cost: Unknown Required Timeframe: 2026 onwards Lead Agency: State Govt (Vic Roads)/ Federal Govt Funding Agency: State Govt The Outer Metropolitan Ring (OMR) & E6 The proposed OMR is a major freeway and potential rail route that will connect the outer western port area of Melbourne, Geelong and Avalon Airport with the Hume Freeway. It has the potential to significantly enhance the accessibility of the northern part of the Hume Corridor to these major transport hubs, particularly the Donnybrook Road Employment Precinct and future Beveridge Interstate Freight Terminal in Mitchell Shire. It will also help improve accessibility to the future employment areas in the western and northern areas of Melbourne. Whilst vitally important it does not negate the need for upgrades to parallel arterial roads, notably Mickleham Road and Aitken Boulevard. Priority: Required Infrastructure Cost: Unknown Required Timeframe: by 2031 Lead Agency: State Govt (Vic Roads)/ Federal Govt Funding Agency: State Govt Mickleham Road Mickleham Road is forecast to see a 56% increase in traffic by 2021 (from 2011) as significant development occurs along its length. This will require staged duplication of the 8

13 road north of Somerton Road by 2021 with staged duplication up to Donnybrook Road. An additional lane south of Somerton Road is needed by 2026 with 6 lanes required ultimately along its length to Donnybrook Road. Priority: Fundamental Infrastructure Cost: $110mil (estimate) Required Timeframe: commenced by 2021 & staged Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt Pascoe Vale Road Pascoe Vale Road will be an increasingly important public transport connection in the short to medium term connecting residents north of Somerton Road to the expanding services and job opportunities in the Broadmeadows centre. There is potential to introduce bus priority lanes at intersections or along the entire length. When Aitken Boulevard is completed to the Western Ring Road traffic calming measures should be pursued through the Broadmeadows Metropolitan Activity Centre to improve the amenity of the centre and improve connectivity through this important centre. Priority: Required Infrastructure Cost: $14mil (estimate) Required Timeframe: Bus priority by 2026 and traffic calming post 2031 Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt Somerton Road Somerton Road (combined with Cooper Street) is the most complete east-west arterial road in the Wider Northern Growth Region. Its importance will increase significantly in the short to medium term connecting new residential areas in Greenvale to Roxburgh Park Town Centre and Roxburgh Park Train Station. It is also critical to maintaining excellent connectivity for businesses at Melbourne Airport, the Hume Highway and Cooper Street, and connecting the entire Hume Corridor to Epping Town Centre and the Northern Hospital in Whittlesea. It will also provide important links to and from the growing Sunbury area on completion of the Bulla Bypass. It should be duplicated from Aitken Boulevard to Roxburgh Park Drive with capacity for bus priority on the opening of Aitken Boulevard and also duplicated to Mickleham Road immediately following with duplication to Bulla on completion of the Bulla Bypass. Widening to 6 lanes should commence at the eastern end by Priority: Fundamental Infrastructure Cost: $40mil Required Timeframe: Immediate Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt 9

14 Craigieburn Road Craigieburn Road is the only east-west arterial road within the fast growing Craigieburn area. Duplication from the new Craigieburn Town Centre to the Hume Highway should be complete in the immediate term with capacity for bus priority at intersections to enable efficient bus access to the train station. This is critical to minimising traffic issues through the Craigieburn area and providing a genuine public transport alternative to driving to Craigieburn Train Station. Duplication west of the Town Centre to Mickleham Road should be staged with new development. A more effective connection over the Hume Highway and train line will also be important to manage demand onto the Hume Highway, to commuter parking on Potter Street and connections to future development in the City of Whittlesea. Priority: Fundamental Infrastructure Cost: $40mil plus bridge (estimate) Required Timeframe: Immediate and staged with development Lead Agency: State Govt (Vic Roads/PTV) Funding Agency: State Govt Mount Ridley Road Mount Ridley Road will be a future declared State arterial road that will provide important connectivity across the Hume Freeway to the Craigieburn Employment area and beyond to the Wollert area in Whittlesea. Whilst the bridge over the Hume Freeway is likely to be expensive, it is critical that this connection is made to minimise traffic on Grand Boulevard and the existing freeway crossing to Amaroo that were not designed for high volumes. It should be duplicated with the new bridge constructed by Priority: Required Infrastructure Cost: $42mil plus bridge (estimate) Required Timeframe: by 2031 Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt Donnybrook Road Donnybrook Road will be an increasingly important future east-west arterial road that will connect new businesses to the Hume Freeway and connect residents within Hume and Whittlesea to employment, the Hume Freeway and Donnybrook Station. It will be particularly important in the coming years before the Cameron Street overpass is constructed to its north and the Mount Ridley Road/Summerhill Road overpass is constructed to the south. It should be duplicated immediately to serve the employment area and in full by Ultimately it should be 6 lanes. Priority: Fundamental Infrastructure Cost: $50mil Required Timeframe: Immediate with duplication complete by 2031 Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt 10

15 Western Arterial North of Mickleham (Merrifield Town Centre) A new arterial road is proposed north of the Mickleham (Merrifield) Town Centre that will connect the new residential communities in Mitchell Shire to the Hume Corridor. The first carriageway in each direction will be funded by developers. Priority: Required Infrastructure Cost: $15 million (estimate) Required Timeframe: by 2031 Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt Johnstone Street Johnstone Street is an important east-west link in the south of the Hume Corridor that experiences high volumes at peak time. It is currently a mixture of single lane and dual lane in each direction. Its full duplication would assist in reducing bottlenecks and should certainly occur when Aitken Boulevard is extended south of Somerton Road. Priority: Required Infrastructure Cost: $5-10mil plus bridge (estimate) Required Timeframe: by 2031 Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt Airport Drive Airport Drive is a critical alternative to the Tullamarine Freeway for accessing Melbourne Airport. It is currently being constructed and will need to be duplicated in step with development at Melbourne Airport. Priority: Required Infrastructure Cost: Privately funded Required Timeframe: Immediate and duplicated with development Lead Agency: Federal Government Funding Agency: Melbourne Airport Status: Committed Tullamarine Freeway Tullamarine Freeway is the primary means of accessing Melbourne Airport from the south and provides access to the city via city link. Additional lanes are required in the immediate term to retain adequate access to Melbourne Airport. Priority: Required Infrastructure Cost: Unknown Required Timeframe: by 2021 Lead Agency: State Govt (Vic Roads)/ Federal Govt Funding Agency: State Govt Status: Committed There are a number of new secondary arterial roads that will be constructed as part of the new development areas as single lane roads in each direction initially and will need to be duplicated in the future. These are not likely to be required within the coming 15 years and will be identified in updates to this Infrastructure and Delivery Strategy. 11

16 Public Transport Infrastructure Parking at Craigieburn Train Station Parking at Craigieburn Train Station is a significant priority for the immediate term. Additional parking should be added to address increases in patronage at Craigieburn Station of 250% by 2021 and 450% by 2031 from 2011 levels. Priority: Required Infrastructure Cost: Unknown Required Timeframe: Immediate and staged to meet demand. Lead Agency: State Govt (PTV) Funding Agency: State Govt Extension of Upfield Line The extension of the Upfield Line to Roxburgh Park and ultimately to Wallan is critical to providing appropriate and equitable access to public transport in the north of the Hume Corridor. It should be delivered as soon as feasible and certainly by Priority: Fundamental Infrastructure Cost: $400mil (estimate) Required Timeframe: by 2026 Lead Agency: State Govt (PTV) Funding Agency: State Govt Lockerbie Train Station Lockerbie Train Station is vital to providing sustainable travel options from the northern part of the Hume Corridor (Lockerbie and Mickleham Precincts) and wider northern area in the Northern Region. It is also critical to the potential of the Lockerbie Town Centre to attract large scale office development. It is forecast to attract 900 passengers a day at 2021 if constructed by this date and 8,500 per day by It should be provided by Priority: Fundamental Infrastructure Cost: $50million (estimate) Required Timeframe: by 2026 Lead Agency: State Govt (PTV) Funding Agency: State Govt Upgrade to Donnybrook Train Station Plans are in place to make minor upgrades to Donnybrook Train Station in the immediate term. Further upgrades and significant increases in car parking are needed to manage the anticipated increase in patronage to 700 passengers a day by 2021 and 10,000 per day by Priority: Required Infrastructure Cost: $25mil (estimate) Required Timeframe: by 2021 Lead Agency: State Govt (PTV) Funding Agency: State Govt 12

17 Upgrade to Broadmeadows Train Station The upgrade to Broadmeadows station is vital to improving the appearance and perception of Broadmeadows as an investment location of choice. It should be provided within the immediate term. Priority: Required Infrastructure Cost: $25-40mil (estimate) Required Timeframe: Immediate Lead Agency: State Govt (PTV) Funding Agency: State Govt Buses to Craigieburn Train Station Additional bus services to Craigieburn will be required in the immediate term to meet the demand of residents seeking access to Craigieburn Train Station. Priority: Required Infrastructure Cost: Unknown Required Timeframe: Immediate and staged with development to the north and west of Craigieburn Lead Agency: State Govt (PTV) Funding Agency: State Govt Buses along Aitken Boulevard to Broadmeadows Aitken Boulevard represents a unique opportunity to provide a high quality and highly attractive bus route for residents throughout the Hume Corridor to sustainably access the important large activity centres of Broadmeadows, Craigieburn and Mickleham (Merrifield). It is critical to achieving a socially just and sustainable Hume Corridor and services should be provided as soon as Aitken Boulevard is complete to Somerton Road and extended as Aitken Boulevard is extended (see above). Priority: Required Infrastructure Cost: Unknown Required Timeframe: Immediate and extended as Aitken Boulevard is constructed Lead Agency: State Govt (PTV) Funding Agency: State Govt Buses to Melbourne Airport Melbourne Airport will continue to be one the largest employment areas in Melbourne and attract significant trips from residents throughout the Hume Corridor. Buses from Wallan to the airport utilising Aitken Boulevard or Mickleham Road and the Attwood Connector are anticipated to attract over 10,000 passengers a day by 2031 and be highly viable from Priority: Required Infrastructure Cost: Unknown Required Timeframe: by 2026 Lead Agency: State Govt (PTV) Funding Agency: State Govt 13

18 Map 2.2 Bicycle Network in the Hume Corridor 14

19 Buses to Epping Hospital Until a hospital is constructed in the Hume Corridor, there will be a need to provide improvements in accessibility to the Northern Health Hospital at Epping, particularly for those living in Craigieburn and Roxburgh Park area. Priority: Required Infrastructure Cost: Unknown Required Timeframe: Immediate Lead Agency: State Govt (PTV) Funding Agency: State Govt Bicycle Infrastructure A range of cycle paths and improved cycling infrastructure have been identified in the Hume Bicycle Network Plan and Spatial Strategy that offer potential to reduce the need to travel by private car. Map 2.2 above shows the location of the bicycle routes in the Hume Corridor. The majority of new paths in growth areas will be developed as part of the construction of new roads and linear open space reserves by developers, Vic Roads and Parks Victoria. Within established areas Hume City Council and VicRoads will be the primary agencies for delivering new paths and improved signage to address gaps in the network. Health, Education and Leisure Facilities As the Hume Corridor and wider Northern Region grows, large scale health, education and leisure facilities will be needed to provide acceptable levels of accessibility to these important services. Whilst State Government is still forming its view on the requirements for a hospital or equivalent and a university, Hume City Council is strongly of the view that both are required infrastructure for an area with such a large future population. Such facilities will also provide vital new employment opportunities and help to stimulate greater job diversification. University La Trobe University and RMIT offers a high quality option for students wishing to undertake tertiary education as do the courses run from Hume s Global Learning Centres. However, to bring about the step change in skills needed to maintain and increase the economy of the Hume Corridor and the wider Northern Region, and to ensure adequate access to tertiary education, a new university campus is required. Mickleham (Merrifield) Town Centre offers the optimal location in the Hume Corridor for a new university facility with Lockerbie an alternative. It should be provided as soon as practical and viable. With Aitken Boulevard likely to be constructed by 2021 and development advanced in the Mickleham (Merrifield) Town Centre by 2026, an initial presence in 2026 would be reasonable and provide the catalyst to employment needed in the northern part of the Hume Corridor. 15

20 Priority: Required Infrastructure Cost: Unknown Required Timeframe: 2026 and staged expansion Lead Agency: State Govt Funding Agency: State & Commonwealth Hospital or Equivalent The Northern Health Hospital at Epping provides vital services for the Northern Region but with the population of the Hume, Mitchell and Whittlesea areas exceeding 900,000 people, a new public hospital is required. Mickleham (Merrifield) Town Centre is again the optimal location for a future hospital (or equivalent) with Lockerbie an alternative. With Aitken Boulevard likely to be constructed by 2021 and development advanced in the Mickleham (Merrifield) Town Centre by 2026, an interim facility in 2026 would be appropriate and provide the catalyst to employment needed in the northern part of the Hume Corridor. Priority: Required Infrastructure Cost: Unknown Required Timeframe: 2026 and staged expansion Lead Agency: State Govt Funding Agency: State Govt New Health Services New health services are proposed at Broadmeadows to meet the needs in the southern part of the Hume Corridor and to take pressure off the Epping Hospital in the short to medium term. New health services are also required in Craigieburn either as an extension to the existing facilities or a new facility within the town centre. Priority: Required Infrastructure Cost: Unknown Required Timeframe: Immediate with staged expansion Lead Agency: State Govt Funding Agency: State Govt Sports and Leisure Hub Merrifield Park offers a unique opportunity to provide high quality state scale sports and leisure facilities comparable with Albert Park. Its delivery will require significant investment and commitment to ongoing management arrangements from State Government, Melbourne Water and Hume City Council. It will serve the entire Northern Region, Sunbury and much of the wider northern and western parts of Melbourne. Priority: Desirable Infrastructure Cost: Unknown Required Timeframe: Unknown Lead Agency: State Govt Funding Agency: State Govt 16

