1 LHR Flight Performance Q2 Report 215

2 Contents Executive Summary 3 KPI 4 1ft requirements/infringements 5 Departure Noise Limits 7 Day Noise/Night Noise Infringements 8 Track Keeping 9 CDA 13 Joining Point 15 Go Arounds 19 Night noise/qc Usage 2 Arrival and Departure information 23 Engine Ground Running 24 Additional Information 26 Glossary of Terms 27 Page 2 Heathrow Airport Flight Performance Q2 Report 215

3 Executive summary This report covers January to June 215. January to June 215 has seen an overall East/West split of 74.1% Westerly and 25.9% Easterly. 1ft infringements are down on the same period for 214 from 243 to 119. Of these 119 infringements to the 1ft requirement, 23 were below 9ft. Fluctuations to the 1ft requirement are based mainly around temperature with hotter days leading to more infringements. Night Noise infringements are down from 18 for Q2 in 214 to 12 for of these infringements occurred in the shoulder, and 6 departed after 23:3 when restrictions are at their tightest. There have been 2 Day Noise infringements for Jan-Jun 15. Flight Performance continues to provide noise data to British Airways Aircraft Performance Team for their A38 departures. Track Keeping All Runways has seen a small increase on the same period for last year from 94.68% to 94.77%. CDA Averages remain up for Day and Core Night periods. Night and the 6 Hour are marginally down. The 24 Hour CDA Average is also down from 89.44% to 87.79%. Joining Point for Lates and Lows for both Night and Day show improvement. Late joiners are typically under tactical instructions from ATC, vectoring aircraft for operational reasons on the day. The Summer 215 Night Quota continues well. All charts and graphs are shown on the pages that follow are for reference purposes only. Heathrow Airport Flight Performance Q1 Report 215 Page 3

4 KPI chart to end of June 215 KPI Comparable 214 data 215 Comparison RAG January to June 214 January to June 215 1ft GREEN Noise Infringements Night GREEN Noise Infringements Day 2 Track Keeping Average 27R 98.9% 97.37% GREEN Track Keeping Average 27L 97.64% 96.93% GREEN Track Keeping Average 9R 87.9% 88.92% GREEN Track Keeping Average 9L**** 77.3% 8.9% GREEN Track Keeping All Runways 94.68% 94.77% GREEN CDA Day Average 86.98% 87.25% GREEN CDA Night Average 93.45% 93.44% GREEN CDA Core Night Average 95.21% 96.1% GREEN CDA 6: Hour Average 93.8% 92.74% GREEN 24 Hour CDA Average* 89.44% 87.79% GREEN Joining Point Day LATES Average 1.2%.57% GREEN Joining Point Day LOWS Average 1.61% 1.21% GREEN Joining Point Night LATES Average* 1.77% 1.55% GREEN Joining Point Night LOWS Average* 2.79% 2.66% GREEN Night Quota Pro Rata for Quota Count** 62.5% 56.7% Night Quota Pro Rata for Movements** 82.3% 84.3% * Service levels in NATS contract ** Excess usage pro-rata indicates increased risk of aircraft being refused permission to arrive or depart during 23:3-6:hrs local *** Significant increase in contacts or callers relative to enquiries can indicate a rise in demand on the FEU **** Low numbers of departures off 9L due to the Cranford agreement can result in a wide fluctuation in performance when compared to the other three runways. Caller = person Contact = number of times Enquiries = number of issues Each element of this report is preceded where applicable by the relevant Aeronautical Information Publication (AIP) reference and summary text detailing the purpose of the requirement. Data is then presented on current performance. It should be noted that Heathrow is 83ft above sea level and the ANOMS NTK system measures height relative to Heathrow elevation and not sea level. References in the AIP are usually above sea level (quoted as Heathrow QNH) and therefore need to be reduced by 83ft to be comparable with heights as measured by ANOMS. No account is taken of the variability of heights as measured by the radar which, depending on the distance from the radar head can be +/- 2ft from that indicated. This is obviously allowed for by NATS when managing operations. FOR THE PURPOSES OF THIS REPORT ANY REFERENCE TO HEIGHT SHOULD BE READ AS ABOVE AIRFIELD ELEVATION UNLESS OTHERWISE STATED. ALL DATA CONTAINED WITHIN THIS REPORT SHOULD BE CONSIDERED IN LIGHT OF THE PRECEDING TEXT AND COMMENT BOX THAT FOLLOWS. Page 4 Heathrow Airport Flight Performance Q2 Report 215

5 1ft requirement AIP REFERENCE AD 2-EGLL-1-14 After take-off the aircraft shall be operated in such a way that it is at a height of not less than 1 ft aal at 6.5km from start of roll as measured along the departure track of that aircraft. Period From 1/1/215 to 3/6/215 Height Infringement Reports 1ft Infringements by Month with Temperature No of Aircraft failing to reach 1ft at 6.5 km Jan 15 No of Aircraft failing to reach 1ft at 6.5km against Temp Feb 15 Mar 15 Apr 15 May 15 Jun Average Monthly Temperature Month <1ft Average Temp <9ft Heathrow Airport Flight Performance Q1 Report 215 Page 5

6 1ft infringements by airline London Heathrow Period From 1/1/215 to 3/6/215 Airline < 1 ft < 9 ft ALK SRILANKAN AIRLINES 5 2 BAW BRITISH AIRWAYS 42 3 ETD ETIHAD AIRWAYS 1 MAS MALAYSIA AIRLINES 4 MAU AIR MAURITIUS 9 4 PAL PHILIPPINE AIRLINES Inc 15 7 QAF UNKNOWN 1 QTR QATAR AIRWAYS 1 1 SAA SOUTH AFRICAN AIRWAYS 7 5 UAE EMIRATES 1 UAL UNITED AIRLINES 3 VIR VIRGIN ATLANTIC 7 1 Total of all Infringements: 119 Page 6 Heathrow Airport Flight Performance Q2 Report 215

7 Departure Noise Limits AIP REFERENCE AD 2-EGLL-1-15 Subject to sub-paragraphs (5) and (6) below, any aircraft shall, after take-off, be operated in such a way that it will not cause more than 94 dba Lmax by day (from 7 hours to 23 hours local time) as measured by any noise monitoring terminal at any of the sites referred to in subparagraph (2*) above. Subject to sub-paragraphs (5) and (6) below, any aircraft shall, after take-off, be operated in such a way that it will not cause more than 89 dba Lmax by night (from 23 hours to 7 hours local time) and, that it will not cause more than 87 dba Lmax during the night quota period (from 233 to 6 house local time) as measured by any noise monitoring terminal at any of the sites referred to in subparagraph (2*) above. (5) The limits specified in sub-paragraphs (3*) and (4*) above shall be adjusted in accordance with the following table in respect of any noise monitoring terminal at any of the sites referred to in the table in sub-paragraph (2*) to take into account of the location of that terminal and it s ground elevation relative to the aerodrome elevation. (6) For the purposes of determining an infringement of the limits specified in sub paragraphs (3*) and (4*) above, if the aircraft was requested to take-off with a tailwind, an amount of up to 2dB of the noise recorded at the noise monitor should be disregarded. The amount to be disregarded shall be:.4 db for a tailwind of up to 1 knot..8 db for a tailwind exceeding 1 knot but not exceeding 2 knots 1.2 db for a tailwind exceeding 2 knots but not exceeding 3 knots 1.6 db for a tailwind exceeding 3 knots but not exceeding 4 knots 2. db for a tailwind exceeding 4 knots For this purpose, tailwind is to be calculated from the wind data measured in the on-air field anemometers and wind vanes according to the formula: (windspeed x cosine (runway heading minus wind direction))x-1 * AIP see glossary on page 3 Heathrow Airport Flight Performance Q1 Report 215 Page 7

