Date: 06-24-16 To: Derek Hackett, Public Information Officer From: Sunil Jeboo, Traffic Engineer Re: Road Closure for the Week of 06-27-16 (3236.1) 6 th Pump Station Western Ave. and 6 th SW Western Ave. is open to traffic. Work continues along 6 th street and Western Ave with sidewalk placement. Lane closure may take place for a few hours to protect workers and for concrete placement Project Start Date: 05-16-2016 Project Completion Date: July 1, 2016 Contractor: Mattson Construction Contact Nate Lillemon 701-852-3293 (3375) 1 st Larson West Sanitary Sewer Improvements SW Minot West of Broadway and north of 54 th Ave. (Crystal Springs and Dalin s Additions) 54 th Ave SW is open. Work is taking place in Crystal Springs area. The residential streets in this area (east of 16 th on 51, 52, 53 rd Avenues) will be closed intermittently for sewer work on a day to day basis. Project Start Date: 5-09-2016 Project Completion Date: Week of July 22, 2016 Contractor: Robert Gibb & Sons Contact Greg Eckart 701-367-5560 (3490.1) North Minot Sanitary Sewer Improvements 55 th St. NE Lift Station 55 th St. NE (West Road Shoulder) Approximately 750 ft. North of County Road 12 (4 th Ave. NE) Approximately 450 ft. of the West Shoulder of 55 th will be closed. Speed Limit will be reduced to 35 mph. Project Start Date: May 9, 2016 Project Completion Date: June 25, 2016 Contractor: John T. Jones Construction Contact Tim Boland 701-371-1912
(3490.4) North Minot Sanitary Sewer Improvements 30 th Ave. NE & Livingston Coulee Lift Stations & Force Mains 30 th Ave. NE. Closed between County Road 19 and Mustang Trail NE 30 th Ave. West bound traffic will detour West on 46 th Ave. NE, and South on 13 th St. NE. Contractor required to maintain access to residences and businesses. Project Start Date: 05-02-16 Project Completion Date: June 4, 2016 Contractor: Rice Lake Construction Group Contact Larry McCulley Direct: 218-546-1930 Cell: 612-790-3622 (3573) Statesboro Addition: North Half 35 th Ave NW and Kodiak St NW No street closures or detours Project Start Date: 05-19-2016 Project Completion Date: Anticipated 07-20-2016 Contractor: Wagner Construction, Inc Contact Nigel Tate 701.240.3817 (3573) Statesboro Addition: South Half 32 nd Ave NW near 16 th St NW and 15 th St NW Approx. 300 feet of 32 nd Ave and 15 th St NW will be closed. Traffic control devices shall be used. Contractor required to maintain access to residences/businesses. Project Start Date: 06-22-2016 Project Completion Date: Anticipated Aug-15-2016 Contractor: Wagner Construction, Inc. Contact Nigel Tate 701.240.3817 (3608) Downtown Minot Infrastructure Improvements Phase I Downtown Minot Contractors plan on opening up the block of First SE, from Central Avenue, through the intersection of First Avenue SE. Project Start Date: Monday, April 18, 2016 Project Completion Date: Middle of June 2016 2
Contractor: Strata Corporation Contact Mark Lyman (Project PIO) 857-7205 (3608) Downtown Minot Infrastructure Improvements Phase II Downtown Minot Work will be starting on or about 6/20 around Central Campus High School. This will mean the closure of one block of First SE, from Second Avenue SE through Third Avenue SE and the closure of Second Avenue SE, from Second SE through First SE. Two blocks of Main are closed from Central Avenue to Second Avenue South, and two blocks of First Avenue S are closed from First SE to First SW. The intersection at Main and Second Avenue, as well as the intersection at Main and Central Avenue, are open to the driving public. Project Start Date: May 2nd Project Completion Date: Middle of November 2016 Contractor: Keller Paving Contact Stan Weigel (Superintendent) 701-720-6201 (4009) Storm Sewer Rehabilitation (1) 4 th St NW from 2 nd Ave to 4 th Ave NW (2) 4 th Ave NW from 4 th St to 6 th St NW (1) 3 rd Ave NW from 6 th St to Broadway (2) 4 th St NW from 4 th Ave to 2 nd Ave NW. No detour necessary for residential area. Local traffic only Project Start Date: 4/4/16 Project Completion Date: 7/4/16 Contractor: Wesslen Contact Jerry 701-389-2568 (4006 & 4010) 8 th St. Sewer & Water Improvements (1) 8 th St. and Central Ave E (2) 8 th St. and 2 nd Ave. NE. Includes all of 8 th St. South of Intersection to the River Contractor is required to maintain access to residents during construction. Project Start Date: May 4, 2016 Project Completion Date: May 28, 2016 Contractor: Vortex Drain Tiling Contact Lynn Meyer Office: 701-757-1468 Cell: 701-739-3108 3