21 Hume Regional Aquatic Centre and Athletics Facility A new aquatic and athletics facility is planned as part of the Craigieburn Town Park. It is due to open in The aquatic facility will serve the Craigieburn, Roxburgh Park and Mickleham Road North area while the athletics facility will serve the entire Hume Corridor. Priority: Desirable Infrastructure Cost: $48 million (estimated) Required Timeframe: 2016 Lead Agency: Hume City Council Funding Agency: Hume City Council Status: Committed Lockerbie Regional Sports Facilities Land for additional regional sports facilities is identified in the Lockerbie PSP south of the proposed Lockerbie Town Centre. This facility is intended to serve residents in the Lockerbie area as well as residents in the neighbouring future suburbs in Whittlesea and Mitchell. Priority: Desirable Infrastructure Lead Agency: Hume City Council/City of Whittlesea/Mitchell Shire Council Cost: $50 million (estimated) Funding Agency: Hume City Council/State Govt Required Timeframe: Post 2031 A Performing Arts Centre A Performing Arts Centre in the Hume Corridor is desirable over the coming 30 years to meet demand for performance space. Further work is required to determine the community needs and to advance the future planning and development of such a facility. Priority: Desirable Infrastructure Cost: $30 million (estimated) Required Timeframe: To be determined Lead Agency: Hume City Council Funding Agency: Hume City Council/State Govt Open Space Infrastructure The Hume Corridor contains a number of unique areas of landscape and natural heritage value that also offer significant major passive recreation opportunities. These areas are critical to providing a source of local identity, encouraging healthy lifestyles and interacting with nature. Merri Creek Regional Park The Merri Creek is the largest creek in the Hume Corridor and extends all the way to the Yarra River. High quality parkland, conservation and footpath/bicycle paths are provided from Abbotsford and Fairfield as far as the Western Ring Road. Land has been secured to deliver this to Craigieburn Road and is currently being constructed in stages. Plans are approved to extend this network. There is potential to further this link to Lockerbie Town Centre and beyond in the coming years. 17

22 Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: staged over coming 30 years Lead Agency: State Govt & Hume City Council Funding Agency: To be determined Status: Part committed to Craigieburn Road Craigieburn & Mickleham Green Network There are numerous creek, drainage lines and areas of established and scattered woodland through the growing Craigieburn area that are planned to be connected with walking and bicycle paths and biodiversity links. It will be managed by numerous agencies, notably Parks Victoria and Council. Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: in step with development Lead Agency: State Government & Hume City Council Funding Agency: State Government and Developer A number of existing open space areas will also be improved in the coming years to improve access and enjoyment of open space by residents throughout the Hume Corridor. These include improvements to the Broadmeadows Valley Park and Jacana Valley Park Local Scale Infrastructure To meet the demands of growth, changing community needs and new standards of provision, a large number of local infrastructure projects will also need to be delivered in the coming 30 years within the precincts identified in the Spatial Strategy (see Map 2.2). These will take the form of: New infrastructure new infrastructure where none exists currently to meet an identified service need (typically in new development areas) Expanded infrastructure expansion to existing infrastructure to meet an identified service need (typically in established areas) Renewal infrastructure upgrade to existing infrastructure to improve the condition but not meet an identified service need (typically in established areas). Hume City Council Facilities Appendix 1 lists planned and proposed new or expanded local leisure and community infrastructure that are the responsibility of Hume City Council to deliver. The list is based on current service planning work, discussions with State Agencies and the Hume City Council Open Space Strategy and the Hume City Council Leisure Strategy. There will be a need to provide other new and expanded local infrastructure to meet changing standards and service needs not currently identified, particularly to meet the needs of the increasing number 18

23 Map Precincts of the Hume Corridor 19

24 of older people. Appendix 1 will be updated to reflect these changes, the outcomes of ongoing service planning and updates to the Open Space Strategy and the Leisure Strategy. The funding challenges of delivering this local infrastructure are outlined in Section 5. Local Education and Health Facilities There are a number of local education and health facilities that are identified in existing plans and are the responsibility of State Government and the private sector to deliver. These required facilities must be delivered to support growth and development and will be controlled in precincts where there is a significant delay in their delivery. Whilst the timing of such facilities will ultimately be determined by State Government and the private sector, Table 2.1 below identifies recommended timeframes for additional local education facilities to ensure appropriate access to education in the precincts of the Hume Corridor in Map

25 Table 2.1 Recommended Timing of New Local Education Precinct Location Facility Recommended Timing Mickleham Road South Mickleham Road North Craigieburn Mickleham Lockerbie Government Secondary School Government Primary School west of Mickleham Road Government Primary School south of Craigieburn Road Government Primary School north of Craigieburn Road Private Primary School north of Somerton Road Government Primary School in northern part of Highlands estate Government Primary School South of Craigieburn Road Government Primary School in R2 PSP area Private Primary School in R2 PSP area Government Primary School north of Donnybrook Road Government Primary School south of Donnybrook Road Government Secondary School Private Primary School Government Primary School north of Donnybrook Road Government Primary School south of Gunns Gully Road Government Secondary School Private Primary School 0-5 years 5-10 years 15+ years 15+ years 15+ years Immediate 0-5 years years 0-5 years years 15+ years years years 5-10 years 15+ years years 5-10 years Recommended timing based on HCC analysis and subject to review. Actual timing will be confirmed by Department of Education and Training (DET) and private education providers. 21

26 3. RESIDENTIAL DEVELOPMENT SEQUENCING & INFRASTRUCTURE TIMING At the heart of this strategy is a commitment to better align development with the delivery of the infrastructure identified in Section Why Sequence and Stage Development? Managing the sequencing and staging of development provides a number of significant benefits for the community, government and the developers. These include: Providing early indication of when large infrastructure investments are required, especially those that require long lead in times Prioritising limited infrastructure funding to the most important and most needed infrastructure projects Ensuring that development and growth is directed to the most infrastructure ready areas Aligning various public and private funding and investment streams to development areas at the appropriate time Giving the existing and future community and businesses the confidence that the infrastructure they depend upon will be upgraded. State policy contains a number of clauses that seek to ensure that development and infrastructure are staged, notably Clause which states: Objective To manage the sequence of development in growth areas so that services are available from early in the life of new communities. Strategies Define preferred development sequences in growth areas to better coordinate infrastructure planning and funding. Ensure that new land is released in growth areas in a timely fashion to facilitate coordinated and cost-efficient provision of local and regional infrastructure. Require new development to make a financial contribution to the provision of infrastructure such as community facilities, public transport and roads. Improve the coordination and timing of the installation of services and infrastructure in new development areas. [emphasis added] 3.2. Weaknesses in Existing Plans Unfortunately, even with this strong State Policy Clause, none of the plans prepared in Melbourne s growth areas include any preferred sequencing and staging or development. There is also no comprehensive infrastructure plan and no mechanisms for ensuring that new State infrastructure is delivered when it is required, particularly transport infrastructure. 22

27 This failure is resulting in new communities throughout Melbourne s growth areas being left without adequate infrastructure for periods of time longer than would be desirable, causing economic and social disadvantage Addressing Policy Failure in Development and Infrastructure Coordination The scale of growth in the Hume Corridor makes it critical that more is achieved around the sequencing of development and timely provision of new infrastructure. This Infrastructure and Delivery Strategy seeks to rectify this failure in the current plans for the Hume Corridor in three ways: 1. Identifying what fundamental infrastructure is needed to unlock initial development. 2. Directing development fronts towards locations where there is planned infrastructure needed to unlock and support further development. 3. Identifying limits to development should fundamental infrastructure not be provided when required Preferred Sequencing and Staging of Development and Infrastructure in the Hume Corridor Maps 3.1 to 3.4 shows the preferred sequencing of new residential development within the new development areas of the Hume Corridor over the coming 15 years. It also shows when the major transport, community and recreation infrastructure outlined in Section 2 should be delivered. The sequencing of residential and employment development reflects: Identified constraints to development posed by service infrastructure, topography and land ownership. The need to unlock land to enable the delivery of new major retail, community, recreation and leisure infrastructure at an early stage in the development of new areas. It has been informed by: Discussions with developers about their preferred locations for commencing and intentions for new development fronts. The anticipated rate of development growth based on ID Consulting projections and discussions with developers. Transport modelling and discussions with State transport agencies about the timing of major infrastructure. Community Infrastructure Assessments and discussions with service providers. The potential for Works in Kind (WIK) contributions by developers in lieu of their GAIC payments. There are five broad residential development fronts in the Hume Corridor: Greenvale Lakes and Roxburgh Park Area (in Roxburgh Park and Meadow Heights Precinct) Development in the Roxburgh Park and Meadow Heights precinct should be predominantly to the east of Aitken Boulevard in the coming years (0-5 years) in the 23

28 Greenvale Lakes estate and in the new Roxburgh Park town centre site. This development should facilitate the completion of Aitken Boulevard as a priority with new recreation facilities provided within 5 years. Development west of Aitken Boulevard requires the design and construction of a bund to protect the Greenvale Reservoir before development can commence. Greenvale and Mickleham Road Area (in Mickleham Road South and North Precincts) There are 3 development areas either side of Mickleham Road and Somerton Road that are currently under construction. Land to the south of Somerton Road is fragmented which makes development more complex and slow to deliver. Larger land parcels north of Somerton Road are anticipated to progress more quickly and be complete within 10 years generating sufficient demand for the delivery of additional bus routes and local community and recreation facilities. Land further north along Mickleham Road within the area known as Craigieburn West should commence when development in the Craigieburn precinct starts to reduce (5-10 years). The infrastructure to initially unlock development is principally in place though additional or upgraded intersections will be required from Mickleham Road and Somerton Road. The duplication of Mickleham Road and Somerton Road by 2021 is fundamental to supporting on going development in this precinct. Development that helps to deliver the north-south connector road network parallel to Mickleham Road through Craigieburn West will be prioritised to provide for new bus routes as will road connections into Craigieburn. This is critical to linking this area and the Merrifield West area to Craigieburn Town Centre and Craigieburn train station. Craigieburn Precinct Much of the new development areas in the Craigieburn Precinct are controlled by large developers making sustained high levels of growth likely over the coming 15 years. The preferred sequencing of the new development areas is aimed at initially (0-5 years) expanding south of Craigieburn Road to deliver the final sections of Aitken Boulevard and to unlock land for new community and recreation facilities planned south of Craigieburn Road in both the Highlands Estate and the Aston Estate. In the period from 5 to 10 years, the development should spread westwards north of Craigieburn Road to unlock land for further community and recreation facilities and to deliver a new north-south connector road that will be an important future bus route. The duplication of Craigieburn Road in the short term is fundamental to this area developing appropriately and enabling effective bus services to the Craigieburn Train Station. Mickleham Precinct New intersections from Donnybrook Road are needed to unlock residential development on both sides of Donnybrook Road in the relatively isolated Mickleham Precinct. It is vital that housing development be directed towards the land planned for local retail, 24

29 community and recreation facilities to enable their delivery within 5 to 10 years. Temporary facilities maybe required if development is too slow to help build social connectedness and ensure an appropriate standard of service provision. The extension of Aitken Boulevard from Mount Ridley Road to Donnybrook Road is also vital to enabling appropriate access and bus services from this area to the existing larger scale community and recreation facilities in Craigieburn and the Craigieburn Town Centre, and access to the Craigieburn Train Station. On the north side of Donnybrook Road development should be focussed on delivering a new connector road to the Mickleham (Merrifield) Town Centre once the land identified for community and recreation facilities is unlocked to enable appropriate pedestrian, cycling, bus and car access from this area to the future town centre. Upgrades to Donnybrook Road in step with development and an upgrade to Donnybrook Station within 5 10 years is needed to manage the large increase in commuter and industrial traffic this area will experience. Lockerbie and Kalkallo New intersections from Donnybrook Road are needed to unlock initial residential development in the relatively isolated Lockerbie Precinct. Development should be directed towards unlocking the land identified for recreation and community facilities in the southern part of this precinct to enable their development within 5-10 years. A new access off the Hume Freeway at Gunns Gully Road must be provided to unlock residential development further north as there is insufficient capacity at the intersections with Donnybrook to support development north of Kalkallo. Development utilising this new access should be directed to unlocking the land planned for community and recreation facilities north of Kalkallo (10-15 years) the future Lockerbie Train Station and Donnybrook (Lockerbie) Town Centre to enable their timely delivery. A road connection from this new development area to the initial development immediately north of Donnybrook Road is critical to provide a viable bus route for this area. Upgrades to Donnybrook train station and duplication to Donnybrook Road will be required within 5-10 years to support the additional demand in this precinct and in the neighbouring new development areas in the City of Whittlesea. Development in the Kalkallo Township should occur when reticulated services are provided to the area along Donnybrook Road and Cameron Street. 25

30 Map 3.1 Preferred Sequencing and Staging of New Residential Development 26

31 Map 3.2 Location of New Residential Development

32 Map 3.3 Location of New Residential Development

33 Map 3.4 Location of New Residential Development

34 3.5. Limits to Residential Development in the Growth Areas of Hume Corridor The availability and capacity of existing major transport and community infrastructure is currently acceptable in the Hume Corridor. However, if the fundamental infrastructure identified in Section 2 is not delivered in accordance with the timeframes outlined then the rate of development should be controlled. Table 3.1 lists the fundamental infrastructure needed in the next 10 years that is triggered by new development and the limits to this new development that should apply were that infrastructure not to be delivered. These caps are based on the scale of development included in the Transport Assessments that identified the need for the upgrades listed in Table 3.1 below. The precincts are those in Map 2.2 above. Table 3.1 Limits to Development Fundamental Infrastructure Date Required Limit to Development Mickleham Road Duplication - Somerton Road to Craigieburn Road Somerton Road Duplication - Aitken Boulevard to Roxburgh Park Drive and Mickleham Road Craigieburn Road Duplication Hothlyn Drive to Craigieburn Town Centre and Mickleham Road By 2021 Mickleham Road North Precinct limited to 2,500 lots Craigieburn Precinct limited to 17,500 lots By 2021 Mickleham Road North Precinct limited to 2,500 lots. By 2021 Craigieburn Precinct limited to 17,500 lots The limits identified in Table 3.1 will apply unless infrastructure assessments are provided that demonstrate further development can be supported. These infrastructure assessments must meet the requirements in Box 3.1 below. Beyond the next 10 years, limits to development should apply to development in Mickleham, Lockerbie, Woodstock and Donnybrook (City of Whittlesea) precincts should there be delays to Aitken Boulevard duplication, Mickleham Road duplication, Lockerbie Train Station, Donnybrook Road duplication, and Hume Freeway Upgrade Advocating for Infrastructure Hume City Council does not want to have to limit development but equally is not prepared to support new development that does not have adequate infrastructure. It has advocated since the Urban Growth Boundary was changed in 2010 for State Government to commit to infrastructure delivery in step with development and raised significant concern that the Growth Corridor Plans and Plan Melbourne have been approved with no commitment to infrastructure funding and delivery. 30

35 Hume City Council will continue to advocate for new infrastructure and work with the State Agencies and the development industry to track infrastructure funding. Box 3.1 Infrastructure Assessments for Increased Development Beyond Identified Limits To identify the potential for increased development beyond the identified limits to development in Table 3.1, an Infrastructure Assessment must be undertaken that: 1. Confirms the design capacity of the fundamental infrastructure item 2. Confirms the current use of the fundamental infrastructure item 3. Confirms the spare capacity of the fundamental infrastructure item 4. Confirms the timing and funding for the completion of the upgrade of the fundamental infrastructure item The methodology in the infrastructure assessment must be approved by Hume City Council and relevant State Agency (e.g. Vic Roads). Development proposed beyond the limit identified in Table 3.1 will only be supported if the infrastructure assessment identifies: 1. There is sufficient spare capacity within the use of the fundamental infrastructure design capacity to support the scale of additional development proposed And/or 2. Funding is provided within the State Government budget for the completion of the full upgrade works required for the fundamental infrastructure within 1 year of the additional proposed development commencing. 31