8 Day Noise Infringements Day Noise Infringements Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Month Night Noise Infringements Night Noise Infringements Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Month Page 8 Heathrow Airport Flight Performance Q2 Report 215

9 Departure Track Keeping AIP REFERENCE AD 2-EGLL-1-17 For monitoring purposes, a departure will be deemed to have complied with the Noise Preferential Routeing (NPR) if, in the portion of flight below the appropriate vectoring altitude (see note 9 right), it is properly recorded by the airport s noise and trackkeeping (NTK) system as having flown wholly within the Lateral Swathe (LS). The LS is defined from the centre-line of the relevant route coded in the NTK system, based upon a map accredited for this purpose by the Department for Transport, by the closer to the centre-line depicted on the map of (a) a pair of lines either side, each diverging at an angle of 1 from a point on the runway centre-line 2m from startof-roll; and (b) a pair of parallel lines representing a distance of 1.5 km either side of the route centreline. For avoidance of doubt, the depicted route and LS may include curved sections representing turns. Note 9. Aircraft which have attained an altitude of 4 ft ( Heathrow QNH ) may be directed by air traffic controllers onto a different heading and commanders complying with any such direction will not by reason of so complying be deemed to have departed from the NPR. Track deviations by runway Period From 1/1/215 to 3/6/215 Runway Total Departures 215 Total Deviations 215 % Compliance R 42,3 1, L 41,26 1, R 33,379 3, L Totals 116,868 6, Heathrow Airport Flight Performance Q1 Report 215 Page 9

10 % of On Track Departures by Flow and Route Current and Previous Year for 1/1/215 to 3/6/215 Easterly Month 9LBPK 9LBUZ 9LCPT 9LDET 9LDVR 9LMID1P 9LMID1P 9LMID1Q 9LSAM Jan Feb Mar Apr May-14 Jun Jan Feb Mar Apr May Jun Easterly Month 9RBPK 9RBUZ 9RCPT 9RDET 9RDVR 9RGAS 9RMID 9RMID1M 9RMID1N 9RSAM Jan Feb Mar Apr May Jun Jan Feb Mar Apr May Jun * The percentage of all 9L routes will vary greatly due to the small number of departures off that runway due to the Cranford agreement. Page 1 Heathrow Airport Flight Performance Q2 Report 215

11 % of On Track Departures by Flow and Route Current and Previous Year for 1/1/215 to 3/6/215 Westerly Month 27LBPK 27LCPT 27LDET 27LDOK1C 27LDOK1D 27LDVR 27LGOG 27LMID 27LSAM 27LWOB Jan Feb Mar Apr May Jun Jan Feb Mar Apr May Jun Westerly Month 27RBPK 27RCPT 27RDET 27RDOK1A 27RDOK1B 27RDVR 27RGOG 27RMID 27RSAM 27RWOB Jan Feb Mar Apr May Jun Jan Feb Mar Apr May Jun Heathrow Airport Flight Performance Q1 Report 215 Page 11

12 Track Keeping Key Performance Indicator Period from 1/1/215 to 3/6/ Jun-97 Jan-15 Feb-15 Mar-15 Percentage on track Apr-15 May-15 Jun-15 West% East%-9RCPT Total%-9RCPT East% Total % Page 12 Heathrow Airport Flight Performance Q2 Report 215

13 Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Continuous Descent Approach (CDA) AIP REFERENCE AD 2-EGLL-1-17 ( Note 7 ) For monitoring purposes, a descent will be deemed to have been continuous provided that no segment of level flight longer than 2.5 nautical miles (nm) occurs below 6ft QNH and level flight is interpreted as any segment of flight having a height change of not more than 5ft over a track distance of 2 nm or more, as recorded in the airport Noise and Trackkeeping system. * The CDA data is broken down into four time periods, Day (7hrs 23hrs), Night (23hrs 7hrs), Core night (233hrs 6hrs ) and the 6:hr (6hrs 7hrs) CDA Use during the day 7-23 CDA over 24 months. Three month Rolling Average line CDA% Heathrow Airport Flight Performance Q1 Report 215 Page 13

14 CDA Use in Night 23-7 CDA 24 Months Rolling Average CDA% Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 CDA Use in Core Night CDA 24 Months Rolling Average CDA% Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Page 14 Heathrow Airport Flight Performance Q2 Report 215

15 CDA Use during 6-7 CDA 24 Months Rolling Average CDA% Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Joining Point AIP REFERENCE AD 2-EGLL-1-16 ( Note 1 ) Between 6 and 233 hours (local time) where the aircraft is approaching runway 27 (L or R) and is using the ILS in IMC or VMC it shall not descend on the glidepath below an altitude of 25 ft (Heathrow QNH) before being established on the localizer, nor thereafter fly below the glidepath. An aircraft approaching without assistance from the ILS shall follow a descent path which will not result in its being at any time lower than the approach path that would be followed by an aircraft using the ILS glidepath, and shall follow a track to intercept the extended runway centre-line at or above 25 ft (Heathrow QNH). Between 233 and 6 hours (local time) where the aircraft is approaching runway 27 (L or R) and is using the ILS in IMC or VMC it shall not descend on the glidepath below an altitude of 3 ft (Heathrow QNH) before being established on the localizer at not less than 1nm from touchdown, nor thereafter fly below the glidepath. An aircraft approaching without assistance from the ILS shall follow a descent path which will not result in its being at any time lower than the approach path that would be followed by an aircraft using the ILS glidepath, and shall follow a track to intercept the extended runway centre-line at or above 3 ft (Heathrow QNH). Heathrow Airport Flight Performance Q1 Report 215 Page 15

16 Between 7 and 23 hours (local time) where the aircraft is approaching runway 9 (L or R) and is using the ILS in IMC or VMC it shall not descend on the glidepath below an altitude of 25 ft (Heathrow QNH) before being established on the localizer, nor thereafter fly below the glidepath. An aircraft approaching without assistance from the ILS shall follow a descent path which will not result in its being at any time lower than the approach path that would be followed by an aircraft using the ILS glidepath, and shall follow a track to intercept the extended runway centre-line at or above 25 ft (Heathrow QNH). Between 23 and 7 hours (local time) where the aircraft is approaching runway 27 (L or R) and is using the ILS in IMC or VMC it shall not descend on the glidepath below an altitude of 3 ft (Heathrow QNH) before being established on the localizer, at not less than 1nm from touchdown, nor thereafter fly below the glidepath. An aircraft approaching without assistance from the ILS shall follow a descent path which will not result in its being at any time lower than the approach path that would be followed by an aircraft using the ILS glidepath, and shall follow a track to intercept the extended runway centre-line at or above 3 ft (Heathrow QNH). The NTK system is unable to take into account multiple fluctuations in pressure within an hour. This can lead to an increase in the reported number of LOWS in the summer months. Page 16 Heathrow Airport Flight Performance Q2 Report 215

