SONOMA MARIN AREA RAIL TRANSIT SMART CENTRAL SAN RAFAEL STATUS UPDATE SAN RAFAEL City Council January 20, 2015
CENTRAL SAN RAFAEL SMART SOUTH OF PUERTO SUELLO TUNNEL 1. Active Construction 2. Construction Prior to Rail Operations 3. Future Construction After Rail Operations
ACTIVE DESIGN AND CONSTRUCTION
NORTH Highway 101 ACTIVE CONSTRUCTION Puerto Suello Tunnel SMART Rail Line Paloma Avenue Pacheco Street Mission Avenue 5 th Avenue 4 th Street Road Crossings Downtown Station End of Initial Operating Segment (Third St)
ACTIVE CONSTRUCTION NORTH SMART Rail Line Track to be Reconstructed
1. Remove Existing Rail GENERAL TRACK CONSTRUCTION (SMART) ACTIVE CONSTRUCTION 2. Area Excavated 3. Rock (Ballast) Placed 4. Ties Placed 5. Steel Rail Attached 5. Lastly, additional rock is added to lock in the ties and the rail.
Existing Puerto Suello Pathway Mission Avenue Crossing Completed in November 2014 5 th Avenue Crossing Completed last Thursday 4 th Street Crossing Under construction today NTPP Puerto Suello Pathway to Transit Center
TRACK CROSSINGS AT ROADWAYS (SMART) ACTIVE CONSTRUCTION Mission Ave. Crossing completed in November 2014 5 th Avenue completed last Thursday 4 th Street under construction
TRACK CROSSINGS AT ROADWAYS (SMART) ACTIVE CONSTRUCTION Paloma Avenue Pacheco Street
Paloma Avenue Coleman Elementary School Pedestrian Overcrossing Access to School Pacheco Street Puerto Suello Multi-Use Pathway
ACTIVE CONSTRUCTION Existing Rail Pacheco St Looking toward Puerto Suello Pathway. Pacheco St Looking toward Lincoln Ave.
SMART plan Pacheco St. ACTIVE CONSTRUCTION
Existing Rail ACTIVE CONSTRUCTION Paloma Ave. Looking toward Puerto Suello Pathway. Paloma Ave Looking toward Lincoln Ave.
SMART plan Paloma Ave. ACTIVE CONSTRUCTION
ACTIVE CONSTRUCTION Tunnel Construction (SMART)
ACTIVE CONSTRUCTION Station Platform Construction (SMART) 4 feet Rail to Platform
SIGNAL OPERATIONS (SMART) ACTIVE CONSTRUCTION
Regional Transportation System Enhancements Project (City of San Rafael) ACTIVE CONSTRUCTION 23 Curb Ramps Installations/Upgrades 2 nd & Irwin 2 nd & Irwin 3 rd & Lincoln Each Ramp is different some require drainage modifications and retaining walls which can be expensive. 2 nd & Hetherton
Regional Transportation System Enhancements Project (City of San Rafael) 17 Traffic Signal Controller Upgrades Existing KFT Controller Cobalt Controller System
Sidewalk Widening Regional Transportation System Enhancements Project (City of San Rafael) ACTIVE CONSTRUCTION Count-Down Pedestrian Indications Blank Out Signs Pole Relocations
Regional Transportation System Enhancements Project (City of San Rafael) ACTIVE CONSTRUCTION AGENDA
Regional Transportation System Enhancements Project (City of San Rafael) Queue Cutter Installations
Regional Transportation System Enhancements Project (City of San Rafael) Traffic and Incident Monitoring New Central Monitoring System New CCTV Cameras Changeable Message Sign(s) Alerts & Quicker Response
ACTIVE CONSTRUCTION SMART Rail Line End of Existing Puerto Suello Pathway New Median NTPP Puerto Suello Pathway to Transit Center NTPP Puerto Suello Hill Path to Transit Center (City of San Rafael)
NTPP Puerto Suello Hill Path to Transit Center (City of San Rafael) ACTIVE CONSTRUCTION
San Rafael Downtown Integrated Traffic Center Study (City of San Rafael) ACTIVE End of Current Rail Service End of Platform Study will assess options for the Transit Center. DOWNTOWN PARKING AND WAYFINDING STUDY (City of San Rafael)
Transportation Authority of Marin Transit Study (City of San Rafael/Fairfax/San Anselmo) ACTIVE SMART Downtown Station West to San Anselmo West to Fairfax
CONSTRUCTION PRIOR TO DAY ONE OPERATIONS
Regional Transportation System Enhancements Project (City of San Rafael) CONSTRUCTION (PRIOR TO DAY ONE RAIL OPERATIONS) AGENDA
Signal Installation (SMART) CONSTRUCTION (PRIOR TO DAY ONE RAIL OPERATIONS) New Signal Poles to be installed
Station Architectural Finish Construction (SMART & San Rafael Council Subcommittee) CONSTRUCTION (PRIOR TO DAY ONE RAIL OPERATIONS)
Regulatory Approvals (SMART) CONSTRUCTION (PRIOR TO DAY ONE RAIL OPERATIONS)
Quiet Zones (City of San Rafael) CONSTRUCTION (PRIOR TO DAY ONE RAIL OPERATIONS) Pictures from SMART web site.
Taxi, Shuttle and Transit Connectivity (City of San Rafael & Other Agencies) CONSTRUCTION (PRIOR TO DAY ONE RAIL OPERATIONS) West Tamalpais between 3 rd and 2 nd Streets East Tamalpais between 3 rd and 4 th Streets will be behind East Rail Platform
FUTURE STUDIES, DESIGN AND CONSTRUCTION
Ramp Metering (Caltrans) FUTURE CONSTRUCTION (AFTER RAIL OPERATIONS) Ramp Metering Lights in place but not in operation Northbound 101 On-Ramp Southbound 101 On-Ramp
SMART Extension to Larkspur FUTURE CONSTRUCTION (AFTER RAIL OPERATIONS) Rail Extension to Larkspur Mahon Creek Crossing
SMART Extension to Larkspur FUTURE CONSTRUCTION (AFTER RAIL OPERATIONS) Future Rail line to Larkspur
SMART Extension to Larkspur FUTURE CONSTRUCTION (AFTER RAIL OPERATIONS) Future Rail line to Larkspur
CIVIC CENTER STATION RANCH ROAD CROSSING RANCHITOS ROAD CLASS II PUERTO SUELLO MULTI-USE PATHWAY ANDERSEN DRIVE CLASS 2 BIKE PATH
WEST FRANCISCO BLVD. DITCH TO BE LEFT OPEN