36 4. ACHIEVING POPULATION & JOBS GROWTH BALANCE Around the world, expanding cites are facing significant challenges in matching local jobs growth with population growth. Melbourne is no different and the distance and journey time its residents travel to access work has increased significantly as the city has grown. The Hume Corridor currently has a high level of self sufficiency (112%) and relatively high self containment rate with approximately 18,000 people living and working in the area. The timing and the rate of development in employment areas is highly dependent upon the performance of the economy and business confidence and is less predictable than residential development. Table 4.1 shows the recent rates and aspirational projections of employment growth within the Hume Corridor compared to growth in the labour force and working population. It shows that if these aspirational projections are met, the Hume Corridor will retain a high level of self sufficiency of jobs to labour force. Table 4.1: Population and Jobs Growth Working Age Labour Force Target Number of Self Sufficiency Population Jobs ,800 50,000 56, % ,400 58,000 65, % ,900 75,530 83, % ,000 91, , % , , , % Source: AEC Economic Assessment To achieve this, an additional 35ha employment land (45ha of gross) and around 5,000 to 7,000sq.m of office floorspace would be required each year. To provide maximum potential for these job targets and land requirements to be met, it is critical that the infrastructure (particularly transport infrastructure) identified in Section 2 is delivered in the timeframes identified to: unlock new development sites achieve quality access to major road and transport network retain short journey times to major destinations like Melbourne Airport provide a high level of reliability in journey times provide access to a large workforce retain and enhance the image of the Hume Corridor as a high quality location for businesses and investment. 32

37 5. FUNDING INFRASTRUCTURE 5.1. Funding State Infrastructure The cost of providing the State road, public transport, education, health and leisure infrastructure identified in Section 2 as well as in the Wider Northern Growth Area is phenomenal. State Infrastructure is principally funded through the annual budgeting process. However, the Growth Area Infrastructure Contribution (GAIC) provides State Government with a modest additional pool of funds to deliver State infrastructure in growth areas. Table 5.1 shows the current and projected GAIC funds in the Hume Corridor and compares this to the estimated expenditure required to deliver the State infrastructure needed in accordance with the timeframes of this Strategy. Due to uncertainty on costings, this table does not include costs for the extension to Upfield Line, the OMR, additional lane on Hume Freeway, new bus services, additional parking at train stations and a new university. Table 5.1a: State Infrastructure Costs & GAIC Collected Over Time Years State Infrastructure Costs GAIC Collected Surplus/Deficit $107,170,000 $53,100,000 -$54,070, $332,622,000 $69,400,000 -$263,222, $668,910,000 $54,500,000 -$614,410, $856,038,000 $45,200,000 -$810,838, $189,260,000 $41,800,000 -$147,460,000 Total $2,154,000,000 $264,000,000 -$1,890,000,000 Note: Table excludes the Upfield Line Extension, OMR, additional lane on Hume Freeway, new bus services, additional parking at train stations and a new university as costs are unknown It shows a significant funding allocation will need to be identified in the State budget on an annual basis to supplement the GAIC. It also shows that the GAIC funding will need to be prioritised appropriately. Hume City Council believes that the GAIC funding should be prioritised towards the Fundamental infrastructure items outlined in Section 2 with priority given to the projects listed in Table 5.1b GAIC Works in Kind New legislation allows for developers to undertake works in kind (WIK) in lieu of making their GAIC payments. The legislation contains a number of conditions relating to when WIK is permitted, notably that a WIK Agreement must be lodged prior to GAIC being triggered for a title. Table 5.2 below identifies the projects that would be suitable for WIK in the Hume Corridor. There are a number of Fundamental Infrastructure items identified in Section 2 that are not 33

38 listed. Whilst these are significant priorities for delivery, the cost and timing of these items means that WIK is not considered a suitable funding approach. For more information on the GAIC please go to Table 5.1b Priority State Infrastructure Projects for GAIC Funding Priority Infrastructure Project 1 Somerton Road Duplication 2 Craigieburn Train Station Parking Location Cost Suitable GAIC WIK Staged with priority initially to Aitken Boulevard and then Mickleham Road Land adjoining Craigieburn Train Station 3 Craigieburn Road Staged with priority Hanson Road to Dorchester Close and then Aitken Boulevard to Mickleham Road 4 Mickleham Road Duplication 5 Aitken Boulevard North of Somerton Road 6 Donnybrook Road Duplication 7 Donnybrook Train Station Upgrade 8 Lockerbie Train Station Staged with priority Somerton Road to Craigieburn Road and then to Donnybrook Road New road through inter urban break. Staged duplication with priority to Mount Ridley Road to Craigieburn Road and then south to Somerton Road before completing duplication north Staged with Priority from Hume Freeway to Aitken Boulevard and Hume Freeway to Donnybrook Station before completing duplication On Donnybrook Road east of Lockerbie East of Donnybrook (Mickleham) Town Centre $10-15 million (estimate) Unknown $15-20 million (estimate) $40-50 million (estimate) $ million (estimate) $25-30 million (estimate) $10-25 million (estimate) $50-80 million (estimate) Yes in parts No Yes (see Table 5.2) Yes in parts (see Table 5.2) Yes in parts (see Table 5.2) Yes (see Table 5.2) Yes (see Table 5.2) Yes (see Table 5.2) 34

39 Table 5.2 Suitable GAIC Works in Kind Projects Infrastructure Project Aitken Boulevard first lane through inter urban break and duplication Lockerbie Train Station Donnybrook Train Station Upgrade Mickleham Road Duplication Craigieburn Road Location Cost Justification WIK to be Provided by Mickleham Precinct Lockerbie Precinct Lockerbie Precinct Mickleham Road North Precinct & Mickleham Precinct Mickleham Road North $9-12mil (estimate) $50-80mil (estimate) $10-25 million (estimate) $40-50mil (estimate) $15-20mil (estimate) Aitken Boulevard is a critical part of the arterial road and principal public transport network serving the Northern Growth Region. The first lane is required to be constructed through the Donnybrook Road and Merrifield Employment Precinct as part of their development. Extending this first lane south and duplicating it as part of development would help to unlock the employment potential of this precinct and provide vehicular, public transport and cycling access for residents in the Mickleham Precinct to Craigieburn Town Centre and Craigieburn Train Station. Lockerbie Station is the most vital additional station in the Northern Growth Region and critical to providing train services into the Melbourne CBD for over 30,000 future residents. Delay in its delivery will place unacceptable pressure on Craigieburn Train Station. The station would unlock employment potential of the Donnybrook (Lockerbie) Town Centre Donnybrook Station will be required to service in the short to medium term until Lockerbie Train Station is constructed. It requires upgrade including significant additional parking. Mickleham Road is a critical part of the arterial road and freight network serving the Northern Growth Region. It is forecast to see significant growth in use in the coming years. Duplicating the road at the same time as providing new intersections would utilise resources more efficiently. Craigieburn Road is a critical part of the arterial road and principal public transport network serving the Northern Growth Region. It provides the Developers in the Mickleham Precinct Developers in the Lockerbie Precinct Developers in the Lockerbie Precinct Developers in the Mickleham Road North Precinct Developers in the Mickleham 35

40 Infrastructure Project Location Cost Justification WIK to be Provided by Duplication Precinct main point of access to Craigieburn Town Centre and Train Station and is forecast to see significant growth in use in the coming years. Duplicating the road at the same time as providing new intersections would utilise resources more efficiently. Donnybrook Road Duplication Gunns Gully Road Interchange Cameron Street Bridge Hume Freeway Interchange Construction of Merrifield Park Mickleham Precinct Mickleham & Lockerbie Precinct Mickleham Precinct Mickleham & Hume Highway Precinct Mickleham Precinct $25-30mil (estimate) $50-70 mil (estimate) $20-30 million (estimate) $30 40 million (estimate) Unknown Donnybrook Road is a critical part of the arterial road and freight network serving the Northern Growth Region. It is vital to unlocking the employment potential in the Mickleham Precinct and will see significant growth in use in the coming years. Duplicating the road at the same time as providing new intersections would utilise resources more efficiently. This interchange is needed to unlock development in the central and northern part of the Lockerbie precinct. It will also help unlock the employment potential of the Donnybrook Town Centre and potential employment area to the west of Hume Freeway. Cameron Street Bridge across the Hume Freeway is an important connection between two large residential and employment growth areas and potential important part of the principal public transport network. The interchange with the Hume Freeway is critical to unlocking and realising the potential of two large employment areas and minimising congestion on the Donnybrook Road ramps. Merrifield Park represents a unique opportunity to increase participation in sports and leisure in the Northern Growth Region. It would help to realise the economic potential of Mickleham (Merrifield) Town Centre. Road Precinct North Developers in the Mickleham Precinct Developers in the Mickleham & Lockerbie Precincts Developers in the Mickleham Precinct Developers in Mickleham & Hume Highway North Precincts Developers in the Mickleham Precinct 36

41 5.3 Funding of Local & Higher Order Infrastructure As with State Infrastructure, the funding of new and upgraded local and higher order infrastructure and services will be drawn from mainstream funding as well as bids to State and Federal Government. However, a significant proportion of the funding for new infrastructure will be drawn from development contributions to meet the demands generated from new development. Development Contribution Plans (DCPs) are already approved for many of the new development areas. Table 5.3 and 5.4 shows that for some of these plans and these development areas there is a fairly significant shortfall in funding, particularly for higher order infrastructure. Some of this shortfall can be met through Council rates and revenue but other funding sources will be required. Table 5.3 Shortfall in Infrastructure Funding in Development Contribution Plans for Local Infrastructure Development Cost of Development Shortfall in funding Contribution Plan Infrastructure Contribution Lockerbie $120,234,454 $120,234,454 $0 Merrifield West $88,573,625 $66,929,821 $21,643,804 Greenvale Central $40,505,411 $37,517,632 $2,987,779 Greenvale North R1 $15,427,021 $7,100,313 $8,326,708 Greenvale West R3 $13,874,725 $10,597,106 $3,277,619 Craigieburn R2 $52,199,015 $40,691,167 $11,507,848 Total $330,814,250 $283,070,492 $47,743,757 Table 5.4 Shortfall in Infrastructure Funding in Development Contribution Plans for Higher Order Infrastructure Development Cost of Development Shortfall in funding Contribution Plan Infrastructure Contribution Lockerbie $79,638,515 $16,400,000 $63,238,515 Merrifield West $111,975,508 $9,476,562 $102,498,946 Craigieburn R2 $45,899,455 $2,721,769 $43,177,686 Total $237,513,478 $28,598,331 $208,915,147 Values based on Jan 2015 figures. Tables subject to review and change. For the higher order infrastructure in Lockerbie, some development contributions will be collected from new developments covered by the Lockerbie DCP in the City of Whittlesea and Mitchell Shire. Additional funding from both Councils may also be directed to these facilities as there are a number of residents that will live within the catchment of these facilities and are likely to use them. 37

42 Land acquisition for the higher order facilities at Mickleham (Merrifield) Major Town Centre and Merrifield Regional Park is only partially funded by the Merrifield West DCP. Development contributions from new development areas in the catchment area of these facilities should be directed to this funding shortfall. These include the adjoining Beveridge West area in Mitchell Shire, Mickleham Major Town Centre and Lindum Vale in Hume. Even with these potential contributions, significant State and Federal funding will be required to address the significant shortfalls in funding in the new development areas. Should additional funding not be identified to meet these funding shortfalls, Hume City Council will need to consider the following measures: 1. Reviewing the approved DCPs to reduce the funding shortfall. 2. Reduction in the identified scope of works for infrastructure, particularly for underfunded infrastructure. 3. Delaying the delivery of infrastructure that is underfunded and not required to deliver essential services. 38

43 6. FURTHER WORK 6.1. Housing Strategy The Spatial Strategy identified a range of future housing challenges in the Hume Corridor, particularly a lack of diversity in house size to meet the needs of the growing number of small households. It identified areas with the best potential to deliver this more diverse housing. Further work is required to fully respond to these challenges. The aim of this further work is to: Prepare a housing strategy which informs future planning zone changes and other measures to increase housing diversity. The objectives for this further work are: 1. To fully quantify the likely demand and potential to deliver more diverse housing product within the Hume Corridor 2. To map the areas where changes to planning zones and controls would be suitable to facilitate this more diverse housing product whilst protecting existing street character 3. To prepare guidelines to inform the future design of smaller housing product and future car parking requirements. This work should be undertaken in the coming 5 years and should be used to inform future reviews of infrastructure needs Craigieburn Road Design Craigieburn Road is a major arterial road in the Hume Corridor that links new and existing residential areas to the Craigieburn Town Centre, Craigieburn Plaza, Craigieburn Train Station and the Hume Highway/Freeway. New development is and will continue to occur along its length in the 25 coming years. Detailed design work is required to ensure that the future upgrade of Craigieburn Road appropriately balances the need to address the current and future transport requirements for the road with the potential to support and facilitate the future new development along its length. Design guidance is also required for the new development to ensure that it does not adversely impact on the transport requirements and maximises the benefits of any investment in the road reserve, particularly in the public realm and landscaping. The aim of this further work is to: Prepare a detailed road design along the length of Craigieburn Road to ensure that the future upgrade of the road and new development appropriately accommodate the existing 39

44 and future transport requirements and maximise the potential for transit oriented development. The objectives for this further work are: 1. To map and identify the current, planned and potential future land use and development along the length of Craigieburn Road 2. To confirm the future transport role and road, bus and bicycle requirements of Craigieburn Road in the coming 5, 15 and 30 years in consultation with VicRoads and Public Transport Victoria 3. To identify the optimal location and design of future carriageways, medians, bus lanes, bike paths and landscaping, intersections and service roads 4. To prepare design guidelines for the interfacing development so that it realises the optimal transit orientated development outcome. This work should be undertaken in the coming 5 years to guide future investment in the road and adjoining land Mickleham Road Design Mickleham Road is a major arterial road in the Hume Corridor that will service major new residential development along its length and provide an important connection between the future Donnybrook Road employment precinct, Melbourne Airport and the Western Ring Road prior to the Outer Metropolitan Ring being constructed. Detailed design work is required to inform its future upgrade and relationship with future residential areas. The aim of this further work is to: Prepare a detailed road design for Mickleham Road to ensure that it addresses future transport requirements, retains a strong landscaped character and provides an appropriate amenity for future residential development. The objectives for this study are: 1. To confirm the future transport role and road, bus and bicycle requirements of Mickleham Road in the coming 5, 15 and 30 years in consultation with VicRoads and Public Transport Victoria 2. To identify the optimal location and design of future carriageways, medians, bus lanes, bike paths and landscaping, intersections and service roads This work should be undertaken in the coming 5 years to guide future planning for the future Craigieburn West area and detailed road design. 40