17 Rolling 2 years Joining Point Period from Jul 13 to Jun Percentage on Joining Point Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Month DayLates DayLows NightLates NightLows Day Joining Point Lates* Period from Jul 13 to Jun Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Percentages on Day Lates Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Month * Lates and Lows see glossary on page 3 Heathrow Airport Flight Performance Q1 Report 215 Page 17

18 Day Joining Point Lows* Period from Jul 13 to Jun Percentage on Day Lows Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Month Night Joining Point Lates* Period from Jul 13 to Jun Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Percentages on Night Lates Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Month * Lates and Lows see glossary on page 3 Page 18 Heathrow Airport Flight Performance Q2 Report 215

19 Night Joining Point Lows* Period from Jul 13 to Jun Percentage on Night Lows Jul 13 Aug 13 Sep 13 Oct 13 Nov 13 Dec 13 Jan 14 Feb 14 Mar 14 Apr 14 May 14 Jun 14 Jul 14 Aug 14 Sep 14 Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15 Apr 15 May 15 Jun 15 Month Go Around* Data Period from Jan 15 to Jun Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Month Go Arounds * Lates and Lows see glossary on page 3 * Go Around see glossary on page 3 Heathrow Airport Flight Performance Q1 Report 215 Page 19

20 Night Noise Winter 28 Summer 215 Season Movement Limit Quota Points Winter (including carry over* from previous season) Summer Winter (including carry over* from previous season) Summer Winter (including carry over* from previous season) Summer Winter (including carry over* from previous season) Summer Winter (including carry over* from previous season) Summer Winter (including carry over * from previous season) Summer Winter (including carry over * from previous season) Summer Limits are set by the DfT The regime applies to a night period (23 7 hours) during which the noisiest types of aircraft (QC8 and QC16) may not be scheduled to land or take off. In addition QC4 types may not be scheduled to land or takeoff in the night quota period (233 6).In addition, between hours (the night quota period) there are further restrictions the number of aircraft movements are restricted by a movements limit and additionally there is a limit of noise quota points. These limits are set for each summer and winter season. Neither of these limits may be exceeded, ie if the movements limit were to be reached, no further movements would be able to take place even if quota points were still available, and vice versa Summary of allocation usage Winter 26 Summer 215 Season Seasons Seasons QC points Movements Total Total Total Movements Exempt Not Not Not Quota movements carried carried QC points movements QC against counted counted counted Points limit over over allowed allowed value limit Delays DfT Emergency Limit Winter Summer Winter Summer Winter Summer Winter Summer Winter Summer Winter Summer Winter Summer Winter Summer Winter Summer * Carry over see glossary on page 3 Page 2 Heathrow Airport Flight Performance Q2 Report 215

21 Summer Usage of QC Points (including carry over) Period from Summer 97 to Summer QC Points S97 S98 S99 S S1 S2 S3 S4 S5 S6 S7 S8 S9 S1 S11 S12 S13 S14 S15 Season Quote Count Limits Actual Use Summer Usage of Movements (including carry over) Period from Summer 97 to Summer S97 S98 S99 S S1 S2 Movements S3 S4 S5 S6 S7 S8 S9 S1 S11 S12 S13 S14 S15 Season Movement Limits Actual Use Heathrow Airport Flight Performance Q1 Report 215 Page 21

22 Summer Season Weekly Pro Rata Usage Comparison (MV) 12 Percentage Pro rata Week number Target Summer 26 Summer 27 Summer 28 Summer 29 Summer 21 Summer 211 Summer 212 Summer 213 Summer 214 Summer 215 Summer Season Weekly Pro Rata Usage Comparison (QC) Percentage Pro rata Week number Target Summer 26 Summer 27 Summer 28 Summer 29 Summer 21 Summer 211 Summer 212 Summer 213 Summer 214 Summer 215 Page 22 Heathrow Airport Flight Performance Q2 Report 215

23 Arrival and Departure information Runway Alteration Adherence Arrivals 96.% 95.% 94.% 93.% 92.% 91.% 9.% 89.% 88.% 87.% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 215 TEAM after 7L Pure West Days only Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 215 Departures off landing Runway Jan-Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 215 Heathrow Airport Flight Performance Q1 Report 215 Page 23

24 Engine Ground Running The maximum total ground running exposure time over the night period from 23 to 7 hours must not exceed 15 minutes. Within the total 15 minutes, the maximum amount of ground running at high power must not exceed 6 minutes in any one night or exceed a rolling 3 day average of 2 minutes. Number of tests in each month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Ground Idle Runs 26 Ground Idle Runs 27 Ground Idle Runs 28 Ground Idle Runs 29 Ground Idle Runs 21 Ground Idle Runs 211 Ground Idle Runs 212 Ground Idle Runs 213 Ground Idle Runs 214 Ground Idle Runs 215 Page 24 Heathrow Airport Flight Performance Q2 Report 215

25 Total running time in the month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total Run Time 26 Total Run Time 27 Total Run Time 28 Total Run Time 29 Total Run Time 21 Total Run Time 211 Total Run Time 212 Total Run Time 213 Total Run Time 214 Total Run Time 215 Average number of tests per night Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Heathrow Airport Flight Performance Q1 Report 215 Page 25

26 Additional information Information on noise is also available on the BAA Heathrow website. This part of the website was updated in May 27. It includes a flight tracking system called WebTrak which enables local residents to log on and view flight tracks for aircraft arriving at and departing from Heathrow. As well as being able to track flights, WebTrak also gives details of the aircraft s height and position. Noise complaints and enquiries may now be made from the website. These facilities have been introduced to complement the long-standing facilities so complaints/enquiries may still be made by telephone or (see right). Updated statistical information on complaints and enquiries is now included in BAA Heathrow s Corporate Responsibility Report which is available in full on our website ( A summary is available from Heathrow Public Affairs, telephone Making noise complaints or enquiries On the Website By telephone Public Affairs Noise Complaints Freephone By noise_complaints@baa.com Useful websites for information on government policies in relation to Heathrow aircraft movements, ie night flights; changes to night-time use of Heathrow s runways, etc. Information on Noise Insulation and Noise and Blight Schemes is available in the BAA Heathrow Corporate Responsibility Report (see above). Page 26 Heathrow Airport Flight Performance Q2 Report 215

