Ongoing Projects 26 th to 34 th Street, West Avenue to Bay Avenue ($6.5 million contract awarded) 46 th Street (complete) 29 th Street Firehouse South Jersey Gas improvements 34 th Street playground repairs and tennis court resurfacing 46 th Street Post Office ramp (complete) 3/16/2017 2
Ongoing Projects Beach path accessibility Beach mats accessibility On-street bike racks at beach entrances 46 th Street Firehouse roof and HVAC 52 nd Street playground and basketball court improvements 3/16/2017 3
Grants Grant Programs Project Agency - Funding Program Grant Notice Dollars Associated with Grant Flood Mitigation Assistance (FMA) - 2016 Will help to fund home elevations in Cape May County. This program was open to Repetitive Loss (RL) and Severe Repetitive Loss (SRL) property owners. 15 properties in Ocean City applied under this application, which was coordinated by Cape May County and Ocean City supported with staff FEMA Waiting Notice Dollars individual to each property owner - Approximately $160,000 on average for each property elevation if funded Hazard Mitigation Grant Program (HMGP) Ocean City North End Pump Station Project (1st to 8th Streets) FEMA Awarded Grant $4,984,384 (Federal Grant); $3,756,993 (City Share); $8,741,377 (Total Project) National Fish and Wildlife Foundation (NFWF) Hurricane Sandy Coastal Resiliency Competitive Grants 150 acres of wetlands restoration (Potential for a resiliency berm) NFWF Awarded Grant $2,630,000 (Grant Amount - Ocean City Share $2,080,000 Somers Point Share $550,000); Note Matching Share: Ocean City $1,017,206.25 and Somers Point $259,568.25 New Jersey Department of Transportation (NJDOT) - Municipal Aid Program 1. 31st, 32nd, and 33rd Streets & 2. 14th to 16th Streets NJDOT Awarded Grants $172,000 & $175,000 3/16/2017 4
What is Next for 2017 in Fourth Ward? 3/16/2017 5
Drainage Project 26 th to 34th 3/16/2017 6
2017 - Road Improvement Program Cost 2017 Road Improvement Program Project 1 $1.1 Million (Paving and Drainage Fourth Ward) $1,100,000 Roadway From To 53rd Street Bay Avenue West Avenue Haven/West alley 53rd Street 52nd Street Haven/West alley 52nd Street 51st Street West/Asbury alley 47th Street 46th Street Haven/West alley Fire House 45th Street 46th Street West Avenue Central Avenue 46th Street Central Avenue Beach 47th Street West Avenue Central Avenue 47th Street Bay West Avenue 47th Street Central Avenue Beach Asbury Avenue 47th Street 45th Street 45th Street Haven Avenue West Avenue Haven/West alley 45th Street 43rd Street 3/16/2017 7
Beach entrances and bike racks Hard-pack dune crossovers and blue mobi-mats: 30 th, 31 st, 32 nd, 33 rd, 34 th, 36 th, 37 th, 39 th, 40 th, 41 st, 42 nd, 44 th, 45 th, 46 th 47 th, 48 th, 49 th, 50 th, 51 st, 52 nd, 53 rd, 54 th, 56 th, 57 th, 58 th, 59 th. Bike racks: 26 th, 28 th, 29 th, 30 th, 32 nd, 34 th, 36 th, 39 th, 40 th, 42 nd, 44 th, 46 th, 48 th, 50 th, 53 rd, 55 th. 3/16/2017 8
2017 Road Improvement Program - Miscellaneous Projects - $175,000 Bulkhead (Paving and Drainage Fourth Ward) 3/16/2017 9
Neighborhood Projects To Date 3/16/2017 10
Neighborhood Projects Planning for the Future 3/16/2017 11
Fourth Ward 2018 to 2021 3/16/2017 12
2018 - Road Improvement Program Cost 2018 Road Improvement Program Project 1 - $3.9 Million (Paving and Drainage Fourth Ward) $3,900,000 Roadway From To Asbury Avenue 52nd Street 47th Street Asbury Avenue 55th Street 52nd Street Asbury Avenue Southern Terminus 55th Street West Avenue 59th Street 55th Street 48th Street Haven Avenue West Avenue 48th Street West Avenue Beach St. David's Place West Avenue Beach Merion Place West Avenue Beach 49th Street West Avenue Beach Haven Avenue 50th Street 49th Street 50th Street West Avenue Beach 51st Street West Avenue Beach 52nd Street West Avenue Central Avenue 53rd Street West Avenue Beach 54th Street West/Asbury Alley Beach 56th Street Bay Avenue West Avenue 56th Street West Avenue Central Avenue 57th Street West Avenue Beach 58th Street West Avenue Central Avenue 59th Street West Avenue Central Avenue Haven/West alley 56th Street 55th Street Asbury/Central alley 58th Street 57th Street 3/16/2017 13
2019 - Road Improvement Program Cost 2019 Road Improvement Program Project 1 - $2.1 Million (Paving and Drainage Fourth Ward) $2,100,000 Roadway From To West Avenue 31st Street 26th Street West Avenue 33rd Street 32nd Street West Avenue 32nd Street 31st Street Asbury/Central Alley 31st Street 30th Street 30th Street Haven Avenue Beach 29th Street West Avenue Central Avenue Haven/West alley 31st Street 30th Street 28th Street Haven Avenue West Avenue 3/16/2017 14
2020 Road Improvement Program Project 3 - $1.2 Million (Paving and Drainage Fourth Ward) $1,200,000 Roadway From To Asbury Avenue 39th Street 36th Street 40th Street Central Avenue Beach 39th Street Central Avenue Beach 38th Street Central Avenue Beach 38th Street - drainage pipe 1/2 road pave only West Avenue Central Avenue 39th Street - drainage pipe 1/2 road pave only Asbury Avenue Central Avenue 36th Street West Avenue Beach 37th Street West Avenue Beach West/Asbury alley 37th Street 36th Street Asbury/Central alley 38th Street 37th Street Asbury/Central alley 39th Street 38th Street West/Asbury alley 39th Street 38th Street 3/16/2017 15
2021 - Road Improvement Program Cost 2021 Road Improvement Program Project 1 - $700,000 (Paving and Drainage Fourth Ward) $700,000 Roadway From To Central Avenue 29th Street 28th Street Central Avenue 30th Street 29th Street Central Avenue 31st Street 30th Street Central Avenue 32nd Street 31st Street Central Avenue 33rd Street 32nd Street Central Avenue 34th Street 33rd Street 31st Street Asbury Avenue Beach 3/16/2017 16
Future Projects Dredging of Waterview and Clubhouse Lagoons 2018 beach replenishment (if necessary) More beach mats accessibility Flood remediation in south end neighborhoods. 3/16/2017 17