45 6.4. Campbellfield Structure Plan / Urban Development Framework The Spatial Strategy identifies the significant potential for change around the Campbellfield Activity Centre. A Structure Plan or Urban Design Framework should be prepared to facilitate and manage this change. The aim of this further work is to: Prepare a Structure Plan or Urban Design Framework to guide change around the Campbellfield Activity Centre that realises the opportunities for a bulky goods precinct, office/high tech business park that retains the option for a metropolitan and High Speed Rail Station. The objectives for this study are: 1. Guide the development of a bulky goods precinct along Hume Highway to Bolinda Road and an office/high tech business park along Camp Road to the west of the train line 2. Safeguard the potential for a metropolitan train station with grade separated train crossing of Camp Road, and the long term potential for a High Speed Rail Station 3. Retain the potential for residential and more office development should either station be developed 4. Enable links to the Merri Creek Regional Parklands. This work should be undertaken in the coming 5 years to guide future planning for the land around the centre Craigieburn Structure Plan / Urban Development Framework The Spatial Strategy identifies the significant potential for change around the Craigieburn Plaza and Craigieburn Train Station Activity Centre. A Structure Plan or Urban Design Framework should be prepared to facilitate and manage this change. The aim of this further work is to: Prepare a Structure Plan or Urban Design Framework to guide change around the Craigieburn Plaza and Craigieburn Train Station that realises the opportunities for a more intense and diverse range of housing, improvements to the movement network and increased local retail and service provision. The objectives for this study are: 1. Guide the redevelopment of Benston Street as a major pedestrian and cycle connection to the station from Craigieburn Road and Craigieburn Plaza 2. Enable the development of high quality townhouses and apartment housing along the parts of Craigieburn Road, Benston Street and Hothlyn Drive near the station 41

46 3. Enable the development of more health and community service uses with above ground floor apartments along Craigieburn Road. This work should be undertaken in the coming 5 years to guide future planning for the land around the centre. 42

47 7. MONITORING AND REVIEW This Infrastructure and Delivery Strategy sets out the indicative development and infrastructure timelines and further work required to enable sustainable growth of the Hume Corridor as set out in the Hume Corridor HIGAP Spatial Strategy. It will be continually monitored and updated to reflect changes in circumstance, particularly if the projected rate of development exceeds or significantly slows. Monitoring and review of the rate of development and delivery of infrastructure is particularly important to ensure that there is not an inappropriate lag between the commencement of development and the required infrastructure. As outlined in Section 2, delays to the delivery of Fundamental and Required infrastructure may require a revision to the Spatial Strategy and measures to slow or control further development. A Monitoring Report will be prepared every two years in accordance with the Monitoring Indicators in the Spatial Strategy and reproduced below. This Monitoring Report will report any minor changes to this Infrastructure and Delivery Strategy with a more comprehensive update undertaken every 5 years or sooner if required. 43

48 Table 7.1 Monitoring Indicators HIGAP AIM Monitoring Indicators Frequency Source Build on the economic strengths of the Hume Corridor whilst seeking to diversify the economy and increase the number, accessibility and range of business and employment opportunities. Enable a high level of choice and accessibility to popular and viable activity centres throughout the Hume Corridor containing a range of employment, shopping, cultural and leisure and health facilities The change in the number and diversity of jobs compared to the 2011 Census data. The amount of additional industrial and commercial land developed and available within the Hume Corridor 5 Years Census Data 2 years UDP The change in the scale of retail and office floorspace in activity centres 5 Years HCC against the targets and caps in the Spatial Strategy. The number of additional activity centres within the Hume Corridor. 5 Years HCC The number of additional leisure and health facilities located in the activity centres within the Hume Corridor. 5 Years HCC To manage travel demand and realise the economic, social and environmental benefits of increased transport choice The provision of new fundamental, required and desirable regional 2 Years HCC transport infrastructure compared to the requirements and timelines specified in the Infrastructure and Delivery Strategy. The change in mode share of trips within the Hume Corridor. 5 Years HCC To increase the diversity and choice of housing, particularly for smaller households and the growing number of older and younger people The change in the vehicle travel times between key destinations within the Hume Corridor. 5 years HCC The scale of new low, conventional, medium and high density housing 5 Years HCC within Hume Corridor. The change in the mix of housing in the Hume Corridor. 5 Years HCC The scale of housing land supply in the Hume Corridor 2 Years UDP 44

49 HIGAP AIM Monitoring Indicators Frequency Source Secure the delivery of state and regional scale health, education and sports infrastructure in the Hume Corridor Deliver and fund local community and leisure facilities to meet the full and changing needs of the community over time throughout the Hume Corridor Protect and manage the areas of significant natural heritage in ways that balance protection with opportunities for leisure and recreation, sensitive urban development and road connectivity where appropriate. Enable appropriately staged development that is coordinated with appropriately funded and timely infrastructure delivery The provision of new fundamental, required and desirable regional health, education and sports infrastructure and services compared to the requirements and timelines specified in the Infrastructure & Delivery Strategy. The provision of new fundamental, required and desirable community, leisure, cultural and educational infrastructure and services compared to the requirements and timelines specified in the Infrastructure & Delivery Strategy. Amount of land contained within conservation reserves in the Hume Corridor. Amount of land containing natural heritage values that is accessible to the public. Number of additional road connections within areas of natural heritage sensitivity. The provision of new fundamental, required and desirable infrastructure compared to the timelines specified in the Delivery & Infrastructure Strategy. The location of new development compared to the staging plans contained within the Infrastructure and Delivery Strategy. 2 Years HCC 2 Years HCC 2 Years HCC 2 Years HCC 2 Years HCC 2 Years HCC 2 years HCC 45

50 Appendix 1 Schedule of Council Local Infrastructure Precinct Infrastructure Type Description Anticipated Timing Broadmeadows Surrounds and Learning & Education Expansion of Broadmeadows Global Learning Centre TBC Leisure and Recreation Regional Soccer Facility at John Ilhan Reserve 0-5 years Leisure and Recreation Upgrade to Jack Roper Reserve 0-5 years Mickleham Road South Leisure and Recreation New sports grounds and facilities at Greenvale Recreation Reserve Roxburgh Park and Surrounds Leisure and Recreation Upgrade and expansion to Greenvale Recreation Centre 0-5 years Leisure and Recreation Community Facility New cricket and soccer facilities in Greenvale Lakes development Expansion of Bluebird Way community facility to include expansion of meeting spaces for adult learning, PAG, youth and arts/cultural activity Under construction 0-5 years 5-10 years Hume Highway South Leisure and Recreation New park at Bolinda Road 0-5 years Mickleham Road North Community Facility New multi purpose community facility west of Mickleham Road to include preschool, occasional child care, MCH, adult learning, PAG, large and small community meeting spaces, arts and cultural spaces 0-5 years Leisure and Recreation New sports reserve west of Mickleham Road 5-10 years Leisure and Recreation Leisure and Recreation Community Facility New sports reserve north of Craigieburn Road sports to be determined New sports reserve south of Mount Ridley Road sports to be determined New multi purpose community facility south of Craigieburn Road to include preschool, MCH, occasional care, visiting services, adult learning, PAG, community meeting space 15+ years 15+ years 15+ years 46

51 Precinct Infrastructure Type Description Anticipated Timing Community Facility Community Facility New multi purpose community facility north of Craigieburn Road to include preschool, MCH, occasional care, adult learning, consulting rooms, youth facilities, community meeting spaces Expansion of community hall south of Mount Ridley Road to include preschool, MCH, occasional care, community meeting space 15+ years years Craigieburn Leisure and Recreation New sports reserve in north part of R2 PSP area for years tennis Leisure and Recreation New sports reserve in central part of R2 PSP area for 5-10 years AFL/Cricket Leisure and Recreation New sports reserve in southern part of R2 PSP area for 0-5 years soccer Leisure and Recreation Upgrade to Craigieburn Gardens 0-5 years Leisure and Recreation New sports reserve in southern Highlands for 0-5 years AFL/Cricket Community facility Upgrade to early years community facility on 0-5 years Craigieburn Road Community Facility New multi purpose community facility in southern 0-5 years Highlands to include preschool, MCH, visiting services, adult learning, PAG, community meeting space Community Facility New multi purpose community facility in R2 PSP Area to years include preschool, MCH, community meeting space Hume Highway North Leisure and Recreation Upgrade to Laffan Reserve sports to be determined 5-10 years Mickleham Leisure and Recreation New sports reserve south of Donnybrook Road for AFL/Cricket Leisure and Recreation New sports reserve south of Donnybrook Road adjoining woodlands AFL/Cricket or Soccer 15+ years 5-10 years 47

52 Precinct Infrastructure Type Description Anticipated Timing Leisure and Recreation Community Facility Community Facility New sports reserve north of Donnybrook Road for AFL/Cricket and tennis New multi purpose community facility south of Donnybrook Road to include preschool, occasional child care, MCH, adult learning, PAG, large and small community meeting spaces, arts and cultural spaces New multi purpose community facility north of Donnybrook Road to include preschool, occasional child care, MCH, adult learning, PAG, large and small community meeting spaces, arts and cultural spaces Lockerbie Leisure and Recreation New sports reserve north of Donnybrook Road for Soccer and tennis Leisure and Recreation Community Facility Community Facility New sports reserve south of Gunns Gully Road for AFL/Cricket and tennis New multi purpose community facility north of Donnybrook Road to include preschool, playgroup and other flexible community meeting space New multi purpose community facility south of Gunns Gully Road to include preschool, MCH, playgroup, occasional child care, large and small community meeting space, classrooms for adult education/neighborhood house programs, arts/cultural spaces 15+ years 15+ years years 5-10 years 15+ years 5-10 years 15+ years Components of community facilities and identified sports are subject to change. Anticipated timing is indicative and should not be relied upon for investment decisions. Timings are based on assumptions about anticipated rates of development, community need and forward funding. They are subject to continual review and updates. 48

53 HUME CITY COUNCIL SUNBURY HIGAP Delivery & INFRASTRucture Strategy July

54 Preamble This Delivery and Infrastructure Strategy aims to provide a sense of what an appropriate order and timing to the delivery of new development and new infrastructure would be to guide the growth of Sunbury. It does not guarantee that development and infrastructure will occur as outlined and for this reason the Strategy will be updated frequently (at least every 5 years) with the costs, staging and funding of development and infrastructure updated accordingly. 1

55 Contents 1. Introduction New Infrastructure Development & Infrastructure Staging Infrastructure Funding Further Work Monitoring and Review

56 1. Introduction Sunbury is identified as one of the principal growth corridors in the Melbourne area. Its delivery is critical to achieving the housing objective of State Government to provide plentiful and cheap land for housing development. Sunbury s growth is also critical to achieving the long held aspirations of Hume City Council and the Sunbury community to make Sunbury more self contained and to attract new development and investment to support improved infrastructure provision. Hume City Council has developed a Spatial Strategy to guide the future development of Sunbury. The Spatial Strategy outlines the future vision for Sunbury and details where and when new development and change will occur and what infrastructure is required. This Delivery & Infrastructure Strategy outlines in more detail how this development, change and infrastructure will be delivered. In doing so, this document serves a number of purposes: A document outlining where, when and how new development and infrastructure will be enabled; how much it will cost, and who is likely to fund it including investment from Council, State Agencies and State government; A key piece of 'evidence' to demonstrate that, with the right action and investment, the sustainable growth of the area, as set out in the Spatial Strategy, can be achieved. A tool to guide, prioritise and co-ordinate the delivery of development in step with infrastructure and to facilitate sustainable growth and change; A 'bidding' document to a variety of State and Federal Government, seeking their commitment to contribute to funding; A document that can be used to support detailed precinct specific Development Contributions Plans or any potential future development tariff based approach to developer contributions and support negotiations with private sector developers where they are expected to contribute to projects; and A clear document identifying what further work is required, when and by whom to facilitate and enable development and change Status of this Document Hume City Council has met with, and will continue to meet, a range of service providers and private sector agencies to ascertain future plans and to help secure investment in the infrastructure priorities in the area. However, many of the actions and investment strategies are outside the control of Hume City Council and therefore it cannot guarantee that the responsible agencies will commit to the work and funding outlined in this document in their own forward planning and investment plans. This Strategy aims to provide a sense of what an appropriate order and timing to the delivery of new development and new infrastructure would be to guide the growth of Sunbury. It does not guarantee that development and infrastructure will occur as outlined and for this reason the Strategy will be updated frequently (at least every 5 years) with the costs, staging and funding of development and infrastructure updated accordingly. 3

57 This document is not intended to be a comprehensive list of all infrastructure and funding in Sunbury. In particular, it does not include investment in the maintenance and improvement of roads or upgrade to existing facilities Planning as the Delivery Process The planning process is an important means by which the Spatial Strategy and growth in Sunbury will be implemented and delivered with planning permits required before the majority of the new development can commence. For large and complex sites, a range of more detailed plans will need to be prepared prior to permits being approved for large sites in Sunbury with the large areas zoned Urban Growth Zone (UGZ) requiring the preparation of Precinct Structure Plans (PSPs) and Development Contribution Plans (DCPs). In other areas and for less complex development proposals, the Hume Planning Scheme outlines the policies and factors that need to be considered. The Spatial Strategy and particularly the strategies contained within it will be reflected in the Hume Planning Scheme as it is updated. Precinct Structure Plans (PSPs) Precinct Structure Plans (PSPs) will be prepared either by Council or the Growth Areas Authority (GAA) in cooperation with the landowners and developers as well as State Government and other key stakeholders. Council will ensure that the Spatial Strategy and particularly the elements that relate to the UGZ areas is reflected through the preparation of the PSPs as far as possible. Typically, community consultation will be undertaken on the PSP as part of their preparation or prior to them being submitted to the Planning Minister for approval in the form of a Planning Scheme Amendment. Map 1.1 below shows the proposed boundaries for future PSPs as defined by the GAA. The Sunbury West PSP area has been enlarged to incorporate land along Barrington Lane and land adjacent to the Calder which is currently outside of the UGB. For more information on the Planning Process please visit and for more information on the PSPs please visit Other Delivery Processes As outlined in the remainder of this document, there are a significant range of other processes beyond the planning process, particularly for the delivery and funding of new infrastructure, required to deliver the Spatial Strategy and sustainable new development in Sunbury. 4