27 Glossary of Terms AIP ANOMS Carry over CDA dba FEU FLOPC Go Around IMC ILS KPI Lates and Lows LHR LS nm NATS NPR NTK QC QNH TEAM VMC Aeronautical Information Publication Noise, track keeping and complaints system Night restrictions are set on a seasonal basis. Up to 1% of a season's unused quota can be carried forward (known as "carry over") to the next season and up to 1% of a following season's quota can be anticipated Continuous Descent Approach A-weighted decibels Flight Evaluation Unit Flight Operations Performance Committee A go around is an aborted landing of an aircraft which is on approach to the runway Instrument Meteorological Conditions Instrument Landing System Key performance indicators During the daytime the aircraft are required to be "established" on the ILS at 7.5nm from touchdown. This equates to approximately 25ft aal. At night the distance is extended to 1nm which equates to approximately 3ft aal. London Heathrow Lateral swathes Nautical Miles National Air Traffic Services Noise Preferential Routes Noise and Track Keeping monitoring system Quota Count The barometric pressure at sea level (QFE is the barometric pressure at the aerodrome) Tactically Enhanced Arrivals Mode. In order to help alleviate delay in the stacks, ATC may change from the published alternation schedule. In order to maintain minimum separation distances between inbound aircraft, maintain usual high safety standards and keep air traffic flowing, ATC may use both runways for arrivals for a short period. Visual Meteorological Conditions Heathrow Airport Flight Performance Q1 Report 215 Page 27

28 Produced by Heathrow Flight Performance team, Second Floor Meridian, The Compass Centre, Nelson Road, London Heathrow Airport, Hounslow TW6 2GW. Further information If you would like further information, please contact the Flight Performance team: By telephone: By noise_complaints@baa.com By post: Flight Performance team Second Floor Meridian The Compass Centre Nelson Road London Heathrow Airport Hounslow TW6 2GW Website: Make an enquiry on our website: Please note that the freephone telephone number is an answerphone. Please leave your name, contact details and brief details of your enquiry. A member of the FEU will contact you as soon as possible. Page 28 Heathrow Airport Flight Performance Q2 Report 215

Executive summary. This report covers January to March 2014.

Executive summary. This report covers January to March 2014. LHR Flight Performance Q1 Report 214 Contents Executive Summary 3 KPI 4 1ft requirements/infringements 5 Departure Noise Limits 7 Day Noise/Night Noise Infringements 8 Track Keeping 9 CDA 13 Joining Point

More information

Executive summary. This report covers January to December 2014.

Executive summary. This report covers January to December 2014. LHR Flight Performance Q4 Report 214 Contents Executive Summary 3 KPI 4 1ft requirements/infringements 5 Departure Noise Limits 7 Day Noise/Night Noise Infringements 8 Track Keeping 9 CDA 13 Joining Point

More information

Executive summary. This report covers January to September 2014.

Executive summary. This report covers January to September 2014. LHR Flight Performance Q3 Report 214 Contents Executive Summary 3 KPI 4 1ft requirements/infringements 5 Departure Noise Limits 7 Day Noise/Night Noise Infringements 8 Track Keeping 9 CDA 13 Joining Point

More information

Executive summary. This report covers January to December 2013.

Executive summary. This report covers January to December 2013. LHR Flight Performance Q4 Report 213 Contents Executive Summary 3 KPI 4 1ft requirements/infringements 5 Departure Noise Limits 7 Day Noise/Night Noise Infringements 8 Track Keeping 9 CDA 13 Joining Point

More information

Executive summary. This report covers January to December 2017.

Executive summary. This report covers January to December 2017. LHR Airspace & Noise Performance Q4 Report 217 Contents Executive Summary 3 KPI 4 1ft requirements/infringements 5 Departure Noise Limits 7 Day Noise/Night Noise Infringements 8 Track Keeping 9 CDA 14

More information

Executive summary. This report covers January to September 2017.

Executive summary. This report covers January to September 2017. LHR Airspace & Noise Performance Q3 Report 217 Contents Executive Summary 3 KPI 4 1ft requirements/infringements 5 Departure Noise Limits 7 Day Noise/Night Noise Infringements 8 Track Keeping 9 CDA 14

More information

Gatwick Airport Flight Performance Report. Q2 Data 2014

Gatwick Airport Flight Performance Report. Q2 Data 2014 Gatwick Airport Flight Performance Report Q2 Data 2014 Introduction ABOUT THIS REPORT This report is produced by the Gatwick Flight Performance Team (FPT). This team is responsible for recording, investigating

More information

Flight Performance Annual Report 2016

Flight Performance Annual Report 2016 Flight Performance Annual Report 2016 Contents Introduction 3 Role of Flight Performance 3 IT Systems 4 Flight Analysis Data 6 Noise Action Plan 25 Air Quality Action Plan 28 Airspace Trials 29 Flight

More information

Gatwick Airport Flight Performance Report

Gatwick Airport Flight Performance Report Gatwick Airport Flight Performance Report This report covers the period (1st January 31st March 2016) Gatwick Airport Flight Performance Team Report covering the period January to March 2016 0 Contents

More information

Gatwick Airport Flight Performance Report

Gatwick Airport Flight Performance Report Gatwick Airport Flight Performance Report This report covers the period (1st April 30th June 2017) Gatwick Airport Flight Performance Team Report covering the period April to June 2017 0 Contents Introduction...

More information

2 Introduction. Security, safety and responsibly managing our environmental impact are always our top priorities.

2 Introduction. Security, safety and responsibly managing our environmental impact are always our top priorities. 2 Introduction Contents: Section A Air Traffic Movement data 3 Section B Night flights 5 Section C Arrivals and departures 9 Section D Aircraft noise 16 Section E Enquiries 18 Glossary of terms 20 Gatwick

More information

Flight Evaluation Report 2006/07

Flight Evaluation Report 2006/07 Flight Evaluation Report 2006/07 2 Section A Contents: Section A Movement data 2 Section B Night flights 5 Section C Arrivals and departures 7 Section D Aircraft noise 13 Section E Enquiries 15 Flight

More information

2 Introduction. Security, safety and responsibly managing our environmental impact are always our top priorities.

2 Introduction. Security, safety and responsibly managing our environmental impact are always our top priorities. F L I G H T P E R F O R M A N C E T E A M R E P O R T 2 0 1 1 2 Introduction Contents: Section A Air Traffic Movement data 3 Section B Night flights 5 Section C Arrivals and departures 9 Section D Aircraft

More information

HEATHROW AIRPORT Operations Handbook

HEATHROW AIRPORT Operations Handbook HEATHROW AIRPORT Operations Handbook Contents Contents Page 1. KEY ROLES AND RESPONSIBILITIES... 1 1.1 HEATHROW: THE AIRPORT OPERATOR... 1 1.2 AIRLINES... 1 1.3 NATS AIR NAVIGATION SERVICE PROVIDER...