(4029.02) US HWY 2 Bypass Ditch Repair US Hwy 2 Bypass South of 16 th Ave. to the Mouse River No closures or detours. Traffic control devices are on road edge line. Project Start Date: June 06, 2016 Project Completion Date: June 30, 2016 Contractor: Blue Stone Construction Contact Leif Anderson 701-240-4915 (4032) Oak Park Bridge Replacement 4 th Avenue NW Closed between 16 th NW and the entrance to Oak Park. Closure at Oak Park Bridge on 4 th Ave NW near 16 th St NW Detour from 4 th Ave NW 16 th St NW University Ave W N Broadway 4 th Ave NW Project Start Date: April 5, 2016 Project Completion Date: July 8, 2016 Contractor: Industrial Builders Contact Brent Wherley Cell: 701-793-8374 (4070) 37 th Ave SW 37 th Ave SW From 16 th St SW to 37 th St SW 37 th Ave S is closed to all traffic from 16 th St SW to 37 th Ave SW. A passenger vehicle detour is operation on 30 th St SW, 20 th Ave SW, and 16 th Ave SW. A truck detour route is operational using Ward County Road 17 from 37 th Ave SW to the US 2 junction. Businesses on the North side of 37 th will be accessed on 35 th Ave SW with a temporary road to 36 th Ave SW. Businesses on the South side of 37 th will be accessed on 30 th St SW with a temporary road to South West Crossing. Project Start Date: 5 May 2016 Project Completion Date: Estimated - 29 Oct 2016 Contractor: Wagner Construction Contact Jess Kindred (218)244-8466 (4071) 36 th Avenue NW Extension to N. Broadway 1. 36 TH Avenue NW 2. 36 th Ave NW Broadway Turn Lane Extension 3. 8 th St. NW and Broadway frontage road (in front of EZ Park) 4
1. 36 th Avenue NW from 8 th to Broadway will be closed. The frontage road will be closed off at the North and South sides of 36 th Avenue NW beginning Friday May 6 th, 2016. Detours will be put in place to accommodate access to surrounding businesses. 2. West lane of North bound traffic will be closed from 34 th Ave NE to 200 North of the 36 th Ave NW/Broadway intersection. East lane of the south bound traffic will be closed from 40h Ave NW to 200 South of 36 th Ave NW/Broadway intersection. Contractor extending turn lanes in both directions. One lane traffic for both North and South bound lanes. 3. 8 th St NW will be closed off from 36 th Ave NW to the north where the gravel meets the existing pavement. The frontage road will be closed off from 36 th Ave NW right in front of the EZ Park electronic sign Project Start Date: 4/11/2016 Project Completion Date: 8/26/2016 - Expected Contractor: Keller Paving Contact Dustin Keller 701-340-2909 (4088.1) Hillcrest Retaining Wall Project Hillcrest Drive & 3rd St NE & 11th Ave NE The intersection of 3rd St NE, Hillcrest Drive and 11th Ave NE will have traffic control devices controlling each leg of the intersection, while construction is taking place, the intersection will be an ALL WAY STOP. No detours will be used. Project Start Date: 06-03-2016 Project Completion Date: Estimated 10-21-2016 Contractor: Veit & Company, LLC. Contact Blaine Sherbrooke 701-226-8458 (4092) Improvement District 496 - MPIP North of Hwy 2 and East of 72 nd East No detours in place. Existing business has access at all times. Project Start Date: 05-16-2016 Project Completion Date: 9-01-2016 Contractor: Excavating Inc. Contact Jeff Anderson 701-340-4104 (4162) Water Main Replacement Harrison Drive Harrison Drive closed from Northwest Ave. North to 20 th St. NW Project Start Date: 6-13-16 Project Completion Date: 9-16-16 Contractor: Post Construction Contact 839-5386 5
(4163) Manhole Rehabilitation Areas within the following perimeter: 1 st St NW West to 8 th St NE Railway Ave North to 11 th Ave NE and NW Lane Closure on Burdick Expressway from Broadway to Main East Bound Traffic tentatively scheduled for Monday, 06-27-16, in the morning or late afternoon Construction crews will have their work zone delineated with traffic control devices Due to various locations of manholes, construction crews will be moving from location to location within the perimeter streets listed above. Look for advanced warning signs and flaggers. Project Start Date: 6-20-16 Project Completion Date: 7-22-2016 Contractor: KEY Contact (4184) Minot Improvement District Randy 701-238-4825 Ben Cofell SE Minot Asphalt patching at the following locations: 13 th Ave SE to 19 th Ave SE and from 1 st ST SW to Hiawatha St 8 th and 9 th Ave SE between 5 th St and 3 rd St 4 th St SE between 5 th Ave and 10 th Ave SE All s and Avenues from 28 th NW to 24 th NW and between 4 th Avenue NW to Central Avenue Vehicles will always have access to one side of the street. Cones will mark patches that are open. Project Start Date: April 27 th 2016 Project Completion Date: 10-15-16 Contractor: Keller Paving & Landscaping Inc. Contact Dustin Keller 701-340-2909 HMGP Water Treatment Plant flood protection project North and west of the Minot Water Treatment Plant in SW Minot 16 th SW, from the north side of the 16 th SW/Burdick Expressway intersection to just back the bridge that is north of the Water Treatment Plant by Forest Road Project Start Date: Tuesday, May 31 Project Completion Date: Middle of August 2016 Contractor: Wagner Construction Contact Odney (PIO) 857-7205 Matt G. (Wagner) 218-240-9045 6