58 Map 1.1 Proposed Precinct Structure Plan (PSP) Boundaries 5

59 2. New Infrastructure The work undertaken to underpin the Spatial Strategy makes it clear that there are major challenges to address in order to deliver the scale of development in Sunbury, not least investment in a wide range of infrastructure, services and facilities required to support the planned growth. Significant investment for road and public transport, health, education, community, leisure and open space infrastructure will need to be obtained from a range of sources of funding to appropriately support the growth of Sunbury. It is also important that this infrastructure is provided in step with development to ensure that new development does not put an unacceptable strain upon existing infrastructure. In particular, it is important that transport infrastructure is provided early to enable residents to access work opportunities and services outside of Sunbury. This section outlines what these infrastructure projects are and who is responsible for their delivery. It prioritises the infrastructure projects with the highest priority given to the infrastructure projects that are directly related to unlocking the potential growth of Sunbury or enabling it to function sustainably. Finally, it discusses how they will be funded and identifies a significant funding gap for State Government and a large infrastructure bill for Local Government Infrastructure Requirements, Responsibilities & Priorities State Government is responsible for the funding and delivery of the most critical, the largest and the most expensive infrastructure projects identified in the Spatial Strategy. These include three new train stations, major road upgrades, new schools and a higher education/tafe facility and a new hospital. Local Government is responsible for the funding and delivery of more local infrastructure, including local roads, new active sports reserves, community meeting spaces, and early years facilities such as maternal child health and pre schools. Mainstream State and Local Government funding will be the principal source of funding for much of this new infrastructure with developers also making a significant contribution through Growth Area Infrastructure Charge (GAIC) and local Development Contributions Plans (DCPs). In many cases, mainstream funding is only set for a short period (often less than 5 years). This is in contrast to the 30 year time horizon of the Spatial Strategy and therefore the delivery of both State and Local infrastructure is subject to changing budget commitments. That said, there are clearly differing priorities for infrastructure that should make the delivery of the most important and most significant infrastructure items less susceptible to changing commitments or reduced funding. 6

60 Hume City Council has identified a priority for each of the infrastructure projects identified in the Spatial Strategy in the Sunbury / Diggers Rest area based on the following three levels: Priority 1: Fundamental Infrastructure this is infrastructure that is fundamental to the Spatial Strategy such that it must happen to enable development to occur and failure to deliver would require the Spatial Strategy to be reviewed. Priority 2: Required Infrastructure this is infrastructure that is required and must happen if growth is to be achieved in a timely and sustainable manner. Failure to deliver could result in development being refused planning permit or the Spatial Strategy to be reviewed. Priority 3: Desirable Infrastructure this is infrastructure is desirable to deliver the overall vision in the Spatial Strategy such that it would enhance the overall quality of life in the area but failure to deliver is unlikely to prevent development occurring or result in the Spatial Strategy being reviewed. The remainder of this section outlines what new infrastructure is required starting with the large scale infrastructure covering transport, health, community, leisure and open space. In addition to these there is an extensive list of required smaller scale infrastructure that includes: primary schools, secondary schools, active sports, multipurpose community facilities which are discussed below. The Lead Agency refers to the primary agency responsible for progressing the planning and delivery of that specific piece of infrastructure. The Funding Agency refers to the primary agency responsible for funding that piece of infrastructure. In some cases other agencies will be involved in either progressing or funding the infrastructure. Note: All costs and timeframes subject to revision 2.2. Large Scale New Infrastructure Transport Infrastructure The most important and costly infrastructure for Sunbury is transport infrastructure. Without its delivery, new development will place a significant and unacceptable strain upon the existing road and public transport infrastructure and badly impact upon the liveability and sustainability of Sunbury. The Bulla Bypass The proposed Bulla Bypass is an arterial road that is critical to relieving pressure on the Sunbury Bulla Road and improving connectivity between Sunbury and the existing and future employment nodes and service centres in the Northern Growth Corridor. It is important in the short-term to provide capacity along Sunbury-Bulla Road for future development in Sunbury s East. 7

61 Priority: Fundamental Infrastructure Cost: Subject to Vic Roads investigations Required Timeframe: 0-5 years Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt undergoing feasibility testing Upgrade to Sunbury Bulla Road The Sunbury Bulla Road currently carries in excess of 20,000 vehicles a day which is significantly beyond its design capacity resulting in congestion and safety issues. Whilst part of the road is duplicated, other sections are not, notably at the narrow bridge crossing. Upgrade to this important arterial road, along with the Bulla Bypass, is critical to enabling safe and efficient access from Sunbury to Melbourne Airport and other employment and service centres. Priority: Fundamental Infrastructure Cost: $21 million (estimate) Required Timeframe: 0-5 years Lead Agency: State Govt (Vic Roads/ DOT) Funding Agency: State Govt Provision of High Frequency Bus Services along Sunbury Bulla Road To support more affordable and sustainable travel, there needs to be a high frequency bus service running along Sunbury Road connecting Sunbury residents to Melbourne Airport and the Hume Corridor, especially Broadmeadows. Priority: Fundamental Infrastructure Cost: Unknown Required Timeframe: 0-5 years Lead Agency: State Govt (DOT) Funding Agency: State Govt The Outer Metropolitan Ring (OMR) The proposed OMR is a major freeway and potential rail route that will connect the outer western port area of Melbourne, Geelong and Avalon Airport with the Hume Freeway. It has the potential to significantly enhance the accessibility of the Sunbury to these major transport hubs and could therefore make an important long term contribution to the marketability and viability of the Sunbury area as an employment area and node. It will also help improve accessibility to the future employment areas in the western and northern areas of Melbourne. Priority: Required Infrastructure Cost: Unknown Required Timeframe: 5-10 years Lead Agency: State Govt (Vic Roads) Funding Agency: State Govt Jacksons Hill Train Station The existing Sunbury Town Centre train station suffers from high demand, limited accessibility and limited commuter parking. The provision of additional train stations is critical to maximising the investment of State Government in the electrification of 8

62 the Sunbury line, to relieving the pressures on the Town Centre and encouraging sustainable travel patterns early in the life of new neighbourhoods. The potential Jacksons Hill train station is the most suitable option and should be delivered early to support transit orientated development in Sunbury South. Priority: Fundamental Infrastructure Cost: $38 million (estimate) Required Timeframe: 0-5 years Lead Agency: State Govt (DOT) Funding Agency: State Govt Electrification of Train Line to Northern Stations There is potential to extend the electrification of the Train Line to the future northern stations in the north east of Sunbury. This would enable a more frequent and sustainable service to be provided from the new development areas in north east Sunbury and the provision of two new northern train stations (see below). Priority: Required Infrastructure Cost: $200 million (estimate) Required Timeframe: 15 + years Lead Agency: State Govt (DOT) Funding Agency: State Govt Northern Train Stations Along with the potential Jacksons Hill train station, there are two potential locations for future train stations in the north east of Sunbury to encourage transit orientated in these new neighbourhood areas. Priority: Required Infrastructure Cost: $38 million each (estimate) Required Timeframe: 15 + years Lead Agency: State Govt (DOT) Funding Agency: State Govt Duplication of Plumpton Road & Provision of High Frequency Bus Services As the western growth corridor of Melbourne grows, connectivity between Sunbury and this corridor will become more important. The duplication of Plumpton Road will be necessary to support the potential future traffic whilst a high frequency bus service will be important to provide affordable and sustainable travel. Priority: Required Infrastructure Cost: Unknown Required Timeframe: 15 years + Lead Agency: State Govt (Vic Roads/DOT) Funding Agency: State Gov The Southern Link Providing an orbital road and public transport connection in Sunbury is important to connect neighbourhoods and communities without the need to travel through Sunbury Town Centre. The Southern Link will be particularly important in the short to medium term to open up access to the southern part of Sunbury and to connect new communities on the eastern side of Sunbury to the Calder Freeway whilst the Bulla Bypass and upgrade to Sunbury Road are being constructed. It will also provide connectivity to the future Jacksons Hill Train Station. 9

63 Priority: Fundamental Infrastructure Cost: $60 million (estimate) Required Timeframe: 0-5 years Lead Agency: State Govt (Vic Roads/ DOT) Funding Agency: State Govt The Northern Link Like the Southern Link, the Northern Link will be important to connect communities and provide improved access to Sunbury Town Centre and the Calder Freeway for the future communities in the north eastern parts of Sunbury and for communities north of Sunbury. Priority: Required Infrastructure Cost: $40 million (estimate) Required Timeframe: 15+ years Lead Agency: State Govt (Vic Roads/DOT) Funding Agency: State Govt Upgrade to Lancefield Road Lancefield Road is currently a very fast stretch of road carrying large volumes of traffic. As new neighbourhoods are developed along Lancefield Road it will need to be duplicated with new intersections added. This will need to occur in step with development and high frequency bus services operating along it as part of the orbital bus route around Sunbury. Priority: Required Infrastructure Cost: Estimated $40 million Required Timeframe: in stages in advance of development Lead Agency: State Govt (Vic Roads/DOT) Funding Agency: State Govt Completion of Elizabeth Drive Elizabeth Drive is part constructed and will form part of the orbital road and bus route around Sunbury when completed. Priority: Required Infrastructure Cost: Developer funded Required Timeframe: 0-10 years Lead Agency: Hume City Council Funding Agency: Developers Status: Committed subject to development contributions Provision of High Frequency Bus Services along the Sunbury Orbital Route A high frequency bus service along the proposed orbital route in Sunbury (running along Lancefield Road, the Southern Link, Elizabeth Drive and the Northern Link) will provide Sunbury residents with convenient public transport access to the Sunbury Town Centre and to other parts of Sunbury. Priority: Required Infrastructure Cost: Unknown Required Timeframe: in step with development Lead Agency: State Govt (DOT) Funding Agency: State Govt 10

64 Viaduct Way Places Victoria is required to provide a crossing of the rail line as part of the development of their Jacksons Hill estate. Council is currently working with Places Victoria and other stakeholders to determine the feasibility of providing the crossing at the viaduct and whether there are alternative solutions. Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: 0-5 years Lead Agency: HCC & Places Victoria Funding Agency: HCC & Places Victoria subject to design and approvals Walking & Cycling Trail to Melbourne CBD Walking and cycling link along Jacksons Creek and the Maribyrnong River to connect Sunbury with Organ Pipes, Brimbank Park and the Melbourne CBD. Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: 15+ years Lead Agency: Hume/Brimbank City Councils Funding Agency: To be determined Walking & Cycling Trail to Melbourne Airport Walking and cycling link along Sunbury Road linking Sunbury to the Melbourne Airport. To be developed as part of upgrades to Sunbury Road and the Bulla Bypass. Priority: Required Infrastructure Cost: To be determined Required Timeframe: 0-5 years Lead Agency: State Govt (DOT) Funding Agency: State Govt Health, Education and Leisure Facilities As Sunbury grows its capacity to support large scale health, education and leisure facilities will increase reducing the need for the Sunbury community to leave the township to access these facilities and services. Whilst State Government is still forming its view on the requirements for a hospital or equivalent and a university/tafe, Hume City Council is strongly of the view that both are desirable infrastructure. A number of the facilities listed below are typically provided when the population is much larger and therefore are likely to be provided beyond the next 15 years. University/TAFE Hume City Council is working with State Government to develop an educational blueprint for Sunbury (see Section 5). The former VU site at Jacksons Hill represents one of a number of possible locations for the provision of a university/tafe (or 11

65 equivalent). The other potential alternative locations identified in the Spatial Strategy include the Sunbury Town Centre and land adjoining the Northern Station. Priority: Desirable Infrastructure Cost: $52 million (estimate) Required Timeframe: 15+ years Lead Agency: State Govt Funding Agency: State & Commonwealth Hospital or Equivalent The Sunbury Day Hospital provides day medical and surgical procedures as well as dialysis treatment and specialty clinics. The current and projected population is unlikely to trigger the need for a tertiary hospital but Sunbury is well suited to service a larger regional population and needs the provision of both emergency and after hours services. The Spatial Strategy identifies the town centre as the preferred location for a future hospital (or equivalent) if one is required with land adjoining one of the Northern Stations as an alternative location. Priority: Desirable Infrastructure Cost: Unknown Required Timeframe: 15+ years Lead Agency: State Govt Funding Agency: State Govt Extension to Community Health Centre The existing Community Health Centre in Sunbury will also require upgrading and expanding to support future demand arising from the population growth. The future development requirements of the Community Health Centre will form part of future research. The Spatial Strategy identifies the potential to expand this facility. The current site has potential for future expansions (as a 2 nd level) and this could provide an additional 3,000sqm in the town centre. Alternatively, a range of visiting health services and programs could be delivered from new community hub facilities in the new activity centres. Further consultation is required with the Community Health Sector. Priority: Required Infrastructure Cost: $7.5 million (estimated) Required Timeframe: 15+ years Lead Agency: State Govt Funding Agency: State Govt Library and Learning Centre The Hume Global Learning Centre in Broadmeadows is a highly successful and popular facility that provides a range of learning and educational services for the community. Hume City Council has constructed a similar facility in Craigieburn and is committed to providing an expanded facility in Sunbury. Design work is anticipated to start in the short term and be completed in 2016 and the facility opened in Priority: Desirable Infrastructure Cost: $24 million Required Timeframe: 5-10 years Lead Agency: Hume City Council Funding Agency: Hume City Council 12

66 Upgrade to Aquatic Centre The existing Sunbury Aquatic and Leisure Centre provide adequate provision for the current population. Facilities are ageing and will need major redevelopment including expansion to respond to population growth and provide for changing leisure and wellbeing participation needs. Priority: Desirable Infrastructure Cost: $25 million (estimated) Required Timeframe: 5-15 years Lead Agency: Hume City Council Funding Agency: Hume City Council Regional Soccer Facility Sunbury has an existing regional scale AFL facility but requires a number of other regional scale facilities. The first to be planned and delivered is the regional soccer facility, potentially at Langama Park. Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: 0-10 years Lead Agency: Hume City Council Funding Agency: Hume City Council Additional Regional Sports Facility As the population of Sunbury grows it will generate sufficient demand to justify the provision of a dedicated regional space for other sports including athletics and hockey. The preferred location for a dedicated facility to support these sports is in the vicinity of one of the northern train stations and in good proximity to the proposed Major Activity Centre. Priority: Desirable Infrastructure Cost: $30 million (estimated) Required Timeframe: 15+ years Lead Agency: Hume City Council Funding Agency: Hume City Council/State Govt Sunbury Performing Arts Centre A Performing Arts Centre in Sunbury is desirable over the coming 30 years to meet demand for performance space in the township. Further work is required to determine the community needs and to advance the future planning and development of such a facility and its potential to meet needs of a large meeting space. Priority: Desirable Infrastructure Cost: $30 million (estimated) Required Timeframe: 15+ years Lead Agency: Hume City Council Funding Agency: Hume City Council/State Govt Open Space Infrastructure Sunbury has a fantastic and unique landscape with many impressive features, including hill tops and creeks with impressive escarpments. This landscape is critical to the rural feel and rural outlook that Sunbury enjoys and provides a number of open space 13