More information

Noise Abatement Summary Airline performance against AIP Noise Abatement Criteria

Noise Abatement Summary Airline performance against AIP Noise Abatement Criteria Noise Abatement Summary 2012 Airline performance against AIP Noise Abatement Criteria Introduction Under Section 78(1) of the Civil Aviation Act 1982, London Stansted Airport is a noise designated airport

More information

Arriving and departing aircraft at Edinburgh Airport

Arriving and departing aircraft at Edinburgh Airport Arriving and departing aircraft at Edinburgh Airport Contents Introduction... 3 Arriving aircraft... 3 The Instrument Landing System (ILS)... 6 Visual Approach... 6 Non Directional Beacon Approach... 6

More information

Noise Abatement Summary Airline performance against AIP Noise Abatement Criteria

Noise Abatement Summary Airline performance against AIP Noise Abatement Criteria Noise Abatement Summary 2015-16 Airline performance against AIP Noise Abatement Criteria Introduction Under Section 78(1) of the Civil Aviation Act 1982, London Stansted Airport is a noise designated airport

More information

NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT JULY - SEPTEMBER 2011

NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT JULY - SEPTEMBER 2011 NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT JULY - SEPTEMBER 211 Date Version Comments Page 2 Foreword Airservices Australia has established a Noise and Flight Path Monitoring System

More information

NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT OCTOBER - DECEMBER 2013

NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT OCTOBER - DECEMBER 2013 NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT OCTOBER - DECEMBER 213 Date Version Comments Page 2 Foreword Airservices Australia has established a Noise and Flight Path Monitoring System

More information

NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT JULY - SEPTEMBER 2011

NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT JULY - SEPTEMBER 2011 NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT JULY - SEPTEMBER 211 Date Version Comments Page 2 Foreword Airservices Australia has established a Noise and Flight Path Monitoring System

More information

NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT JULY - SEPTEMBER 2013

NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT JULY - SEPTEMBER 2013 NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT JULY - SEPTEMBER 213 Date Version Comments Page 2 Foreword Airservices Australia has established a Noise and Flight Path Monitoring System

More information

NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT OCTOBER - DECEMBER 2012

NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT OCTOBER - DECEMBER 2012 NOISE AND FLIGHT PATH MONITORING SYSTEM MELBOURNE QUARTERLY REPORT OCTOBER - DECEMBER 212 Date Version Comments Page 2 Foreword Airservices Australia has established a Noise and Flight Path Monitoring

More information

USE OF RADAR IN THE APPROACH CONTROL SERVICE

USE OF RADAR IN THE APPROACH CONTROL SERVICE USE OF RADAR IN THE APPROACH CONTROL SERVICE 1. Introduction The indications presented on the ATS surveillance system named radar may be used to perform the aerodrome, approach and en-route control service:

More information

Gatwick Airport Flight Evaluation Unit

Gatwick Airport Flight Evaluation Unit Gatwick Airport Flight Evaluation Unit Quarterly report for the period July to September About Gatwick Airport Gatwick Airport opened in 958 with just over 86, passengers passing through in our first year

More information

AIRSERVICES AUSTRALI A

AIRSERVICES AUSTRALI A AIRSERVICES AUSTRALI A NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT JANUARY - MARCH 211 Page 2 Foreword Airservices Australia has established a Noise and Flight Path Monitoring System

More information

AIRSERVICES AUSTRALI A

AIRSERVICES AUSTRALI A AIRSERVICES AUSTRALI A NOISE AND FLIGHT PATH MONITORING SYSTEM BRISBANE QUARTERLY REPORT APRIL - JUNE 211 Date Version Comments Page 2 Foreword Airservices Australia has established a Noise and Flight

More information

Heathrow Community Noise and Track-keeping Report: Burhill

Heathrow Community Noise and Track-keeping Report: Burhill Heathrow Community Noise and Track-keeping Report: Burhill This document reports on an 1-day period of continuous noise monitoring from 14 June 211 to 21 September 211 using a Larson Davies LD 87 sound

More information

Technical Report. Aircraft Overflight and Noise Analysis. Brisbane, California. December Prepared by:

Technical Report. Aircraft Overflight and Noise Analysis. Brisbane, California. December Prepared by: Aircraft Noise Abatement Office Technical Report Aircraft Overflight and Noise Analysis Brisbane, California Prepared by: P.O. Box 8097 San Francisco, California 94128 (650) 821-5100 Introduction In response

More information

Quarterly Monitoring Report. Qtr

Quarterly Monitoring Report. Qtr Quarterly Monitoring Report Qtr 1 2018 Page 1 1 st Quarter 2018 INTRODUCTION The purpose of this report is to advise the community of statistics concerning aircraft operations at London Luton Airport (LLA)

More information

APA NOISE REPORT. August 2018

APA NOISE REPORT. August 2018 August 2018 [Grab your reader s attention with a great quote from the document or use this space to emphasize a key point. To place this text box anywhere on the page, just drag it.] APA NOISE REPORT 1

More information

PRELIMINARY WEB DOCUMENT

PRELIMINARY WEB DOCUMENT APA NOISE REPORT May 2018 [Grab your reader s attention with a great quote from the document or use this space to emphasize a key point. To place this text box anywhere on the page, just drag it.] 1 TABLE

More information

APA NOISE REPORT. January 2018

APA NOISE REPORT. January 2018 January 2018 [Grab your reader s attention with a great quote from the document or use this space to emphasize a key point. To place this text box anywhere on the page, just drag it.] APA NOISE REPORT

More information

Heathrow Airport. Subject Matter: Investigation into breaches of the Noise Preferential Routes associated with Heathrow Standard Instrument Departures

Heathrow Airport. Subject Matter: Investigation into breaches of the Noise Preferential Routes associated with Heathrow Standard Instrument Departures Heathrow Airport An analysis conducted by NATS NSL on behalf of Heathrow Airport Limited (HAL) Subject Matter: Investigation into breaches of the Noise Preferential Routes associated with Heathrow Standard

More information

APA NOISE REPORT. August 2017

APA NOISE REPORT. August 2017 August 2017 [Grab your reader s attention with a great quote from the document or use this space to emphasize a key point. To place this text box anywhere on the page, just drag it.] APA NOISE REPORT 1

More information

January 2018 Air Traffic Activity Summary

January 2018 Air Traffic Activity Summary January 2018 Air Traffic Activity Summary Jan-2018 Jan-2017 CY-2018 CY-2017 Passengers 528,947 505,421 4.7% 528,947 505,421 4.7% Passengers 537,332 515,787 4.2% 537,332 515,787 4.2% Passengers 1,066,279

More information

AIRCRAFT NOISE INFORMATION PACK: CANNING VALE

AIRCRAFT NOISE INFORMATION PACK: CANNING VALE AIRCRAFT NOISE INFORMATION PACK: Table of Contents CANNING VALE 1. Aircraft movements affecting Canning Vale... 2 2. Effects of wind on runway selection... 2 3. Seasonal winds... 2 4. Flight path illustrations...

More information

GATWICK NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES

GATWICK NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES LOCAL RULE 1 GATWICK NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES 1. Policy All Night Flights require the prior allocation of a slot and corresponding Night Quota (movement and noise quota). Late arrivals

More information

Gold Coast Airport Aircraft Noise Information Report

Gold Coast Airport Aircraft Noise Information Report Gold Coast Airport Aircraft Noise Information Report Quarter 3 2012 (July to September) 1 Version Control Version Number Detail Prepared by Date 1 - Environment 2 November 2012 2 Updated Figure 10 Environment

More information

Community Impact: Focus on Knowle

Community Impact: Focus on Knowle Community Impact: Focus on Knowle With flights to more than 140 destinations worldwide and a workforce of more than 6,000 people, Birmingham is the UK s 7 th largest airport and an economic powerhouse,

More information

Portable Noise Monitor Report

Portable Noise Monitor Report Portable Noise Monitor Report Chicago O Hare International Airport Site 2117 5843 N. Christiana Avenue, Chicago July 14, 217 through August 2, 217 USH5-ILH15-ILS8-CHI39 Visit the O Hare Noise webpage on

More information

Portable Noise Monitor Report

Portable Noise Monitor Report Portable Noise Monitor Report Chicago O Hare International Airport Site 299 93 Wilshire Avenue, Elk Grove Village June 27, 217 through July 1, 217 USH8-ILH55-ILS28 Visit the O Hare Noise webpage on the

More information

Portable Noise Monitor Report

Portable Noise Monitor Report Portable Noise Monitor Report Chicago O Hare International Airport Site 2114 5516 N. Neenah Avenue, Chicago July 12, 217 through August 9, 217 USH5-ILH19-ILS1-CHI45 Visit the O Hare Noise webpage on the

More information

GATWICK NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES

GATWICK NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES LOCAL RULE 1 GATWICK NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES 1. Policy All Night Flights require the prior allocation of a slot and corresponding Night Quota (movement and noise quota). Late arrivals

More information

Noise data for the first 17 months of Boeing 787 operations at Heathrow airport

Noise data for the first 17 months of Boeing 787 operations at Heathrow airport Environmental Research and Consultancy Department Noise data for the first 17 months of Boeing 787 operations at Heathrow airport CAP 1191 Civil Aviation Authority 2014 All rights reserved. Copies of this

More information

Portable Noise Monitor Report

Portable Noise Monitor Report Portable Noise Monitor Report Chicago O Hare International Airport Site 2198 5N67 Rochefort Lane, Wayne May 9, 218 through June 3, 218 USH6-ILH49-ILS25 Visit the O Hare Noise webpage on the Internet at

More information

SECTION 4 - APPROACH CONTROL PROCEDURES

SECTION 4 - APPROACH CONTROL PROCEDURES SECTION 4 - APPROACH CONTROL PROCEDURES CHAPTER 1 - PROVISION OF SERVICES 1.1 An approach control unit shall provide:- a) Approach control service. b) Flight Information service. c) Alerting service. RESPONSIBILITIES

More information

O Hare Noise Compatibility Commission Technical Committee April 19, Proposed Interim Fly Quiet Runway Rotation Plan

O Hare Noise Compatibility Commission Technical Committee April 19, Proposed Interim Fly Quiet Runway Rotation Plan O Hare Noise Compatibility Commission Technical Committee April 19, 2016 Proposed Interim Fly Quiet Runway Rotation Plan O HARE MODERNIZATION ROD - FLY QUIET Record of Decision (ROD) was issued on September

More information

Community Impact: Focus on Barston

Community Impact: Focus on Barston Community Impact: Focus on Barston With flights to more than 140 destinations worldwide and a workforce of more than 6,000 people, Birmingham is the UK s 7th largest airport and an economic powerhouse,

More information

ERCD REPORT London Heathrow Airport. Strategic Noise Maps D J Monkman J McMahon

ERCD REPORT London Heathrow Airport. Strategic Noise Maps D J Monkman J McMahon Environmental Research and Consultancy Department ERCD REPORT 0706 London Heathrow Airport Strategic Noise Maps 2006 D J Monkman J McMahon www.caa.co.uk Environmental Research and Consultancy Department

More information

NIGHT NOISE POLICY

NIGHT NOISE POLICY NIGHT NOISE POLICY 2012-2018 manchesterairport.co.uk/communitylinks NIGHT NOISE POLICY WINTER 2012 - SUMMER 2018 This document sets out Manchester Airport s policies for controlling Night Noise. We have

More information

Date: 01 Jun 2018 Time: 0959Z Position: 5121N 00048W Location: 6nm N Farnborough

Date: 01 Jun 2018 Time: 0959Z Position: 5121N 00048W Location: 6nm N Farnborough AIRPROX REPORT No 2018103 Date: 01 Jun 2018 Time: 0959Z Position: 5121N 00048W Location: 6nm N Farnborough PART A: SUMMARY OF INFORMATION REPORTED TO UKAB Recorded Aircraft 1 Aircraft 2 Aircraft DA62 BE90

More information

Departure Noise Mitigation: Main Report

Departure Noise Mitigation: Main Report Environmental Research and Consultancy Department Departure Noise Mitigation: Main Report CAP 1691 Published by the Civil Aviation Authority, 2018 Civil Aviation Authority, Aviation House, Gatwick Airport

More information

IFR SEPARATION USING RADAR

IFR SEPARATION USING RADAR IFR SEPARATION USING RADAR 1. Introduction When flying IFR inside controlled airspace, air traffic controllers either providing a service to an aircraft under their control or to another controller s traffic,

More information

2 Introduction. Security, safety and responsibly managing our environmental impact are always our top priorities. Contents:

2 Introduction. Security, safety and responsibly managing our environmental impact are always our top priorities. Contents: F L I G H T P E R F O R M A N C E T E A M R E P O R T 2 0 1 2 2 Introduction Contents: Section A Air Traffic Movement data 3 Section B Night flights 5 Section C Arrivals and departures 9 Section D Aircraft

More information

Case study London Heathrow & London Heathrow-Amsterdam

Case study London Heathrow & London Heathrow-Amsterdam Case study London Heathrow & London Heathrow-Amsterdam VFE workshop Andrew Burke - Michael Glen - Sam Peeters NATS Heathrow Airport EUROCONTROL/PRU 26 November 2018 Climb & descent London Heathrow Case

More information

LFPG / Paris-Charles de Gaulle / CDG

LFPG / Paris-Charles de Gaulle / CDG This page is intended to draw commercial and private pilots attention to the aeronautical context and main threats related to an aerodrome. They have been identified in a collaborative way by the main

More information

Portable Noise Monitor Report

Portable Noise Monitor Report Portable Noise Monitor Report Chicago O Hare International Airport Site 213 475 W. Hutchinson Street, Chicago April 8, 217 through May 3, 217 USH5-ILH19-ILS1-CHI45 Visit the O Hare Noise webpage on the

More information

SJC North and South Flow

SJC North and South Flow SJC North and South Flow Pre and Post OAPM Date: January 2018 Phases of Flight ATCC ARTCC ATCC 2 AviationTerms VFR- Visual Flight Rules. Pilots must maneuver to avoid clouds and are responsible for their

More information

Recommendations for Northbound Aircraft Departure Concerns over South Minneapolis

Recommendations for Northbound Aircraft Departure Concerns over South Minneapolis Recommendations for Northbound Aircraft Departure Concerns over South Minneapolis March 21, 2012 Noise Oversight Committee Agenda Item #4 Minneapolis Council Member John Quincy Background Summer of 2011

More information

Portable Noise Monitor Report

Portable Noise Monitor Report Portable Noise Monitor Report Chicago O Hare International Airport Site 241 61 Grange Road, Elk Grove Village October 3, 215 through October 19, 215 USH8-ILH55-ILS28 Visit the O Hare Noise webpage on the

More information

HEATHROW NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES Version 3

HEATHROW NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES Version 3 LOCAL RULE 1 HEATHROW NIGHT MOVEMENT AND QUOTA ALLOCATION PROCEDURES Version 3 1. POLICY All Night Flights require the prior allocation of a slot and corresponding Night Quota (movement and noise quota).