67 opportunities that will distinguish Sunbury from other parts of Melbourne and other growth areas and increase community enjoyment of the Sunbury s landscape. Jacksons Creek Regional Park Jackson s Creek is the most visible and accessible of the landscape features in Sunbury and some of the land adjoining the creek and along its escarpment already in public ownership. There is significant potential for more land to be acquired and for a Regional Park to be established with walking and cycling trails along both the creek and its escarpment. Concept planning is required to determine the approximate cost for provision of this Regional Park. Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: 5-15 years Lead Agency: State Govt & Hume City Council Funding Agency: To be determined Emu Creek Regional Park Emu Creek is of equal value to Jacksons Creek but less accessible. There is therefore significant potential for a similar Regional Park to be established along the creek and escarpment with walking and cycling trails. Concept planning is required to determine the approximate cost for provision of this Regional Park. Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: 5-15 years Lead Agency: State Govt & Hume City Council Funding Agency: To be determined Mount Holden Hilltop Park Sunbury s hilltops are well known and popular landscape features. Mount Holden is the largest and most impressive and plans have been approved to develop a hilltop park. Priority: Desirable Infrastructure Cost: n/a Required Timeframe: 0-10 years Lead Agency: Hume City Council Funding Agency: Hume City Council Redstone Hill Hilltop Park Redstone Hill is another hilltop that has the potential to become a hilltop park. Concept planning of this reserve will be required at the Precinct Structure Planning stage to determine design and cost of this reserve. Priority: Desirable Infrastructure Cost: To be determined Required Timeframe: 5-15 years Lead Agency: Hume City Council Funding Agency: Developer/Hume City Council 2.3. New Local Scale Infrastructure In addition to the above there is a lengthy list of required infrastructure that will be used principally by those who live in a particular neighbourhood (e.g. multi purpose 14

68 community centre and schools). These additional requirements are outlined in Table 2.1 below for each of the precincts outlined in the Spatial Strategy and shown in Map 2.1 below. Only the development within the precincts that require the local infrastructure will be required to contribute to this infrastructure. As with other infrastructure, the items listed in Table 2.1 are indicative only and subject to change and refinement over time, particularly as service provision requirements change and a more detailed understanding of specific needs is identified. Table 2.1: Other Required Local Infrastructure Precinct Sunbury West (5-10+ Years) Local Infrastructure Potential consolidation and expansion of existing facilities 1 x Multi Purpose Community Facility on Gap Road potentially comprising: 2 x Pre School Room 2 x MCH Consulting Room Space for 120 place Long Day Care Centre Community meeting space Neighbourhood House Children s Activity Space Family Resource Centre 1 x Primary School Sunbury South ( Years) 1 x 10.25ha of District Active Open space (sports to be determined) 1 x Multi Purpose Community Facility potentially comprising: 2 x Pre School Room 2 x MCH Consulting Room Space for 120 place Long Day Care Centre 100 person Community meeting space Neighbourhood House Children s Activity Space Family Resource Centre 1 x Primary School 1 x Secondary School Sunbury South East (15+ years) 1 x 10.25ha of District Active Open space (sports to be determined) Expansion of facilities in Goonawarra 1 x Multi Purpose Community Facility in Large NAC potentially comprising: 2 x Pre School Room 15

69 Precinct Local Infrastructure 2 x MCH Consulting Room Space for 120 place Long Day Care Centre 100 person Community meeting space Children s Activity Space Family Resource Centre 1 x Multi Purpose Community Facility off Lancefield Rd potentially comprising: 1 x Pre School Room 2 x MCH Consulting Room Children s Activity Space Space for 120 place Long day care centre Neighbourhood House 1x Multi Purpose Community Facility in South potentially comprising: 1 x Pre School & 1 x MCH Consulting Room Children s Activity Space 2 x Primary School 1 x Secondary School 1 x Potential Catholic/Private School Sunbury North East (15+ years) 3 x 10.25ha of District Active Open space (sports to be determined) 3 x Multi Purpose Community Facility potentially comprising: 3 x Pre School Room 3 x MCH Consulting Room Space for 120 place Long Day Care Centre 100 person Community meeting space Neighbourhood House Children s Activity Space Family Resource Centre 3 x Primary School 1 x Secondary School 1 x Catholic/Private School Sunbury North 2 x 10.25ha of District Active Open space (sports to be determined) 1x 5ha of Sub District Active Open space (sports to be determined) 1 x Indoor recreation facility Upgrade of existing community facilities (5-15 years) NB: The scale, number and composition of facilities listed in Table 2.1 may change to reflect changing community needs and service provision models. 16

70 Map 2.1 Sunbury s Precincts 17

71 3. Development & Infrastructure Staging Committing to large expenditure on infrastructure in growth areas is politically difficult to justify compared to investment in established areas where public demand is more apparent and articulated. However, there are significant economic, social and environmental benefits of delivering infrastructure in step with development, notably reduced construction costs, reduced travel and environmental damage, increased social cohesion and livability, and improved affordable living. There are therefore significant benefits in being proactive and transparent in articulating the staging of development in helping to: identify what infrastructure investments are required by various parties and when; ensure that the right level of development and growth to the most infrastructure ready areas; align various public and private funding and investment streams; and give the existing and future community an understanding of the implications upon them. This section outlines when certain areas/precincts in Sunbury should be developed and when certain infrastructure should be delivered to support that development Staging of Development and Infrastructure The supply of housing land in Sunbury has shrunk in recent years as developments have reached completion and new land has not been released. This has reduced the annual number of new lots released in Sunbury from around 380 in 2007 to around 290 in There are a number of developments that will continue to provide housing in Sunbury over the coming 5 years before the new growth areas begin releasing lots quickly, including the remaining lots in Jacksons Hill, Canterbury Hills and at Mount Holden as well as new developments off Vineyard Road and Racecourse Road. This is anticipated to deliver around 200 to 250 lots per annum. However, it is anticipated that it will take some time for the demand and development capacity in Sunbury to be sufficient to support large numbers of new housing. ID Consulting have predicted that lot completions will not exceed 500 lots per annum until 2021 and 750 lots per annum until The projected rate of lot release and the total number of dwellings in Sunbury is shown in Chart 3.1 below. This is for a number of reasons: it will take time for the marketing of the developers in Sunbury to have the level of effect required to generate the demand to support a large increase in lot yields other growth locations in Craigieburn and Melton are well established and will generate more demand in the short to medium term 18

72 there is a plentiful supply of land and choice in more established growth locations there are only a limited number of large developers operating in Sunbury Table 3.1 outlines for each area/precinct the anticipated start date and the projected rate of development. Note: Actual start date and rate of delivery may vary Chart 3.1 Forecast Residential Development for Sunbury Table 3.1 Start Date and Rate of Development Anticipated Date Start Anticipated Rate of Development p.a Land between Mitchells Lane and Vineyard Road (Millet Land) lots Land at Racecourse Road lots Land to West of Sunbury to 120 lots Land to South of Sunbury lots Land to East of Sunbury lots Land to North East of Sunbury lots Land Beyond the UGB - Sunbury South Subject to UGB Unknown change NB: Actual start date and rate of delivery may vary Land between Mitchells Lane and Vineyard Road (Millet Land) The land between Mitchells Lane and Vineyard Road is currently zoned for residential development and subject to the preparation of the Development Plan and as such it is anticipated that development could start in 2 years (2014) and develop 19

Co-ordinated and Orderly Growth A Suite of Infrastructure and Public Assets for the Future... 1

Co-ordinated and Orderly Growth A Suite of Infrastructure and Public Assets for the Future... 1 Co-ordinated and Orderly Growth... 1 A Suite of Infrastructure and Public Assets for the Future... 1 Funding Sources, Revenues and Prioritising Expenditure... 2 Stage 1 Short Term Growth Sunbury to 50,000...

More information

PLANNING THE SUNBURY GROWTH CORRIDOR

PLANNING THE SUNBURY GROWTH CORRIDOR SUNBURY GROWTH CORRIDOR NOVEMBER 2016 PLANNING THE SUNBURY GROWTH CORRIDOR Sunbury Planning Background The Victorian Planning Authority, in consultation with Hume City Council, is undertaking a number

More information

Review of Government Secondary School Requirements within the Sunbury South Precinct Structure Plan

Review of Government Secondary School Requirements within the Sunbury South Precinct Structure Plan Review of Government Secondary School Requirements within the Sunbury South Precinct Structure Plan Expert Witness Statement August 11 th, 2017 Prepared by Robert Panozzo Director, ASR Research Pty Ltd

More information

PSP 75 Lancefield Road. Northern Jacksons Creek Crossing Supplementary Information

PSP 75 Lancefield Road. Northern Jacksons Creek Crossing Supplementary Information PSP 75 Lancefield Road Northern Jacksons Creek Crossing Supplementary Information September 2017 The northern crossing of Jacksons Creek proposed within the Lancefield Road PSP is a key part of the ultimate

More information

South East Traffic Solution

South East Traffic Solution South East Traffic Solution A MAJORITY LIBERAL GOVERNMENT WILL: Complete the Hobart Airport Interchange project Fix the Tasman Highway near Tasmania Golf Club Replace the Midway Point Roundabout with additional

More information

Submission to Infrastructure Victoria s Draft 30-Year Infrastructure Strategy

Submission to Infrastructure Victoria s Draft 30-Year Infrastructure Strategy Submission to Infrastructure Victoria s Draft 30-Year Infrastructure Strategy 1. Introduction This submission is a response to Infrastructure Victoria s assessment of the need to construct a heavy rail

More information

Regional Town Centre and Employment Land Assessment

Regional Town Centre and Employment Land Assessment Regional Town Centre and Employment Land Assessment PSP 1067 Donnybrook PSP 1096 Woodstock PSP 25.2 English Street Prepared for Metropolitan Planning Authority by Essential Economics Pty Ltd J u n e 2

More information

Kilometres. Blacktown. Penrith. Parramatta. Liverpool Bankstown. Campbelltown

Kilometres. Blacktown. Penrith. Parramatta. Liverpool Bankstown. Campbelltown 0 5 10 15 20 Kilometres Penrith Blacktown Parramatta Liverpool Bankstown Campbelltown accessibility outcomes Legend Outcomes targeted in Western Sydney are: public transport that is accessible throughout

More information

Draft City Centre Transport Proposals

Draft City Centre Transport Proposals Draft City Centre Transport Proposals Introduction This draft position paper provides an overview of the current City Centre transport issues, including concepts of the possible future City Centre transport

More information

East Lancashire Highways and Transport Masterplan East Lancashire Rail Connectivity Study Conditional Output Statement (Appendix 'A' refers)

East Lancashire Highways and Transport Masterplan East Lancashire Rail Connectivity Study Conditional Output Statement (Appendix 'A' refers) Report to the Cabinet Member for Highways and Transport Report submitted by: Director of Corporate Commissioning Date: 1 June 2015 Part I Electoral Divisions affected: All East Lancashire Highways and

More information

WELLINGTON $422 MILLION $614 MILLION $83 MILLION 22% SPEND $1.9 BILLION

WELLINGTON $422 MILLION $614 MILLION $83 MILLION 22% SPEND $1.9 BILLION WELLINGTON WELLINGTON $1.9 BILLION FORECAST TOTAL WELLINGTON INVESTMENT The Wellington region s transport challenges are dominated by the region s concentration of population in the metropolitan cities,

More information

The Facts about Australia s outer suburbs

The Facts about Australia s outer suburbs Australia s population is booming and so are its outer suburbs. More than a third of our nation s population growth from 2011-2016 occurred in the outer suburbs, where National Growth Areas Alliance councils

More information

FUTURE TRANSPORT STRATEGY AND GREATER SYDNEY SERVICES AND INFRASTRUCTURE PLAN. Western Parkland City

FUTURE TRANSPORT STRATEGY AND GREATER SYDNEY SERVICES AND INFRASTRUCTURE PLAN. Western Parkland City FUTURE TRANSPORT STRATEGY AND GREATER SYDNEY SERVICES AND INFRASTRUCTURE PLAN Western Parkland City 2 Transport for NSW Future Transport Strategy and Greater Sydney Services and Infrastructure Plan Western

More information

Draft Greater Sydney Region Plan

Draft Greater Sydney Region Plan Powered by TCPDF (www.tcpdf.org) Draft Greater Sydney Region Plan Submission_id: 31119 Date of Lodgment: 12 Dec 2017 Origin of Submission: Online Organisation name: Serapark Pty Ltd Organisation type:

More information

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. Connecting People Building Opportunities 198 Brisbane Airport Corporation CHAPTER 10

More information

Part four. In this part you will find: The next steps to deliver the master plan

Part four. In this part you will find: The next steps to deliver the master plan Part four NEXT STEPS In this part you will find: The next steps to deliver the master plan 6. How COULD the Master Plan be delivered? There are a number of steps required to take the proposals in the master

More information

Strategic Transport Forum 21 st September 2018

Strategic Transport Forum 21 st September 2018 Strategic Transport Forum 21 st September 2018 Agenda Item 4: Heathrow Airport Expansion: Surface Access Strategy Update Recommendation: It is recommended that the Forum consider the update provided by

More information

Donnybrook Precinct Structure Plan Utilities Servicing and Infrastructure Assessment

Donnybrook Precinct Structure Plan Utilities Servicing and Infrastructure Assessment Donnybrook Precinct Structure Plan Utilities Servicing and Infrastructure Assessment Project Number: CG130061 Prepared for Metropolitan Planning Authority 4 September 2014 Donnybrook Precinct Structure

More information

Public Transport for Perth in 2031

Public Transport for Perth in 2031 South West Group Submission Public Transport for Perth in 2031 October 2011 South West Group Vision and Mission Local Governments in South Metropolitan Perth, through cooperation with industry, community

More information

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content

Gold Coast. Rapid Transit. Chapter twelve Social impact. Chapter content Gold Coast Rapid Transit Chapter twelve Social impact Chapter content Social impact assessment process...235 Existing community profile...237 Consultation...238 Social impacts and mitigation strategies...239

More information

Hume Amendment C207 Sunbury South PSP

Hume Amendment C207 Sunbury South PSP s Hume Amendment C207 Expert Evidence Traffic and Transport V171123 Prepared for HWL Ebsworth Lawyers 11 August 2017 Document Information Prepared for HWL Ebsworth Lawyers Project Name File Reference V171123_PAN001F01.docx

More information

AUCKLAND $1.2 BILLION $1.9 BILLION $149 MILLION 15% SPEND $5.7 BILLION

AUCKLAND $1.2 BILLION $1.9 BILLION $149 MILLION 15% SPEND $5.7 BILLION AUCKLAND AUCKLAND $5.7 BILLION FORECAST TOTAL AUCKLAND INVESTMENT The next 10 years are expected to underline Auckland s performance as the fastest growing major city in Australasia. The city is expected

More information

Beveridge North West PSP Retail and Needs Assessment

Beveridge North West PSP Retail and Needs Assessment Beveridge North West PSP 1059 Retail and Needs Assessment Prepared for Metropolitan Planning Authority by Essential Economics Pty Ltd A u g u s t 2 0 1 4 Authorship Report stage Author Date Review Date

More information

Northern Beaches Transport Action Plan

Northern Beaches Transport Action Plan Northern Beaches Transport Action Plan The NSW Government is taking action now to deliver transport improvements for the Northern Beaches, as well as planning for the future growth of the area. $633 million

More information

TOWN PLANNING SUBMISSION TO THE GREATER SYDNEY COMMISSION LANDS AT ARTARMON

TOWN PLANNING SUBMISSION TO THE GREATER SYDNEY COMMISSION LANDS AT ARTARMON TOWN PLANNING SUBMISSION TO THE GREATER SYDNEY COMMISSION LANDS AT ARTARMON March 2017 TABLE OF CONTENTS 1.0 INTRODUCTION 3 2.0 THE SUBJECT SITE 4 3.0 STRATEGIC PLANNING CONTEXT 6 4.0 SUMMARY AND CONCLUSIONS

More information

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub

Report to: Greater Cambridge Partnership Joint Assembly 18 January A10 Foxton level crossing bypass and travel hub Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018 Lead officer: Chris Tunstall GCP Director of Transport A10 Foxton level crossing bypass and travel hub 1. Purpose 1.1 The list of

More information

What is Rail Futures?