More information

Performance monitoring report 2017/18

Performance monitoring report 2017/18 Performance monitoring report /18 Gatwick Airport Limited 1. Introduction Date of issue: 20 July 2018 This report provides an update on performance at Gatwick in the financial year /18, ending 31 March

More information

ERCD REPORT Strategic Noise Maps for Heathrow Airport J Lee L Edmonds J Patel

ERCD REPORT Strategic Noise Maps for Heathrow Airport J Lee L Edmonds J Patel Environmental Research and Consultancy Department Directorate of Airspace Policy Civil Aviation Authority ERCD REPORT 1204 Strategic Noise Maps for Heathrow Airport 2011 J Lee L Edmonds J Patel Prepared

More information

Heathrow DET09 Steeper Departure Trial. Interim Trial Presentation Trial Data: January - June 2018

Heathrow DET09 Steeper Departure Trial. Interim Trial Presentation Trial Data: January - June 2018 Heathrow DET09 Steeper Departure Trial Interim Trial Presentation Trial Data: January - June 2018 The Trial Heathrow are trialling a steeper Standard Instrument Departure (SID) for runway 09R DET departures

More information

Flight Performance Team Annual Report 2016

Flight Performance Team Annual Report 2016 Gatwick Airport Flight Performance Team Annual Report 2016 This report covers the period 1 January 2016 31 December 2016 CONTENTS ABOUT GATWICK AIRPORT... 02 GATWICK S FRAMEWORK FOR NOISE MANAGEMENT...

More information

UNITED KINGDOM AERONAUTICAL INFORMATION CIRCULAR

UNITED KINGDOM AERONAUTICAL INFORMATION CIRCULAR UNITED KINGDOM AERONAUTICAL INFORMATION CIRCULAR AIC 127/2006 (Pink 110) 7 December NATS Limited Aeronautical Information Service Control Tower Building, London Heathrow Airport Hounslow, Middlesex TW6

More information

Noise from Arriving Aircraft. An Industry Code of Practice

Noise from Arriving Aircraft. An Industry Code of Practice Noise from Arriving Aircraft An Industry Code of Practice 2nd Edition November 2006 Executive Summary This voluntary Code of Practice has been compiled by a group representing airlines, air traffic control,

More information

Presented at the June 2, Airport Community Roundtable Meeting. SFO Aircraft Noise Abatement Office

Presented at the June 2, Airport Community Roundtable Meeting. SFO Aircraft Noise Abatement Office Presented at the June, Airport Community Roundtable Meeting SFO Aircraft Noise Abatement Office March Monthly Noise Exceedance Report Noise Exceedances Airline Total Total Exceedances Noise Exceedance

More information

ERCD REPORT London Gatwick Airport. Strategic Noise Maps D J Monkman J McMahon

ERCD REPORT London Gatwick Airport. Strategic Noise Maps D J Monkman J McMahon Environmental Research and Consultancy Department ERCD REPORT 0707 London Gatwick Airport Strategic Noise Maps 2006 D J Monkman J McMahon www.caa.co.uk Environmental Research and Consultancy Department

More information

Cairns Airport Aircraft Noise Information Report. Quarter (July to September)

Cairns Airport Aircraft Noise Information Report. Quarter (July to September) Cairns Airport Aircraft Noise Information Report Quarter 3 2012 (July to September) 1 Version Control Version Number Detail Prepared by Date 1 - Environment 19 December 2012 Airservices Australia. All

More information

Chapter 6. Brize Radar, Speedbird 213 Heavy, request radar advisory. Speedbird 123 change call sign to BA 123

Chapter 6. Brize Radar, Speedbird 213 Heavy, request radar advisory. Speedbird 123 change call sign to BA 123 INTRODUCTION The procedures for and VFR are mostly identical but some words and procedures are generally only used by large commercial aircraft; hence they appear in this section. In this chapter we will

More information

Canberra Airport Aircraft Noise Information Report

Canberra Airport Aircraft Noise Information Report Canberra Airport Aircraft Noise Information Report Quarter 3 2012 (July to September) 1 Version Control Version Number Detail Prepared by Date 1 - Environment 5 December 2012 2 - Environment 13 December

More information

ALTIMETER SETTING PROCEDURES

ALTIMETER SETTING PROCEDURES AIP New Zealand ENR 1.7-1 ENR 1.7 ALTIMETER SETTING PROCEDURES 1 INTRODUCTION 1.1 General 1.1.1 The requirements for altimeter setting are detailed in CAR Part 91. The requirements are summarised in this

More information

ATM Network Performance Report

ATM Network Performance Report ATM Network Performance Report 2018. Page 1 of 16 Table of contents Summary... 3 Network Wide Performance... 4 Airborne delay... 4 Sydney... 6 Airborne delay... 6 Notable events... 6 Melbourne... 9 Airborne

More information

Noise Compatibility Year End, 2012

Noise Compatibility Year End, 2012 Year End, 2012 April 5, 2013 Noise Highlights of 2012 Airport operations for Year 2012 were down 3.97%, compared to Year 2011. The FAA issued a Record of Approval (ROA) for the new Program (NCP) Update

More information

Performance monitoring report for 2014/15

Performance monitoring report for 2014/15 Performance monitoring report for 20/15 Date of issue: August 2015 Gatwick Airport Limited Summary Gatwick Airport is performing well for passengers and airlines, and in many aspects is ahead of the performance

More information

LONDON SOUTHEND AIRPORT DRAFT NOISE ACTION PLAN. 13 October 2009

LONDON SOUTHEND AIRPORT DRAFT NOISE ACTION PLAN. 13 October 2009 LONDON SOUTHEND AIRPORT DRAFT NOISE ACTION PLAN 13 October 2009 INTRODUCTION 1 This draft Noise Action Plan has been prepared in accordance with the Environmental Noise (England) Regulations 2006 (the

More information

TAG Farnborough Airport

TAG Farnborough Airport TAG Farnborough Airport Farnborough Aerodrome Consultative Committee TAG Information Report November 2014 1. Aircraft Movements 1.1 The permitted movement numbers for 2014 are 43,000 movements of which

More information

Application of Wake Turbulence Separation at London Heathrow. Paul Johnson Development Manager NATS Heathrow

Application of Wake Turbulence Separation at London Heathrow. Paul Johnson Development Manager NATS Heathrow Application of Wake Turbulence Separation at London Heathrow Paul Johnson Development Manager NATS Heathrow Heathrow Vital Statistics Passengers per year 67 Million Aircraft movements per year 470,000

More information

This section sets forth all Los Angeles World Airports (LAWA) noise abatement procedures, restrictions, and regulations involving aircraft operations.