What is Rail Futures? What is Rail Futures? Rail Futures Institute is an independent nonpartisan group. It was formed to advocate cost-effective rail and intermodal solutions for public transport and freight problems based

More information

The Coalition s Policy to Build Melbourne s East West Link

The Coalition s Policy to Build Melbourne s East West Link 1 Our Plan Real Solutions for all Australians The direction, values and policy priorities of the next Coalition Government. The Coalition s Policy to Build Melbourne s East West Link August 2013 Our Plan

More information

Masterplan M One Cit an y P la y c,

Masterplan M One Cit an y P la y c, Masterplan Many Places One City, The Stockland story For 65 years, we ve been creating places that meet the needs of our customers and communities. And for years those customers and communities have been

More information

Wellington $312 $49 $456 OVERVIEW WELLINGTON REGIONAL SUMMARY

Wellington $312 $49 $456 OVERVIEW WELLINGTON REGIONAL SUMMARY National Land Transport Programme 2015 18 Wellington WELLINGTON REGIONAL SUMMARY OVERVIEW The Wellington region is made up of a number of cities, urban areas and supporting rural hinterland. The city is

More information

MELBOURNE METRO RAIL PROJECT EXPANDING MELBOURNE S UNDERGROUND RAIL NETWORK UPDATE FOR RESIDENTS OF THE DOMAIN PRECINCT APRIL 2016

MELBOURNE METRO RAIL PROJECT EXPANDING MELBOURNE S UNDERGROUND RAIL NETWORK UPDATE FOR RESIDENTS OF THE DOMAIN PRECINCT APRIL 2016 MELBOURNE METRO RAIL PROJECT EXPANDING MELBOURNE S UNDERGROUND RAIL NETWORK UPDATE FOR RESIDENTS OF THE DOMAIN PRECINCT APRIL 2016 MEETING THE CHALLENGE OF POPULATION GROWTH 24 14.4 12.6 MELBOURNE METRO

More information

Sunshine Coast Airport Master Plan September 2007

Sunshine Coast Airport Master Plan September 2007 Sunshine Coast Airport Master Plan September 2007 Contents CONTENTS... I ACKNOWLEDGEMENT... II DISCLAIMER... III 1 EXECUTIVE SUMMARY...IV 1 INTRODUCTION... 1 2 AVIATION DEMAND FORECAST... 5 3 AIRCRAFT

More information

PO Box 257 PO Box 257 PARRAMATTA NSW 2124 PARRAMATTA NSW 2124

PO Box 257 PO Box 257 PARRAMATTA NSW 2124 PARRAMATTA NSW 2124 31 March 2017 Sean O Toole Sheridan Dudley District Commissioner - West District Commissioner - South West Greater Sydney Commission Greater Sydney Commission PO Box 257 PO Box 257 PARRAMATTA NSW 2124

More information

ALL ABOARD LABOR S LONG TERM PASSENGER TRANSPORT STRATEGY

ALL ABOARD LABOR S LONG TERM PASSENGER TRANSPORT STRATEGY ALL ABOARD LABOR S LONG TERM PASSENGER TRANSPORT STRATEGY Revitalising Passenger Transport Increasing traffic congestion in our cities and a lack of transport services in our regional towns is frustrating

More information

The Coalition s Policy to Build the Swan Valley Bypass and Perth Gateway

The Coalition s Policy to Build the Swan Valley Bypass and Perth Gateway 1 Our Plan Real Solutions for all Australians The direction, values and policy priorities of the next Coalition Government. The Coalition s Policy to Build the Swan Valley Bypass and Perth Gateway August

More information

CHRISTCHURCH MOTORWAYS. Project Summary Statement February 2010

CHRISTCHURCH MOTORWAYS. Project Summary Statement February 2010 CHRISTCHURCH MOTORWAYS Project Summary Statement February 2010 Table of Contents 1. Purpose of Document 2. Strategic Context 3. Benefits 4. Project Scope and Economics 5. Implementation Plan 1 ROADS OF

More information

SUBURBPROFILE POPULATION TO DOUBLE OV E RVIE W CITY OF WY ND H AM FORECAST POPULATION WYNDHAM CITY COUNCIL

SUBURBPROFILE POPULATION TO DOUBLE OV E RVIE W CITY OF WY ND H AM FORECAST POPULATION WYNDHAM CITY COUNCIL TA R NI E T 1 SUBURBPROFILE The suburb is located within the boundaries of the City of Wyndham which is one of the fastest growing municipalities in Victoria and the third fastest in Australia. OV E RVIE

More information

Presentation to Planning Panel

Presentation to Planning Panel Presentation to Planning Panel Amendment C207 & C208 to the Hume Planning Scheme Lancefield Road PSP & Sunbury South PSP August 2017 1 Historical Planning Context Sunbury has long been identified as a

More information

The Coalition s Policy

The Coalition s Policy The Coalition s Policy Key Commitments Townsville is a city with immense potential. With a population of around 170,000, some 16,000 regional businesses, and regional product of over $11 billion, Townsville

More information

N4 Carrick-on-Shannon to Dromod Road Project. 2.1 Introduction

N4 Carrick-on-Shannon to Dromod Road Project. 2.1 Introduction Chapter 2 Need for the Scheme 2.1 Introduction The National Primary Route N4, Dublin to Sligo is a strategic corridor from Dublin to the northwest and border counties (See RCSR 101 in Volume 2). The National

More information

OBJECTION TO AMENDMENT TO PLANNING SCHEME AND GRANTING OF PLANNING PERMIT

OBJECTION TO AMENDMENT TO PLANNING SCHEME AND GRANTING OF PLANNING PERMIT PLANNING AND ENVIRONMENT ACT 1987 OBJECTION TO AMENDMENT TO PLANNING SCHEME AND GRANTING OF PLANNING PERMIT AMENDMENT C32 APPLICATION 0873/02 Public Transport Users Association Inc. 247-249 Flinders Lane

More information

5 Rail demand in Western Sydney

5 Rail demand in Western Sydney 5 Rail demand in Western Sydney About this chapter To better understand where new or enhanced rail services are needed, this chapter presents an overview of the existing and future demand on the rail network

More information

REGION OF WATERLOO INTERNATIONAL AIRPORT AIRPORT MASTER PLAN EXECUTIVE SUMMARY MARCH 2017

REGION OF WATERLOO INTERNATIONAL AIRPORT AIRPORT MASTER PLAN EXECUTIVE SUMMARY MARCH 2017 REGION OF WATERLOO INTERNATIONAL AIRPORT AIRPORT MASTER PLAN EXECUTIVE SUMMARY MARCH 2017 Contact: Chris Wood, Airport General Manager cwood@regionofwaterloo.ca (519) 648-2256 ext. 8502 Airport Master

More information

The Strategic Commercial and Procurement Manager

The Strategic Commercial and Procurement Manager Item 3 To: Procurement Sub Committee On: 8 June 2016 Report by: The Strategic Commercial and Procurement Manager Heading: Renfrewshire Council s Community Benefit Strategy 2016 1. Summary 1.1. The purpose

More information

21.07 ECONOMIC DEVELOPMENT AND EMPLOYMENT 19/03/2015 C323 Proposed C Key issues and influences. Economic Role and Function

21.07 ECONOMIC DEVELOPMENT AND EMPLOYMENT 19/03/2015 C323 Proposed C Key issues and influences. Economic Role and Function 21.07 ECONOMIC DEVELOPMENT AND EMPLOYMENT 19/03/2015 C323 Proposed C347 21.07-1 Key issues and influences 14/10/2010 C168 Economic Role and Function Geelong is the largest regional city in Victoria and

More information

PCAL Case Study Retail Areas: Rouse Hill Town Centre

PCAL Case Study Retail Areas: Rouse Hill Town Centre PCAL Case Study Retail Areas: Rouse Hill Town Centre Introduction Rouse Hill Town Centre is a new mixed use development on a greenfield site in Sydney s North West. It has been planned to be a major hub

More information

The Sunshine Coast is part of the global community and generates wealth through export, high-value industries and new investment.

The Sunshine Coast is part of the global community and generates wealth through export, high-value industries and new investment. 3.2 Strategic intent 3.2.1 Shaping growth an overview In 2031, the Sunshine Coast is renowned for its vibrant economy, ecological values, unique character and strong sense of community. It is Australia

More information

A THIRD RUNWAY AT HONG KONG INTERNATIONAL AIRPORT IS CRUCIAL TO HONG KONG S ECONOMIC FUTURE

A THIRD RUNWAY AT HONG KONG INTERNATIONAL AIRPORT IS CRUCIAL TO HONG KONG S ECONOMIC FUTURE A THIRD RUNWAY AT HONG KONG INTERNATIONAL AIRPORT IS CRUCIAL TO HONG KONG S ECONOMIC FUTURE Cathay Pacific firmly believes that a third runway at Hong Kong International Airport (HKIA) is a vital component

More information

5 PRECINCT INFRASTRUCTURE PLAN

5 PRECINCT INFRASTRUCTURE PLAN The following planning design guidelines should be met. Rainwater tanks are recommended for each dwelling other relevant building structures. Table 10: Category Drainage Drainage Floodplain Management

More information

A TRANSPORT SYSTEM CONNECTING PEOPLE TO PLACES

A TRANSPORT SYSTEM CONNECTING PEOPLE TO PLACES THE MAYOR'S VISION FOR TRANSPORT A TRANSPORT SYSTEM CONNECTING PEOPLE TO PLACES VISION We will build a transport system that works for everyone, connecting people to the places they want to go within the

More information

The Coalition s Policy

The Coalition s Policy The Coalition s Policy Key Commitments The Coalition s plan for a strong new economy will provide jobs and growth and secure the future for Australian families through smart investment in infrastructure.

More information

Moving Brisbane is the Newman Liberal team s blueprint for a modern and efficient transport system.

Moving Brisbane is the Newman Liberal team s blueprint for a modern and efficient transport system. Moving Brisbane Moving Brisbane is the Newman Liberal team s blueprint for a modern and efficient transport system. From roads and river crossings, to buses and bikes, Moving Brisbane addresses every component

More information

Creating a High Quality Business District

Creating a High Quality Business District Date Month Date Month Friday 7 November 2014 Nine Elms on the South Bank A Bilfinger Real Estate company Creating a High Quality Business District New London Architecture Introduction Nine Elms Vauxhall

More information

Response to the London Heathrow Airport Expansion Public Consultation

Response to the London Heathrow Airport Expansion Public Consultation Response to the London Heathrow Airport Expansion Public Consultation Summary This report sets out the response to the Heathrow Airport s consultation on airport expansion and airspace change. The consultation

More information

PERTH-ADELAIDE CORRIDOR STRATEGY

PERTH-ADELAIDE CORRIDOR STRATEGY INTRODUCTION The Royal Automobile Association of SA Inc (RAA), the State s principal advocate for motorists on a broad range of motoring-related issues, represents the views of more than 560,000 South

More information

Draft Greater Sydney Region Plan

Draft Greater Sydney Region Plan Draft Greater Sydney Region Plan Submission_id: 31392 Date of Lodgment: 14 Dec 2017 Origin of Submission: Online Organisation name: Greenfields Development Company No. 2 Pty Limited Organisation type:

More information

FEDERAL BUDGET PRIORITIES FOR THE SOUTH WEST METROPOLITAN REGION 2018 TO 2022

FEDERAL BUDGET PRIORITIES FOR THE SOUTH WEST METROPOLITAN REGION 2018 TO 2022 A Co-operative venture of the municipalities of: Cockburn, East Fremantle, Fremantle, Kwinana, Melville & Rockingham Tuesday, 5 December 2017 Enquiries: Mick McCarthy 9364 0631 Our Ref: Federal Budget

More information

Sunbury South Precinct Structure Plan - Community Infrastructure Assessment

Sunbury South Precinct Structure Plan - Community Infrastructure Assessment Sunbury South Precinct Structure Plan - Community Infrastructure Assessment Consultation Report K2 Planning 19 th March 2014 CONTENTS 1. Key Findings... 6 2. Recommendations... 12 3. Introduction... 13

More information

WELCOME TO ARENA MELBOURNE S NEW SPORTS HUB

WELCOME TO ARENA MELBOURNE S NEW SPORTS HUB ROXBURGH PARK WELCOME TO ARENA MELBOURNE S NEW SPORTS HUB Growing families looking to build a healthy, active life in Melbourne s north need look no further than Arena, Peet s vibrant new community in

More information

Committee for Melbourne Briefing Note Victorian State Budget Overview of Key Announcements

Committee for Melbourne Briefing Note Victorian State Budget Overview of Key Announcements Committee for Melbourne Briefing Note 2013-14 Victorian State Budget Overview of Key Announcements Strong and secure finances In 2013-14, the Coalition Government will deliver an estimated operating surplus

More information

TOTTENHAM TO ALBURY JUNE We re progressing our planning in Victoria for Inland Rail Australia s largest rail freight project

TOTTENHAM TO ALBURY JUNE We re progressing our planning in Victoria for Inland Rail Australia s largest rail freight project We re progressing our planning in Victoria for Inland Rail Australia s largest rail freight project TOTTENHAM TO ALBURY JUNE 2018 The need for Inland Rail About Inland Rail Inland Rail is a once-in-a-generation

More information

Growing Regional Victoria 2018 Victorian Election Priorities GROWING REGIONAL VICTORIA 2018 VICTORIAN ELECTION PRIORITIES

Growing Regional Victoria 2018 Victorian Election Priorities GROWING REGIONAL VICTORIA 2018 VICTORIAN ELECTION PRIORITIES GROWING REGIONAL VICTORIA 2018 VICTORIAN ELECTION PRIORITIES Message from the Chair, Cr Margaret O Rourke Regional Cities Victoria Growing Regional Victoria Regional Cities Victoria (RCV) is uniquely positioned

More information

NSW PRE-BUDGET STATEMENT FUTURE ECONOMY FUTURE JOBS

NSW PRE-BUDGET STATEMENT FUTURE ECONOMY FUTURE JOBS 2017-18 NSW PRE-BUDGET STATEMENT FUTURE ECONOMY FUTURE JOBS Executive Summary The 2017-18 NSW State Budget presents an opportunity for the NSW Government to future-proof the tourism and transport sectors.