This section sets forth all Los Angeles World Airports (LAWA) noise abatement procedures, restrictions, and regulations involving aircraft operations. This section sets forth all Los Angeles World Airports (LAWA) noise abatement procedures, restrictions, and regulations involving aircraft operations. 13.1. Aircraft Noise Abatement 13.1.1. All aircraft

More information

Portable Noise Monitor Report

Portable Noise Monitor Report Portable Noise Monitor Report Chicago O Hare International Airport Site 221 5716 N. Virginia Avenue, Chicago July 23, 214 through August 11, 214 Visit the O Hare Noise Management Webpage on the Internet

More information

1.2 An Approach Control Unit Shall Provide the following services: c) Alerting Service and assistance to organizations involved in SAR Actions;

1.2 An Approach Control Unit Shall Provide the following services: c) Alerting Service and assistance to organizations involved in SAR Actions; Section 4 Chapter 1 Approach Control Services Approach Control Note: This section should be read in conjunction with Section 2 (General ATS), Section 6 (Separation Methods and Minima) and Section 7 (ATS

More information

2017/ Q1 Performance Measures Report

2017/ Q1 Performance Measures Report 2017/2018 - Q1 Performance Measures Report Contents Ridership & Revenue... 1 Historical Revenue & Ridership... 1 Revenue Actual vs. Planned... 3 Mean Distance Between Failures... 5 Maintenance Cost Quarter

More information

Doncaster Sheffield Airport Airspace Change Proposal for the Introduction of RNAV (GNSS) Departure and Approach Procedures ANNEX B TO PART B

Doncaster Sheffield Airport Airspace Change Proposal for the Introduction of RNAV (GNSS) Departure and Approach Procedures ANNEX B TO PART B Doncaster Sheffield Airport Airspace Change Proposal for the Introduction of RNAV (GNSS) Departure and Approach Procedures ANNEX B TO PART B ANNEX B TO PART B: Runway 20 Westerly Departure UPTON 2B 2 Contents

More information

ENR 1.7 ALTIMETER SETTING PROCEDURES

ENR 1.7 ALTIMETER SETTING PROCEDURES AIP LEBANON ENR 1.7-1 11 APR 2008 ENR 1.7 ALTIMETER SETTING PROCEDURES 1. Introduction: 1.1 The procedures herein describe the method used in providing adequate vertical separation between aircraft and

More information

In this document the following words shall have the following meanings: Airport Coordination Limited, the Coordinator of London City Airport

In this document the following words shall have the following meanings: Airport Coordination Limited, the Coordinator of London City Airport LOCAL RULE 1 ADMINISTRATION OF THE LONDON CITY MOVEMENT CAP 1. POLICY A planning condition applicable at London City Airport limits the number of aircraft movements permitted at London City Airport to

More information

OPERATIONS MANUAL PART A

OPERATIONS MANUAL PART A PAGE: 1 Table of Content A.GENERAL /CHAPTER 7 -....3 7.... 3 7.1 Minimum Flight Altitudes /Flight Levels VFR Flight... 3 7.2 Minimum Flight Altitudes /Flight Levels IFR Flight... 4 7.2.1 IFR flights non

More information

Opportunities to improve noise management and communications at Heathrow

Opportunities to improve noise management and communications at Heathrow Opportunities to improve noise management and communications at Heathrow Summary of a dialogue between Aviation Environment Federation, British Airways, HACAN, Heathrow Airport and NATS 1. Introduction

More information

GATWICK RNAV-1 SIDS CAA PIR ROUTE ANALYSIS REPORT

GATWICK RNAV-1 SIDS CAA PIR ROUTE ANALYSIS REPORT GATWICK RNAV-1 SIDS GATWICK RNAV-1 SIDS CAA PIR ROUTE ANALYSIS REPORT ROUTE ANALYSIS REPORT FOR GATWICK This section explains the track distribution of conventional SIDs and the RNAV SID replications using

More information

Departure Noise Mitigation Review. Dr Darren Rhodes Civil Aviation Authority 18 July

Departure Noise Mitigation Review. Dr Darren Rhodes Civil Aviation Authority 18 July Departure Noise Mitigation Review Dr Darren Rhodes Civil Aviation Authority 18 July 2018 1 Departure Noise Review: Terms of Reference Conduct a review of the existing policy objectives and desired outcomes

More information

Technical Report. Aircraft Noise Analysis. Portola Valley and Woodside, California. July Prepared by: Aircraft Noise Abatement Office

Technical Report. Aircraft Noise Analysis. Portola Valley and Woodside, California. July Prepared by: Aircraft Noise Abatement Office Technical Report Aircraft Noise Analysis Portola Valley and Woodside, California Prepared by: San Francisco International Airport P.O. Box 8097 San Francisco, California 94128 (650) 821-5100 Introduction

More information

Airport Noise Management System

Airport Noise Management System July Monthly Report Airport Noise Management System Chicago O Hare International Airport City of Chicago Department of Aviation Visit the Community Noise Resource Center on the Internet at www.flychicago.com

More information

Safety and Airspace Regulation Group

Safety and Airspace Regulation Group Safety and Airspace Regulation Group 24 August 2015 Policy Statement POLICY FOR POINT MERGE AND TROMBONE TRANSITION PROCEDURES 1 Introduction 1.1 The Point Merge transition procedure is an Area Navigation

More information

Airport Noise Management System Chicago Midway International Airport

Airport Noise Management System Chicago Midway International Airport 1 st Quarter 2018 Quarterly Report Airport Noise Management System Midway International Airport Visit the Midway Noise webpage on the Internet at www.flychicago.com/midwaynoise Airport Noise Management

More information

TAG Farnborough Airport

TAG Farnborough Airport TAG Farnborough Airport Farnborough Aerodrome Consultative Committee TAG Information Report - March 2012 1. Aircraft Movements 1.1 Following the acceptance of the TAG appeal on the 11 th February 2011,

More information

Phases of a departure

Phases of a departure Phases of a departure Hours, days or even months prior, an airline will submit a flight plan to NATS requesting an air traffic routing to its destination. The filed route to be flown will include the designated

More information

Hampton in Arden. Community Impact: Focus on

Hampton in Arden. Community Impact: Focus on Community Impact: Focus on Hampton in Arden With flights to nearly 150 destinations worldwide and a workforce of around 7,000 people, Birmingham is the UK s 7 th largest airport and an economic powerhouse,

More information

ERCD REPORT London Stansted Airport. Strategic Noise Maps D J Monkman J McMahon

ERCD REPORT London Stansted Airport. Strategic Noise Maps D J Monkman J McMahon Environmental Research and Consultancy Department ERCD REPORT 0708 London Stansted Airport Strategic Noise Maps 2006 D J Monkman J McMahon www.caa.co.uk Environmental Research and Consultancy Department

More information

Northern Regional Training Scheme. EGNT Newcastle Aerodrome Pilot s Guide. REVISION 2 (Wednesday, 03 August 2011 at 15:51)

Northern Regional Training Scheme. EGNT Newcastle Aerodrome Pilot s Guide. REVISION 2 (Wednesday, 03 August 2011 at 15:51) Northern Regional Training Scheme EGNT Newcastle Aerodrome Pilot s Guide REVISION 2 (Wednesday, 03 August 2011 at 15:51) PUBLISHED Wednesday, 03 August 2011 1 Contents 1 Contents... 2 2 Departures... 3

More information

Airport Director s Report. Presented at the April 6, 2016 Airport Community Roundtable Meeting SFO Aircraft Noise Abatement Office October 2015

Airport Director s Report. Presented at the April 6, 2016 Airport Community Roundtable Meeting SFO Aircraft Noise Abatement Office October 2015 Airport Director s Report Presented at the April 6, 16 Airport Community Roundtable Meeting SFO Aircraft Noise Abatement Office October 15 Monthly Noise Exceedance Report Noise Exceedances Airline Total

More information