More information

FIVE-YEAR IMPLEMENTATION PLAN

FIVE-YEAR IMPLEMENTATION PLAN FIVE-YEAR IMPLEMENTATION PLAN Accessibility If you would like to receive this publication in an alternative format, please telephone the Customer Service Centre on 136 186, email customer.service@delwp.vic.gov.au

More information

Gold Coast. Rapid Transit. Chapter content. Chapter four Route selection and staging

Gold Coast. Rapid Transit. Chapter content. Chapter four Route selection and staging Chapter four Route selection and staging Gold Coast Rapid Transit Chapter four Route selection and staging Chapter content Route selection...73 Section one: Helensvale to Griffith University...74 Section

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director / Senior Planning Policy Officer

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director / Senior Planning Policy Officer SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Leader and Cabinet 8 May 2008 AUTHOR/S: Executive Director / Senior Planning Policy Officer SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL S RESPONSE TO UTTLESFORD

More information

Smart Cities Plan IMPLEMENTATION. Townsville City Deal. April 2017

Smart Cities Plan IMPLEMENTATION. Townsville City Deal. April 2017 Smart Cities Plan IMPLEMENTATION Townsville City Deal April 2017 ACKNOWLEDGEMENTS The Commonwealth Government, Queensland Government and the Townsville City Council would like to thank the Townsville community

More information

Higher Order Community Infrastructure Needs Assessment

Higher Order Community Infrastructure Needs Assessment Higher Order Community Infrastructure Needs Assessment Final Report K2 Planning 7 th May 2014 Contents 1. KEY FINDINGS... 5 2. RECOMMENDATIONS... 12 3. INTRODUCTION... 13 4. PROJECT CONTEXT... 14 4.1 PRECINCT

More information

Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018

Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018 Report of the Strategic Director of Place to the meeting of Executive to be held on 11 September 2018 Subject: M Arrangements for the establishment of a West Yorkshire Urban Traffic Management Control

More information

As part of our transport vision, Leeds City Council, working with the West Yorkshire Combined Authority and Leeds Bradford Airport Company, is

As part of our transport vision, Leeds City Council, working with the West Yorkshire Combined Authority and Leeds Bradford Airport Company, is As part of our transport vision, Leeds City Council, working with the West Yorkshire Combined Authority and Leeds Bradford Airport Company, is considering options for improving surface access and connectivity

More information

UNLOCKING THE BRIGHTON MAINLINE

UNLOCKING THE BRIGHTON MAINLINE UNLOCKING THE BRIGHTON MAINLINE The highly successful Coast to Capital region, which runs from South London to Brighton and across the coast to Chichester, needs significant long-term rail investment to

More information

A Response to: Belfast On The Move Transport Masterplan for Belfast City Centre, Sustainable Transport Enabling Measures

A Response to: Belfast On The Move Transport Masterplan for Belfast City Centre, Sustainable Transport Enabling Measures West Belfast Partnership 218-226 Falls Road Belfast BT12 6AH T: 02890809202 A Response to: Belfast On The Move Transport Masterplan for Belfast City Centre, Sustainable Transport Enabling Measures Issued

More information

Blackburn Road Blackburn Level Crossing Removal. Frequently Asked Questions August 2014 GENERAL

Blackburn Road Blackburn Level Crossing Removal. Frequently Asked Questions August 2014 GENERAL Frequently Asked Questions August 2014 Blackburn Road Blackburn Level Crossing Removal GENERAL What is the project? The Victorian Government has committed to eliminating a number of the busiest level crossings

More information

LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN. Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS

LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN. Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS APPENDIX 15.1-3 LYNDHURST NEW URBAN DEVELOPMENT AREA STRUCTURE PLAN Purpose of the Structure Plan Lyndhurst New Urban Development Area Structure Plan OUTCOMES AND PERFORMANCE STANDARDS LSP-P1 The District

More information

4 Transport projects underway in Western Sydney

4 Transport projects underway in Western Sydney 4 Transport projects underway in Western Sydney About this chapter This chapter provides an overview of the Australian and NSW government s significant investments in road, bus and rail infrastructure

More information

EAST WEST RAIL EASTERN SECTION. prospectus for growth

EAST WEST RAIL EASTERN SECTION. prospectus for growth EAST WEST RAIL EASTERN SECTION prospectus for growth September 2018 executive summary The East West Rail Consortium, a partnership of local authorities, rail operators and Network Rail, continues to promote

More information

2017 POLICY DOCUMENT. M1 Action Plan. Putting Queenslanders First

2017 POLICY DOCUMENT. M1 Action Plan. Putting Queenslanders First 2017 POLICY DOCUMENT Putting 2 Contents Message from the Premier 3 Our Commitment 4 The Newman-Nicholls Legacy 5 The Palaszczuk 6 Government s Record Our Plans: Putting 8 Call: 07 3844 8101 Mail: PO Box

More information

Sport Capital Improvement Plan. Paul Borci Manager, Campus Planning Property & Campus Services

Sport Capital Improvement Plan. Paul Borci Manager, Campus Planning Property & Campus Services Sport Capital Improvement Plan Paul Borci Manager, Campus Planning Property & Campus Services What is SCIP? Property and Campus Services (PCS) in collaboration with Melbourne University Sport (MU Sport)

More information

The Committee for Gippsland Inc

The Committee for Gippsland Inc The www.committeeforgippsland.com.au ABN: 68225605779 P: 03 5623 3219 PO Box 380 E: info@gipps.com.au F: 03 5623 2905 Level 1, 62 Smith St Warragul VIC 3820 Mr Michel Masson Chief Executive Officer Infrastructure

More information

1.2 Corridor History and Current Characteristics

1.2 Corridor History and Current Characteristics SECTION 1 Description and Background of Study Area 1.1 Introduction This preliminary engineering report was prepared for the Alaska Department of Transportation and Public Facilities (ADOT&PF). It is part

More information

Draft Western District Plan

Draft Western District Plan Powered by TCPDF (www.tcpdf.org) Draft Western District Plan Submission_id: 31732 Date of Lodgment: 15 Dec 2017 Origin of Submission: Online Organisation name: APP Corporation Pty Ltd Organisation type:

More information

West Midlands Sustainable Urban

West Midlands Sustainable Urban West Midlands Sustainable Urban Transport Strategy and its Delivery: Movement for Growth Liveable City Conference Transport and Connectivity Seminar - 30/11/2017 Adam Harrison, Strategy & Intelligence

More information

The State of Transport in Macquarie Park

The State of Transport in Macquarie Park The State of Transport in Macquarie Park 31st August 2015 Overview Macquarie Park is a major economic centre that contributes over $9billion to Australia s economy each year. Providing access to and from

More information

Memorandum of Understanding with ACT Government

Memorandum of Understanding with ACT Government MEDIA RELEASE 8 April 2015 Memorandum of Understanding with ACT Government The ACT Government and Canberra Airport today entered into a new Memorandum of Understanding (MoU) on key areas of common interest

More information

Part 005 Implementation Strategy _

Part 005 Implementation Strategy _ Part 0 Implementation Strategy www. landlab.co.nz Queenstown Town Centre Masterplan Version 7 14 June 28 Section 0 Page 4 5.1 Implementation Plan The projects and initiatives contained within the Queenstown

More information

STRATEGIC INVESTMENT IN MANCHESTER AIRPORT

STRATEGIC INVESTMENT IN MANCHESTER AIRPORT Report To: EXECUTIVE CABINET Date: 7 February 2018 Cabinet Deputy/Reporting Officer: Subject: Report Summary: Cllr Bill Fairfoull Executive Member (Finance & Performance) Tom Wilkinson, Assistant Director

More information

HARBOUR EDGE STITCH. Uniting the Waterfront with the City Centre

HARBOUR EDGE STITCH. Uniting the Waterfront with the City Centre 78 AC_BEU_CCMP_2_TM1_4 _FD.indd 78 20/07/12 12:04 PM 01 HARBOUR EDGE STITCH Uniting the Waterfront with the City Centre 01 VISION OUR 2032 VISION IS: Quay Street as a high-quality Harbour Edge space that

More information

VICTORIA IN FUTURE Population 5.5 million Population 10 million. Deaths 2 million. Births 3.8 million. Natural increase 1.

VICTORIA IN FUTURE Population 5.5 million Population 10 million. Deaths 2 million. Births 3.8 million. Natural increase 1. VICTORIA IN FUTURE Births 3.8 million Deaths 2 million 2011 Population 5.5 million Natural increase 1.8 million Net migration 2.7 million 2051 Population 10 million Net overseas migration 2.7 million Net

More information

TRANSPORT CANBERRA. LIGHT RAIL NETWORK Delivering a modern transport system for a growing city

TRANSPORT CANBERRA. LIGHT RAIL NETWORK Delivering a modern transport system for a growing city TRANSPORT CANBERRA LIGHT RAIL NETWORK Delivering a modern transport system for a growing city LIGHT RAIL NETWORK A modern transport system for a growing city INTRODUCTION Minister Mick Gentleman The ACT

More information

Transport in Melbourne s Westen Suburbs: Alternatives to the Westgate Tunnel

Transport in Melbourne s Westen Suburbs: Alternatives to the Westgate Tunnel Transport in Melbourne s Westen Suburbs: Alternatives to the Westgate Tunnel The people of Melbourne s west have a huge problem with noise and poisonous exhaust from hundreds of trucks on their residential

More information

1. FORECAST VISITATION FOR GREAT OCEAN ROAD

1. FORECAST VISITATION FOR GREAT OCEAN ROAD 1. FORECAST VISITATION FOR GREAT OCEAN ROAD 1.1. INTRODUCTION This section provides a 20-year forecast of visitation to the Great Ocean Road Region, modelled from Australian Tourism Forecast Committee

More information

SUBMISSION ON PERTH TRANSPORT PLAN FOR 3.5 MILLION

SUBMISSION ON PERTH TRANSPORT PLAN FOR 3.5 MILLION SUBMISSION ON PERTH TRANSPORT PLAN FOR 3.5 MILLION PREPARED : THE SOUTH WEST GROUP OCTOBER 2016 EXECUTIVE SUMMARY The draft Perth Transport Plan (PTP) for 3.5 Million presents a strategic blueprint for

More information

The Government s Aviation Strategy Transport for the North (TfN) response

The Government s Aviation Strategy Transport for the North (TfN) response The Government s Aviation Strategy Transport for the North (TfN) response Transport for the North Background Good transport links are a crucial part of a strong economy supporting labour markets and delivering

More information

FNORTHWEST ARKANSAS WESTERN BELTWAY FEASIBILITY STUDY

FNORTHWEST ARKANSAS WESTERN BELTWAY FEASIBILITY STUDY FNORTHWEST ARKANSAS WESTERN BELTWAY FEASIBILITY STUDY EXECUTIVE SUMMARY The 2030 Northwest Arkansas Regional Transportation Plan developed by the Northwest Arkansas Regional Planning Commission (NWARPC)

More information

Tourism Development Framework for Scotland. Executive Summary- Development Framework to 2020 for the Visitor Economy (Refresh 2016)

Tourism Development Framework for Scotland. Executive Summary- Development Framework to 2020 for the Visitor Economy (Refresh 2016) Tourism Development Framework for Scotland Executive Summary- Development Framework to 2020 for the Visitor Economy (Refresh 2016) Introduction The Tourism Development Framework for Scotland refresh 2016:

More information

Reimagining Central Station Precinct

Reimagining Central Station Precinct Reimagining Central Station Precinct Submission by BusNSW 1. Introduction BusNSW members provide bus and coach transport services throughout NSW under various contractual and regulatory environments. This

More information

OUTLINE RESPONSE FROM WELWYN PLANNING & AMENITYGROUP (WPAG) TO CONSULTATION OVER PROPOSED EXPANSION OF LUTON AIRPORT

OUTLINE RESPONSE FROM WELWYN PLANNING & AMENITYGROUP (WPAG) TO CONSULTATION OVER PROPOSED EXPANSION OF LUTON AIRPORT OUTLINE RESPONSE FROM WELWYN PLANNING & AMENITYGROUP (WPAG) TO CONSULTATION OVER PROPOSED EPANSION OF LUTON AIRPORT This draft follows the format of the supplied response booklet. The contents have been

More information

Sunshine Coast Council Locked Bag 72 Sunshine Coast Mail Centre QLD Submitted via online portal. 2 June 2017.

Sunshine Coast Council Locked Bag 72 Sunshine Coast Mail Centre QLD Submitted via online portal. 2 June 2017. Sunshine Coast Council Locked Bag 72 Sunshine Coast Mail Centre QLD 4560 Submitted via online portal 2 June 2017 Dear Sir /Madam, RE: DRAFT ENVIRONMENTAL AND LIVEABILITY STRATEGY The Green Building Council

More information

Rail Delivery Group. Consultation on the future of the East Midlands rail franchise

Rail Delivery Group. Consultation on the future of the East Midlands rail franchise Rail Delivery Group Response to: Department for Transport Consultation on the future of the East Midlands rail franchise Date: 11 October 2017 Rail Delivery Group Limited Registered Office, 2nd Floor,

More information

A140 study and Major Road Network

A140 study and Major Road Network A140 study and Major Road Network Executive Summary The Government s new Transport Investment Strategy sets out a new long-term approach for government infrastructure spending. Funding will be targeted

More information